Fly ash grouting-based composite pipe jacking construction method for sewage pipe network

By using a double-layer composite structure of an outer reinforced concrete pipe and an inner steel pipe, along with fly ash grouting technology, the problems of structural safety and environmental impact during pipe jacking construction were solved. This enabled safe and environmentally friendly construction of sewage pipe networks, improved construction accuracy and corrosion resistance, and extended pipeline life.

CN123154183APending Publication Date: 2026-11-24THE GUANGDONG NO 3 WATER CONSERVANCY & HYDRO ELECTRIC ENG BOARD CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202611523098.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-29
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing pipe jacking construction methods have problems such as high safety risks to pipeline structures, significant impact on ground subsidence and the environment, difficulty in later maintenance, improper handling of gaps between inner and outer pipes, and insufficient construction accuracy and safety when crossing urban areas. Construction is particularly difficult under complex geological conditions, and traditional inner pipe jacking construction has problems such as welding difficulties and easy damage to the anti-corrosion layer.

Method used

The system employs a double-layer composite pipe structure consisting of an outer reinforced concrete pipe and an inner steel pipe. The pipe is filled with fly ash grout to ensure compaction. Combined with laser ranging and tilt sensor concentricity monitoring, the inner and outer pipes are positioned concentrically. Segmented grouting is used to control the grouting quality, forming a multi-layer waterproof structure that ensures the safety and environmental friendliness of the construction process.

Benefits of technology

It enabled safe and environmentally friendly construction under complex urban conditions, reduced the impact of construction on the environment, extended the service life of pipelines, improved structural safety and durability, reduced the difficulty of later maintenance, and ensured grouting quality and anti-leakage performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123154183A_ABST
    Figure CN123154183A_ABST
Patent Text Reader

Abstract

This invention, entitled "A Composite Pipe Jacking Construction Method for Sewage Pipe Networks Based on Fly Ash Grouting," belongs to the field of engineering construction technology. The technical problem to be solved is the high safety risk of the pipeline structure. The key points of the technical solution are: S1, construction preparation; S2, jacking construction of the outer reinforced concrete pipe; S3, cleaning and inspection of the interior of the outer reinforced concrete pipe; S4, jacking and welding a steel pipe inside the outer reinforced concrete pipe as an inner sleeve steel pipe, and installing the inner sleeve steel pipe; S5, sealing and grouting: after the inner sleeve steel pipe is installed and fixed, a grouting pipe is buried in the annular gap between the outer reinforced concrete pipe and the inner sleeve steel pipe; fly ash mortar is injected into the gap through the grouting pipe, and the gap is filled and compacted using a segmented grouting method; the grouting pipe opening is sealed after grouting; S6, acceptance and restoration.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of engineering construction technology, specifically to a composite pipe jacking construction method for sewage pipe networks based on fly ash grouting. Background Technology

[0002] Pipe jacking is a commonly used trenchless construction method for urban sewage pipeline construction. The conventional approach involves first constructing the working and receiving shafts, then using a pipe jacking machine to push the pipe sections in one by one, forming a sewage transport channel. The jacking method primarily uses slurry-balanced pipe jacking, and the pipe material is mostly F-shaped steel socket Class III reinforced concrete pipe. For pipe sections that need to cross main urban roads, rivers, and existing structures, pipe jacking is widely used due to its advantages such as eliminating the need for road excavation, reducing the need for related road occupancy permits, minimizing traffic disruption, and reducing noise.

[0003] For construction within urban areas, when crossing existing structures, pipe jacking has some drawbacks: 1. High Safety Risks in Pipeline Structure: Pipe jacking is an underground, concealed project with complex and variable geological conditions, resulting in significant construction risks. Single reinforced concrete pipes are susceptible to groundwater corrosion and uneven soil settlement during long-term service, leading to pipe rupture, high repair costs, and significant delays. In conventional internal pipe laying construction, the increased weight of large-diameter pipes after welding not only makes jacking difficult but also easily damages the pipe's anti-corrosion layer.

[0004] 2. Significant Impacts on Surface Subsidence and the Surrounding Environment: Large-diameter pipe jacking construction causes severe soil disturbance, easily leading to ground subsidence. Construction under shallow overburden and high water table conditions can easily cause road surface cracking, triggering foundation settlement of nearby buildings. The pipe jacking machine head is prone to "jumping" in complex geological formations; failure to implement water-stopping measures at the side wall openings can cause water leakage between the pipe wall and the opening, resulting in soil erosion and environmental pollution.

[0005] 3. Difficulty in post-construction maintenance: After conventional reinforced concrete pipe jacking is put into operation, the inner wall of the pipe is prone to corrosion and scaling. Due to the large burial depth and location below the structure, inspection and maintenance are extremely difficult. Existing lining pipe repair solutions are mostly post-construction repairs, and require the removal of the inspection well shaft and top, making construction complex.

[0006] 4. Improper handling of the gap between the inner and outer tubes: In the existing technology, the gap between the inner and outer tubes is mostly filled with self-compacting concrete. Although it has good fluidity, its density is large, which will put a large load on the installed inner tube and may cause deformation of the inner tube. In addition, the shrinkage rate of concrete after hardening is large, which can easily form gaps at the interface.

[0007] 5. Insufficient precision and safety in internal pipe penetration construction: Traditional internal pipe penetration construction often uses the method of laying guide rails on the base of the casing for transportation. When the casing diameter is small or the crossing distance is long, the working space is limited, and the laying of guide rails and the connection and transportation of pipes are difficult. After welding, the self-weight of large-diameter pipes increases, which not only makes jacking difficult, but also easily causes damage to the anti-corrosion layer of the pipe. Although there are solutions in the existing technology to set up support components, they mostly use support rollers and limit brackets, which lack active support and positioning functions for the inner steel pipe.

[0008] 6. The concentricity monitoring of multi-layer casing is not effective during construction; and the grouting in sections cannot be automatically controlled, making it difficult to guarantee the grouting quality.

[0009] For example, the relevant patent documents retrieved: This document, published in China (CN104806816A), discloses a construction method for jacking a cast iron pipe using a double-layer PE pipe. The key technical points are: it includes a PE pipe and an outer reinforced concrete pipe, with the PE pipe nested inside the outer reinforced concrete pipe, and a transition fit between the outer reinforced concrete pipe and the PE pipe. It employs a second protective outer reinforced concrete pipe nested outside the PE pipe, where the outer casing protects the gas main pipeline replaced by the inner PE pipe.

[0010] Therefore, it is still necessary to design a construction method that can solve the aforementioned problems. Summary of the Invention

[0011] The purpose of this invention is to provide: A composite pipe jacking construction method for sewage pipe networks based on fly ash grouting is proposed to address technical issues such as high safety risks in pipeline structures, or combinations thereof. This invention employs a double-layer composite pipe structure of "outer reinforced concrete pipe + inner steel pipe," and through scientific construction procedures and quality control measures, achieves safe and environmentally friendly construction of sewage pipe networks under complex urban conditions.

[0012] Terminology Explanation: Unless otherwise defined, all technical terms herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention pertains.

[0013] It should be understood that the above brief description and the following detailed description are exemplary and for illustrative purposes only, and do not limit the subject matter of the invention in any way. In this invention, the singular is used in conjunction with the plural unless otherwise specifically stated. It should also be noted that, unless otherwise stated, the use of “or” or “or” means “and / or”. Furthermore, the use of the term “comprising” and other forms such as “including,” “containing,” and “contains” are not limiting.

[0014] Unless otherwise stated, conventional methods within the scope of the art shall be used.

[0015] Unless specifically defined herein, the use of various commercially available products herein employs standard techniques. For example, they may be implemented in a manner known in the art or as described in this invention. The techniques and methods described herein can generally be implemented according to conventional methods well known in the art, based on the descriptions in the various summary and more specific documents cited and discussed in this specification.

[0016] The terms “optional / arbitrary” or “optionally / arbitrarily” mean that the event or situation described below may or may not occur, including both the occurrence and non-occurrence of the event or situation.

[0017] In a first aspect, the present invention provides: A composite pipe jacking construction method for sewage pipe networks based on fly ash grouting includes the following steps: S1. Construction preparation; S2. Perform jacking construction on the outer layer of reinforced concrete pipe; S3. Clean and inspect the interior of the outer reinforced concrete pipe; S4. Insert a welded steel pipe into the outer reinforced concrete pipe as an inner steel pipe and install the inner steel pipe. S5. Sealing and Grouting: After the inner steel pipe is installed and fixed, a grouting pipe is buried in the annular gap between the outer reinforced concrete pipe and the inner steel pipe; fly ash mortar is injected into the gap through the grouting pipe, and the gap is filled and compacted by segmented grouting; the grouting pipe opening is sealed after grouting is completed. S6. Acceptance and restoration.

[0018] Based on further solutions to the technical problems of the present invention, or simultaneous solutions to multiple technical problems, the preferred solution in the technical solution provided in the first aspect of the present invention includes: In S4, the construction process is as follows: A pipe section receiving platform and an inner steel pipe transport device are installed inside the working well; The inner steel pipe sections are hoisted one by one to the pipe section receiving platform, and then transported into the concrete jacking pipe by a lifting transport vehicle; The pipe sections are spliced ​​and welded together in sequence inside the concrete jacking pipe to form a continuous inner steel pipe. During the installation of the inner steel pipe, a support rod is installed every 3m along the axial direction; Both ends of the inner steel pipe are sealed with plugs and coated with waterproof mortar to ensure a tight seal at the ends.

[0019] Based on the above technical solution, further, in S4, during installation, the concentricity between the inner steel pipe and the outer reinforced concrete pipe is monitored in real time. The structure for concentricity monitoring includes: a ring bracket, a laser rangefinder, an tilt sensor, a control terminal, and a support rod. The ring bracket is fixedly installed on the outer wall of the front end of the inner steel pipe, and four laser ranging sensors are evenly arranged on the ring bracket along the circumference. The emission direction of each laser ranging sensor is radially pointing towards the inner wall of the outer reinforced concrete pipe. The ring-shaped bracket extends towards the middle and has a support rod. The end of the support rod is located at the center of the ring-shaped bracket, and the tilt sensor is installed at the center. The support rods are installed between the inner steel pipe and the outer reinforced concrete pipe, and are evenly distributed along the circumference.

[0020] Based on the above technical solution, the monitoring process is further as follows: Each laser rangefinder sensor measures its radial distance to the inner wall of the outer reinforced concrete pipe, which are respectively , , , After receiving these distance values, the control terminal calculates the concentricity deviation of the inner steel pipe axis relative to the outer reinforced concrete pipe axis. The calculation process is as follows: The four distance values ​​are divided into two groups of radial direction measurements. Preferably, the measurements are... and As a group, and The distances are grouped together, and half the absolute value of the difference between the two distance values ​​in each group is the eccentricity in that direction; among them, the eccentricity in the horizontal direction is... Vertical eccentricity ;Concentricity deviation ; The tilt sensor detects the tilt angle θ of the inner steel pipe axis; the control terminal generates a correction control signal based on the concentricity deviation e and the tilt angle θ. When the control terminal detects that the concentricity deviation in a certain direction exceeds the preset threshold and the tilt angle θ is not 0°, the corresponding support rod issues an extension or retraction command, pushing the inner steel pipe to move towards the center position.

[0021] Based on the above technical solution, the closed-loop control process is further as follows: The control terminal periodically collects data from the laser rangefinder sensor, calculates the current concentricity deviation, and compares it with the previous cycle. If the deviation is within the set allowable range, the current adjustment direction is maintained; if the deviation exceeds the set allowable range, the adjustment is reversed. Through iterative control, the concentricity deviation is kept within the allowable range.

[0022] Based on the above technical solution, further, in S5, the segmented grouting structure includes: a grouting main pipe, branch pipes of the grouting pipe, a pressure sensor, a flow sensor, a grouting pump, and a control terminal; specifically, the annular gap between the outer reinforced concrete pipe and the inner steel pipe is divided into multiple grouting sections along the axial direction, each section being 5-10m in length; each section is equipped with a branch pipe of the grouting pipe, which is connected to the grouting main pipe; each branch pipe of the grouting pipe is equipped with a pressure sensor and a flow sensor, which are used to detect the grouting pressure P and grouting flow rate Q of the grouting section in real time, respectively; the grouting pump is located at the inlet end of the grouting main pipe.

[0023] Based on the above technical solution, the segmented grouting process is further as follows: The control terminal stores preset target pressure ranges [Pmin, Pmax] and target flow thresholds Qth; When the real-time pressure P falls within the target pressure range [Pmin, Pmax] and the real-time flow rate Q is lower than the flow rate threshold Qth, it is determined that the annular void of the grouting section has been filled and compacted by the grout. The valve set at the outlet end of the corresponding grouting pipe is closed to stop the grouting of that section. When the real-time pressure P is lower than Pmin, it indicates that the grouting has not been filled or the grout has been lost. Control the grouting pump to increase the output power and increase the grouting pressure. When the real-time pressure P is higher than Pmax, it indicates that the grouting channel is blocked or there is a risk of over-grouting. Control the grouting pump to reduce the output power or stop grouting. Resume grouting after the pressure drops back to the target range.

[0024] Based on the above technical solution, further in S6, the process is as follows: conduct a water tightness test and strength test on the pipeline, restore the inspection well after confirming that it is qualified, and complete all construction.

[0025] Based on the above technical solution, further, in S6, the pipeline water tightness test process includes: Divide the test pipe section; Segmented water immersion treatment; Determine the test head; Water head observation of seepage volume; the calculation process for seepage volume is as follows: In the formula, q represents the measured seepage volume, in L / (min) (km); W is the total water replenishment volume; T is the observation time; L is the length of the test pipe section; Simultaneous visual inspection; Qualification: After the test is passed, drain the test water from the pipe and clean up any accumulated water and debris.

[0026] Based on the above technical solution, further, in S6, the intensity monitoring process includes: Inner steel pipe quality inspection; Inspection of the outer reinforced concrete pipe; Quality inspection of the annular grouting filling layer between the inner steel pipe and the outer reinforced concrete pipe; Comprehensive acceptance of the integrated composite pipeline system.

[0027] Compared with the prior art, the present invention has at least the following beneficial effects: 1. In terms of environmental protection improvement: 1) Trenchless construction with minimal environmental impact: Using the pipe jacking method eliminates the need for large-scale excavation of urban roads, reducing permit procedures, minimizing traffic disruption, and resulting in low noise and minimal earthwork excavation. The entire process is underground and concealed, having minimal impact on the lives and businesses of surrounding residents. Compared to traditional open-cut construction, it reduces earthwork excavation, construction dust emissions, and construction noise.

[0028] 2) Green-filled fly ash mortar: Using fly ash mortar as a filler material realizes the resource utilization of industrial solid waste. Furthermore, the low density of fly ash mortar significantly reduces the load on the inner steel pipe. Fly ash mortar has good fluidity and strong self-compacting properties, allowing for compaction without vibration, resulting in low noise and low energy consumption during construction.

[0029] 3) Excellent seepage prevention performance; the multi-layer waterproof structure (outer reinforced concrete pipe, fly ash mortar filling layer, inner steel pipe, and end waterproof mortar) ensures that sewage does not leak during transportation, protecting urban groundwater resources and soil environment.

[0030] 4) Resource conservation and energy reduction: After the inner steel pipe is sealed at both ends, the annular space between the inner and outer pipes is filled with fly ash mortar, forming an effective heat insulation and buffer layer, reducing heat loss and energy consumption during pipeline operation. The double-layer pipe structure can effectively extend the service life of the pipeline and significantly reduce the resource consumption and environmental impact caused by pipeline replacement.

[0031] 2. Enhanced security: 1) Structural safety and reliability: The outer reinforced concrete pipe provides strong external resistance against earth pressure, vehicle loads, and earthquakes; the inner steel pipe serves as the sewage transport channel, offering corrosion resistance and leak-proof performance. This dual-structure protection ensures that even in extreme circumstances where the outer reinforced concrete pipe suffers partial damage, the inner steel pipe will still prevent sewage leakage, avoiding environmental pollution accidents. Compared to the design life of a single concrete pipe, the double-layer pipe structure effectively extends the pipeline's service life.

[0032] 2) The construction process is safe and controllable; a support rod is installed every 3 meters to ensure the stability and accuracy of the inner steel pipe during installation, avoiding safety accidents caused by pipe section displacement or deformation. The active support system of this invention can provide more reliable concentric positioning. The fully enclosed waterproof structure at the ends and the pre-embedded grouting pipe design effectively prevent groundwater infiltration and the risk of sudden water and mud inrush.

[0033] 3) Long-term operational safety: The double-layer pipe structure significantly extends the service life of the pipeline and reduces the frequency and difficulty of later maintenance. Even if maintenance is required, the inner steel pipe can be used as an independent channel for inspection and repair.

[0034] 3. Double-layer composite pipe structure design: The pipeline employs a double-layer composite structure consisting of an outer reinforced concrete pipe and an inner steel pipe. The outer layer, made of Class III reinforced concrete, withstands external soil pressure and resists uneven settlement, while the inner layer, made of welded steel, carries the sewage and serves as a corrosion barrier. The two layers work together to significantly enhance the pipeline's structural safety and durability.

[0035] 4. Segmented jacking and support structure for the inner steel pipe: During the jacking process of the inner steel pipe, a support rod is installed every 3 meters to form a multi-point support system. The support rod system can provide more reliable concentric positioning and structural stability, effectively solving the problems of deformation and damage to the anti-corrosion layer caused by excessive weight of the large-diameter inner steel pipe during long-distance jacking.

[0036] 5. Filling method for fly ash mortar grouting: The annular gap between the inner and outer pipe structures is filled with fly ash mortar, which can significantly reduce the load on the inner steel pipe. It has good fluidity and strong self-compacting properties, and can fully fill the narrow annular gap. At the same time, the use of industrial solid waste fly ash has significant environmental benefits.

[0037] 6. Fully enclosed waterproof structure at the ends: The inner steel pipe is sealed at both ends and coated with waterproof mortar to form a complete end sealing structure. Combined with the pre-embedded grouting pipe and fly ash and mortar grouting, a multi-layer waterproof system is constructed to effectively prevent groundwater from seeping into the gap between the inner and outer pipes and avoid sewage leakage from polluting groundwater resources and soil environment.

[0038] 7. Concentricity monitoring results: 1) Dynamically maintain concentricity of inner and outer tubes during long-distance jacking to avoid eccentric compression: no longer relying on fixed support rods for passive positioning, continuous monitoring is carried out during jacking. Once a deviation occurs, the electric support rods immediately extend and retract to adjust the position in real time; no need to stop the machine for manual measurement and correction, greatly improving construction efficiency; 2) Effectively avoids local stress concentration in the inner steel pipe caused by eccentricity, prevents the anti-corrosion layer of the inner steel pipe from being scratched or abraded by the inner wall of the outer pipe, protects the anti-corrosion system of the steel pipe, and improves the long-term service life of the pipeline. 3) Closed-loop automatic control reduces reliance on the experience level of construction personnel and reduces the risk of human error, making it especially suitable for composite pipe jacking conditions involving long-distance, inclined drilling.

[0039] 8. Segmented grouting effect: 1) This invention simultaneously verifies two dimensions: pressure and flow rate. Only when both conditions are met—pressure meets the standard and flow rate decreases significantly—is the filling considered dense, significantly reducing the probability of voids caused by insufficient grouting. 2) Automatic overpressure protection: If the pressure rises sharply but the flow rate does not decrease, the system will automatically shut down to prevent the inner steel pipe from being deformed due to excessive pressure of fly ash mortar, thus protecting the inner steel pipe structure. 3) Each grouting section is independently controllable, with automatic start and stop of grouting, reducing manual supervision, standardizing grouting quality, and retaining original pressure-flow records throughout the construction process for easy quality traceability later. Attached Figure Description

[0040] Figure 1 This is a flowchart of the method of the present invention; Figure 2 This is a partial cross-sectional view of the present invention.

[0041] Figure label: 1. Inner steel pipe; 2. Outer reinforced concrete pipe; 3. Grouting pipe; 4. Fly ash mortar. Detailed Implementation

[0042] The following non-limiting embodiments are intended to enable those skilled in the art to gain a more comprehensive understanding of the present invention, but do not limit the invention in any way. The following content is merely an exemplary description of the scope of protection claimed by the present invention, and those skilled in the art can make various changes and modifications to the present invention based on the disclosed content, and such changes should also fall within the scope of protection claimed by the present invention.

[0043] The present invention will be further described below by way of specific embodiments. Unless otherwise specified, all instruments, devices, equipment, products, etc., used in the embodiments of the present invention are obtained through conventional commercial means.

[0044] Example 1 Reference Figure 1 and Figure 2 As shown in the figure, this embodiment provides a method for constructing a composite pipe jacking system for sewage pipe networks based on fly ash grouting, which includes the following steps: S1. Construction preparation; Among them, construction preparation is the foundation for ensuring the smooth achievement of the safety, quality, and schedule goals of the entire construction process. It should follow the principle of "survey first, design later, and then construction" and be implemented item by item. Specifically, this includes, but is not limited to, the following preparatory work: 1. Technical data review and special plan compilation: Collect survey reports, pipeline and structure data, review design parameters, compile special plans for intelligent construction of double-layer composite pipe jacking, and formulate special control parameters for concentricity correction, segmented grouting, etc.; complete plan review and carry out special technical briefings on equipment operation; 2. Site preparation: Complete the site layout, secure temporary power and configure a backup generator, complete the enclosure of the working well and receiving well, and inspect the hoisting equipment; set up surface environmental monitoring points and collect initial monitoring baseline data; 3. Inspection of pipes and auxiliary materials upon arrival: Inspect the outer reinforced concrete pipe 2 and the inner steel pipe 1 upon arrival; complete the sampling test of fly ash mortar 4 raw materials and determine the mortar mix ratio; 4. Verification of civil engineering conditions of the well body: Verify the seepage resistance of the working well and receiving well structure and the conditions of the reserved opening; debug the pipe section receiving platform and lifting transport vehicle; check the integrity of the water-stop ring at the opening; 5. Safety and emergency preparedness: Configure confined space protection and gas detection equipment, prepare emergency response plans for failures, and stockpile emergency sealing and spare components and materials; 6. Personnel training and safety briefing: Provide technical briefings to construction personnel, clarifying the key points and quality standards of each construction process; provide specialized training to operators; organize safety technical briefings and prepare emergency plans.

[0045] S2. Perform jacking construction on the outer layer of reinforced concrete pipe; Specifically, the construction of the working shaft and receiving shaft for pipe jacking will proceed according to the designed route. Pipe jacking machines and other equipment will be used to jack up Class III reinforced concrete pipes (F-type steel sockets) section by section, traversing urban roads and beneath existing structures. Preferably, the pipe diameter is DN1500-DN2000mm. During the jacking process, the axial deviation will be controlled to not exceed ±50mm, and the elevation deviation will not exceed ±30mm.

[0046] S3. Clean and inspect the interior of the outer reinforced concrete pipe 2; Specifically, after the outer reinforced concrete pipe 2 is jacked through, a high-pressure water gun can be used to clean the inside of the outer reinforced concrete pipe 2, removing debris and accumulated water. Pipeline inspection equipment is used to inspect the integrity of the outer pipe, confirming that there are no cracks or leaks, and that the axis and elevation deviations meet the design requirements.

[0047] S4. Insert a welded steel pipe into the outer reinforced concrete pipe 2 as an inner steel pipe 1, and install the inner steel pipe 1. Specifically, the construction process is as follows: 1) Install a pipe section receiving platform and an inner steel pipe transport device inside the working shaft, such as a lifting transport vehicle; 2) Hoist the inner steel pipe section 1 one by one to the pipe section receiving platform, and transport the pipe sections to the concrete jacking pipe using a lifting transport vehicle; 3) The pipe sections are spliced ​​and welded together in sequence inside the concrete jacking pipe to form a continuous inner steel pipe 1; 4) During the installation of the inner steel pipe 1, a support rod is set every 3m along the axial direction to ensure the concentric positioning and structural stability of the inner steel pipe 1 and the outer reinforced concrete pipe 2. 5) Both ends of the inner steel pipe 1 are sealed with existing structures such as plugs and plastered with waterproof mortar to ensure the end is sealed; Furthermore, during the installation of the inner steel pipe, the concentricity between the inner steel pipe 1 and the outer reinforced concrete pipe 2 is monitored in real time. The structure for concentricity monitoring includes: a ring support, a laser rangefinder, an inclination sensor, a control terminal, and an adjustable support rod. The control terminal can be a computer or other terminal equipment. The specific monitoring process based on these structures is as follows: A ring-shaped bracket is fixedly installed on the outer wall of the front end of the inner steel pipe 1. Four laser rangefinders are evenly arranged circumferentially on the ring-shaped bracket; other numbers can also be used, depending on actual needs. The emission direction of each laser rangefinder is radially directed towards the inner wall of the outer reinforced concrete pipe 2. A support rod extends from the ring-shaped bracket towards the center, with its end located at the center of the ring-shaped bracket. An inclination sensor is installed at this center position to detect the axial inclination angle of the inner steel pipe 1. It should be noted that multiple support rods can be installed, with their ends intersecting at the center of the ring-shaped bracket. During installation, the support rods may or may not contact the front end of the inner steel pipe 1; this does not affect the detection effect. Each laser rangefinder sensor measures its radial distance to the inner wall of the outer reinforced concrete pipe 2, which are respectively , , , After receiving these distance values, the control terminal calculates the concentricity deviation of the inner steel pipe 1 axis relative to the outer reinforced concrete pipe 2 axis. The specific calculation method is as follows: divide the four distance values ​​into two groups of measurements along the radial direction. Preferably, the measurements are... and As a group, and The distances are grouped together, and half the absolute value of the difference between the two distance values ​​in each group is the eccentricity in that direction; among them, the eccentricity in the horizontal direction is... Vertical eccentricity ;Concentricity deviation ; An inclination sensor detects the inclination angle θ of the inner steel pipe 1. The control terminal generates a correction control signal based on the concentricity deviation e and the inclination angle θ. Adjustable support rods are installed between the inner steel pipe 1 and the outer reinforced concrete pipe 2, evenly distributed circumferentially. The support rods can be electric push rods or hydraulic cylinders, connected to the control terminal signal. When the control terminal detects that the concentricity deviation in a certain direction exceeds a preset threshold (e.g., a preset value such as 5mm) and the inclination angle θ is not 0°, it sends an extension or retraction command to the support rod corresponding to that direction, pushing the inner steel pipe 1 to move towards the center position. The adjustment process of the support rod adopts closed-loop control: the control terminal periodically (e.g., every 5 seconds) collects data from the laser rangefinder sensor, calculates the current concentricity deviation, and compares it with the previous cycle. If the deviation is within the set allowable range, the current adjustment direction is maintained; if the deviation exceeds the set allowable range, the adjustment is reversed; through iterative control, the concentricity deviation is controlled within the allowable range. It should be noted that the allowable range is set based on actual construction conditions, which will not be elaborated on here.

[0048] S5. Sealing and grouting; Specifically, after the inner steel pipe 1 is installed and fixed, a grouting pipe 3 is buried in the annular gap between the outer reinforced concrete pipe 2 and the inner steel pipe 1; fly ash mortar 4 is injected into the gap through the grouting pipe 3, and the gap is filled tightly by segmented grouting; after the grouting is completed, the opening of the grouting pipe 3 is sealed. The segmented grouting structure includes: a main grouting pipe, branch pipes of grouting pipe 3, pressure sensors, flow sensors, a grouting pump, and a control terminal. Specifically, the annular gap between the outer reinforced concrete pipe 2 and the inner steel pipe 1 is divided axially into multiple grouting sections, each with a length of 5-10m. Each section is equipped with a branch pipe of grouting pipe 3, which is connected to the main grouting pipe. Each branch pipe of grouting pipe 3 is equipped with a pressure sensor and a flow sensor, which are used to detect the grouting pressure P and grouting flow rate Q of the grouting section in real time, respectively. The grouting pump is located at the inlet end of the main grouting pipe. Furthermore, the control process for segmented grouting based on the above structure is as follows: The control terminal stores preset target pressure ranges [Pmin, Pmax] and target flow thresholds Qth; When the real-time pressure P falls within the target pressure range [Pmin, Pmax] and the real-time flow rate Q is lower than the flow rate threshold Qth, it is determined that the annular void of the grouting section has been filled and compacted by the grout. The valve set at the outlet end of the corresponding grouting pipe is closed to stop the grouting of that section. When the real-time pressure P is lower than Pmin, it indicates that the grouting has not been filled or the grout has been lost. Control the grouting pump to increase the output power and increase the grouting pressure. When the real-time pressure P is higher than Pmax, it indicates that the grouting channel may be blocked or there is a risk of over-grouting. Control the grouting pump to reduce the output power or stop grouting, and resume grouting after the pressure drops back to the target range.

[0049] The above control logic is implemented through a PLC controller with a control cycle of 5 seconds to ensure real-time response to the grouting status. A pressure sensor with a range of 0-10 MPa is selected; an electromagnetic flow meter is used as the flow sensor, with the range selected based on the rated flow rate of the grouting pump.

[0050] Furthermore, the fly ash mortar, by weight, consists of: 100 parts cement, 30-60 parts fly ash, 45-60 parts water, and 0.5-1.5 parts water-reducing agent.

[0051] Fly ash should be grade II or above, with a residue of ≤25% on a 45μm sieve; When the fly ash content is less than 30 parts, the drag reduction effect is insufficient; When the fly ash content is >60 parts, the later consolidation strength is insufficient (the cement hydration products are insufficient to activate all the fly ash). The optimal fly ash content is 40-50 parts, at which point the funnel viscosity is 35-50s, balancing pumpability and drag reduction. During the jacking stage, fly ash forms a rolling lubricating layer between the outer wall of the steel pipe and the inner wall of the concrete pipe, transforming sliding friction into rolling friction.

[0052] Consolidation stage: The active SiO2 / Al2O3 of fly ash undergoes secondary hydration with the cement hydration product Ca(OH)2 to generate CSH gel, which fills the gaps, and the final consolidated body has a strength ≥5MPa.

[0053] S6. Acceptance and restoration; Specifically, after completing the above procedures, a water tightness test and strength test are conducted on the pipeline. Once the test is confirmed to be qualified, the inspection well is restored, and all construction is completed. Furthermore, the pipeline water tightness test process is as follows: 1) Divide the test sections: Divide the test sections according to the distance between inspection wells, and a single test should not exceed 5 consecutive well sections; 2) Slow water filling and soaking in sections: Water is injected from the upstream of the pipeline into the inner steel pipe 1 in 3 stages: the first stage is filled to 1 / 3 of the test water head, the second stage is filled to 2 / 3 of the test water head, and the third stage is filled to the specified test water head; after filling with water, soak for no less than 24 hours to allow the pipe wall to be fully wetted and eliminate the false water level drop caused by water absorption by concrete and welds.

[0054] 3) Determination of test head: The inner wall of the top of the upstream pipeline + 2m; when the calculated head exceeds the wellhead, the wellhead elevation shall be taken as the test head.

[0055] 4) Water head observation of seepage: After the soaking period is over, water is added to maintain a constant test water head, and the timing observation begins; the total observation time of seepage is not less than 30 minutes, water is continuously added to maintain a constant water head, and the total water inflow W, observation time T, and test tube length L are recorded.

[0056] 5) Calculate the measured seepage volume: In the formula, q represents the measured seepage volume, in L / (min) (km); W is the total water replenishment volume; T is the observation time; L is the length of the test pipe section.

[0057] 6) Simultaneous visual inspection: Inspect all steel pipe welds and end sealing locations throughout the process to check for dripping water, leakage, or dampness.

[0058] 7) Qualification criteria: ① No visible leakage at any pipe wall, weld, or end sealing position; ② The measured leakage amount is less than or equal to the allowable leakage amount of the pipe material specification, then the water tightness test is qualified; if it is not qualified, the leakage points should be investigated, repaired, and the water tightness test should be carried out again.

[0059] 8) After the test is passed, drain the test water from the pipe and clean up any accumulated water and debris in the pipe.

[0060] Furthermore, the strength testing process is as follows: 1. Quality inspection of inner steel pipe: 1) Visual inspection: Inspect the steel pipe body and circumferential welds for cracks, undercuts, and pores; check the anti-corrosion layer for scratches, bulges, peeling, or damage. 2) Non-destructive testing of welds: For the butt welds of the pipe sections, sampled ultrasonic testing (UT) was carried out to inspect for internal defects in the welds; the welding quality of the welds was confirmed to ensure the structural strength of the inner steel pipe 1; 3) Deformation inspection: retrieve historical data of concentricity monitoring throughout the construction process; verify the maximum radial deformation, and confirm that the steel pipe has no permanent plastic deformation and that the pipe wall has no local bulging or denting deformation.

[0061] 2. Inspection of the outer layer Grade III F-type steel socket reinforced concrete pipe: 1) Visual inspection: The spigot and socket of the pipe section are intact, without cracks, missing corners, or broken pieces; 2) Data verification: Verify the factory external pressure strength test report to confirm that the external pressure load level of the outer pipe meets the design requirements for soil cover and ground vehicle load; 3) CCTV pipe endoscopic inspection: The robot enters the interior of the outer pipe to inspect the pipe wall and pipe joint interfaces to see if there are any new cracks or misalignments caused by later jacking and grouting.

[0062] 3. Quality inspection of the annular grouting filling layer between the inner and outer pipes: The annular void is a critical load-bearing layer in the double-layer composite pipe and is not suitable for direct hydrostatic testing. A combination of data verification and non-destructive testing is used for assessment. The specific process is as follows: 1) Review of original construction process records: retrieve complete historical data of pressure and flow rate for each grouting segment stored in the intelligent grouting subsystem; verify whether each segment meets the criterion of "pressure reaching the design final pressure, while flow rate decreases to the termination flow rate threshold"; check for any abnormal overpressure alarm records. 2) Localized core sampling inspection: Drill cores in representative pipe sections to check the density of fly ash mortar 4 filling and observe whether there are holes, honeycombs, or delamination; after the core sampling is completed, seal the borehole with mortar to restore it; 3) Ultrasonic density test: The ultrasonic transmission method is used to test the annular grout layer to determine whether there are large-scale void defects.

[0063] 4. Comprehensive acceptance of the integrated composite pipeline: 1) All project qualification requirements: ① The water tightness test of the inner steel pipe 1 passed and there was no leakage; ②The weld of the inner steel pipe 1 passed the flaw detection test and showed no plastic deformation; ③ No new damage or cracks were found in the outer reinforced concrete pipe 2; ④ Circular grouting layer: The grouting history is complete, and random inspection / ultrasonic testing shows that the filling is dense and there are no large-area voids; ⑤ The concentricity monitoring records for the entire long-distance jacking process are complete, and the correction records are comprehensive.

[0064] 2) If all the above conditions are met, the overall strength and tightness of the composite pipe section are deemed to be qualified for acceptance; only then can the subsequent inspection well restoration process proceed.

[0065] Finally, it should be noted that the above content is only used to illustrate the technical solution of the present invention, and is not intended to limit the scope of protection of the present invention. Simple modifications or equivalent substitutions made by those skilled in the art to the technical solution of the present invention do not depart from the essence and scope of the technical solution of the present invention.

Claims

1. A method for constructing a composite pipe jacking system for sewage pipe networks based on fly ash grouting, characterized in that, Includes the following steps: S1. Construction preparation; S2. Perform jacking construction on the outer reinforced concrete pipe; S3. Clean and inspect the interior of the outer reinforced concrete pipe; S4. Insert a welded steel pipe into the outer reinforced concrete pipe as an inner steel pipe and install the inner steel pipe. S5. Sealing and Grouting: After the inner steel pipe is installed and fixed, a grouting pipe is buried in the annular gap between the outer reinforced concrete pipe and the inner steel pipe; fly ash mortar is injected into the gap through the grouting pipe, and the gap is filled and compacted by segmented grouting; the grouting pipe opening is sealed after grouting is completed. S6. Acceptance and restoration.

2. The method for constructing a composite pipe jacking system for sewage pipe networks based on fly ash grouting according to claim 1, characterized in that, In S4, the construction process is as follows: A pipe section receiving platform and an inner steel pipe transport device are installed inside the working well; The inner steel pipe sections are hoisted one by one to the pipe section receiving platform, and then transported into the concrete jacking pipe using a transport device; The pipe sections are spliced ​​and welded together in sequence inside the concrete jacking pipe to form a continuous inner steel pipe. During the installation of the inner steel pipe, a support rod is installed every 3m along the axial direction; Both ends of the inner steel pipe are sealed with plugs and coated with waterproof mortar to ensure a tight seal at the ends.

3. The method for constructing a composite pipe jacking system for sewage pipe networks based on fly ash grouting according to claim 1, characterized in that, In S4, during installation, the concentricity between the inner steel pipe and the outer reinforced concrete pipe is monitored in real time. The structure for concentricity monitoring includes: a ring bracket, a laser rangefinder, an tilt sensor, a control terminal, and a support rod. The ring bracket is fixedly installed on the outer wall of the front end of the inner steel pipe, and four laser ranging sensors are evenly arranged on the ring bracket along the circumference. The emission direction of each laser ranging sensor is radially pointing towards the inner wall of the outer reinforced concrete pipe. The ring-shaped bracket extends towards the middle and has a support rod. The end of the support rod is located at the center of the ring-shaped bracket, and the tilt sensor is installed at the center. The support rods are installed between the inner steel pipe and the outer reinforced concrete pipe, and are evenly distributed along the circumference.

4. The method for constructing a composite pipe jacking system for sewage pipe networks based on fly ash grouting according to claim 3, characterized in that, The monitoring process is as follows: Each laser rangefinder sensor measures its radial distance to the inner wall of the outer reinforced concrete pipe, which are respectively , , , After receiving these distance values, the control terminal calculates the concentricity deviation of the inner steel pipe axis relative to the outer reinforced concrete pipe axis. The calculation process is as follows: The four distance values ​​are divided into two groups of measurements in the radial direction. Let... and As a group, and The distances are grouped together, and half the absolute value of the difference between the two distance values ​​in each group is the eccentricity in that direction; among them, the eccentricity in the horizontal direction is... Vertical eccentricity ;Concentricity deviation ; The tilt sensor detects the tilt angle θ of the inner steel pipe axis; the control terminal generates a correction control signal based on the concentricity deviation e and the tilt angle θ. When the control terminal detects that the concentricity deviation in a certain direction exceeds the preset threshold and the tilt angle θ is not 0°, the corresponding support rod issues an extension or retraction command, pushing the inner steel pipe to move towards the center position.

5. The method for constructing a composite pipe jacking system for sewage pipe networks based on fly ash grouting according to claim 4, characterized in that, The closed-loop control process is as follows: The control terminal periodically collects data from the laser rangefinder sensor, calculates the current concentricity deviation, and compares it with the previous cycle. If the deviation is within the set allowable range, the current adjustment direction is maintained; if the deviation exceeds the set allowable range, the adjustment is reversed. Through iterative control, the concentricity deviation is kept within the allowable range.

6. The method for constructing a composite pipe jacking system for sewage pipe networks based on fly ash grouting according to claim 3, characterized in that, In S5, the segmented grouting structure includes: a main grouting pipe, branch pipes of the grouting pipe, a pressure sensor, a flow sensor, a grouting pump, and a control terminal; The annular gap between the outer reinforced concrete pipe and the inner steel pipe is divided into multiple grouting sections along the axial direction, each section being 5-10m in length. Each section is equipped with a branch pipe of the grouting pipe, which is connected to the main grouting pipe. Each branch pipe of the grouting pipe is equipped with a pressure sensor and a flow sensor, which are used to detect the grouting pressure P and grouting flow rate Q of the grouting section in real time, respectively. The grouting pump is located at the inlet end of the main grouting pipe.

7. The method for constructing a composite pipe jacking system for sewage pipe networks based on fly ash grouting according to claim 6, characterized in that, The segmented grouting process is as follows: The control terminal stores preset target pressure ranges [Pmin, Pmax] and target flow thresholds Qth; When the real-time grouting pressure P falls within the target pressure range [Pmin, Pmax] and the real-time flow rate Q is lower than the target flow rate threshold Qth, it is determined that the annular gap of the grouting section has been filled and compacted by the grout. The valve set at the outlet end of the corresponding grouting pipe is closed to stop the grouting of that section. When the real-time grouting pressure P is lower than Pmin, it indicates that the grouting has not been fully filled or the grout has been lost. Control the grouting pump to increase the output power and increase the grouting pressure. When the real-time grouting pressure P is higher than Pmax, it indicates that the grouting channel is blocked or there is a risk of over-grouting. Control the grouting pump to reduce the output power or stop grouting. Resume grouting after the pressure drops back to the target range.

8. The method for constructing a composite pipe jacking system for sewage pipe networks based on fly ash grouting according to claim 1, characterized in that, In S6, the process is as follows: conduct a water tightness test and strength test on the pipeline, restore the inspection well after confirming that it is qualified, and complete all construction.

9. A method for constructing a composite pipe jacking system for sewage pipe networks based on fly ash grouting according to claim 8, characterized in that, In S6, the pipeline water tightness test process includes: Divide the test pipe section; Segmented water immersion treatment; Determine the test head; Water head observation of seepage volume; the calculation process for seepage volume is as follows: In the formula, q represents the measured seepage volume, in L / (min) (km); W is the total water replenishment volume; T is the observation time; L is the length of the test pipe section; Simultaneous visual inspection; Qualification: After the test is passed, drain the test water from the pipe and clean up any accumulated water and debris.

10. A method for constructing a composite pipe jacking system for sewage pipe networks based on fly ash grouting according to claim 8, characterized in that, In S6, the intensity monitoring process includes: Inner steel pipe quality inspection; Inspection of the outer reinforced concrete pipe; Quality inspection of the annular grouting filling layer between the inner steel pipe and the outer reinforced concrete pipe; Comprehensive acceptance of the integrated composite pipeline system.