Geothermal and biomass coupled energy supply system and its heating method

By integrating geothermal extraction and irrigation, heat exchange, biomass heat source and heat pump upgrading unit, deep coupling of medium and low temperature geothermal energy and biomass energy is achieved, solving the problems of low utilization efficiency of medium and low temperature geothermal resources and insufficient stability of biomass energy supply, and improving the energy utilization efficiency and energy supply reliability of the system.

CN123154491APending Publication Date: 2026-11-24PETROCHINA CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611346769.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-01
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Due to their low grade and small temperature difference, medium and low temperature geothermal resources are not very efficient to use directly and have poor economic performance; biomass gasification combustion systems have insufficient energy supply stability and are affected by fluctuations in raw material supply.

Method used

By integrating the geothermal extraction and irrigation unit, heat exchange unit, biomass heat source unit, and heat pump quality improvement unit, and through two-stage cascade heat release and heat pump circulation, deep coupling of medium and low temperature geothermal energy and biomass energy is achieved. The saturated steam generated by the biomass heat source drives the heat pump to improve the heat quality of the geothermal water, and outputs two heating circulation water to meet the heating demand.

Benefits of technology

It improves the system's energy utilization efficiency, economy, and energy supply reliability, overcomes the problems of low utilization efficiency of medium and low temperature geothermal resources and insufficient stability of biomass energy supply, and realizes the cascade and efficient utilization of medium and low temperature geothermal energy and biomass energy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123154491A_ABST
    Figure CN123154491A_ABST
Patent Text Reader

Abstract

This application discloses a geothermal and biomass coupled energy supply system and its heating method, integrating a geothermal extraction and irrigation unit, a heat exchange unit, a biomass heat source unit, and a heat pump upgrading unit to achieve complementarity between medium- and low-temperature geothermal energy and biomass energy. Specifically, the geothermal water undergoes a two-stage heat release process, transferring heat to the first-path heating circulating water and the heat pump heat source water, respectively, to address the shortcomings of low-grade geothermal resources, resulting in poor utilization efficiency and economic performance. The saturated steam generated by the biomass heat source serves as the heat pump drive source, enabling the heat pump to extract low-grade heat from the heat pump heat source water heated by the geothermal water and raise it to a usable heating temperature, overcoming the insufficient energy supply stability when biomass operates alone. This application achieves coupling between geothermal heat release and biomass steam generation through a heat pump, enabling high-grade heat energy to drive low-grade heat energy upgrading, and allows for the joint output of two hot water supply lines, comprehensively improving the system's energy utilization efficiency, economy, and energy supply reliability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application belongs to the field of clean energy multi-energy complementary energy supply technology, specifically relating to a geothermal and biomass coupled energy supply system and its heating method. Background Technology

[0002] Geothermal resources are a typical clean energy source, widely distributed and directly exploitable. Biomass energy is also a clean and renewable energy source, with abundant reserves, second only to the three major fossil fuels: oil, coal, and natural gas. Biomass gasification technology can partially oxidize or decompose biomass under high-temperature conditions, converting it into biomass fuel gas rich in combustible components such as H2, CO, and CH4. Its energy utilization efficiency can reach over 75%, approximately twice the efficiency of traditional direct biomass combustion, and the process emits fewer pollutants.

[0003] However, the development and utilization of geothermal and biomass energy are currently largely independent. Low- and medium-temperature geothermal resources, due to their low grade and small temperature difference, have low direct utilization efficiency and poor economic viability. While biomass gasification and combustion systems can provide high-temperature heat sources, their energy supply stability is insufficient when operating alone due to fluctuations in raw material supply. Therefore, there is an urgent need to propose an energy supply system that deeply couples low- and medium-temperature geothermal energy with biomass energy to achieve cascaded and efficient utilization. Summary of the Invention

[0004] This application aims to provide a geothermal and biomass coupled energy supply system and its heating method, integrating a geothermal extraction and irrigation unit, a heat exchange unit, a biomass heat source unit, and a heat pump upgrading unit, enabling medium- and low-temperature geothermal energy and biomass energy to complement each other. Specifically, the geothermal water undergoes a two-stage heat release process, transferring heat to the first-line heating circulating water and the heat pump heat source water, respectively, to address the shortcomings of low-grade geothermal resources, resulting in poor utilization efficiency and economic performance. The saturated steam generated by the biomass heat source serves as the heat pump drive source, enabling the heat pump to extract low-grade heat from the heat pump heat source water heated by the geothermal water and raise it to a usable heating temperature, overcoming the insufficient energy supply stability when biomass operates alone. This application achieves coupling between geothermal heat release and biomass steam generation through a heat pump, enabling high-grade heat energy to drive low-grade heat energy upgrading, and allows for the joint output of two hot water supply lines, comprehensively improving the system's energy utilization efficiency, economy, and energy supply reliability.

[0005] To solve the above-mentioned technical problems, this application is implemented as follows: In a first aspect, embodiments of this application propose a geothermal and biomass coupled energy supply system, the energy supply system comprising: Geothermal extraction and irrigation unit (1), heat exchange unit (2), biomass heat source unit (3) and heat pump quality improvement unit (4); The heat exchange unit (2) includes a first heat exchanger (21) and a second heat exchanger (22); the geothermal extraction and irrigation unit (1) is connected to the first heat exchanger (21), and the first heat exchanger (21) is connected to the second heat exchanger (22); The biomass heat source unit (3) and the second heat exchanger (22) are respectively connected to the heat pump upgrading unit (4); The geothermal extraction and irrigation unit (1) is configured to collect geothermal water and transport the geothermal water to the heat exchange unit (2). The heat exchange unit (2) is configured to exchange heat between the geothermal water and the first heating circulation water in the first heat exchanger (21), whereby the first heating circulation water reaches the heating temperature after being heated, and the geothermal water completes the first cooling; and to exchange heat between the geothermal water that has completed the first cooling and the heat pump source water in the second heat exchanger (22), whereby the heat pump source water enters the heat pump quality improvement unit (4) after being heated, and the geothermal water completes the second cooling and is reinjected; The biomass heat source unit (3) is configured to generate combustible gas from biomass through a gasification reaction, and to burn the combustible gas to heat condensate water to obtain saturated steam. The heat pump upgrading unit (4) is configured to use the saturated steam as the driving heat source and the heated heat pump heat source water as the low-temperature heat source. The heat is raised through the heat pump circulation and then heated to heat the second heating circulation water, so that the second heating circulation water reaches the heating temperature. The first heating circulation water and the second heating circulation water are used together as the heat source output.

[0006] Optionally, the heat pump boosting unit (4) includes an evaporator, a generator, a condenser, and an absorber; The evaporator is connected to the second heat exchanger (22), and the generator is connected to the biomass heat source unit (3); The heat pump upgrading unit (4) is configured to use the saturated steam as a driving heat source to input into the generator, and the heated heat pump heat source water as a low-temperature heat source to input into the evaporator. After the heat is increased by the heat pump circulation, the heat is released in the absorber and the condenser to heat the second heating circulation water, so that the second heating circulation water is heated to the heating temperature.

[0007] Optionally, the geothermal production and injection unit (1) includes a geothermal production well (11) and a reinjection well (12). The geothermal production well (11) is connected to the first heat exchanger (21), and the reinjection well (12) is connected to the second heat exchanger (22); The geothermal extraction and injection unit (1) is configured to extract geothermal water using the geothermal production well (11) and transport it to the first heat exchanger (21), and to reinject the geothermal water discharged from the second heat exchanger (22) after the second cooling through the reinjection well (12) back into the underground thermal reservoir.

[0008] Optionally, the geothermal extraction and irrigation unit (1) further includes a cyclone separator (13) and a water-gas separator (14). The cyclone desander (13) and the water-gas separator (14) are connected in series between the geothermal production well (11) and the first heat exchanger (21); The cyclone desander (13) is configured to desand the geothermal water extracted from the geothermal production well (11); The water-gas separation device (14) is configured to perform gas-liquid separation on the geothermal water after sand removal in order to remove free gas from the geothermal water.

[0009] Optionally, the biomass heat source unit (3) includes a biomass gasifier (31) and a biomass gas-fired steam boiler (32). The gas outlet of the biomass gasifier (31) is connected to the burner inlet of the biomass gas-fired steam boiler (32); the biomass gas-fired steam boiler (32) is also connected to the heat pump upgrading unit (4). The biomass gasifier (31) is configured to convert pretreated biomass raw materials into the combustible gas through anoxic gasification reaction; The biomass gas-fired steam boiler (32) is configured to burn the combustible gas to heat the condensate into saturated steam and deliver the saturated steam to the heat pump upgrading unit (4).

[0010] Optionally, the biomass heat source unit (3) further includes a pretreatment device (33). The pretreatment device (33) is connected to the inlet of the biomass gasifier (31); The pretreatment device (33) is configured to crush, dry and screen the biomass raw material so that the processed biomass raw material meets the feeding requirements of the biomass gasifier (31).

[0011] Optionally, the system further includes a relay pressurization station (5); The first heat exchanger (21) is connected to a heating pipeline, and the relay pressurization station (5) is located on the heating pipeline; The first heat exchanger (21) is configured to send the first heating circulating water heated to the heating temperature through the heating pipe; The relay pressurization station (5) is configured to pressurize the first heating circulating water in the heating pipeline to overcome the transmission resistance.

[0012] Secondly, embodiments of this application provide a geothermal and biomass coupled energy supply method, the method being implemented through the energy supply system described in the first aspect, the energy supply method comprising; Geothermal water is extracted through the geothermal extraction and injection unit and transported to the first heat exchanger to exchange heat with the first heating circulation water. After the geothermal water completes the first cooling, it enters the second heat exchanger to exchange heat with the heat pump heat source water. After the geothermal water completes the second cooling, it is reinjected into the ground. The pretreated biomass raw materials are fed into a biomass heat source unit for oxygen-deficient oxidation to generate combustible gas, which is then burned to heat condensate and obtain saturated steam. The saturated steam and the heated heat pump source water are sent into the heat pump quality improvement unit. The saturated steam drives the heat pump, and the heated heat pump source water is used as a low-temperature heat source. The temperature of the second heating circulation water is raised to the heating temperature through the heat pump circulation. Then, the second heating circulation water and the first heating circulation water are combined as a heat source for output.

[0013] Optionally, the temperature of the geothermal water extracted by the geothermal extraction and irrigation unit is 60℃-70℃; The temperature of the geothermal water after the first cooling process is 40℃-50℃; The temperature of the geothermal water after the second cooling process is 20℃-30℃; The heating temperature is 85℃-95℃.

[0014] Optionally, the temperature of the heat pump source water after heating is 40℃-50℃; The temperature of the saturated steam is 160℃-180℃.

[0015] Beneficial technical effects: In the embodiments of this application, by integrating the geothermal extraction and injection unit, the heat exchange unit, the biomass heat source unit, and the heat pump quality improvement unit, the medium and low temperature geothermal energy and biomass energy are deeply complementary. Among them, the geothermal water releases heat in two stages through the first heat exchanger and the second heat exchanger in the heat exchange unit, transferring the medium and low temperature heat it carries to the first heating circulation water and the heat pump heat source water respectively, so that the geothermal water is fully extracted for heat energy before reinjection, thereby overcoming the defects of poor economic efficiency of medium and low temperature geothermal resources due to small temperature difference and low direct utilization efficiency. Meanwhile, the biomass heat source unit converts biomass into combustible gas through gasification reaction and burns it to produce saturated steam, which serves as a high-grade driving heat source for the heat pump upgrading unit. This allows the heat pump upgrading unit to drive the heat pump cycle with the saturated steam, extracting low-grade heat from the heat pump heat source water heated by geothermal water and raising it to a high-grade heat that can be used for heating. Thus, when the supply of biomass raw materials fluctuates, it can maintain basic heating capacity in combination with the continuous and stable output of geothermal water, thereby overcoming the defect of insufficient energy supply stability when the biomass gasification combustion system is running alone. In this application system, the heat release process of geothermal water is deeply coupled with the combustion and steam generation process of biomass energy. Through the heat pump upgrading unit, high-grade heat energy is driven and low-grade heat energy is upgraded. The high-grade steam generated by biomass not only directly serves as the driving source of the heat pump, but the heat exchanged by the heat pump is mainly used to upgrade the heat grade of the waste heat of geothermal water. This allows the medium and low temperature geothermal energy, which was originally difficult to use directly, to be transported to the temperature range where it can be heated. Finally, the two streams of hot water heated to the heating temperature are jointly output to the outside, realizing the cascaded and efficient utilization and grade matching of medium and low temperature geothermal energy and biomass energy, and improving the overall energy utilization efficiency, operating economy and energy supply reliability of the system.

[0016] Additional aspects and advantages of this application will be set forth in part in the description which follows, and in part will be obvious from the description, or may be learned by practice of this application. Attached Figure Description

[0017] The above and / or additional aspects and advantages of this application will become apparent and readily understood from the description of the embodiments taken in conjunction with the following drawings, in which: Figure 1 This is a schematic diagram of a geothermal and biomass coupled energy supply system proposed in an embodiment of this application; Figure 2 This is a schematic diagram of another geothermal and biomass coupled energy supply system proposed in an embodiment of this application.

[0018] Figure label: 1. Geothermal extraction and injection unit; 11. Geothermal production well; 12. Reinjection well; 13. Cyclone desander; 14. Water-gas separator; 2. Heat exchange unit; 21. First heat exchanger; 22. Second heat exchanger; 3. Biomass heat source unit; 31. Biomass gasifier; 32. Biomass gas-fired steam boiler; 33. Pretreatment device; 4. Heat pump upgrading unit; 5. Intermediate pressurization station; 6. Condensate storage tank; 7. Deaerator. Detailed Implementation

[0019] The embodiments of this application will now be described in detail. Examples of these embodiments are illustrated in the accompanying drawings, wherein the same or similar reference numerals denote the same or similar elements or elements having the same or similar functions throughout. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain this application, and should not be construed as limiting this application. All other embodiments obtained by those skilled in the art based on the embodiments of this application without inventive effort are within the scope of protection of this application.

[0020] The terms "first" and "second" in the specification and claims of this application may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise stated, "multiple" means two or more. Furthermore, "and / or" in the specification and claims indicates at least one of the connected objects, and the character " / " generally indicates that the preceding and following objects are in an "or" relationship.

[0021] In the description of this application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc., indicating the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this application.

[0022] In the description of this application, it should be noted that, unless otherwise expressly specified and limited, the terms "installation," "connection," and "linking" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection between two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.

[0023] Among related technologies, geothermal resources are a typical clean energy source, widely distributed, and directly exploitable. The Dongying Depression is a Cenozoic sedimentary basin, with its heat source mainly originating from deep crustal heat flow, indicating significant geothermal resource development potential. However, the geothermal reservoirs in this area are affected by geological structure and sedimentary characteristics, resulting in geothermal well water temperatures of only around 65℃ and a yield of approximately 90 m³ / min. 3Geothermal resources are of low quality, and developing them for heating or steam supply alone is costly and economically inefficient, making large-scale application difficult. Biomass energy is a clean and renewable energy source with abundant reserves. However, when used alone, biomass energy has a limited total heat output and is subject to seasonal fluctuations.

[0024] The embodiments of this application aim to achieve the following objectives through a three-in-one design of geothermal cascade heat exchange—biomass gasification and combustion—absorption heat pump enhancement: (1) By introducing medium-low temperature geothermal water at around 65℃ into the biomass energy steam-water circulation system, the cascade utilization of geothermal resources can be realized, the economic efficiency of geothermal development can be improved, and the problems of low grade of medium-low temperature geothermal resources and poor economic efficiency of individual development can be solved. (2) Using the high-temperature steam generated by biomass gasification as the driving heat source of the absorption heat pump, the low-temperature waste heat of geothermal water is pumped to the high-temperature zone to achieve energy complementarity between geothermal and biomass, two renewable energy sources, so as to raise the temperature and meet the heating or steam supply needs. (3) By using multi-energy coupling and cascade utilization, fossil energy consumption can be reduced, overall energy supply costs can be lowered, and the investment payback period can be shortened; Specifically, embodiments of this application propose an energy supply system that couples geothermal and biomass energy, such as... Figure 1 As shown, the power supply system includes: Geothermal extraction and irrigation unit 1, heat exchange unit 2, biomass heat source unit 3, and heat pump quality improvement unit 4; The heat exchange unit 2 includes a first heat exchanger 21 and a second heat exchanger 22; the geothermal extraction and irrigation unit 1 is connected to the first heat exchanger 21, and the first heat exchanger 21 is connected to the second heat exchanger 22. The biomass heat source unit 3 and the second heat exchanger 22 are respectively connected to the heat pump quality improvement unit 4; The geothermal extraction and irrigation unit 1 is configured to collect geothermal water and transport the geothermal water to the heat exchange unit 2; The heat exchange unit 2 is configured to exchange heat between the geothermal water and the first heating circulating water in the first heat exchanger 21, where the first heating circulating water reaches the heating temperature after being heated, and the geothermal water completes its first cooling; and to exchange heat between the geothermal water that has completed its first cooling and the heat pump source water in the second heat exchanger 22, where the heat pump source water enters the heat pump quality improvement unit 4 after being heated, and the geothermal water completes its second cooling and is reinjected. The biomass heat source unit 3 is configured to generate combustible gas from biomass through a gasification reaction, and to burn the combustible gas to heat condensate water to obtain saturated steam. The heat pump upgrading unit 4 is configured to use the saturated steam as the driving heat source and the heated heat pump heat source water as the low-temperature heat source. The heat is increased through the heat pump circulation and then heated to heat the second heating circulation water, so that the second heating circulation water reaches the heating temperature. The first heating circulation water and the second heating circulation water are used together as the heat source output.

[0025] It should be noted that, as Figure 1 As shown, the heat exchange unit 2 includes a first heat exchanger 21 and a second heat exchanger 22, and the two heat exchangers can be arranged in series. The output end of the geothermal extraction and irrigation unit 1 is connected to the geothermal water inlet of the first heat exchanger 21, so that the geothermal water extracted from the ground first enters the first heat exchanger 21; The geothermal water outlet of the first heat exchanger 21 is connected to the geothermal water inlet of the second heat exchanger 22, so that the geothermal water after the first cooling can enter the second heat exchanger 22 for a second cooling; thus, the geothermal water flows through the first heat exchanger 21 and the second heat exchanger 22 in sequence, realizing two-stage heat release. Both the first and second heat exchangers are plate heat exchangers. It should also be noted that in the first heat exchanger 21, the geothermal water exchanges heat with the first heating circulation water flowing through the heat exchanger. The geothermal water transfers heat to the heating circulation water, raising its temperature to the heating temperature before being directly output to the heat users. At the same time, in the second heat exchanger 22, the geothermal water, after completing the first cooling, exchanges heat with the heat pump source water flowing through the heat exchanger. The geothermal water transfers its remaining heat to the heat pump source water, raising its temperature before entering the heat pump upgrading unit 4 as a low-temperature heat source. After completing the second cooling, the geothermal water itself is discharged from the outlet of the second heat exchanger 22 and reinjected into the ground. The biomass heat source unit 3 is used to convert biomass raw materials into combustible gas through gasification reaction, and to heat condensate (at a temperature of 90°C) by burning the combustible gas to obtain saturated steam; the saturated steam is transported to the heat pump upgrading unit 4 through pipelines as the driving heat source of the heat pump upgrading unit 4. The external interfaces of the heat pump upgrading unit 4 are connected to the biomass heat source unit 3 and the second heat exchanger 22 respectively. Specifically, the driving heat source inlet of the heat pump upgrading unit 4 is connected to the steam outlet of the biomass heat source unit 3 for receiving saturated steam, and the low temperature heat source inlet of the heat pump upgrading unit 4 is connected to the heat pump heat source water outlet of the second heat exchanger 22 for receiving heat pump heat source water heated by geothermal water. The heat pump upgrading unit 4 has a heat outlet for outputting a second heating circulating water that has been heated to the heating temperature. The second heating circulating water and the first heating circulating water output from the first heat exchanger 21 are combined and jointly transported to heat users as a heating medium.

[0026] In this embodiment, the geothermal water undergoes two stages of heat exchange. In the first heat exchanger 21, it directly heats the first heating circulation water, achieving primary utilization of geothermal energy. In the second heat exchanger 22, the remaining heat is transferred to the heat pump source water, realizing the recovery of waste heat from the geothermal tailwater. The combustible gas produced by biomass gasification is burned to generate saturated steam, which is input into the heat pump upgrading unit 4 as a driving heat source. This allows the heat pump upgrading unit 4 to extract heat from the heat source water heated by the geothermal waste heat and raise it to a usable heating temperature before outputting it. Through the system of this embodiment, the utilization of geothermal energy is no longer limited to direct heat exchange within a limited temperature difference; its tailwater waste heat can also be fully recovered for heating. While providing a high-temperature driving heat source, biomass energy complements geothermal energy in terms of base load and peak load. When the supply of biomass raw materials fluctuates, geothermal energy can still continuously output heat. The two work together to ensure energy supply stability, solving the problems of low grade and poor economic efficiency of medium- and low-temperature geothermal resources, and the insufficient stability of biomass operating alone. This achieves efficient, stable, and low-cost clean energy supply.

[0027] In some embodiments of this application, such as Figure 1 As shown, the geothermal production and injection unit 1 includes a geothermal production well 11 and a reinjection well 12; The geothermal production well 11 is connected to the first heat exchanger 21, and the reinjection well 12 is connected to the second heat exchanger 22; The geothermal extraction and injection unit 1 is configured to extract geothermal water using the geothermal production well 11 and transport it to the first heat exchanger 21, and to reinject the geothermal water discharged from the second heat exchanger 22 after the second cooling through the reinjection well 12 back into the underground thermal reservoir.

[0028] It should be noted that, as Figure 1 As shown, the geothermal production and injection unit 1 consists of a geothermal production well 11 and a reinjection well 12. The geothermal production well 11 is a production well used to extract geothermal water from the underground thermal reservoir. The outlet of the geothermal production well 11 is connected to the first heat exchanger 21 to send the extracted geothermal water into the system for heat exchange. The reinjection well 12 is an injection well. The reinjection well 12 is connected to the geothermal water outlet of the second heat exchanger 22 and is used to reinject the cooled geothermal water after heat exchange into the underground thermal reservoir.

[0029] This embodiment of the application establishes a geothermal production well 11 and a reinjection well 12, connecting them respectively to a first heat exchanger 21 and a second heat exchanger 22, thereby achieving sustainable utilization of geothermal water without consuming water. The geothermal water extracted from the production well 11 releases heat through two stages of heat exchange and is then reinjected into the same underground geothermal reservoir via the reinjection well 12. This maintains the pressure balance of the geothermal reservoir, extends the service life of the geothermal field, and avoids resource waste and environmental pollution caused by direct discharge of geothermal water.

[0030] In some embodiments of this application, such as Figure 1 As shown, the geothermal extraction and irrigation unit 1 also includes a cyclone separator 13 and a water-gas separator 14; The cyclone desander 13 and the water-gas separator 14 are connected in series between the geothermal production well 11 and the first heat exchanger 21. The cyclone desander 13 is configured to desand the geothermal water extracted from the geothermal production well 11. The water-gas separation device 14 is configured to perform gas-liquid separation on the geothermal water after sand removal, so as to remove free gas from the geothermal water.

[0031] It should be noted that the cyclone desander 13 and the water-gas separator 14 are installed in series on the produced water pipeline between the geothermal production well 11 and the first heat exchanger 21 in the order of first removing sand and then degassing. Specifically, the outlet of the geothermal production well 11 is connected to the inlet of the cyclone separator 13, the outlet of the cyclone separator 13 is connected to the inlet of the water-gas separator 14, and the outlet of the water-gas separator 14 is then connected to the geothermal water inlet of the first heat exchanger 21. Among them, the hydrocyclone sand separator 13 utilizes the principle of centrifugal sedimentation to separate and settle solid particles such as sand carried in geothermal water during rotation, thereby preventing sand particles from abrading downstream pipes and equipment. The water-gas separation device 14 performs gas-liquid separation on the geothermal water after sand removal, separating and discharging the free gases (such as air, a small amount of associated gas, etc.) mixed in the geothermal water, so as to prevent the gas from accumulating on the heat exchange surface after entering the heat exchanger and forming gas resistance, which would affect the heat exchange efficiency.

[0032] In this embodiment, a cyclone desander 13 and a water-gas separator 14 are connected in series between the geothermal production well 11 and the first heat exchanger 21 to perform desandering and gas-liquid separation pretreatment on the extracted geothermal water. This effectively removes solid impurities and free gases from the geothermal water, preventing impurities from causing blockage, wear, and corrosion to the downstream first heat exchanger 21, second heat exchanger 22, and heat pump upgrading unit 4. This ensures the safe and efficient operation of the heat exchange equipment and extends the overall service life of the system.

[0033] In some embodiments of this application, such as Figure 1 As shown, the inlet of the second heat exchanger 22 in heat exchange unit 2 is connected to the heat pump lifting unit 4; It should be noted that the second heat exchanger 22 has a heat pump heat source water inlet and a heat pump heat source water outlet. The heat pump heat source water outlet of the second heat exchanger 22 is connected to the low-temperature heat source inlet of the heat pump upgrading unit 4, and is used to send the heated heat pump heat source water into the heat pump upgrading unit 4. The low-temperature heat source outlet of the heat pump upgrading unit 4 is connected to the heat pump heat source water inlet of the second heat exchanger 22, and is used to send the cooled heat pump heat source water back to the second heat exchanger 22 for reheating.

[0034] In practice, the heat pump source water absorbs heat from the geothermal water after the first cooling in the second heat exchanger 22, and after being heated to the set temperature, it enters the heat pump upgrading unit 4. After releasing heat in the evaporator of the heat pump upgrading unit 4, the temperature decreases, and then it returns to the second heat exchanger 22 through the pipeline to absorb heat and be heated again. This cycle repeats, forming a closed heat pump source water circulation loop between the second heat exchanger 22 and the heat pump upgrading unit 4. This loop exchanges heat with the geothermal water flow path in the second heat exchanger 22, realizing the continuous recovery and transportation of waste heat from the geothermal tailwater.

[0035] In some embodiments of this application, such as Figure 1 As shown, the biomass heat source unit 3 includes a biomass gasifier 31 and a biomass gas-fired steam boiler 32. The gas outlet of the biomass gasifier 31 is connected to the burner inlet of the biomass gas-fired steam boiler 32; the biomass gas-fired steam boiler 32 is also connected to the heat pump upgrading unit 4. The biomass gasifier 31 is configured to convert pretreated biomass raw materials into the combustible gas through an oxygen-deficient gasification reaction; The biomass gas-fired steam boiler 32 is configured to burn the combustible gas to heat the condensate into saturated steam and deliver the saturated steam to the heat pump upgrading unit 4.

[0036] It should be noted that the biomass gasifier 31 has a gas outlet, and the biomass gas-fired steam boiler 32 has a burner inlet. The gas outlet of the biomass gasifier 31 and the burner inlet of the biomass gas-fired steam boiler 32 are connected through a gas pipeline to transport the combustible gas generated by the biomass gasifier 31 to the boiler for combustion. The biomass gas-fired steam boiler 32 also has a steam outlet, which is connected to the generator inlet of the heat pump upgrading unit 4, for delivering the generated saturated steam to the heat pump upgrading unit 4 as a driving heat source.

[0037] In practice, the pretreated biomass feedstock enters the biomass gasifier 31, where it undergoes drying, pyrolysis, oxidation, and reduction reactions under oxygen-deficient conditions, transforming into biomass gas rich in combustible components such as H2, CO, and CH4. This gas enters the burner of the biomass gas-fired steam boiler 32 via a gas pipeline, where it burns and releases heat in the furnace to heat the condensate in the boiler to a saturated steam state. The saturated steam is then transported through the steam outlet and steam pipeline to the generator of the heat pump upgrading unit 4, serving as a driving heat source to promote the heat pump cycle.

[0038] In this embodiment, the biomass gasifier 31 is combined with the biomass gas-fired steam boiler 32. The biomass raw material is first converted into combustible gas through oxygen-deficient gasification, and then the combustible gas is fed into the boiler for combustion to generate saturated steam. The saturated steam is used as a driving heat source and delivered to the heat pump upgrading unit 4, so that the biomass energy is coupled with the geothermal energy in the form of high-temperature heat energy, providing a stable and reliable high-grade driving energy for the heat pump upgrading unit 4 to improve the heat grade of the low-temperature heat source water.

[0039] In some embodiments of this application, such as Figure 1 As shown, the biomass heat source unit 3 also includes a pretreatment device 33; The pretreatment device 33 is connected to the inlet of the biomass gasification furnace 31; The pretreatment device 33 is configured to crush, dry and screen the biomass raw material so that the processed biomass raw material meets the feeding requirements of the biomass gasifier 31.

[0040] It should be noted that the pretreatment device 33 is located upstream of the biomass gasifier 31, and its outlet is connected to the raw material inlet of the biomass gasifier 31 through a conveying mechanism, such as a belt conveyor or a screw feeder. The pretreatment device 33 is equipped with a crushing mechanism, a drying mechanism and a screening mechanism. The crushing mechanism includes a crusher or a pulverizer, the drying mechanism includes a hot air dryer, and the screening mechanism includes a vibrating screen. The biomass mainly comes from the pruning of a large number of fruit trees and garden trees in the surrounding area.

[0041] In practice, the biomass feedstock is first fed into the pretreatment device 33, where it is crushed to break large pieces into suitable sizes. Then, it is dried to reduce the moisture content to within the allowable range for the gasification process. Next, it is screened to remove impurities and select qualified feedstock with uniform particle size. After these treatments, the biomass feedstock is conveyed into the biomass gasifier 31 for anoxic gasification.

[0042] This embodiment of the application adds a pretreatment device 33 to the biomass heat source unit 3 and establishes a connection between it and the biomass gasifier 31, so that the particle size, moisture content and uniformity of the biomass raw material can meet the feeding requirements of the gasifier, thereby ensuring the stability of the reaction and gasification efficiency in the gasifier, and avoiding problems such as bridging blockage, insufficient reaction and fluctuation of gas calorific value caused by excessively large raw material size, excessively high moisture content or impurities.

[0043] In some embodiments of this application, such as Figure 1 As shown, the heat pump boosting unit 4 includes an evaporator, a generator, a condenser, and an absorber; The evaporator is connected to the second heat exchanger 22, and the generator is connected to the biomass heat source unit 3; The heat pump upgrading unit 4 is configured to use the saturated steam as a driving heat source input to the generator, and the heated heat pump heat source water as a low-temperature heat source input to the evaporator. After the heat is increased by the heat pump circulation, the heat is released in the absorber and the condenser to heat the second heating circulation water, so that the second heating circulation water is heated to the heating temperature.

[0044] It should be noted that the heat pump upgrading unit 4 is a type I absorption heat pump, which mainly includes four core components: evaporator, generator, condenser and absorber. In terms of external connections, the evaporator is connected to the second heat exchanger 22 in the heat exchange unit 2. Specifically, the heat pump heat source water outlet of the second heat exchanger 22 is connected to the heat source water inlet of the evaporator, and the heat source water outlet of the evaporator is connected to the heat pump heat source water inlet of the second heat exchanger 22 to form a closed loop of heat pump heat source water. The generator is connected to the biomass heat source unit 3. Specifically, the steam outlet of the biomass gas-fired steam boiler 32 is connected to the steam inlet of the generator, and the condensate outlet of the generator is connected to the return water outlet of the biomass gas-fired steam boiler 32 to form a closed loop of steam condensate. The absorber and condenser are connected to the hot water supply circuit to release heat to the second heating circulation water flowing through it.

[0045] It should also be noted that the coefficient of performance (COP) of the first type of absorption heat pump is about 0.4-0.5. Although the COP is less than 1, since waste heat (geothermal waste heat) and biomass steam are used as driving heat sources, the equivalent performance coefficient can reach 50-70 based on the electricity consumption, which has significant energy-saving significance and economic value. The heat pump can increase the hot water temperature by 15-30℃, effectively improving the utilization value of medium and low temperature geothermal water.

[0046] In practice, saturated steam generated by biomass heat source unit 3 enters the generator and serves as the driving heat source to heat the absorbent solution inside the generator, causing the refrigerant vapor in the solution to evaporate and precipitate. Simultaneously, heat pump heat source water, heated by the second heat exchanger 22, enters the evaporator and releases heat to the refrigerant inside the evaporator under vacuum, causing the refrigerant to evaporate into low-temperature steam. The high-temperature, high-pressure refrigerant vapor generated by the generator enters the condenser, releases heat, and condenses into liquid refrigerant. The low-temperature steam generated by the evaporator enters the absorber, is absorbed by the absorbent solution returning from the generator, and releases absorbed heat. Then, heat pump upgrading unit 4 releases the above heat to the second heating circulation water flowing through the absorber and condenser, raising its temperature to the heating temperature.

[0047] The heat pump upgrading unit 4 in this embodiment is an absorption heat pump structure. It uses saturated steam generated by biomass heat source unit 3 as the driving heat source input generator and heat pump heat source water heated in the second heat exchanger 22 as the low-temperature heat source input evaporator. This allows the heat pump upgrading unit 4 to use high-temperature steam to drive the heat pump cycle, extract low-grade heat from the low-temperature heat source water and raise it to a usable heating temperature before outputting it. This raises the waste heat of medium- and low-temperature geothermal tailwater, which is difficult to use directly, to a usable heating grade, thereby improving the utilization rate of medium- and low-temperature geothermal resources. Both the first and second heating circulating water lines come from the return water of the heating users' heating systems, with a temperature of approximately 45℃.

[0048] In some embodiments of this application, such as Figure 1 As shown, the system also includes a condensate storage tank 6 and a deaerator 7; The condensate storage tank 6 is connected to the heat pump upgrading unit 4, and the deaerator 7 is connected to both the condensate storage tank 6 and the biomass gas-fired steam boiler 32.

[0049] It should be noted that the condensate storage tank 6 is located between the generator and the deaerator 7 of the heat pump upgrading unit 4. The generator of the heat pump upgrading unit 4 has a condensate outlet, which is connected to the inlet of the condensate storage tank 6 and is used to receive the cooled condensate discharged from the generator. The outlet of the condensate storage tank 6 is connected to the inlet of the deaerator 7, which is used to send the stored condensate into the deaerator 7 for deoxygenation treatment. The outlet of the deaerator 7 is connected to the feedwater inlet of the biomass gas-fired steam boiler 32, and is used to send the deaerated condensate back to the boiler for reheating.

[0050] This embodiment of the application adds a condensate storage tank 6 and a deaerator 7 to the system to form a complete closed-loop cycle for steam condensate recovery and treatment. The condensate storage tank 6 collects and buffers the high-temperature condensate discharged from the generator, avoiding heat loss and water waste caused by direct discharge of condensate; the deaerator 7 deoxygenates the condensate to remove dissolved oxygen, preventing oxygen from corroding the boiler and steam pipelines and extending the service life of the equipment; the deoxygenated condensate is returned to the boiler for reheating into steam, realizing the recycling of condensate and the cascade recovery of heat, further improving the energy utilization efficiency and operational safety of the system.

[0051] In some embodiments of this application, such as Figure 1 As shown, the system also includes a relay pressurization station 5; The first heat exchanger 21 is connected to a heating pipeline, and the relay pressurization station 5 is located on the heating pipeline; The first heat exchanger 21 is configured to send the first heating circulating water heated to the heating temperature through the heating pipeline; The relay pressurization station 5 is configured to pressurize the first heating circulating water in the heating pipeline to overcome the transmission resistance.

[0052] It should be noted that the heating circulating water outlet of the first heat exchanger 21 is connected to a heating pipe, which is used to transport the first heating circulating water heated to the heating temperature in the first heat exchanger 21 to the heat user. The relay booster station 5 is set on the heating pipeline. The inlet of the relay booster station 5 is connected to the heating pipeline downstream of the first heat exchanger 21, and the outlet of the relay booster station 5 is connected to the heating pipeline leading to the heat user. The relay booster station 5 is equipped with a circulating water pump and supporting control and monitoring devices. It should also be noted that the relay pressurization station 5 is only installed on the heating side pipeline. The production well and reinjection well 12 of the geothermal extraction and injection unit 1 are not equipped with pressurization devices. The extraction of geothermal water relies on deep well submersible pumps, and the reinjection relies on natural water level differences. The extraction and reinjection on the geothermal extraction and injection side remain under no pressure or normal pressure, thereby realizing differentiated pressure management between pressurized transportation on the heating side and unpressurized reinjection on the geothermal side.

[0053] This embodiment of the application sets up a relay pressurization station 5 on the heating pipeline to pressurize and transport the first heating circulating water after it has been heated. This effectively overcomes the friction resistance and local resistance caused by long-distance transportation in the heating network, ensures that the heat medium can stably reach the end of each heat user, and improves the hydraulic conditions and heating effect of the heating system.

[0054] In some embodiments of this application, the heating return water is returned to the first heat exchanger 21 via the relay pressurization station 5 to be heated to the heating temperature, thus enabling the hot water to be recycled.

[0055] In some embodiments of this application, a structure with two sets of water circulation heating can also be used, specifically: like Figure 2 As shown, the geothermal extraction and irrigation unit 1 can be equipped with two independently operating geothermal extraction and irrigation units 1. The two sets of circulation structures are the same, each containing its own geothermal production well 11, cyclone desander 13, water-gas separator 14 and reinjection well 12.

[0056] To match the two sets of water circulation heating, the heat exchange unit 2 is also set as two independent structures, and each structure is the same, each containing its own first heat exchanger 21 and second heat exchanger 22.

[0057] The produced water from both geothermal circulation systems is transported to their respective heat exchangers for cascade heat exchange. The heating circulating water generated by the heat exchange is then combined and supplied to heat users. The geothermal water after heat exchange is reinjected into the underground thermal reservoir through their respective reinjection wells 12.

[0058] like Figure 2 As shown, when two independent geothermal extraction and irrigation units 1 are set up, only one set of biomass heat source unit 3 and heat pump quality improvement unit 4 is required.

[0059] In practice, two geothermal production wells 11 extract geothermal water from the underground geothermal reservoir and transport it through produced water pipelines. A hydrocyclone desander 13 and a water-gas separator 14 are connected in series along the water flow direction on the produced water pipelines. The geothermal water first enters the hydrocyclone desander 13 to remove sand and other solid particles carried in it, and then enters the water-gas separator 14 for gas-liquid separation to remove free gas entrained in the geothermal water. After desandering and degassing pretreatment, the geothermal water enters its own independently installed first heat exchanger 21 through the produced water pipelines.

[0060] The geothermal water enters the first heat exchanger 21 and exchanges heat with the first heating circulation water. After the geothermal water releases heat, its temperature decreases, completing the first cooling process. The first heating circulation water absorbs heat and rises in temperature, and is then output as a heating medium through the heating pipeline.

[0061] After the first cooling process, the geothermal water flows out from the geothermal water outlet of the first heat exchanger 21 and enters the geothermal water side channel of the second heat exchanger 22 through a pipeline. Simultaneously, the heat pump source water returning from the heat pump upgrading unit 4 is pressurized by a circulating pump and enters its own independently configured second heat exchanger 22. In the second heat exchanger 22, the geothermal water exchanges heat with the heat pump source water. The geothermal water releases heat again, lowering its temperature and completing the second cooling process. The heat pump source water absorbs heat, raises its temperature, and then enters the evaporator of the heat pump upgrading unit 4 through the heat pump source water circulation pipeline, serving as a low-temperature heat source to release heat into the heat pump circulation. After releasing heat in the evaporator, the heat pump source water lowers its temperature and then returns to its own independently configured second heat exchanger 22 via the circulating pump to absorb heat again and raise its temperature, forming a closed-loop circulation of the heat pump source water between the second heat exchanger 22 and the heat pump upgrading unit 4.

[0062] After the second cooling process, the geothermal water flows out from the geothermal water outlet of the second heat exchanger 22 and is transported to the reinjection well 12 through their respective reinjection pipelines. Under no-pressure or normal-pressure conditions, it is naturally reinjected into the same underground thermal reservoir to achieve same-layer reinjection and maintain the pressure balance of the thermal reservoir.

[0063] Biomass heat source unit 3 is shared by two geothermal extraction and irrigation heat exchange cycles. After pretreatment, the biomass feedstock is fed into biomass gasifier 31 for oxygen-deficient gasification, producing biomass fuel gas rich in combustible components such as H2, CO, and CH4. The fuel gas is then fed into biomass fuel gas steam boiler 32 for combustion, heating the condensate to obtain saturated steam. The saturated steam is transported via steam pipeline to the generator of heat pump upgrading unit 4, serving as the driving heat source to power the heat pump cycle. After releasing heat, the saturated steam condenses into condensate, which is collected in a softened condensate tank, deoxygenated by deaerator 7, and then returned to the boiler for reheating, forming a closed-loop cycle of steam and condensate.

[0064] The heat pump upgrading unit 4 employs a type I absorption heat pump, comprising an evaporator, a generator, a condenser, and an absorber. The evaporator receives heat pump source water heated by two sets of second heat exchangers 22, using it as a low-temperature heat source to release heat; the generator receives saturated steam as a driving heat source. The heat pump upgrading unit 4 uses saturated steam to drive an internal heat pump circulation, extracting and raising the low-grade heat from the heat pump source water to the heating temperature, releasing heat in the absorber and condenser to heat the second heating circulation water. The second heating circulation water first flows through the absorber within the heat pump upgrading unit 4, where it is heated by absorbed heat, and then flows through the condenser, where it is further heated to the heating temperature by condensation heat, and is output as the heating medium. The second heating circulation water merges with the first heating circulation water, is pressurized by a relay pressurization station 5 located on the heating pipeline, and together they are transported to heat users as the heating medium.

[0065] In some embodiments of this application, such as Figure 2As shown, when using two independent geothermal extraction and irrigation units 1, the heating return water is pressurized by the relay pressurization station 5 and then returned to the two independently operating first heat exchangers 21 to continue heating to the heating temperature, thus making the hot water circulate.

[0066] This application embodiment also provides an energy supply method that couples geothermal and biomass, the method through... Figure 1 The illustrated power supply system is implemented, and the power supply method includes: Step S1: Geothermal water is extracted through the geothermal extraction and injection unit 1 and transported to the first heat exchanger 21 to exchange heat with the first heating circulation water. After the geothermal water completes the first cooling, it enters the second heat exchanger 22 to exchange heat with the heat pump heat source water. After the geothermal water completes the second cooling, it is reinjected into the ground. Step S2: The pretreated biomass raw material is fed into the biomass heat source unit 3 for oxygen-deficient oxidation to generate combustible gas, and then the combustible gas is burned to heat the condensate to obtain saturated steam. Step S3: The saturated steam and the heated heat pump source water are sent into the heat pump quality improvement unit 4. The saturated steam drives the heat pump, and the heated heat pump source water is used as a low-temperature heat source. The temperature of the second heating circulation water is raised to the heating temperature through the heat pump circulation. Then the second heating circulation water and the first heating circulation water are combined as the output heat source.

[0067] It should be noted that step S1 is a geothermal cascade heat exchange step. The geothermal extraction and injection unit 1 extracts geothermal water from the underground thermal reservoir and transports it to the first heat exchanger 21 to exchange heat with the first heating circulation water for the first time. After the geothermal water releases some heat, it completes the first cooling. Then it enters the second heat exchanger 22 to exchange heat with the heat pump heat source water for the second time. After the geothermal water releases the remaining usable heat, it completes the second cooling. Then it is reinjected into the underground thermal reservoir through the reinjection well 12. Step S2 is the biomass steam generation step. The pretreated biomass feedstock enters the gasifier and undergoes a gasification reaction under oxygen-deficient conditions to generate biomass gas rich in combustible components such as H2, CO, and CH4. This gas is then fed into a gas-fired steam boiler for combustion, and the heat released heats the condensate in the boiler to a saturated steam state. Step S3 is the heat pump quality improvement and heating step. The heat pump heat source water heated in the second heat exchanger 22 in step S1 enters the evaporator of the heat pump quality improvement unit 4 as a low-temperature heat source. The saturated steam generated in step S2 enters the generator of the heat pump quality improvement unit 4 as a driving heat source. The heat pump quality improvement unit 4 drives the internal heat pump circulation with saturated steam to extract and raise the low-grade heat in the heat pump heat source water to the available heating temperature to heat the second heating circulation water. The second heating circulation water heated to the heating temperature is combined with the first heating circulation water heated in the first heat exchanger 21 in step S1 and together they are used as a heat source to be output to the heat user.

[0068] The energy supply method provided in this application integrates geothermal extraction and irrigation, cascade heat exchange, biomass gasification steam generation, and heat pump upgrading and heating into a complete process, achieving deep coupling between geothermal energy and biomass energy. The geothermal water undergoes two stages of heat exchange, realizing the cascade release and full utilization of geothermal energy. The saturated steam generated after the biomass raw material is gasified and burned serves as the driving heat source input to the heat pump upgrading unit 4, extracting and raising the waste heat of the originally low-grade, difficult-to-use geothermal tailwater to a usable heating temperature. This effectively solves the problems of low direct utilization efficiency of medium- and low-temperature geothermal resources and insufficient stability of biomass operating alone. This method has good operability and engineering applicability.

[0069] In the embodiments of this application, the temperature of the geothermal water extracted by the geothermal extraction and irrigation unit 1 is 60℃-70℃; The temperature of the geothermal water after the first cooling process is 40℃-50℃; The temperature of the geothermal water after the second cooling process is 20℃-30℃; The heating temperature is 85℃-95℃.

[0070] It should be noted that the geothermal water extracted from the underground thermal reservoir by geothermal extraction and irrigation unit 1 has a temperature of 60℃-70℃, which covers the actual water output temperature range of most medium and low temperature geothermal resources. After the geothermal water undergoes its first heat exchange with the first heating circulation water via the first heat exchanger 21, its temperature drops to 40℃-50℃. At this point, some of the heat from the geothermal water has been extracted for direct heating of the hot water supply. After the geothermal water undergoes a second heat exchange with the heat pump source water via the second heat exchanger 22, its temperature further drops to 20℃-30℃. At this point, the usable heat in the geothermal water has been largely released, reaching the appropriate temperature conditions for reinjection. The first heating circulating water is directly heated by the first heat exchanger 21, and the second heating circulating water is heated by the heat pump quality improvement unit 4. Both reach a heating temperature of 85℃-95℃, which matches the water supply temperature of the radiator heating system.

[0071] The method described in this application establishes a temperature-gradient utilization path, in which geothermal water is gradually cooled from 60℃-70℃ to 20℃-30℃ before reinjection. This achieves full release and tiered extraction of geothermal heat, avoiding heat waste due to insufficient cooling or reinjection difficulties due to excessive cooling. The heating temperature reaches 85℃-95℃, which matches the design parameters of radiator heating systems and has good engineering adaptability. Simultaneously, the reinjection temperature is controlled at 20℃-30℃, close to the normal ground temperature, resulting in minimal thermal disturbance to the geothermal reservoir. This is beneficial for maintaining long-term stable reinjection of the geothermal reservoir and the sustainable development of geothermal resources.

[0072] In some embodiments of this application, the temperature of the heat pump heat source water after heating is 40°C-50°C; The temperature of the saturated steam is 160℃-180℃.

[0073] It should be noted that the temperature of the heat pump source water after heating is 40℃-50℃. This heat pump source water absorbs the remaining heat from the geothermal water after the first cooling in the second heat exchanger 22, and then enters the evaporator of the heat pump upgrading unit 4, where it releases heat to the heat pump circulation as a low-temperature heat source. The temperature range of 40℃-50℃ ensures that the heat pump source water can effectively extract waste heat from the geothermal water, and also meets the requirements of the heat pump evaporator for the inlet heat source temperature, enabling the evaporator to stably and efficiently evaporate the refrigerant under this temperature condition.

[0074] The saturated steam has a temperature of 160℃-180℃. This saturated steam is generated by heating condensate at 85℃-95℃ in a biomass gas-fired steam boiler 32, and then enters the generator of the heat pump upgrading unit 4 as a driving heat source to drive the heat pump cycle. The temperature range of 160℃-180℃ falls within the medium-low pressure saturated steam temperature range, which provides a sufficiently high driving temperature for the absorption heat pump generator to maintain the normal operation of the heat pump cycle, while avoiding the equipment cost and safety risks associated with requiring a high-pressure steam boiler due to excessively high temperatures.

[0075] To enable those skilled in the art to better understand this application, the following embodiments will be used to provide a detailed description of a geothermal and biomass coupled energy supply system and its heating method provided in this application.

[0076] Example 1 Example 1 uses the following Figure 1 The system shown includes the following steps: 1. After the system starts, open the produced water valve of geothermal production well 11, start the submersible pump, and geothermal production well 11 extracts geothermal water at a temperature of 65℃ from the underground thermal reservoir at a flow rate of 90m³ / h. 3 / h, transported through the produced water pipeline; the 65℃ geothermal water first enters the hydrocyclone desander 13 to remove solid particles such as sand carried in the geothermal water, and then enters the water-gas separator 14 for gas-liquid separation treatment to remove free gas mixed in the geothermal water. 2. After pretreatment by sand removal and degassing, the 65°C geothermal water enters the geothermal water side channel of the first heat exchanger 21. At the same time, the 45°C return water from the heating system enters the hot water side channel of the first heat exchanger 21 as the first heating circulating water. In the first heat exchanger 21, the 65°C geothermal water exchanges heat with the 45°C first heating circulating water. After releasing heat, the geothermal water's temperature drops to 48°C, completing the first cooling. After absorbing heat, the first heating circulating water rises to 90°C and is then transported to the heat users as a heating medium. 3. After the first cooling, the 48°C geothermal water flows out from the first heat exchanger 21 and enters the geothermal water side channel of the second heat exchanger 22. At the same time, the 22°C heat pump source water returning from the heat pump upgrading unit 4 enters the heat source water side channel of the second heat exchanger 22. In the second heat exchanger 22, the 48°C geothermal water and the 22°C heat pump source water undergo secondary heat exchange. After the geothermal water releases heat again, its temperature drops to 24°C, completing the second cooling. After absorbing heat, the heat pump source water rises to 45°C and enters the evaporator of the heat pump upgrading unit 4 as a low-temperature heat source. After completing the two cooling processes, the 24°C geothermal water is transported to the reinjection well 12 through the reinjection pipeline and is naturally reinjected into the same underground thermal reservoir under no-pressure or normal-pressure conditions. 4. The biomass raw material is fed into the pretreatment device 33, where it is crushed, dried and screened in sequence to remove impurities and control the particle size and moisture content of the raw material so that it meets the feeding requirements of the gasifier. 5. The pretreated biomass feedstock is fed into biomass gasifier 31, where it undergoes a gasification reaction under anaerobic conditions, sequentially going through four stages: drying, pyrolysis, oxidation, and reduction, transforming it into a product rich in H2, CO, and CH4. 44 Biomass gas with combustible components; the biomass gasifier 31 achieves self-balancing load regulation by controlling the amount of raw material supplied and the amount of gasifying agent supplied; 6. The biomass gas produced by the biomass gasifier 31 is drawn to the burner of the biomass gas-fired steam boiler 32 by a gas-fired induced draft fan. It burns and releases heat in the boiler furnace, heating the 90°C condensate in the boiler to 170°C saturated steam. The 170°C saturated steam is transported via steam pipeline to the generator of the heat pump upgrading unit 4, serving as a driving heat source to power the heat pump cycle. After releasing heat in the generator, the steam condenses into 90°C condensate, which is collected and buffered in the condensate storage tank 6 and then sent to the deaerator 7 for deoxygenation. The deoxygenated 90°C condensate is returned to the biomass gas-fired steam boiler 32 for reheating, forming a closed-loop circulation of steam condensate. The charcoal residue produced by the biomass gasifier 31 enters the charcoal residue steam boiler for further recovery of waste heat. 7. The heat pump upgrading unit 4 adopts a type I absorption heat pump, including an evaporator, a generator, a condenser, and an absorber. The heat pump source water heated to 45°C by the second heat exchanger 22 enters the evaporator, releases heat to the refrigerant, and then drops to 22°C. It returns to the second heat exchanger 22 via a circulation pump to absorb heat again and be heated, forming a closed loop of heat pump source water. 170°C saturated steam enters the generator, heats the absorbent solution, causing the refrigerant vapor in it to evaporate and precipitate. The steam itself releases heat and then condenses into 90°C condensate, which returns to the boiler for reheating. The high-temperature and high-pressure refrigerant vapor generated by the generator enters the condenser, releases heat, and condenses into liquid refrigerant. After throttling, it enters the evaporator. The low-temperature steam generated by the evaporator enters the absorber, is absorbed by the absorbent solution returning from the generator, and releases absorbed heat. The second heating circulation water flowing through the absorber and condenser is heated to 90°C. 8. The second heating circulating water, heated to 90°C, is pressurized by the relay pressurization station 5 located on the heating water supply pipeline, and then merges with the first heating circulating water, which is also heated to 90°C, to be transported to the heat users as a heating medium. The heating return water is returned to the first heat exchanger 21 via the relay pressurization station 5 for further heating, and so on.

[0077] In this embodiment 1, the system further includes the following configuration and operation control methods: In terms of system configuration, the geothermal extraction and injection unit is equipped with 6 geothermal production wells and 6 reinjection wells. Each production well has an outlet water temperature of 65℃ and a flow rate of 90 m³ / h. 3 / h; The geothermal extraction and irrigation unit is equipped with one cyclone sand separator 13 and one water-gas separator 14; the heat exchange unit is equipped with six primary plate heat exchangers 21 and six secondary plate heat exchangers 22; the heat pump upgrading unit is equipped with one Class I absorption heat pump, which includes an evaporator, a generator, a condenser and an absorber. The biomass heat source unit is equipped with three biomass gasification furnaces 31 and one biomass gas-fired steam boiler 32, and is also equipped with a pretreatment device 33 and a gas-fired induced draft fan. The system is also equipped with several temperature sensors, pressure sensors, and flow sensors, several electric regulating valves, and a central control system.

[0078] During normal operation, the central control system automatically adjusts the opening of each electric regulating valve and the load of the biomass gasifier 31 based on feedback parameters such as heat load demand, geothermal water temperature, geothermal water flow rate, and steam pressure from the heat user side, so as to maintain stable operation of the system under the set operating conditions.

[0079] Actual measurements show that, with the above configuration and operating mode, the geothermal heat exchange load is approximately 25.1MW, the biomass steam-driven heat load is approximately 23MW, the total system heating load is approximately 48.1MW, the geothermal water reinjection temperature is 24℃, and the annual operating cost is approximately 18.92 million yuan.

[0080] In summary, the embodiments of this application, through the cascade heat exchange setup of the first and second heat exchangers, enable the 65°C geothermal water to release heat sequentially, and finally reduce the temperature to 24°C for reinjection, significantly improving the utilization rate of geothermal resources. A single system can achieve a geothermal heat exchange load of approximately 25.1MW, effectively solving the technical bottlenecks of low quality of medium and low temperature geothermal resources and poor economic viability of independent development.

[0081] In this embodiment, the biomass source is mainly pruned branches from a large number of fruit trees and garden trees in the surrounding area, and the fuel supply cycle matches the heating cycle. By coupling the low-temperature waste heat from geothermal water with the high-temperature heat source of biomass steam through a first-type absorption heat pump, a temperature gradient of "low-temperature geothermal → medium-temperature heat medium → high-temperature heating" is achieved. The biomass gasification combustion system provides approximately 23MW of steam-driven heat load, which, together with the geothermal system, achieves a total heating load of 48.1MW. The two energy sources complement each other, significantly improving the overall energy efficiency of the system.

[0082] Compared with the pure biomass energy supply scheme, the "geothermal + biomass" coupling scheme adopted in this application increases the investment by about RMB 8.04 million. However, by replacing part of the biomass heating with geothermal heating, the annual operating cost is reduced by about RMB 2.88 million. The static investment payback period for the additional investment is only 2.79 years. The system operating cost is significantly reduced, and the economic efficiency is significantly better than the single energy supply scheme.

[0083] In the description of this specification, the references to terms such as "one embodiment," "some embodiments," "illustrative embodiment," "example," "specific example," or "some examples," etc., indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment or example is included in at least one embodiment or example of this application. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples.

[0084] Although embodiments of this application have been shown and described, those skilled in the art will understand that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of this application, the scope of which is defined by the claims and their equivalents.

Claims

1. A geothermal and biomass coupled energy supply system, characterized in that, The energy supply system includes: Geothermal extraction and irrigation unit (1), heat exchange unit (2), biomass heat source unit (3) and heat pump quality improvement unit (4); The heat exchange unit (2) includes a first heat exchanger (21) and a second heat exchanger (22); the geothermal extraction and irrigation unit (1) is connected to the first heat exchanger (21), and the first heat exchanger (21) is connected to the second heat exchanger (22); The biomass heat source unit (3) and the second heat exchanger (22) are respectively connected to the heat pump upgrading unit (4); The geothermal extraction and irrigation unit (1) is configured to collect geothermal water and transport the geothermal water to the heat exchange unit (2). The heat exchange unit (2) is configured to exchange heat between the geothermal water and the first heating circulation water in the first heat exchanger (21), whereby the first heating circulation water reaches the heating temperature after being heated, and the geothermal water completes the first cooling; and to exchange heat between the geothermal water that has completed the first cooling and the heat pump source water in the second heat exchanger (22), whereby the heat pump source water enters the heat pump quality improvement unit (4) after being heated, and the geothermal water completes the second cooling and is reinjected; The biomass heat source unit (3) is configured to generate combustible gas from biomass through a gasification reaction, and to burn the combustible gas to heat condensate water to obtain saturated steam. The heat pump upgrading unit (4) is configured to use the saturated steam as the driving heat source and the heated heat pump heat source water as the low-temperature heat source. The heat is raised through the heat pump circulation and then heated to heat the second heating circulation water, so that the second heating circulation water reaches the heating temperature. The first heating circulation water and the second heating circulation water are used together as the heat source output.

2. The geothermal and biomass coupled energy supply system according to claim 1, characterized in that, The heat pump upgrading unit (4) includes an evaporator, a generator, a condenser, and an absorber; The evaporator is connected to the second heat exchanger (22), and the generator is connected to the biomass heat source unit (3); The heat pump upgrading unit (4) is configured to use the saturated steam as a driving heat source to input into the generator, and the heated heat pump heat source water as a low-temperature heat source to input into the evaporator. After the heat is increased by the heat pump circulation, the heat is released in the absorber and the condenser to heat the second heating circulation water, so that the second heating circulation water is heated to the heating temperature.

3. The geothermal and biomass coupled energy supply system according to claim 1, characterized in that, The geothermal production and injection unit (1) includes a geothermal production well (11) and a reinjection well (12). The geothermal production well (11) is connected to the first heat exchanger (21), and the reinjection well (12) is connected to the second heat exchanger (22); The geothermal extraction and injection unit (1) is configured to extract geothermal water using the geothermal production well (11) and transport it to the first heat exchanger (21), and to reinject the geothermal water discharged from the second heat exchanger (22) after the second cooling through the reinjection well (12) back into the underground thermal reservoir.

4. The geothermal and biomass coupled energy supply system according to claim 3, characterized in that, The geothermal extraction and irrigation unit (1) also includes a cyclone separator (13) and a water-gas separator (14). The cyclone desander (13) and the water-gas separator (14) are connected in series between the geothermal production well (11) and the first heat exchanger (21); The cyclone desander (13) is configured to desand the geothermal water extracted from the geothermal production well (11); The water-gas separation device (14) is configured to perform gas-liquid separation on the geothermal water after sand removal in order to remove free gas from the geothermal water.

5. The geothermal and biomass coupled energy supply system according to claim 1, characterized in that, The biomass heat source unit (3) includes a biomass gasifier (31) and a biomass gas-fired steam boiler (32). The gas outlet of the biomass gasifier (31) is connected to the burner inlet of the biomass gas-fired steam boiler (32); the biomass gas-fired steam boiler (32) is also connected to the heat pump upgrading unit (4). The biomass gasifier (31) is configured to convert pretreated biomass raw materials into the combustible gas through anoxic gasification reaction; The biomass gas-fired steam boiler (32) is configured to burn the combustible gas to heat the condensate into saturated steam and deliver the saturated steam to the heat pump upgrading unit (4).

6. The geothermal and biomass coupled energy supply system according to claim 5, characterized in that, The biomass heat source unit (3) also includes a pretreatment device (33); The pretreatment device (33) is connected to the inlet of the biomass gasifier (31); The pretreatment device (33) is configured to crush, dry and screen the biomass raw material so that the processed biomass raw material meets the feeding requirements of the biomass gasifier (31).

7. The geothermal and biomass coupled energy supply system according to claim 1, characterized in that, The system also includes a relay pressurization station (5); The first heat exchanger (21) is connected to a heating pipeline, and the relay pressurization station (5) is located on the heating pipeline; The first heat exchanger (21) is configured to send the first heating circulating water heated to the heating temperature through the heating pipe; The relay pressurization station (5) is configured to pressurize the first heating circulating water in the heating pipeline to overcome the transmission resistance.

8. A method for supplying energy through geothermal and biomass coupling, characterized in that, The method is implemented by the energy supply system according to any one of claims 1-7, and the energy supply method includes: Geothermal water is extracted through the geothermal extraction and injection unit and transported to the first heat exchanger to exchange heat with the first heating circulation water. After the geothermal water completes the first cooling, it enters the second heat exchanger to exchange heat with the heat pump heat source water. After the geothermal water completes the second cooling, it is reinjected into the ground. The pretreated biomass raw materials are fed into a biomass heat source unit for oxygen-deficient oxidation to generate combustible gas, which is then burned to heat condensate and obtain saturated steam. The saturated steam and the heated heat pump source water are sent into the heat pump quality improvement unit. The saturated steam drives the heat pump, and the heated heat pump source water is used as a low-temperature heat source. The temperature of the second heating circulation water is raised to the heating temperature through the heat pump circulation. Then, the second heating circulation water and the first heating circulation water are combined as a heat source for output.

9. The energy supply method for geothermal and biomass coupling according to claim 8, characterized in that, The temperature of the geothermal water extracted by the geothermal extraction and irrigation unit is 60℃-70℃; The temperature of the geothermal water after the first cooling process is 40℃-50℃; The temperature of the geothermal water after the second cooling process is 20℃-30℃; The heating temperature is 85℃-95℃.

10. The energy supply method for geothermal and biomass coupling according to claim 8, characterized in that, The temperature of the heat source water in the heat pump after heating is 40℃-50℃; The temperature of the saturated steam is 160℃-180℃.