Method for installing an electric arc furnace suspended horizontal conveyor

By using segmented adjustment and phased tightening of connecting bolts, the problems of high construction costs and difficulty in ensuring accuracy during the installation of suspended horizontal conveyors for electric arc furnaces were solved. This resulted in an efficient and precise installation process, avoiding equipment malfunctions and reducing construction requirements.

CN123154644APending Publication Date: 2026-11-24CHINA NO 18 METALLURGICAL CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611582096.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-10-13
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

The existing installation method for suspended horizontal conveyors for electric arc furnaces requires a large assembly area and large lifting equipment, resulting in high construction costs and difficulty in ensuring the deviation of the horizontal and vertical center lines and the accuracy of the elevation of the whole machine, which leads to abnormal operation of the equipment.

Method used

The method of segmented adjustment and phased tightening of connecting bolts was adopted. The temporary support and the bottom surface of the truss were used as the elevation reference surface for adjustment. After the whole structure was lowered and suspended, the stress of the suspension rod bolts was adjusted. The equipment accuracy and balanced stress were ensured through a single grouting and cold-state load test run.

Benefits of technology

It eliminates the need for large offline assembly sites and large hoisting equipment, reducing construction costs, improving installation efficiency and accuracy, avoiding abnormal swaying and noise during equipment operation, and ensuring one-time acceptance of the entire machine.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123154644A_ABST
    Figure CN123154644A_ABST
Patent Text Reader

Abstract

This invention discloses an installation method for a suspended horizontal conveyor for an electric arc furnace. Temporary supports are installed under each truss section. The horizontal and vertical centerlines and elevations are adjusted using the bottom surface of the truss as a reference plane. After adjustment, the bottom surface of the truss is higher than the design elevation. The truss sections are connected as a whole. Rocker bases are installed and positioned and adjusted according to the bottom support beams of the truss. The rocker bases are grouted once. The anchor bolts are precisely adjusted and tightened. The hanger bolts and nuts are installed. The temporary supports are removed, allowing the entire conveyor to be lowered and suspended on the hanger bolts. The hanger bolts are re-measured and adjusted to ensure all hangers are under load. A cold-state load test run is conducted. After passing the test and all hangers are under load, a second grouting is performed. This method eliminates the need for a large assembly area and large hoisting equipment, controls cumulative deformation, ensures installation accuracy, ensures balanced load on the hangers, avoids equipment damage, and achieves one-time acceptance of the entire machine.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of metallurgical engineering installation technology, specifically to an installation method for a suspended horizontal conveyor for an electric arc furnace. Background Technology

[0002] The electric arc furnace suspended horizontal conveyor is a common piece of equipment used in the metallurgical steelmaking industry for the continuous conveying of scrap steel. This type of conveyor is usually composed of multiple truss sections and a conveying trough. The bottom of the truss is equipped with a supporting beam, which is suspended and supported by the hanger bolts on the rocker base. When the conveyor is running, it uses an eccentric vibration method to swing back and forth in the feeding direction to feed the material.

[0003] In existing installation methods, the common approach is to assemble and adjust the entire machine offline before hoisting it to the installation location. This involves assembling the truss sections and conveyor troughs into a single unit at the offline site, completing preliminary adjustments, and then using large lifting equipment to hoist the entire machine to the installation position. However, this method requires a large assembly area, and the overall hoisting requires large lifting equipment, resulting in high construction costs and stringent requirements for site conditions. Furthermore, after the truss sections are connected offline, cumulative deformation has already occurred, making on-site adjustments difficult and challenging to ensure the accuracy of the machine's transverse and longitudinal centerline deviations and elevation. Moreover, after the equipment is hoisted into place, uneven stress on the bolts of the lifting rods can lead to abnormal swaying and noise during operation, and may even cause equipment damage, if not adjusted in time. Summary of the Invention

[0004] In view of the shortcomings of the prior art, the technical problem to be solved by the present invention is: how to provide an installation method for an electric arc furnace suspended horizontal conveyor that does not require additional assembly space, reduces hoisting requirements, reduces installation costs, and improves installation efficiency and accuracy.

[0005] To solve the above-mentioned technical problems, the present invention adopts the following technical solution:

[0006] An installation method for a suspended horizontal conveyor for an electric arc furnace includes the following steps:

[0007] (1) Temporary supports are installed under each section of the truss of the conveyor to support each section of the truss at the installation position;

[0008] (2) Using the bottom surface of the truss as the elevation reference surface, the transverse centerline deviation, longitudinal centerline deviation and elevation of each truss section are adjusted. The elevation of the bottom surface of the truss after adjustment is higher than the design elevation.

[0009] (3) Connect the adjusted truss sections into a whole;

[0010] (4) Install the rocker base, put the rocker base in place and temporarily fix it, and adjust the position of the rocker base according to the support beam at the bottom of the truss connected as a whole;

[0011] (5) Grout the rocker base once. After the grout strength reaches the equipment installation requirements, fine-tune the rocker base and tighten the anchor bolts; install the hanger bolts on the rocker base so that the hanger bolts pass through the bolt holes of the support beam at the bottom of the truss, and install nuts on the hanger bolts.

[0012] (6) Remove the temporary supports to lower the entire conveyor and suspend it on the boom bolts of the rocker base;

[0013] (7) After the conveyor is lowered and suspended as a whole, re-measure and adjust the suspension bolts to ensure that all suspension bolts are under stress;

[0014] (8) Conduct a cold-load test run of the conveyor. After the cold-load test run is qualified and all the boom bolts are under force, perform secondary grouting of the rocker base.

[0015] This invention utilizes temporary supports under each truss section, using the bottom surface of the truss as a reference plane for segmented adjustment. After connecting the adjusted truss sections into a whole, the rocker base is positioned and adjusted. Following initial grouting, fine-tuning, and installation of the hanger bolts, the temporary supports are removed, allowing the conveyor to be lowered and suspended on the hanger bolts. The hanger bolts are then re-measured and adjusted to ensure all bolts are under load. A second grouting is performed after a successful cold-load test run and all hanger bolts are under load. This eliminates the need for large offline assembly areas and large hoisting equipment, enabling segmented adjustment and overall suspension under on-site conditions. It effectively controls the cumulative deformation of multi-segment splicing equipment, ensuring the overall machine's transverse and longitudinal centerline deviations and elevation accuracy. It also ensures balanced stress on all hanger bolts in the suspension system, preventing abnormal swaying, noise, and damage during equipment operation. This improves installation efficiency and accuracy, and allows for one-time acceptance of the entire machine.

[0016] As an optimization, in step (1), the temporary support includes support seats symmetrically arranged relative to the longitudinal centerline of the truss. The two symmetrically arranged support seats are connected by brackets, and the bottom of the support seats is fixed to the ground by expansion bolts. A set of shims is provided on the top of the support seats. This provides a stable, adjustable, and symmetrical support foundation for each truss segment, ensuring that the truss does not tilt or shift during segmental adjustment. The shims facilitate precise elevation adjustment and help reduce construction costs.

[0017] As an optimization, in step (2), before installation, the elevation of all the shim sets of each truss segment is adjusted to be 4-6mm lower than the elevation reference plane. This allows for adjustment margins to be reserved for truss hoisting and subsequent adjustments, preventing the truss from failing to be positioned during hoisting due to slight deformation during manufacturing and transportation, and facilitating the subsequent precise lifting of the truss to the design position by adding shims.

[0018] As an optimization, in step (2), the elevation of the lower bottom surface of the truss after adjustment is 1-2 mm higher than the design elevation. This compensates for the elevation drop caused by the truss's own deflection and the thread gap of the hanger bolts after the temporary support is removed, so that the elevation of the equipment drops to just near the design elevation after the overall descent and suspension, avoiding repeated adjustments due to insufficient or excessive pre-height.

[0019] As an optimization, in step (3), the truss sections are connected into a whole by connecting bolts. The connecting bolts are tightened in stages at 50%, 75%, and 100% of the design torque value. After each stage of tightening, the deviation of the transverse and longitudinal center lines and the elevation of the truss are re-measured. After tightening to 100% of the design torque value, the tightening is repeated at least once. The tightening sequence of the connecting bolts is from the first section of the conveyor near the electric arc furnace end to the last section near the feeding end. This effectively controls the cumulative deformation of the multi-segment splicing equipment, ensures the accuracy of the transverse and longitudinal center lines and elevation of the whole machine, and avoids stress concentration and accuracy deviation caused by one-time tightening or improper sequence.

[0020] As an optimization, in step (4), the rocker base is adjusted longitudinally with respect to the longitudinal centerline of the truss. The elevation is based on the top hanger bolt support surface of the rocker base. The lateral centerline deviation of the rocker base is measured by hanging a line to determine whether the bolt holes of the support beam at the bottom of the truss and the hanger bolt holes of the rocker base are concentric. This ensures the positioning accuracy of the rocker base, allowing the hanger bolts to be suspended vertically and pass through the bolt holes of the support beam, avoiding eccentric stress or inability to install the hanger bolts due to base misalignment.

[0021] As an optimization, in step (6), the temporary support is removed after the truss is lifted using jacks. This achieves a smooth transition from load-bearing by temporary supports to load-bearing by suspension bolts.

[0022] As an optimization, in step (7), if the suspension bolts are not under stress, after lifting the truss with a jack, adjust the system by estimating the nut feed amount, tightening the nut, and loosening the jack. This gradually balances the stress on each suspension bolt, ensuring the safety and reliability of the suspension system.

[0023] As an optimization, if the hanger bolts are still not under tension after multiple adjustments, they will not be adjusted temporarily. Instead, after the conveyor undergoes a cold-state load test run, the increased weight will cause deflection. Then, the tension on the hanger bolts will be adjusted by tightening the nuts and loosening the jacks according to the estimated nut feed amount. For situations where the hanger bolts are still not under tension after multiple adjustments, the approach is to temporarily refrain from adjustment until the conveyor undergoes a cold-state load test run, after which the increased weight will cause deflection. Adjustments will then be made precisely using the estimated nut feed amount to ultimately ensure that all hanger bolts are under tension.

[0024] As an optimization, in step (8), welding is performed between the various sections of the conveyor troughs after the conveyor is lowered and suspended as a whole and before the cold-state load test run. This reduces the impact of welding heat on the accuracy of the calibrated truss.

[0025] Compared with existing technologies, this invention has the following advantages: It eliminates the need for large-area offline assembly sites and large-scale hoisting equipment, reducing construction costs and site requirements; by segmented adjustment, phased tightening of connecting bolts, and adjustment of the load on the boom bolts after overall descent and suspension, it effectively controls the cumulative deformation of multi-segment splicing equipment, ensuring the overall machine's longitudinal and transverse centerline deviations and elevation accuracy, and ensuring balanced load on each boom bolt, avoiding abnormal swaying, noise, and damage during equipment operation; secondary grouting is performed after successful cold-state load testing and all boom bolts are under load, ensuring stable stress after grouting, allowing for one-time acceptance of the entire machine without rework, thus improving installation efficiency and accuracy. Attached Figure Description

[0026] Figure 1 This is a flowchart of the installation process of the present invention;

[0027] Figure 2 This is a cross-sectional schematic diagram of the conveyor in this invention. Detailed Implementation

[0028] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of the present invention. The components of the embodiments of the present invention described and shown in the accompanying drawings can generally be arranged and designed in various different configurations. Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely represents selected embodiments of the invention. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without inventive effort are within the scope of protection of the present invention.

[0029] like Figure 1 and Figure 2 As shown in the figure, the installation method of the electric arc furnace suspended horizontal conveyor in this specific embodiment includes a supporting beam 1 located at the bottom of the truss, a conveying trough 2 located at the upper part of the truss, and a hanger bolt installed on the rocker base 3. The hanger bolt passes through the bolt holes of the supporting beam 1 to suspend and support the conveyor. The installation method includes the following steps:

[0030] Step (1): Set up temporary support

[0031] Temporary supports are installed under each section of the conveyor truss to support the truss sections in their installation positions. The temporary supports include support bases symmetrically arranged with respect to the longitudinal centerline of the truss. Two symmetrically arranged support bases are connected by brackets. The bottom of the support base is fixed to the ground with expansion bolts, and a set of pads is installed on the top of the support base.

[0032] Specifically, each truss section is equipped with two pairs of support bases. The height of the support bases is lower than the design elevation of the truss, leaving gaps for the placement of shim sets. The support bases are arranged symmetrically in pairs, and the two support bases are connected by two equilateral angle steels. The bottom channel steel is fixed to the concrete surface with expansion bolts.

[0033] Step (2): Truss Adjustment

[0034] Using the bottom surface of the truss as the elevation reference plane, the lateral centerline deviation, longitudinal centerline deviation, and elevation of each truss section are adjusted. After adjustment, the elevation of the bottom surface of the truss is higher than the design elevation. Before installation, the elevation of all the shim sets of each truss section is adjusted to be 4-6mm lower than the elevation reference plane, preferably 5mm. The reason for this is that the truss is a process steel structure splicing device, and slight deformation may occur during manufacturing and transportation. Allowing for adjustment leeway facilitates subsequent lifting of the truss to the design position by adding or removing shims. The adjusted bottom surface elevation of the truss is 1-2mm higher than the design elevation. This is because the conveyor equipment is heavy. After removing the temporary supports, the entire weight of the equipment is suspended on the hanger bolts of the rocker base 3. Due to truss deflection and hanger bolt thread clearance, the equipment elevation will decrease. Pre-adjusting it 1-2mm ensures that the equipment elevation drops to near the design elevation after the supports are removed.

[0035] During calibration, the conveyor trough 2 is hoisted onto the support base, and the transverse and longitudinal center deviations and elevation deviations of each truss section are adjusted sequentially from the electric arc furnace end to the feeding end. The elevation is based on the bottom surface of the truss, not the working surface of the conveyor trough 2, because the conveyor trough 2 wears significantly after conveying scrap steel for a period of time and needs to be replaced periodically. The elevation of the trough will change after replacement, while the truss, as the skeleton of the conveyor, only requires maintenance.

[0036] During calibration, jacks are symmetrically arranged at the bottom of the truss. The load-bearing points of the jacks are not located on the conveyor body, but are supported separately on the concrete foundation surface to prevent damage to the conveyor body from the reaction force of the jacks. For lateral centerline deviation, the first section of the feeding section must meet the requirements, while a certain degree of deviation is allowed in the last section. Longitudinal centerline deviation is the key to controlling calibration accuracy. The longitudinal centerline pattern punched at the truss factory is used as the longitudinal calibration benchmark. Excessive longitudinal centerline deviation will cause excessive lateral swaying of the conveyor, resulting in either excessive noise or, in severe cases, irregular swaying and violent shaking of the entire machine, causing equipment damage or accelerating the wear of the rocker base 3 hanger bolts.

[0037] Step (3): Connect the trusses into a whole.

[0038] The adjusted truss sections are connected into a whole. The truss sections are connected into a whole by connecting bolts (high-strength bolts). The connecting bolts are tightened in stages at 50%, 75%, and 100% of the design torque value. After each stage of tightening, the deviation of the transverse and longitudinal center lines and the elevation of the truss are re-measured. After tightening to 100% of the design torque value, the tightening is repeated at least once. The tightening sequence of the connecting bolts is from the first section of the conveyor near the electric arc furnace end to the last section near the feeding end.

[0039] Specifically, tighten the bolts according to the torque and sequence required by the design. First, starting from the section closest to the electric arc furnace and ending at the section closest to the feeding end, tighten all connecting bolts of the conveyor truss to 50% torque. After verifying the deviation of the conveyor's transverse and longitudinal centerlines and elevation, tighten to 75%, repeating the measurement. Finally, tighten to 100% and measure again. The 100% torque value needs to be repeated at least once. After verifying the deviation of the transverse and longitudinal centerlines and elevation again, mark each connecting bolt, nut, and washer with a paint pen.

[0040] Step (4): Installation and positioning adjustment of the joystick base

[0041] Install the rocker base 3, positioning and temporarily fixing it in place. Position and adjust the rocker base 3 according to the supporting beam 1 at the bottom of the truss, which forms a whole. Adjust the longitudinal deviation of the rocker base 3 using the longitudinal centerline of the truss. Use the top hanger bolt support surface of the rocker base 3 as a reference plane. Measure the lateral centerline deviation of the rocker base 3 by hanging a line to check if the bolt holes of the supporting beam 1 at the bottom of the truss and the hanger bolt holes of the rocker base 3 are concentric. If there is a deviation, correct the rocker base 3.

[0042] Step (5): First grouting and installation of hanger bolts

[0043] Grouting is performed on the rocker base 3 once. After the grouting strength reaches the equipment installation requirements, the rocker base 3 is finely aligned and the anchor bolts are tightened. Hanger bolts are installed on the rocker base 3, so that the hanger bolts pass through the bolt holes of the support beam 1 at the bottom of the truss, and nuts are installed on the hanger bolts.

[0044] Specifically, after the initial grouting strength meets the equipment installation requirements, the rocker base 3 is precisely aligned, and the anchor bolts are tightened. The hanger bolts, matching washers, raised blocks, and nuts are then installed. The nuts are not tightened with a wrench; they are simply hand-tightened to ensure they are flush against the bottom of the supporting beam 1. All hanger bolts on the rocker base 3 must have a consistent exposed thread length and must be kept vertically suspended; secondary grouting is not performed at this stage.

[0045] Step (6): Overall lowering suspension

[0046] After the truss is lifted using jacks, the temporary supports are removed, allowing the conveyor to descend and suspend from the boom bolts of the rocker base 3. Specifically, ultra-thin jacks are installed on the channel steel surface next to the temporary support pads. The jacks are simultaneously lifted until the pads loosen slightly. Construction workers then use tools to knock off the pads. This process is repeated to remove the pads from all temporary supports. Then, the jacks on both sides are lowered simultaneously, at which point the conveyor descends and suspends from the boom bolts of the rocker base 3 on both sides.

[0047] Step (7): Adjusting the force on the hanger bolts

[0048] After the conveyor is lowered and suspended, re-measure and adjust the suspension bolts to ensure that all suspension bolts are under tension. If any of the suspension bolts are not under tension, use jacks to lift the truss, then adjust by estimating the nut feed amount, tightening the nuts, and loosening the jacks. Do not force the bolts to be tightened with a sledgehammer.

[0049] If the suspension bolts are still not under tension after multiple adjustments, do not adjust them for the time being. After the conveyor has been cold-run with load for trial operation, the increased weight will cause deflection. Then, adjust the tension of the suspension bolts by tightening the nuts and loosening the jacks according to the estimated nut feed amount.

[0050] Step (8): Cold-state load test run and secondary grouting

[0051] The conveyor was subjected to a cold-load test run. After the cold-load test run was successful and all the boom bolts were under stress, the rocker base 3 was grouted a second time.

[0052] After the conveyor is lowered and suspended as a whole, and before the cold-state load test run, welding is performed between the various conveying troughs 2 on the conveyor. At this time, the weight of the equipment is suspended from the rocker base 3 by the hanger bolts, and the truss is under actual stress. The amount of welding deformation can be reduced by utilizing the equipment's own weight. The cold-state load test run is a test run conducted without a heat source, after loading scrap steel onto the conveyor. The criteria for passing the cold-state load test run include smooth operation of the conveyor, no abnormal noise, no jamming, and the transverse and longitudinal centerline deviations and elevations meeting the requirements.

[0053] During or after the cold-state load test run, readjust the hanger bolts to ensure that all hanger bolts are under stress. Secondary grouting must be carried out after the cold-state load test run is qualified and all hanger bolts are under stress. After secondary grouting, the position of rocker base 3 and hanger bolts should not be adjusted again.

[0054] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit the technical solutions. Those skilled in the art should understand that any modifications or equivalent substitutions to the technical solutions of the present invention without departing from the spirit and scope of the present invention should be covered within the scope of the claims of the present invention.

Claims

1. A method of installing an electric arc furnace suspended horizontal conveyor, characterized in that: Includes the following steps: (1) Temporary supports are installed under each section of the truss of the conveyor to support each section of the truss at the installation position; (2) Using the bottom surface of the truss as the elevation reference surface, the transverse centerline deviation, longitudinal centerline deviation and elevation of each truss section are adjusted. The elevation of the bottom surface of the truss after adjustment is higher than the design elevation. (3) Connect the adjusted truss sections into a whole; (4) Install the rocker base, put the rocker base in place and temporarily fix it, and adjust the position of the rocker base according to the support beam at the bottom of the truss connected as a whole; (5) Grout the rocker base once. After the grout strength reaches the equipment installation requirements, fine-tune the rocker base and tighten the anchor bolts; install the hanger bolts on the rocker base so that the hanger bolts pass through the bolt holes of the support beam at the bottom of the truss, and install nuts on the hanger bolts. (6) Remove the temporary supports to lower the entire conveyor and suspend it on the boom bolts of the rocker base; (7) After the conveyor is lowered and suspended as a whole, re-measure and adjust the suspension bolts to ensure that all suspension bolts are under stress; (8) Conduct a cold-load test run of the conveyor. After the cold-load test run is qualified and all the boom bolts are under force, perform secondary grouting of the rocker base.

2. The method of installing an electric arc furnace suspended horizontal conveyor as claimed in claim 1, characterized in that: In step (1), the temporary support includes support seats arranged symmetrically with respect to the longitudinal centerline of the truss. The two symmetrically arranged support seats are connected by a bracket. The bottom of the support seats is fixed to the ground by expansion bolts, and the top of the support seats is provided with a set of pads.

3. The method of installing an electric arc furnace suspended horizontal conveyor as claimed in claim 2, characterized in that: In step (2), before installation, the elevation of all the shim groups of each truss section is adjusted to be 4-6 mm lower than the elevation reference plane.

4. The method of installing an electric arc furnace suspended horizontal conveyor as claimed in claim 1, characterized in that: In step (2), the elevation of the bottom surface of the truss after adjustment is 1-2 mm higher than the design elevation.

5. The method of installing an electric arc furnace suspended horizontal conveyor as defined in claim 1, characterized in that: In step (3), each section of the truss is connected into a whole by connecting bolts. The connecting bolts are tightened in stages according to 50%, 75%, and 100% of the design torque value. After each stage of tightening, the deviation of the transverse and longitudinal center lines and the elevation of the truss are re-measured. After tightening to 100% of the design torque value, the tightening is repeated at least once. The tightening sequence of the connecting bolts is from the first section of the conveyor near the electric arc furnace end to the last section near the feeding end.

6. The method of installing an electric arc furnace suspended horizontal conveyor as defined in claim 1, characterized in that: In step (4), the rocker base is adjusted for longitudinal deviation with respect to the longitudinal centerline of the truss. The elevation is based on the top hanger bolt support surface of the rocker base. The transverse centerline deviation of the rocker base is measured by hanging a line to determine whether the bolt holes of the support beam at the bottom of the truss and the hanger bolt holes of the rocker base are concentric.

7. The method of installing an electric arc furnace suspended horizontal conveyor as defined in claim 1, characterized in that: In step (6), the temporary support is removed after the truss is lifted using jacks.

8. The method of installing an electric arc furnace suspended horizontal conveyor as defined in claim 1, characterized in that: In step (7), if the lifting bolt is not under force, after the truss is lifted by jacking, the nut feed is estimated, the nut is tightened, and the jack is loosened to make adjustment.

9. The method of installing an electric arc furnace suspended horizontal conveyor as claimed in claim 8, characterized in that: If the suspension bolts are still not under tension after multiple adjustments, do not adjust them for the time being. After the conveyor has been cold-run with load for trial operation, the increased weight will cause deflection. Then, adjust the tension of the suspension bolts by tightening the nuts and loosening the jacks according to the estimated nut feed amount.

10. The method of installing an electric arc furnace suspended horizontal conveyor as defined in claim 1, characterized in that: In step (8), welding between each section of the conveying trough on the conveyor is carried out after the whole conveyor is hung down and before the cold-state belt load trial run.