A method for three-phase transient voltage measurement for cable termination to overhead line

By deploying electric field sensors at cable terminals to overhead lines, acquiring electric field signals, and constructing a voltage-electric field coupling matrix, the problem of real-time overvoltage monitoring without power interruption in cable terminal to overhead lines is solved. This achieves high-precision transient voltage measurement and monitoring, and is suitable for cable terminal to overhead lines under complex working conditions.

CN123155918APending Publication Date: 2026-11-24NORTH CHINA ELECTRIC POWER UNIV +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611322772.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-28
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing technologies lack the means to conduct real-time overvoltage monitoring without power interruption in the scenario of cable terminals transitioning to overhead lines. Traditional methods cannot be applied to scenarios with unknown line operating voltages, making it difficult to conduct online assessment and early warning of the insulation status of cable terminals, thus increasing the risk of cable accidents.

Method used

Electric field sensors are installed below the three-phase conductors under test and near the towers of the cable terminal to the overhead line to obtain electric field signals. The three-phase transient voltage values ​​are obtained by using the fixed coupling relationship of the fundamental frequency, third harmonic, and fifth harmonic phasors. A voltage-electric field coupling matrix is ​​constructed to realize the measurement of the three-phase transient voltage of the cable terminal to the overhead line.

Benefits of technology

It achieves high-precision transient voltage measurement of cable terminals to overhead lines under uninterrupted power supply conditions, overcomes the problem of electric field distortion caused by the metal structure of cable terminal towers, and gets rid of the installation limitations of traditional voltage transformers, making it suitable for transient voltage monitoring under complex working conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123155918A_ABST
    Figure CN123155918A_ABST
Patent Text Reader

Abstract

This application discloses a method for measuring three-phase transient voltage in cable terminal-to-overhead line transitions, relating to the field of overvoltage monitoring technology. The method includes: acquiring a first electric field measured by a first set of electric field sensors under energized operation of the three-phase conductors; extracting the fundamental, third, and fifth harmonic phasors of the first electric field; solving for the fundamental, third, and fifth harmonic voltage phasors of the three-phase conductors; acquiring a second electric field measured by a second set of electric field sensors under energized operation of the three-phase cable terminal-to-overhead line transitions; extracting the fundamental, third, and fifth harmonic phasors of the second electric field; calculating the voltage-electric field coupling matrix between the three-phase cable terminal-to-overhead line and the second set of electric field sensors; and determining the transient voltage value and waveform of the three-phase cable terminal-to-overhead line based on the voltage-electric field coupling matrix and several transient electric field values. This application enables effective monitoring of overvoltage in cable terminal-to-overhead line transitions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of overvoltage monitoring technology, and in particular to a method for measuring three-phase transient voltage in cable-terminated overhead lines. Background Technology

[0002] With the continuous and rapid development of my country's economy and society, the demand for electricity continues to grow. Power cables have been widely used in power distribution networks and high-voltage transmission systems due to their advantages such as convenient laying and small footprint. In particular, power cables have irreplaceable advantages in urban centers and in situations where it is difficult to lay overhead lines across rivers and seas.

[0003] In practical engineering, cable lines are often used in conjunction with overhead transmission lines, resulting in numerous cable-overhead transmission line hybrid lines. When lightning strikes an overhead line connecting a cable terminal to a low-impedance cable, it triggers a complex electromagnetic transient process. Lightning overvoltage traveling waves are reflected at the connection point between the overhead line and the low-impedance cable due to abrupt changes in wave impedance, potentially amplifying the overvoltage. Simultaneously, the extremely high-frequency components of the lightning current easily induce oscillations, prolonging the overvoltage duration. This transient process poses a dual threat to critical equipment: for surge arresters, they must not only withstand steep wave impacts but, more importantly, absorb the additional energy released from the cable's large capacitance to ground, risking damage due to energy exceeding limits; for cables, high-frequency oscillating overvoltages may exceed their insulation withstand levels, causing partial discharge or breakdown and damaging the metallic sheath system, thus threatening the safe and reliable operation of the system. Therefore, studying and accurately assessing this unique transient process is a crucial prerequisite for designing effective protection schemes and ensuring the stability of the transmission system.

[0004] However, currently, there is a lack of means to monitor overvoltage in real time without power interruption for the special scenario of cable terminals transitioning to overhead lines. Most existing overvoltage monitoring calculation methods for cable terminals transitioning to overhead lines are based on the assumption that the real-time operating voltage of the line is known, making them unsuitable for scenarios where the real-time operating voltage is unknown. Measurements would require power outages and the installation of voltage transformers. Furthermore, non-contact overvoltage monitoring methods, which are only applicable to transmission lines, do not consider the complex environment of cable terminals transitioning to overhead lines and are difficult to apply directly to this scenario. This lack of monitoring means makes it difficult to conduct online assessments and early warnings of the insulation status of cable terminals, increasing the risk of cable accidents and hindering safety management and maintenance decisions. Summary of the Invention

[0005] The purpose of this application is to provide a method for measuring the three-phase transient voltage of a cable terminal to an overhead line. This method can invert the three-phase transient voltage of the cable terminal to an overhead line through the transient electric field and construct the corresponding three-phase voltage waveform, thereby realizing effective monitoring of overvoltage in the cable terminal to overhead line.

[0006] To achieve the above objectives, this application provides the following solution: In a first aspect, this application provides a method for measuring three-phase transient voltage in cable-terminated overhead lines, comprising: The first electric field is obtained by the first set of electric field sensors when the three-phase conductor under test is energized. The first set of electric field sensors is arranged on the horizontal ground directly below the three-phase transmission line under test, at least 200m away from the tower. They are installed at the same height from the ground in the direction perpendicular to the conductor, arranged in a row, and the distance between adjacent sensors is equal. The number of electric field sensors is greater than or equal to 9.

[0007] Extract the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field.

[0008] Based on the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test are obtained by joint solution.

[0009] The second electric field is obtained by a second set of electric field sensors when the three-phase cable terminal to overhead line is energized. The second electric field includes transient electric field values ​​measured by several electric field sensors. When the second set of electric field sensors is arranged on the cable terminal support platform near the cable terminal to overhead line tower, the number of electric field sensors is greater than or equal to 3. When the second set of electric field sensors is arranged on a large open area near the cable terminal to overhead line tower, the number of electric field sensors is greater than or equal to 9. The three-phase conductor to be tested and the three-phase cable terminal to overhead line are the same circuit, and the voltage of each phase is equal at the same time.

[0010] Extract the fundamental, third, and fifth harmonic phasors of the second electric field.

[0011] Based on the fundamental, third, and fifth harmonic phasors of the second electric field, and in conjunction with the fundamental, third, and fifth harmonic voltage phasors of the three-phase conductor under test, the voltage-electric field coupling matrix between the three-phase cable terminal to overhead line and the second set of electric field sensors is calculated.

[0012] Based on the voltage-electric field coupling matrix and several transient electric field values, the transient voltage values ​​and transient voltage waveforms of the three-phase cable terminal to overhead line are determined.

[0013] Optionally, the expression for the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test is as follows: ; in, For the fundamental frequency, third harmonic, and fifth harmonic phasors, m=1,3,5; The fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test; , , For the conductor or cable terminal under test to the overhead line A, B, and C phases. m Second harmonic; M is the coupling matrix, and the expression of the coupling matrix is: ; in, M iA , M iB , M iC These are the first electric field sensors in the first group. i The coupling relationship between the electric field measured by the electric field sensor and the voltages of the three-phase conductors A, B, and C; x A , x B , x C The horizontal coordinates of the three-phase conductor under test; h A , h B , h C The vertical height of the three-phase conductor under test; x i , h i These are the first electric field sensors in the first group. i The horizontal coordinates and vertical height of an electric field sensor; r 0 represents the radius of the three-phase conductor to be tested.

[0014] Optionally, based on the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test are jointly solved to obtain the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, specifically including: Based on the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, a residual function is constructed.

[0015] Based on the residual function, the local minimum value is obtained by optimizing the objective function using the least squares method, and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test are obtained.

[0016] Optionally, the expression for the residual function is: ; in, It is the residual function; For the optimization of the coupling matrix; Optimization of phasors for fundamental, third, and fifth harmonic voltages of three-phase conductors under test; For the fundamental frequency, third harmonic, and fifth harmonic phasors, m =1,3,5.

[0017] The expression for the least squares optimization objective function is as follows: ; in, The objective function of the least squares method for finding local minima; X Let be the solution vector to be optimized, and the expression for the solution vector to be optimized is: ; in, U Am , U Bm , U Cm The three-phase voltages are A, B, and C. m The voltage amplitude of the second harmonic; , , The three-phase voltages are A, B, and C. m The voltage phase angle of the subharmonic; x A , x B , x C The horizontal coordinates of the three-phase conductor under test; h A , h B , h C The vertical height of the three-phase conductor to be measured.

[0018] Optionally, based on the fundamental, third, and fifth harmonic phasors of the second electric field, and in conjunction with the fundamental, third, and fifth harmonic voltage phasors of the three-phase conductor under test, the voltage-electric field coupling matrix between the three-phase cable terminal to overhead line and the second set of electric field sensors is calculated, specifically including: Based on the fundamental, third, and fifth harmonic phasors of the second electric field, and in conjunction with the fundamental, third, and fifth harmonic voltage phasors of the three-phase conductor under test, the second set of electric field sensors is divided into... N / 3 groups, to obtain each group k matrix, N This represents the number of electric field sensors in the second group.

[0019] Each of the groups k The matrices are concatenated to obtain the voltage-electric field coupling matrix.

[0020] Optionally, each group's k The expression for a matrix is: ; in, k xA , k xB , k xC For each group in the second group of electric field sensors x The coupling relationship between the electric field measured by the electric field sensor and the voltage of the overhead line at the terminals of the three-phase cables A, B, and C. x =1,2,3; For the second group of electric field sensors, each group of the first... x Individual electric field sensors m Second harmonic m =1,3,5; , , For the conductor or cable terminal under test to the overhead line A, B, and C phases. m Secondary harmonics.

[0021] Optionally, the formula for calculating the transient voltage value of the three-phase cable terminal to overhead line is as follows: ; in, U A ( t ), U B ( t ), U C ( t () represents the transient voltage values ​​of phases A, B, and C of the three-phase cable terminal to the overhead line; k nA , k nB , k nC For the second group of electric field sensors n The sensors measured the coupling relationship between the electric field and the voltage of the overhead line at the terminals of the three-phase cables A, B, and C. n =1,…, N , N This represents the number of the second group of electric field sensors; E n ( t ) is the second group of electric field sensors n The transient electric field value measured by an electric field sensor.

[0022] Secondly, this application provides a three-phase transient voltage measuring device for cable terminal to overhead line conversion, characterized in that the device is used to implement the aforementioned three-phase transient voltage measuring method for cable terminal to overhead line conversion, the device comprising: The first set of electric field sensors is used to acquire the first electric field measured by the first set of electric field sensors when the three-phase transmission line under test is energized. The first set of electric field sensors is arranged on the horizontal ground directly below the three-phase transmission line under test, at least 200m away from the tower. They are installed at the same height from the ground in the direction perpendicular to the conductor, arranged in a row, and the distance between adjacent sensors is equal. The number of electric field sensors is greater than or equal to 9.

[0023] The first extraction unit is used to extract the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field.

[0024] The first calculation unit is used to jointly solve for the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test based on the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test.

[0025] The second set of electric field sensors is used to acquire the second electric field measured by the second set of electric field sensors when the three-phase cable terminal to overhead line is energized. The second electric field includes transient electric field values ​​measured by several electric field sensors. When the second set of electric field sensors is arranged on the cable terminal support platform near the cable terminal to overhead line tower, the number of electric field sensors is greater than or equal to 3. When the second set of electric field sensors is arranged on a large open area near the cable terminal to overhead line tower, the number of electric field sensors is greater than or equal to 9. The three-phase conductor to be tested and the three-phase cable terminal to overhead line are the same circuit, and the voltage of each phase is equal at the same time.

[0026] The second extraction unit is used to extract the fundamental frequency, third harmonic, and fifth harmonic phasors of the second electric field.

[0027] The second calculation unit is used to calculate the voltage-electric field coupling matrix between the three-phase cable terminal to overhead line and the second set of electric field sensors based on the fundamental frequency, third harmonic, and fifth harmonic phasors of the second electric field, combined with the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test.

[0028] The determining unit is used to determine the transient voltage value and transient voltage waveform of the three-phase cable terminal to overhead line based on the voltage-electric field coupling matrix and several transient electric field values.

[0029] Thirdly, this application provides a computer device, including: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement the three-phase transient voltage measurement method for cable terminal to overhead line as described above.

[0030] Fourthly, this application provides a computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the three-phase transient voltage measurement method for cable terminal to overhead line described above.

[0031] According to the specific embodiments provided in this application, this application has the following technical effects: This application provides a method for measuring the three-phase transient voltage of a cable terminal to an overhead line. It acquires the first electric field measured by a first set of electric field sensors when the three-phase conductors are energized. The method extracts the fundamental, third, and fifth harmonic phasors of the first electric field. This solves the problem that the original time-domain signal of the first electric field is mixed with a large amount of noise, and that the power frequency and major harmonic components cannot be directly read. It achieves accurate separation of the fundamental, third, and fifth harmonic electric field phasors from the distortion-free first electric field, preparing frequency domain characteristic data for subsequent voltage calculation. Based on the fixed coupling relationship between the fundamental, third, and fifth harmonic phasors of the first electric field and the fundamental, third, and fifth harmonic voltage phasors of the three-phase conductors under test, the method jointly solves the problem to obtain the three-phase voltage measurement result. This method measures the fundamental, third, and fifth harmonic voltage phasors of conductors, solving the problem of lacking electric field-voltage conversion basis and difficulty in back-calculating the actual harmonic voltage phasors of the line under known electric field conditions in distortion-free measurement areas. It achieves high-precision calculation of the three-phase fundamental, third, and fifth harmonic voltage phasors by relying on the fixed geometric coupling relationship between the pure electric field signal and voltage, obtaining a reference harmonic voltage for the entire line as a true value. Furthermore, it acquires the second electric field measured by a second set of electric field sensors under the condition of a three-phase cable terminal transitioning to an overhead line under energized operation; extracts the fundamental, third, and fifth harmonic phasors of the second electric field. This method addresses the problem of complex time-domain signal components of transient electric fields obtained under distorted environments around towers, where harmonic components are affected by noise and distortion. To address the difficulty in extracting component masking data, this method accurately extracts the fundamental, third, and fifth harmonic electric field phasors from the distorted second electric field sampling data, providing frequency domain input for solving the coupling matrix. By combining the fundamental, third, and fifth harmonic phasors of the second electric field with the fundamental, third, and fifth harmonic voltage phasors of the three-phase conductor under test, the voltage-electric field coupling matrix between the three-phase cable terminal to overhead line and the second set of electric field sensors is calculated. This solves the problem that towers and cable terminal metal supports alter the spatial electric field distribution, leading to large deviations between the coupling matrix calculated theoretically based on geometric parameters and the actual coupling relationship on-site, making it unsuitable for direct voltage back-calculation at the terminal location. It also achieves the integration of the reference harmonic voltage phasor already solved at the remote end. The voltage-electric field coupling matrix is ​​calculated using the quantity and second electric field harmonic phasor to obtain a true and effective voltage-electric field coupling matrix suitable for the cable terminal distortion environment, and the coupling parameters in the distortion region are calibrated on-site. Based on the voltage-electric field coupling matrix and several transient electric field values, the transient voltage values ​​and transient voltage waveforms of the three-phase cable terminal to overhead line are determined. This solves the problems of high construction difficulty and cost of traditional contact-type transient voltage transformers installed on-site in the cable-to-overhead transition section, and the inability to directly apply the ideal coupling formula to back-calculate the transient voltage under distorted electric field conditions. It realizes the accurate reconstruction of the three-phase transient voltage values ​​and complete transient voltage waveforms of the cable terminal to overhead line using the on-site calibrated coupling matrix and the transient electric field values ​​collected by the sensor.This application adopts the overall approach of first calibrating the line reference harmonic voltage at a remote distortion-free site, then calibrating the coupling matrix of the distortion area near the tower, and finally inverting the transient voltage. This overcomes the problem of electric field distortion caused by the metal structure of the cable terminal tower, and gets rid of the installation limitations of traditional voltage transformers. It can complete the measurement of the three-phase transient voltage waveform at the cable-to-overhead transition position using only non-contact electric field sensors. It takes into account both steady-state harmonic calibration and transient fault voltage restoration. The overall measurement accuracy is high and the deployment is flexible, making it suitable for transient voltage monitoring under complex working conditions of cable terminal to overhead line transition. Attached Figure Description

[0032] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0033] Figure 1 A flowchart illustrating a method for measuring three-phase transient voltage in a cable terminal to overhead line according to an embodiment of this application; Figure 2 This is a schematic diagram of the installation position of the conductor under test and the first set of electric field sensors provided in an embodiment of this application; Figure 3 A schematic diagram of the installation positions of the cable terminal under test and the second set of electric field sensors when N=3, provided in an embodiment of this application; Figure 4 This application provides a schematic diagram of the installation position of the cable terminal to overhead line and the second set of electric field sensors when N=9, according to one embodiment. Figure 5 A functional module schematic diagram of a three-phase transient voltage measuring device for cable terminal to overhead line provided in an embodiment of this application; Figure 6 This is a schematic diagram of the structure of a computer device provided in an embodiment of this application. Detailed Implementation

[0034] The technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.

[0035] This application addresses the shortcomings of the prior art by proposing a method for measuring the three-phase transient voltage of cable terminal-to-overhead lines. It provides a method for obtaining the voltage-electric field decoupling matrix without power interruption when the operating voltage of the cable terminal-to-overhead line is unknown. Furthermore, it improves upon the traditional time-domain single-point solution method by constructing equations in the frequency domain to obtain a more accurate operating voltage of the cable terminal-to-overhead line and calculates its coupling relationship with the monitoring electric field sensor. This enables the inversion of the three-phase transient voltage of the cable terminal-to-overhead line through the transient electric field and the construction of the corresponding three-phase voltage waveform, thus achieving effective monitoring of overvoltage in the cable terminal-to-overhead line.

[0036] Specifically, the steps include: 1) Installing a first set of no less than nine electric field sensors on a horizontal ground directly below the conductors of the three-phase transmission line under test and away from equipment such as towers. Based on the electric field phasors measured by the first set of electric field sensors, the voltage phasors of the three-phase conductors under test are jointly solved to obtain the voltage phasors of the three-phase conductors under test; 2) Installing a second set of electric field sensors near the towers of the overhead line at the cable terminal. Based on the electric field phasors measured by the second set of sensors and the voltage phasors of the three-phase conductors under test already obtained, calculating the coupling matrix between the three-phase mixed line under test and the second set of electric field sensors; 3) Calculating the transient voltage value of the three-phase mixed line under test based on the coupling matrix and the real-time electric field value measured by the second set of electric field sensors, realizing the transient voltage measurement of the three-phase mixed line under test, and constructing the transient voltage waveform.

[0037] To make the above-mentioned objectives, features and advantages of this application more apparent and understandable, the application will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0038] Example 1: In one exemplary embodiment, such as Figure 1 As shown, a method for measuring the three-phase transient voltage of a cable terminal to an overhead line is provided. The method includes the following steps: S1: Obtain the first electric field measured by the first group of electric field sensors when the three-phase conductor under test is energized; the first group of electric field sensors is arranged on the horizontal ground directly below the three-phase transmission line under test, at least 200m away from the tower, installed at the same height from the ground in the direction perpendicular to the conductor, arranged in a row, and the distance between adjacent sensors is equal, and the number of electric field sensors is greater than or equal to 9.

[0039] S2: Extract the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field.

[0040] S3: Based on the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test are obtained by joint solution.

[0041] S4: Obtain the second electric field measured by the second set of electric field sensors when the three-phase cable terminal to overhead line is energized; the second electric field includes transient electric field values ​​measured by several electric field sensors; when the second set of electric field sensors is arranged on the cable terminal support platform near the cable terminal to overhead line tower, the number of electric field sensors is greater than or equal to 3; when the second set of electric field sensors is arranged on a large open area near the cable terminal to overhead line tower, the number of electric field sensors is greater than or equal to 9; the three-phase conductor to be tested and the three-phase cable terminal to overhead line are the same circuit, and the voltage of each phase is equal at the same time.

[0042] S5: Extract the fundamental frequency, third harmonic, and fifth harmonic phasors of the second electric field.

[0043] S6: Based on the fundamental frequency, third harmonic, and fifth harmonic phasors of the second electric field, and in conjunction with the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, calculate the voltage-electric field coupling matrix between the three-phase cable terminal to overhead line and the second set of electric field sensors.

[0044] S7: Based on the voltage-electric field coupling matrix and several transient electric field values, determine the transient voltage value and transient voltage waveform of the three-phase cable terminal to overhead line.

[0045] By implementing steps S1 to S7 above, this application addresses the problems of complex electrical environment, unknown real-time operating voltage of the line, and lack of transient voltage measurement and overvoltage monitoring methods that do not require power outages in the scenario of cable terminal to overhead line. It provides an effective way to achieve three-phase voltage measurement without power outage and calculate the line voltage-electric field coupling matrix, and realizes long-term transient voltage measurement and overvoltage monitoring of cable terminal to overhead line based on the voltage-electric field coupling matrix.

[0046] As an optional implementation, all electric field sensors measure in a direction perpendicular to the ground.

[0047] As an optional implementation, the fundamental, third, and fifth harmonic phasors of the first electric field With the fundamental, third, and fifth harmonic voltage phasors of the three-phase conductor under test There is a fixed coupling relationship between them: ; in, For the fundamental frequency, third harmonic, and fifth harmonic phasors, m =1,3,5; The fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test; , , For the conductor or cable terminal under test to the overhead line A, B, and C phases. m Second harmonic; in this coupling relationship , , For the conductor under test, phases A, B, and C m Second harmonic; M is the coupling matrix, and the expression of the coupling matrix is: ; in, M iA , M iB , M iC These are the first electric field sensors in the first group. i The coupling relationship between the electric field measured by the electric field sensor and the voltages of the three-phase conductors A, B, and C; x A , x B , x C The horizontal coordinates of the three-phase conductor under test; h A , h B , h C The vertical height of the three-phase conductor under test; x i , h i These are the first electric field sensors in the first group. i The horizontal coordinates and vertical height of an electric field sensor; r 0 represents the radius of the three-phase conductor to be tested.

[0048] As an optional implementation, in step S3, based on the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test are jointly solved to obtain the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, specifically including: S31: Based on the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, a residual function is constructed; the expression of the residual function is: ; in, It is the residual function; For the optimization of the coupling matrix; Optimization of phasors for fundamental, third, and fifth harmonic voltages of three-phase conductors under test; For the fundamental frequency, third harmonic, and fifth harmonic phasors, m=1,3,5.

[0049] S32: Based on the residual function, the local minimum value is solved by optimizing the objective function using the least squares method to obtain the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test; the expression of the least squares optimization objective function is: ; in, The objective function of the least squares method for finding local minima; X Let be the solution vector to be optimized, and the expression for the solution vector to be optimized is: ; in, U Am , U Bm , U Cm The three-phase voltages are A, B, and C. m The voltage amplitude of the second harmonic; , , The three-phase voltages are A, B, and C. m The voltage phase angle of the subharmonic; x A , x B , x C The horizontal coordinates of the three-phase conductor under test; h A , h B , h C The vertical height of the three-phase conductor to be measured.

[0050] As an optional implementation, the fundamental, third, and fifth harmonic phasors of the second electric field The three-phase cable under test terminal to overhead line fundamental frequency, third harmonic, and fifth harmonic voltage phasors , , There is a fixed coupling relationship between them: ; Where K is the voltage-electric field coupling matrix, which is N A ×3 matrix N This represents the number of electric field sensors in the second group.

[0051] It should be noted that since the three-phase conductor under test and the three-phase cable terminal to overhead line under test are on the same circuit, the voltage of each phase is equal at the same time. Therefore, the voltages of phases A, B, and C of the conductor under test or the cable terminal to overhead line under test are equal. m Subharmonics are used , , express.

[0052] The voltage-electric field coupling matrix K is calculated by dividing the second group of electric field sensors into... N / 3 groups, for each group: ; In the formula, For each group of the second group of sensors x ( x =1,2,3) sensors m Subharmonics ( m =1,3,5), here , , For the cable terminal under test, the A, B, and C phases of the overhead line are connected. m Second harmonics; k xA , k xB , k xC For each group in the second group of electric field sensors x The coupling relationship between the electric field measured by the electric field sensor and the voltage of the overhead line at the terminals of the three-phase cables A, B, and C.

[0053] Each group k The matrices are concatenated together to obtain N A K matrix of size ×3.

[0054] As an optional implementation, the formula for calculating the transient voltage value of the three-phase cable terminal to overhead line is: ; in, U A ( t ), U B ( t ), U C ( t () represents the transient voltage values ​​of phases A, B, and C of the three-phase cable terminal to the overhead line; k nA , k nB , k nC For the second group of electric field sensors n The sensors measured the coupling relationship between the electric field and the voltage of the overhead line at the terminals of the three-phase cables A, B, and C. n =1,…, N, N This represents the number of the second group of electric field sensors; E n ( t ) is the second group of electric field sensors n The transient electric field value measured by an electric field sensor.

[0055] It should be noted that the first set of electric field sensors is only used for calibration, and can be removed after obtaining the specific value of the voltage-electric field coupling matrix K.

[0056] Example 2: A method for measuring three-phase transient voltage in cable-terminated overhead lines includes the following steps: 1) In a single-circuit transmission scenario of a 220kV cable terminal to overhead line, on the horizontal ground 200m away from the tower, directly below the conductors of the three-phase transmission line under test, a first group of nine electric field sensors (e.g., each 0.1m above the ground, arranged in a row with a 2m spacing between adjacent sensors) are installed perpendicular to the conductors. Figure 2 As shown), when the three-phase conductors under test are energized, based on the electric field V measured by the first set of sensors, the fundamental frequency, third harmonic, and fifth harmonic phasors are extracted. (m=1,3,5), the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test are obtained by joint solution. , , ; Specifically, the electric field fundamental frequency, third harmonic, and fifth harmonic phasors measured by the first set of electric field sensors The fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test , , There is a fixed coupling relationship between them: ; Where M is the coupling matrix, and the expression for the coupling matrix is: ; in, M iA , M iB , M iC These are the first electric field sensors in the first group. i The coupling relationship between the electric field measured by the electric field sensor and the voltages of the three-phase conductors A, B, and C; x A , x B , x CLet be the horizontal coordinates of the three-phase conductor under test, and be the unknowns; h A , h B , h C The vertical height of the three-phase conductor under test is an unknown. x i , h i These are the first electric field sensors in the first group. i The horizontal coordinates and vertical height of each electric field sensor are known values; r 0 represents the radius of the three-phase conductor to be tested, which is a known value.

[0057] This method solves for the fundamental, third, and fifth harmonic voltage phasors of a three-phase conductor by constructing a residual function and optimizing the objective function using the least squares method to achieve a local minimum within a given solution range. , , The constructed residual function expression is as follows: ; in, It is the residual function; For the optimization of the coupling matrix; Optimize the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test.

[0058] The expression for the least squares optimization objective function is as follows: ; in, The objective function for finding local minima using the least squares method; X is the solution vector to be optimized, and the expression for the solution vector to be optimized is: ; in, U Am , U Bm , U Cm The three-phase voltages are A, B, and C. m The voltage amplitude of the second harmonic; , , The three-phase voltages are A, B, and C. m Phase angle of the subharmonic voltage.

[0059] When the objective function reaches a local minimum within the constraints, the solution vector X contains... U Am , U Bm , UCm and , , That is, the fundamental frequency, third harmonic, and fifth harmonic voltage phasors to be solved. , , .

[0060] 2) Near the cable terminal to overhead line tower, install a second set of N electric field sensors at predetermined locations. With the three-phase cable terminal to overhead line under test energized, measure the electric field using the second set of electric field sensors. E Extract its fundamental frequency, third harmonic, and fifth harmonic phasors. The fundamental, third, and fifth harmonic voltage phasors of the three-phase conductor voltages obtained at the same time using the method in step 1) are combined. , , Calculate the voltage-electric field coupling matrix K between the three-phase cable terminal to overhead line and the second set of sensors to obtain the specific value of the coupling matrix K; Specifically, the second group total N According to the expected installation plan for the installation site, the electric field sensor is scheduled to be installed on the cable terminal support platform near the cable terminal tower of the overhead line. N =3 (e.g.) Figure 3 (As shown), when the intended installation location is a large open area nearby. N =9 (e.g.) Figure 4 (As shown). N Let's take 9 as an example and proceed with the next calculation.

[0061] The second set of electric field sensors measured the fundamental frequency, third harmonic, and fifth harmonic phasors of the electric field. The three-phase cable under test terminal to overhead line fundamental frequency, third harmonic, and fifth harmonic voltage phasors , , There is a fixed coupling relationship between them: ; Where K is the voltage-electric field coupling matrix, which is a 9×3 matrix.

[0062] Divide the second group of sensors into 3 groups to solve for the voltage-electric field coupling matrix K. For each group, we have: ; in, For each group of the second group of sensors x (x=1,2,3) sensors m Second harmonics (m=1,3,5). , , For the cable terminal under test, the A, B, and C phases of the overhead line are connected. m Secondary harmonics.

[0063] By concatenating the k matrices of each group, we obtain a 9×3 voltage-electric field coupling matrix K, which has the following form: ; Where, in the formula, k nA , k nB , k nC The second group of electric field sensors are respectively n The sensors measured the coupling relationship between the electric field and the voltage of the overhead line at the terminals of the three-phase cables A, B, and C.

[0064] 3) Based on the voltage-electric field coupling matrix K The transient electric field value measured by the second set of sensors E ( t ), calculate the transient voltage value of the three-phase cable terminal to overhead line. U ( t This enables the measurement of transient voltage at the three-phase cable terminal to the overhead line, and the construction of transient voltage waveforms.

[0065] Specifically, the transient voltage value of the three-phase cable terminal to overhead line. U ( t The calculation method is as follows: ; In the formula, E n ( t ) is the second group of electric field sensors n The transient electric field value measured by an electric field sensor; U A ( t ), U B ( t ), U C ( t () represents the transient voltage values ​​of phases A, B, and C of the three-phase cable terminal to overhead line.

[0066] Furthermore, all the first and second groups of electric field sensors are one-dimensional spherical electric field sensors, and their measurement direction is perpendicular to the ground.

[0067] Furthermore, the three-phase conductor under test and the three-phase cable under test terminal overhead line are the same circuit, and the voltage of each phase is equal at the same time.

[0068] Furthermore, the first set of electric field sensors is only used for calibration and can be removed after step 2).

[0069] Example 3: Based on the same inventive concept, this application also provides a three-phase transient voltage measuring device for cable terminal to overhead line conversion, which implements the above-described method for measuring three-phase transient voltage of cable terminal to overhead line conversion. The solution provided by this device is similar to the solution described in the above method. Therefore, the specific limitations of one or more embodiments of the three-phase transient voltage measuring device for cable terminal to overhead line conversion provided below can be found in the limitations of the three-phase transient voltage measuring method for cable terminal to overhead line conversion described above, and will not be repeated here.

[0070] In one exemplary embodiment, such as Figure 5 As shown, a three-phase transient voltage measuring device for cable termination to overhead line is provided, the device comprising: The first set of electric field sensors is used to acquire the first electric field measured by the first set of electric field sensors when the three-phase transmission line under test is energized. The first set of electric field sensors is arranged on the horizontal ground directly below the three-phase transmission line under test, at least 200m away from the tower. They are installed at the same height from the ground in the direction perpendicular to the conductor, arranged in a row, and the distance between adjacent sensors is equal. The number of electric field sensors is greater than or equal to 9.

[0071] The first extraction unit is used to extract the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field.

[0072] The first calculation unit is used to jointly solve for the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test based on the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test.

[0073] The second set of electric field sensors is used to acquire the second electric field measured by the second set of electric field sensors when the three-phase cable terminal to overhead line is energized. The second electric field includes transient electric field values ​​measured by several electric field sensors. When the second set of electric field sensors is arranged on the cable terminal support platform near the cable terminal to overhead line tower, the number of electric field sensors is greater than or equal to 3. When the second set of electric field sensors is arranged on a large open area near the cable terminal to overhead line tower, the number of electric field sensors is greater than or equal to 9. The three-phase conductor to be tested and the three-phase cable terminal to overhead line are the same circuit, and the voltage of each phase is equal at the same time.

[0074] The second extraction unit is used to extract the fundamental frequency, third harmonic, and fifth harmonic phasors of the second electric field.

[0075] The second calculation unit is used to calculate the voltage-electric field coupling matrix between the three-phase cable terminal to overhead line and the second set of electric field sensors based on the fundamental frequency, third harmonic, and fifth harmonic phasors of the second electric field, combined with the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test.

[0076] The determining unit is used to determine the transient voltage value and transient voltage waveform of the three-phase cable terminal to overhead line based on the voltage-electric field coupling matrix and several transient electric field values.

[0077] Example 4: In one exemplary embodiment, a computer device is provided, which may be a server or a terminal, and its internal structure diagram may be as follows. Figure 6 As shown, this computer device includes a processor, memory, input / output (I / O) interfaces, and a communication interface. The processor, memory, and I / O interfaces are connected via a system bus, and the communication interface is also connected to the system bus via the I / O interfaces. The processor provides computational and control capabilities. The memory includes non-volatile storage media and internal memory. The non-volatile storage media stores the operating system, computer programs, and a database. The internal memory provides the environment for the operation of the operating system and computer programs stored in the non-volatile storage media. The database stores electric fields measured by electric field sensors. The I / O interfaces are used for information exchange between the processor and external devices. The communication interface is used for communication with external terminals via a network connection. When executed by the processor, the computer program implements a method for measuring three-phase transient voltages in overhead lines connected to cable terminals.

[0078] Figure 6 The structures shown are merely block diagrams of some structures related to the present application and do not constitute a limitation on the computer device to which the present application is applied. Specific computer devices may include more or fewer components than shown in the figures, or combine certain components, or have different component arrangements. In an exemplary embodiment, a computer device is provided, including a memory and a processor. The memory stores a computer program, and the processor executes the computer program to implement the steps in the above-described method embodiments.

[0079] Example 5: In one exemplary embodiment, a computer-readable storage medium is provided storing a computer program that, when executed by a processor, implements the steps in the above-described method embodiments.

[0080] It should be noted that the user information (including but not limited to user device information, user personal information, etc.) and data (including but not limited to data used for analysis, data stored, data displayed, etc.) involved in this application are all information and data authorized by the user or fully authorized by all parties, and the collection, use and processing of related data must comply with relevant regulations and be authorized by the owner of the corresponding device.

[0081] Those skilled in the art will understand that all or part of the processes in the above embodiments can be implemented by a computer program instructing related hardware. The computer program can be stored in a non-volatile computer-readable storage medium. When executed, the computer program can include the processes of the embodiments described above. Any references to memory, databases, or other media used in the embodiments provided in this application can include at least one of non-volatile and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetic random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. By way of illustration and not limitation, RAM can take many forms, such as Static Random Access Memory (SRAM) or Dynamic Random Access Memory (DRAM).

[0082] The databases involved in the embodiments provided in this application may include at least one type of relational database and non-relational database. Non-relational databases may include, but are not limited to, blockchain-based distributed databases. The processors involved in the embodiments provided in this application may be general-purpose processors, central processing units, graphics processing units, digital signal processors, programmable logic devices, quantum computing-based data processing logic devices, etc., and are not limited to these.

[0083] The technical features of the above embodiments can be combined in any way. For the sake of brevity, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0084] This document uses specific examples to illustrate the principles and implementation methods of this application. The descriptions of the above embodiments are only for the purpose of helping to understand the methods and core ideas of this application. Furthermore, those skilled in the art will recognize that, based on the ideas of this application, there will be changes in the specific implementation methods and application scope. Therefore, the content of this specification should not be construed as a limitation of this application.

Claims

1. A method for measuring the three-phase transient voltage of a cable terminal to an overhead line, characterized in that, include: Acquire the first electric field measured by the first set of electric field sensors when the three-phase conductor under test is energized; The first group of electric field sensors is arranged on the horizontal ground directly below the three-phase transmission line under test, at least 200m away from the tower. They are installed at the same height from the ground in the direction perpendicular to the conductor, arranged in a row, and the distance between adjacent sensors is equal. The number of electric field sensors is greater than or equal to 9. Extract the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field; Based on the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test are obtained by joint solution. The second electric field is obtained by the second set of electric field sensors when the three-phase cable under test is switched to an overhead line under energized operation; the second electric field includes transient electric field values ​​measured by several electric field sensors; When the second set of electric field sensors is arranged on the cable terminal support platform near the cable terminal to overhead line tower, the number of electric field sensors is greater than or equal to 3. When the second set of electric field sensors is arranged on a large open area near the cable terminal to overhead line tower, the number of electric field sensors is greater than or equal to 9. The three-phase conductor under test and the three-phase cable under test terminal to overhead line are the same circuit, and the voltage of each phase is equal at the same time; Extract the fundamental, third, and fifth harmonic phasors of the second electric field; Based on the fundamental frequency, third harmonic, and fifth harmonic phasors of the second electric field, and in conjunction with the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, the voltage-electric field coupling matrix between the three-phase cable terminal to overhead line and the second set of electric field sensors is calculated. Based on the voltage-electric field coupling matrix and several transient electric field values, the transient voltage values ​​and transient voltage waveforms of the three-phase cable terminal to overhead line are determined.

2. The method for measuring the three-phase transient voltage of a cable terminal to an overhead line according to claim 1, characterized in that, The expression for the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test is as follows: ; in, For the fundamental frequency, third harmonic, and fifth harmonic phasors, m =1,3,5; The fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test; , , For the conductor or cable terminal under test to the overhead line A, B, and C phases. m Second harmonic; M is the coupling matrix, and the expression of the coupling matrix is: ; in, M iA , M iB , M iC These are the first electric field sensors in the first group. i The coupling relationship between the electric field measured by the electric field sensor and the voltages of the three-phase conductors A, B, and C; x A , x B , x C The horizontal coordinates of the three-phase conductor under test; h A , h B , h C The vertical height of the three-phase conductor under test; x i , h i These are the first electric field sensors in the first group. i The horizontal coordinates and vertical height of an electric field sensor; r 0 represents the radius of the three-phase conductor to be tested.

3. The method for measuring the three-phase transient voltage of a cable terminal to an overhead line according to claim 1, characterized in that, Based on the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, a joint solution is performed to obtain the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, specifically including: Based on the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test, a residual function is constructed. Based on the residual function, the local minimum value is obtained by optimizing the objective function using the least squares method, and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test are obtained.

4. The three-phase transient voltage measurement method for cable terminal to overhead line according to claim 3, characterized in that, The expression for the residual function is: ; in, It is the residual function; For the optimization of the coupling matrix; Optimization of phasors for fundamental, third, and fifth harmonic voltages of three-phase conductors under test; For the fundamental frequency, third harmonic, and fifth harmonic phasors, m =1,3,5; The expression for the least squares optimization objective function is as follows: ; in, The objective function for finding local minima using the least squares method; X is the solution vector to be optimized, and the expression for the solution vector to be optimized is: ; in, U Am , U Bm , U Cm The three-phase voltages are A, B, and C. m The voltage amplitude of the second harmonic; , , The three-phase voltages are A, B, and C. m The voltage phase angle of the subharmonic; x A , x B , x C The horizontal coordinates of the three-phase conductor under test; h A , h B , h C The vertical height of the three-phase conductor to be measured.

5. The method for measuring the three-phase transient voltage of a cable terminal to an overhead line according to claim 1, characterized in that, Based on the fundamental, third, and fifth harmonic phasors of the second electric field, and in conjunction with the fundamental, third, and fifth harmonic voltage phasors of the three-phase conductor under test, the voltage-electric field coupling matrix between the three-phase cable terminal to overhead line and the second set of electric field sensors is calculated, specifically including: Based on the fundamental, third, and fifth harmonic phasors of the second electric field, and in conjunction with the fundamental, third, and fifth harmonic voltage phasors of the three-phase conductor under test, the second set of electric field sensors is divided into... N / 3 groups, to obtain each group k matrix, N This represents the number of the second group of electric field sensors; Each of the groups k The matrices are concatenated to obtain the voltage-electric field coupling matrix.

6. The method for measuring three-phase transient voltage of cable terminal to overhead line according to claim 5, characterized in that, Each group k The expression for a matrix is: ; in, k xA , k xB , k xC For each group in the second group of electric field sensors x The coupling relationship between the electric field measured by the electric field sensor and the voltage of the overhead line at the terminals of the three-phase cables A, B, and C. x =1,2,3; For the second group of electric field sensors, each group of the first... x Individual electric field sensors m Second harmonic m =1,3,5; , , For the conductor or cable terminal under test to the overhead line A, B, and C phases. m Secondary harmonics.

7. The method for measuring three-phase transient voltage of cable terminal to overhead line according to claim 1, characterized in that, The formula for calculating the transient voltage value of the three-phase cable terminal to overhead line is as follows: ; in, U A ( t ), U B ( t ), U C ( t () represents the transient voltage values ​​of phases A, B, and C of the three-phase cable terminal to the overhead line; k nA , k nB , k nC For the second group of electric field sensors n The sensors measured the coupling relationship between the electric field and the voltage of the overhead line at the terminals of the three-phase cables A, B, and C. n =1,…, N , N This represents the number of the second group of electric field sensors; E n ( t ) is the second group of electric field sensors n The transient electric field value measured by an electric field sensor.

8. A three-phase transient voltage measuring device for cable termination to overhead line, characterized in that, The device is used to implement the three-phase transient voltage measurement method for cable terminal to overhead line as described in any one of claims 1-7, and the device comprises: The first set of electric field sensors is used to acquire the first electric field measured by the first set of electric field sensors when the three-phase transmission line under test is energized. The first set of electric field sensors is arranged on the horizontal ground directly below the three-phase transmission line under test, at least 200m away from the tower. They are installed at the same height from the ground in the direction perpendicular to the conductor, arranged in a row, and the distance between adjacent sensors is equal. The number of electric field sensors is greater than or equal to 9. The first extraction unit is used to extract the fundamental frequency, third harmonic, and fifth harmonic phasors of the first electric field; The first calculation unit is used to jointly solve for the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test based on the fixed coupling relationship between the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the first electric field and the fundamental frequency, third harmonic, and fifth harmonic voltage phasors of the three-phase conductor under test; The second set of electric field sensors is used to acquire the second electric field measured by the second set of electric field sensors when the three-phase cable terminal to overhead line is energized. The second electric field includes transient electric field values ​​measured by several electric field sensors. When the second set of electric field sensors is arranged on the cable terminal support platform near the cable terminal to overhead line tower, the number of electric field sensors is greater than or equal to 3. When the second set of electric field sensors is arranged on a large open area near the cable terminal to overhead line tower, the number of electric field sensors is greater than or equal to 9. The three-phase conductor to be tested and the three-phase cable terminal to overhead line are the same circuit, and the voltage of each phase is equal at the same time. The second extraction unit is used to extract the fundamental frequency, third harmonic, and fifth harmonic phasors of the second electric field; The second calculation unit is used to calculate the voltage-electric field coupling matrix between the three-phase cable terminal to overhead line and the second set of electric field sensors based on the fundamental frequency, third harmonic and fifth harmonic phasors of the second electric field, combined with the fundamental frequency, third harmonic and fifth harmonic voltage phasors of the three-phase conductor under test; The determining unit is used to determine the transient voltage value and transient voltage waveform of the three-phase cable terminal to overhead line based on the voltage-electric field coupling matrix and several transient electric field values.

9. A computer device, comprising: A memory, a processor, and a computer program stored in the memory and capable of running on the processor, characterized in that the processor executes the computer program to implement the three-phase transient voltage measurement method for cable terminal overhead lines as described in any one of claims 1-7.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that, When executed by a processor, the computer program implements the three-phase transient voltage measurement method for cable terminal overhead lines as described in any one of claims 1-7.