An environment-friendly and energy-saving intelligent management and control method, system, medium and product

By processing data from steel production sites and predicting changes in dust concentration, multi-dimensional control commands for dust removal equipment are generated. This solves the problem that the operational potential of dust removal equipment under complex working conditions has not been fully explored in existing technologies, and achieves precise environmental protection and energy-saving control.

CN123156809APending Publication Date: 2026-11-24BEIJING RUIDA HONGXIN TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611284852.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-24
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

The existing control methods for dust removal equipment in steel production are insufficient to achieve precise environmental protection, energy saving, and intelligent management when faced with complex and ever-changing production conditions, resulting in the underutilization of its operational potential.

Method used

By acquiring and preprocessing raw sensing data from the steel production site, a standardized structured dataset is established. Combined with time-series alignment and normalization, the concentration change rate of historical dust concentration sequences is extracted, multiple sets of candidate operating parameters are generated, and control instructions are generated based on the predicted dust concentration and equipment status, enabling multi-dimensional decision-making for dust removal equipment.

Benefits of technology

It significantly improves the accuracy of intelligent control of environmental protection and energy saving of dust removal equipment under complex working conditions, fully taps its operating potential, and realizes the dual constraints of environmental compliance and energy consumption optimization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123156809A_ABST
    Figure CN123156809A_ABST
Patent Text Reader

Abstract

An environment-friendly and energy-saving intelligent management and control method, system, medium and product are related to the technical field of data processing. In the method, first, the original sensing data on site is acquired, and a fusion data set is obtained through preprocessing, time sequence alignment and normalization; second, the change rate of the historical smoke dust concentration sequence is calculated to predict the future smoke dust concentration change trend; then, candidate parameters are generated based on the fusion data and the change trend, and the operating parameters that meet the emission limit value and are expected to have the lowest energy consumption are screened out; at the same time, potential fault information is determined according to the comparison of the equipment state data; finally, the dust removal equipment control instructions are generated and executed by comprehensively considering the smoke dust concentration change trend, the lowest energy consumption operating parameters and the potential fault information of the equipment. The technical scheme provided by the application can improve the accuracy of environment-friendly and energy-saving intelligent management and control.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of data processing technology, specifically to an environmentally friendly and energy-saving intelligent management and control method, system, medium, and product. Background Technology

[0002] With increasingly stringent national environmental protection policies, the steel industry, as a key sector subject to strict control due to its high energy consumption and high emissions, faces increasingly severe dual pressures on environmental protection and energy conservation. During steel production, processes such as sintering, ironmaking, and steelmaking generate large amounts of dust-laden flue gas, which must be treated by dust removal equipment to meet emission standards. The operational effectiveness of dust removal equipment directly affects a company's environmental compliance, while its energy consumption significantly impacts production costs. Therefore, how to achieve energy-efficient operation of dust removal equipment while ensuring that flue gas emissions meet standards has become a pressing technical challenge for steel companies.

[0003] Currently, dust removal equipment management in steel production sites primarily employs an automatic control method based on threshold feedback. This method involves installing dust concentration sensors at the dust collector outlet to monitor dust concentration values ​​in real time. When the monitored value exceeds a preset control threshold, the operating power of the dust collector is automatically increased to enhance dust removal efficiency; when the monitored value is below the threshold, the operating power is reduced to save energy. This control method enables automated operation of dust removal equipment, achieving a balance between environmental protection requirements and energy consumption control to a certain extent.

[0004] However, in practical applications, the aforementioned control methods face challenges due to the complex and frequently changing conditions in steel production. Different production stages and raw material ratios lead to significant differences in dust generation characteristics. Existing control systems lack a systematic and comprehensive decision-making mechanism for adjusting operating parameters under these complex conditions, often relying on empirical, single-feedback adjustment strategies. This approach struggles to fully exploit the operational potential of dust removal equipment under varying production environments, reducing the accuracy of intelligent environmental protection and energy-saving management. Summary of the Invention

[0005] This application provides an environmental protection and energy-saving intelligent management and control method, system, medium, and product, which can improve the accuracy of environmental protection and energy-saving intelligent management and control.

[0006] The first aspect of this application provides an environmentally friendly and energy-saving intelligent management and control method, comprising:

[0007] Acquire raw sensing data from the steel production site and preprocess the raw sensing data to obtain standardized structured data;

[0008] The standardized structured data is subjected to time-series alignment and normalization to obtain a fused dataset;

[0009] Extract the historical dust concentration sequence from the fused dataset, calculate the concentration change rate of the historical dust concentration sequence within a preset time window, and calculate the predicted dust concentration based on the concentration change rate and the dust concentration at the current moment. Use the predicted dust concentration as dust concentration change trend data.

[0010] Based on the fused dataset and the soot concentration change trend data, multiple sets of candidate operating parameters are generated, and the expected energy consumption and expected soot emissions corresponding to each set of candidate operating parameters are calculated respectively.

[0011] Select the target operating parameters from which the expected smoke and dust emissions are less than the preset emission limit, and take the set of target operating parameters with the smallest expected energy consumption value as the minimum energy consumption operating parameters of the dust removal equipment;

[0012] Based on feature comparison of the device operating status data in the fused dataset, potential device fault status information is determined.

[0013] By combining the dust concentration change trend data, the minimum energy consumption operating parameters, and the potential fault status information of the equipment, a dust removal equipment control command is generated, and the dust removal equipment is controlled to execute the dust removal equipment control command.

[0014] By adopting the above technical solution, standardized structured data is obtained by acquiring raw sensing data from the steel production site and preprocessing it. This data is then fused into a dataset through time-series alignment and normalization, thus establishing a unified data foundation and solving the problem of insufficient information utilization caused by scattered data sources and inconsistent formats in existing technologies. Based on this, this application extracts historical dust concentration sequences and calculates their concentration change rate within a preset time window. Combined with the current dust concentration, a predicted dust concentration is calculated as the dust concentration change trend data, achieving forward-looking prediction of dust concentration changes and overcoming the limitations of existing threshold-based feedback control methods that rely solely on current monitoring values ​​for delayed responses. Furthermore, this application generates multiple sets of candidate operating parameters based on the fused dataset and dust concentration change trend data, and calculates the expected energy consumption and expected dust emission for each set of candidate operating parameters. By screening out target operating parameters whose expected dust emission is less than the preset emission limit, and selecting the set with the smallest expected energy consumption as the minimum energy consumption operating parameters, a dual-constraint decision-making mechanism for environmental compliance and energy consumption optimization is constructed, changing the current situation where the existing technology uses an empirical single feedback adjustment strategy, resulting in insufficient exploration of operating potential. At the same time, this application determines the potential fault status information of equipment by performing feature comparison on the equipment operating status data in the fused dataset, and generates dust removal equipment control instructions by combining dust concentration change trend data, minimum energy consumption operating parameters, and potential equipment fault status information. This realizes multi-dimensional comprehensive decision-making of operating condition prediction, parameter optimization, and equipment health status. Targeting the complex and frequently changing operating conditions of steel production, it can systematically adjust the operating parameters under different operating conditions, fully explore the operating potential of dust removal equipment in a variable production environment, and thus significantly improve the accuracy of intelligent environmental protection and energy-saving management.

[0015] Optionally, the raw sensing data is acquired by IoT sensors deployed at the steel production site at a preset acquisition frequency. The raw sensing data includes real-time dust concentration, equipment operating conditions, production line process parameters, and meteorological indicators. The raw sensing data is transmitted to a data acquisition gateway deployed on-site. In the data acquisition gateway, outlier removal and noise reduction are performed on the raw sensing data using a sliding window algorithm and a mean filtering algorithm to obtain cleaned data. The cleaned data is then parsed and format converted according to a preset data mapping template to obtain the standardized structured data.

[0016] Optionally, heterogeneous data from different devices are obtained from the standardized structured data; the sampling period attribute of the heterogeneous data is extracted, and the heterogeneous data is time-series matched based on the sampling period attribute to obtain aligned data; the aligned data is subjected to dimension elimination and normalization processing to obtain the fused dataset.

[0017] Optionally, the fan operating frequency and valve opening parameters are extracted from the minimum energy consumption operating parameters; a dynamic upper limit threshold for the fan operating frequency is determined based on the potential fault status information of the equipment, and a dynamic lower limit threshold for the valve opening parameter is determined based on the dust concentration change trend data; the fan operating frequency is compared with the dynamic upper limit threshold, and the valve opening parameter is compared with the dynamic lower limit threshold; when the fan operating frequency is less than or equal to the dynamic upper limit threshold, and the valve opening parameter is greater than or equal to the dynamic lower limit threshold, the verification is deemed successful, and a dust removal equipment control command containing the fan operating frequency and the valve opening parameter is generated; the dust removal equipment control command is converted into a control electrical signal, and the control electrical signal is sent to the frequency converter drive unit and the valve actuator, the frequency converter drive unit adjusts the fan speed of the dust removal equipment, and the valve actuator adjusts the duct airflow.

[0018] Optionally, real-time dust concentration feedback data at the dust removal equipment outlet is obtained; the concentration difference between the real-time dust concentration feedback data and the preset emission limit is calculated; if the real-time dust concentration feedback data is greater than or equal to the preset emission limit, the fan speed is increased by a preset ratio to increase the dust removal air volume; if the real-time dust concentration feedback data is less than the preset emission limit and the concentration difference is greater than a preset margin, the fan speed is decreased by a preset ratio to reduce power consumption.

[0019] Optionally, real-time feedback data after the dust removal equipment executes instructions is obtained; the fused dataset and the real-time feedback data are associated and stored to construct a historical operation sample library; according to a preset time period, newly added field operating condition data is extracted from the historical operation sample library, and the actual concentration change rate and actual energy consumption value are calculated using the newly added field operating condition data; the deviation between the actual concentration change rate and the change rate of the concentration change rate, and the energy consumption deviation between the actual energy consumption value and the expected energy consumption value are calculated; based on the change rate deviation and the energy consumption deviation, the calculation weight of the concentration change rate and the evaluation coefficient of the expected energy consumption value are updated respectively.

[0020] Optionally, the average value of the rate of change deviation and energy consumption deviation within a preset evaluation period is calculated; when the average value is greater than a preset error threshold, all historical data in the historical operation sample library is extracted; the all historical data is fitted with minimizing the rate of change deviation and the energy consumption deviation as optimization conditions to obtain global calculation weights and global evaluation coefficients; the current calculation weights and evaluation coefficients are replaced with the global calculation weights and global evaluation coefficients, respectively.

[0021] Secondly, embodiments of this application provide an environmentally friendly and energy-saving intelligent control system, which includes: one or more processors and a memory; the memory is coupled to the one or more processors, and the memory is used to store computer program code, which includes computer instructions, and the one or more processors call the computer instructions to cause the environmentally friendly and energy-saving intelligent control system to perform the method described in the first aspect and any possible implementation thereof.

[0022] Thirdly, embodiments of this application provide a computer-readable storage medium including instructions that, when executed on an environmental protection and energy-saving intelligent control system, cause the environmental protection and energy-saving intelligent control system to perform the method described in the first aspect and any possible implementation thereof.

[0023] Fourthly, embodiments of this application provide a computer program product containing instructions that, when the computer program product is run on an environmental protection and energy-saving intelligent control system, cause the environmental protection and energy-saving intelligent control system to execute the method described in the first aspect and any possible implementation thereof.

[0024] In summary, one or more technical solutions provided in this application have at least the following technical effects or advantages:

[0025] By acquiring raw sensing data from steel production sites and preprocessing it to obtain standardized structured data, and then performing time-series alignment and normalization to form a fused dataset, a unified data foundation is established, solving the problem of insufficient information utilization caused by scattered data sources and inconsistent formats in existing technologies. Based on this, this application extracts historical dust concentration sequences and calculates their concentration change rate within a preset time window. Combined with the current dust concentration, a predicted dust concentration is calculated as dust concentration change trend data, achieving forward-looking prediction of dust concentration changes and overcoming the limitations of existing threshold-based feedback control methods that rely solely on current monitoring values ​​for delayed responses. Furthermore, this application generates multiple sets of candidate operating parameters based on the fused dataset and dust concentration change trend data, and calculates the expected energy consumption and expected dust emissions for each set of candidate operating parameters. By screening out target operating parameters with expected dust emissions lower than preset emission limits, and selecting the set with the smallest expected energy consumption as the lowest energy consumption operating parameter, a dual-constraint decision-making mechanism for environmental compliance and energy consumption optimization is constructed. This changes the current situation where existing technologies use empirical single feedback adjustment strategies, resulting in insufficient exploitation of operational potential. Meanwhile, this application determines potential equipment fault status information by comparing the features of equipment operation status data in the fused dataset, and generates dust removal equipment control instructions by combining dust concentration change trend data, minimum energy consumption operating parameters and potential equipment fault status information. This realizes multi-dimensional comprehensive decision-making of operating condition prediction, parameter optimization and equipment health status. In view of the complex and frequently changing operating conditions of steel production, it can systematically adjust the operating parameters under different operating conditions, fully explore the operating potential of dust removal equipment in the variable production environment, and thus significantly improve the accuracy of environmental protection and energy-saving intelligent control. Attached Figure Description

[0026] Figure 1 This is a flowchart illustrating the environmental protection and energy-saving intelligent management and control method disclosed in the embodiments of this application;

[0027] Figure 2 This is another schematic diagram of the environmental protection and energy-saving intelligent management and control method disclosed in the embodiments of this application;

[0028] Figure 3 This is a schematic diagram of the structure of a system provided in an embodiment of this application.

[0029] Explanation of reference numerals in the attached drawings: 301, Central Processing Unit; 302, Read-Only Memory; 303, Random Access Memory; 304, Bus; 305, Input / Output Interface; 306, Input Section; 307, Output Section; 308, Storage Section; 309, Communication Section; 310, Driver; 311, Removable Media. Detailed Implementation

[0030] To enable those skilled in the art to better understand the technical solutions in this specification, the technical solutions in the embodiments of this specification will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments.

[0031] In the description of the embodiments of this application, the words "for example" or "for instance" are used to indicate examples, illustrations, or explanations. Any embodiment or design that is described as "for example" or "for instance" in the embodiments of this application should not be construed as being more preferred or advantageous than other embodiments or design options. Rather, the use of the words "for example" or "for instance" is intended to present the relevant concepts in a specific manner.

[0032] In the description of the embodiments of this application, the term "multiple" means two or more. For example, multiple systems means two or more systems, and multiple screen terminals means two or more screen terminals. Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the indicated technical features. Thus, a feature defined with "first" or "second" may explicitly or implicitly include one or more of that feature. The terms "comprising," "including," "having," and variations thereof all mean "including but not limited to," unless otherwise specifically emphasized.

[0033] This application provides an environmentally friendly, energy-saving, and intelligent management and control method, referring to... Figure 1 , Figure 1 This is a flowchart illustrating an environmental protection and energy-saving intelligent management and control method provided in an embodiment of this application. The method is applied to a system, which refers to a hardware and software integrated platform capable of executing an environmental protection and energy-saving intelligent management and control program. The system can execute an environmental protection and energy-saving intelligent management and control program. The method includes steps 101 to 107, as follows:

[0034] Step 101: Obtain raw sensing data from the steel production site and preprocess the raw sensing data to obtain standardized structured data.

[0035] In this embodiment, the steel production site refers to the actual operating area including production processes such as sintering, ironmaking, and steelmaking, as well as their supporting dust removal equipment. Raw sensing data refers to unprocessed raw measurement values ​​collected by various sensors deployed at the production site, including multi-dimensional information such as real-time dust concentration, equipment operating conditions, production line process parameters, and meteorological indicators. Preprocessing refers to the process of removing outliers, reducing noise, parsing fields, and converting formats from the collected raw data. Standardized structured data refers to a data set with a clear logical structure organized according to a unified data format and field specifications after preprocessing.

[0036] Specifically, IoT sensors deployed at different locations in the steel production site acquire data at a preset sampling frequency. The raw sensor data is transmitted to a data acquisition gateway deployed on-site via an industrial bus. The data acquisition gateway uses a sliding window algorithm to scan the raw sensor data, with a time window length of 30 seconds. Within each window, the mean and standard deviation of the data are calculated. Values ​​deviating from the mean by more than three times the standard deviation are identified as outliers and removed. A mean filtering algorithm is then used to smooth the data sequence after outlier removal, and the arithmetic mean of five adjacent data points is taken as the filtered output, resulting in cleaned data. The cleaned data is then parsed according to a pre-established data mapping template, mapping data fields from different sensor sources to unified standard field names and converting the data format to a unified floating-point number type and millisecond-level timestamp format, ultimately obtaining standardized structured data.

[0037] In one possible implementation, raw sensing data from the steel production site is acquired, and the raw sensing data is preprocessed to obtain standardized structured data. Specifically, this includes steps 1011-1013, as follows:

[0038] Step 1011: Acquire raw sensing data by using IoT sensors deployed at the steel production site at a preset acquisition frequency. The raw sensing data includes real-time dust concentration, equipment operating conditions, production line process parameters, and meteorological indicators.

[0039] In this embodiment, the Internet of Things (IoT) sensor refers to an intelligent sensing device with data acquisition and network communication capabilities deployed at key locations in the steel production site. The preset acquisition frequency refers to the frequency parameter at which the sensor acquires data at pre-configured fixed time intervals, such as once per second or once every 5 seconds. Real-time dust concentration refers to the mass concentration of suspended particulate matter in the flue gas at the current moment, expressed in milligrams per cubic meter. Equipment operating conditions refer to the real-time operating status parameters of the dust removal equipment and its auxiliary facilities, including motor speed, valve position, and pressure values. Production line process parameters refer to the process control parameters in the steel production process, including furnace temperature, air volume, and material input. Meteorological indicators refer to environmental meteorological conditions data at the production site, including temperature, humidity, wind speed, and atmospheric pressure.

[0040] Specifically, various IoT sensors, including dust concentration sensors, temperature sensors, pressure sensors, flow sensors, and vibration sensors, are deployed at locations such as flue outlets, dust collector inlets and outlets, and production workshops in the steel production site. Preset acquisition frequencies are configured according to the monitoring needs of different sensors: dust concentration sensors are set to acquire data once per second, temperature and pressure sensors once every 5 seconds, and meteorological indicator sensors once every 10 seconds. Each sensor automatically triggers data acquisition when the acquisition time arrives. The dust concentration sensor measures the particulate matter concentration in the flue gas using laser scattering; the temperature sensor measures the medium temperature using thermocouples; the pressure sensor measures the pipeline pressure using a piezoresistive element; and the flow sensor measures the flue gas flow rate using differential pressure. The sensors convert the measured physical quantities into digital signals. Each sensor node encapsulates the acquisition timestamp, sensor identifier, measured value, and unit information into a data packet, which is transmitted to the data acquisition system via wireless or wired network to complete the acquisition of raw sensing data.

[0041] Step 1012: Transmit the raw sensing data to the data acquisition gateway deployed on site. In the data acquisition gateway, use the sliding window algorithm and the mean filtering algorithm to remove outliers and remove noise from the raw sensing data to obtain the cleaned data.

[0042] In this embodiment, the data acquisition gateway refers to an edge computing device deployed on the production site for receiving sensor data, performing preliminary processing, and forwarding data. The sliding window algorithm refers to an algorithm that sets a fixed-length time window, slides the window progressively according to the time sequence, and performs statistical analysis on the data within each window position. The mean filtering algorithm is a digital signal processing method that uses the arithmetic mean of multiple consecutive sampling points as the filtered output value to smooth data fluctuations. Outlier removal refers to the data cleaning operation of identifying and removing abnormal measurement points that deviate from the normal range in the data sequence. Noise reduction and cleaning refers to the process of eliminating random noise and interference components in data through signal processing techniques to improve data quality.

[0043] Specifically, various IoT sensors transmit raw sensing data to the data acquisition gateway via industrial Ethernet or wireless communication networks. Upon receiving the raw sensing data, the data acquisition gateway categorizes and stores the data according to sensor identifiers, establishing data buffer queues for each sensor. A sliding window algorithm is applied to the data queues of each sensor type for outlier detection. The sliding window length is set to 30 seconds, with each slide lasting 1 second. At each window position, the arithmetic mean and standard deviation of all data points within the window are calculated. The absolute value is obtained by subtracting the mean from the absolute value; if this absolute value is greater than three times the standard deviation, the data point is marked as an outlier and removed from the data sequence. The data sequence after outlier removal is then processed using a mean filtering algorithm for noise reduction. The filtering window length is set to 5 sampling points. The values ​​of 5 consecutive data points are added together and divided by 5. The result is used as the filtered output value at the intermediate time point. The filtering window moves point by point to complete the smoothing process of the entire data sequence, resulting in cleaned data.

[0044] Step 1013: According to the preset data mapping template, perform field parsing and format conversion on the cleaned data to obtain standardized structured data.

[0045] In this embodiment, the data mapping template refers to a predefined data conversion rule document that specifies the correspondence between the original field names and standard field names of data from different sources, as well as the conversion specifications for data types and formats. Field parsing refers to the process of identifying the meaning of each field in the cleaned data according to the data mapping template and mapping the original field names to unified standard field names. Format conversion refers to the operation of converting the data representation from the original format to the standard format, including numeric type conversion, time format unification, unit conversion, and other processing.

[0046] Specifically, a preset data mapping template is loaded from the configuration library. This template is stored in tabular form and includes columns for original field names, standard field names, data types, and conversion rules. Each data record in the cleaned data is read, and the field names are extracted. A mapping relationship matching the field name is found in the data mapping template, and the original field name is replaced with the corresponding standard field name. For example, the field name reported by the sensor is replaced from sensor_temp_01 to the standard field name temperature. Based on the data type column in the data mapping template, the field values ​​are converted: string values ​​are converted to floating-point numbers, and integer timestamps are converted to a standard date and time format. Based on the conversion rule column, units are converted: temperature values ​​are converted from Fahrenheit to Celsius by subtracting 32 from the Fahrenheit value, multiplying by 5, and dividing by 9; pressure values ​​are converted from pounds per square inch to Pascals. The data records after field parsing and format conversion are stored in a standardized data table, resulting in standardized structured data.

[0047] Step 102: Perform time-series alignment and normalization on the standardized structured data to obtain the fused dataset.

[0048] In this application embodiment, temporal alignment refers to the process of aligning and matching heterogeneous data from different devices with different sampling periods according to a unified time reference. Normalization refers to the scaling transformation of data with different dimensions and numerical ranges, mapping them to a unified numerical interval. Fusion dataset refers to the integration of multi-source heterogeneous data into a comprehensive dataset with a unified time reference and numerical scale after temporal alignment and normalization.

[0049] Specifically, heterogeneous data from different equipment sources is extracted from standardized structured data. The sampling period attributes of various data types are identified: the sampling period for dust concentration data is 1 second, for temperature data it is 5 seconds, and for process parameter data it is 10 seconds. A minimum sampling period of 1 second is selected as the unified time reference. For data with sampling periods greater than 1 second, a linear interpolation method is used for time-series matching. The interpolation point values ​​are calculated between adjacent sampling points according to the time ratio, ensuring all data have a uniform 1-second sampling interval, resulting in aligned data. Dimensionless processing is performed on the aligned data, identifying the physical units of various data types. The unit for concentration data is unified to milligrams per cubic meter, and the unit for temperature data is unified to degrees Celsius. The dimensionless aligned data is then normalized using a maximum-minimum normalization method. The maximum and minimum values ​​of each data type in historical data are calculated. The current value is subtracted from the minimum value and then divided by the difference between the maximum and minimum values ​​to obtain a normalized value in the range of 0 to 1, ultimately resulting in the fused dataset.

[0050] In one possible implementation, the standardized structured data undergoes time-series alignment and normalization to obtain a fused dataset, specifically including steps 1021-1022, as follows:

[0051] Step 1021: Obtain heterogeneous data from different devices in the standardized structured data; extract the sampling period attribute of the heterogeneous data, and perform time-series matching on the heterogeneous data based on the sampling period attribute to obtain aligned data.

[0052] In this embodiment, heterogeneous data refers to multi-source data from different types of devices with different data structures and sampling periods. The sampling period attribute refers to the time interval characteristic of data acquisition by various sensors or devices, reflecting the frequency of data updates. Time-series matching refers to aligning heterogeneous data with different sampling periods according to a unified time base, so that different data sequences have corresponding values ​​at the same time. Aligned data refers to the set of data where, after time-series matching, all data sequences have a unified sampling period and time base.

[0053] Specifically, the device identification field is read from standardized structured data, and the data is grouped according to the device identification to obtain heterogeneous data subsets from different device sources. Each heterogeneous data subset is traversed, and the timestamps of two adjacent data records in each subset are extracted. The time difference between the two timestamps is calculated, and this time difference is the sampling period attribute of the device. The sampling period attributes of all heterogeneous data are statistically analyzed, and the minimum sampling period is identified as a unified time benchmark, for example, a minimum sampling period of 1 second. Heterogeneous data with sampling periods greater than 1 second are traversed, and time-series matching processing is performed on these data. A new time point is inserted between two adjacent original sampling points at 1-second intervals. The time distance between each inserted time point and the two preceding and following original sampling points is calculated, and a linear interpolation method is used to calculate the value of the inserted time point, specifically the value of the previous sampling point plus the time distance ratio multiplied by the difference between the values ​​of the preceding and following sampling points. After interpolation processing is completed for all heterogeneous data, all data sequences have a unified sampling period of 1 second, resulting in aligned data.

[0054] Step 1022: Perform dimension elimination and normalization on the aligned data to obtain the fused dataset.

[0055] In this embodiment, dimensionless measurement refers to unifying data with different physical units to the same unit of measurement, eliminating the impact of unit differences on data analysis. Normalization refers to mapping data with different numerical ranges to a unified numerical interval through mathematical transformation, typically between 0 and 1 or between -1 and +1, making the data comparable. A fused dataset refers to integrating multi-source heterogeneous data into a comprehensive dataset with a unified measurement standard after dimensionless measurement and normalization.

[0056] Specifically, the dimensions of various data fields in the aligned data are identified, and the unit attribute of each field is read. Temperature data is dimension-unified, with all temperature values ​​converted to degrees Celsius. Concentration data is dimension-unified, with all concentration values ​​converted to milligrams per cubic meter (mg / m³). If concentration data exists in grams per cubic meter, its value is multiplied by 1000 to convert it to mg / m³. Pressure data is dimension-unified, with all pressure values ​​converted to Pascals. After dimension elimination, the data for each field is normalized. The maximum and minimum values ​​of each field over the past 30 days are retrieved from the historical database. For each field value in the current data, the normalized value is calculated by subtracting the minimum value from the current value and then dividing by the difference between the maximum and minimum values. If the maximum and minimum values ​​of a field are equal, the normalized value for that field is set to 0.5. The normalized field data, along with the corresponding timestamps and device identifiers, are organized into a unified data structure and stored in the fused dataset, completing the construction of the fused dataset.

[0057] Step 103: Extract the historical dust concentration sequence from the fused dataset, calculate the concentration change rate of the historical dust concentration sequence within a preset time window, and calculate the predicted dust concentration based on the concentration change rate and the dust concentration at the current moment. Use the predicted dust concentration as the dust concentration change trend data.

[0058] In this embodiment, the historical dust concentration sequence refers to a sequence of historical dust concentration measurements extracted from the fused dataset and arranged in chronological order. The preset time window refers to a fixed time length used to calculate the concentration change rate, such as the time range of the most recent 5 minutes or the most recent 10 minutes. The concentration change rate refers to the rate at which the dust concentration changes over time within the preset time window. The predicted dust concentration refers to the dust concentration value at a future moment calculated based on the current concentration and the concentration change rate. Dust concentration change trend data is used to represent the future development direction and magnitude of dust concentration changes.

[0059] Specifically, all historical values ​​of the smoke concentration field are extracted from the fused dataset and sorted in ascending order by timestamp to obtain a historical smoke concentration sequence. A preset time window length of 300 seconds is set, and all concentration measurements within the most recent 300 seconds of the historical smoke concentration sequence are extracted. The concentration data within the time window are organized into time-concentration data pairs according to chronological order. The concentration change rate within the time window is calculated, and a least squares method is used to linearly fit the time-concentration data pairs. The slope of the fitted line is the concentration change rate, expressed in milligrams per cubic meter per second. The current smoke concentration value is obtained, and the current smoke concentration is added to the product of the concentration change rate and the prediction duration to calculate the predicted smoke concentration. The prediction duration is set to 60 seconds, i.e., predicting the smoke concentration value one minute from now. The calculated predicted smoke concentration is used as smoke concentration change trend data for subsequent processing.

[0060] Step 104: Based on the fused dataset and the soot concentration change trend data, generate multiple sets of candidate operating parameters, and calculate the expected energy consumption and expected soot emissions for each set of candidate operating parameters.

[0061] In this embodiment, candidate operating parameters refer to multiple combinations of different operating parameters that the dust removal equipment may use, including control parameters such as fan operating frequency and valve opening. Expected energy consumption refers to the estimated electrical energy consumed by the dust removal equipment under a certain set of candidate operating parameters, expressed in kilowatt-hours. Expected dust emission refers to the estimated mass of dust emitted into the atmosphere by the dust removal equipment under a certain set of candidate operating parameters, expressed in kilograms.

[0062] Specifically, based on the current equipment operating conditions and production line process parameters in the fused dataset, combined with the dust concentration change trend data, multiple sets of candidate operating parameters are generated. The fan operating frequency is set to an adjustment range of 30 Hz to 50 Hz, and the valve opening is set to an adjustment range of 40% to 80%. Parameters are combined in steps of 5 Hz and 10%, generating 25 sets of candidate operating parameters. For each set of candidate operating parameters, based on the cubic relationship between fan operating frequency and motor power, the real-time power of the fan at that frequency is calculated. The real-time power is multiplied by the expected operating time to obtain the expected energy consumption value for that set of parameters. Based on the correlation between the dust removal efficiency of the dust removal equipment and the fan frequency and valve opening, the percentage of dust removal efficiency for that set of parameters is calculated. The predicted dust concentration from the dust concentration change trend data is multiplied by the flue gas flow rate, then multiplied by 1, and the difference in dust removal efficiency is subtracted to obtain the expected dust emission for that set of parameters. This completes the calculation of the expected energy consumption value and expected dust emission for each set of candidate operating parameters.

[0063] Step 105: Select the target operating parameters whose expected smoke and dust emissions are less than the preset emission limit, and take the set of target operating parameters with the smallest expected energy consumption value as the minimum energy consumption operating parameters of the dust removal equipment.

[0064] In this embodiment, the preset emission limit refers to the maximum concentration or emission threshold of particulate matter allowed to be emitted according to national or local environmental protection standards. The target operating parameters refer to candidate operating parameters that meet the condition that the expected particulate matter emission is less than the preset emission limit. The lowest energy consumption operating parameters refer to the set of operating parameters with the lowest expected energy consumption value among all target operating parameters, used to guide the dust removal equipment to operate in the most energy-efficient manner.

[0065] Specifically, obtain the preset emission limit value, such as a particulate matter emission concentration limit of 10 mg / m³. Iterate through all candidate operating parameters, comparing the expected particulate matter emission of each candidate parameter with the preset emission limit. Candidate parameters with expected particulate matter emissions less than the preset emission limit are marked as qualified parameters, and all qualified parameters are collected to form a target operating parameter set. Energy consumption is compared within the target operating parameter set. For each target operating parameter set, its corresponding expected energy consumption value is extracted, and the minimum expected energy consumption value is found. The target operating parameter with the minimum expected energy consumption value is taken as the lowest energy consumption operating parameter for the dust removal equipment. This parameter includes the fan operating frequency and valve opening value, which are the equipment control parameters with the lowest energy consumption while meeting environmental emission requirements. If the target operating parameter set is empty, the set with the smallest expected particulate matter emission among all candidate operating parameters is selected as the lowest energy consumption operating parameter.

[0066] Step 106: Perform feature comparison based on the device operating status data in the fused dataset to determine the potential fault status information of the device.

[0067] In this embodiment, equipment operating status data refers to various parameter data reflecting the operating status of dust removal equipment contained in the fused dataset, including equipment health-related indicators such as fan vibration value, bearing temperature, filter bag pressure difference, and motor current. Feature comparison refers to the process of comparing and analyzing the current equipment operating status data with a pre-established normal operating characteristic range. Equipment potential fault status information is used to indicate possible abnormal conditions or fault risks of the equipment, such as excessively high bearing temperature or abnormal vibration.

[0068] Specifically, equipment operating status data is extracted from the fused dataset, including current fan vibration values, bearing temperatures, filter bag pressure differentials, motor current, and other parameters. Normal operating characteristic ranges for various equipment operating status parameters are pre-established; for example, the normal range for fan vibration is 0 to 5 mm / s, for bearing temperature it is 40 to 70 degrees Celsius, and for filter bag pressure differential it is 800 to 1500 Pascals. The extracted equipment operating status data is compared item by item with the corresponding normal operating characteristic ranges. If a parameter value exceeds the normal range, it is marked as abnormal. The severity of the marked abnormal parameters is assessed by calculating the deviation of the actual parameter value from the normal range boundary. A deviation greater than 20% is considered a potential fault risk. All parameters with potential fault risks and their deviations are summarized to generate equipment potential fault status information, which includes the abnormal parameter name, current value, normal range, and deviation degree.

[0069] Step 107: Combine the dust concentration change trend data, minimum energy consumption operating parameters and potential equipment fault status information to generate dust removal equipment control instructions, and control the dust removal equipment to execute the dust removal equipment control instructions.

[0070] In this embodiment, the dust removal equipment control command refers to specific instruction information generated based on comprehensive decision-making for controlling the operation of the dust removal equipment, including specific parameter values ​​such as fan operating frequency and valve opening degree, as well as execution time. Dust removal equipment refers to a system of equipment used in steel production sites to treat dust-laden flue gas, including components such as fans, valves, filter bags, and controllers.

[0071] Specifically, the fan operating frequency and valve opening parameters are extracted from the lowest energy consumption operating parameters. A dynamic upper limit threshold for the fan operating frequency is determined based on potential equipment fault status information. If the bearing temperature deviates from the normal range by more than 15%, the dynamic upper limit threshold is set to 80% of the normal maximum frequency; otherwise, it is set to 100% of the normal maximum frequency. A dynamic lower limit threshold for the valve opening parameter is determined based on dust concentration trend data. If the predicted dust concentration rise rate is greater than 0.5 mg / m³ / s, the dynamic lower limit threshold is set to 50%; otherwise, it is set to 40%. The extracted fan operating frequency and valve opening parameters are compared with the dynamic upper and lower limit thresholds. The verification is considered successful when the fan operating frequency is less than or equal to the dynamic upper limit threshold and the valve opening parameter is greater than or equal to the dynamic lower limit threshold. A dust removal equipment control command containing the verified fan operating frequency and valve opening parameters is generated. This control command is converted into control electrical signals and sent to the frequency converter drive unit and valve actuator to control the dust removal equipment to execute the control command.

[0072] In one possible implementation, after controlling the dust removal equipment to execute the dust removal equipment control command, the process further includes steps 1071-1073, as follows:

[0073] Step 1071: Obtain real-time feedback data after the dust removal equipment executes the command; associate and store the fused dataset and the real-time feedback data to build a historical operation sample library.

[0074] In this embodiment, real-time feedback data refers to data collected by sensors after the dust removal equipment executes control commands, reflecting the actual operating effect of the equipment, including parameters such as actual dust emission concentration, actual energy consumption, and equipment response time. Association storage refers to a data management method that binds and stores different datasets with causal or temporal relationships according to association keys. The historical operation sample library refers to a structured database storing historical operation data, containing complete operation records such as input condition data, control parameters, and output effect data.

[0075] Specifically, after the dust removal equipment executes the control command, a real-time feedback data acquisition task is initiated. This involves continuously collecting actual operating data from the equipment via IoT sensors, with a collection duration set to 300 seconds. The collected real-time feedback data includes parameters such as the actual concentration measurement at the dust emission outlet, the actual power and cumulative electricity consumption recorded by the electricity meter, the fan frequency feedback value, and the valve position feedback value. The fused dataset record corresponding to the execution time of the control command is extracted. This record contains information such as the production conditions, equipment status, and environmental parameters before the control was executed. Using the timestamp of the control command execution time as the association key, the fused dataset record is linked and bound to the real-time feedback data. A historical operating sample record is created. This record contains input feature field groups and output result field groups. The input feature field group stores the content of the fused dataset, and the output result field group stores the content of the real-time feedback data, while also recording the parameter content of the control command. The created historical operating sample record is inserted into the historical operating sample library. The historical operating sample library adopts a time-series database structure, indexed by timestamps, supporting fast time-range queries and data traceability.

[0076] Step 1072: According to the preset time period, extract the newly added field operating condition data from the historical operating sample database, and use the newly added field operating condition data to calculate the actual concentration change rate and the actual energy consumption value.

[0077] In this embodiment, the preset time period refers to a fixed time interval for the system to update data and optimize parameters, such as once per hour or per day. Newly added on-site operating data refers to newly generated operating record data stored in the historical operating sample library between the end of the previous time period and the current moment. The actual concentration change rate refers to the actual rate of change of dust concentration calculated based on real-time feedback data, reflecting the true trend of concentration change. The actual energy consumption value refers to the actual electrical energy consumed by the dust removal equipment during actual operation.

[0078] Specifically, a preset time period of 3600 seconds is set, meaning a data extraction task is executed once per hour. The execution timestamp of the previous data extraction task is recorded, and the time difference between the current moment and the previous execution timestamp is calculated. A new data extraction task is triggered when the time difference reaches or exceeds 3600 seconds. All historical operation sample records with timestamps greater than the previous execution timestamp and less than or equal to the current moment are retrieved from the historical operation sample database; these records represent the newly added field condition data. Each record in the newly added field condition data is traversed, and the dust concentration time series in the corresponding real-time feedback data is extracted. The dust concentration time series is arranged chronologically, and the starting and ending concentration values ​​are selected. The difference between the ending and starting concentration values ​​is calculated, and this difference is divided by the time span of the time series to obtain the actual concentration change rate. The cumulative electricity consumption value in the corresponding real-time feedback data is extracted; this cumulative electricity consumption value is the actual energy consumption value. The calculated actual concentration change rate and actual energy consumption value are associated and stored with the corresponding historical operation sample records to complete the calculation of the actual parameters.

[0079] Step 1073: Calculate the deviation between the actual concentration change rate and the concentration change rate, as well as the energy consumption deviation between the actual energy consumption value and the expected energy consumption value; based on the change rate deviation and energy consumption deviation, update the calculation weight of the concentration change rate and the evaluation coefficient of the expected energy consumption value, respectively.

[0080] In this embodiment, the rate of change deviation refers to the difference between the actual concentration change rate and the predicted concentration change rate, used to measure the accuracy of concentration change prediction. The energy consumption deviation refers to the difference between the actual energy consumption value and the expected energy consumption value, used to measure the accuracy of energy consumption prediction. The calculation weight refers to the weight coefficient of each influencing factor when calculating the concentration change rate, used to adjust the contribution of different factors to the calculation result. The evaluation coefficient refers to the correction coefficient used when evaluating the expected energy consumption value, used to adjust the parameter values ​​in the energy consumption calculation formula.

[0081] Specifically, the actual concentration change rate, predicted concentration change rate, actual energy consumption value, and expected energy consumption value are extracted from historical operational sample records. The difference between the actual concentration change rate and the predicted concentration change rate is calculated, and the absolute value of this difference is taken as the rate of change deviation. The difference between the actual energy consumption value and the expected energy consumption value is calculated, and the absolute value of this difference is taken as the energy consumption deviation. The rate of change deviations of the most recent 100 historical operational sample records are statistically analyzed, and the arithmetic mean of these deviation values ​​is calculated. If the average rate of change deviation is greater than 0.1 mg / m³ / s, the calculation weights of the concentration change rate are updated. The gradient descent method is used to adjust the weights, with a learning rate of 0.01. The result of subtracting the learning rate multiplied by the average rate of change deviation from the current weight is used as the new calculation weight. The energy consumption deviations of the most recent 100 historical operational sample records are statistically analyzed, and the arithmetic mean of these deviation values ​​is calculated. If the average energy consumption deviation is greater than 0.5 kWh, the evaluation coefficient of the expected energy consumption value is updated, the ratio of the actual energy consumption value to the expected energy consumption value is calculated, and the ratio is multiplied by the current evaluation coefficient to obtain the new evaluation coefficient, thus completing the calculation of weights and updating of evaluation coefficients.

[0082] In one possible implementation, the calculation weight of the concentration change rate and the evaluation coefficient of the expected energy consumption value are updated based on the change rate deviation and energy consumption deviation, respectively, specifically including steps 10731-10733, as follows:

[0083] Step 10731: Calculate the average value of the rate of change deviation and energy consumption deviation within the preset evaluation period; when the average value is greater than the preset error threshold, extract the full historical data from the historical operation sample library.

[0084] In this embodiment, the preset evaluation period refers to a fixed time period for system performance evaluation and global parameter optimization, typically set to 24 hours or 7 days. The preset error threshold is an error limit value used to determine whether the system's prediction accuracy requires global optimization; when the error exceeds this threshold, global parameter refitting is triggered. Full historical data refers to all historical running records stored in the historical running sample library, including complete running data from system startup to the current moment.

[0085] Specifically, the preset evaluation period is set to 86,400 seconds (24 hours), and the execution timestamp of the last global evaluation is recorded. When the time difference between the current moment and the last execution timestamp reaches 86,400 seconds, the global evaluation task is initiated. All historical operation sample records from the past 24 hours are retrieved from the historical operation sample database, and the rate of change deviation and energy consumption deviation are extracted from each record. The average rate of change deviation is obtained by summing all the rate of change deviation values ​​and dividing by the total number of records. The average energy consumption deviation is obtained by summing all the energy consumption deviation values ​​and dividing by the total number of records. The preset error thresholds for the rate of change deviation and energy consumption deviation are set to 0.2 milligrams per cubic meter per second and 1 kilowatt-hour, respectively. It is determined whether the average rate of change deviation is greater than 0.2 or the average energy consumption deviation is greater than 1. If either condition is met, global parameter optimization is required. A full data query request is initiated to the historical operation sample database. The query conditions are set to a time range from the system startup time to the current time. All historical operation sample records in the query results are extracted to obtain the full historical data. The full historical data includes complete information such as operating condition input characteristics, control parameters, and actual output results.

[0086] Step 10732: Using minimizing the rate of change deviation and energy consumption deviation as optimization conditions, fit the full historical data to obtain the global calculation weight and global evaluation coefficient.

[0087] In this embodiment, the optimization condition refers to the objective function or optimization goal that needs to be achieved during parameter optimization, which here is to minimize the weighted sum of the rate of change deviation and energy consumption deviation. Fitting processing refers to the process of using optimization algorithms to mathematically model historical data and find the optimal parameter combination that minimizes the objective function. Global calculation weights refer to the concentration change rate calculation weight parameters applicable to the overall operating conditions obtained by fitting the entire historical data set. Global evaluation coefficients refer to the energy consumption evaluation coefficient parameters applicable to the overall operating conditions obtained by fitting the entire historical data set.

[0088] Specifically, input feature variables related to concentration change rate are extracted from the full historical data, including parameters such as historical concentration sequences, production line load, and flue gas flow rate. An objective function for calculating the concentration change rate is constructed, defined as the sum of squares of the differences between the predicted and actual concentration change rates. A particle swarm optimization algorithm is used to optimize the calculation weights, initializing 20 particles, each representing a set of calculation weight values, with 100 iterations. In each iteration, the predicted concentration change rate for each record in the full historical data is calculated using the current weights. The sum of squares of the rate deviations across all records is calculated as the fitness value. The particle position and velocity are updated based on the fitness value. After the iteration, the weight corresponding to the particle with the smallest fitness value is taken as the global calculation weight. Energy consumption-related input feature variables are extracted from the full historical data, including parameters such as fan frequency, operating time, and equipment load rate. An objective function for energy consumption assessment is constructed, defined as the sum of squares of the differences between the expected and actual energy consumption values. The least squares method is used to fit the evaluation coefficients, establish a linear relationship between energy consumption and characteristic variables, and calculate the evaluation coefficients that minimize the objective function. These evaluation coefficients are the global evaluation coefficients.

[0089] Step 10733: Replace the current calculated weights and evaluation coefficients with the global calculated weights and global evaluation coefficients, respectively.

[0090] In this embodiment, the current calculation weight refers to the concentration change rate calculation weight parameter currently used by the system. The current evaluation coefficient refers to the energy consumption evaluation coefficient parameter currently used by the system. The replacement operation refers to the parameter update process of updating the system configuration parameters from old values ​​to new values. After the update, the system will use the new parameters for subsequent calculations.

[0091] Specifically, the system reads the current calculation weights and evaluation coefficients from the system configuration file. These parameters are stored in the weight and coefficient fields of the configuration data table. A parameter update transaction is created to ensure the atomicity of the parameter replacement operation. Within the transaction, the values ​​in the weight field of the configuration data table are updated to the values ​​of the global calculation weights, and the values ​​in the coefficient field of the configuration data table are updated to the values ​​of the global evaluation coefficients. The timestamp of the parameter update and the parameter values ​​before and after the update are recorded and written to the parameter change log table for subsequent parameter traceability and effect evaluation. The parameter update transaction is committed to make the parameter changes effective. A parameter update notification message is sent to each calculation module in the system. Upon receiving the notification, the calculation module reloads the configuration parameters. In subsequent concentration change rate calculations, the system will use the updated global calculation weights for calculation, and in subsequent energy consumption assessments, the system will use the updated global evaluation coefficients for calculation, completing the replacement and update of calculation weights and evaluation coefficients.

[0092] In the above embodiments, by acquiring standardized structured data and constructing a fusion dataset, and dynamically updating the calculation weights and evaluation coefficients in conjunction with a historical operating sample library, adaptive optimization of multi-source data perception and prediction parameters for the dust emission status at steel production sites is achieved. To further address the dilemma of simultaneously meeting emission standards while ensuring safe equipment operation and minimizing energy consumption during dust removal equipment control, and to guarantee the operational stability of dust removal equipment under different operating conditions and the real-time responsiveness of control strategies, this application also provides an environmentally friendly and energy-saving intelligent management and control method. This method extracts the fan operating frequency and valve opening parameters from the lowest energy consumption operating parameters. Based on potential equipment fault status information, it determines a dynamic upper limit threshold for the fan operating frequency to avoid equipment overload. Based on dust concentration change trend data, it determines a dynamic lower limit threshold for the valve opening parameter to ensure dust removal efficiency. The extracted operating parameters are double-checked against the corresponding dynamic thresholds. Upon successful verification, a dust removal equipment control command containing the fan operating frequency and valve opening parameters is generated and converted into a control electrical signal. The variable frequency drive unit and valve actuator adjust the fan speed and duct airflow respectively to achieve coordinated control. Simultaneously, after execution of the control, real-time dust concentration feedback data from the dust removal equipment outlet is continuously acquired. Based on the comparison result between the real-time concentration and the preset emission limit, the fan speed is dynamically adjusted up or down according to a preset ratio. This allows the system to more accurately and efficiently handle the coordinated control needs of equipment safety constraints and energy consumption optimization while meeting environmental emission standards. The following section combines... Figure 2 Another environmentally friendly and energy-saving intelligent management and control method in the embodiments of this application is described below:

[0093] Please see Figure 2 This is another flowchart illustrating an environmentally friendly and energy-saving intelligent control method in an embodiment of this application.

[0094] Step 201: Extract the fan operating frequency and valve opening parameters from the lowest energy consumption operating parameters.

[0095] In this embodiment, the minimum energy consumption operating parameters refer to the combination of equipment operating parameters that minimizes the energy consumption of the dust removal equipment while meeting the emission standards. The fan operating frequency refers to the operating frequency of the dust removal fan motor, measured in Hertz (Hz). This frequency determines the fan's rotational speed; for example, a frequency of 40 Hz results in a fan speed of 1200 revolutions per minute. The valve opening parameter refers to the degree of opening of the valves that regulate airflow in the dust removal system, expressed as a percentage; for example, a valve opening of 70% means the valve is open to 70% of its rated opening.

[0096] Specifically, the minimum energy consumption operating parameter data structure is retrieved from the energy consumption optimization calculation results. This data structure contains multiple fields, including fan operating frequency, valve opening parameter, expected energy consumption, and predicted concentration. The fan operating frequency field is located within this data structure, and its stored value, representing the recommended fan operating frequency in Hertz, is retrieved and stored in a temporary variable. The valve opening parameter field is also located within the same data structure, and its stored value, representing the recommended valve opening degree, is retrieved and stored in another temporary variable. The extracted fan operating frequency and valve opening parameters are then validated for data type, confirming that the values ​​are floating-point numbers and within a reasonable range. The fan operating frequency should be between 0 and 60 Hertz, and the valve opening parameter should be between 0 and 100%. After successful validation, the fan operating frequency and valve opening parameters are output as extraction results for subsequent verification and control.

[0097] Step 202: Determine the dynamic upper limit threshold of the fan operating frequency based on the potential fault status information of the equipment, and determine the dynamic lower limit threshold of the valve opening parameter based on the dust concentration change trend data.

[0098] In this embodiment, potential equipment fault status information refers to diagnostic data obtained through equipment health monitoring that reflects abnormal equipment conditions and fault risks, including information such as abnormal bearing temperature, excessive vibration, and degree of wear. The dynamic upper limit threshold refers to the maximum allowable value of parameters dynamically adjusted according to the current equipment status, used to limit the operational intensity of the equipment under abnormal conditions. Dust concentration change trend data refers to the direction and rate of change of dust concentration over historical periods, reflecting whether the concentration is increasing, decreasing, or remaining stable. The dynamic lower limit threshold refers to the minimum allowable value of parameters dynamically adjusted according to the current dust concentration change trend, used to ensure emission control effectiveness.

[0099] Specifically, the system reads the fault risk level field from the potential fault status information of the equipment, which can be set to low, medium, or high risk. Based on the fault risk level, a dynamic upper limit threshold for the fan operating frequency is determined: 50 Hz for low risk, 40 Hz for medium risk, and 30 Hz for high risk. The system also reads the trend type and rate of change fields from the dust concentration trend data. The trend type field can be set to rising, falling, or stable, and the rate of change field is measured in milligrams per cubic meter per minute. Based on the dust concentration trend, a dynamic lower limit threshold for the valve opening parameter is determined: 60% for rising trend and rate of change greater than 0.5, 40% for stable or falling trend, and 50% for rising trend but rate of change not greater than 0.5. The determined dynamic upper and lower thresholds are stored separately for subsequent parameter verification.

[0100] Step 203: Compare the fan operating frequency with the dynamic upper limit threshold and the valve opening parameter with the dynamic lower limit threshold; when the fan operating frequency is less than or equal to the dynamic upper limit threshold and the valve opening parameter is greater than or equal to the dynamic lower limit threshold, the verification is deemed successful, and a dust removal equipment control command containing the fan operating frequency and valve opening parameter is generated.

[0101] In this embodiment, comparison refers to the operation of comparing the magnitude of two values ​​to determine whether one value exceeds the set range of the other. Verification pass means that the parameter to be verified meets all safety and validity constraints and can be accepted and executed by the system. Dust removal equipment control instructions refer to equipment operation commands containing specific control parameters, used to guide the dust removal equipment to operate and adjust according to the specified parameters.

[0102] Specifically, the extracted fan operating frequency value and the determined dynamic upper limit threshold value are read, and a numerical comparison operation is performed to determine whether the fan operating frequency is less than or equal to the dynamic upper limit threshold. If the fan operating frequency is less than or equal to the dynamic upper limit threshold, the first comparison result is marked as meeting the condition; otherwise, it is marked as not meeting the condition. The extracted valve opening parameter value and the determined dynamic lower limit threshold value are read, and a numerical comparison operation is performed to determine whether the valve opening parameter is greater than or equal to the dynamic lower limit threshold. If the valve opening parameter is greater than or equal to the dynamic lower limit threshold, the second comparison result is marked as meeting the condition; otherwise, it is marked as not meeting the condition. The first and second comparison results are checked. If both comparison results meet the condition, the verification is deemed successful. After the verification is deemed successful, a dust removal equipment control instruction data structure is created. This data structure includes an instruction type field, a fan frequency field, a valve opening field, and an execution time field. The instruction type field is set to parameter adjustment, the fan frequency field is set to the extracted fan operating frequency value, the valve opening field is set to the extracted valve opening parameter value, and the execution time field is set to the current timestamp. The created dust removal equipment control commands are encoded and encapsulated to generate sendable command messages, thus completing the generation of dust removal equipment control commands.

[0103] Step 204: Convert the dust removal equipment control command into a control electrical signal, and send the control electrical signal to the frequency converter drive unit and valve actuator. Adjust the fan speed of the dust removal equipment through the frequency converter drive unit, and adjust the air volume of the pipeline through the valve actuator.

[0104] In this embodiment, the control electrical signal refers to the electrical signal that converts digital instructions into analog voltage or current signals for driving the actuator of the device, such as a voltage signal of 0 to 10 volts or a current signal of 4 to 20 milliamps. The variable frequency drive unit refers to a frequency converter device used to adjust the operating frequency of the motor, controlling the motor speed by changing the output power frequency. The valve actuator refers to an electric or pneumatic device that receives control signals and drives the valve opening and closing, including electric actuators or pneumatic actuators. The fan speed refers to the number of revolutions per minute (RPM) of the dust collector fan. The duct air volume refers to the volumetric flow rate of flue gas passing through the dust collector duct per unit time, in cubic meters per hour.

[0105] Specifically, the values ​​of the fan frequency and valve opening fields in the dust removal equipment control commands are read. The fan frequency value is converted into a control electrical signal recognizable by the variable frequency drive unit. A linear mapping method is used to map the frequency range of 0 to 60 Hz to the voltage range of 0 to 10 volts. Specifically, the fan frequency value is divided by 6 to obtain the corresponding voltage value. The calculated voltage value is then converted into an actual analog voltage signal using a digital-to-analog converter. The valve opening parameter value is converted into a control electrical signal recognizable by the valve actuator. A linear mapping method is used to map the opening range of 0 to 100% to the current range of 4 to 20 mA. Specifically, the valve opening parameter value is multiplied by 0.16 and then added to 4 to obtain the corresponding current value. The calculated current value is then converted into an actual analog current signal using a digital-to-analog converter. The converted voltage signal is sent to the variable frequency drive unit via an industrial fieldbus. After receiving the voltage signal, the variable frequency drive unit adjusts its output frequency to drive the fan motor to change its speed. The converted current signal is sent to the valve actuator via an industrial fieldbus. After receiving the current signal, the valve actuator drives the valve to rotate, changing the valve opening and regulating the flow of flue gas through the pipeline.

[0106] In one possible implementation, after adjusting the fan speed of the dust removal equipment through the frequency converter drive unit and adjusting the duct air volume through the valve actuator, the process further includes steps 2041-2042, as follows:

[0107] Step 2041: Obtain real-time dust concentration feedback data at the dust removal equipment outlet; calculate the concentration difference between the real-time dust concentration feedback data and the preset emission limit.

[0108] In this embodiment, real-time dust concentration feedback data refers to the current dust concentration measurement value collected and transmitted in real time by a concentration sensor installed at the flue gas outlet of the dust removal equipment, expressed in milligrams per cubic meter. The preset emission limit refers to the maximum allowable dust emission concentration pre-set according to environmental regulations or enterprise standards; for example, the national standard emission limit is 30 milligrams per cubic meter. The concentration difference refers to the numerical difference between the real-time dust concentration feedback data and the preset emission limit, used to assess the distance between the current emission concentration and the limit.

[0109] Specifically, the system connects to a dust concentration sensor installed at the dust removal equipment outlet via an industrial communication network. This sensor uses laser scattering or photoelectric methods for real-time concentration measurement. The system receives the latest concentration measurement data packet from the sensor, which includes fields such as measurement timestamp, sensor number, concentration value, and data status. The concentration value field in the data packet is extracted; this value is the real-time dust concentration feedback data, in milligrams per cubic meter (mg / m³). The real-time dust concentration feedback data is validated, confirming that the data status field is marked as normal and the value is within a reasonable range (greater than 0 and less than 500 mg / m³). A preset emission limit is read from the system configuration parameters; this limit is set according to emission standards, for example, 30 mg / m³. A concentration difference calculation is performed, subtracting the preset emission limit from the real-time dust concentration feedback data to obtain the concentration difference. If the real-time dust concentration feedback data is 35 mg / m³ and the preset emission limit is 30 mg / m³, the concentration difference is 5 mg / m³, indicating that the current concentration exceeds the limit by 5 mg / m³. If the real-time dust concentration feedback data is 25 mg / m³, then the concentration difference is -5 mg / m³, indicating that the current concentration is 5 mg / m³ below the limit. The calculated concentration difference is stored for subsequent adjustment decision-making.

[0110] Step 2042: If the real-time dust concentration feedback data is greater than or equal to the preset emission limit, the fan speed is increased by a preset ratio to increase the dust removal air volume; if the real-time dust concentration feedback data is less than the preset emission limit and the concentration difference is greater than the preset margin, the fan speed is decreased by a preset ratio to reduce power consumption.

[0111] In this embodiment, the preset ratio refers to a fixed increase / decrease ratio coefficient used when adjusting the fan speed, such as 5% or 10% of the current speed for each adjustment. The preset margin refers to the maximum safety margin allowed when the real-time concentration is below the emission limit; exceeding this margin indicates potential for energy-saving optimization, for example, set to 10 mg / m³. "Increase" refers to increasing the adjustment of equipment operating parameters, thereby increasing the equipment's workload. "Decrease" refers to decreasing the adjustment of equipment operating parameters, thereby reducing the equipment's workload.

[0112] Specifically, the system determines whether the real-time dust concentration feedback data is greater than or equal to the preset emission limit. If the real-time dust concentration feedback data is greater than or equal to the preset emission limit, it indicates that the current emission exceeds or is close to exceeding the limit, requiring enhanced dust removal efficiency. The system reads the preset adjustment ratio from the configuration parameters; this ratio is set to 10%. It reads the current output fan speed value from the variable frequency drive unit, for example, 1200 rpm. The system calculates the adjustment margin by multiplying the current speed value by the preset adjustment ratio (0.1), resulting in an adjustment margin of 120 rpm. The system calculates the target speed by adding the adjustment margin to the current speed value, resulting in a target speed of 1320 rpm. A speed adjustment command is sent to the variable frequency drive unit, converting the target speed into the corresponding frequency value. The control signal drives the variable frequency drive unit to adjust its output frequency, increasing the fan speed to the target speed. If the real-time dust concentration feedback data is less than the preset emission limit, the system determines whether the absolute value of the concentration difference is greater than a preset margin, which is set to 10 mg / m³. If the absolute value of the concentration difference is greater than 10, it indicates that the concentration is far below the limit, leaving room for energy saving. The preset reduction ratio is read from the configuration parameters; this ratio is set to 5%. The reduction amount is calculated by multiplying the current speed value by the preset reduction ratio, i.e., multiplying by 0.05. The target speed is calculated by subtracting the reduction amount from the current speed value. A speed adjustment command is sent to the variable frequency drive unit, driving the fan speed to decrease to the target speed, thus completing the dynamic adjustment of the fan speed.

[0113] The following describes an environmentally friendly and energy-saving intelligent control system from the perspective of hardware processing. Please refer to [link / reference needed]. Figure 3 This is a schematic diagram of the structure of an environmentally friendly and energy-saving intelligent control system in an embodiment of this application.

[0114] It should be noted that, Figure 3 The structure of the environmentally friendly and energy-saving intelligent control system shown is merely an example and should not impose any limitations on the functionality and scope of use of the embodiments of the present invention.

[0115] like Figure 3As shown, an environmentally friendly and energy-saving intelligent control system includes a central processing unit (CPU) 301, which can perform various appropriate actions and processes according to programs stored in read-only memory (ROM) 302 or programs loaded from storage section 308 into random access memory (RAM) 303, such as executing the methods described in the above embodiments. The RAM 303 also stores various programs and data required for system operation. The CPU 301, ROM 302, and RAM 303 are interconnected via a bus 304. An input / output (I / O) interface 305 is also connected to the bus 304.

[0116] The following components are connected to I / O interface 305: input section 306 including audio input devices, push-button switches, etc.; output section 307 including a liquid crystal display (LCD) and audio output devices, indicator lights, etc.; storage section 308 including a hard disk, etc.; and communication section 309 including a network interface card such as a LAN (Local Area Network) card, modem, etc. Communication section 309 performs communication processing via a network such as the Internet. Drive 310 is also connected to I / O interface 305 as needed. Removable media 311, such as a disk, optical disk, magneto-optical disk, semiconductor memory, etc., are installed on drive 310 as needed so that computer programs read from them can be installed into storage section 308 as needed.

[0117] In particular, according to embodiments of the present invention, the processes described above with reference to the flowcharts can be implemented as computer software programs. For example, embodiments of the present invention include a computer program product comprising a computer program carried on a computer-readable medium, the computer program containing computer programs for performing the methods shown in the flowcharts. In such embodiments, the computer program can be downloaded and installed from a network via communication section 309, and / or installed from removable medium 311. When the computer program is executed by central processing unit (CPU) 301, it performs the various functions defined in the present invention.

[0118] It should be noted that specific examples of computer-readable storage media may include, but are not limited to: electrical connections having one or more wires, portable computer disks, hard disks, random access memory (RAM), read-only memory (ROM), erasable programmable read-only memory (EPROM), flash memory, optical fiber, portable compact disc read-only memory (CD-ROM), optical storage devices, magnetic storage devices, or any suitable combination thereof. In this invention, a computer-readable storage medium can be any tangible medium containing or storing a program that can be used by or in conjunction with an instruction execution system, apparatus, or device.

[0119] The flowcharts and block diagrams in the accompanying drawings illustrate the architecture, functionality, and operation of possible implementations of systems, methods, and computer program products according to various embodiments of the present invention. Each block in a flowchart or block diagram may represent a module, segment, or portion of code, which contains one or more executable instructions for implementing a specified logical function. It should also be noted that in some alternative implementations, the functions indicated in the blocks may occur in a different order than those shown in the drawings.

[0120] Specifically, the environmental protection and energy-saving intelligent management and control system of this embodiment includes a processor and a memory. The memory stores a computer program. When the computer program is executed by the processor, it implements the environmental protection and energy-saving intelligent management and control method provided in the above embodiment.

[0121] In another aspect, the present invention also provides a computer-readable storage medium, which may be included in the environmental protection and energy-saving intelligent management and control system described in the above embodiments; or it may exist independently and not assembled into the environmental protection and energy-saving intelligent management and control system. The storage medium carries one or more computer programs, which, when executed by a processor of the environmental protection and energy-saving intelligent management and control system, enable the system to implement the environmental protection and energy-saving intelligent management and control method based on IoT data encryption transmission provided in the above embodiments.

Claims

1. An environmentally friendly and energy-saving intelligent control method, characterized in that, The method includes: Acquire raw sensing data from the steel production site and preprocess the raw sensing data to obtain standardized structured data; The standardized structured data is subjected to time-series alignment and normalization to obtain a fused dataset; Extract the historical dust concentration sequence from the fused dataset, calculate the concentration change rate of the historical dust concentration sequence within a preset time window, and calculate the predicted dust concentration based on the concentration change rate and the dust concentration at the current moment. Use the predicted dust concentration as dust concentration change trend data. Based on the fused dataset and the soot concentration change trend data, multiple sets of candidate operating parameters are generated, and the expected energy consumption and expected soot emissions corresponding to each set of candidate operating parameters are calculated respectively. Select the target operating parameters from which the expected smoke and dust emissions are less than the preset emission limit, and take the set of target operating parameters with the smallest expected energy consumption value as the minimum energy consumption operating parameters of the dust removal equipment; Based on feature comparison of the device operating status data in the fused dataset, potential device fault status information is determined. By combining the dust concentration change trend data, the minimum energy consumption operating parameters, and the potential fault status information of the equipment, a dust removal equipment control command is generated, and the dust removal equipment is controlled to execute the dust removal equipment control command.

2. The method according to claim 1, characterized in that, The process of acquiring raw sensing data from the steel production site and preprocessing the raw sensing data to obtain standardized structured data includes: The raw sensing data is acquired by IoT sensors deployed at the steel production site at a preset acquisition frequency. The raw sensing data includes real-time dust concentration, equipment operating conditions, production line process parameters, and meteorological indicators. The raw sensing data is transmitted to the data acquisition gateway deployed on site. In the data acquisition gateway, the sliding window algorithm and the mean filtering algorithm are used to remove outliers and remove noise from the raw sensing data to obtain cleaned data. According to the preset data mapping template, the cleaned data is parsed and its format is converted to obtain the standardized structured data.

3. The method according to claim 1, characterized in that, The process of performing time-series alignment and normalization on the standardized structured data to obtain the fused dataset includes: Obtain heterogeneous data from different devices within the standardized structured data; Extract the sampling period attribute of the heterogeneous data, and perform time-series matching on the heterogeneous data based on the sampling period attribute to obtain aligned data; The aligned data is subjected to dimension elimination and normalization processing to obtain the fused dataset.

4. The method according to claim 1, characterized in that, The process of combining the dust concentration change trend data, the minimum energy consumption operating parameters, and the potential fault status information of the equipment to generate dust removal equipment control commands, and controlling the dust removal equipment to execute the dust removal equipment control commands, includes: Extract the fan operating frequency and valve opening parameters from the minimum energy consumption operating parameters; The dynamic upper limit threshold of the fan operating frequency is determined based on the potential fault status information of the equipment, and the dynamic lower limit threshold of the valve opening parameter is determined based on the dust concentration change trend data. The fan operating frequency is compared with the dynamic upper limit threshold, and the valve opening parameter is compared with the dynamic lower limit threshold. When the fan operating frequency is less than or equal to the dynamic upper limit threshold and the valve opening parameter is greater than or equal to the dynamic lower limit threshold, the verification is deemed successful, and a dust removal equipment control command containing the fan operating frequency and the valve opening parameter is generated. The dust removal equipment control command is converted into a control electrical signal, and the control electrical signal is sent to the frequency converter drive unit and the valve actuator. The frequency converter drive unit adjusts the fan speed of the dust removal equipment, and the valve actuator adjusts the air volume in the pipeline.

5. The method according to claim 4, characterized in that, After adjusting the fan speed of the dust removal equipment through the variable frequency drive unit and adjusting the duct air volume through the valve actuator, the method further includes: Obtain real-time dust concentration feedback data at the outlet of the dust removal equipment; Calculate the concentration difference between the real-time smoke and dust concentration feedback data and the preset emission limit; If the real-time dust concentration feedback data is greater than or equal to the preset emission limit, the fan speed is increased by a preset ratio to increase the dust removal air volume. If the real-time smoke and dust concentration feedback data is less than the preset emission limit and the concentration difference is greater than the preset margin, the fan speed will be reduced by a preset ratio to reduce power consumption.

6. The method according to claim 1, characterized in that, After the dust removal equipment is controlled to execute the dust removal equipment control command, the method further includes: Obtain real-time feedback data after the dust removal equipment executes the command; The fused dataset and the real-time feedback data are associated and stored to construct a historical running sample library; According to a preset time period, newly added field operating condition data is extracted from the historical operating sample database, and the actual concentration change rate and actual energy consumption value are calculated using the newly added field operating condition data. Calculate the deviation between the actual concentration change rate and the rate of change of the concentration change rate, and the energy consumption deviation between the actual energy consumption value and the expected energy consumption value; Based on the rate of change deviation and the energy consumption deviation, the calculation weight of the concentration change rate and the evaluation coefficient of the expected energy consumption value are updated respectively.

7. The method according to claim 6, characterized in that, After updating the calculation weight of the concentration change rate and the evaluation coefficient of the expected energy consumption value based on the change rate deviation and the energy consumption deviation, respectively, the method further includes: Calculate the average value of the rate of change deviation and energy consumption deviation within the preset evaluation period; When the average value is greater than a preset error threshold, extract all historical data from the historical running sample library; Using minimizing the rate of change deviation and the energy consumption deviation as optimization conditions, the full historical data is fitted to obtain global calculation weights and global evaluation coefficients. Replace the current calculated weights and evaluation coefficients with the global calculated weights and global evaluation coefficients, respectively.

8. An environmentally friendly and energy-saving intelligent control system, characterized in that, The environmental protection and energy-saving intelligent management and control system includes: one or more processors and a memory; the memory is coupled to the one or more processors, the memory is used to store computer program code, the computer program code includes computer instructions, and the one or more processors call the computer instructions to cause the environmental protection and energy-saving intelligent management and control system to perform the method as described in any one of claims 1-7.

9. A computer-readable storage medium comprising instructions, characterized in that, When the instruction is executed on the environmental protection and energy-saving intelligent management and control system, the environmental protection and energy-saving intelligent management and control system performs the method as described in any one of claims 1-7.

10. A computer program product, characterized in that, When the computer program product is run on the environmental protection and energy-saving intelligent control system, the environmental protection and energy-saving intelligent control system performs the method as described in any one of claims 1-7.