Steel bar processing and assembling method and system suitable for steel-concrete composite bridge tower segment

By using BIM digital modeling and CNC bending adaptive compensation technology, high-precision factory prefabrication and assembly of steel-concrete bridge tower segments have been achieved, solving the problems of poor precision, long construction period and major safety hazards in traditional construction, and improving construction efficiency and quality.

CN123158757APending Publication Date: 2026-11-24CHINA RAILWAY BAOQIAO (ZHOUSHAN) CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611427018.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-15
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Traditional steel-concrete bridge tower construction suffers from poor precision, long construction period, and significant safety and corrosion risks, and lacks mature technology for factory prefabrication of complex spatial curved steel bars.

Method used

By adopting BIM digital modeling and combining it with CNC bending adaptive compensation technology, high-precision prefabrication of steel bars and positioning of steel frame are achieved in the factory. The steel bars are automatically cut and spatial curve processing is completed through a three-dimensional CNC bending processing integrated machine and U-shaped buckle fixing, and pre-assembly and testing are carried out in the factory.

Benefits of technology

It improved the precision of steel bar forming, reduced on-site high-altitude open-air operations, reduced the risk of corrosion, shortened the construction cycle, ensured quality and safety, and reduced overall costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123158757A_ABST
    Figure CN123158757A_ABST
Patent Text Reader

Abstract

This invention discloses a method and system for processing and assembling reinforcing bars in steel-concrete composite bridge tower segments. The method includes: establishing a 3D BIM model of the steel-concrete composite bridge tower segment; extracting the 3D coordinates, bending angles, and spatial curve parameters of the reinforcing bars; optimizing the segmentation based on the length of the raw material to improve raw material utilization; assigning a unique number to each reinforcing bar and generating CNC processing instructions; importing the instructions into a 3D CNC bending machine to complete automated material cutting and spatial bending of the reinforcing bars in the factory; and identifying the processed reinforcing bars according to their numbers; erecting a horizontal assembly platform; precisely positioning the steel frame; assembling the reinforcing bars using U-shaped clips after marking lines; and monitoring the frame outline dimensions in real time during assembly; pre-assembling the reinforcing bar components of adjacent segments in the factory; completing overall inspection; and, after the dimensions meet the standards, transferring the reinforcing bar components and the steel frame as a whole to the bridge site for hoisting and installation. This provides reliable technical support for the high-precision prefabrication of reinforcing bars in steel-concrete composite bridge tower segments in the factory.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of prefabricated construction technology for bridge engineering, and more specifically, relates to a method and system for processing and assembling steel bars for steel-concrete composite bridge tower segments. Background Technology

[0002] As my country's comprehensive national strength steadily improves, bridges, as important carriers of people's livelihood and economic development, are constantly making breakthroughs in terms of construction scale, functionality, landscape effect, construction technology, and green and low-carbon development. Long-span bridges spanning rivers and seas consist of bridge towers, bridge decks, and cables. The bridge towers are responsible for transmitting the load of the bridge deck and supporting the bridge's super-large span of over two kilometers, making their construction quality and craftsmanship crucial.

[0003] Traditional steel-concrete composite bridge towers are constructed on-site at the sea bridge site, with materials prepared in a processing shed on-site and individual rebars hoisted to the tower column for binding. The dense arrangement and complex spatial connections of the rebars in the sea-crossing tower columns, along with stringent requirements for rebar spacing, connection accuracy, and protective layer thickness, present numerous drawbacks to this construction method. The harsh open-air high-altitude working environment at sea requires a large workforce and poses significant safety risks; the rebars are susceptible to corrosion from long-term salt spray, and on-site rust removal is difficult to meet standards, reducing structural durability; traditional equipment can only process straight and planar curved rebars, and complex spatial curves rely on manual correction, resulting in large deviations in forming accuracy; a single tower column section contains over 10,000 rebars, requiring 20 people and four days to assemble, severely hindering construction progress; on-site environmental and site limitations make quality control prone to loopholes, resulting in high overall project costs, long construction periods, and multiple safety and quality hazards.

[0004] The industry has proposed a renovation plan that integrates steel sections and reinforcing bars for prefabrication in the factory and hoisting them as a whole at the bridge site. However, there are no precedents for similar engineering manufacturing in China for how to firmly assemble a large number of spatial curved steel bars into the steel frame in the factory. There is a lack of mature process references, and the relevant technical difficulties need to be overcome. Summary of the Invention

[0005] This invention aims to solve the problems of poor on-site construction accuracy, long construction period, and high risk of corrosion in traditional steel-concrete bridge towers. By relying on BIM digitization, CNC bending adaptive compensation, and in-factory assembly and pre-assembly processes, it achieves high-precision prefabrication of irregular-shaped steel bars and forms an integrated segmental hoisting system for steel sections and reinforcing bars.

[0006] To address the aforementioned deficiencies or improvement needs of existing technologies, as a first aspect of this invention, the present invention provides a method for processing and assembling reinforcing bars for steel-concrete composite bridge tower segments, comprising: S1. Establish a 3D BIM model of the steel-concrete composite bridge tower segment. Based on the spatial geometry of the bridge tower segment, extract the 3D coordinate data, bending angle, and spatial curve parameters of each steel bar. Divide the steel bars into blocks according to the length of the raw materials to ensure that the raw material utilization rate during steel bar cutting reaches a preset threshold. Give each steel bar a unique number based on the extracted spatial parameters and generate CNC machining instructions. S2. Import the generated CNC machining instructions into a three-dimensional CNC bending machine to automatically cut and bend the steel bars in the factory workshop; after processing, mark each steel bar to ensure that the steel bar corresponds one-to-one with the number in the BIM model; S3. Erect a horizontal assembly platform in the factory, hoist the steel frame onto the platform and adjust it to the designed position; use the frame position control system to position the steel frame; mark the rebar installation positions on the steel frame according to the designed spacing, and install the processed rebars onto the steel frame in sequence; use U-shaped clips to fix the rebars to the steel frame; use measuring instruments to monitor the geometric dimensions of the rebar frame in real time during the assembly process; S4. Pre-assemble the steel reinforcement components of adjacent segments in the factory; after the pre-assembly is completed, conduct an overall inspection to confirm that all dimensional deviations meet the design requirements, and then transport the steel reinforcement components and the steel frame as a whole unit to the bridge site for hoisting and installation.

[0007] Furthermore, in step S1, the steel reinforcement is divided into blocks, specifically including: The vertical main reinforcement bars are divided into a first preset number of specification lengths, and the horizontal reinforcement bars are divided into a second preset number of specification lengths. During the division, the length of the original reinforcement bar material is used as a constraint condition. A one-dimensional material cutting optimization model is established with the objective function of minimizing the total length of surplus material. Solving the one-dimensional material cutting optimization model yields material cutting combination schemes for each specification length, ensuring that the sum of the lengths of each specification length in each material cutting combination scheme is less than or equal to the original length of the reinforcement bar material, and that the surplus length of a single reinforcement bar material is less than a preset surplus material threshold. During the solution process, priority is given to optimizing the material cutting combination of the vertical main reinforcement bars, ensuring that the utilization rate of the original material for the vertical main reinforcement bars is higher than that for the horizontal reinforcement bars.

[0008] Furthermore, in S2, the spatial curve bending process specifically includes: Based on the spatial curve parameters in the CNC machining instructions, the multi-axis robotic arm of the three-dimensional CNC bending machine is controlled to perform linkage bending. During the bending process, the springback data of the steel bar is collected in real time by the sensor set at the end of the robotic arm, and the springback data is fed back to the control system for compensation and correction, so that the spatial curve of the formed steel bar matches the design curve in the BIM model.

[0009] Furthermore, the step of feeding back the rebound data to the control system for compensation and correction specifically includes: Obtain the average yield strength of the incoming sample from the current batch of reinforcing steel. and average elastic modulus Discretize the design space curves extracted from the BIM model into The nth bend node, for the nth... Each corner node, according to the formula Calculate the initial cornering compensation angle The order was then sent to a CNC bending machine to process the first steel bar. The diameter of the reinforcing bar. For the first The design bending radius of each corner node To design the bending angle, ; After the first rebar is processed, the actual spatial coordinates of each bend node are obtained. The measured spatial curve is then compared node by node with the design spatial curve. The springback deviation at each bend node is decomposed into the angular springback amount within the bend surface. and torsional springback around the axis of the reinforcing bar ; Using the first angular rebound at each bend node According to the formula Back-calculate the material correction factor corresponding to this node. and will The material correction coefficient for each bend node is based on the formula. The average value is used to obtain the comprehensive correction factor for this batch of steel bars. ; Based on the measured angular rebound of each preceding bend node, the cumulative propagation deviation of the preceding bend node to the spatial positioning reference of the subsequent bend node is calculated. The comprehensive correction coefficient and the cumulative propagation deviation are substituted into the compensation calculation of the subsequent bend node to calculate and update the over-bending compensation angle. At the same time, the rotational feed angle of the rebar around its own axis is corrected according to the torsional rebound. In subsequent batch processing, after each rebar is processed, the process of comparing the measured spatial curve, back-calculating the material correction coefficient, calculating the cumulative propagation deviation, and updating the compensation parameters is repeated. The comprehensive correction coefficient and the compensation parameters of each node are continuously updated iteratively using the latest measured data to achieve piece-by-piece adaptive convergence of the rebar rebound compensation for this batch.

[0010] Furthermore, the calculation of the cumulative propagation deviation of the spatial positioning reference of the preceding bends to the subsequent bends, based on the measured angular rebound of each preceding bend node, specifically includes: No. angular rebound at each bend node Make the first The cumulative offset caused by the spatial position of each bend node is calculated according to the formula. Calculation, where , For the first From the first bend node to the first The cumulative arc length of the first bend node along the reinforcing bar axis, the first The total cumulative offset of each bend node is calculated according to the formula. Calculate the vector sum of the propagation deviations of all preceding bend nodes; Simultaneously, the step of substituting the comprehensive correction coefficient and cumulative propagation deviation into the compensation calculation of subsequent corner nodes to calculate and update the cornering compensation angle specifically includes: the first... The updated cornering compensation angle for each bend node is based on the formula. Calculation, where For the first The remaining length from the corner node to the end of the rebar. This is the angle correction amount used to offset the cumulative offset from the preceding sequence.

[0011] Furthermore, in step S3, the steel frame is positioned using a frame position control system, specifically including: Multiple adjustable three-dimensional positioning supports are set on a horizontal assembly platform, and the bottom and sides of the steel frame are abutted against the three-dimensional positioning supports. The actual coordinates of the preset control points on the steel frame are obtained by a total station, and the actual coordinates are compared with the theoretical coordinates in the BIM model. Based on the comparison results, the three-dimensional positioning supports are driven to adjust their spatial position until the spatial posture of the steel frame meets the preset positioning accuracy requirements.

[0012] Furthermore, in step S3, U-shaped clips are used to fix the reinforcing bars to the steel frame, specifically including: Weld connecting plates at the pre-set rebar attachment points on the steel frame, and attach the processed rebars to the surface of the connecting plates; pass U-shaped clips across the rebars and fasten them into the pre-drilled holes on the connecting plates, and apply pre-tightening force to the U-shaped clips by tightening nuts, so that the rebars and the steel frame form a detachable rigid connection.

[0013] Furthermore, in step S4, the pre-assembly of adjacent steel reinforcement components in the factory specifically includes: First, feature point reinforcement bars at the interface of adjacent segments are extracted from the BIM model. These feature point reinforcement bars include reinforcement bars at the inflection points of the tower columns and reinforcement bars at the center of the segments. The feature point reinforcement bars of the previous segment are matched and connected with those of the next segment to verify the spatial position accuracy and connection matching degree. After the verification is qualified, the remaining reinforcement bars are assembled according to the feature point reinforcement bars as the reference, following the order of vertical main reinforcement bars first and then horizontal reinforcement bars, until the pre-assembly of the reinforcement components of the entire segment is completed.

[0014] As a second aspect of the present invention, a steel reinforcement processing and assembly system suitable for steel-concrete composite bridge tower segments is also provided, comprising: The 3D modeling and instruction generation unit is used to create a 3D BIM model of the steel-concrete composite bridge tower segment. Based on the spatial geometry of the bridge tower segment, it extracts the 3D coordinate data, bending angle, and spatial curve parameters of each steel bar. Based on the length of the original steel bar, it divides the steel bars into blocks to ensure that the utilization rate of the original material during steel bar cutting reaches a preset threshold. Based on the extracted spatial parameters, it assigns a unique number to each steel bar and generates CNC machining instructions. The CNC blanking and bending processing unit is used to import the generated CNC machining instructions into the three-dimensional CNC bending processing integrated machine, and to automatically blank and bend the steel bars in the factory workshop; after processing, each steel bar is marked to ensure that the steel bar corresponds one-to-one with the number in the BIM model; The steel frame assembly and rebar installation unit is used to set up a horizontal assembly platform in the factory, hoist the steel frame onto the platform and adjust it to the designed position; the steel frame is positioned using a frame position control system; the rebar installation positions are marked on the steel frame according to the designed spacing, and the processed rebars are installed onto the steel frame in sequence; U-shaped clips are used to fix the rebars to the steel frame; during the assembly process, measuring instruments are used to monitor the geometric dimensions of the rebar frame in real time. The segmental pre-assembly and overall inspection unit is used to pre-assemble the steel reinforcement components of adjacent segments in the factory. After the pre-assembly is completed, an overall inspection is carried out to confirm that the various dimensional deviations meet the design requirements. Then, the steel reinforcement components and the steel frame are transported as an overall unit to the bridge site for hoisting and installation.

[0015] As a third aspect of the invention, a computer-readable storage medium is also provided, on which a computer program is stored, which is executed by a processor, according to any one of the claims, a method for processing and assembling reinforcing bars applicable to steel-concrete composite bridge tower segments.

[0016] In summary, compared with the prior art, the above-described technical solutions conceived by this invention can achieve the following beneficial effects: 1. The present invention provides a method for processing and assembling reinforcing bars in steel-concrete composite bridge tower segments. By constructing a 3D BIM model of the bridge tower to extract spatial parameters of the reinforcing bars, and combining this with a material optimization model to divide the reinforcing bars into segments and generate CNC machining instructions, the method can fully utilize raw reinforcing bars and reduce waste. Each reinforcing bar is assigned an independent number based on the model, establishing a correspondence between the design and the processed components. A unified dimensional reference standard is maintained throughout the process, avoiding dimensional deviations caused by data mismatches at multiple stages. Simultaneously, digital pre-planning eliminates the need for manual on-site layout, reducing on-site processing control pressure from the source and adapting to the early design requirements of densely curved reinforcing bars.

[0017] 2. The steel reinforcement processing and assembling method for steel-concrete composite bridge tower segments of the present invention completes the forming and processing of steel reinforcement through a three-dimensional numerical control bending and processing integrated machine combined with a rebound self-adaptive compensation algorithm. The multi-axis linkage of the equipment realizes the integrated bending of complex spatial curve steel reinforcement, and the compensation parameters are iteratively updated in combination with the measured rebound data to offset the angular and torsional deformation generated during the bending of the steel reinforcement. The processed steel reinforcement is equipped with exclusive identification numbers, which can be quickly sorted and transferred, replacing the traditional on-site manual trimming operation mode for steel reinforcement, stabilizing the forming accuracy of irregular steel reinforcement, avoiding dimensional errors caused by manual correction after planar processing, and meeting the high-precision forming requirements of bridge tower steel reinforcement.

[0018] 3. The steel reinforcement processing and assembling method for steel-concrete composite bridge tower segments of the present invention positions the section steel framework through a factory horizontal assembly platform, uses U-shaped buckles to fix the steel reinforcement and monitors the contour size of the framework in real time, completes the pre-assembly inspection of segment steel reinforcement components in the factory, and transfers them to the bridge site for hoisting after the overall qualification. All steel reinforcement assembly work is transferred to the indoor factory to reduce the amount of open-air high-altitude operations in the sea area, avoid the risk of steel reinforcement salt spray corrosion, eliminate the need for a large number of personnel to tie on site for a long time for a single segment, shorten the on-site construction period, and at the same time, the pre-assembly in the factory can verify the butt joint accuracy of the segments in advance, reducing the hidden danger of on-site splicing quality. Description of the Drawings

[0019] Figure 1 is a flow chart of a steel reinforcement processing and assembling method suitable for steel-concrete composite bridge tower segments according to an embodiment of the present invention; Figure 2 is a schematic diagram of steel reinforcement of different lengths according to an embodiment of the present invention; Figure 3 is a schematic diagram of a horizontal assembly platform according to an embodiment of the present invention; Figure 4 is a schematic diagram of a steel reinforcement limit framework according to an embodiment of the present invention; Figure 5 is a schematic diagram of a U-shaped buckle according to an embodiment of the present invention; Figure 6 is a schematic diagram of segment steel reinforcement according to an embodiment of the present invention; Figure 7 is a schematic diagram of segment division according to an embodiment of the present invention; Figure 8 is a schematic diagram of steel reinforcement pre-assembly according to an embodiment of the present invention; Figure 9 is a schematic diagram of steel reinforcement inspection according to an embodiment of the present invention; Figure 10 is a schematic diagram of a system unit according to an embodiment of the present invention.

[0020] In all the drawings, the same reference numerals denote the same technical features, specifically: 1-steel reinforcement, 2-section steel framework. Detailed Embodiments

[0021] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the invention. Furthermore, the technical features involved in the various embodiments of this invention described below can be combined with each other as long as they do not conflict with each other.

[0022] Example 1 Please refer to Figure 1 This embodiment 1 provides a method for processing and assembling reinforcing bars for steel-concrete composite bridge tower segments, including: S1. Establish a 3D BIM model of the steel-concrete composite bridge tower segment. Based on the spatial geometry of the bridge tower segment, extract the 3D coordinate data, bending angle, and spatial curve parameters of each steel bar. Divide the steel bars into blocks according to the length of the raw materials to ensure that the raw material utilization rate during steel bar cutting reaches a preset threshold. Give each steel bar a unique number based on the extracted spatial parameters and generate CNC machining instructions. S2. Import the generated CNC machining instructions into a three-dimensional CNC bending machine to automatically cut and bend the steel bars in the factory workshop; after processing, mark each steel bar to ensure that the steel bar corresponds one-to-one with the number in the BIM model; S3. Erect a horizontal assembly platform in the factory, hoist the steel frame onto the platform and adjust it to the designed position; use the frame position control system to position the steel frame; mark the rebar installation positions on the steel frame according to the designed spacing, and install the processed rebars onto the steel frame in sequence; use U-shaped clips to fix the rebars to the steel frame; use measuring instruments to monitor the geometric dimensions of the rebar frame in real time during the assembly process; S4. Pre-assemble the steel reinforcement components of adjacent segments in the factory; after the pre-assembly is completed, conduct an overall inspection to confirm that all dimensional deviations meet the design requirements, and then transport the steel reinforcement components and the steel frame as a whole unit to the bridge site for hoisting and installation.

[0023] Please refer to Figures 2 to 9 This embodiment 1 further elaborates on the above steps.

[0024] (1) 3D modeling and instruction generation Based on the design drawings of the bridge tower segments, a 3D BIM model including the steel frame and various reinforcing steel components is established. After the model is established, the reinforcing steel elements are traversed, and the 3D coordinate data, bending angles, and spatial curve parameters of each reinforcing steel are extracted according to the spatial geometry of the bridge tower segments.

[0025] For reinforcing bars containing bends or spatial curves, the three-dimensional coordinates, bending angle, bending radius, and arc length of each bending point are extracted. During the extraction of spatial parameters, each reinforcing bar is uniquely numbered according to a coding rule that includes a segment identification code, component type code, and sequential serial number. The extracted spatial parameters and the unique number together constitute the processing file of the reinforcing bar and are stored.

[0026] Obtain the standard length of the incoming steel reinforcement materials, and calculate the required cutting length of all vertical main reinforcement and horizontal reinforcement for this bridge tower segment based on the processing records. Divide the vertical main reinforcement into a first preset quantity of specification lengths according to the design length requirements, and divide the horizontal reinforcement into a second preset quantity of specification lengths. When dividing the specifications, adjust the theoretical lengths by taking into account the required lap length or mechanical connection joint length of the reinforcement to obtain the actual cutting lengths.

[0027] Using the standard length of the original steel bar as a constraint, a one-dimensional cutting optimization model is established with the objective function of minimizing the total length of the surplus material. This model ensures that the sum of the lengths of each specification of steel bar included in each cutting combination scheme is less than or equal to the length of the original steel bar, and that the length of the surplus material after cutting a single original steel bar is less than a preset surplus material threshold. At the same time, the total number of steel bars of each specification cut by all cutting combination schemes meets the design requirements.

[0028] The one-dimensional material cutting optimization model is solved using integer linear programming or heuristic algorithms, prioritizing the optimization of vertical main reinforcement bars. Since the vertical main reinforcement bars bear the main load in the bridge tower segment's load-bearing structure and are relatively long, prioritizing their optimization reduces the difficulty of handling surplus material from large-diameter reinforcement bars and controls overall material costs, thus resulting in a higher material utilization rate for vertical main reinforcement bars compared to horizontal reinforcement bars.

[0029] After the cutting scheme for the vertical main reinforcement is determined, the horizontal reinforcement is combined and optimized by utilizing the remaining material length space or by allocating the material separately. After the solution is completed, the cutting combination scheme containing the number of material pieces, cutting sequence and leftover material information is output.

[0030] Based on the material cutting combination scheme and rebar processing file, data mapping and code compilation are performed. For each rebar to be processed, its unique number, cutting length, spatial coordinates of each bending point, bending angle and bending radius parameters are converted into CNC machining code according to the CNC machine tool communication protocol.

[0031] When generating code, the design coordinate system is converted into the machine tool machining coordinate system by combining the clamping and positioning reference of the steel bar on the bending machine. This generates a set of CNC machining instructions that includes blanking and cutting instructions and three-dimensional bending and forming instructions. The instruction set is sorted by steel bar number and transmitted to the control device of the CNC bending and machining integrated machine to drive the machine tool to perform automated machining.

[0032] (2) CNC blanking and bending processing The generated CNC machining instructions are imported into a 3D CNC bending machine, enabling automated blanking and spatial curve bending of steel bars within the factory workshop. During the bending process, the multi-axis robotic arm of the 3D CNC bending machine is controlled to perform linked bending based on the spatial curve parameters in the CNC machining instructions. Sensors at the end of the robotic arm collect the springback data of the steel bars in real time, and the springback data is fed back to the control device for compensation and correction, ensuring that the spatial curve of the formed steel bar matches the design curve in the BIM model.

[0033] When performing springback compensation correction, the average yield strength of the incoming sampled steel bars is obtained from the current batch of steel bars. and average elastic modulus Discretize the design space curves extracted from the BIM model into The first corner node. For the first... Each corner node, according to the formula Calculate the initial cornering compensation angle The order was then sent to a CNC bending machine to process the first steel bar. The diameter of the reinforcing bar. For the first The design bending radius of each corner node To design the bending angle, .

[0034] After the first rebar is processed, the actual spatial coordinates of each bend node are obtained using measuring equipment. The measured spatial curve is then compared node by node with the design spatial curve. The springback deviation at each bend node is decomposed into the angular springback amount within the bend surface. and torsional springback around the axis of the reinforcing bar .

[0035] Using the first angular rebound at each bend node According to the formula Back-calculate the material correction factor corresponding to this node. and will The material correction coefficient for each bend node is based on the formula. The average value is used to obtain the comprehensive correction factor for this batch of steel bars. .

[0036] Because the springback of the preceding bend will cause the spatial positioning reference of the subsequent bend to shift when the steel bar is continuously bent, it is necessary to calculate the cumulative propagation deviation of the spatial positioning reference of the preceding bend to the subsequent bend based on the measured springback of the preceding bend nodes.

[0037] No. angular rebound at each bend node Make the first The cumulative offset caused by the spatial position of each bend node is calculated according to the formula. Calculation, where , For the first From the first bend node to the first The cumulative arc length of each bend node along the reinforcing bar axis. The total cumulative offset of each bend node is calculated according to the formula. Calculate the vector sum of the propagation deviations of all preceding bend nodes.

[0038] Substituting the comprehensive correction factor and cumulative propagation deviation into the compensation calculation of subsequent corner nodes, the first... The updated cornering compensation angle for each bend node is based on the formula. Calculation, where For the first The remaining length from the corner node to the end of the rebar. The angle correction is used to offset the cumulative offset of the preceding step, and the rotational feed angle of the reinforcing bar about its own axis is corrected according to the torsional springback.

[0039] In subsequent batch processing, after each steel bar is processed, the process of comparing the measured spatial curve, back-calculating the material correction coefficient, calculating the cumulative propagation deviation, and updating the compensation parameters is repeated. The comprehensive correction coefficient and the compensation parameters of each node are continuously updated using the latest measured data to achieve piece-by-piece adaptive convergence of the springback compensation of this batch of steel bars.

[0040] After the reinforcing bars are fabricated, each bar is labeled to ensure a one-to-one correspondence between the bar number and the number in the BIM model. A QR code containing a unique number is applied to the end or side of the bar using either a binding label or spray painting. This unique number matches the number in the digital fabrication file established in step S1. Construction personnel can scan the QR code with a mobile terminal to obtain the design parameters, fabrication batch, and usage location information of the reinforcing bar. This facilitates rapid identification and comparison during transportation, stacking, and on-site assembly, preventing the misuse or mixing of reinforcing bars.

[0041] (3) Frame assembly and steel reinforcement installation A horizontal assembly platform is erected within the factory. This platform utilizes welded steel sections to form a frame structure, and leveling pads are installed on the platform surface to ensure the flatness of the supporting surface. The steel frame is then hoisted onto the horizontal assembly platform and initially adjusted to the designed position. Subsequently, a frame position control system is used to precisely position the steel frame.

[0042] The frame positioning control system includes multiple adjustable three-dimensional positioning supports distributed on a horizontal assembly platform, spaced apart longitudinally and laterally along the platform. Each three-dimensional positioning support includes a base, a horizontal slide, and a vertical lifting platform. The horizontal slide is driven by a lead screw to achieve horizontal displacement adjustment, while the vertical lifting platform is driven by a hydraulic cylinder or an electric push rod to achieve vertical displacement adjustment. The bottom and sides of the steel frame are brought into contact with the abutment surfaces of the three-dimensional positioning supports, allowing the weight and lateral thrust of the steel frame to be transferred to each positioning support.

[0043] Several pre-set control points are established on the top and sides of the steel frame. The actual three-dimensional coordinates of each control point are acquired using a total station, and the data is transmitted to the control device. The control device compares the actual coordinates with the corresponding theoretical coordinates in the BIM model and calculates the coordinate deviation value of each control point. Based on the coordinate deviation value, the control device sends adjustment commands to the corresponding three-dimensional positioning supports, driving the horizontal slide and vertical lifting platform to adjust their spatial positions. During the adjustment process, the total station continuously tracks and measures the coordinate changes of each control point until the spatial posture of the steel frame meets the pre-set positioning accuracy requirements, at which point the current position of each three-dimensional positioning support is locked.

[0044] After the steel frame is positioned, according to the reinforcement layout parameters in the BIM model, mark the reinforcement installation positions on the flange and web surfaces of the steel frame at the designed spacing. These marks include the installation baselines for the vertical main reinforcement and the horizontal reinforcement. The fabricated reinforcement bars are then hoisted to their corresponding positions on the steel frame according to their unique numbers from step S1, with the vertical main reinforcement installed first, followed by the horizontal reinforcement. The vertical main reinforcement bars are placed vertically along the height of the steel frame, while the horizontal reinforcement bars are placed horizontally along the transverse or longitudinal direction of the steel frame, aligning each reinforcement bar with its corresponding mark.

[0045] A connecting plate is welded to the pre-set attachment points of the reinforcing bars on the steel frame. The surface of the connecting plate is in contact with the flange or web surface of the steel frame, and pre-drilled holes are made on the connecting plate. The processed reinforcing bars are attached to the surface of the connecting plate, and U-shaped clips are used to cross over the outside of the reinforcing bars and snap into the pre-drilled holes on the connecting plate. After the two ends of the U-shaped clips pass through the pre-drilled holes, a pre-tightening force is applied to the U-shaped clips by tightening nuts, so that the reinforcing bars and the steel frame form a detachable rigid connection. The pre-tightening force of the tightening nuts is determined according to the diameter of the reinforcing bars and the load-bearing capacity of the connecting plate to ensure that the reinforcing bars do not loosen or slip during subsequent assembly and transportation. For reinforcing bars of different diameters, U-shaped clips of corresponding specifications are selected so that the inner radius of the U-shaped clip matches the outer diameter of the reinforcing bars.

[0046] During assembly, measuring instruments are installed on the outside of the reinforcing steel cage to monitor its geometric dimensions in real time. These instruments include a total station and a laser scanner. The total station monitors the coordinate deviations of key control points on the reinforcing steel cage, while the laser scanner acquires point cloud data of the cage's surface. The real-time point cloud data is compared with the design outline in the BIM model. When a localized area's reinforcing steel position deviation exceeds the allowable range, installation in that area is paused. Installation continues after adjusting the tightness of the U-shaped clips or readjusting the rebar's positioning until the overall geometric dimensions of the reinforcing steel cage meet the design requirements.

[0047] (4) Segment pre-assembly and overall testing Pre-assembly jigs are erected in the factory. The structure of the pre-assembly jig is similar to a horizontal assembly platform, but it must be set up according to the design axis orientation of the bridge tower segments so that the steel reinforcement components of adjacent segments can simulate the actual spatial relationship on site during pre-assembly. The assembled steel reinforcement components of adjacent segments are then sequentially hoisted onto the pre-assembly jig, ensuring that the bottom surface of the previous segment is vertically aligned with the top surface of the next segment.

[0048] During pre-assembly, the feature point reinforcement at the interface between adjacent segments is first extracted from the BIM model. This feature point reinforcement includes reinforcement at the tower column inflection points and reinforcement at the segment center. The tower column inflection point reinforcement is located at the point where the bridge tower cross-section profile changes direction, while the segment center reinforcement is located near the geometric center of the segment's cross-section.

[0049] The feature point reinforcement bars of the previous segment are matched and connected with those of the next segment. During the connection process, a total station is used to measure the three-dimensional coordinates of the ends of the feature point reinforcement bars of the upper and lower segments. The measured coordinates are compared with the theoretical coordinates in the BIM model to verify the spatial position accuracy and connection matching degree. If the connection deviation exceeds the allowable range, the U-shaped clips at the corresponding positions are loosened and adjusted, the reinforcement bar positions are readjusted, and then tightened again until the connection deviation of the feature point reinforcement bars meets the design requirements.

[0050] After the characteristic point reinforcement is verified as qualified, the remaining reinforcement is assembled using the characteristic point reinforcement as a reference, following the order of vertical main reinforcement first and then horizontal reinforcement. The vertical main reinforcement is joined using lap splices or mechanical connection sleeves, connecting the lower end of the previous segment's vertical main reinforcement to the upper end of the next segment's vertical main reinforcement. For vertical main reinforcement using mechanical connection sleeves, the sleeve is first screwed into the threaded section at the end of the previous segment's vertical main reinforcement. After the upper and lower segments are joined, the sleeve is unscrewed from the threaded section and placed across the connection point of the two reinforcements. The specified torque is then applied using a torque wrench to tighten the connection.

[0051] Horizontal reinforcing bars are joined by tying, with tie wire used to secure them within the lap joint area between upper and lower horizontal reinforcing bar segments. During assembly, construction personnel check each reinforcing bar according to its unique number in step S1 to ensure that each bar is installed in the position specified in the design.

[0052] After the pre-assembly of the entire segment of reinforcing steel components is completed, an overall inspection is conducted. A 3D laser scanner is installed on the outside of the reinforcing steel components to scan their overall outline and obtain point cloud data of their surface. The point cloud data is imported into the BIM model and compared with the design model to check whether parameters such as the cross-sectional dimensions of the reinforcing steel components, the spacing of the main reinforcement bars, the thickness of the protective layer, and the butt joint deviation at the segment interfaces meet the design requirements.

[0053] Simultaneously, a total station was used to measure the coordinates of key control points at the top and bottom of the reinforcing steel components to verify the overall axial deviation and verticality deviation of the components. If the test results met the design requirements, the pre-assembly was confirmed as qualified, and the reinforcing steel components and the steel frame were disassembled from the pre-assembly jig as a whole unit and transported to the bridge site for hoisting and installation. If any deviation in the test results exceeded the allowable range, the deviation area was locally adjusted and retested until all dimensional deviations met the design requirements.

[0054] Example 2 Please refer to Figure 10 This embodiment 2 provides a steel reinforcement processing and assembly system suitable for steel-concrete composite bridge tower segments, including: The 3D modeling and instruction generation unit is used to create a 3D BIM model of the steel-concrete composite bridge tower segment. Based on the spatial geometry of the bridge tower segment, it extracts the 3D coordinate data, bending angle, and spatial curve parameters of each steel bar. Based on the length of the original steel bar, it divides the steel bars into blocks to ensure that the utilization rate of the original material during steel bar cutting reaches a preset threshold. Based on the extracted spatial parameters, it assigns a unique number to each steel bar and generates CNC machining instructions. The CNC blanking and bending processing unit is used to import the generated CNC machining instructions into the three-dimensional CNC bending processing integrated machine, and to automatically blank and bend the steel bars in the factory workshop; after processing, each steel bar is marked to ensure that the steel bar corresponds one-to-one with the number in the BIM model; The steel frame assembly and rebar installation unit is used to set up a horizontal assembly platform in the factory, hoist the steel frame onto the platform and adjust it to the designed position; the steel frame is positioned using a frame position control system; the rebar installation positions are marked on the steel frame according to the designed spacing, and the processed rebars are installed onto the steel frame in sequence; U-shaped clips are used to fix the rebars to the steel frame; during the assembly process, measuring instruments are used to monitor the geometric dimensions of the rebar frame in real time. The segmental pre-assembly and overall inspection unit is used to pre-assemble the steel reinforcement components of adjacent segments in the factory. After the pre-assembly is completed, an overall inspection is carried out to confirm that the various dimensional deviations meet the design requirements. Then, the steel reinforcement components and the steel frame are transported as an overall unit to the bridge site for hoisting and installation.

[0055] Example 3 This embodiment 3 also provides a computer-readable storage medium storing a computer program. When the computer program is executed by a processor, it can implement any step of a method for processing and assembling steel bars for steel-concrete composite bridge tower segments.

[0056] The computer-readable storage medium may include various media capable of storing program code, such as USB flash drives, portable hard drives, read-only memory (ROM), random access memory (RAM), magnetic disks, or optical disks.

[0057] For a description of the computer-readable storage medium provided in this application, please refer to the above method embodiments; further details will not be repeated here.

[0058] Those skilled in the art will readily understand that the above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.

Claims

1. A method for processing and assembling reinforcing bars for steel-concrete composite bridge tower segments, characterized in that, include: S1. Establish a 3D BIM model of the steel-concrete composite bridge tower segment. Based on the spatial geometry of the bridge tower segment, extract the 3D coordinate data, bending angle, and spatial curve parameters of each steel bar. Divide the steel bars into blocks according to the length of the raw materials to ensure that the raw material utilization rate during steel bar cutting reaches a preset threshold. Give each steel bar a unique number based on the extracted spatial parameters and generate CNC machining instructions. S2. Import the generated CNC machining instructions into a three-dimensional CNC bending machine to automatically cut and bend the steel bars in the factory workshop; after processing, mark each steel bar to ensure that the steel bar corresponds one-to-one with the number in the BIM model; S3. Erect a horizontal assembly platform in the factory, hoist the steel frame onto the platform and adjust it to the designed position; use the frame position control system to position the steel frame; mark the rebar installation positions on the steel frame according to the designed spacing, and install the processed rebars onto the steel frame in sequence; use U-shaped clips to fix the rebars to the steel frame; use measuring instruments to monitor the geometric dimensions of the rebar frame in real time during the assembly process; S4. Pre-assemble the steel reinforcement components of adjacent segments in the factory; after the pre-assembly is completed, conduct an overall inspection to confirm that all dimensional deviations meet the design requirements, and then transport the steel reinforcement components and the steel frame as a whole unit to the bridge site for hoisting and installation.

2. The method for processing and assembling reinforcing bars for steel-concrete composite bridge tower segments according to claim 1, characterized in that, In step S1, the steel reinforcement is divided into blocks, specifically including: The vertical main reinforcement bars are divided into a first preset number of specification lengths, and the horizontal reinforcement bars are divided into a second preset number of specification lengths. During the division, the length of the original reinforcement bar material is used as a constraint condition. A one-dimensional material cutting optimization model is established with the objective function of minimizing the total length of surplus material. Solving the one-dimensional material cutting optimization model yields material cutting combination schemes for each specification length, ensuring that the sum of the lengths of each specification length in each material cutting combination scheme is less than or equal to the original length of the reinforcement bar material, and that the surplus length of a single reinforcement bar material is less than a preset surplus material threshold. During the solution process, priority is given to optimizing the material cutting combination of the vertical main reinforcement bars, ensuring that the utilization rate of the original material for the vertical main reinforcement bars is higher than that for the horizontal reinforcement bars.

3. The method for processing and assembling reinforcing bars for steel-concrete composite bridge tower segments according to claim 1, characterized in that, In S2, the spatial curve bending process specifically includes: Based on the spatial curve parameters in the CNC machining instructions, the multi-axis robotic arm of the three-dimensional CNC bending machine is controlled to perform linkage bending. During the bending process, the springback data of the steel bar is collected in real time by the sensor set at the end of the robotic arm, and the springback data is fed back to the control system for compensation and correction, so that the spatial curve of the formed steel bar matches the design curve in the BIM model.

4. The method for processing and assembling reinforcing bars for steel-concrete composite bridge tower segments according to claim 1, characterized in that, The process of feeding back the rebound data to the control system for compensation and correction specifically includes: Obtain the average yield strength of the incoming sample from the current batch of reinforcing steel. and average elastic modulus Discretize the design space curves extracted from the BIM model into The nth bend node, for the nth... Each corner node, according to the formula Calculate the initial cornering compensation angle The order was then sent to a CNC bending machine to process the first steel bar. The diameter of the reinforcing bar. For the first The design bending radius of each corner node To design the bending angle, ; After the first rebar is processed, the actual spatial coordinates of each bend node are obtained. The measured spatial curve is then compared node by node with the design spatial curve. The springback deviation at each bend node is decomposed into the angular springback amount within the bend surface. and torsional springback around the axis of the reinforcing bar ; Using the first angular rebound at each bend node According to the formula Back-calculate the material correction factor corresponding to this node. and will The material correction coefficient for each bend node is based on the formula. The average value is used to obtain the comprehensive correction factor for this batch of steel bars. ; Based on the measured angular rebound of each preceding bend node, the cumulative propagation deviation of the preceding bend node to the spatial positioning reference of the subsequent bend node is calculated. The comprehensive correction coefficient and the cumulative propagation deviation are substituted into the compensation calculation of the subsequent bend node to calculate and update the over-bending compensation angle. At the same time, the rotational feed angle of the rebar around its own axis is corrected according to the torsional rebound. In subsequent batch processing, after each rebar is processed, the process of comparing the measured spatial curve, back-calculating the material correction coefficient, calculating the cumulative propagation deviation, and updating the compensation parameters is repeated. The comprehensive correction coefficient and the compensation parameters of each node are continuously updated iteratively using the latest measured data to achieve piece-by-piece adaptive convergence of the rebar rebound compensation for this batch.

5. The method for processing and assembling reinforcing bars for steel-concrete composite bridge tower segments according to claim 4, characterized in that, The calculation of the cumulative propagation deviation of the preceding bends from the spatial positioning reference of the subsequent bends, based on the measured angular rebound of each preceding bend node, specifically includes: No. angular rebound at each bend node Make the first The cumulative offset caused by the spatial position of each bend node is calculated according to the formula. Calculation, where , For the first From the first bend node to the first The cumulative arc length of the first bend node along the reinforcing bar axis, the first The total cumulative offset of each bend node is calculated according to the formula. Calculate the vector sum of the propagation deviations of all preceding bend nodes; Simultaneously, the step of substituting the comprehensive correction coefficient and cumulative propagation deviation into the compensation calculation of subsequent corner nodes to calculate and update the cornering compensation angle specifically includes: the first... The updated cornering compensation angle for each bend node is based on the formula. Calculation, where For the first The remaining length from the corner node to the end of the rebar. This is the angle correction amount used to offset the cumulative offset from the preceding sequence.

6. The method for processing and assembling reinforcing bars for steel-concrete composite bridge tower segments according to claim 1, characterized in that, In step S3, the steel frame is positioned using a frame position control system, specifically including: Multiple adjustable three-dimensional positioning supports are set on a horizontal assembly platform, and the bottom and sides of the steel frame are abutted against the three-dimensional positioning supports. The actual coordinates of the preset control points on the steel frame are obtained by a total station, and the actual coordinates are compared with the theoretical coordinates in the BIM model. Based on the comparison results, the three-dimensional positioning supports are driven to adjust their spatial position until the spatial posture of the steel frame meets the preset positioning accuracy requirements.

7. The method for processing and assembling reinforcing bars for steel-concrete composite bridge tower segments according to claim 1, characterized in that, In step S3, U-shaped clips are used to fix the reinforcing bars to the steel frame, specifically including: Weld connecting plates at the pre-set rebar attachment points on the steel frame, and attach the processed rebars to the surface of the connecting plates; pass U-shaped clips across the rebars and fasten them into the pre-drilled holes on the connecting plates, and apply pre-tightening force to the U-shaped clips by tightening nuts, so that the rebars and the steel frame form a detachable rigid connection.

8. The method for processing and assembling reinforcing bars for steel-concrete composite bridge tower segments according to claim 1, characterized in that, In step S4, the pre-assembly of steel reinforcement components of adjacent segments is carried out in the factory, specifically including: First, feature point reinforcement bars at the interface of adjacent segments are extracted from the BIM model. These feature point reinforcement bars include reinforcement bars at the inflection points of the tower columns and reinforcement bars at the center of the segments. The feature point reinforcement bars of the previous segment are matched and connected with those of the next segment to verify the spatial position accuracy and connection matching degree. After the verification is qualified, the remaining reinforcement bars are assembled according to the feature point reinforcement bars as the reference, following the order of vertical main reinforcement bars first and then horizontal reinforcement bars, until the pre-assembly of the reinforcement components of the entire segment is completed.

9. A steel bar processing and assembly system suitable for steel-concrete composite bridge tower segments, characterized in that, include: The 3D modeling and instruction generation unit is used to create a 3D BIM model of the steel-concrete composite bridge tower segment. Based on the spatial geometry of the bridge tower segment, it extracts the 3D coordinate data, bending angle, and spatial curve parameters of each steel bar. Based on the length of the original steel bar, it divides the steel bars into blocks to ensure that the utilization rate of the original material during steel bar cutting reaches a preset threshold. Based on the extracted spatial parameters, it assigns a unique number to each steel bar and generates CNC machining instructions. The CNC blanking and bending processing unit is used to import the generated CNC machining instructions into the three-dimensional CNC bending processing integrated machine, and to automatically blank and bend the steel bars in the factory workshop; after processing, each steel bar is marked to ensure that the steel bar corresponds one-to-one with the number in the BIM model; The steel frame assembly and rebar installation unit is used to set up a horizontal assembly platform in the factory, hoist the steel frame onto the platform and adjust it to the designed position; the steel frame is positioned using a frame position control system; the rebar installation positions are marked on the steel frame according to the designed spacing, and the processed rebars are installed onto the steel frame in sequence; U-shaped clips are used to fix the rebars to the steel frame; during the assembly process, measuring instruments are used to monitor the geometric dimensions of the rebar frame in real time. The segmental pre-assembly and overall inspection unit is used to pre-assemble the steel reinforcement components of adjacent segments in the factory. After the pre-assembly is completed, an overall inspection is carried out to confirm that the various dimensional deviations meet the design requirements. Then, the steel reinforcement components and the steel frame are transported as an overall unit to the bridge site for hoisting and installation.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that, The computer program is executed by a processor according to any one of claims 1-8, which describes a method for processing and assembling steel bars for steel-concrete composite bridge tower segments.