Steel reinforced concrete construction simulation method based on BIM three-dimensional visualization

By using BIM 3D visualization to simulate steel-concrete construction, the problem of dynamic inspection of changes in space occupancy during construction operations was solved, continuous inspection of the feasibility and trajectory integrity of the construction sequence was achieved, and adjustment schemes for the construction sequence were provided.

CN123158769APending Publication Date: 2026-11-24CHINA CONSTR FIFTH ENG BUREAU (SICHUAN) CONSTR DEV CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611686511.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-10-29
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing BIM construction simulations are unable to reflect the dynamic changes in space occupancy during construction operations, cannot conduct complete and continuous feasibility checks on the project confirmation trajectories of objects entering the site, actual operations, and tool removal, and are difficult to adjust the construction sequence based on actual sources of obstruction.

Method used

The BIM-based 3D visualization-based steel-concrete composite construction simulation method acquires the BIM 3D model of the steel-concrete composite nodes, candidate construction sequences, and forced process relationships. It divides the operation trajectory into three stages: entry, operation, and withdrawal. It performs continuous collision checks in three stages to determine the set of blocking components and generates local sequence relationships and construction order adjustment requirements.

Benefits of technology

It enables complete and continuous inspection of object entry, operation, and tool removal during construction, ensuring the feasibility of the construction sequence, avoiding misjudgments of single-stage passage or trajectory splicing results, and providing a solution for adjusting the construction sequence to address spatial obstruction issues.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123158769A_ABST
    Figure CN123158769A_ABST
Patent Text Reader

Abstract

This invention discloses a BIM-based 3D visualization-based method for simulating steel-concrete composite construction, belonging to the field of digital simulation technology for construction processes. This method establishes a pre-operation occupancy state according to the candidate construction sequence, divides the confirmed project trajectory into entry, operation, and withdrawal stages, and performs continuous collision checks. When all trajectories are actually blocked, the first blocked stage for each trajectory is determined, and a candidate component set is formed and expanded in a limited manner for each trajectory. Feasible blocking schemes are collected, and the blocking component set with the fewest components is determined. Based on the source of the blockage, local sequential relationships or output tools, trajectories, and construction method adjustment requirements are generated, and then forced process relationships are merged for reordering and reconstruction verification. This method is used for the feasibility check and 3D simulation of the construction sequence of steel-concrete composite joints.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of digital simulation technology for construction processes, specifically to a method for simulating steel-concrete composite construction based on BIM three-dimensional visualization. Background Technology

[0002] A steel-concrete joint can simultaneously contain steel beams, steel columns, connecting plates, stiffening plates, high-strength bolt connections, longitudinal reinforcement, and stirrups in the joint area. During joint construction, different operations have corresponding entry directions, work positions, and evacuation requirements. The solid structures remaining within the joint after the completion of previous procedures will continue to occupy the space required for subsequent operations.

[0003] Existing BIM construction simulations typically control the state changes of components according to the construction sequence and perform spatial checks based on the final installation position of the components. However, the fact that the final installation positions of components do not intersect does not mean that reinforcement, tools, or installation aids can continuously complete the process of entering nodes, performing operations, and withdrawing from nodes. Components formed by previous processes may block the entry of subsequent objects or restrict tool operations, and newly positioned entities may also prevent the withdrawal of tools or installation aids.

[0004] Therefore, it is necessary to combine the candidate construction sequence to form the space occupancy before each operation begins, further reflecting the changes in occupancy caused by the movement of objects, the placement of entities, and the withdrawal of tools within the same operation, and to check the complete and continuous process of the project's confirmed trajectory. When the trajectory is obstructed, it is also necessary to determine the actual source of the obstruction and its corresponding process, and select process reordering or tool, trajectory, and construction method adjustments based on the obstruction stage and source, and re-verify the feasibility of the adjusted construction sequence. Summary of the Invention

[0005] To address the shortcomings of existing technologies, this invention proposes a BIM-based 3D visualization-based steel-concrete construction simulation method. This method solves the problems that existing BIM construction simulations cannot reflect the dynamic changes in space occupancy during construction operations, cannot perform complete and continuous feasibility checks on the project confirmation trajectories of objects entering the site, actual operations, and tool removal, and cannot adjust the construction sequence based on actual sources of obstruction.

[0006] To achieve the above objectives, the present invention provides the following technical solution: A BIM-based 3D visualization-based method for simulating steel-concrete composite construction includes: Obtain the BIM 3D model of the steel-concrete joint, candidate construction sequence, forced process relationships, and project confirmation trajectory of each operation; According to the candidate construction sequence, the existing main components and completed processes are simulated to complete the entity before the operation and the occupied state is formed. Each trajectory is divided into the entry, operation and withdrawal stages. The operation objects, tools or installation accessories that move along the trajectory in the corresponding stage are identified as the current objects, and the occupied state of the stage is formed according to their movement, positioning and exit. A three-stage continuous collision check is performed on each trajectory. The operation is deemed feasible when at least one trajectory passes completely. When all trajectories are actually blocked, a candidate component set is formed by the non-intersecting components of the first blocked stage of each trajectory. After temporary removal and re-checking, the blocking component set with the fewest components is determined from the schemes to restore complete passage. When there is no feasible scheme or multiple schemes with the same fewest components cannot be distinguished, the blocking attribution result is marked as pending verification. When the blocking component is a completed entity formed by the preceding process, the local sequence relationship of the blocked operation preceding the source process is generated; when the blocking component is a main component that already exists before the simulation and cannot be changed in order, or when the new entity in place for this operation causes the withdrawal to be blocked, the requirements for adjusting the output tool, trajectory or method are generated. Merge and sort local sequence relationships and forced process relationships, clear the pre-operation occupancy status, stage occupancy status and obstruction records of the old sequence, re-examine from the initial pre-operation occupancy status, and output the construction sequence that has passed the review or the unresolved conflicts.

[0007] Furthermore, component identifiers, geometric shapes, spatial locations, and connection relationships are read from the BIM 3D model, and the geometric data is unified to the coordinate system used by the nodes; Establish a process object table based on the candidate construction sequence, record the operation objects, tools or installation accessories of each operation, and determine the current object of the corresponding stage based on the movement and collision inspection objects of each stage. At the same time, record the objects that are allowed to move before the operation starts, the completed entities of the process, and the objects that are removed after the operation is completed. This is used to determine the inspection objects of each stage and update the pre-operation occupancy status of subsequent operations.

[0008] Furthermore, based on the actual construction method, the geometric shape, starting and ending postures, allowable degrees of freedom and allowable operation directions of the current object at each stage, a trajectory is formed that extends continuously from the starting posture to the ending posture, and this trajectory is confirmed by the project. The position and attitude in the trajectory change continuously with the trajectory parameters, and fully cover the process of the current object entering the node in the entry phase, the current object completing the actual operation in the operation phase, and the tool or installation aid exiting the node in the withdrawal phase.

[0009] Furthermore, during the entry phase, the components in the pre-operation occupied state before the current operation begins are used as background occupied components, and entities formed after the current operation is completed are not added in advance; During the work phase, the background occupies the components, and the current objects that are moving, transposing, or temporarily occupying space, as well as the actual temporary connection states, are added. The evacuation phase adds a new occupying component to the phase where the current operation is in place and continues to remain, removes objects that are allowed to exit with the tool, and checks the exit movement of the tool or installation aid.

[0010] Furthermore, the geometry of the current object in the corresponding stage is transformed into swept geometry along the continuous pose transformation of that stage, and the swept geometry is compared with other occupied components in the occupied state of the corresponding stage, excluding the current object. Construction tolerance is derived from project construction standards, tool data, or detailed design requirements. It is registered for objects or object pairs and remains unchanged in the same round of simulation. Collision judgment is participated in by geometric outer envelope offset or equivalent minimum gap threshold. Contacts are allowed to be pre-registered according to object, stage, and contact type. Other different object instances are judged to determine whether they are not allowed to intersect based on the geometric relationship after construction tolerance processing.

[0011] Furthermore, if the entry, operation and withdrawal phases of the same project confirmation trajectory all pass the continuous collision check, the operation is deemed executable when at least one project confirmation trajectory passes completely. Trajectories with only discrete poses and where the continuous transformation relationship between adjacent poses cannot be determined are converted to be verified. If there is no complete pass track and there is a track to be verified, keep the operation as pending verification and stop blocking attribution. Blocking attribution will only be performed when all confirmed tracks are actually blocked.

[0012] Furthermore, when all project trajectories are actually blocked, the earliest non-intersecting position and intersecting object in the first blocking stage of each trajectory are identified as valid collision witnesses. The intersecting and occupying components in the valid collision witnesses form a candidate component set, and the current object, the pre-registered objects that are allowed to contact, and the objects whose source cannot be determined are excluded. Enumerate the temporary removal combinations in ascending order of the number of components. The combinations that allow the corresponding trajectory to be restored to complete passage are collected as feasible blocking schemes. When a new valid collision witness appears in a subsequent stage, the corresponding occupying component is added to the candidate component set and the enumeration continues. The set of blocking components with the fewest components is determined from all feasible blocking solutions. If there are no feasible solutions or multiple equally few solutions that cannot be distinguished, the blocking attribution result is marked as pending verification.

[0013] Furthermore, the source process is determined based on the component identification of the already identified blocking component and the correspondence between the component and the completed entity of the process; When the blocking component is a completed entity formed by the preceding process, a local sequence relationship is generated where the blocked operation precedes the source process. If the obstructing component is a main component that already exists before the simulation and cannot be changed by reordering, or if the newly positioned entity in this operation causes the evacuation to be obstructed, no local sequence relationship will be generated, and the tool, trajectory, or construction method adjustment requirements will be output.

[0014] Furthermore, the deduplicated local sequence relationships and the forced process relationships are merged to form a process relationship diagram. A new construction order is obtained through topological sorting, and the relative order of multiple processes in the original candidate construction order is maintained when there is no definite sequence requirement. Clear the occupancy status and obstruction records formed by the old sequence, reconstruct the occupancy status before the initial operation from the existing main components before the simulation, and re-check according to the new construction sequence; If the process relationship diagram forms a directed cycle, and after re-checking there are still actual obstacles and no new effective local sequence relationships are formed, or if the same occupancy status and obstruction record reappear, the output will show an unresolved conflict.

[0015] Furthermore, the BIM 3D model continuously plays the verified construction sequence according to the process, and displays the project confirmation trajectory of each operation, the occupancy status of each stage, and the continuous collision check results in association with the corresponding process, for the preparation of construction plans and the review of node construction planning.

[0016] Compared with existing technologies, it has the following advantages: This invention establishes a pre-operation occupancy state according to the candidate construction sequence and further distinguishes object changes in three stages: entry, operation, and withdrawal. This allows the construction simulation to check the entry of objects beyond the final position of the components, the actual operation, and the tool withdrawal process. By forming sweep geometry through the continuous pose of the current object and combining construction tolerance and allowed contact for continuous collision checks, it can distinguish between single discrete positions that do not intersect and complete, executable motion processes, avoiding the substitution of complete passage with single-stage passage or stage splicing results of different trajectories.

[0017] When all project trajectories are confirmed to be blocked, this invention forms and expands a limited set of candidate components for each trajectory, compiling feasible blocking schemes that can restore the corresponding trajectory to full passage. From these, the set of blocking components with the fewest components is determined, ensuring that the source of the blockage corresponds to the actual recoverable trajectory. Based on the blocking stage and the source of the blocking components, local sequence relationships or output tool, trajectory, and construction method adjustment requirements are generated. After reordering, the occupancy status formed by the old sequence is cleared, and the occupancy status before the initial operation is rechecked, ensuring that the output construction sequence has a corresponding reconstruction and verification process. Attached Figure Description

[0018] Figure 1This is a schematic diagram of the construction simulation method of the present invention.

[0019] Figure 2 This is a schematic diagram of the blockage attribution and processing flow of the present invention. Detailed Implementation

[0020] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0021] Please see Figure 1 This embodiment provides a BIM-based 3D visualization-based steel-concrete composite construction simulation method to check whether the rebar insertion or installation, connection operations, and tool removal processes within steel-concrete composite joints can be completed continuously according to the candidate construction sequence. This method is executed by BIM construction simulation software, BIM software extensions, or a construction planning system connected to a BIM 3D model. The BIM 3D model provides component identification, geometric shape, spatial location, and connection relationships for subsequent occupancy status formation and clash detection.

[0022] Before implementing this method, obtain the node BIM 3D model, candidate construction sequences, and mandatory process relationships. Candidate construction sequences are derived from the construction organization design, project schedule, or construction planning results. Mandatory process relationships are derived from the construction technology adopted by the project. These mandatory process relationships record the sequential constraints that must be maintained according to the actual construction technology; local sequential relationships do not replace the mandatory process relationships. Project personnel also provide the operating objects, tools or installation aids, tool geometry, operating start and end postures, allowable degrees of freedom, allowable contact, construction tolerances, project-confirmed trajectories, and existing main components based on the detailed design and actual construction methods. The tool geometry uses product data, measured geometric data, or a conservative envelope confirmed by the project, without arbitrarily reducing the tool's shape to avoid spatial conflicts.

[0023] Construction tolerances are derived from project construction standards, tool documentation, or detailed design requirements, and are registered for the corresponding objects or object pairs. Construction tolerances can be used to participate in collision detection by offsetting the corresponding geometric envelope, or by using an equivalent minimum gap threshold to determine whether necessary gaps are maintained between objects. The source and processing method of tolerances for the same object or object pair remain unchanged in the same simulation round, and are only updated after the engineering conditions are re-entered.

[0024] Permitted contacts must be registered before continuous collision checks. Each permitted contact must specify at least the objects that can make contact, the permitted operational stage, and the contact type (e.g., mating, bonding, or guiding). The system first identifies permitted contacts that match the registered information, and then determines whether disallowed intersections occur for the remaining objects based on the geometric relationships adjusted for construction tolerances. Unregistered object contacts are not excluded as permitted contacts, and registered permitted contacts are not extended to other objects, other stages, or other contact types.

[0025] The system reads steel columns, steel beams, connecting plates, stiffening plates, high-strength bolt connections, longitudinal reinforcement, and stirrups in the node area from the BIM 3D model. It unifies the geometric shape and spatial position of each object into the coordinate system used by the node, and retains the correspondence between geometric data and component identifiers. The processed geometric data is used for subsequent trajectory movement, sweep geometry formation, space occupancy, and continuous collision checks. The final installation state in the BIM 3D model is not directly used as the result for determining whether construction actions are executable.

[0026] The system establishes a process object table based on the candidate construction sequence. For each operation, the process object table records at least the operation object, tools, or installation aids, and identifies objects that move along the project-confirmed trajectory within the corresponding stage and participate in continuous collision checks as the current object; it also records objects allowed to move before the operation begins, process-completed entities that remain in the node after the operation is completed, and objects removed after the operation is completed. A process-completed entity is a component or material entity that remains and occupies node space after the corresponding process is completed. The system uses this object table to determine the objects participating in collision checks at each stage and updates the pre-operation occupancy status of the next operation after the process is completed. Objects allowed to move before the operation begins are used to adjust the occupancy relationship of the corresponding stage according to the actual movement status confirmed by the project; objects that have moved without confirmation are not excluded from the original pre-operation occupancy status.

[0027] At the start of the simulation, project personnel identify the main components already existing within the node before the first operation. The system uses these main components to establish the initial pre-operation occupied state. After an operation is completed according to the candidate construction sequence, the system only adds the completed entities of the corresponding process to the pre-operation occupied state of subsequent operations. Reinforcing bars, connectors, and other components that have not yet been executed are not added to the occupied state in advance because they already exist in the final state of the BIM 3D model. Tools or installation aids that have been completed and removed from the node do not continue to occupy space for subsequent operations.

[0028] For each operation to be performed, project personnel determine one or more continuous trajectories based on the actual construction method and the geometry, starting and ending postures, permissible degrees of freedom, and permissible operating directions of the object, tool, or installation fixture. These confirmed trajectories are then used as the project confirmation trajectories. The project confirmation trajectory represents the operation process from the initial posture to the final posture using continuously changing trajectory parameters. Each value of the trajectory parameter corresponds to the position and posture of the object, tool, or installation fixture moving along that trajectory in the nodal coordinate system. The position and posture change continuously with the trajectory parameters, enabling the system to obtain continuous pose transformations between adjacent operation states, rather than simply obtaining a few separate static positions.

[0029] Project-confirmed trajectories can be continuously recorded by project personnel in the 3D operating interface, or they can be generated by the system based on the input start and end postures and allowed degrees of freedom, and then submitted to project personnel for confirmation. Regardless of the generation method, the project-confirmed trajectory must cover the complete process of the operation object, tools, or installation accessories completing the entry, operation, and withdrawal according to the actual construction method. Search results that have not been confirmed by the project are only used as trajectory suggestions and do not participate in the formal determination of operational feasibility.

[0030] The system divides each project confirmation trajectory into three stages: the entry stage, the operation stage, and the withdrawal stage, based on the actual action boundaries. Within each stage, the operating objects, tools, or installation aids that move along the project confirmation trajectory and participate in continuous collision checks are identified as the current object. The entry stage represents the continuous process of the current object entering the node from its initial position and reaching the operation position. The operation stage represents the continuous process of the current object completing actions such as fitting, rotating, aligning, inserting, rotating, fastening, or positioning at the operation position. The withdrawal stage represents the continuous process of tools or installation aids leaving the node after the new entity is in place. These three stages together constitute the complete operation process of the project confirmation trajectory; the result of passing one stage cannot replace the result of passing the entire project confirmation trajectory.

[0031] For the entry phase, the system uses components in the pre-operation occupancy state before the current operation begins as background occupancy components and includes the current object entering the node in the motion check, but does not add entities formed after the current operation is completed. For the operation phase, the system continues to retain background occupancy components, while adding current objects that are moving, repositioning, or temporarily occupying positions, as well as temporary connection states actually formed during the operation. For the withdrawal phase, the system uses entities that have been positioned and are still retained as newly added occupancy components for the current operation, while removing objects that are allowed to be withdrawn with the tool according to the actual construction method, and then checks the withdrawal movement of the tool or installation aids. Thus, the three phases respectively reflect the occupancy before the operation begins, the changes in objects during the operation, and the newly added occupancy after the operation is completed, without using a single static state to represent the entire operation process.

[0032] The system distinguishes between the current object, background occupied components, and newly added occupied components by component identifier and object instance. The same object instance cannot participate in collision determination as both a moving object and a background obstacle at the same time. Different object instances are checked according to the aforementioned rules on permissible contact and construction tolerance.

[0033] The system checks a project confirmation trajectory in a fixed sequence of entry, operation, and withdrawal. The operation phase is checked only after the entry phase is passed, and the withdrawal phase is checked only after the operation phase is passed. For each phase, the system moves the geometry of the current object continuously from its initial pose to its final pose according to the continuous pose transformations given by the project confirmation trajectory. This geometry, through all the continuous poses, forms the corresponding swept geometry. The system compares the swept geometry with the background occupies and newly added occupies in that phase. After excluding permissible contacts, it determines whether any disallowable intersections occurred during the movement based on the construction tolerance processing results.

[0034] Continuous collision checking covers the entire motion range between adjacent poses using sweep geometry, and does not directly determine whether a stage passes based on the absence of intersections at trajectory endpoints or a few discrete positions. When the trajectory data only contains discrete poses, but also provides a clear continuous transformation relationship between adjacent poses, the system forms sweep geometry based on this continuous transformation. When the trajectory data only contains discrete poses, and it is not possible to determine how adjacent poses continuously change, the system cannot rule out the possibility of intersecting intermediate motions, and the corresponding trajectory is converted to pending verification.

[0035] After excluding permitted contact, if the swept geometry formed by the current object does not intersect with other objects after construction tolerance processing, and the continuous movement of the corresponding stage can be completed, then that stage passes the continuous collision check. Let E(p) represent the complete pass indication of the project confirmation trajectory p. This indication is only used to characterize whether the trajectory meets the complete pass condition; when all three stages—entry, operation, and withdrawal—have been checked and all have passed, E(p) = 1. The actual obstruction and pending verification states of the trajectory are recorded independently according to the aforementioned state rules, without distinguishing between them using E(p).

[0036] The system performs phase checks in the order of entry, operation, and withdrawal. If any checked phase encounters an actual obstruction, the trajectory is directly marked as failed, and the inspection of subsequent phases is stopped. No pass or fail result is forcibly assigned to unexecuted phases. If insufficient data or inability to determine the situation occurs before an actual obstruction, the trajectory is marked as pending verification, and subsequent checks are stopped. Pending verification is an independent status and is not equivalent to failure.

[0037] When an operation has multiple project confirmation tracks, as long as at least one track satisfies E(p)=1, the system determines that the current operation is executable under the current work's occupancy status and saves the track, the occupancy status of each stage, and the inspection results for subsequent simulation playback and construction planning review. Passing a single stage or splicing together stages that have passed separately from different tracks cannot be used as evidence that a project confirmation track has passed completely.

[0038] After the current operation passes inspection, the system adds the completed entity of the corresponding process to the pre-occupancy state of the next operation, removes tools or installation aids that have exited the node from the occupancy, and then checks the next operation according to the candidate construction order. The system proceeds item by item in this way, so that the inspection input for each operation is formed by the existing main components before simulation and the previously completed processes, rather than being obtained all at once from all the final components of the BIM 3D model.

[0039] Taking a steel-concrete composite beam-column joint using high-strength bolts as an example, the candidate construction sequence can include, in sequence, the placement of the steel beam, installation and initial tightening of the connecting plates, final tightening of the high-strength bolts, installation or passing of longitudinal reinforcement bars through the beam, and installation or closure of stirrups in the joint area. The steel beam, connecting plate, and the initially tightened connecting plates are in a pre-operation occupied state before the final tightening of the high-strength bolts begins; longitudinal reinforcement bars and stirrups that have not yet been installed are not added to this state in advance.

[0040] For the final tightening of high-strength bolts, project personnel confirm the complete final tightening trajectory based on the geometry of the wrench and socket to be used, the location of the connection pair, the permissible operating direction, and the actual construction method. The system defines the process of the wrench and socket reaching the connection pair as the entry phase, the process of the socket being fitted onto the connection pair and completing the tightening action as the operation phase, and the process of the wrench and socket leaving the node after tightening as the withdrawal phase. The system continuously updates the tool posture in the three phases, forming the sweep geometry of the wrench and socket in each phase, and performs continuous collision checks with the corresponding background occupiers and newly added occupiers in the phase. After the complete final tightening trajectory is verified, the system marks the final tightening operation as executable; the wrench and socket do not enter the pre-operation occupancy state of the next operation after withdrawal.

[0041] For the installation of longitudinal reinforcement bars in beams, project personnel confirm the complete installation trajectory based on the reinforcement bar shape, installation method, permissible direction, start and end postures, and installation tools determined by the detailed design. The system considers the process of reinforcement bars and installation tools entering the node as the entry stage, the process of reinforcement bars moving, rotating, aligning, and positioning within the connection area as the operation stage, and the process of installation tools exiting the node after reinforcement bars are positioned as the withdrawal stage. At the start of the withdrawal inspection, the already positioned reinforcement bars continue to occupy space as newly added occupiers in this stage. The system compares the sweep geometry formed by the installation tools along the continuous withdrawal posture with the reinforcement bars and other occupiers to determine whether the installation tools can be withdrawn after the reinforcement bars are positioned. After the complete installation trajectory is passed, the reinforcement bars become the completed entity and are added to the pre-operation occupied state for subsequent stirrup installation or closure operations.

[0042] For the installation or closure of stirrups in the node area, the system adopts the same processing method. Based on the actual stirrup type and installation method, it obtains the operation object, installation tools, and project confirmation trajectory. Following the aforementioned rules, it determines the current object for each stage and checks the entry, operation, and withdrawal stages sequentially. When at least one project confirmation trajectory has been successfully completed for all operations, the system outputs the approved construction sequence and continuously plays the steel section connection, high-strength bolt final tightening, longitudinal reinforcement installation, and stirrup installation or closure processes in that sequence. The output also retains the project confirmation trajectory used for each operation, the occupancy status of each stage, and the corresponding inspection results for review during construction plan preparation and node construction planning.

[0043] For operations with multiple project confirmation trajectories, the system records the results of each trajectory according to the aforementioned rules of complete passage, actual obstruction, and pending verification. Only when all project confirmation trajectories are determined to be actually obstructed will the obstruction attribution process begin, and the first obstruction stage and the corresponding obstruction source for each trajectory be determined.

[0044] Please see Figure 2 When all project trajectories are confirmed to be blocked, the system determines the initial stage that each trajectory cannot complete, according to the order of entry, operation, and withdrawal. For a trajectory blocked due to direct intersection, after excluding permissible contact and processing according to construction tolerances, the system saves the earliest non-permissible intersection position within the first blocked stage of the trajectory, along with the occupying component that makes a non-permissible intersection with the current object at that position. The position and the corresponding intersecting object are identified as valid collision witnesses for the trajectory. Valid collision witnesses are used to form a candidate component set for the trajectory, and the blocked position is correlated with the source of the relevant component in its pre-operation occupancy state or newly added occupancy state in the current stage.

[0045] For each actual obstructed trajectory p, the system forms a set of candidate components during the first obstruction stage of that trajectory. The candidate component set includes background occupied components that are not allowed to intersect with the current object in the valid collision witnesses, as well as newly added occupied components in the stage. The current object itself, already registered and meeting the contact conditions for allowed contact, and objects whose origin is uncertain are not included in the candidate component set of this trajectory. Objects whose origin is uncertain are recorded separately as objects to be verified and are not used to generate local sequence relationships.

[0046] For each trajectory, the system enumerates subsets of candidate component sets in ascending order of the number of components contained in the combination. For each candidate subset, the system removes it only in the temporary state used for collision checking, and then re-executes the checks for the three stages of entry, operation, and withdrawal according to the same stage sequence and termination conditions as the original trajectory, without changing the original BIM 3D model, the actual component status, or the registered process relationships. The candidate subsets that allow the corresponding trajectory to pass completely after temporary removal constitute the feasible blocking schemes for that trajectory.

[0047] After temporarily removing a candidate combination, if the original first blocked stage passes, but a new first blocked stage appears in a subsequent stage, the system, according to the aforementioned rules for forming valid collision witnesses, adds background occupiers that are not allowed to intersect with the current object and have not been previously registered, or newly added occupiers in the new stage, to the candidate component set of the trajectory. Each expansion adds at least one previously unregistered component that meets the aforementioned candidate conditions, and the system then re-enumerates the temporarily removed combinations in ascending order of component quantity. When no new components meeting the aforementioned candidate conditions appear in the candidate component set, the expansion and re-enumeration stop.

[0048] Let uppercase letter P represent the set of project confirmation trajectories for the same operation, and lowercase letter p represent any project confirmation trajectory in set P. Let B represent the set of candidate components after a finite expansion of the trajectory p. The set of components selected and temporarily removed during the inspection state, in order to Let F represent the complete passage indicator of trajectory p obtained after temporarily removing B, following the same stage sequence and termination conditions. Let F represent the set of feasible blocking schemes obtained by aggregating all trajectories, and the set of feasible blocking schemes satisfies the following relation:

[0049] This relation only includes candidate combinations that can restore at least one project confirmation trajectory to full pass in the set of feasible blocking solutions. Combinations that are temporarily removed and are pending verification or fail will not be included in this set.

[0050] When the set of feasible blocking solutions F is not empty, the system first determines the minimum feasible blocking solution based on the number of components. If the minimum feasible blocking solution is unique, it is determined as the final set of blocking components. If multiple minimum feasible blocking schemes with the same number of components exist, they are distinguished using valid collision witnesses of the corresponding trajectories, and a decision is made only when they can be distinguished. When it cannot be distinguished, it is uncertain. The attribution results for blocking will be marked as pending verification. If the final determination is made according to the above rules... Then the following relation is satisfied:

[0051] This relationship only indicates that the final determined solution is the feasible blocking solution with the fewest components. It does not mean that one solution can be chosen when there are multiple indistinguishable minimum solutions, nor does it use the number of collisions, overlap volume, or human scoring to replace the determination of the number of components.

[0052] When the candidate component set stops expanding and no feasible blocking solutions are formed, the system marks the blocking attribution result as pending verification, determines the blocking component set, and does not generate local priority relationships. When the blocking attribution result is pending verification, the system will re-execute the continuous collision check and blocking component set determination process after project personnel supplement geometric data, access permission registration information, or actual usable project confirmation trajectories.

[0053] The system determines the source process of each blocking component based on its component identifier and the correspondence between that component and the completed process entity. When a blocking component belongs to a completed process entity formed by a preceding process, regardless of whether the first obstruction stage is the entry, operation, or withdrawal stage, the system generates a local priority relationship between the current obstructed operation and the source process of the blocking component. This local priority relationship is used to transform spatial obstruction causes that can be eliminated through reordering into process adjustment constraints; if this local priority relationship and the forced process relationship together form a directed loop, it is treated as an unresolved conflict.

[0054] For example, a candidate construction sequence might be to first thread or install the longitudinal reinforcement of the beam and then install or close the stirrups in the joint area, followed by the final tightening of the high-strength bolts. The reinforcement and the connection pair may not have geometric overlap at the final installation position, but the wrench and sleeve may still be obstructed by the installed stirrups during entry, insertion, or rotation of the connection pair. The system checks the complete final tightening trajectory confirmed for each item. For trajectories where the first obstruction stage is a working stage and a valid collision between the wrench and the stirrup is observed, the system includes the stirrup in the candidate component set for that trajectory. If, after removing the stirrup in a temporary state, the final tightening trajectory returns to complete passage, and this scheme is determined to be the one with the fewest and most distinguishable components after comparison with all feasible obstruction schemes, the system identifies the stirrup as the obstruction component and traces back to the stirrup installation or closure process, thereby generating a local sequential relationship where the final tightening of the high-strength bolts precedes the stirrup installation or closure process.

[0055] The system deduplicates newly added local sequence relationships and then writes them together with the mandatory process relationships that must be retained according to construction process requirements into the process relationship diagram. The system performs topological sorting based on the merged relationships, and all mandatory process relationships and local sequence relationships must be satisfied in the sorting results. When multiple processes do not have a definite sequence requirement in the relationship diagram, the relative order of these processes in the original candidate construction sequence is maintained to avoid order changes without any obstruction basis.

[0056] After obtaining the new construction sequence, the system does not use the pre-operation occupancy status, stage occupancy status, and obstruction records formed by the old sequence. The system clears these process states, rereads the main components that existed before the simulation started, reconstructs the initial pre-operation occupancy status, and replays the operation from the first operation according to the new construction sequence. Each operation still uses the corresponding project confirmation trajectory, allowed contact, construction tolerance, and three stage boundaries, and performs continuous collision checks according to the aforementioned sweep geometry formation method. Only after passing the checks is the completed entity added to the pre-operation occupancy status of the next operation. When all operations after replay have at least one project confirmation trajectory that has passed completely, the system directly outputs the construction sequence that has passed the review, without outputting unresolved conflicts because no new local sequence relationship was formed in this round.

[0057] In the case of the aforementioned stirrup blocking the final tightening tool, after reordering, the system will re-check the occupied state before the initial operation according to the aforementioned reconstruction and verification rules; when all related operations have at least one complete and passed project confirmation trajectory, the system will output the adjusted construction sequence and the corresponding verification record.

[0058] When an obstruction occurs during the withdrawal phase, the system handles it according to the identified source of the obstruction. If the obstructing component is a completed entity formed by a preceding process, a local sequence relationship is generated according to the aforementioned rules, indicating that the current obstructed operation precedes the source process. If the source of the obstruction is a newly positioned entity of the current operation, no local sequence relationship is generated indicating that the current operation points to itself. For example, if the reinforcing bars and installation tools can enter the node and position the reinforcing bars, but the positioned reinforcing bars occupy the exit space of the installation tools, preventing the installation tools from withdrawing along the project-confirmed trajectory, the system records the withdrawal phase as the first obstruction phase, outputs requirements for tool replacement, confirmation of other trajectories, change of allowed withdrawal direction, or adjustment of construction methods, and keeps the conflict unresolved until project personnel provide new actual operating conditions and re-perform the three-phase check.

[0059] When the obstructing component is a pre-existing main component that cannot be changed through reordering, the system does not generate local sequence relationships, but instead outputs tool, trajectory, or method adjustment requirements. When the obstruction occurs during the withdrawal phase but it cannot be clearly distinguished whether it is caused by background occupancy components or newly added occupancy components in the phase, the system marks the obstruction attribution result as pending verification and does not generate process constraints based on incomplete source judgment.

[0060] When a newly generated local sequence relationship is opposite in direction to an existing forced process relationship, and causes the process relationship diagram to form a directed loop, the system retains the conflicting relationship and its source, does not delete the forced process relationship, and does not output a false executable order. The system outputs the operations involved in the loop, the blocking components, and the first blocked stage as unresolved conflicts, allowing project personnel to review them again after adjusting tools, trajectories, structures, or construction methods.

[0061] If, after re-inspection, actual obstruction still exists and no new effective local sequence relationship can be formed, or if the same pre-occupancy state and obstruction record reappear after replaying from the initial occupancy state, the system will terminate automatic reordering and output unresolved conflicts. This process is used to avoid repeatedly adjusting the same group of processes without new technical conditions.

[0062] When the project does not provide the complete geometry of the tool or reinforcement, the start and end postures of the operation, the continuous transformation relationship between adjacent postures, the allowable degrees of freedom, the allowable contact, the construction tolerance, the project-confirmed trajectory, the reinforcement installation method, or the entity information of the completed process, the system cannot determine that the corresponding operation is executable. The system records the missing data object, keeps the operation as pending verification, and re-executes it from the trajectory formation and three-stage occupancy state establishment process after the project personnel supplement the actual information.

[0063] When a BIM 3D model has duplicate component identifiers, damaged geometric data, inconsistent coordinate systems, or an inability to establish a correspondence between components and processes, the system stops using the affected objects to generate local sequence relationships and outputs the corresponding data anomalies. After completing geometric repair or object association, the system rereads the geometric data of the affected objects and verifies them from their pre-operation state.

[0064] When nodes are connected by full welding and there is no final tightening operation of high-strength bolts, it is not necessary to establish the corresponding process object and project confirmation trajectory for the final tightening of high-strength bolts. When an operation is located in an open area and is not restricted by installed components, its project confirmation trajectory data can be simplified according to the actual action. The above adjustments do not change the processing principle of this method, that is, to form a pre-operation occupancy state according to the candidate construction sequence, form a three-stage occupancy state according to the internal changes of the operation, perform continuous collision checks on the project confirmation trajectory, and select process reordering or tool, trajectory and construction method adjustment according to the first obstruction stage and the source of obstruction.

[0065] The executable results output by this method are limited to the geometric data, construction sequence, project-confirmed trajectory, permissible contact, construction tolerances, and three-stage boundaries that have been input and confirmed by the project. These results are used for construction planning, detail refinement, and 3D construction process verification. This result does not replace specialized inspections of component load-bearing capacity, temporary support stability, welding quality, bolt installation quality, and personnel safety distances.

[0066] The above embodiments are only used to illustrate the technical methods of the present invention and are not intended to limit it. Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical methods of the present invention without departing from the spirit and scope of the technical methods of the present invention.

Claims

1. A method for construction simulation of steel reinforced concrete based on BIM three-dimensional visualization, characterized in that, include: Obtain the BIM 3D model of the steel-concrete joint, candidate construction sequence, forced process relationships, and project confirmation trajectory of each operation; According to the candidate construction sequence, the existing main components and completed processes are simulated to complete the entity before the operation and the occupied state is formed. Each trajectory is divided into the entry, operation and withdrawal stages. The operation objects, tools or installation accessories that move along the trajectory in the corresponding stage are identified as the current objects, and the occupied state of the stage is formed according to their movement, positioning and exit. A three-stage continuous collision check is performed on each trajectory. If at least one trajectory passes completely, the operation is deemed feasible. If all trajectories are actually blocked, a candidate component set is formed by the non-intersecting components of the first blocked stage of each trajectory. After temporary removal and re-checking, the blocking component set with the fewest components is determined from the solutions to restore complete passage. If there is no feasible solution or multiple solutions with the same fewest components cannot be distinguished, the blocking attribution result is marked as pending verification. When the blocking component is a completed entity formed by the preceding process, the local sequence relationship of the blocked operation preceding the source process is generated. When the blocking component is a main component that already exists before the simulation and cannot be changed in order, or when the newly positioned entity of this operation causes the withdrawal to be blocked, the output tool, trajectory or method adjustment requirements are generated. Merge and sort local sequence relationships and forced process relationships, clear the pre-operation occupancy status, stage occupancy status and obstruction records of the old sequence, re-examine from the initial pre-operation occupancy status, and output the construction sequence that has passed the review or the unresolved conflicts.

2. The BIM-based three-dimensional visualization of steel reinforced concrete construction simulation method according to claim 1, characterized in that, include: Read component identifiers, geometric shapes, spatial locations, and connection relationships from the BIM 3D model, and unify the geometric data to the coordinate system used by the nodes; Establish a process object table based on the candidate construction sequence, record the operation objects, tools or installation accessories of each operation, and determine the current object of the corresponding stage based on the movement and collision inspection objects of each stage. At the same time, record the objects that are allowed to move before the operation starts, the completed entities of the process, and the objects that are removed after the operation is completed. This is used to determine the inspection objects of each stage and update the pre-operation occupancy status of subsequent operations.

3. The BIM-based three-dimensional visualization of steel reinforced concrete construction simulation method according to claim 1, characterized in that, include: Based on the actual construction method, the geometry, starting and ending postures, allowed degrees of freedom and allowed operation directions of the object at each stage, a trajectory is formed that extends continuously from the starting posture to the ending posture, and this trajectory is confirmed by the project. The position and attitude in the trajectory change continuously with the trajectory parameters, and fully cover the process of the current object entering the node in the entry phase, the current object completing the actual operation in the operation phase, and the tool or installation aid exiting the node in the withdrawal phase.

4. The BIM-based three-dimensional visualization of steel reinforced concrete construction simulation method according to claim 1, characterized in that, include: During the entry phase, the components in the pre-operation occupied state before the current operation begins are used as background occupied components, and entities formed after the current operation is completed are not added in advance; During the work phase, the background occupies the components, and the current objects that are moving, transposing, or temporarily occupying space, as well as the actual temporary connection states, are added. The evacuation phase adds a new occupying component to the phase where the current operation is in place and continues to remain, removes objects that are allowed to exit with the tool, and checks the exit movement of the tool or installation aid.

5. The BIM-based three-dimensional visualization of steel reinforced concrete construction simulation method according to claim 1, characterized in that, include: The geometry of the current object in the corresponding stage is transformed into swept geometry along the continuous pose transformation of the stage, and the swept geometry is compared with other occupied components in the occupied state of the corresponding stage, excluding the current object. Construction tolerance is derived from project construction standards, tool data, or detailed design requirements. It is registered for objects or object pairs and remains unchanged in the same round of simulation. Collision judgment is participated in by geometric outer envelope offset or equivalent minimum gap threshold. Contact is allowed to be pre-registered according to object, stage and contact type. Other different object instances are judged to determine whether they are not allowed to intersect according to the geometric relationship after construction tolerance processing.

6. The BIM-based 3D visualization-based steel-concrete composite construction simulation method according to claim 1, characterized in that, include: When the entry, operation and withdrawal phases of the same project confirmation trajectory all pass the continuous collision check, the operation is deemed to be executable when at least one project confirmation trajectory passes the complete check. Trajectories with only discrete poses and where the continuous transformation relationship between adjacent poses cannot be determined are classified as pending verification. If there is no complete pass track and there is a track to be verified, keep the operation as pending verification and stop the obstruction attribution. Obstruction attribution will only be performed when all confirmed tracks are actually obstructed.

7. The BIM-based three-dimensional visualization-based steel-concrete composite construction simulation method according to claim 1, characterized in that, include: When all project trajectories are actually blocked, the earliest non-intersecting position and intersecting object in the first blocking stage of each trajectory are identified as valid collision witnesses. The intersecting and occupying components in the valid collision witnesses form a candidate component set, and the current object, objects pre-registered as allowed to contact, and objects whose source cannot be determined are excluded. Enumerate the temporary removal combinations in order of increasing number of components, and collect the combinations that will restore the corresponding trajectory to complete passage into feasible blocking schemes; When a new valid collision witness appears in a subsequent stage, the corresponding occupied component will be added to the candidate component set and the enumeration will continue. The set of blocking components with the fewest components is determined from all feasible blocking solutions. If there are no feasible solutions or multiple equally few solutions that cannot be distinguished, the blocking attribution result is marked as pending verification.

8. The BIM-based 3D visualization-based steel-concrete composite construction simulation method according to claim 1, characterized in that, include: The source process is determined based on the component identification of the already identified blocking component and the correspondence between the component and the completed entity. When the blocking component is a completed entity formed by the preceding process, a local sequence relationship is generated where the blocked operation precedes the source process. If the obstructing component is a main component that already exists before the simulation and cannot be changed by reordering, or if the newly positioned entity in this operation causes the evacuation to be obstructed, no local sequence relationship will be generated, and the tool, trajectory, or construction method adjustment requirements will be output.

9. The BIM-based three-dimensional visualization-based steel-concrete composite construction simulation method according to claim 1, characterized in that, include: The deduplicated local sequence relationships and the forced process relationships are merged to form a process relationship diagram. A new construction order is obtained through topological sorting, and the relative order of multiple processes in the original candidate construction order is maintained when there are no definite sequence requirements. Clear the occupancy status and obstruction records formed by the old sequence, reconstruct the occupancy status before the initial operation from the existing main components before the simulation, and re-check according to the new construction sequence; If the process relationship diagram forms a directed cycle, and after re-checking there are still actual obstacles and no new effective local sequence relationships are formed, or if the same occupancy status and obstruction record reappear, the output will show an unresolved conflict.

10. The BIM-based three-dimensional visualization-based steel-concrete composite construction simulation method according to claim 1, characterized in that, In the BIM 3D model, the construction sequence that has passed the review is played continuously according to the process, and the project confirmation trajectory of each operation, the occupancy status of each stage, and the continuous collision check results are displayed in association with the corresponding process, so as to provide a basis for the preparation of construction plans and the review of node construction planning.