A method for predicting the pre-tightening force attenuation of a tie rod bolt of a flue gas turbine and the maintenance opportunity

By establishing a multi-parameter coupled model, the preload decay state of the flue gas turbine tie rod bolts is evaluated, which solves the problem that the existing technology fails to effectively combine high-temperature relaxation and shear fatigue. This enables accurate evaluation of the bolt group and early maintenance decision-making, improving the accuracy of preload decay prediction and the predictability of maintenance.

CN123158902APending Publication Date: 2026-11-24KETEK GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611379065.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-07
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing technologies fail to effectively combine high-temperature relaxation, shear fatigue, and on-site operating conditions, making it difficult to accurately assess the preload decay state of flue gas turbine tie rod bolts. This results in the inability to quantitatively determine in advance whether the preload is close to the risk boundary, the lack of a comprehensive evaluation of the average preload and non-uniformity of the entire bolt group, and the lack of a continuous technical process from test parameters to on-site data.

Method used

By acquiring high-temperature loss parameters, shear fatigue loss parameters, and rotor risk parameters, a multi-parameter coupled model is established to calculate the average preload and non-uniformity index of the bolt group. Combined with the future operating condition prediction maintenance window, a field correction coefficient is introduced to correct the data, forming a hierarchical state evaluation from single bolt to bolt group.

Benefits of technology

It enables accurate assessment of bolt preload, identifies hidden risk conditions, provides directly actionable maintenance decision information, improves the accuracy of preload decay prediction and the predictability of maintenance, and solves the problem of difficulty in combining parameters with field data in existing technologies.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123158902A_ABST
    Figure CN123158902A_ABST
Patent Text Reader

Abstract

This invention provides a method for predicting the preload decay and maintenance timing of flue gas turbine tie rod bolts, comprising: acquiring high-temperature loss parameters, shear fatigue loss parameters, rotor risk parameters, and on-site correction parameters; for each bolt, determining the high-temperature loss ratio and fatigue loss ratio based on the initial preload, and calculating the remaining preload in conjunction with the on-site correction parameters; calculating the average preload and non-uniformity index of the bolt group based on the remaining preload of each bolt, and comparing it with the safety boundary; extending the calculation to future operating conditions based on the loss ratio change rule, predicting the time point when the average preload first falls below the minimum allowable value or the non-uniformity index first exceeds the limit, as a suggested maintenance window. This method couples and quantifies high-temperature relaxation, shear fatigue, and on-site conditions, realizing hierarchical evaluation from single bolt to bolt group, predicting maintenance windows in advance, and improving the accuracy of maintenance decisions by continuously correcting the model through on-site measured data.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of flue gas turbine rotor connection condition assessment and maintenance decision-making technology, and in particular to a method for predicting the preload decay of flue gas turbine tie rod bolts and maintenance timing. Background Technology

[0002] The tie rod bolts in a flue gas turbine are used to tighten components such as the turbine disc and main shaft to form the rotor assembly. During long-term operation, the tie rod bolts are subjected to high temperatures, vibration, temperature cycling, and shear loads, causing their preload to gradually decrease. If the preload decreases at different bolts at different rates, it can lead to uneven rotor connection stiffness, which in turn can induce abnormal vibration. Therefore, accurately assessing the preload decay of the tie rod bolts and determining appropriate maintenance timing based on this assessment is crucial for ensuring the safe operation of the flue gas turbine.

[0003] However, existing technologies have the following shortcomings: Existing analysis methods typically treat high-temperature relaxation, shear fatigue, and rotor vibration risks separately, failing to establish a quantitative model for preload attenuation that combines multiple parameters. This makes it difficult to effectively combine the obtained parameters with field operation data, and thus cannot form maintenance recommendations that can directly guide field operation and maintenance.

[0004] Existing methods focus on whether a single bolt has loosened, but lack comprehensive evaluation methods for the average preload level and preload unevenness of the entire bolt group. This makes it difficult to identify hidden risk conditions where the average value of the entire bolt group is qualified but local deviations are too large.

[0005] Existing maintenance strategies mostly rely on fixed maintenance cycles or shutdown inspections after abnormal vibrations occur, which cannot quantitatively determine in advance whether the preload is close to the risk boundary during unit operation.

[0006] In addition, existing technologies lack a continuous technical process from test parameter acquisition, on-site data conversion, condition assessment to maintenance window prediction output. The lack of effective connection between each link makes it difficult to directly transform condition assessment results into actionable maintenance decision information.

[0007] Therefore, to solve the above problems, this invention proposes a method for predicting the preload decay and maintenance timing of flue gas turbine tie rod bolts. This method can couple and quantify high-temperature relaxation, shear fatigue and field operating conditions, realize hierarchical state evaluation from single bolt to bolt group, predict maintenance windows in advance and establish a closed-loop correction of test parameters and field data. Summary of the Invention

[0008] To address the problems existing in the prior art, this invention provides a method for predicting the preload decay and maintenance timing of flue gas turbine tie rod bolts.

[0009] According to one objective of the present invention, the present invention provides a method for predicting the preload decay and maintenance timing of flue gas turbine tie rod bolts, comprising the following steps: Obtain high-temperature loss parameters, shear fatigue loss parameters, rotor risk parameters, and on-site correction parameters; Based on the high temperature loss parameters, shear fatigue loss parameters, and field correction parameters, the high temperature loss ratio and fatigue loss ratio of each bolt are determined, and its remaining preload is calculated. Based on the current remaining preload of each bolt, calculate the average preload and preload non-uniformity index of the bolt group; The average preload and the preload non-uniformity index are compared with the safety boundary in the rotor risk parameters; Based on the rules governing the changes in the high-temperature loss ratio and fatigue loss ratio, calculations are extended to future operating conditions to predict the time when the average preload first falls below the minimum allowable average preload, or when the preload unevenness index first exceeds the maximum allowable value, and these predictions serve as suggested maintenance windows.

[0010] Preferably, the preload attenuation rule is implemented according to the following formula: Fi=F0_i×(1-H_i)×(1-S_i)×C_i Wherein, F0_i is the initial preload of the i-th bolt, H_i is the high temperature loss ratio, S_i is the fatigue loss ratio, and C_i is the field correction coefficient.

[0011] Preferably, the high-temperature loss parameter is obtained in the following way: Tie rod bolts of the same specification, material, and heat treatment state were tensioned with different initial preloads. They were then kept at the actual service temperature of the bolts for a preset time. The change in preload before and after the heat preservation was measured, and a correlation between temperature, time, and preload loss rate was established.

[0012] Preferably, the shear fatigue loss parameter is obtained in the following way: Different shear loads and cycles were applied to the flange-bolt specimens, and the changes in preload before and after the cycles were recorded to establish the relationship between shear load, number of cycles, and preload loss rate.

[0013] Preferably, the rotor risk parameters are obtained in the following manner: On a rotor test bench, the average preload and preload deviation of the bolt group are changed, and the rotor vibration amplitude, spectrum and critical speed changes are measured to determine the minimum allowable average preload and the maximum allowable coefficient of variation.

[0014] Preferably, the high-temperature loss ratio is obtained by looking up the temperature-time-preload loss rate parameter table, or calculated by an empirical formula fitted based on high-temperature relaxation test data; the coefficients in the empirical formula are calibrated by the test data.

[0015] From a physical perspective, the stress relaxation process of bolts at high temperatures can be described by the Kohlrausch-Williams-Watts relaxation function, whose general form is σ(t) = σ0·exp[-(t / τ)^β], where σ0 is the initial stress, τ is the temperature-dependent characteristic relaxation time, and β is the tensile exponent (0 < β ≤ 1). In engineering applications, to facilitate on-site calculations or programming implementation, this Kohlrausch-Watts relaxation function can be fitted into an empirical formula that includes temperature, time, and initial stress within the range of experimental data. For example, the following fitting form can be used: H_i=a0+a1·ln(1+t / t0)+a2·(T-T0)+a3·(σ0_i-σ ref ) Where t is the running time, T is the running temperature, σ0_i is the initial stress of the i-th bolt, and a0-a3, t0, T0, σ ref To obtain the constants by fitting the high-temperature holding test data described above, those skilled in the art can calibrate them through a limited number of tests based on the material and specifications of the bolts used.

[0016] Preferably, the fatigue loss ratio is obtained by referring to the shear load-cycle number-preload loss rate parameter table, or calculated by the following formula: S_i=b0+b1·ln(1+N / N0)+b2·τ / τ0 Where N is the number of start-stop cycles or shear cycles, τ is the shear load, and b0-b2, N0, and τ0 are constants obtained by fitting experimental data.

[0017] Preferably, the initial value of the on-site correction coefficient is determined based on assembly records, historical data of the same type of unit, or empirical values; When the site has ultrasonic retesting of the pre-tightening force or actual pre-tightening force F measured during disassembly and inspection. meas When _i, it is corrected according to the following formula: C_i=F meas _i / [F0_i×(1-H_i)×(1-S_i)] If there is data from multiple retests, a weighted correction is applied based on the time elapsed between the retests.

[0018] Preferably, after maintenance or retesting, the measured preload is backfilled, and the on-site correction coefficient is recalculated and updated to improve the accuracy of subsequent predictions.

[0019] Preferably, the current maintenance level is determined by comparing the average preload and the preload non-uniformity index with the safety boundary; The maintenance levels include: When the average preload is higher than the safety boundary and the preload unevenness index is lower than the corresponding threshold, the operation level is output to continue. When the average preload or the preload non-uniformity index approaches the corresponding boundary, an enhanced monitoring level is output. When the average preload is close to the minimum allowable average preload, or when the preload unevenness index is close to the maximum allowable value, the planned maintenance level is output. When the average preload is lower than the minimum allowable average preload, or the preload unevenness index exceeds the maximum allowable value, or there is abnormal vibration on site, the shutdown inspection level will be output.

[0020] Preferably, the suggested maintenance window further includes: Based on the given time point, output the remaining operating hours, the suggested retest date, and the bolt numbers that require special attention.

[0021] Compared with the prior art, the beneficial effects of the present invention are: This invention quantifies high-temperature relaxation, shear fatigue, and field variations through a preload attenuation coupling rule, establishing a complete technical chain from calculating the remaining preload of a single bolt to evaluating bolt group uniformity and correlating rotor vibration risks. This overcomes the shortcomings of existing technologies that treat each physical field separately, making it difficult to formulate actionable maintenance recommendations in the field. By obtaining fundamental parameters such as temperature-time-loss rate and load-cycle-loss rate through high-temperature holding tests and shear fatigue tests, and then combining these with a rotor test bench to determine safety boundaries such as the minimum allowable average preload and the maximum allowable coefficient of variation, the maintenance judgment criteria are no longer fixed empirical thresholds but physical boundaries directly linked to the rotor dynamic response, significantly improving the accuracy of risk identification. Compared to existing technologies that estimate based solely on fixed reduction factors or operating hours, this method, by introducing multi-parameter coupling of temperature-time-loss rate and shear load-cycle-loss rate, significantly improves the accuracy of preload attenuation prediction and provides a quantitative basis for evaluating bolt group uniformity and correlating rotor vibration risks. Based on the calculation of the remaining preload of a single bolt, this invention further introduces the average preload and preload non-uniformity index of the bolt group for comprehensive evaluation. It can identify hidden risk conditions where the average value is qualified but the local deviation is too large, and overcomes the shortcomings of existing methods that only focus on whether a single bolt is loose and lack comprehensive judgment on the average preload and coefficient of variation of the entire bolt group. This invention predicts the time when the average preload first falls below the minimum allowable value or the coefficient of variation first exceeds the maximum allowable value by extending calculations to future operating conditions. It outputs suggested maintenance windows, remaining operating hours, suggested retest dates, and bolt numbers requiring special attention. This shifts from fixed-cycle maintenance or shutdowns after abnormal vibration to predictive maintenance, enabling quantitative assessment of whether the preload is approaching the risk boundary during operation, providing directly actionable decision-making information for on-site maintenance. Furthermore, by introducing a field correction coefficient to correct for differences between test conditions and actual unit conditions, and by updating the measured preload after maintenance or retest, the model continuously adapts to the actual operational evolution of specific units. This solves the prediction deviation problem caused by inconsistencies between parameters and on-site operating conditions, ensuring long-term reliability.

[0022] The present invention will be further described below with reference to the accompanying drawings and embodiments. Attached Figure Description

[0023] Figure 1 This is a flowchart illustrating the method for predicting the preload decay and maintenance timing of flue gas turbine tie rod bolts according to the present invention. Figure 2 This diagram illustrates the input and output relationship of the preload decay rule in the method for predicting the preload decay and maintenance timing of flue gas turbine tie rod bolts according to the present invention. Detailed Implementation

[0024] The following description is intended to provide a detailed account of the invention so that those skilled in the art can implement it. The preferred embodiments described below are merely examples, and other obvious variations will occur to those skilled in the art. The basic principles of the invention defined in the following description can be applied to other embodiments, modifications, improvements, equivalents, and other technical solutions that do not depart from the spirit and scope of the invention.

[0025] like Figure 1 As shown, this invention provides a technical solution: a method for predicting the preload decay and maintenance timing of flue gas turbine tie rod bolts. The required basic parameters include high-temperature loss parameters, shear fatigue loss parameters, rotor risk parameters, and field correction parameters. These parameters collectively constitute the underlying data support required for the calculation of this method. First, the basic parameters are obtained through high-temperature holding tests, shear fatigue tests, and rotor response tests. Then, the field operating data is converted into preload loss. Finally, the remaining preload and bolt group uniformity are used to determine the maintenance timing. The calculation can be achieved using parameter tables, piecewise fitting formulas, or empirical correction coefficients.

[0026] The present invention will be described in detail below with reference to four embodiments.

[0027] Implementation Method 1: Establishing a Parameter Table High-temperature holding and shear fatigue tests were conducted on tie rod bolts of the same specification, material, and heat treatment state to obtain the preload loss ratio under different temperatures, times, loads, and cycles, forming a parameter table or fitting formula as the basis for subsequent field calculations.

[0028] The high-temperature loss parameter is used to characterize the influence of temperature and holding time on bolt preload. Specifically, it is obtained by tensioning tie rod bolts of the same specification, material, and heat treatment state with different initial preloads, holding them at the actual service temperature for a preset time, and measuring the change in preload before and after holding. A temperature-time-preload loss rate correlation is then established. The temperature is the actual operating temperature of the bolt in the flue gas turbine. In this embodiment, based on the actual operating temperature of the bolt (e.g., 650℃, 700℃, etc., the specific temperature is determined according to the actual service conditions of the unit), holding at the corresponding temperature (e.g., 40h, 200h, 1000h, etc.), measuring the change in preload before and after holding, and recording the temperature-time-preload loss rate data to form a high-temperature loss parameter table or fitting formula coefficients.

[0029] Shear fatigue loss parameters are used to characterize the decrease in additional preload caused by start-up, shutdown, vibration, and shear loads. Specifically, they are obtained by applying different shear loads and cycles to flange-bolt specimens, recording the change in preload before and after each cycle, and establishing the correlation between shear load, cycle number, and preload loss rate. Those skilled in the art can obtain shear fatigue loss parameters through conventional testing.

[0030] After completing the above two types of tests, the basic data of high temperature loss ratio and fatigue loss ratio can be obtained. The "temperature-time-loss rate" parameter table and the "shear load-cycle number-loss rate" parameter table can be directly established for on-site reference, or empirical formula coefficients can be obtained through further fitting, providing a calculation basis for subsequent on-site applications.

[0031] Implementation Method 2: Establishing Risk Boundaries Rotor risk parameters are used to characterize the correlation between the average preload and non-uniformity of the bolt group and the rotor vibration response, providing a safety boundary for subsequent maintenance judgments. Through scaled-down rotor tests, the impact of the decrease in average preload and bolt group non-uniformity on rotor vibration is determined, establishing the minimum average preload and maximum permissible CV value as the safety boundary for maintenance judgments.

[0032] Specifically, on a rotor test bench (e.g., a scaled-down rotor test bench or a full-scale rotor test bench), the average preload and preload deviation within the bolt group are varied, and the rotor vibration amplitude, spectrum, and critical speed changes are measured to determine the minimum allowable average preload and the maximum allowable coefficient of variation. In practice, a scaled-down model or a full-scale physical prototype can be selected for testing based on equipment conditions and testing requirements. Full-scale testing usually yields results closer to reality. The minimum allowable average preload and the maximum allowable coefficient of variation are obtained through rotor test bench testing, and their specific values ​​are related to the rotor structure and dimensions. Those skilled in the art can determine these values ​​through testing based on the specific unit conditions.

[0033] The above experiments directly link the mechanical state of the bolt group with the rotor's dynamic response, making subsequent maintenance judgment criteria no longer fixed empirical thresholds, but physical boundaries linked to the actual vibration risk of the rotor. This boundary, together with the parameter table established in Implementation Method 1, constitutes the complete underlying data required for field applications.

[0034] Implementation Method 3: Field Application The initial preload, operating temperature, cumulative operating time, number of start-stop cycles, and retest values ​​for each bolt are entered. Based on the parameter table obtained in Implementation Method 1 and the risk boundary obtained in Implementation Method 2, the remaining preload, CV, and maintenance window are calculated, and maintenance suggestions that can be directly executed are output.

[0035] The specific calculation process is as follows. For the i-th tie rod bolt, based on its initial preload F0_i, the high-temperature loss ratio H_i is determined based on the high-temperature loss parameter, the fatigue loss ratio S_i is determined based on the shear fatigue loss parameter, and combined with the field correction parameters, the current remaining preload Fi is calculated according to the preload decay rule. See [link / reference] Figure 2 In this embodiment, the preload attenuation rule is implemented according to the following formula: Fi=F0_i×(1-H_i)×(1-S_i)×C_i Wherein, F0_i is the initial preload of the i-th bolt, H_i is the high temperature loss ratio, S_i is the fatigue loss ratio, and C_i is the field correction coefficient, which is used to correct the difference between the test conditions and the actual unit operating conditions. Its initial value is determined based on the assembly record, ultrasonic retest record, disassembly and inspection record, re-tightening record, historical data of the same model of unit, or empirical value.

[0036] The high-temperature stress reduction ratio H_i can be obtained by interpolation from the "temperature-time-loss rate" parameter table, or calculated using an empirical formula fitted based on high-temperature relaxation test data. From a physical perspective, the stress relaxation process of a bolt at high temperatures can be described by the Kohlrausch-Williams-Watts relaxation function, whose general form is σ(t)=σ0·exp[-(t / τ)^β], where σ0 is the initial stress, τ is the temperature-dependent characteristic relaxation time, and β is the tensile exponent (0<β≤1). In engineering applications, this KWW relaxation function can be fitted into an empirical formula that includes temperature, time, and initial stress within the scope of experimental data, for example: H_i=a0+a1·ln(1+t / t0)+a2·(T-T0)+a3·(σ0_i-σ ref ) Where t is the running time, T is the running temperature, σ0_i is the initial stress of the i-th bolt, and a0-a3, t0, T0, σ ref The values ​​of H_i are obtained by fitting experimental data, and the range of values ​​is determined based on the experimental boundaries. All the above parameters are constants obtained by fitting high-temperature holding test data. Those skilled in the art can calibrate them through a limited number of tests based on the specific material and specifications of the bolts used, without requiring creative effort.

[0037] The fatigue loss ratio S_i can be obtained by interpolation from the "shear load - number of cycles - loss rate" parameter table, or it can be calculated using the following formula: S_i=b0+b1·ln(1+N / N0)+b2·τ / τ0 Where N represents the number of start-stop cycles or shear cycles, τ represents the shear load, b0-b2, N0, and τ0 are obtained by fitting experimental data, and the range of S_i is determined based on the experimental boundaries. These parameters are obtained by fitting shear fatigue test data and can be calibrated by those skilled in the art through conventional fatigue tests on flange-bolt specimens.

[0038] After calculating Fi for each bolt individually, the average preload Favg, maximum deviation Dmax, and coefficient of variation CV of the bolt group are further calculated. Favg is used to determine if the overall tension capacity of the group is insufficient, while Dmax and CV are used to determine if the preload of each bolt is excessively uneven. Based on this, the average preload Favg and the preload unevenness index (CV and / or Dmax) are compared with the safety boundary in the rotor risk parameters to determine the current maintenance level.

[0039] Specifically, the maintenance level can adopt a four-level output: when the average preload is higher than the safety boundary and the coefficient of variation (CV) is lower than the corresponding threshold, it is recommended to continue operation; when the average preload or CV is close to the corresponding boundary, it is recommended to strengthen monitoring; when the average preload is close to the minimum allowable average preload, or the CV is close to the maximum allowable value, it is recommended to plan maintenance; when the average preload is lower than the minimum allowable average preload, the CV exceeds the maximum allowable value, or there is abnormal vibration on site, it is recommended to stop the machine for inspection, retightening, or replacement. "Close to" refers to reaching the corresponding safety boundary preset percentage threshold, such as 80%~90%, the specific value of which is determined by the operation and maintenance strategy.

[0040] Furthermore, after obtaining Fi, Favg, and CV at the current moment, the calculation is extended to future operating conditions according to the same rules governing the changes in high-temperature loss ratio and fatigue loss ratio as described above. Assuming that future operating temperatures, start-stop frequencies, and other operating conditions continue with the current trends, the system calculates the time point at which the average preload Favg first falls below the minimum allowable average preload, or the coefficient of variation CV first exceeds the maximum allowable CV value. This time point is the upper limit of the recommended maintenance window. Simultaneously, based on this time point, the system outputs the remaining operating hours, the recommended retest date, and the bolt numbers requiring special attention, thus generating maintenance decision-making information that can directly guide on-site operation and maintenance.

[0041] Implementation Method 4: Rolling Correction After the unit is in operation or undergoes maintenance and testing, the actual preload is backfilled to correct the on-site correction coefficient, improve the accuracy of the next prediction, and enable this method to continuously adapt to the actual operating evolution of the unit.

[0042] In the above calculation process, the initial value of the on-site correction coefficient C_i is determined based on assembly records, historical data of the same model of unit, or empirical values. When the on-site ultrasonic re-measurement preload F... meas When inspecting or measuring the preload, C_i should be corrected according to the following formula: C_i=F meas _i / [F0_i×(1-H_i)×(1-S_i)] If multiple retest data are available, a weighted correction is applied based on the time elapsed between retests to ensure the calculation results closely reflect the specific unit. After maintenance or retesting, the measured preload is backfilled, and the on-site correction coefficients are recalculated and updated to improve the accuracy of subsequent predictions, thus forming a rolling parameter update mechanism.

[0043] Validation data To verify the effectiveness of this method, the following multi-dimensional verifications were conducted.

[0044] Supporting testing methods include: high-temperature holding test, shear fatigue test, rotor response test, and comprehensive prediction verification. During comprehensive verification, a parameter table can be established using the load data from the first two time points or the first few load levels. Then, the remaining preload at subsequent time points or higher cycle numbers can be predicted and compared with the measured values. The embodiments described above are only used to illustrate the technical ideas and features of the present invention. Their purpose is to enable those skilled in the art to understand the content of the present invention and implement it accordingly. The scope of patent application of the present invention should not be limited by these embodiments. That is, any equivalent changes or modifications made in accordance with the spirit disclosed in the present invention still fall within the patent scope of the present invention.

Claims

1. A method for predicting the attenuation of preload on flue gas turbine tie rod bolts and the timing of maintenance, characterized in that, Includes the following steps: Obtain high-temperature loss parameters, shear fatigue loss parameters, rotor risk parameters, and on-site correction parameters; Based on the high temperature loss parameters, shear fatigue loss parameters, and field correction parameters, the high temperature loss ratio and fatigue loss ratio of each bolt are determined, and its remaining preload is calculated. Based on the current remaining preload of each bolt, calculate the average preload and preload non-uniformity index of the bolt group; The average preload and the preload non-uniformity index are compared with the safety boundary in the rotor risk parameters; Based on the rules governing the changes in the high-temperature loss ratio and fatigue loss ratio, calculations are extended to future operating conditions to predict the time when the average preload first falls below the minimum allowable average preload, or when the preload unevenness index first exceeds the maximum allowable value, and these predictions serve as suggested maintenance windows.

2. The method according to claim 1, characterized in that, The preload attenuation rule is implemented according to the following formula: Fi=F0_i×(1-H_i)×(1-S_i)×C_i Wherein, F0_i is the initial preload of the i-th bolt, H_i is the high temperature loss ratio, S_i is the fatigue loss ratio, and C_i is the field correction coefficient.

3. The method according to claim 1, characterized in that, The high-temperature loss parameters are obtained through the following methods: Tie rod bolts of the same specification, material, and heat treatment state were tensioned with different initial preloads. They were then kept at the actual service temperature of the bolts for a preset time. The change in preload before and after the heat preservation was measured, and a correlation between temperature, time, and preload loss rate was established.

4. The method according to claim 1, characterized in that, The shear fatigue loss parameters are obtained in the following way: Different shear loads and cycles were applied to the flange-bolt specimens, and the changes in preload before and after the cycles were recorded to establish the relationship between shear load, number of cycles, and preload loss rate.

5. The method according to claim 1, characterized in that, The rotor risk parameters are obtained through the following methods: On a rotor test bench, the average preload and preload deviation of the bolt group are changed, and the rotor vibration amplitude, spectrum and critical speed changes are measured to determine the minimum allowable average preload and the maximum allowable coefficient of variation.

6. The method according to claim 1, characterized in that, The high-temperature loss ratio is obtained by referring to the temperature-time-preload loss rate parameter table, or by calculating it using an empirical formula fitted based on high-temperature relaxation test data; the coefficients in the empirical formula are calibrated by the test data.

7. The method according to claim 1, characterized in that, The fatigue loss ratio is obtained by referring to the shear load-cycle number-preload loss rate parameter table, or calculated using the following formula: S_i=b0+b1·ln(1+N / N0)+b2·τ / τ0 Where N is the number of start-stop cycles or shear cycles, τ is the shear load, and b0-b2, N0, and τ0 are constants obtained by fitting experimental data.

8. The method according to claim 2, characterized in that, The initial value of the on-site correction coefficient is determined based on assembly records, historical data of the same type of unit, or empirical values. When the site has ultrasonic retesting of the pre-tightening force or actual pre-tightening force F measured during disassembly and inspection. meas When _i, it is corrected according to the following formula: C_i=F meas _i / [F0_i×(1-H_i)×(1-S_i)] If there is data from multiple retests, a weighted correction is applied based on the time elapsed between the retests.

9. The method according to claim 1, characterized in that, After maintenance or retesting, the measured preload is backfilled, and the on-site correction coefficient is recalculated and updated to improve the accuracy of subsequent predictions.

10. The method according to claim 1, characterized in that, The current maintenance level is determined by comparing the average preload and the preload non-uniformity index with the safety boundary. The maintenance levels include: When the average preload is higher than the safety boundary and the preload unevenness index is lower than the corresponding threshold, the operation level is output to continue. When the average preload or the preload non-uniformity index approaches the corresponding boundary, an enhanced monitoring level is output. When the average preload is close to the minimum allowable average preload, or when the preload unevenness index is close to the maximum allowable value, the planned maintenance level is output. When the average preload is lower than the minimum allowable average preload, or the preload unevenness index exceeds the maximum allowable value, or there is abnormal vibration on site, the shutdown inspection level will be output.

11. The method according to claim 1, characterized in that, The recommended maintenance window also includes: Based on the given time point, output the remaining operating hours, the suggested retest date, and the bolt numbers that require special attention.