A single-well production division method and system under the condition of platform well gas volume co-metering
By combining multi-factor calculations and total closure constraints, the problem of high accuracy and auditability of single-well production classification in offshore oil and gas fields has been solved. It has achieved high accuracy and interpretability of single-well production classification without adding new facilities, thus improving the robustness and compliance of the system.
Patent Information
- Application Number
- CN202611453578.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-18
- Publication Date
- 2026-11-24
AI Technical Summary
In the production management of offshore oil and gas fields and onshore gathering and transportation stations, existing technologies cannot achieve high-precision, interpretable, and auditable single-well production classification without adding new single-well continuous metering facilities. Especially when facing dynamic scenarios such as high gas-water ratio, intermittent production, or newly commissioned wells, there are problems such as low time resolution, poor representativeness, and physical inconsistency, and they cannot meet high compliance requirements.
By acquiring the total gas volume and operating data of each individual well from the platform, candidate contribution amounts are calculated using a combination of multiple factors such as throttling opening, differential pressure drive, pressure stability, historical capacity, and data reliability. Combined with total closure constraints, production is divided using a weighted product or weighted summation model. Abnormal data is eliminated by combining a state gating mechanism, and an anomaly correction mechanism is introduced to meet the quality conservation requirement, generating traceable audit records.
It enables high-precision, interpretable, and auditable dynamic allocation of single-well production without adding new facilities, improving the physical consistency and engineering interpretability of production allocation, enhancing the system's robustness to edge scenarios, and meeting high compliance requirements.
Smart Images

Figure CN123159130A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of natural gas production statistics technology, specifically to a method and system for classifying single-well production under the condition of joint metering of gas volume in platform wells. Background Technology
[0002] In the production management of offshore oil and gas fields and onshore gathering and transportation stations, platform-level gas volume metering typically adopts a unified metering method after manifolding, where the produced gas flows from multiple wells are mixed and then measured in total using the same flow meter. While this shared metering model reduces hardware investment and maintenance costs, it also makes it impossible to directly obtain real-time production data from each individual well. To achieve refined production allocation, dynamic analysis, and performance evaluation, the platform's total gas volume must be rationally allocated to each individual well. Currently, the industry mainly relies on two traditional methods: one is to install an independent flow meter for each well, but due to limitations in offshore platform space, load-bearing capacity, and safety regulations, large-scale installation is neither economical nor practical; the other is to use a periodic well rotation testing method, obtaining instantaneous production by briefly switching the metering separator between individual wells and then extrapolating it to the entire cycle. However, this method suffers from problems such as a short testing window, poor representativeness, and disruption to normal production rhythm, and it cannot reflect production changes caused by operating condition fluctuations, equipment failures, or parameter adjustments during non-testing periods, resulting in a serious disconnect between the allocation results and the actual production status.
[0003] To address the aforementioned issues, various alternative or auxiliary solutions have emerged in existing technologies. For example, some patents focus on booster process optimization or equipment health diagnosis, involving single-well parameter monitoring, but lacking a production allocation mechanism under total gas volume constraints. Other technologies propose a static splitting coefficient method based on stratified test data, but this assumes a constant contribution ratio for each stratum, making it difficult to adapt to dynamic scenarios such as high gas-water ratios, intermittent production, or newly commissioned wells. Further research attempts to introduce virtual metering or soft measurement models, using historical data to train regression relationships, but these generally lack explicit guarantees for real-time state gating, anomaly data identification, and total physical conservation within the metering cycle, leading to model outputs that may violate engineering common sense and lack traceability. Furthermore, most existing methods do not consider the requirements for data link integrity verification and audit trails, failing to provide verifiable calculation processes and decision-making basis when facing regulatory reviews, trade disputes, or internal debriefings, thus limiting their practical application in scenarios with high compliance requirements.
[0004] Therefore, there is an urgent need for a method and system for classifying single-well production under the condition of joint metering of gas volume in platform wells. This method should be able to achieve high-precision, interpretable, and auditable dynamic classification of single-well production by comprehensively utilizing existing operating data without adding new continuous metering facilities for each well. This can be achieved through state awareness, multi-factor contribution quantification, total volume closure constraints, and anomaly adaptive correction. The method should not only overcome the temporal resolution deficiencies of traditional well-cycle testing and the physical inconsistencies of pure data-driven models, but also possess robust handling capabilities for edge conditions (such as new well commissioning, sensor drift, and total meter anomalies), and simultaneously generate complete calculation trajectory records to meet the comprehensive needs of modern oil and gas fields for transparent, compliant, and intelligent production metering. Summary of the Invention
[0005] This invention discloses a method and system for classifying single-well production under the condition of joint metering of gas volume in platform wells.
[0006] The method includes the following steps:
[0007] S1. Obtain the total gas volume jointly measured by the platform and the operating data of each individual well within the metering cycle; S2. Determine the effective production well set to participate in the division in the current metering cycle based on the operating data of each individual well; S3. Calculate the candidate contribution of each individual well based on the operating data of each individual well in the effective production well set; S4. Using the total gas volume jointly measured by the platform as the constraint boundary, perform closed division of production of the effective production well set according to the candidate contribution, and obtain the gas volume of each individual well; wherein, the sum of the gas volumes of each individual well is equal to the total gas volume jointly measured by the platform.
[0008] Furthermore, in step S3, the candidate contribution is calculated by a combination of at least two of the following factors: throttle opening factor, which characterizes the mapping relationship between the throttle valve opening of a single well and its gas production capacity; differential pressure driving factor, which characterizes the driving strength of the single well's production differential pressure on the instantaneous flow rate; pressure stability factor, which characterizes the impact of the degree of pressure fluctuation of a single well on the reliability of the measurement within the measurement period; historical capacity factor, which characterizes the benchmark production capacity level of a single well during the historical stable production stage; and data reliability factor, which characterizes the integrity and abnormal state of the single well's operating condition data acquisition link.
[0009] Furthermore, the combined calculation adopts a weighted product model or a weighted summation model, and the weight coefficients of each factor are determined by one of the following methods: regression calibration based on historical well test data; adaptive adjustment based on correlation analysis of multi-well dynamic response; or preset based on expert experience rules and corrected according to actual deviation feedback.
[0010] Furthermore, in step S2, the specific rules for determining the effective production well set include: removing single wells that are in a shut-in state, have zero throttle valve opening, or are in a communication interruption state; applying weight reduction processing or marking as a transitional state well to single wells that have not resumed production for a preset time; applying weight reduction processing or marking as a suspicious well to single wells whose operating data drift exceeds a preset threshold; and including the remaining single wells into the effective production well set.
[0011] Furthermore, after step S4, there is also an anomaly correction step: when the deviation between the sum of candidate contributions and the total gas volume jointly measured by the platform exceeds the preset validity threshold, the anomaly correction mechanism is triggered; the anomaly correction mechanism includes at least one of the following: enabling fallback weight allocation, time-segmented back calculation, or introducing data from adjacent metering cycles for smooth compensation; after correction, step S4 is re-executed until the constraint boundary is met or the maximum number of iterations is reached.
[0012] Furthermore, the anomaly correction steps also include: recording the cause of the anomaly, the basis for the correction strategy selection, and a comparison of data before and after the correction; and outputting the records as audit metadata and the gas volume allocation for each individual well simultaneously.
[0013] Furthermore, in step S4, the production closure division adopts the proportional normalization method, and the specific formula is as follows:
[0014]
[0015] in, For the first Gas volume is allocated to a single well. The platform will jointly measure the total gas volume. For the first Single well candidate contribution. It is the sum of the candidate contributions of all single wells in the effective production well cluster.
[0016] Furthermore, in step S1, the operating data of each single well includes throttle valve opening, oil pressure, casing pressure, temperature and valve status signals, and all data are aligned to a unified timestamp and converted into standard status parameters.
[0017] Furthermore, the method also includes: generating traceable audit records, which include: input data snapshots, calculation parameter version numbers, status gating judgment results, anomaly tags, and review operation logs; the audit records are bound to the gas volume of each single well and stored, and support post-event backtracking verification.
[0018] The system provided by this invention includes:
[0019] The data acquisition module is used to acquire the total gas volume jointly measured by the platform and the operating data of each individual well within the metering cycle; the status gating module is used to determine the effective production well set to be divided in the current metering cycle based on the operating data of each individual well; the contribution calculation module is used to calculate the candidate contribution of each individual well based on the operating data of each individual well in the effective production well set; the total gas volume boundary module is used to perform production closure division of the effective production well set based on the candidate contribution, with the total gas volume jointly measured by the platform as the constraint boundary, to obtain the gas volume of each individual well, and to ensure that the sum of the gas volumes of each individual well is equal to the total gas volume jointly measured by the platform.
[0020] Beneficial Effects: The method disclosed in this invention constructs a core technical architecture of "state gating—multi-factor candidate contribution—total closed-loop partitioning," achieving dynamic and high-precision partitioning of single-well production under platform-wide joint metering conditions without adding new single-well continuous metering facilities. This effectively overcomes the shortcomings of traditional well-cycle testing, such as low time resolution, poor representativeness, and the lack of physical constraints in pure data-driven models. By introducing multi-dimensional factors such as throttling opening, differential pressure drive, pressure stability, historical capability, and data reliability to calculate candidate contributions, and combining this with total closed-loop constraints, the partitioning results strictly satisfy quality conservation. This significantly improves the physical consistency and engineering interpretability of production allocation. Simultaneously, the built-in state gating mechanism automatically eliminates invalid or abnormal operating condition data. Combined with anomaly correction and fallback strategies, it enhances the system's robustness to edge scenarios such as new well commissioning, sensor drift, and master meter failures. Furthermore, the entire process synchronously generates traceable audit records including input snapshots, parameter versions, anomaly tags, and review logs, making the allocation process transparent and verifiable. This meets the comprehensive needs for transparent, auditable, and intelligent production measurement in high-compliance scenarios, providing a reliable data source for refined production allocation, dynamic analysis, and performance evaluation.
[0021] It should be noted that the terms "first," "second," and similar terms used in this article are merely for describing the constituent elements of the technical solution and do not constitute a limitation on the technical solution, nor should they be interpreted as an indication or implication of the importance of the corresponding elements; elements with terms such as "first," "second," or similar terms indicate that at least one of the elements is included in the corresponding technical solution. Attached Figure Description
[0022] To more clearly illustrate the technical solution of the present invention and facilitate a further understanding of its technical effects, features, and objectives, the present invention will be described in detail below with reference to the accompanying drawings. The drawings constitute an essential part of the specification and are used together with Embodiment 1 of the present invention to illustrate the technical solution of the present invention, but do not constitute a limitation on the present invention.
[0023] Figure 1 This is a flowchart of an embodiment of the method of the present invention;
[0024] Figure 2 This is a schematic diagram of the topology of an embodiment of the system of the present invention. Detailed Implementation
[0025] The present invention will be further described in detail below with reference to the accompanying drawings and embodiments. Of course, the specific embodiments described below are merely illustrative of the technical solutions of the present invention, and not intended to limit the present invention. Furthermore, the parts described in the embodiments or drawings are merely illustrative examples of relevant parts of the present invention, and not the entirety of the present invention. At the same time, all other embodiments obtained by those skilled in the art based on the embodiments of the present invention should naturally fall within the protection scope of the present invention.
[0026] Example 1
[0027] In this embodiment, as Figure 1 As shown in the flowchart, this embodiment of the invention discloses a method for dividing the production of a single well under the condition of joint metering of gas volume in platform wells, which includes the following steps:
[0028] S1. Obtain the total gas volume jointly measured by the platform and the operating data of each individual well within the metering cycle. In this embodiment, the metering cycle is set to 24 hours, and the total gas volume jointly measured by the platform... The cumulative values are taken from the standard orifice plate flowmeter after the manifold and have been converted to standard conditions (20℃, 101.325 kPa). Operating data for each well are collected via the gas well's control system at a frequency of 1 minute per acquisition, including throttle valve opening. Hydraulic , sleeve pressure ,temperature and valve switch status signals subscript Indicates the first A single well, This represents the timestamp. Simultaneously, all raw data undergoes the following preprocessing before being stored in the time-series database: 1. Timestamp alignment: using whole minutes as the baseline, linear interpolation is performed on missing sampling points, and the mean is taken for redundant sampling points; 2. Outlier removal: using... The criteria identify and remove outliers, and fill the empty spaces after removal with a weighted average of the effective values before and after; 3. Standard state conversion: convert the operating volume flow rate to the standard state volume flow rate based on the real-time temperature and pressure. The conversion formula follows GB / T21446-2008 "Measurement of natural gas flow rate with standard orifice plate flow meter".
[0029] S2. Determine the effective production well set for the current metering cycle based on the operating data of each individual well. The status gating module determines the set well by well according to the following rules:
[0030] 1. Hard rejection criteria: If any of the following conditions are met, the valid production well set will be directly excluded: Valve status signal The "off" state accounts for ≥95% of the metering cycle; throttle valve opening degree The duration of 0% or more is ≥23 hours; the cumulative duration of communication interruption is ≥30 minutes.
[0031] 2. Transitional state marking and deweighting conditions: the time required for a single well to resume production after switching from "off" to "on". (This embodiment is set) If the value is less than 1 hour, it is marked as a "transitional well", and a weighting factor is applied when calculating its subsequent candidate contribution. .
[0032] 3. Suspicious well marking and deweighting conditions: if the oil pressure fluctuation rate during the measurement period... (This embodiment is set) or the magnitude of temperature change (This embodiment is set) If a well is marked as "suspicious," a weighting factor is applied. .
[0033] 4. Inclusion criteria for effective wells: Single wells that have not been forcibly removed and have completed the above-mentioned marking process are included in the effective production well set. .
[0034] In this embodiment, the platform has a total of 12 wells. After status gating: Well No. 3 was removed because all valves were closed; Well No. 7 was opened at 10:00 AM on the same day, and production was restored for less than 2 hours, so it was marked as transitional; Well No. 11 had an oil pressure fluctuation rate of 18%, so it was marked as suspicious; the remaining 9 wells were normal wells. Therefore... The classification includes 11 wells: 9 normal wells, 1 transitional well, and 1 suspected well.
[0035] S3. Based on the operating data of each well in the effective production well cluster, calculate the candidate contribution of each well. Specifically, this embodiment uses a weighted product model, selecting five types of factor combinations to calculate the first... Candidate contribution of a single well The calculation formula is as follows:
[0036]
[0037] in, The total number of factors, For the first Class factor value, For the corresponding weight coefficients, and satisfying The definitions and calculation methods for each factor are as follows:
[0038] 1. Throttling opening factor Based on the flow characteristic curve (equal percentage type) provided by the valve manufacturer, the average opening degree within the metering period is used. Relative circulation capacity can be obtained by looking up the table. Then normalize to the [0,1] interval:
[0039]
[0040] 2. Pressure difference driving factor The driving force of the production pressure differential on the instantaneous flow rate is characterized by the following formula:
[0041]
[0042] in, The average oil pressure during the metering cycle. Due to pipeline pressure, To design the maximum production pressure differential.
[0043] 3. Pressure stabilizing factor The formula for characterizing the impact of pressure fluctuations on measurement reliability is as follows:
[0044]
[0045] It's worth noting that when volatility exceeds a threshold, this factor automatically decreases, reflecting a decline in data quality.
[0046] 4. Historical ability factor : Take the average daily production during the past 30 days of stable production (excluding testing, well shut-in, and abnormal periods). Normalized to the current maximum value of the effective well set:
[0047]
[0048] 5. Data credibility factor Assign a value based on the state gating result: Normal well Transitional well Suspicious well .
[0049] Factor weight coefficients The values obtained through regression calibration using historical well test data are as follows: , , , , The weighting process employs a nonlinear least squares method, with the objective function being to minimize the weighted square error between historically classified gas volume and the measured gas volume from well rotation tests.
[0050] S4. Using the total gas volume jointly measured by the platform as the constraint boundary, perform a closed-loop division of production output. Specifically, the proportional normalization method is used to ensure that the division result strictly satisfies the law of conservation of mass. The calculation formula is as follows:
[0051]
[0052] in, For the first Gas volume is allocated to a single well. The total gas volume is jointly measured by the platform, with the denominator being the sum of the candidate contributions from all single wells in the effective production well pool. As can be seen from the formula, Heng was established.
[0053] S5. Anomaly Correction and Audit Output. Calculate the relative deviation between the sum of candidate contributions and the total gas volume. :
[0054]
[0055] like (This embodiment is set) If the error occurs, the anomaly correction mechanism is triggered. The correction strategies, in order of priority, are as follows: ① Activate fallback weight allocation (increase the weight of the historical capability factor to 0.5, and compress the weights of other factors proportionally); ② Perform time-segmented backcalculation (divide the 24 hours into four 6-hour sub-cycles, execute s2-s4 respectively, and then perform a weighted sum); ③ Introduce data from adjacent measurement cycles for smoothing compensation (take 30% of the previous cycle's division result as a priori constraint). After correction, s4 is executed again until... Or reach the maximum number of iterations (set to 3 in this embodiment).
[0056] It's worth noting that regardless of whether a correction is triggered, the system automatically generates traceable audit records, including: a snapshot of the input data (containing the original operating conditions of 12 wells and the total meter readings), the version number of the calculation parameters (v2.3.1), the status gating judgment results (9 normal + 1 transitional + 1 suspicious), anomaly tags (none / present and type), the basis for the correction strategy selection, a comparison of data before and after the correction, and a review operation log (automatic execution / manual confirmation). These audit records are linked to the gas volume allocated to each individual well and stored in an independent audit database, supporting multi-dimensional backtracking verification by time, well number, anomaly type, and other dimensions.
[0057] In this embodiment, If no correction is triggered, the system will automatically complete the partitioning and generate a complete audit record.
[0058] Example 2
[0059] Building upon Example 1, this example further provides an online adaptive adjustment method for weight coefficients. When the deviation between the division results of n consecutive measurement cycles (n=7 in this example) and the subsequent well test data exceeds a preset threshold, the system automatically initiates the weight recalibration process:
[0060] 1. Collect the most recent m valid well test samples (m=20 in this embodiment); 2. Construct a multi-well dynamic response correlation matrix and analyze the Pearson correlation coefficient between each factor and the actual production; 3. Using the correlation coefficient as the initial weight, optimize using a constrained gradient descent method, with the following constraints: and 4. The new weights will take effect after manual review and the version change log will be recorded.
[0061] This mechanism enables the model to adapt to long-term changes such as formation pressure decay, equipment aging, and process adjustments, avoiding systematic biases caused by fixed weights.
[0062] Example 3
[0063] like Figure 2 As shown, the single-well production division system provided in this embodiment includes a data acquisition module, a status gating module, a contribution calculation module, and a total gas volume boundary module, as well as an anomaly correction module and an audit output module. Specifically, the data acquisition module acquires the total gas volume jointly measured by the platform and the operating data of each single well within the metering cycle; the status gating module determines the effective production well set participating in the division for the current metering cycle based on the operating data of each single well; the contribution calculation module calculates the candidate contribution of each single well based on the operating data of each single well in the effective production well set; the total gas volume boundary module performs closed-loop division of the effective production well set based on the candidate contribution, using the total gas volume jointly measured by the platform as the constraint boundary, to obtain the divided gas volume of each single well, ensuring that the sum of the divided gas volumes of each single well equals the total gas volume jointly measured by the platform; the anomaly correction module triggers a correction mechanism and re-divides the wells when the deviation between the sum of the candidate contribution and the total gas volume exceeds the limit; and the audit output module generates and binds traceable audit records for storage.
[0064] It should be noted that the above embodiments are only for more clearly illustrating the technical solution of the present invention. Those skilled in the art will understand that the implementation of the present invention is not limited to the above content. Any obvious changes, substitutions or replacements made based on the above content do not exceed the scope of the technical solution of the present invention. Other implementations will also fall within the scope of the present invention without departing from the concept of the present invention.
Claims
1. A method for dividing single-well production under the condition of joint metering of gas volume in platform wells, characterized in that, include: S1. Obtain the total gas volume measured by the platform and the operating conditions of each individual well within the metering cycle. S2. Determine the effective production well set to be divided in the current metering cycle based on the operating data of each single well. S3. Based on the operating data of each individual well in the effective production well set, calculate the candidate contribution of each individual well; S4. Using the total gas volume jointly measured by the platform as the constraint boundary, perform closed-loop division of the effective production well set according to the candidate contribution amount to obtain the gas volume of each individual well. The sum of the gas volumes allocated to each individual well is equal to the total gas volume measured by the platform.
2. The method according to claim 1, characterized in that, In step S3, the candidate contribution is calculated from at least two combinations of the following factors: Throttling opening factor characterizes the mapping relationship between the opening degree of a single well's throttle valve and its gas production capacity; Differential pressure driving factor characterizes the driving strength of single-well production differential pressure on instantaneous flow rate; The pressure stability factor characterizes the impact of single-well pressure fluctuations on measurement reliability during the measurement period. Historical capacity factor, which characterizes the baseline production capacity level of a single well during its historical stable production phase; The data reliability factor characterizes the integrity and abnormal status of the data acquisition link for a single well.
3. The method according to claim 2, characterized in that, The combined calculation employs a weighted product model or a weighted summation model, and the weight coefficients of each factor are determined using one of the following methods: Regression calibration based on historical well test data; Adaptive adjustment based on correlation analysis of dynamic response of multiple wells; The rules are preset based on expert experience and corrected according to actual deviation feedback.
4. The method according to claim 1, characterized in that, In step S2, the specific rules for determining the effective production well set include: Remove wells that are shut in, have zero throttle valve opening, or are in a state of communication interruption; For wells that fail to resume production within the preset time, apply a weight reduction treatment or mark them as transitional wells; For single wells whose operating data drift exceeds a preset threshold, apply a weight reduction process or mark them as suspicious wells; The remaining individual wells are included in the effective production well set.
5. The method according to claim 1, characterized in that, Step S4 is followed by an anomaly correction step: When the deviation between the sum of the candidate contributions and the total gas volume jointly measured by the platform exceeds a preset validity threshold, an anomaly correction mechanism is triggered. The anomaly correction mechanism includes at least one of the following: enabling fallback weight allocation, time-segmented back calculation, or introducing data from adjacent metering periods for smoothing compensation. After correction, step S4 is re-executed until the constraint boundary is satisfied or the maximum number of iterations is reached.
6. The method according to claim 5, characterized in that, The anomaly correction step also includes: Record the reasons for the anomaly, the basis for selecting the correction strategy, and a comparison of data before and after the correction; The records are output synchronously as audit metadata along with the gas volume allocation for each individual well.
7. The method according to claim 1, characterized in that, In step S4, the production closure division adopts the proportional normalization method, and the specific formula is as follows: in, For the first Gas volume is allocated to a single well. The platform will jointly measure the total gas volume. For the first Single well candidate contribution. It is the sum of the candidate contributions of all single wells in the effective production well cluster.
8. The method according to claim 1, characterized in that, In step S1, the operating data of each single well includes throttle valve opening, oil pressure, casing pressure, temperature and valve status signal, and all data are aligned to a unified timestamp and converted into standard status parameters.
9. The method according to any one of claims 1 to 8, characterized in that, The method further includes: Generate traceable audit records, which include: input data snapshots, calculation parameter version numbers, status gating judgment results, anomaly tags, and review operation logs; The audit records are linked to the gas volume of each individual well and are stored in a manner that supports retrospective verification.
10. A single-well production allocation system under the condition of joint metering of gas volume in platform wells, used to implement the method described in any one of claims 1 to 9, characterized in that, include: The data acquisition module is used to acquire the total gas volume measured by the platform and the operating data of each individual well within the metering cycle; The status gating module is used to determine the effective production well set to be divided in the current metering cycle based on the operating data of each single well. The contribution calculation module is used to calculate the candidate contribution of each well based on the operating data of each well in the effective production well set. The total gas volume boundary module is used to perform production closure division of the effective production well set according to the candidate contribution amount, with the total gas volume jointly measured by the platform as the constraint boundary, to obtain the gas volume of each individual well, and to ensure that the sum of the gas volumes of each individual well is equal to the total gas volume jointly measured by the platform.