Dynamic calculation and optimization method and system for construction fuel consumption of a trailing suction dredger
By deconstructing the construction process into discrete operation stages and combining multi-source data fusion and dynamic correction coefficients, refined management of fuel consumption of trailing suction hopper dredgers has been achieved, solving the problems of extensive fuel consumption management and lack of real-time guidance in existing technologies, and improving the level of energy efficiency management.
Patent Information
- Application Number
- CN202610982060.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-02
- Publication Date
- 2026-11-24
AI Technical Summary
Existing technologies for trailing suction hopper dredgers have a crude approach to fuel consumption management, lacking real-time guidance and dynamic analysis. This results in lagging fuel consumption control, difficulty in scientifically assessing the impact of construction processes on fuel consumption, and an inability to achieve precise energy efficiency management.
By deconstructing the construction process into discrete operation stages and combining multi-source data fusion, fuel consumption at each stage is calculated in real time. A dynamic correction coefficient is introduced to generate a high-precision fuel consumption index, providing real-time energy efficiency assessment and operation optimization.
It enables refined management of fuel consumption for trailing suction hopper dredgers, can promptly reflect the impact of operational changes on energy consumption, provide real-time optimization suggestions, reduce operating costs, and improve energy efficiency management.
Smart Images

Figure CN123159587A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of dredging equipment and energy-saving technology, and in particular to a dynamic calculation and optimization method and system for fuel consumption per 10,000 cubic meters of dredging vessel. More specifically, this invention combines Internet of Things technology, edge computing platform and data analysis algorithm to realize real-time monitoring, accurate calculation and operation optimization of fuel consumption of dredging vessel, which is applicable to intelligent management and energy conservation and emission reduction of dredging projects. Background Technology
[0002] Trailing suction hopper dredgers are the main type of vessel used in dredging projects, and are widely used in port and waterway dredging, land reclamation, and other projects. Their fuel costs account for 30% to 50% of their total operating costs, making fuel consumption management crucial. However, current industry management of trailing suction hopper rig fuel consumption is generally quite rudimentary, with the following main problems: 1. Rough measurement: Existing methods typically use monthly or quarterly static statistics of "total fuel consumption / total output," which cannot reflect the true fuel consumption level under different working conditions and operations in a single construction cycle, making it difficult to detect abnormal fuel consumption in a timely manner; 2. Isolated factors: Fuel consumption is strongly correlated with multiple factors such as vessel navigation status (speed, load), equipment operation (mud pump speed, drag head pressure), soil conditions, and sea conditions, but existing methods lack models that can unify and analyze these dynamic factors; 3. Lack of real-time guidance: Current systems are mostly based on post-event statistics, unable to provide captains and operators with real-time energy efficiency data and optimization suggestions during construction, resulting in lagging fuel consumption control; 4. Insufficient optimization basis: Existing solutions are difficult to scientifically assess the impact of different construction techniques (such as overflow control strategies), speed, and loading strategies on fuel consumption, and energy-saving optimization lacks data support, relying on experience-based judgment. Therefore, there is an urgent need for a dynamic method and system that can calculate the fuel consumption of trailing suction hopper dredgers in real time, accurately and itemized, and guide energy-saving operations, so as to reduce operating costs and improve energy efficiency management. Summary of the Invention
[0003] This invention provides a method and system for dynamic calculation and optimization of fuel consumption per 10,000 cubic meters of dredger. By deconstructing the continuous construction process into discrete operation stages with distinct energy consumption characteristics, the fuel consumption of each stage is dynamically calculated in real time through multi-source data fusion. Combined with the corrected effective dredging volume, a high-precision fuel consumption index per 10,000 cubic meters is generated, thereby achieving energy efficiency assessment and operation optimization.
[0004] The dynamic calculation and optimization method for fuel consumption per 10,000 cubic meters of dredger operation includes the following steps: S1: Intelligent identification and division of construction phase: Based on the data flow of the ship's integrated automation system, a predefined rule engine is used to determine the current construction phase in real time; S2: Real-time acquisition of multi-source energy consumption data and dynamic calculation of fuel consumption at each stage: Based on the identified construction stages, the ship's integrated automation system collects equipment power data and operating parameter data in real time through a sensor network deployed on the ship's deck, and obtains the dynamic fuel consumption for each construction stage. ; S3: Dynamic Measurement and Correction of Effective Dredging Volume: Calculates the real-time volume of mixture inside the ship's hold. A dynamic correction factor is introduced to calculate the effective dredging volume within a specific construction period. Effective dredging volume The formula is: ; In the formula, This is the overflow loss correction factor; This is the soil conversion factor; S4: Real-time Synthesis and Energy Efficiency Assessment of Fuel Consumption Indicators: The ship integrated automation system summarizes the fuel consumption of each construction stage to obtain the total fuel consumption. And combined with S3, the calculation results are obtained. The dynamic fuel consumption index (FOC) for this period is synthesized in real time, and its formula is as follows: ; S5: Energy-saving diagnosis and operation suggestion generation: Based on the stored historical period database, the ship integrated automation system benchmarks the current period's fuel consumption (FOC) and stage fuel consumption ratio against the historical best or average level under similar operating conditions. If an anomaly is found, the system will trigger an early warning and generate specific and actionable suggestions in conjunction with the pre-set expert rule base.
[0005] Preferably, the stages in step S1 include: empty navigation, loading process, heavy-load navigation, mud dumping operation, and circling standby.
[0006] Preferably, in step S2, the dynamic fuel consumption for each construction stage is obtained. Includes the following steps: S20: The power-fuel consumption rate characteristic function of the power equipment is obtained by fitting bench test data or long-term historical operating data. And it is integrated into the ship's integrated automation system; S21: Power-fuel consumption rate characteristic functions of each major power unit built into the ship's integrated automation system. With real-time power Combined, the instantaneous fuel consumption rate of each device is calculated; S22: Integrate the instantaneous fuel consumption rate of all equipment within a construction phase over time to obtain the dynamic fuel consumption for that phase. Its formula is:
[0007] In the formula, and These represent the start and end times of a specific construction phase, expressed in seconds (s). The total number of equipment involved in fuel consumption calculation during a specific construction phase; For device indexing.
[0008] Preferably, the volume of the real-time mixture inside the ship's cabin is calculated in step S3. Includes the following steps: S31: Based on the ship's tank capacity table and real-time liquid level, the volume of a mixture inside the tank is obtained by referring to a table. ; S32: Measure the average density of the mixture inside the chamber using an in-chamber density meter, and then... The volume of another mixture inside the chamber was obtained, and the two volumes were weighted and averaged to obtain the final volume. ; S33: In Based on this, two dynamic correction coefficients are introduced to calculate the effective dredging volume for this construction cycle. Its formula is: In the formula, This is the overflow loss correction factor. This is the soil conversion factor.
[0009] Preferably, the overflow loss correction coefficient in step S3 Based on the relationship between the underwater density and turbidity meter readings at the overflow pipe outlet and the average density in the mud tank, the proportion of sediment loss caused by the overflow is estimated using a concentration ratio model, as shown in the following formula: ; In the formula, These are empirical calibration coefficients; The density of the mixture at the overflow pipe outlet; The average density of the mixture within the mud tank; The density of the local seawater; In step S3, the ship integrated automation system matches the current working pressure of the rake head and the mud pump absorption concentration with the historical working condition database to identify the current soil type and call the corresponding empirical data. value.
[0010] Preferably, step S4 further includes the ship's integrated automation system calculating the fuel consumption ratio for each stage. It generates visualization charts to intuitively display the distribution of energy efficiency, including calculations. The formula is as follows: .
[0011] Preferably, the dynamic calculation and optimization method further includes step S6: model self-learning and calibration, which includes the following steps: S41: The ship's integrated automation system periodically updates the total fuel consumption calculated by the model. Compared with the actual refueling records of the ship A comparison is performed, and if the deviation exceeds a threshold, a calibration process is automatically triggered. The calibration targets include the power-fuel consumption rate characteristic function of the power equipment. Empirical calibration coefficient Soil conversion coefficient ; S42: Adjust the parameter vector of the calibration object This makes the model's total fuel consumption... Approaching the actual value ; S43: Stage power data based on multiple construction cycles Actual fuel consumption record And loading the current device feature library Values, output calibrated parameter vector ; S44: Collect data from M historical periods and calculate the average deviation using the following formula: ; In the formula, For the first Each cycle uses the current parameters Calculated total fuel consumption; S45: If the average deviation If the threshold is exceeded, perform gradient descent iteration, as shown in the formula: until <Threshold or reaching the maximum number of iterations; where, The learning rate controls the convergence speed; the gradient... It is obtained through numerical difference or automatic differentiation calculation.
[0012] Preferably, the average deviation in step S45 Force stop after <2% or 10 iterations to avoid overfitting.
[0013] This application also provides a system for dynamic calculation and optimization of fuel consumption per 10,000 cubic meters of dredging by a trailing suction hopper dredger, the system comprising: The data acquisition module includes a sensor network and data interface deployed at the ship's end; The edge computing module includes computing units deployed on shipboard industrial control computers or servers, used for real-time calculation, stage identification and preliminary analysis of steps S1 to S5; The data storage module is used to store historical periodic data, device-specific curves, expert rule bases, and parameters after self-learning calibration; and The application demonstration module includes a real-time dashboard on the bridge and a statistical analysis interface for the shore-based management platform.
[0014] Preferably, the sensor network includes a shaft power meter, a density meter, a level gauge, and a GPS measuring instrument.
[0015] As can be seen from the above technical solutions, the present invention has the following beneficial effects: In this invention, the calculation of fuel consumption (FOC) is refined to a single construction cycle and each operational stage, enabling traceability and benchmarking of fuel consumption. Utilizing real-time data-driven calculations, the impact of operational changes on energy consumption can be reflected promptly, providing possibilities for process optimization. Data-based diagnosis and suggestions can effectively guide captains and operators to adopt economical operations, providing a powerful data tool for fleet energy efficiency management, construction scheme comparison, and accurate cost accounting. Furthermore, through a self-learning mechanism, the model can adapt to aging ship equipment and changes in the marine environment, maintaining long-term accuracy. Moreover, the method of this invention can be extended to applications such as real-time carbon emission calculation and predictive maintenance of equipment health. Attached Figure Description
[0016] Figure 1 This is a schematic diagram of the overall process for the dynamic calculation and optimization method of fuel consumption per 10,000 cubic meters of construction volume of a trailing suction hopper dredger provided by the present invention. Figure 2 A schematic diagram of the system architecture for dynamic calculation and optimization of fuel consumption per 10,000 cubic meters of construction using a trailing suction hopper dredger, provided by the present invention. Figure 3 This is a schematic diagram of the real-time instrument panel on the driver's console.
[0017] In the diagram, 10 is the data acquisition module; 20 is the edge computing module; 30 is the data storage module; and 40 is the application display module. Detailed Implementation
[0018] A preferred embodiment of the present invention will now be described in detail with reference to the accompanying drawings.
[0019] To achieve the above objectives, the embodiments of the present invention adopt the following technical solutions: (Refer to...) Figure 1 , Figure 3 The dynamic calculation and optimization method for fuel consumption per 10,000 cubic meters of dredger operation includes the following steps: S1: Intelligent identification and division of construction phase: Based on the data flow of the ship's integrated automation system, a predefined rule engine is used to determine the current construction phase in real time.
[0020] Specifically, based on data streams from the ship's Integrated Automation System (IAS) (such as speed, cargo hold change rate, boom status, and GPS location), a predefined rule engine (which can be optimized using machine learning models) determines the current construction stage in real time. The stages are divided into: empty-load navigation, loading process (which can be further subdivided into normal loading and overflow loading sub-stages), heavy-load navigation, mud dumping operations, and circling standby. The identification criteria are implemented through the rule engine to ensure accurate stage division. The judgment criteria of the rule engine include, but are not limited to: Unloaded navigation: When the speed is greater than the preset threshold (e.g., 8 knots) and the mud hopper capacity is less than the preset threshold (e.g., 5%), the rake arm is in the lifting state.
[0021] Loading process: The rake arm is lowered, the mud pump is started, and the mud hopper capacity continues to increase. By monitoring the turbidity or concentration at the overflow outlet, when the value continues to be higher than the set threshold, it is determined that the overflow loading sub-stage has begun.
[0022] Heavy load navigation: mud hopper capacity > preset threshold (e.g., 85%), speed > preset threshold, rake arm lift.
[0023] Mud dumping operation: Located in the mud dumping area (based on GPS location), the mud gate is opened, and the mud hopper capacity decreases rapidly.
[0024] Circling standby: When the speed is extremely low (e.g., <2 knots) and the ship is not in a construction area or mud dumping area, the main equipment may be in a low-power standby state.
[0025] Building upon the above approach, further step S2: Real-time acquisition of multi-source energy consumption data and dynamic calculation of fuel consumption at each stage: Within each identified construction stage, the system collects the following two types of data in real time through a sensor network deployed at the ship's bow: (1) Equipment power data: including main shaft power, auxiliary load power, drive power of each mud pump, and power of rake head motor / hydraulic system.
[0026] (2) Operating parameters: main engine speed, mud pump speed, rake head working pressure, and sailing speed (to land and to water).
[0027] The system incorporates power-fuel consumption rate characteristic functions for each major power unit. This function can be obtained by fitting bench test data or long-term historical operating data. This characteristic function is then compared with real-time power data. Combined, the instantaneous fuel consumption rate of each piece of equipment is calculated. The dynamic fuel consumption of that phase is obtained by integrating the instantaneous fuel consumption rates of all equipment over time over a construction phase. The formula for calculating its integral is: In the formula, and These represent the start and end times of a specific construction phase, measured in seconds (s). The total number of equipment involved in fuel consumption calculation during a specific construction phase; For device indexing, i=1 represents the main unit, i=2 represents the mud pump, For time t, the first Real-time power data for each device, including main unit, auxiliary unit, mud pump, etc. For the first The power-fuel consumption rate characteristic function of each device. Compared with static statistics, the advantage of this method is that it can accurately capture the instantaneous power changes caused by operational adjustments (such as changes in pump speed and speed) and attribute fuel consumption to specific operating stages, providing a data foundation for refined management.
[0028] Based on the above method, further step S3: dynamic measurement and correction of effective dredging volume, which specifically includes the following process: First, the real-time mixture volume Calculation: Generally, the volume of a mixture in a tank can be obtained by referring to a table based on the ship's tank capacity table and real-time liquid level. Simultaneously, the average density of the mixture inside the chamber can be measured using an in-chamber density meter, and then... The volume of the mixture inside another chamber is obtained, and the two volumes are then weighted and averaged to obtain the final volume. ; It should be noted that the volume of the mixture within the same mud tank (a trailing suction hopper vessel has one mud tank) is obtained in two ways: the first is by looking up a table; the second is by calculation. This refers to the volume of the mixture inside the tank calculated using the density method. Specifically, the average density of the mixture inside the tank is measured by an internal density meter. Meanwhile, considering the total mass m of the mixture in the tank (the ship's displacement changes before and after loading mud, and this change in displacement is equal to the total mass of the mud-water mixture loaded into the mud tank), the volume of the mixture under the second method can be calculated. ; Secondly, effective earthwork volume Calculation: In Based on this, two dynamic correction coefficients are introduced to calculate the effective excavation volume and effective earthwork volume for this construction cycle. The calculation formula is as follows: In the formula, This is the overflow loss correction factor. It should be noted that the higher the overflow concentration, the greater the loss, and the smaller the correction factor. This is the soil conversion factor.
[0029] It should be noted that the overflow loss correction coefficient in step S3 Dynamic calculations were employed, primarily based on the relationship between the underwater density and turbidity meter readings at the overflow pipe inlet and the average density within the mud tank. A concentration ratio model was used to estimate the proportion of sediment loss caused by the overflow. The formula is as follows: In the formula, These are empirical calibration coefficients, determined through historical data inversion analysis, used to correct model errors. ; The density of the mixture at the overflow pipe inlet is measured in real time by an underwater density meter at the overflow pipe inlet, and the unit is t / m³. 3 ; The average density of the mixture inside the mud tank is measured in real time by a density meter inside the tank, and the unit is t / m³. 3 ; The local seawater density is used as a known benchmark value, with units of t / m³. 3 .
[0030] Meanwhile, soil conversion coefficient The following scheme was adopted: The ship integrated automation system matches the current working pressure of the rake head and the absorption concentration of the mud pump with the historical working condition database to identify the current soil type and call the corresponding empirical data. Value, that The value is used to convert the volume of the mixture into the volume of the engineering earthwork.
[0031] Building upon the above approach, further step S4: Real-time synthesis and energy efficiency assessment of fuel consumption indicators: After a complete construction cycle, the system summarizes the fuel consumption of each stage to obtain the total fuel consumption. And combined with S3, the calculation results are obtained. The dynamic fuel consumption index (FOC) for this period is synthesized in real time, and its formula is as follows: In addition, the ship's integrated automation system calculates the fuel consumption percentage at each stage. It generates visualization charts to intuitively display the distribution of energy efficiency, among which, The formula is as follows: It should be noted that the visual tables can be displayed on the dashboard for easy viewing.
[0032] Building upon the above approach, further step S5: Energy-saving diagnosis and operation suggestion generation: Based on the stored historical period database, the system benchmarks the current period's fuel consumption per 10,000 cubic meters (FOC) and stage fuel consumption ratio against historical best or average levels under similar working conditions (e.g., same soil type, similar transport distance). If an anomaly occurs (e.g., significantly higher FOC per 10,000 cubic meters, or abnormal fuel consumption ratio in a certain stage), the system will trigger an alert. Combined with a pre-set expert rule base (e.g., "If the fuel consumption ratio in the overflow stage exceeds 50% of the loading stage, and the overflow duration exceeds 30% of the total loading duration, it is recommended to optimize the mud pump speed and rake head height"), specific and actionable suggestions are generated. These suggestions are pushed to the operator via the real-time dashboard, realizing the transformation from "post-event statistics" to "in-event optimization." Energy efficiency benchmarking and diagnosis are performed based on the historical period database and current period data.
[0033] Furthermore, the dynamic calculation and optimization method also includes step S6: model self-learning and calibration, specifically, Compared with the actual refueling records of the ship A comparison is performed, and if the deviation exceeds a threshold (e.g., 5%), the calibration process is automatically triggered. The calibration objects include: (1) Power-fuel consumption rate characteristic function of power equipment To adapt to efficiency changes caused by equipment aging; (2) Calculation Model parameters (such as the α coefficient); (3) Specific soil types value.
[0034] The calibration algorithm is designed to minimize the deviation between calculated and actual fuel consumption, employing an iterative optimization method. The following uses the power-fuel consumption rate characteristic function of the power equipment. For example, other parameters (such as α, (This can be handled similarly.)
[0035] 1. Formalizing the calibration problem (1) Objective: To adjust the power-fuel consumption rate characteristic function of the power equipment. parameter vector (For example, to Model as a quadratic function ,but ), making the model's total fuel consumption Approaching the actual value .
[0036] (2) Input: Historical dataset: Stage power data across multiple construction periods Actual fuel consumption record .
[0037] Initial parameters: Current parameters loaded from the device feature library value.
[0038] (3) Output: calibrated parameter vector .
[0039] 2. Recommendation Algorithm: Online Learning Based on Gradient Descent This is a commonly used and interpretable algorithm, suitable for deployment in edge computing layers. The steps are as follows: (1) Deviation calculation: Each month, data from M historical periods are collected, and the average deviation is calculated using the following formula: In the formula, For the first Each cycle uses the current parameters Calculate the total fuel consumption.
[0040] (2) Parameter update rules: If the average deviation If the threshold is exceeded (e.g., 5%), perform gradient descent iterations, as shown in the formula: until <Threshold or reaching the maximum number of iterations; where, The learning rate (e.g., 0.01) is used to control the convergence speed; the gradient... It is calculated by numerical difference or automatic differentiation (suitable for edge devices).
[0041] (3) Convergence and safeguards: Termination criteria: Stop the process if the deviation is less than 2% or after 10 iterations to avoid overfitting.
[0042] Historical data weighting: Recent data has higher weighting to respond quickly to changes.
[0043] This self-learning mechanism enables the model to adapt to changes and maintain the long-term accuracy of the core computing modules.
[0044] Reference Figure 2This application also provides a system for dynamic calculation and optimization of fuel consumption per 10,000 cubic meters of dredger operation, used to implement the aforementioned dynamic calculation and optimization method. The system includes a data acquisition module 10, an edge computing module 20, a data storage module 30, and an application display module 40. Further, the data acquisition module 10 includes a sensor network and data interface deployed on the ship's end. The sensor network includes shaft power meters, density meters, level gauges, GPS measuring instruments, etc., and the data interface is used to connect to the IAS system. The edge computing module 20 includes a computing unit deployed on the ship's industrial control computer or server. This computing unit is used for real-time calculation, stage identification, and preliminary analysis of operation steps S1 to S5. The data storage module 30 is used to store historical periodic data, equipment-specific curves, expert rule bases, and parameters after self-learning calibration. The application display module 40 includes a real-time instrument panel on the bridge and a statistical analysis interface of the shore-based management platform. The real-time instrument panel on the bridge can display the current FOC, stage progress, real-time suggestions, etc., and the statistical analysis interface of the shore-based management platform can support multi-ship comparison, trend analysis, and report generation.
[0045] Example 1: The following section utilizes the dynamic calculation and optimization method for fuel consumption per 10,000 cubic meters of dredging vessel provided in this application to conduct dredging operations in a specific application scenario, in order to verify the significant advantages of the solution provided in this application.
[0046] Implementation scenario: A trailing suction hopper dredger with a capacity of 10,000 cubic meters is working in a sandy area, with a transport distance of 10 nautical miles.
[0047] S1: Intelligent Identification and Division of Construction Phase: The system automatically identifies the following through IAS data streams: After leaving berth, accelerate to 12 knots and enter "empty sailing"; upon arrival at the construction area, lower the rake arm and start the mud pump, the hopper volume begins to increase, and the system enters the "loading process"; after the hopper volume reaches 85%, the data shows that the overflow port concentration remains high, and the system determines that it has entered the "overflow loading" sub-stage; after the hopper volume reaches 98%, loading stops, the rake arm is raised, and the system accelerates to 10 knots to enter "heavy-load sailing"; upon arrival at the mud dumping area, the mud gate is opened, and the system enters "mud dumping operation"; after mud dumping is completed, the system returns to port and enters the next cycle.
[0048] S2: Real-time acquisition of multi-source energy consumption data and dynamic calculation of stage fuel consumption: During the "loading process", the system collects the following data in real time: main engine power 4500kW (load rate 85%), power of each of the two mud pumps 1800kW, and total auxiliary power 600kW. Based on their respective characteristic curves (e.g., the fuel consumption rate of the main engine at 85% load is 198g / kWh), the instantaneous fuel consumption per second for this stage is calculated and accumulated.
[0049] S3: Dynamic measurement and correction of effective dredging volume: At the end of loading, the average density measured by the density meter in the hopper was 1.4 t / m³. 3The calculated volume of the mixture is 9800 cubic meters. Overflow loss coefficient. The model calculates it to be 0.92. Soil coefficient. Based on the type of sandy soil, a value of 1.05 is taken. =9800*0.92*1.05≈9470 square meters.
[0050] S4: Real-time synthesis and energy efficiency assessment of Wanfang fuel consumption index: The model calculates the total fuel consumption for the entire cycle (including no-load, loaded, heavy-load, and mud dumping). = 1250kg. Therefore, the dynamic fuel consumption (FOC) per 10,000 cubic meters in this cycle is approximately 1320kg / 10,000 cubic meters. The system shows that the loading stage accounts for the highest proportion of fuel consumption (45%), with the overflow sub-stage accounting for 60% of the loading stage.
[0051] S5: Energy-saving diagnosis and operation suggestion generation: Compared with the historical average FOC (1250 kg / 10,000 cubic meters) under the same working conditions (sand, 10 nautical miles), the current cycle is higher. The diagnosis points out that "the proportion of overflow stage is abnormally high". Based on the overflow duration and concentration data, the expert rule base gives the following suggestion: "For the next operation, it is recommended to reduce the mud pump speed in advance when the tank volume reaches 88%, and to fine-tune the rake head height to reduce the overflow concentration and shorten the high-energy-consuming overflow time."
[0052] S6: Model self-learning and calibration: During the monthly summary, the model calculated the total fuel consumption to be 385 tons, while the actual refueling record was 398 tons, with a deviation of 3.3%, which is within the threshold and the model does not need to be calibrated.
[0053] Through the above methods, this invention achieves refined and dynamic management of fuel consumption for trailing suction hopper dredgers, resulting in significant energy savings and economic value.
[0054] The above-described embodiments are merely preferred embodiments of the present invention and are not intended to limit the scope of the present invention. Various modifications and improvements made by those skilled in the art to the technical solutions of the present invention without departing from the spirit of the present invention should fall within the protection scope defined by the claims of the present invention.
Claims
1. A dynamic calculation and optimization method for fuel consumption per 10,000 cubic meters of dredger operation, characterized in that, Includes the following steps: S1: Intelligent identification and division of construction phase: Based on the data flow of the ship's integrated automation system, a predefined rule engine is used to determine the current construction phase in real time; S2: Real-time acquisition of multi-source energy consumption data and dynamic calculation of fuel consumption at each stage: Based on the identified construction stages, the ship's integrated automation system collects equipment power data and operating parameter data in real time through a sensor network deployed on the ship's deck, and obtains the dynamic fuel consumption for each construction stage. ; S3: Dynamic Measurement and Correction of Effective Dredging Volume: Calculates the real-time volume of mixture inside the ship's hold. A dynamic correction factor is introduced to calculate the effective dredging volume within a specific construction period. Effective dredging volume The formula is: ; In the formula, This is the overflow loss correction factor; This is the soil conversion factor; S4: Real-time Synthesis and Energy Efficiency Assessment of Fuel Consumption Indicators: The ship integrated automation system summarizes the fuel consumption of each construction stage to obtain the total fuel consumption. And combined with S3, the calculation results are obtained. The dynamic fuel consumption index (FOC) for this period is synthesized in real time, and its formula is as follows: ; S5: Energy-saving diagnosis and operation suggestion generation: Based on the stored historical period database, the ship integrated automation system benchmarks the current period's fuel consumption (FOC) and stage fuel consumption ratio against the historical best or average level under similar operating conditions. If an anomaly is found, the system will trigger an early warning and generate specific and actionable suggestions in conjunction with the pre-set expert rule base.
2. The dynamic calculation and optimization method according to claim 1, characterized in that, The steps in step S1 are divided into the following stages: empty navigation, loading process, heavy-load navigation, mud dumping operation, and circling standby.
3. The dynamic calculation and optimization method according to claim 1, characterized in that, In step S2, the dynamic fuel consumption of each construction stage is obtained. Includes the following steps: S20: The power-fuel consumption rate characteristic function of the power equipment is obtained by fitting bench test data or long-term historical operating data. And it is integrated into the ship's integrated automation system; S21: Power-fuel consumption rate characteristic functions of each major power unit built into the ship's integrated automation system. With real-time power Combined, the instantaneous fuel consumption rate of each device is calculated; S22: Integrate the instantaneous fuel consumption rate of all equipment within a construction phase over time to obtain the dynamic fuel consumption for that phase. Its formula is: ; In the formula, and These represent the start and end times of a specific construction phase, expressed in seconds (s). The total number of equipment involved in fuel consumption calculation during a specific construction phase; For device indexing.
4. The dynamic calculation and optimization method according to claim 1, characterized in that, The volume of real-time mixture inside the ship's cabin is calculated in S3. Includes the following steps: S31: Based on the ship's tank capacity table and real-time liquid level, the volume of a mixture inside the tank is obtained by referring to a table. ; S32: Measure the average density of the mixture inside the chamber using an in-chamber density meter, and then... The volume of another mixture inside the chamber was obtained, and the two volumes were weighted and averaged to obtain the final volume. In the formula, m is the mass of the mixture. Density of the mixture inside the cabin; S33: In Based on this, two dynamic correction coefficients are introduced to calculate the effective dredging volume for this construction cycle. Its formula is: In the formula, This is the overflow loss correction factor. This is the soil conversion factor.
5. The dynamic calculation and optimization method according to claim 1, characterized in that, Overflow loss correction coefficient in step S3 Based on the relationship between the underwater density and turbidity meter readings at the overflow pipe outlet and the average density in the mud tank, the proportion of sediment loss caused by the overflow is estimated using a concentration ratio model, as shown in the following formula: ; In the formula, These are empirical calibration coefficients; The density of the mixture at the overflow pipe outlet; The average density of the mixture within the mud tank; The density of the local seawater; In step S3, the ship integrated automation system matches the current working pressure of the rake head and the mud pump absorption concentration with the historical working condition database to identify the current soil type and call the corresponding empirical data. value.
6. The dynamic calculation and optimization method according to claim 5, characterized in that, Step S4 also includes the ship integrated automation system calculating the fuel consumption ratio at each stage. It generates visualization charts to intuitively display the distribution of energy efficiency, including calculations. The formula is as follows: .
7. The dynamic calculation and optimization method according to claim 6, characterized in that, The dynamic calculation and optimization method further includes step S6: model self-learning and calibration, which includes the following steps: S41: The ship's integrated automation system periodically updates the total fuel consumption calculated by the model. Compared with the actual refueling records of the ship A comparison is performed, and if the deviation exceeds a threshold, a calibration process is automatically triggered. The calibration targets include the power-fuel consumption rate characteristic function of the power equipment. Empirical calibration coefficient Soil conversion coefficient ; S42: Adjust the parameter vector of the calibration object This makes the model's total fuel consumption... Approaching the actual value ; S43: Stage power data based on multiple construction cycles Actual fuel consumption record And loading the current device feature library Values, output calibrated parameter vector ; S44: Collect data from M historical periods and calculate the average deviation using the following formula: ; In the formula, For the first Each cycle uses the current parameters Calculated total fuel consumption; S45: If the average deviation If the threshold is exceeded, perform gradient descent iteration, as shown in the formula: until <Threshold or reaching the maximum number of iterations; where, The learning rate controls the convergence speed; the gradient... It is obtained through numerical difference or automatic differentiation calculation.
8. The dynamic calculation and optimization method according to claim 7, characterized in that, The average deviation in step S45 Force stop after <2% or 10 iterations to avoid overfitting.
9. A system for dynamic calculation and optimization of fuel consumption per 10,000 cubic meters during dredging operations using a trailing suction hopper dredger, the system being used to implement the dynamic calculation and optimization method as described in any one of claims 1-8, characterized in that... The system includes: The data acquisition module (10) includes a sensor network and data interface deployed at the ship's end; The edge computing module (20) includes a computing unit deployed on a shipboard industrial control computer or server for real-time calculation, stage identification and preliminary analysis of steps S1 to S5. Data storage module (30) is used to store historical periodic data, device-specific curves, expert rule base, and parameters after self-learning calibration; and The application demonstration module (40) includes a real-time dashboard on the bridge and a statistical analysis interface for the shore-based management platform.
10. The system according to claim 9, characterized in that, The sensor network includes a shaft power meter, a density meter, a level gauge, and a GPS measuring instrument.