Method for intelligent prediction of hydropower and water conservancy project investment
By using OCR to identify and structure the bill of quantities and preliminary budget data for hydropower and water conservancy projects, and combining differentiated algorithms and early warning models, the problem of dynamic accuracy in investment forecasting for hydropower and water conservancy projects has been solved, improving data processing efficiency and investment control capabilities.
Patent Information
- Application Number
- CN202611078671.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-20
- Publication Date
- 2026-11-24
AI Technical Summary
Existing technologies cannot dynamically and accurately predict the investment upon completion of hydropower and water conservancy projects, leading to contract overruns, budget overruns, and difficulties in investment control. Furthermore, the unstructured nature of the bill of quantities and management budget data results in low efficiency, large errors, and difficulty in extracting the value of the data.
By using OCR to identify unstructured bills of quantities and management budget scans, structured data is generated. Combining the quantity-price multiplication method, contract amount adjustment method, and budget amount adjustment method, the investment forecast values of various contracts are dynamically calculated, and an investment early warning model is established to achieve comprehensive investment forecasting and early warning.
It has achieved efficient processing and improved accuracy of engineering cost data, dynamically and accurately calculated project investment, broken down the data barriers between budget and contract, reduced the risk of investment loss of control, and realized intelligent investment calculation and early warning throughout the entire cycle and in all dimensions.
Smart Images

Figure CN123159588A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to an intelligent prediction method for investment in hydropower and water conservancy projects. It is applicable to the field of digital management technology for engineering projects. Background Technology
[0002] In recent years, with the accelerated digital transformation of the energy industry, the requirements for digital management of hydropower and water conservancy project investment have continued to increase. Currently, most domestic and international engineering management software only achieves structured storage of investment management data and online business processes, supporting the correlation query and simple calculation of metering, settlement, and payment data, and enabling online approval processes. However, during project construction, there is a lack of mature technical solutions and practical applications for predicting the investment upon completion of contracts and the overall project. Because it is impossible to dynamically and accurately predict the total investment at the completion stage, contract overruns and budget overruns frequently occur during implementation, posing a significant challenge to project cost control.
[0003] Furthermore, in engineering scenarios, contract bills of quantities and management estimates are mostly in the form of PDF scans. Unstructured data relies on manual input, which is inefficient, prone to errors, and makes it difficult to effectively extract data value. The estimate management system and the contract execution system are independent of each other, with fragmented data links, making it impossible to automatically aggregate and form a global investment view. Investment risk control is mostly handled after the fact, lacking a hierarchical early warning mechanism from details to the whole, which can easily lead to problems such as project investment getting out of control and investment exceeding the budget. Summary of the Invention
[0004] The technical problem to be solved by this invention is to provide an intelligent prediction method for investment in hydropower and water conservancy projects, addressing the aforementioned problems.
[0005] The technical solution adopted in this invention is: In a first aspect, the present invention provides an intelligent prediction method for investment in hydropower and water conservancy projects, comprising: S1. Receive scanned copies of the contract bill of quantities and management budget, identify the scanned copies, map the identification results to preset fields, generate structured bill of quantities data and management budget data, and store them in the system database. S2. For construction and installation contracts that have been signed, retrieve the contract quantity, design blueprint quantity and design change quantity from the system database, calculate the expected completed quantity of each item in the bill of quantities based on the bill of quantities structure, and establish and dynamically update the construction and installation contract quantity ledger. S3. Perform investment forecast calculations separately for each project category, including: For signed construction and installation contracts, the quantity-price multiplication method is used. Based on the unit price of each item in the bill of quantities and the corresponding expected completed work quantity, the expected change claim costs are calculated and added to obtain the investment forecast value of the construction and installation contract. For signed non-construction and installation contracts, the contract value adjustment method is adopted, and the investment forecast value of non-construction and installation contracts is obtained by superimposing the adjusted value on the signed contract value. For projects without signed contracts, the estimated amount adjustment method is adopted, and the investment forecast value of the projects without signed contracts is obtained by superimposing the corresponding management estimated value with the adjustment value. S4. Establish a coding mapping relationship between the management budget sub-items and signed and unsigned contract projects. Sum the investment forecast values of various projects mapped to the same management budget sub-item to obtain the investment forecast results of each level of management budget sub-item and the overall project.
[0006] Through the aforementioned technical means, the unstructured scanned documents of the bill of quantities and management estimates are automatically converted into structured data, replacing manual data entry and building a standardized cost data foundation, thus solving the problem of the difficulty in effectively mining and utilizing engineering cost data. Differentiated prediction algorithms are adopted for different types and stages of hydropower projects to achieve full-scope investment prediction for signed construction and installation contracts, signed non-construction and installation contracts, and unsigned contracts. Through the mapping relationship between the estimate and the contract, the hierarchical aggregation from the bill of quantities to the estimate is completed, and the investment prediction results of each level of the estimate and even the entire project are automatically output. This solves the core pain point that existing technologies cannot dynamically and accurately predict the investment upon project completion, and realizes intelligent calculation of investment throughout the entire cycle and in all dimensions.
[0007] As a preferred option, it also includes: S5. Establish an investment early warning model. The early warning trigger conditions of this model include: The risk of exceeding the list item is judged by comparing the cumulative settlement amount with the contract work amount; the risk of contract overrun is judged by comparing the contract investment forecast value with the signed contract amount; and the risk of budget overrun is judged by comparing the estimated investment forecast result with the management budget amount. When any of the early warning trigger conditions are met, an early warning message is pushed to the client of the corresponding responsible user, and the early warning process is closed after receiving the cause analysis uploaded by the user.
[0008] Through the aforementioned technical means, the risk of overspending in different dimensions can be automatically identified based on investment forecasts and early warnings can be proactively pushed out. At the same time, the early warning process is closed-loop by uploading the cause, transforming investment control from post-event handling to in-process early warning, effectively reducing the risk of investment running out of control and exceeding the budget.
[0009] As a preferred embodiment, step S1, which involves identifying the scanned document, includes: The scanned document undergoes image preprocessing, which involves calling the OCR engine to perform table and text recognition on the scanned document. The image preprocessing includes tilt correction, noise reduction, binarization, and resolution unification.
[0010] The above-mentioned technical means can optimize the image quality of tilted, blurry, and low-quality engineering scans, effectively improve the OCR engine's recognition accuracy and robustness of engineering tables and text, adapt to old, dirty, and improperly photographed scanned documents in hydropower engineering scenarios, and ensure the quality of structured data collection.
[0011] As a preferred embodiment, step S1, mapping the recognition result to a preset field, includes: The identification results are mapped to a pre-defined bill of quantities field library and management budget field library using a strategy that combines regular expression matching and keyword matching.
[0012] By employing the aforementioned technical means and a dual-matching strategy, unstructured text and table content recognized by OCR can be accurately categorized into corresponding standard fields, automatically adapting to different formats of bills of quantities and budget documents, thereby improving the accuracy and adaptability of structured parsing.
[0013] As a preferred embodiment, the bill of quantities field library includes bill of quantities code, project name, unit of measurement, quantity, unit price, and total price, while the management budget field library includes budget project code, project name, cost type, and amount.
[0014] As a preferred embodiment, step S2, calculating the expected completed work volume, includes: For items in the contract list, the estimated completed work volume equals the design blueprint volume plus the design change volume. The design blueprint volume before the drawings are produced is taken as the contract volume. For items in the change list, the estimated completed work volume is taken as the changed work volume.
[0015] By using the above-mentioned technical means, and combining the contract quantity, blueprint quantity, and change quantity to dynamically calculate the expected completed work quantity, the impact of design changes and drawing updates on the work quantity can be reflected in real time. This adapts to the dynamic changes in the work quantity during the construction process and provides accurate work quantity data support for the prediction of construction contract investment.
[0016] As a preferred embodiment, step S4, establishing a coding mapping relationship between management budget sub-items and signed / unsigned contract items, includes: For projects with signed contracts, the contract will be linked to the corresponding management budget item in the basic contract information to establish a permanent association that will remain in effect in the long term. For projects without signed contracts, the project will be temporarily bound to the corresponding management budget item when executing investment forecasts, establishing a temporary association that is only valid for that forecast.
[0017] By employing the aforementioned technical means and a mapping model that combines permanent and temporary associations, the stability of the correspondence between signed contracts and budget estimates is ensured, while also meeting the business needs for flexible calculation of unsigned projects, thereby enhancing the flexibility and applicability of the total budget investment forecast.
[0018] Secondly, the present invention provides an intelligent prediction device for investment in hydropower and water conservancy projects, comprising: The document recognition module is used to receive scanned copies of the contract bill of quantities and management budget, recognize the scanned copies, map the recognition results to preset fields, generate structured bill of quantities data and management budget data, and store them in the system database. The completion calculation module is used to retrieve the contract quantity, design blueprint quantity, and design change quantity from the system database for construction and installation contracts that have been signed. Based on the bill of quantities structure, it calculates the expected completed quantity of each item in the bill of quantities and establishes and dynamically updates the construction and installation contract quantity ledger. The classification forecasting module is used to perform investment forecast calculations separately according to project categories, including: For signed construction and installation contracts, the quantity-price multiplication method is used. Based on the unit price of each item in the bill of quantities and the corresponding expected completed work quantity, the expected change claim costs are calculated and added to obtain the investment forecast value of the construction and installation contract. For signed non-construction and installation contracts, the contract value adjustment method is adopted, and the investment forecast value of non-construction and installation contracts is obtained by superimposing the adjusted value on the signed contract value. For projects without signed contracts, the estimated amount adjustment method is adopted, and the investment forecast value of the projects without signed contracts is obtained by superimposing the corresponding management estimated value with the adjustment value. The investment forecasting module is used to establish a coding mapping relationship between management budget sub-items and signed and unsigned contract projects. It sums up the investment forecast values of various projects mapped to the same management budget sub-item to obtain the investment forecast results of each level of management budget sub-item and the project as a whole.
[0019] Thirdly, the present invention provides a storage medium storing a computer program executable by a processor, wherein the computer program, when executed, implements the steps of the intelligent prediction method for investment in hydropower and water conservancy projects.
[0020] Fourthly, the present invention provides an intelligent prediction device for hydropower and water conservancy project investment, which has a memory and a processor. The memory stores a computer program that can be executed by the processor. When the computer program is executed, it implements the steps of the intelligent prediction method for hydropower and water conservancy project investment.
[0021] The beneficial effects of this invention are: by replacing manual data entry with OCR recognition and standardized field mapping, this invention solves the problems of low utilization rate and large data entry errors of unstructured scanned documents, greatly improves the efficiency and accuracy of cost data processing, and builds a high-quality data foundation for investment management.
[0022] This invention constructs a comprehensive investment forecasting algorithm system covering signed construction and installation contracts, signed non-construction and installation contracts, and unsigned contracts. It can dynamically and accurately calculate the completed investment of various projects, filling the technical gap in dynamic investment forecasting during the construction of hydropower and water conservancy projects.
[0023] This invention breaks down the data barriers between the budget management system and the contract execution system through a 1:N coding mapping mechanism between the budget and the contract. It can automatically aggregate and generate investment forecast results for each level of the budget and the overall project, thereby achieving global and hierarchical control of investment.
[0024] This invention establishes a three-tiered investment early warning and closed-loop handling mechanism, which can proactively identify risks of exceeding investment limits, contracts, and budgets, transforming investment management from post-investment remediation to in-process early warning and prevention, effectively avoiding investment loss of control and exceeding budget risks. Attached Figure Description
[0025] Figure 1 This is a flowchart of the intelligent prediction method for hydropower and water conservancy project investment in the embodiment; Figure 2 This is a schematic diagram illustrating the linking of contracts to the management budget in the example. Figure 3 This is a schematic diagram of investment forecasting and over-prediction intelligent early warning in the example. Detailed Implementation
[0026] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
[0027] Example 1: As Figure 1 As shown in the figure, this embodiment is a method for intelligent prediction of investment in hydropower and water conservancy projects, which specifically includes the following steps: S1. Receive scanned copies of the contract bill of quantities and management budget, identify the scanned copies, map the identification results to preset fields, generate structured bill of quantities data and management budget data, and store them in the system database.
[0028] In this embodiment, a PDF scan containing a contract bill of quantities and management budget is received from a user. The local OCR engine is automatically triggered to recognize the scan. To improve the recognition accuracy of low-quality, old, or tilted scans, image preprocessing is performed on the PDF scan before calling the local OCR engine for table and text recognition. This preprocessing process specifically includes: Tilt correction: Based on Hough transform or projection analysis, the tilt angle of the text lines on the page is detected and rotated to ensure that the text is level. Denoising: Median filtering or Gaussian filtering is used to remove salt-and-pepper noise and background interference generated during the scanning process; Binarization: Applying an adaptive thresholding algorithm (such as the Otsu algorithm) to convert a grayscale image into a black and white binary image enhances the contrast between text and background; Uniform resolution: All page images are uniformly scaled to a standard resolution of no less than 300 DPI to ensure clear character edges.
[0029] The above preprocessing significantly improves the robustness of subsequent OCR in recognizing blurred, damaged, or tilted tables. The preprocessed image is then fed into a locally deployed OCR engine (such as Tesseract, PaddleOCR, or a self-developed model). This engine focuses on recognizing the table structure (rows, columns, merged cells) and text content, outputting preliminary recognition results including location coordinates and text.
[0030] In this embodiment, unstructured text and tabular data identified by OCR are parsed into structure and mapped to preset data fields. The specific implementation method is as follows: A pre-established bill of quantities field library is created, including: bill of quantities code, project name, unit of measurement, quantity, unit price, and total price; at the same time, a management budget field library is created, including: budget project code, project name, cost type, amount, and remarks. During parsing, the system combines two strategies: regular expression matching and keyword matching: (1) Regular expression matching, for example, using the regular expression "\d{1,2}\.\d{1,3}" to identify the bill of quantities code; (2) Keyword matching: using a keyword dictionary (such as "total", "subtotal", "unit: yuan", etc.) to locate the table header or key rows and determine the semantics of each column.
[0031] In this example, the identified text is categorized into the corresponding fields, and special cases such as unit conversion, uniform numerical format (e.g., removal of thousands separators), and expansion of merged cells are automatically handled. For unmatched or ambiguous content, an exception log is recorded and a manual review is requested. After the structured data (including the bill of quantities data table and the management budget data table) has been mapped, it is written to the system database in batches after passing data validation (e.g., mandatory field checks and numerical reasonableness checks).
[0032] S2. For construction and installation contracts that have been signed, retrieve the contract quantity, design blueprint quantity, and design change quantity from the system database, calculate the expected completed quantity of each item in the bill of quantities based on the bill of quantities structure, and establish and dynamically update the construction and installation contract quantity ledger.
[0033] In this example, for construction contracts, the system uses the bill of quantities structure as a basis to link contract quantities, design blueprint quantities, and design change quantities. Contract quantities are batch-imported from the bill of quantities; design blueprint quantities are obtained by the user by breaking down the physical quantities in the design drawings into sub-items of the bill of quantities; new items added outside the contract in the design change quantities are associated with a parent node of the bill of quantities when the change process is initiated; items reduced within the contract in the design change quantities are selected by entering the corresponding reduction value in a specific bill of quantities sub-item when the change process is initiated. Once the change process is complete, the change quantities are automatically updated in the quantity ledger.
[0034] In this embodiment, for contract list items, the estimated completed work volume equals the design blueprint volume plus the design change volume; when drawings are not yet produced, the design blueprint volume is the contract volume. For change list items, the estimated completed work volume equals the change volume.
[0035] S3. Perform investment forecast calculations separately for each project category, including: I. For signed construction and installation contracts, the quantity-price multiplication method is used. Based on the unit price of each item in the bill of quantities and the corresponding estimated completed work quantity, and by adding the estimated change order claims, the projected investment value for the construction and installation contract is obtained. The formula is as follows: in, Forecast investment value for construction and installation contracts for projects with signed contracts; Unit price corresponding to each item in the list; The estimated completed work volume for each item in the bill of quantities; Total quantity of items in the bill of quantities; Costs for changes to the contract that were not anticipated to occur.
[0036] II. For signed non-construction and installation contracts, the contract amount adjustment method is adopted. The investment forecast value of non-construction and installation contracts is obtained by superimposing the adjusted value of the signed contract amount.
[0037] The contract value adjustment method is used to predict the completion investment of other types of contracts for signed projects. It is worth noting that, to ensure a comprehensive investment calculation, these other types of contracts include not only actual signed non-construction and installation contracts, such as equipment procurement, design, supervision, and commissioning, but also virtual contracts manually entered and maintained by the user, such as corporate management fees and construction period loan interest. The formula is as follows: in, Forecasted investment values for other types of contracts for projects already under contract; Contract amount; : Adjustment value.
[0038] III. For projects without signed contracts, the estimated investment adjustment method is used. The projected investment value for these projects is obtained by adding adjustments to the corresponding management estimated investment value. The formula is as follows: in, Forecasted investment value for projects without signed contracts; : The management budget value corresponding to the contract.
[0039] S4. Establish a coding mapping relationship between the management budget sub-items and signed and unsigned contract projects. Sum the investment forecast values of various projects mapped to the same management budget sub-item to obtain the investment forecast results of each level of management budget sub-item and the overall project.
[0040] In this embodiment, the coding mapping relationship includes permanent association and temporary association. For signed contract projects, the contract is directly linked to a certain item in the management budget in the basic contract information, that is, a permanent association relationship is established (e.g., Figure 2 (As shown); For projects without signed contracts, simply add the project under a specific item in the management budget when making the preliminary investment forecast; this forecast is only valid for this specific time. Based on the management budget structure, the system automatically forecasts the investment at different levels of the budget and the overall project investment (e.g., Figure 3 (As shown).
[0041] S5. Establish an investment early warning model. The early warning trigger conditions of this model include: ① Assess the risk of exceeding the quota for bill of quantities based on a comparison between the cumulative settlement amount and the contracted work quantity: in, : The amount of each item in the contract list up to the current period's settlement amount; : Contract list items and quantities up to the previous period's settlement amount; Contract list items and quantities; The total number of visas issued for this item in each visa application form this period is: item.
[0042] ② Assess the risk of contract overruns by comparing the projected investment value with the contract amount: in, Forecast investment value for construction and installation contracts for projects with signed contracts; Forecasted investment values for other types of contracts for projects already under contract; : Contract amount.
[0043] ③ Assess the risk of budget overrun based on a comparison between the estimated investment forecast and the management budget: : The estimated investment value for a specific sub-project in the management budget; The total estimated investment in construction and installation contracts for signed projects mapped to this management budget sub-item is [amount missing]. item; : The projected investment value of other types of contracts for signed projects mapped to this management budget sub-item, totaling item; : The projected investment value of uncontracted projects mapped to this management budget sub-item, totaling item; : Management estimate: The estimated value corresponding to this sub-item.
[0044] When any of the warning trigger conditions are met, an investment warning is automatically initiated, and the warning information is pushed to the client of the corresponding responsible user. After receiving the cause analysis uploaded by the user, the warning process is closed.
[0045] Example 2: This example is an intelligent prediction device for investment in hydropower and water conservancy projects, comprising: The document recognition module is used to receive scanned copies of the contract bill of quantities and management budget, recognize the scanned copies, map the recognition results to preset fields, generate structured bill of quantities data and management budget data, and store them in the system database. The completion calculation module is used to retrieve the contract quantity, design blueprint quantity, and design change quantity from the system database for construction and installation contracts that have been signed. Based on the bill of quantities structure, it calculates the expected completed quantity of each item in the bill of quantities and establishes and dynamically updates the construction and installation contract quantity ledger. The classification forecasting module is used to perform investment forecast calculations separately according to project categories, including: For signed construction and installation contracts, the quantity-price multiplication method is used. Based on the unit price of each item in the bill of quantities and the corresponding expected completed work quantity, the expected change claim costs are calculated and added to obtain the investment forecast value of the construction and installation contract. For signed non-construction and installation contracts, the contract value adjustment method is adopted, and the investment forecast value of non-construction and installation contracts is obtained by superimposing the adjusted value on the signed contract value. For projects without signed contracts, the estimated amount adjustment method is adopted, and the investment forecast value of the projects without signed contracts is obtained by superimposing the corresponding management estimated value with the adjustment value. The investment forecasting module is used to establish a coding mapping relationship between management budget sub-items and signed and unsigned contract projects. It sums up the investment forecast values of various projects mapped to the same management budget sub-item to obtain the investment forecast results of each level of management budget sub-item and the project as a whole.
[0046] Example 3: This example is a storage medium that stores a computer program that can be executed by a processor. When the computer program is executed, it implements the steps of the intelligent prediction method for hydropower and water conservancy project investment described in Example 1.
[0047] Example 4: This example is an intelligent prediction device for hydropower and water conservancy project investment, which has a memory and a processor. The memory stores a computer program that can be executed by the processor. When the computer program is executed, it implements the steps of the intelligent prediction method for hydropower and water conservancy project investment described in Example 1.
[0048] The warning information is distributed to the relevant contract and budget personnel through the system. After the user uploads the analysis of the reasons for the excess or over-limit, the warning information is closed.
[0049] Those skilled in the art will understand that, unless otherwise defined, all terms used herein (including technical and scientific terms) have the same meaning as commonly understood by one of ordinary skill in the art to which this application pertains. It should also be understood that terms such as those defined in general dictionaries should be understood to have the same meaning as in the context of the prior art, and should not be interpreted in an idealized or overly formal sense unless defined as herein.
[0050] Based on the above-described preferred embodiments of the present invention, and through the foregoing description, those skilled in the art can make various changes and modifications without departing from the inventive concept. The technical scope of this invention is not limited to the contents of the specification, but must be determined according to the scope of the claims.
Claims
1. A method for intelligent prediction of investment in hydropower and water conservancy projects, characterized in that, include: S1. Receive scanned copies of the contract bill of quantities and management budget, identify the scanned copies, map the identification results to preset fields, generate structured bill of quantities data and management budget data, and store them in the system database. S2. For construction and installation contracts that have been signed, retrieve the contract quantity, design blueprint quantity and design change quantity from the system database, calculate the expected completed quantity of each item in the bill of quantities based on the bill of quantities structure, and establish and dynamically update the construction and installation contract quantity ledger. S3. Perform investment forecast calculations separately for each project category, including: For signed construction and installation contracts, the quantity-price multiplication method is used. Based on the unit price of each item in the bill of quantities and the corresponding expected completed work quantity, the expected change claim costs are calculated and added to obtain the investment forecast value of the construction and installation contract. For signed non-construction and installation contracts, the contract value adjustment method is adopted, and the investment forecast value of non-construction and installation contracts is obtained by superimposing the adjusted value on the signed contract value. For projects without signed contracts, the estimated amount adjustment method is adopted, and the investment forecast value of the projects without signed contracts is obtained by superimposing the corresponding management estimated value with the adjustment value. S4. Establish a coding mapping relationship between the management budget sub-items and signed and unsigned contract projects. Sum the investment forecast values of various projects mapped to the same management budget sub-item to obtain the investment forecast results of each level of management budget sub-item and the overall project.
2. The intelligent prediction method for hydropower and water conservancy project investment according to claim 1, characterized in that, Also includes: S5. Establish an investment early warning model. The early warning trigger conditions of this model include: The risk of exceeding the list item is judged by comparing the cumulative settlement amount with the contract work amount; the risk of contract overrun is judged by comparing the contract investment forecast value with the signed contract amount; and the risk of budget overrun is judged by comparing the estimated investment forecast result with the management budget amount. When any of the early warning trigger conditions are met, an early warning message is pushed to the client of the corresponding responsible user, and the early warning process is closed after receiving the cause analysis uploaded by the user.
3. The intelligent prediction method for hydropower and water conservancy project investment according to claim 1, characterized in that, In step S1, the scanned document is identified, including: The scanned document undergoes image preprocessing, which involves calling the OCR engine to perform table and text recognition on the scanned document. The image preprocessing includes tilt correction, noise reduction, binarization, and resolution unification.
4. The intelligent prediction method for hydropower and water conservancy project investment according to claim 1, characterized in that, In step S1, mapping the recognition result to a preset field includes: The identification results are mapped to a pre-defined bill of quantities field library and management budget field library using a strategy that combines regular expression matching and keyword matching.
5. The intelligent prediction method for hydropower and water conservancy project investment according to claim 4, characterized in that, The bill of quantities field library includes bill of quantities code, project name, unit of measurement, quantity, unit price, and total price; the management estimate field library includes estimate project code, project name, cost type, and amount.
6. The intelligent prediction method for investment in hydropower and water conservancy projects according to claim 1, characterized in that, In step S2, the calculation of the expected completed work volume includes: For items in the contract list, the estimated completed work volume equals the design blueprint volume plus the design change volume. The design blueprint volume before the drawings are produced is taken as the contract volume. For items in the change list, the estimated completed work volume is taken as the changed work volume.
7. The intelligent prediction method for hydropower and water conservancy project investment according to claim 1, characterized in that, In step S4, establishing a coding mapping relationship between management budget sub-items and signed and unsigned contract items includes: For projects with signed contracts, the contract will be linked to the corresponding management budget item in the basic contract information to establish a permanent association that will remain in effect in the long term. For projects without signed contracts, the project will be temporarily bound to the corresponding management budget item when executing investment forecasts, establishing a temporary association that is only valid for that forecast.
8. A smart prediction device for investment in hydropower and water conservancy projects, characterized in that, include: The document recognition module is used to receive scanned copies of the contract bill of quantities and management budget, recognize the scanned copies, map the recognition results to preset fields, generate structured bill of quantities data and management budget data, and store them in the system database. The completion calculation module is used to retrieve the contract quantity, design blueprint quantity, and design change quantity from the system database for construction and installation contracts that have been signed. Based on the bill of quantities structure, it calculates the expected completed quantity of each item in the bill of quantities and establishes and dynamically updates the construction and installation contract quantity ledger. The classification forecasting module is used to perform investment forecast calculations separately according to project categories, including: For signed construction and installation contracts, the quantity-price multiplication method is used. Based on the unit price of each item in the bill of quantities and the corresponding expected completed work quantity, the expected change claim costs are calculated and added to obtain the investment forecast value of the construction and installation contract. For signed non-construction and installation contracts, the contract value adjustment method is adopted, and the investment forecast value of non-construction and installation contracts is obtained by superimposing the adjusted value on the signed contract value. For projects without signed contracts, the estimated amount adjustment method is adopted, and the investment forecast value of the projects without signed contracts is obtained by superimposing the corresponding management estimated value with the adjustment value. The investment forecasting module is used to establish a coding mapping relationship between management budget sub-items and signed and unsigned contract projects. It sums up the investment forecast values of various projects mapped to the same management budget sub-item to obtain the investment forecast results of each level of management budget sub-item and the project as a whole.
9. A storage medium storing a computer program executable by a processor, characterized in that, When the computer program is executed, it implements the steps of the intelligent prediction method for hydropower and water conservancy project investment as described in any one of claims 1 to 7.
10. An intelligent prediction device for investment in hydropower and water conservancy projects, comprising a memory and a processor, wherein the memory stores a computer program executable by the processor, characterized in that, When the computer program is executed, it implements the steps of the intelligent prediction method for hydropower and water conservancy project investment as described in any one of claims 1 to 7.