Intelligent analysis and management system for tunnel progress based on surrounding rock rules
By establishing an intelligent analysis and control system for tunnel progress based on surrounding rock rules, refined and intelligent control of the entire tunnel construction process has been achieved. This has solved the problems of scattered data, rough progress analysis, and low collaborative efficiency in traditional tunnel construction, and improved the accuracy and efficiency of construction.
Patent Information
- Application Number
- CN202610397358.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-03-30
- Publication Date
- 2026-11-24
AI Technical Summary
Traditional tunnel construction progress control models cannot adapt to complex geological conditions, resulting in a disconnect between construction procedures and geological conditions, fragmented data management, rough progress analysis, lack of refined simulation and collaborative control, and difficulty in ensuring construction safety and cost control.
Establish a tunnel progress intelligent analysis and control system based on surrounding rock rules. Through a complete control architecture of multi-source data acquisition, dual-drive rule construction, progress prediction and identification, root cause diagnosis and decision-making, and BIM collaborative visualization, achieve standardized governance and unified access to multi-source data throughout the tunnel construction cycle, construct a construction rule system adapted to dynamic changes in surrounding rock, and complete refined progress prediction and multi-role collaborative control of all processes.
It has enabled refined and intelligent management and control of the entire tunnel construction process, improved the accuracy and efficiency of construction, solved the problems of disconnect between rules and the site, data barriers and low collaboration efficiency in the traditional management and control model, and ensured construction safety and cost control.
Smart Images

Figure CN123159647A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of intelligent management and control technology for tunnel construction, specifically to an intelligent analysis and control system for tunnel progress based on surrounding rock rules. Background Technology
[0002] In the ongoing development of my country's transportation infrastructure, tunnel engineering, as a key control project in highways, railways, urban rail transit, and water conservancy projects, is experiencing a continuous increase in construction scale and difficulty. More and more tunnel projects need to traverse areas with complex and variable geological conditions. The uncertainty of surrounding rock conditions poses significant challenges to the schedule management, cost control, and safety management of tunnel construction. Construction schedule management, as a core aspect of tunnel project management, directly determines whether the overall project goals can be successfully achieved and is closely related to project safety, engineering quality, and construction costs. With the deep integration of digital and intelligent technologies in the engineering construction field, smart construction site construction has become a core direction for the tunnel engineering industry. The industry's demand for refined, intelligent, and full-process management of tunnel construction progress is increasingly urgent. There is a pressing need to establish an intelligent management system that can adapt to dynamic changes in surrounding rock geological conditions and connect the entire chain of data collection, rule adaptation, progress analysis, and collaborative management. This system is essential to address various management challenges in tunnel construction under complex geological conditions and achieve scientific management and efficient advancement of tunnel construction progress.
[0003] In the current field of tunnel construction progress control, traditional technical models still have many unresolved pain points and defects, failing to adapt to the refined management needs of tunnel construction under complex geological conditions. Traditional progress control relies heavily on manual experience, employing a crude schedule planning and control model that cannot achieve dynamic adaptation between construction procedures and surrounding rock geological conditions. It exhibits a significant lag in response to changes in surrounding rock conditions, easily leading to a disconnect between construction procedures and on-site geological conditions, making it difficult to ensure the rationality and standardization of construction procedures. At the data management level, under the traditional model, various types of tunnel construction data are scattered across different stages, systems, and participants, with inconsistent data formats and severe data silos, making it impossible to achieve comprehensive data aggregation. The traditional approach of centralized, standardized processing and shared access makes it difficult to fully leverage the supporting role of data in progress control. In terms of progress analysis and handling, traditional progress projections are mostly macro-level and extensive schedule planning, failing to achieve refined progress projections for all processes. Progress deviation identification is lagging, and there is a lack of hierarchical early warning mechanisms. Once progress deviations occur, it is impossible to accurately pinpoint the root cause. Handling solutions often rely on manual experience and lack data support, resulting in insufficient targeting and effectiveness. At the same time, the traditional model lacks efficient multi-role collaborative management and full-link visualization methods, leading to poor information exchange among participants, low collaboration efficiency, and a high risk of delays, cost overruns, and even potential construction safety hazards. It cannot meet the current development needs of intelligent construction in tunnel engineering. Summary of the Invention
[0004] The purpose of this invention is to overcome the shortcomings of existing technologies and provide an intelligent analysis and control system for tunnel progress based on surrounding rock rules. It establishes a complete control architecture encompassing multi-source data acquisition and processing, dual-drive rule construction, progress prediction and identification, root cause diagnosis and decision-making, and BIM collaborative visualization. The system achieves standardized governance and unified access to multi-source data throughout the entire tunnel construction cycle, constructs a construction rule system adapted to dynamic changes in surrounding rock, completes refined progress prediction for all processes, graded early warning of deviations, and precise root cause location, and combines a lightweight BIM model to achieve multi-role collaboration and full-link visualized control. This invention opens up a closed loop for the entire tunnel construction progress control process, solving the pain points of traditional control models such as extensiveness, data barriers, and delayed response, significantly improving the refinement and intelligence level of tunnel construction control, and providing reliable technical support for efficient and safe tunnel construction.
[0005] To solve the above-mentioned technical problems, the present invention provides the following technical solution: a tunnel progress intelligent analysis and control system based on surrounding rock rules, the system comprising:
[0006] Multi-source data acquisition module: Used to acquire tunnel construction data through various acquisition methods, collect historical and benchmark data to form a full data pool, process the raw data using standardized fusion algorithms, build a construction data platform, and realize real-time data updates and unified access;
[0007] The construction data platform adopts a distributed storage architecture, storing all standardized data processed by a standardized fusion algorithm, aggregated historical construction data, and benchmark data from similar projects. The data platform supports real-time data backup and can store data throughout the entire tunnel construction cycle. It features a fast retrieval function, allowing users to search for target data based on three dimensions: construction section, time, and data type. The data platform uses a B / S architecture to adapt to multi-terminal access, enabling real-time data updates and unified access, ensuring that all modules can quickly obtain the data required by the platform.
[0008] Dual-drive rule construction module: Based on the standardized surrounding rock geological data in the full data pool output by the multi-source data acquisition module, it establishes a single-cycle construction rule library for different surrounding rock levels, formulates adaptive transition rules between surrounding rocks, supports free splitting and connection of construction sections, and establishes an automatic mapping mechanism between surrounding rock construction rules and construction sections.
[0009] The automatic mapping mechanism between the surrounding rock construction rules and construction segments established by the dual-drive rule construction module is as follows: The system acquires standardized surrounding rock geological data of each construction segment from the multi-source data acquisition module in real time and extracts the current surrounding rock grade of each construction segment; based on the extracted surrounding rock grade, it matches the corresponding level of construction rules from the single-cycle construction rule library and automatically allocates parameters such as excavation step distance and operation time of each process in the rules to the corresponding construction segment; when the surrounding rock grade of a certain construction segment changes, the system automatically re-extracts the new surrounding rock grade of the construction segment, matches the corresponding single-cycle construction rule, and updates the construction parameters of the construction segment; when a construction segment is split or merged, the system automatically re-identifies the surrounding rock grade of each construction segment after splitting or merging and re-establishes the mapping relationship between each construction segment and the surrounding rock construction rules.
[0010] Progress prediction and identification module: Based on the standardized data of the multi-source data acquisition module and the rule system of the dual-drive rule construction module, the progress prediction algorithm driven by the surrounding rock rules is used to predict the progress of the whole process in hours, compare the deviation between the predicted progress and the actual progress in real time, and output the deviation information.
[0011] Root cause diagnosis and decision-making module: Based on the deviation information output by the progress deduction and identification module and the full data of the multi-source data acquisition module, it quantifies the deviation contribution of each potential root cause through a causal inference-type deviation root cause contribution algorithm to identify the root cause, automatically generates treatment suggestions, and synchronizes the results to the data platform.
[0012] BIM Collaborative Visualization Module: Used to call data from the multi-source data acquisition module and the dual-drive rule construction module based on the BIM lightweight engine, automatically build and update the lightweight tunnel BIM model in real time, and support multi-role collaborative work and full-link data visualization.
[0013] Furthermore, the multi-source data acquisition module employs various acquisition methods, including face image recognition acquisition, monitoring sensor acquisition, mobile terminal acquisition, and on-site industrial control system integration acquisition. Face image recognition acquisition involves deploying 3-5 high-definition imaging devices at the face, automatically acquiring face images every 30 minutes. Image recognition technology is used to extract parameters such as rock joint spacing, integrity coefficient, and groundwater seepage status, automatically matching the preliminary rock grade determination results, and synchronously uploading them to the construction data platform. Monitoring sensors are deployed in a distributed manner, with convergence sensors, stress sensors, and vibration sensors deployed around the face, inside the rock, and on the construction equipment. The sensor sampling frequency is set to once per hour, collecting real-time data on rock deformation, equipment vibration values, and support stress.
[0014] Furthermore, the mathematical expression of the standardized fusion algorithm is:
[0015] in For the first Standardized fusion values of core construction data; For the first Number of data collection sources; For the first In the class of data, the first Weight of each data source; For the first In the class of data, the first The original collected values from each source; For the first In the class of data, the first The data credibility correction factor for each collection source ranges from 0.8 to 1.0; For the first Correlation coefficient between class data and surrounding rock geological conditions; For the first The amount of correction for the deviation between the data and historical benchmark data of similar projects; When processing the raw data using the standardized fusion algorithm, outliers are first removed from the collected raw data. The 3σ principle is used to identify and delete data that exceeds the reasonable range. Then, the raw data in different formats are uniformly converted. Data collected by image recognition, sensors, mobile terminals, and on-site industrial control systems are uniformly converted into JSON format. Finally, the converted standardized data is associated and labeled. Rock-related data, equipment-related data, and progress-related data are labeled one-to-one with construction sections and construction procedures to form tagged standardized data. After completing the entire process of raw data processing, the data is pushed to the construction data platform.
[0016] Furthermore, the dual-drive rule construction module targets different surrounding rock levels, including Class III, Class IV, and Class V surrounding rock. The specific parameters of the single-cycle construction rule library are as follows: for Class III surrounding rock, the single-cycle excavation step distance is 8-10m, the excavation operation time is 6-8h, the support operation time is 3-4h, and the lining operation time is 10-12h; for Class IV surrounding rock, the single-cycle excavation step distance is 5-8m, the excavation operation time is 8-10h, the support operation time is 4-6h, and the lining operation time is 14-16h; for Class V surrounding rock, the single-cycle excavation step distance is 3-5m, the excavation operation time is 10-12h, the support operation time is 6-8h, and the lining operation time is 18-20h. The operation time of each process can be dynamically adjusted according to the actual construction efficiency on site, with the adjustment range not exceeding ±20%.
[0017] Furthermore, the adaptive transition rules between surrounding rocks formulated by the dual-drive rule construction module set corresponding transition methods for changes in the surrounding rock grades of Class III, IV, and V. When the surrounding rock grade of the construction section changes from a high grade to a low grade, the single-cycle construction rule corresponding to the low-grade surrounding rock is directly adopted from the first construction cycle of the surrounding rock grade change. When the surrounding rock grade of the construction section changes from a low grade to a high grade, a transition cycle is set, and the operation time of each process in the transition cycle is gradually adjusted according to the average of the standard operation time of the corresponding process in the low-grade surrounding rock and the high-grade surrounding rock. After the transition cycle is completed, the single-cycle construction rule corresponding to the high-grade surrounding rock is switched.
[0018] Furthermore, in the progress prediction and identification module, the mathematical expression of the surrounding rock rule-driven hourly progress prediction algorithm is:
[0019] in for The cumulative construction progress is driven by the surrounding rock rules at all times, progressing hourly. This represents the initial construction progress. for The number of construction cycles completed within a given time period; For the first The actual working time of each construction cycle; For the first The surrounding rock grade adaptation coefficient for each cycle, Class III surrounding rock Class IV surrounding rock Class V surrounding rock ; For the first Standardized data of the surrounding rock corresponding to each cycle; For the first Standard operation time for each cycle; for The number of non-construction periods within a given timeframe; For the first The duration of each non-construction period; For the first Progress deduction coefficient for non-construction periods, complete work stoppage Partial work stoppage ; The algorithm uses a surrounding rock rule-driven hourly progress projection algorithm to project the progress of all construction processes in hourly units. Specifically, it uses one hour as the minimum time unit, calls the single-cycle construction rule library and adaptive transition rules of the dual-drive rule construction module to obtain parameters such as the surrounding rock grade adaptation coefficient and single-cycle standard operation time for each construction section. Combined with the standardized data output by the multi-source data acquisition module, it calculates the actual operation time and completion progress of each process in each construction section within each hour. It automatically deducts the user-defined non-construction time period and accumulates the completion mileage of each process in each construction section hourly to generate hourly construction progress data. At the same time, it supports parallel projection of multiple schedule plans. Each plan has its own construction rhythm and non-construction time period parameters, and each plan carries out full-process progress projection and outputs its own projection data.
[0020] Furthermore, in the full-process progress simulation of the progress simulation and identification module, the type, duration, and frequency of non-construction periods can be customized. Equipment maintenance periods are set to a fixed day per week, with each maintenance lasting 8-12 hours. Downtime periods can be temporarily set according to construction needs, and the corresponding non-construction time is automatically deducted during progress simulation. The deviation between the simulated progress and the actual progress is compared in real time, and a three-level early warning threshold is set: Level 1 deviation is ≤5%, Level 2 deviation is 5% < deviation ≤10%, and Level 3 deviation is >10%. Early warning information is pushed to personnel with different permissions for different levels of deviation.
[0021] Furthermore, the mathematical expression for the causal inference-type bias root cause contribution algorithm in the root cause diagnosis decision module is:
[0022] in For the first The contribution of each potential root cause to the schedule deviation, ranging from 0 to 1; for The absolute value of the progress deviation at any given time; For the first The influence weight of each root cause; For the first Standardized data corresponding to each root cause; This represents the total number of potential root causes, categorized into 8 types. For the first The correlation correction coefficient between root causes and surrounding rock grade, and the root causes of surrounding rock types. Non-surrounding rock root causes ; To identify root causes, a causal inference-based deviation root cause contribution algorithm is used to quantify the deviation contribution of each potential root cause. Specifically, the following steps are taken: First, a causal analysis network for schedule deviations is constructed, including eight core nodes: surrounding rock geology, equipment operating conditions, personnel efficiency, material supply, process coordination, external environment, design changes, and safety management. Each core node has at least three sub-nodes. The full historical and real-time data from the multi-source data acquisition module are used to assign values to each node to quantify its impact on schedule deviations. The deviation contribution of each potential root cause is calculated using the algorithm and sorted from highest to lowest contribution value. Root causes with a contribution value of at least 30% are selected as root causes, and the corresponding sub-nodes and associated data for each root cause are clearly marked.
[0023] Furthermore, each potential root cause in the root cause diagnosis and decision-making module corresponds to eight core nodes: surrounding rock geology node, equipment condition node, personnel efficiency node, material supply node, process connection node, external environment node, design change node, and safety management node. Each core node contains at least three sub-nodes. The equipment condition node includes three sub-nodes: equipment failure, equipment maintenance, and equipment efficiency. The surrounding rock geology node includes three sub-nodes: changes in surrounding rock grade, excessive surrounding rock deformation, and surrounding rock breakage. The personnel efficiency node includes three sub-nodes: personnel allocation, skill level, and work shifts.
[0024] Furthermore, the lightweight BIM model of the tunnel in the BIM collaborative visualization module is constructed based on the tunnel design data, surrounding rock geological data, and construction segment data output by the multi-source data acquisition module and the dual-drive rule construction module, which are called by the BIM lightweight engine. The model includes components of the tunnel surrounding rock, excavation outline, initial support, secondary lining, invert arch, construction access road, and working face. The size and material parameters of each component are consistent with the standardized data output by the multi-source data acquisition module. The division of construction segment components corresponds completely to the construction segments split by the dual-drive rule construction module, and can be displayed in layers according to the division of construction segments. Each layer corresponds to one construction segment. The components of each construction segment are labeled with the parameters of the corresponding surrounding rock grade and construction rules, and are linked in real time with the data output by the multi-source data acquisition module, the dual-drive rule construction module, the progress prediction and identification module, and the root cause diagnosis and decision-making module. Beneficial effects
[0025] Compared with existing technologies, this intelligent tunnel progress analysis and control system based on surrounding rock rules has the following advantages: I. This invention establishes a construction data platform with distributed storage, efficient retrieval, and multi-terminal adaptability through multi-dimensional construction data collection and standardized management. This platform enables the collection, standardized processing, unified storage, and real-time retrieval of multi-source heterogeneous data throughout the entire tunnel construction cycle, effectively breaking down barriers between multiple data sources during tunnel construction and achieving seamless data sharing across the entire construction chain. Simultaneously, based on standardized surrounding rock geological data, it constructs a single-cycle construction rule library adapted to different surrounding rock conditions and adaptive transition rules between different surrounding rocks. An automatic mapping mechanism between construction rules and construction segments is established, allowing for dynamic adaptation of construction rules as surrounding rock conditions change and construction segments adjust. This achieves precise matching between tunnel construction procedures and geological conditions, solving the problems of disconnect between rules and the actual site and coarse procedure control in traditional construction management, significantly improving the refinement and standardization of tunnel construction management.
[0026] Second, this invention utilizes an hourly, full-process progress prediction algorithm driven by surrounding rock rules to achieve refined, time-by-time prediction of tunnel construction progress. It can compare the predicted progress with the actual progress in real time and trigger tiered early warnings, enabling timely identification and control of progress anomalies. Simultaneously, through a causal inference-based root cause analysis algorithm, it constructs a causal analysis network covering all dimensions of construction influencing factors, quantifies the contribution of various potential factors to progress deviations, accurately locates the root causes of deviations, and automatically generates remedial suggestions. Combined with a lightweight BIM model that links with all modules of data in real time, it enables multi-role collaborative operations and full-link data visualization, establishing a closed-loop process encompassing data collection, rule adaptation, progress prediction, root cause diagnosis, and collaborative management. This addresses the pain points of traditional tunnel progress management, such as lagging progress, inaccurate problem location, and low collaborative efficiency, comprehensively improving the intelligence level of tunnel construction progress management and overall construction efficiency.
[0027] Other advantages, objectives and features of the invention will be set forth in part in the description which follows, and in part will be apparent to those skilled in the art from the following examination or study, or may be learned from the practice of the invention. Attached Figure Description
[0028] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the accompanying drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are merely some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without any creative effort.
[0029] Figure 1 This is a framework diagram of a tunnel progress intelligent analysis and control system based on surrounding rock rules. Figure 2This is a schematic diagram of data transmission between modules of a tunnel progress intelligent analysis and control system based on surrounding rock rules. Detailed Implementation
[0030] To further illustrate the technical means and effects of the present invention in achieving its intended purpose, the following detailed description of the specific implementation methods, structures, features, and effects of the present invention, in conjunction with the accompanying drawings and preferred embodiments, is provided below. Example
[0031] The intelligent tunnel progress analysis and control system based on surrounding rock rules of the present invention, such as Figure 1 The system includes a multi-source data acquisition module, a dual-drive rule construction module, a progress prediction and identification module, a root cause diagnosis and decision-making module, and a BIM collaborative visualization module. The multi-source data acquisition module establishes data connections with each of these modules; the dual-drive rule construction module establishes data connections with both the progress prediction and identification module and the BIM collaborative visualization module; the progress prediction and identification module establishes a data connection with the root cause diagnosis and decision-making module; and the root cause diagnosis and decision-making module synchronizes the analysis results to the construction data platform built by the multi-source data acquisition module. These modules work collaboratively to achieve intelligent analysis, prediction, deviation identification, and control decisions for tunnel construction progress. The specific process is as follows: Figure 2 As shown.
[0032] Multi-source data acquisition module: The multi-source data acquisition module is responsible for the collection, processing, storage, and retrieval of all tunnel construction data. It achieves comprehensive acquisition of construction data through various acquisition methods, and after standardized processing, a construction data platform is built to provide unified, real-time data source support for other modules. The specific implementation method is as follows: Multiple data acquisition methods: The data acquisition methods include four categories: face image recognition acquisition, monitoring sensor acquisition, mobile terminal acquisition, and on-site industrial control system integration acquisition. These methods work together to achieve comprehensive acquisition of multi-dimensional data such as surrounding rock geology, equipment operation, and process operations. Working face image recognition and acquisition: Deploy 3-5 high-definition imaging devices in the working face area, with the device deployment positions covering the entire field of view of the working face. The acquisition frequency is set to automatically acquire working face images every 30 minutes. The acquired images are analyzed using image recognition technology to extract geological parameters related to the surrounding rock, such as the spacing of rock joints, integrity coefficient, and groundwater seepage status. Based on the extracted parameters, the preliminary judgment result of the surrounding rock grade is automatically matched. The original image data, extracted parameters, and preliminary judgment result of the surrounding rock grade are uploaded to the construction data platform in real time.
[0033] Monitoring sensor acquisition: A distributed deployment method is adopted, with convergence sensors, stress sensors, and vibration sensors deployed around the working face, inside the surrounding rock, and on the construction equipment. The sampling frequency of the sensors is uniformly set to once per hour, collecting data such as the deformation of the surrounding rock, support stress, and vibration values of the equipment in real time. The collected data is directly uploaded to the construction data platform after signal conversion.
[0034] Mobile data collection: Construction workers can manually fill in and upload data such as the completion status of construction procedures, on-site manual inspection data, and construction problem records through their mobile terminals, adapting to the data acquisition needs of areas without automatic data collection equipment.
[0035] Data collection and integration with on-site industrial control systems: Data is integrated with the industrial control systems of tunnel boring machines, support equipment, and transportation equipment at the tunnel construction site to achieve automatic capture and synchronization of equipment and process-related data such as construction equipment operating parameters, process operation duration, and construction mileage.
[0036] Construction data platform setup: The construction data platform adopts a distributed storage architecture, storing all standardized data processed by a standardized fusion algorithm, collected historical tunnel construction data, and benchmark data from similar tunnel projects. The platform features an automatic real-time backup mechanism once per hour, with storage capacity sufficient to meet at least five years of tunnel construction lifecycle data storage needs. It also includes a fast retrieval function, allowing for precise searching of target data based on construction section, time, and data type, with a retrieval response time of less than one second. The platform employs a B / S architecture, adapting to multiple terminals such as computers, tablets, and mobile devices, enabling real-time data updates and unified access, ensuring that all other modules of the system can quickly obtain the necessary data from the platform.
[0037] Raw data standardization processing: A standardized fusion algorithm is used to process the raw data acquired through various acquisition methods throughout the entire process. The mathematical expression of the standardized fusion algorithm is:
[0038] in For the first Standardized fusion values of core construction data; For the first Number of data collection sources; For the first In the class of data, the first Weight of each data source; For the first In the class of data, the first The original collected values from each source; For the first In the class of data, the first The data credibility correction factor for each collection source ranges from 0.8 to 1.0; For the first Correlation coefficient between class data and surrounding rock geological conditions; For the first The amount of correction for the deviation between the data and the benchmark data of similar projects in the past.
[0039] The standardization process for raw data is implemented in three steps: data purification, format standardization, and associated annotation. Outlier removal: The 3σ principle is used to identify outliers in the collected raw data, and outliers that exceed the reasonable range are deleted to ensure the validity of the data.
[0040] Unified format conversion: The raw data of different formats are uniformly converted, and the image analysis data collected by the face image recognition, the sensor data collected by the monitoring sensor, the manual data filled in by the mobile terminal, and the equipment operation data collected by the on-site industrial control system are all converted into JSON format to eliminate data format differences.
[0041] Association labeling: The standardized data after format conversion is classified and labeled, and the surrounding rock related data, equipment related data, and progress related data are associated with the corresponding construction sections and construction procedures to form standardized data with labels. After processing, the data is pushed to the construction data platform for storage.
[0042] Dual-drive rule construction module: The dual-drive rule construction module is based on the standardized surrounding rock geological data in the full data pool output by the multi-source data acquisition module. It constructs a corresponding construction rule system around the surrounding rock grade of tunnel construction, establishes a dynamic mapping relationship between construction rules and construction segments, and provides a rule basis for progress prediction. The specific implementation method is as follows: Establishment of a single-cycle construction rule base: For Class III, IV, and V surrounding rock commonly encountered in tunnel construction, corresponding single-cycle construction rule libraries are established, clarifying the key construction parameters for each rock class. These parameters can be dynamically fine-tuned based on actual on-site construction efficiency, with an adjustment range not exceeding ±20%. Specific parameter settings are as follows: Class III surrounding rock: The single-cycle excavation step distance is 8-10m, the excavation operation time is 6-8h, the support operation time is 3-4h, and the lining operation time is 10-12h. Class IV surrounding rock: The single-cycle excavation step distance is 5-8m, the excavation operation time is 8-10h, the support operation time is 4-6h, and the lining operation time is 14-16h. Class V surrounding rock: The single-cycle excavation step distance is 3-5m, the excavation operation time is 10-12h, the support operation time is 6-8h, and the lining operation time is 18-20h.
[0043] Formulating adaptive transition rules between surrounding rocks: For the changes in surrounding rock grades III, IV, and V, corresponding transition methods for construction rules are set. All parameters of the transition rules can be manually adjusted according to the actual geological conditions of the construction section, with the adjustment range not exceeding ±15% of the corresponding parameters of the single-cycle construction rules. Change from high-grade to low-grade surrounding rock: When the surrounding rock grade of the construction section changes from high-grade to low-grade, starting from the first construction cycle of the change in surrounding rock grade, the single-cycle construction rule corresponding to the low-grade surrounding rock is directly adopted, without the need to set a transition stage. Change from low-grade to high-grade surrounding rock: When the surrounding rock grade of the construction section changes from low-grade to high-grade, 3-5 transition cycles are set. The operation time of each process in the transition cycle is gradually adjusted according to the average of the standard operation time of the corresponding process in low-grade and high-grade surrounding rock. After the transition cycle is completed, the single-cycle construction rule corresponding to the high-grade surrounding rock is officially switched.
[0044] The automatic mapping mechanism between construction rules and construction segments is implemented. An automatic mapping mechanism between surrounding rock construction rules and construction segments is established to achieve dynamic and accurate matching between construction rules and construction segments. The specific implementation steps are as follows: The system acquires standardized surrounding rock geological data of each construction section in real time from the multi-source data acquisition module, and extracts the current surrounding rock grade of each construction section based on the data; Based on the extracted surrounding rock grade, the corresponding construction rules are matched from the single-cycle construction rule library, and the parameters such as the excavation step distance and the operation time of each process in the rules are automatically allocated to the corresponding construction section. When the surrounding rock grade of a construction section changes, the system automatically extracts the new surrounding rock grade of the construction section, matches the corresponding single-cycle construction rules, and updates the construction parameters of the construction section in real time. When construction sections are split or merged, the system automatically re-identifies the surrounding rock grade of each construction section after the split or merge, re-establishes the mapping relationship between each construction section and the surrounding rock construction rules, and allocates the corresponding construction parameters.
[0045] Meanwhile, the module supports the free splitting and connection of construction sections, and the construction sections can be flexibly adjusted according to the on-site construction needs. After the adjustment, the mapping mechanism will automatically trigger an update to ensure the effectiveness of the matching between the rules and the construction sections.
[0046] Progress prediction and identification module: The progress prediction and identification module is based on the standardized data from the multi-source data acquisition module and the rule system of the dual-drive rule construction module. It uses a surrounding rock rule-driven hourly progress prediction algorithm to achieve hourly progress prediction for all tunnel construction processes. Simultaneously, it compares the predicted progress with the actual progress and provides tiered early warnings. The specific implementation method is as follows: Implementation of hourly progress projection algorithm: The mathematical expression for the hourly progress prediction algorithm driven by surrounding rock rules is:
[0047] in for The cumulative construction progress is driven by the surrounding rock rules at all times, progressing hourly. This represents the initial construction progress. for The number of construction cycles completed within a given time period; For the first The actual working time of each construction cycle; For the first The surrounding rock grade adaptation coefficient for each cycle, Class III surrounding rock Class IV surrounding rock Class V surrounding rock ; For the first Standardized surrounding rock data corresponding to each cycle; For the first Standard operation time for each cycle; for The number of non-construction periods within a given timeframe; For the first The duration of each non-construction period; For the first Progress deduction coefficient for non-construction periods, complete work stoppage Partial work stoppage .
[0048] The entire process schedule is simulated using 1 hour as the smallest time unit. The specific steps are as follows: Call the single-cycle construction rule library and adaptive transition rule of the dual-drive rule construction module to obtain basic parameters such as the surrounding rock grade adaptation coefficient and single-cycle standard operation time for each construction section; By combining the standardized data output from the multi-source data acquisition module, the actual working time and completion progress of each process in each construction section are calculated for each hour. Based on preset non-construction period parameters, the system automatically deducts the duration of the corresponding period and accumulates the completed mileage of each construction section and each process hourly to generate hourly construction progress data.
[0049] The module supports parallel simulation of multiple schedule plans. Each plan can be set with parameters such as construction rhythm and non-construction periods. The system conducts full-process progress simulation for each plan and outputs simulation data independently, providing multi-dimensional reference for the construction party's schedule planning.
[0050] Custom settings for non-construction periods: The system supports custom settings for the type, duration, and frequency of non-construction periods. During progress simulation, the corresponding non-construction time is automatically deducted. The preset basic non-construction periods are set as follows: Nighttime no-work hours: Fixed at 22:00-6:00 the next day, which is the legally mandated no-work hours and cannot be manually adjusted; Equipment maintenance period: Set to one fixed day per week, with each maintenance session lasting 8-12 hours. The maintenance date and specific duration can be manually adjusted according to the maintenance needs of the construction equipment. Temporary work stoppage periods: can be added, deleted, and modified temporarily according to on-site construction needs to accommodate work stoppages caused by unforeseen circumstances such as weather, materials, and personnel.
[0051] Schedule Deviation Comparison and Graded Early Warning: The system compares the hourly projected progress data with the actual construction progress data collected by the multi-source data acquisition module in real time, calculates the deviation, and sets a three-level early warning threshold to issue warnings for different levels of deviation. Different levels of deviation are pushed with warning information to construction management personnel with different permissions. The specific thresholds are set as follows: Level 1 Deviation: Deviation ≤ 5%, which is a minor deviation. Warning information will be sent to the on-site construction team management personnel. Level 2 deviation: 5% < deviation ≤ 10%, which is considered a moderate deviation. The warning information will be sent to the person in charge of the project construction management department. Level 3 Deviation: Deviation > 10% is considered a severe deviation, and the warning information will be sent to both the person in charge of the project construction management department and the project manager.
[0052] Root cause diagnosis decision module: The root cause diagnosis and decision-making module, based on the deviation information output by the schedule projection and identification module and the full data from the multi-source data acquisition module, quantifies the deviation contribution of each potential root cause using a causal inference-based deviation root cause contribution algorithm. This accurately identifies the root cause of schedule deviations and automatically generates remedial recommendations, synchronizing the analysis results and remedial recommendations to the construction data platform. The specific implementation method is as follows: Implementation of the Root Cause Contribution Algorithm The mathematical expression for the causal inference-based biased root cause contribution algorithm is:
[0053] in For the first The contribution of each potential root cause to the schedule deviation, ranging from 0 to 1; for The absolute value of the progress deviation at any given time; For the first The influence weight of each root cause; For the first Standardized data corresponding to each root cause; This represents the total number of potential root causes, categorized into 8 types. For the first The correlation correction coefficient between root causes and surrounding rock grade, and the root causes of surrounding rock types. Non-surrounding rock root causes .
[0054] Root cause identification of schedule deviations: Using a causal inference-based root cause contribution algorithm as the core, the root causes of schedule deviations are identified through the following steps: Construct a causal analysis network for schedule deviations. The network includes eight types of nodes: surrounding rock geology, equipment condition, personnel efficiency, material supply, process connection, external environment, design changes, and safety management. Each node has at least three sub-nodes. The equipment condition node includes three sub-nodes: equipment failure, equipment maintenance, and equipment efficiency. The surrounding rock geology node includes three sub-nodes: changes in surrounding rock grade, excessive surrounding rock deformation, and surrounding rock breakage. The personnel efficiency node includes three sub-nodes: personnel allocation, skill level, and work shifts. The full historical and real-time data from the multi-source data acquisition module are called to assign values to each node in the causal analysis network, quantifying the impact of each node on the progress deviation. The bias contribution of each potential root cause is calculated using a causal inference-based bias root cause contribution algorithm, and the calculation results are sorted from high to low according to the contribution value. Root causes with a contribution rate of no less than 30% are selected as the fundamental causes of progress deviations. Each root cause is clearly marked with its corresponding sub-nodes and related data to achieve accurate root cause location.
[0055] Action recommendations are automatically generated and synchronized with data: Based on the identified root causes and corresponding related data, combined with industry standards for tunnel construction and benchmark experience from similar projects, the system automatically generates targeted suggestions for addressing schedule deviations. These suggestions cover aspects such as adjusting construction parameters, optimizing resource allocation, and improving workflow coordination. Simultaneously, the root cause analysis results, contribution calculation data, and action suggestions are all synchronized and stored in the construction data platform, providing data support for subsequent construction progress management and the application of experience from similar projects.
[0056] BIM Collaborative Visualization Module: The BIM collaborative visualization module, based on the lightweight BIM engine, calls relevant data from the multi-source data acquisition module and the dual-drive rule building module to automatically construct and update the lightweight BIM model of the tunnel in real time. This enables multi-role collaborative work and end-to-end data visualization in tunnel construction. The specific implementation method is as follows: Lightweight BIM model construction for tunnels: Based on the lightweight BIM engine, the tunnel design data and surrounding rock geological data output by the multi-source data acquisition module and the construction segment data output by the dual-drive rule construction module are retrieved to automatically construct a lightweight BIM model of the tunnel. The model includes various components such as tunnel surrounding rock, excavation outline, initial support, secondary lining, invert arch, construction access road, and working face. The size, material and other parameters of each component are kept consistent with the standardized data output by the multi-source data acquisition module in real time. The division of construction segment components corresponds completely to the construction segments split by the dual-drive rule construction module, ensuring that the model is highly matched with the actual on-site construction conditions.
[0057] Model visualization and data interaction: Layered display: The model can be displayed in layers according to the division of construction sections. Each layer corresponds to one construction section. The components of each construction section are marked with key information such as the corresponding surrounding rock grade and construction rules and related parameters, which makes it convenient for managers to view and analyze the construction status of each construction section separately. Data viewing: All components of the model can be selected individually. After selection, you can view the detailed data corresponding to that component, including design parameters, real-time construction data, progress simulation data, deviation analysis data, etc. Real-time linkage: The model maintains real-time linkage with the data output from the multi-source data acquisition module, dual-drive rule construction module, progress prediction and identification module, and root cause diagnosis and decision-making module. When the data of any module is updated, the model will be adjusted and refreshed synchronously to ensure that the content displayed by the model is the latest construction data.
[0058] Multi-role collaborative work: The model is adapted to the work needs of different roles in tunnel construction, such as design, construction, and management. It sets corresponding operation and viewing permissions for each role, and each role can access the model through multiple terminals to realize the sharing and collaborative viewing of construction data. This solves the problem of information asymmetry among roles in traditional construction and improves the efficiency of construction collaboration.
[0059] The intelligent tunnel progress analysis and control system based on surrounding rock rules of this invention establishes a unified construction data platform through comprehensive collection and standardized processing of multi-source data. It constructs a refined construction rule system based on the surrounding rock grade, enabling hourly progress projection of the entire tunnel construction process. Combined with algorithms, it accurately identifies the root causes of progress deviations and generates remedial suggestions. At the same time, it realizes the visualization of construction data and multi-role collaboration through a lightweight BIM model, forming an intelligent management system for the entire process of tunnel construction progress collection, projection, identification, diagnosis, and control. This effectively improves the accuracy and efficiency of tunnel construction progress management and solves the problems of data disorder, rough projection, and vague root cause location in traditional tunnel progress management.
[0060] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention in any way. Although the present invention has been disclosed above with reference to preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art can make some modifications or alterations to the above-disclosed technical content to create equivalent embodiments without departing from the scope of the present invention. Any simple modifications, equivalent changes and alterations made to the above embodiments based on the technical essence of the present invention without departing from the scope of the present invention shall still fall within the scope of the present invention.
Claims
1. A tunnel progress intelligent analysis and control system based on surrounding rock rules, characterized in that, The system includes: Multi-source data acquisition and processing module: Used to acquire tunnel construction data through various acquisition methods, collect historical and benchmark data to form a full data pool, process the raw data using standardized fusion algorithms, build a construction data platform, and realize real-time data updates and unified access; Dual-drive rule construction module: Based on the standardized surrounding rock geological data in the full data pool output by the multi-source data acquisition module, it establishes a single-cycle construction rule library for different surrounding rock levels, formulates adaptive transition rules between surrounding rocks, supports free splitting and connection of construction sections, and establishes an automatic mapping mechanism between surrounding rock construction rules and construction sections. Progress prediction and identification module: Based on the standardized data of the multi-source data acquisition module and the rule system of the dual-drive rule construction module, the progress prediction algorithm driven by the surrounding rock rules is used to predict the progress of the whole process in hours, compare the deviation between the predicted progress and the actual progress in real time, and output the deviation information. Root cause diagnosis and decision-making module: Based on the deviation information output by the progress deduction and identification module and the full data of the multi-source data acquisition module, it quantifies the deviation contribution of each potential root cause through a causal inference-type deviation root cause contribution algorithm to identify the root cause, automatically generates treatment suggestions, and synchronizes the results to the data platform. BIM Collaborative Visualization Module: Used to call data from the multi-source data acquisition module and the dual-drive rule construction module based on the BIM lightweight engine, automatically build and update the lightweight tunnel BIM model in real time, and support multi-role collaborative work and full-link data visualization.
2. The intelligent tunnel progress analysis and control system based on surrounding rock rules according to claim 1, characterized in that, The multi-source data acquisition module employs various acquisition methods, including face image recognition acquisition, monitoring sensor acquisition, mobile terminal acquisition, and on-site industrial control system integration acquisition. Face image recognition acquisition involves deploying 3-5 high-definition imaging devices at the face, automatically acquiring face images every 30 minutes. Image recognition technology is used to extract parameters such as rock joint spacing, integrity coefficient, and groundwater seepage status, automatically matching the preliminary rock grade determination results, and synchronously uploading them to the construction data platform. Monitoring sensors are deployed in a distributed manner, with convergence sensors, stress sensors, and vibration sensors deployed around the face, inside the rock, and on the construction equipment. The sensor sampling frequency is set to once per hour, collecting real-time data on rock deformation, equipment vibration values, and support stress.
3. The intelligent tunnel progress analysis and control system based on surrounding rock rules according to claim 1, characterized in that, The mathematical expression for the standardized fusion algorithm is: in For the first Standardized fusion values of core construction data; For the first Number of data collection sources; For the first In the class of data, the first Weight of each data source; For the first In the class of data, the first The original collected values from each source; For the first In the class of data, the first The data credibility correction factor for each collection source ranges from 0.8 to 1.0; For the first Correlation coefficient between class data and surrounding rock geological conditions; For the first The amount of correction for the deviation between the data and the benchmark data of similar projects in the past.
4. The intelligent tunnel progress analysis and control system based on surrounding rock rules according to claim 1, characterized in that, The dual-drive rule construction module targets different surrounding rock levels, including Class III, Class IV, and Class V surrounding rock. The specific parameters of the single-cycle construction rule library are as follows: for Class III surrounding rock, the single-cycle excavation step distance is 8-10m, the excavation operation time is 6-8h, the support operation time is 3-4h, and the lining operation time is 10-12h; for Class IV surrounding rock, the single-cycle excavation step distance is 5-8m, the excavation operation time is 8-10h, the support operation time is 4-6h, and the lining operation time is 14-16h; for Class V surrounding rock, the single-cycle excavation step distance is 3-5m, the excavation operation time is 10-12h, the support operation time is 6-8h, and the lining operation time is 18-20h. The operation time of each process can be dynamically adjusted according to the actual construction efficiency on site, with the adjustment range not exceeding ±20%.
5. The intelligent tunnel progress analysis and control system based on surrounding rock rules according to claim 1, characterized in that, The adaptive transition rules between surrounding rocks formulated by the dual-drive rule construction module set corresponding transition methods for changes in the surrounding rock grades of Class III, IV, and V. When the surrounding rock grade of the construction section changes from a high grade to a low grade, the single-cycle construction rule corresponding to the low-grade surrounding rock is directly adopted from the first construction cycle of the surrounding rock grade change. When the surrounding rock grade of the construction section changes from a low grade to a high grade, a transition cycle is set. The operation time of each process in the transition cycle is gradually adjusted according to the average of the standard operation time of the corresponding process in the low-grade surrounding rock and the high-grade surrounding rock. After the transition cycle is completed, the single-cycle construction rule corresponding to the high-grade surrounding rock is switched.
6. The intelligent tunnel progress analysis and control system based on surrounding rock rules according to claim 1, characterized in that, In the progress prediction and identification module, the mathematical expression of the hourly progress prediction algorithm driven by the surrounding rock rule is: in for The cumulative construction progress is driven by the surrounding rock rules at all times, progressing hourly. This represents the initial construction progress. for The number of construction cycles completed within a given time period; For the first The actual working time of each construction cycle; For the first The surrounding rock grade adaptation coefficient for each cycle, Class III surrounding rock Class IV surrounding rock Class V surrounding rock ; For the first Standardized surrounding rock data corresponding to each cycle; For the first Standard operation time for each cycle; for The number of non-construction periods within a given timeframe; For the first The duration of each non-construction period; For the first Progress deduction coefficient for non-construction periods, complete work stoppage Partial work stoppage .
7. The intelligent tunnel progress analysis and control system based on surrounding rock rules according to claim 1, characterized in that, In the full-process progress simulation of the progress simulation and identification module, the type, duration and frequency of non-construction periods can be customized. The equipment maintenance period is set to a fixed day of one week, with each maintenance lasting 8-12 hours. The downtime can be temporarily set according to construction needs. The corresponding non-construction time is automatically deducted during the progress simulation. The deviation between the simulated progress and the actual progress is compared in real time and a three-level early warning threshold is set. The first level deviation is ≤5%, the second level deviation is 5% < deviation ≤10%, and the third level deviation is >10%. Early warning information is pushed to personnel with different permissions for different levels of deviation.
8. The intelligent analysis and control system for tunnel progress based on surrounding rock rules according to claim 1, characterized in that, The mathematical expression for the causal inference-type bias root cause contribution algorithm in the root cause diagnosis decision module is as follows: in For the first The contribution of each potential root cause to the schedule deviation, ranging from 0 to 1; for The absolute value of the progress deviation at any given time; For the first The influence weight of each root cause; For the first Standardized data corresponding to each root cause; This represents the total number of potential root causes, categorized into 8 types. For the first The correlation correction coefficient between root causes and surrounding rock grade, and the root causes of surrounding rock types. Non-surrounding rock root causes .
9. The intelligent tunnel progress analysis and control system based on surrounding rock rules according to claim 1, characterized in that, Each potential root cause in the root cause diagnosis and decision-making module corresponds to eight core nodes: surrounding rock geology node, equipment condition node, personnel efficiency node, material supply node, process connection node, external environment node, design change node, and safety control node. Each core node contains at least three sub-nodes. The equipment condition node includes three sub-nodes: equipment failure, equipment maintenance, and equipment efficiency. The surrounding rock geology node includes three sub-nodes: changes in surrounding rock grade, excessive surrounding rock deformation, and surrounding rock breakage. The personnel efficiency node includes three sub-nodes: personnel allocation, skill level, and work shifts.
10. The intelligent tunnel progress analysis and control system based on surrounding rock rules according to claim 1, characterized in that, The lightweight BIM model of the tunnel in the BIM collaborative visualization module is constructed based on the tunnel design data, surrounding rock geological data output by the multi-source data acquisition module, and construction segment data output by the dual-drive rule construction module, which are called by the BIM lightweight engine. The model includes components of the tunnel surrounding rock, excavation outline, initial support, secondary lining, invert arch, construction access road, and working face. The size and material parameters of each component are consistent with the standardized data output by the multi-source data acquisition module. The division of construction segment components corresponds completely to the construction segments split by the dual-drive rule construction module, and can be displayed in layers according to the division of construction segments. Each layer corresponds to one construction segment. The components of each construction segment are labeled with the parameters of the corresponding surrounding rock grade and construction rules, and are linked in real time with the data output by the multi-source data acquisition module, dual-drive rule construction module, progress prediction and identification module, and root cause diagnosis and decision-making module.