Carbon emission calculation method and system for building decoration modification process

By constructing BIM models before and after the renovation and a graded carbon emission factor library, and combining them with the actual working conditions of construction equipment, the problems of inaccurate identification of the renovation scope and unclear accounting boundaries during the renovation process were solved, and more accurate carbon emission calculations were achieved.

CN123159658APending Publication Date: 2026-11-24CHINA CONSTRUCTION EIGHTH BUREAU GENERAL CONTRACTING CONSTRUCTION CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611251466.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-18
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing technologies make it difficult to accurately identify the actual scope of renovations during building decoration and renovation, resulting in unclear carbon emission accounting boundaries and difficulty in reflecting the actual operating conditions of construction equipment, leading to significant deviations in carbon emission calculations.

Method used

By constructing BIM models before and after the renovation, the renovation status and quantity of components are determined, a graded carbon emission factor library is established, and carbon emission is calculated in combination with the actual working conditions of construction equipment, including static carbon emission factors of materials and carbon emission factors of construction conditions, and the carbon emission of related materials and construction is integrated.

Benefits of technology

It improves the accuracy of carbon emission calculations during renovation and upgrading, reduces the duplication of existing materials and omissions in actual renovations, reflects the actual operational changes of construction equipment, and improves the correspondence between calculations and actual activities.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123159658A_ABST
    Figure CN123159658A_ABST
Patent Text Reader

Abstract

This invention discloses a method and system for carbon emission calculation during building decoration and renovation processes, belonging to the field of building carbon emission calculation technology. The method includes: constructing BIM models before and after the renovation; determining the renovation status and quantity of components based on component correspondence, parameter differences, and changes in engineering quantities; forming renovation task units and determining carbon emission accounting boundaries; establishing a hierarchical factor library of static carbon emission factors for materials and carbon emission factors for construction conditions; matching factors based on material information and actual operating conditions of construction equipment; associating the calculation results from the material side and the construction side with the renovation task units; and summarizing the results to obtain the carbon emission calculation results for the renovation process. This invention can reduce the duplication of existing materials and the omission of actual renovation parts, improving the correspondence between carbon emission calculation and actual renovation activities.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building carbon emission measurement technology, specifically to a method and system for measuring carbon emissions during building decoration and renovation processes. Background Technology

[0002] Building decoration and renovation typically involve the retention, demolition, replacement, partial renovation, and addition of existing wall, ceiling, floor, and partition components, along with material input, equipment construction, and energy consumption. Therefore, carbon emission calculation during the renovation process has become an important part of building energy conservation management and renovation scheme evaluation.

[0003] Currently, carbon emission calculations typically rely on bill of quantities, renovation design models, or BIM models to calculate material quantities and then match them with corresponding material carbon emission factors. For the construction phase, carbon emissions are often estimated based on the rated power of construction equipment, number of shifts, operating time, or energy type, combined with fixed carbon emission factors. This method can complete the overall carbon emission statistics for the project, but its calculation basis usually focuses on the post-renovation quantities or planned construction data. However, building decoration and renovation projects are different from new construction projects. The same existing component may have different ranges of changes such as retention, demolition, material replacement and partial renovation. It is difficult to accurately determine the actual amount of work changed in this renovation based solely on the model after the renovation or the difference in the amount of work. It is easy to double-count existing materials that have not changed, or to omit the partial demolition and new parts. At the same time, construction equipment has different operating states such as low load, normal load and high load during actual operation. Using uniform equipment parameters or fixed working condition factors is difficult to reflect the changes in actual construction energy consumption. Therefore, existing technologies are still insufficient to simultaneously address the problems of inaccurate identification of the actual renovation scope, unclear carbon emission accounting boundaries, and insufficient reflection of the actual operating conditions of construction equipment during the renovation process. To this end, it is necessary to provide carbon emission calculation methods and systems for the building decoration and renovation process in order to improve the correspondence between carbon emission calculations during the renovation process and actual construction activities. Summary of the Invention

[0004] To address the aforementioned technical issues, this solution provides a method and system for carbon emission calculation during the building decoration and renovation process. This technical solution resolves the problems of inaccurate identification of the actual renovation scope, unclear accounting boundaries, and difficulty in accurately reflecting changes in the operating conditions of construction equipment, which lead to significant deviations in carbon emission calculation.

[0005] To achieve the above objectives, the technical solution adopted by the present invention is as follows: Methods for calculating carbon emissions during building decoration and renovation processes include: S1. Based on the original building information and renovation design information of the building decoration and renovation project, construct the pre-renovation BIM model and the post-renovation BIM model, and associate the component identification, component parameters, material information, construction procedures and construction equipment; determine the component renovation status and status engineering quantity according to the correspondence between the components before and after the renovation, the differences in component parameters and the changes in engineering quantity, form a renovation task unit, and obtain the equipment operation parameters of the construction equipment. S2. Establish a graded carbon emission factor library, including static carbon emission factors of materials and construction condition carbon emission factors graded according to construction procedures, equipment types, energy types and equipment operating conditions. S3. Determine the carbon emission accounting boundary for each modification task unit based on the component modification status and the state engineering quantity, and limit the material changes, construction procedures and construction equipment included in the calculation. S4. Match the static carbon emission factor of the material with the material change based on the material information, determine the actual working condition of the equipment based on the equipment operating parameters, and match the carbon emission factor of the construction condition in combination with the construction procedure, construction equipment and actual working condition of the equipment; take the same transformation task unit as the associated object, merge and associate the matching results of the static carbon emission factor of the material and the carbon emission factor of the construction condition to determine the carbon emission of the material and the carbon emission of the construction. S5. Summarize the carbon emissions of materials and construction for each renovation task unit to obtain the carbon emission calculation results for the building decoration and renovation process.

[0006] Preferably, in step S1, determining the component modification status includes: Establish the correspondence between components before and after the modification based on component identification; for components for which the correspondence cannot be established based on component identification, establish the correspondence based on component category, spatial location and geometric parameters; Components that only exist in the pre-renovation BIM model are identified as demolished, and components that only exist in the post-renovation BIM model are identified as newly added. For the corresponding components that exist both before and after the renovation, the components whose parameters and material information have not changed within the corresponding scope of the project are determined to be retained. When changes in component parameters or material information cover all corresponding quantities of work, the corresponding component is identified as a replacement component. When changes in component parameters or material information only cover a portion of the corresponding engineering quantity, the corresponding component is identified as a partial modification state, and the part that has changed is identified as the scope of the partial modification. For components whose geometric range changes before and after the modification, the parts that were unique before the modification are identified as the parts to be demolished, and the parts that were unique after the modification are identified as the parts to be added.

[0007] Preferably, in step S1, determining the state engineering quantity includes: For components that exist only in the pre-renovation BIM model, all their quantities are defined as demolition quantities; for components that exist only in the post-renovation BIM model, all their quantities are defined as new quantities. For components that have a corresponding relationship before and after the renovation, their geometric ranges are superimposed to determine the spatial overlap area, the area unique before the renovation, and the area unique after the renovation. The quantities of work in the overlapping spatial areas where the component parameters and material information have not changed are defined as the quantities of work in the retained state; the quantities of work in the unique areas before the renovation are defined as the quantities of work in the demolition state; and the quantities of work in the unique areas after the renovation are defined as the quantities of work in the newly added state. When the changes in component parameters or material information in the spatially overlapping area cover the entire spatially overlapping area, the engineering quantity of the spatially overlapping area is determined as the engineering quantity of the replacement state. When the changes only cover a portion of the overlapping spatial area, the engineering quantity of the changed portion is determined as the engineering quantity of the partial renovation state.

[0008] Preferably, in step S2, establishing a graded carbon emission factor database includes: Establish a material factor index and a construction condition factor index. The material factor index is associated with the static carbon emission factor of the material according to the material category, material specification and unit of measurement. The construction condition factor index is associated with the carbon emission factor of the construction condition according to the construction procedure, equipment type, energy type and equipment condition.

[0009] Preferably, in step S3, determining the carbon emission accounting boundary for each transformation task unit includes: For the retained state, the existing material usage of the original component is excluded from the material change, and the material change, construction procedures and construction equipment corresponding to the materials consumed in this construction associated with the retained component are included in the carbon emission calculation; For projects in the demolition phase, the demolition construction procedures and equipment shall be included in the calculation of the demolition work volume according to the demolition phase. For newly added statuses, the quantities of new materials, installation procedures, and construction equipment shall be included in the calculation based on the quantities of the newly added status. For replacement or partial renovation, the demolished and newly added parts are determined separately, and the construction procedures and equipment corresponding to the demolished part and the material changes, construction procedures and equipment corresponding to the newly added part are included in the carbon emission calculation.

[0010] Preferably, in step S4, determining the actual operating conditions of the equipment based on the equipment operating parameters includes: The equipment operating parameters include operating power, rated power, operating time, and energy consumption. For construction equipment in operation, the equipment load rate is determined based on the ratio of operating power to rated power. Set a first load threshold and a second load threshold greater than the first load threshold, and define the operating states of the equipment load rate as low load condition, normal load condition and high load condition respectively when the load rate is less than the first load threshold, not less than the first load threshold and less than the second load threshold, and not less than the second load threshold.

[0011] Preferably, in step S4, the fusion association includes: Set a task identifier for each renovation task unit, and use the task identifier as a common association field to establish a material-side matching relationship with material information, material change amount and matched material static carbon emission factor, and establish a construction-side matching relationship with construction procedure, construction equipment, actual equipment working condition and matched construction working condition carbon emission factor, and associate the material-side matching relationship and construction-side matching relationship with the same renovation task unit. The carbon emissions of the material are determined based on the material change and the corresponding static carbon emission factor of the material, and the carbon emissions of the construction are determined based on the energy consumption in the equipment operating parameters and the corresponding carbon emission factor of the construction conditions.

[0012] Preferably, in step S4, matching the carbon emission factors of the construction conditions includes: The operation process of the construction equipment is divided into continuous working condition periods according to the collection time sequence of the equipment operating parameters. When the equipment load rate moves from the load range corresponding to one working condition to the load range corresponding to another working condition, the current working condition period ends and the next working condition period is established. The carbon emission factor for each construction condition is matched according to the actual operating conditions of the equipment for each working period. The carbon emission amount for construction is determined based on the energy consumption and the corresponding carbon emission factor for each working period. The carbon emission amounts for construction in each working period are then summed to obtain the carbon emission amount for the construction equipment.

[0013] Preferably, in step S5, the summary includes: The carbon emissions of materials and construction corresponding to the same renovation task unit are combined to obtain the carbon emissions of the task unit. Based on the component identification and construction procedures associated with each renovation task unit, the carbon emissions at the component level and the carbon emissions at the procedure level are summarized separately. Finally, the carbon emissions of each renovation task unit are summarized to obtain the carbon emission calculation results of the building decoration and renovation project.

[0014] A carbon emission measurement system for building decoration and renovation processes includes: The BIM processing module is used to construct the pre-renovation BIM model and the post-renovation BIM model. Based on the component correspondence, component parameter differences and changes in engineering quantity, it determines the component renovation status and status engineering quantity, forms renovation task units with associated material information, construction procedures and construction equipment, and obtains the operating parameters of construction equipment. The factor library management module is used to establish a graded carbon emission factor library, which includes static carbon emission factors of materials and carbon emission factors of construction conditions classified by construction process, equipment type, energy type and equipment operating condition. The accounting boundary determination module is used to determine the material changes, construction procedures and construction equipment included in the calculation of each modification task unit based on the component modification status and the status engineering quantity. The fusion calculation module is used to match the static carbon emission factor of the material with the material change amount, determine the actual working condition of the equipment based on the operating parameters of the construction equipment and match the carbon emission factor of the construction condition, and fuse the matching results of the two types of factors with the transformation task unit as the associated object to determine the carbon emission of the material and the carbon emission of the construction. The summary module is used to summarize the carbon emissions of materials and construction of each renovation task unit, and obtain the carbon emission calculation results of the building decoration and renovation process.

[0015] Compared with the prior art, the beneficial effects of the present invention are as follows: This invention determines the modification status and quantity of components by comparing BIM models before and after the modification, and delineates the carbon emission accounting boundaries for each modification task unit accordingly. This solves the problem of accurately distinguishing the scope of existing component retention, demolition, addition, replacement, and partial modification, reducing duplicate inclusion of existing materials and omission of actual modification parts. By establishing a hierarchical factor library of static carbon emission factors for materials and carbon emission factors for construction conditions, and matching factors with the actual operating conditions of construction equipment, this invention solves the problem that fixed-condition calculations cannot reflect actual changes in equipment operation. By linking the calculation results of the material side and the construction side of the modification task unit, it achieves unified aggregation and source traceability of carbon emissions, improving the correspondence between carbon emission calculations during the renovation process and actual renovation activities. Attached Figure Description

[0016] Figure 1 This is a flowchart of the method of the present invention; Figure 2 This is a system framework diagram of the present invention. Detailed Implementation

[0017] The following description is intended to disclose the invention and enable those skilled in the art to implement it. The preferred embodiments described below are merely examples, and other obvious variations will occur to those skilled in the art.

[0018] Reference Figure 1As shown, the carbon emission measurement method for building decoration and renovation processes includes: S1. Based on the original building information and renovation design information of the building decoration and renovation project, construct the pre-renovation BIM model and the post-renovation BIM model, and associate the component identification, component parameters, material information, construction procedures and construction equipment; determine the component renovation status and status engineering quantity according to the correspondence between the components before and after the renovation, the differences in component parameters and the changes in engineering quantity, form a renovation task unit, and obtain the equipment operation parameters of the construction equipment. In step S1, determining the component modification status includes: Establish the correspondence between components before and after the modification based on component identification; for components for which the correspondence cannot be established based on component identification, establish the correspondence based on component category, spatial location and geometric parameters; Components that only exist in the pre-renovation BIM model are identified as demolished, and components that only exist in the post-renovation BIM model are identified as newly added. For the corresponding components that exist both before and after the renovation, the components whose parameters and material information have not changed within the corresponding scope of the project are determined to be retained. When changes in component parameters or material information cover all corresponding quantities of work, the corresponding component is identified as a replacement component. When changes in component parameters or material information only cover a portion of the corresponding engineering quantity, the corresponding component is identified as a partial modification state, and the part that has changed is identified as the scope of the partial modification. For components whose geometric range changes before and after the modification, the parts that were unique before the modification are identified as the parts to be demolished, and the parts that were unique after the modification are identified as the parts to be added.

[0019] Furthermore, original building information can be obtained from existing building BIM models, original building as-built drawings, and on-site re-measurement data; renovation design information can be obtained from decoration and renovation construction drawings, material lists, and construction organization data. Component parameters should at least include dimensional parameters describing the spatial range and quantity of the component, and material information should at least include material category and material specifications.

[0020] When matching components, direct matching is first performed using component identifiers. If component identifiers cannot be directly matched due to remodeling, renumbering, or component splitting during the renovation design phase, candidate components with the same category as those before the renovation are selected from the renovated BIM model, and a correspondence is established based on the overlap of the spatial location and geometric extent of the candidate components.

[0021] When a pre-modification component has spatial overlap with multiple post-modification components, the overlapping areas between each post-modification component and the pre-modification component are retained, establishing a one-to-many correspondence. When multiple pre-modification components have spatial overlap with a single post-modification component, the overlapping areas between each pre-modification component and the post-modification component are retained, establishing a many-to-one correspondence. Only when multiple candidate components correspond to the same spatial range and a correspondence conflict occurs, the corresponding component is determined based on the degree of spatial overlap.

[0022] After completing the component mapping, the component parameters and material information within the corresponding range are compared. If both parameters and material information remain unchanged, the range will be retained in this renovation. If the component parameters or materials of all corresponding ranges change, replacement is performed. If only part of the range changes, partial renovation is performed. For cases where the component's geometric boundary expands or shrinks, the demolished and newly added parts are determined by superimposing the geometric ranges before and after the renovation.

[0023] For example, before the renovation, the quantity of a gypsum board partition wall was 100m². After the renovation, the spatial location, component parameters, and materials of 60m² remained unchanged, the spatial location of 20m² remained unchanged but the finishing material was changed, and the remaining 20m² did not exist in the BIM model after the renovation. Then, the corresponding components include the 60m² retained part, the 20m² partially renovated part, and the 20m² demolished part, where the quantity of the retained part is 60m², the quantity of the partially renovated part is 20m², and the quantity of the demolished part is 20m².

[0024] In step S1, the determination of the state engineering quantity includes: For components that exist only in the pre-renovation BIM model, all their quantities are defined as demolition quantities; for components that exist only in the post-renovation BIM model, all their quantities are defined as new quantities. For components that have a corresponding relationship before and after the renovation, their geometric ranges are superimposed to determine the spatial overlap area, the area unique before the renovation, and the area unique after the renovation. The quantities of work in the overlapping spatial areas where the component parameters and material information have not changed are defined as the quantities of work in the retained state; the quantities of work in the unique areas before the renovation are defined as the quantities of work in the demolition state; and the quantities of work in the unique areas after the renovation are defined as the quantities of work in the newly added state. When the changes in component parameters or material information in the spatially overlapping area cover the entire spatially overlapping area, the engineering quantity of the spatially overlapping area is determined as the engineering quantity of the replacement state. When the changes only cover a portion of the overlapping spatial area, the engineering quantity of the changed portion is determined as the engineering quantity of the partial renovation state.

[0025] Furthermore, the geometric boundaries of the corresponding components before and after the modification are superimposed, and the area covered by both forms a spatial overlap area. The area belonging only to the component before the modification forms a unique area before the modification, and the area belonging only to the component after the modification forms a unique area after the modification. The engineering quantities corresponding to the above areas are obtained according to the engineering quantity measurement method of the corresponding components.

[0026] For surface-shaped decorative components such as walls, ceilings, and floors, area can be used as the quantity of work in a state; for linear decorative components, length can be used; for components with solid volume, volume or mass can be used; for discrete components such as lighting fixtures, quantity can be used. The same measurement standard should be used for similar components before and after the renovation.

[0027] Taking the aforementioned 100m² gypsum board partition wall as an example, after geometric superposition, an 80m² overlapping area and a 20m² unique area before renovation are obtained. Among them, the material and component parameters of 60m² in the overlapping area remain unchanged, while the material of 20m² changes. Therefore, the engineering quantity in the retained state is determined to be 60m², the engineering quantity in the partial renovation state is 20m², and the engineering quantity in the demolition state is 20m².

[0028] After the quantity of work completed is determined, modification task units are formed based on the different modification activities that actually occur on the component. Each modification task unit initially records the corresponding task identifier, component identifier, component modification status, quantity of work completed, material information, construction procedures, and construction equipment. After determining the material change in step S3, the corresponding material change is supplemented and associated with the modification task unit. When different modification activities occur on the same component, multiple modification task units can be formed, so that subsequent material carbon emissions and construction carbon emissions can be respectively mapped to the actual modification scope.

[0029] S2. Establish a graded carbon emission factor library, including static carbon emission factors of materials and construction condition carbon emission factors graded according to construction procedures, equipment types, energy types and equipment operating conditions. In step S2, establishing a graded carbon emission factor database includes: Establish a material factor index and a construction condition factor index. The material factor index is associated with the static carbon emission factor of the material according to the material category, material specification and unit of measurement. The construction condition factor index is associated with the carbon emission factor of the construction condition according to the construction procedure, equipment type, energy type and equipment condition.

[0030] Furthermore, the material factor index records at least the material category, material specifications, unit of measurement, and corresponding static carbon emission factor. For example, gypsum board can be further classified into ordinary gypsum board, moisture-proof gypsum board, and thickness specifications, while light steel keel can be classified according to specifications and unit mass.

[0031] When the unit of measurement for material quantities in the BIM model differs from the unit of measurement for the static carbon emission factor of materials, a unified conversion must be performed before calculation. For example, if the BIM model records the quantity of gypsum board work in terms of area, while the static carbon emission factor of materials is expressed in terms of carbon emission per unit mass, the area quantity of work should be converted into material mass based on the unit area mass of the corresponding specification of gypsum board.

[0032] The construction condition factor index is established step by step according to the actual construction activities. For example, for wall panel cutting construction, index items such as "cutting process - electric cutting machine - electricity - low load condition", "cutting process - electric cutting machine - electricity - normal load condition" and "cutting process - electric cutting machine - electricity - high load condition" can be established, and the corresponding construction condition carbon emission factors can be associated with them respectively.

[0033] The static carbon emission factor of materials is matched according to the corresponding material data after the material category and specifications are determined; the carbon emission factor of construction conditions is further affected by the actual operating conditions of the on-site construction equipment, thus forming a hierarchical management structure of static material factors and dynamic construction condition factors applicable to the building decoration and renovation process.

[0034] Furthermore, the material factor index and construction condition factor index also record the factor value, unit of measurement, data source, applicable region, applicable time and data version respectively; the same building decoration and renovation project uses the material static carbon emission factor with consistent life cycle boundary and measurement caliber to calculate material carbon emissions.

[0035] In this embodiment, the life cycle boundary of the material static carbon emission factor and the accounting boundary of construction carbon emissions are recorded separately, and the same division principle is maintained within the same project. For carbon emission stages already included in the material static carbon emission factor, the same emission items are not counted again on the construction side; in this embodiment, the accounting boundary of the material static carbon emission factor does not repeatedly include carbon emissions generated by on-site construction equipment energy consumption calculated separately by this method.

[0036] The construction condition carbon emission factor is a unit energy consumption carbon emission factor that establishes an index relationship with construction procedures, equipment types, energy types, and equipment operating conditions. The construction condition carbon emission factor can be derived from a pre-selected carbon emission database for the project, equipment test data with clearly defined units of measurement and applicable operating conditions, or operating condition calibration data formed from historical construction data of the project.

[0037] In one specific implementation, the carbon emission factor of the construction condition that matches the construction procedure, equipment type, energy type, and equipment operating condition in the carbon emission database designated by the project is preferred. When there is no carbon emission factor of the construction condition corresponding to the equipment operating condition in the carbon emission database, test data of the same type of equipment operating condition confirmed by the project or historical construction condition calibration data are used. When there is still no data on differences in equipment operating conditions, the basic carbon emission factor of the corresponding energy type is used as the carbon emission factor of the construction condition corresponding to the low load condition, normal load condition, and high load condition.

[0038] During the calculation period for the same project, the data source, data version, and selection order of the carbon emission factors for construction conditions should remain unchanged. The carbon emission factors for construction conditions corresponding to the same energy type under different equipment operating conditions may be the same or different, and the factor value matching the corresponding equipment operating condition in the data source used shall prevail.

[0039] In this embodiment, the carbon emission accounting scope of the building decoration and renovation process includes the carbon emissions of materials corresponding to the newly added or replaced materials in this renovation, as well as the construction carbon emissions corresponding to the energy consumption of construction equipment during on-site demolition, processing, installation and fixing; existing materials in the original building that have not changed in this renovation are not included in the carbon emission accounting again, and the carbon emissions during the operation phase after the building is delivered are not within the calculation scope of this embodiment.

[0040] S3. Determine the carbon emission accounting boundary for each modification task unit based on the component modification status and the state engineering quantity, and limit the material changes, construction procedures and construction equipment included in the calculation. In step S3, determining the carbon emission accounting boundary for each transformation task unit includes: For the retained state, the existing material usage of the original component is excluded from the material change, and the material change, construction procedures and construction equipment corresponding to the materials consumed in this construction associated with the retained component are included in the carbon emission calculation; For projects in the demolition phase, the demolition construction procedures and equipment shall be included in the calculation of the demolition work volume according to the demolition phase. For newly added statuses, the quantities of new materials, installation procedures, and construction equipment shall be included in the calculation based on the quantities of the newly added status. For replacement or partial renovation, the demolished and newly added parts are determined separately, and the construction procedures and equipment corresponding to the demolished part and the material changes, construction procedures and equipment corresponding to the newly added part are included in the carbon emission calculation.

[0041] Furthermore, the carbon emission accounting boundary is used to distinguish between materials already present in the original building and the actual material inputs and construction activities involved in this renovation.

[0042] The material change is determined based on the actual material consumption or theoretical material usage at the project stage. When material requisition and return records corresponding to the modification task unit are available, the net material consumption after deducting the returned material consumption is determined as the corresponding material change, and the material change is associated with the corresponding task identifier.

[0043] When no actual material issuance and return records have been established, the theoretical material usage is determined based on the state engineering quantity and unit engineering quantity material usage corresponding to the renovation task unit. The unit engineering quantity material usage can be obtained from the renovation design material list, BIM component material properties, or project material usage list; when the BIM model can directly extract the material mass, volume, or quantity within the corresponding state engineering quantity range, the corresponding material usage is directly adopted.

[0044] When the theoretical material usage needs to be factored in construction losses, the theoretical material usage is adjusted according to the material loss rate determined in the project material quota or construction plan to obtain the corresponding material change. Subsequently, after obtaining the actual material issuance and return records, the material change of the corresponding renovation task unit is updated using the actual net material consumption.

[0045] For retained components, the original materials already existed before the start of this renovation project, so they will not be recalculated as materials for this project. If the retained components are repaired or painted during this project, only the materials newly consumed and the construction equipment actually used will be recorded.

[0046] For dismantled components, the original materials will not be recalculated as new materials. Instead, the actual construction procedures such as dismantling, cutting, and crushing, as well as the construction equipment, will be included in the construction-side accounting.

[0047] For newly added components, the actual material change is obtained based on the new state engineering quantity and corresponding material specifications, and the construction equipment corresponding to material processing, installation, fixing and other processes is included in the calculation.

[0048] For components that are replaced or partially modified, the removal of raw materials and the introduction of new materials are handled separately. For replacement, the quantities of work in the replacement state are divided into the quantities for the removal of the original components and the quantities for the addition of new components or materials. The quantities for the removal of the original components are used to determine the corresponding demolition procedures and equipment, while the quantities for the addition of new components or materials are used to determine the material changes and the corresponding installation procedures and equipment.

[0049] For partial renovations, only the quantities of work in the partial renovation phase are used as the basis for the quantities of work on the corresponding demolition and new construction phases. When a partial renovation only adds materials and there is no demolition of raw materials, only the new construction phase accounting object is established. When a partial renovation only involves demolition and there are no new materials, only the demolition phase accounting object is established.

[0050] For example, when replacing the finishing material on a 20m² wall, the carbon emissions are calculated only for the 20m² area, including the removal of the old finishing material and the installation of the new finishing material. The remaining unchanged work on the same wall is not included in the carbon emission calculation.

[0051] This allows the carbon emission accounting objects to correspond to the actual scope of the renovation project that has been altered.

[0052] S4. Match the static carbon emission factor of the material with the material change based on the material information, determine the actual working condition of the equipment based on the equipment operating parameters, and match the carbon emission factor of the construction condition in combination with the construction procedure, construction equipment and actual working condition of the equipment; take the same transformation task unit as the associated object, merge and associate the matching results of the static carbon emission factor of the material and the carbon emission factor of the construction condition to determine the carbon emission of the material and the carbon emission of the construction. Furthermore, by querying the material factor index based on the material category, specifications, and unit of measurement within the transformation task unit, the corresponding static carbon emission factor for each material is obtained. The carbon emission of a material is determined based on the actual material change and the corresponding static carbon emission factor; when a task unit contains multiple materials, the emissions for each material are calculated separately and then accumulated.

[0053] Specifically, the carbon emissions of the materials in the kth modification task unit are: In the formula, The carbon emissions of the materials in the kth modification task unit; Let i be the material change of the i-th material in the k-th modification task unit; Let be the static carbon emission factor of the i-th material; The quantity of material types included in the calculation for the kth modification task unit.

[0054] When the unit of measurement for material change is inconsistent with that for static carbon emission factor of material, the unit should be converted to the same measurement caliber according to the unit conversion relationship in step S2 before calculation.

[0055] In step S4, determining the actual operating conditions of the equipment based on the equipment operating parameters includes: The equipment operating parameters include operating power, rated power, operating time, and energy consumption. For construction equipment in operation, the equipment load rate is determined based on the ratio of operating power to rated power. Set a first load threshold and a second load threshold greater than the first load threshold, and define the operating states of the equipment load rate as low load condition, normal load condition and high load condition respectively when the load rate is less than the first load threshold, not less than the first load threshold and less than the second load threshold, and not less than the second load threshold.

[0056] Furthermore, the operating power and energy consumption can be obtained from the construction equipment controller, smart meter, construction distribution box metering device, or independent energy consumption acquisition terminal, and the rated power can be obtained from the equipment nameplate or equipment file.

[0057] Equipment load rate reflects the degree to which the actual operating power of construction equipment is utilized relative to its rated power. For example, if an electric cutting machine with a rated power of 2.0kW operates at 1.2kW at a certain sampling moment, then the equipment load rate is 0.60.

[0058] The first and second load thresholds can be set based on the trial operation data before the corresponding equipment is installed. Specifically, the load rate ranges of the equipment under light load, normal construction operation, and continuous high power operation can be collected respectively, and the two thresholds can be determined according to the boundaries of the load rate ranges corresponding to different operating states.

[0059] In one specific implementation, the first load threshold is 0.35 and the second load threshold is 0.75. When the equipment load rate is less than 0.35, it corresponds to a low load condition; when it is not less than 0.35 and less than 0.75, it corresponds to a normal load condition; and when it is not less than 0.75, it corresponds to a high load condition.

[0060] In step S4, the fusion association includes: Set a task identifier for each renovation task unit, and use the task identifier as a common association field to establish a material-side matching relationship with material information, material change amount and matched material static carbon emission factor, and establish a construction-side matching relationship with construction procedure, construction equipment, actual equipment working condition and matched construction working condition carbon emission factor, and associate the material-side matching relationship and construction-side matching relationship with the same renovation task unit. The carbon emissions of the material are determined based on the material change and the corresponding static carbon emission factor of the material, and the carbon emissions of the construction are determined based on the energy consumption in the equipment operating parameters and the corresponding carbon emission factor of the construction conditions.

[0061] Furthermore, task identifiers are used to establish a correspondence between two types of accounting data generated from the same renovation and alteration activity.

[0062] When the construction equipment starts to execute a modification task unit, the corresponding task identifier and task start time are recorded. When the modification task unit is completed, the task end time is recorded, and the equipment operation parameters collected between the task start time and the task end time are associated with the corresponding task identifier.

[0063] When the same construction equipment continuously executes different modification task units, the equipment operation parameters are divided according to the start and end times of each task unit; the equipment operation data between adjacent task units are respectively assigned to the task identifier within the corresponding time range to avoid the same energy consumption being repeatedly associated with multiple modification task units.

[0064] For example, if task T001 corresponds to a partial renovation of a 20m² wall, the material side records the material category, material specifications, material variation, and static carbon emission factor of the material corresponding to T001; the construction side records the demolition or installation procedure, construction equipment, actual equipment operating conditions, energy consumption, and carbon emission factor of the construction conditions corresponding to the same task identifier T001.

[0065] Both the material-side and construction-side calculation results retain the same task identifier and are ultimately grouped together into the carbon emission result corresponding to T001. Therefore, the fusion correlation in this invention does not directly synthesize two carbon emission factors with different measurement calibers into a new factor, but rather uses the same retrofit task unit as a common accounting object, establishing a data correlation between the matching results of static material factors and the matching results of dynamic construction condition factors.

[0066] When construction equipment uses electric energy, the energy consumption is based on the actual electricity consumption and matched with the carbon emission factor of the construction condition using the same energy metering caliber; when fuel-fired equipment is used, the actual fuel consumption is calculated using the carbon emission factor of the construction condition corresponding to the energy type.

[0067] In step S4, matching the carbon emission factors for the construction conditions includes: The operation process of the construction equipment is divided into continuous working condition periods according to the collection time sequence of the equipment operating parameters. When the equipment load rate moves from the load range corresponding to one working condition to the load range corresponding to another working condition, the current working condition period ends and the next working condition period is established. The carbon emission factor for each construction condition is matched according to the actual operating conditions of the equipment for each working period. The carbon emission amount for construction is determined based on the energy consumption and the corresponding carbon emission factor for each working period. The carbon emission amounts for construction in each working period are then summed to obtain the carbon emission amount for the construction equipment.

[0068] Furthermore, the operating power of the construction equipment is collected according to a preset sampling period; for construction equipment that can directly output the cumulative energy consumption, the cumulative energy consumption is collected simultaneously. In one specific implementation, the sampling period is 1 minute, and the equipment operating condition is determined according to the equipment load rate corresponding to each sampling time, and the sampling records that are continuously in the same load range are merged to form a continuous operating condition period.

[0069] When the equipment load rate enters another load range, the equipment operating condition is switched and confirmed. To reduce frequent operating condition switching caused by short-term fluctuations in the equipment load rate near the load threshold, when two consecutive sampling periods enter the new load range, it is confirmed that the actual operating condition of the equipment has changed, and the sampling time of the first entry into the new load range is taken as the end time of the previous continuous operating condition period and the start time of the next continuous operating condition period; when only one sampling period enters the new load range and the next sampling period returns to the original load range, the sampling period is still included in the original continuous operating condition period.

[0070] For construction equipment whose cumulative energy consumption can be directly obtained, the energy consumption corresponding to each continuous working period is determined based on the difference between the cumulative energy consumption at the end of the continuous working period and the cumulative energy consumption at the beginning.

[0071] For construction equipment that uses electric energy and cannot directly output the cumulative electricity consumption, the electricity consumption is determined based on the operating power collected during the continuous working period and the corresponding sampling duration. When the operating power is expressed in kW and the sampling duration is expressed in h, the product of the operating power and the corresponding sampling duration of each sampling period is accumulated to obtain the electricity consumption during the continuous working period.

[0072] For construction equipment using fuel oil, the cumulative fuel consumption corresponding to the start and end times of each continuous working period is obtained through a fuel metering device or equipment controller. The difference between the cumulative fuel consumption at the end time and the cumulative fuel consumption at the start time is taken as the fuel consumption for that continuous working period. When a fuel consumption record is used, the fuel consumption record includes fuel consumption and corresponding time information. The fuel consumption belonging to that continuous working period is determined based on the start and end times of each continuous working period, and the carbon emission factor of the construction working condition, which is consistent with the unit of measurement of the fuel consumption, is used for calculation.

[0073] Based on the actual operating conditions of the equipment corresponding to each continuous operating period, the carbon emission factors of the construction operating conditions are matched in the construction operating condition factor index according to the construction procedure, equipment type, energy type and equipment operating conditions.

[0074] Specifically, the carbon emissions from the construction of the kth renovation task unit are: In the formula, Let be the carbon emissions from the construction of the kth renovation task unit; The number of construction equipment included in the calculation for the kth renovation task unit; This represents the number of continuous operating time periods corresponding to the d-th construction equipment. Let d be the energy consumption of the d-th construction equipment during the j-th continuous operating period; The carbon emission factor of the construction condition matched for the d-th construction equipment in the j-th continuous operating period.

[0075] The carbon emissions of the same construction equipment are summed up for each continuous working period to obtain the carbon emissions of that construction equipment; then the carbon emissions of the construction equipment in the same renovation task unit are summed up to obtain the carbon emissions of the renovation task unit.

[0076] For example, if an electric cutting machine with a rated power of 2.0kW continuously performs a certain modification task for 80 minutes, the load rate is in the low load range for the first 15 minutes, in the normal load range for the middle 50 minutes, and in the high load range for the last 15 minutes, then three continuous working conditions are formed.

[0077] For the three working periods, the construction working condition factor index is queried by combining the cutting process, electric cutting machine, power energy and corresponding low load, normal load and high load working conditions. The construction carbon emissions are determined according to the actual energy consumption recorded in each period. Then the construction carbon emissions of each working period are added together.

[0078] Therefore, the actual load changes of the same construction equipment at different construction stages can be reflected in the construction carbon emission calculation, avoiding the need to use a fixed equipment operating condition for estimation throughout the entire construction process.

[0079] S5. Summarize the carbon emissions of materials and construction for each renovation task unit to obtain the carbon emission calculation results for the building decoration and renovation process.

[0080] In step S5, the summary includes: The carbon emissions of materials and construction corresponding to the same renovation task unit are combined to obtain the carbon emissions of the task unit. Based on the component identification and construction procedures associated with each renovation task unit, the carbon emissions at the component level and the carbon emissions at the procedure level are summarized separately. Finally, the carbon emissions of each renovation task unit are summarized to obtain the carbon emission calculation results of the building decoration and renovation project.

[0081] Furthermore, firstly, according to the task identifier, the carbon emissions of each material record and the carbon emissions of each construction equipment record in the same renovation task unit are summarized to obtain the carbon emissions of the task unit; then, according to the component identifier, the renovation task units belonging to the same component are summarized to obtain the carbon emissions of the component.

[0082] When summarizing at the process level, a corresponding construction process identifier is set for each material carbon emission record and construction carbon emission record. Construction carbon emissions generated by construction equipment are aggregated according to the construction process actually performed by the construction equipment; material carbon emissions are aggregated according to the construction process associated with the actual input of the corresponding material. In principle, the same material carbon emission record and the same construction carbon emission record belong to only one construction process and are not counted repeatedly in multiple construction processes.

[0083] After summarizing at the task unit, component, and process levels, the carbon emissions of all renovation task units are added together to obtain the total carbon emission calculation result for the building decoration and renovation project. The calculation results at the task unit, component, and process levels are output as different statistical dimensions and are not added together again.

[0084] Reference Figure 2 As shown, the carbon emission measurement system for building decoration and renovation processes includes: The BIM processing module is used to construct the pre-renovation BIM model and the post-renovation BIM model. Based on the component correspondence, component parameter differences and changes in engineering quantity, it determines the component renovation status and status engineering quantity, forms renovation task units with associated material information, construction procedures and construction equipment, and obtains the operating parameters of construction equipment. The factor library management module is used to establish a graded carbon emission factor library, which includes static carbon emission factors of materials and carbon emission factors of construction conditions classified by construction process, equipment type, energy type and equipment operating condition. The accounting boundary determination module is used to determine the material changes, construction procedures and construction equipment included in the calculation of each modification task unit based on the component modification status and the status engineering quantity. The fusion calculation module is used to match the static carbon emission factor of the material with the material change amount, determine the actual working condition of the equipment based on the operating parameters of the construction equipment and match the carbon emission factor of the construction condition, and fuse the matching results of the two types of factors with the transformation task unit as the associated object to determine the carbon emission of the material and the carbon emission of the construction. The summary module is used to summarize the carbon emissions of materials and construction of each renovation task unit, and obtain the carbon emission calculation results of the building decoration and renovation process.

[0085] Example: An office building is undergoing interior decoration and renovation, which includes adjusting partition walls, replacing partial ceilings, replacing floor finishes, and adding new partitions.

[0086] Taking wall W001 as an example, the project volume before the renovation was 100m². After comparing the BIM models before and after the renovation, 60m² kept the original spatial location and material information unchanged, 20m² kept the spatial location unchanged but the finishing material was changed, and the other 20m² was cancelled after the renovation.

[0087] Accordingly, 60m² is defined as the quantity of work to be retained, 20m² for material replacement is defined as the quantity of work to be partially renovated, and 20m² for cancellation is defined as the quantity of work to be demolished.

[0088] Task T001 is established for a 20m² partial renovation area. Based on the construction material records, the actual amount of new gypsum board, connecting components, and caulking materials added to T001 are determined, and the corresponding static carbon emission factor is matched for each material. At the same time, the construction equipment such as electric cutting machines and electric drills actually used in the removal of the old finish and the installation of the new finish are associated with T001.

[0089] During equipment operation, operating power, rated power, operating time, and actual electricity consumption are collected. Different continuous operating periods are defined based on equipment load rate, and each operating period is matched with a corresponding construction condition carbon emission factor. The calculation results from both the material and construction sides are correlated with T001, thereby obtaining the carbon emission amount for the task unit corresponding to this 20m² partial renovation activity.

[0090] For the additional 20m² demolition area, task T002 is established. The existing wall materials are not re-included in the material change calculation. Only the energy consumption of the construction equipment actually generated during this demolition is included in the construction side calculation.

[0091] The remaining ceilings, floors, and newly added partitions were treated in the same way, and the carbon emission calculation results for the entire building decoration and renovation project were finally obtained.

[0092] The foregoing has shown and described the basic principles, main features, and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The embodiments and descriptions in the specification are merely principles of the invention. Various changes and modifications can be made to the invention without departing from its spirit and scope, and all such changes and modifications fall within the scope of the claimed invention. The scope of protection claimed by the appended claims and their equivalents is defined.

Claims

1. A method for calculating carbon emissions during building decoration and renovation processes, characterized in that, include: S1. Based on the original building information and renovation design information of the building decoration and renovation project, construct the pre-renovation BIM model and the post-renovation BIM model, and associate the component identification, component parameters, material information, construction procedures and construction equipment; determine the component renovation status and status engineering quantity according to the correspondence between the components before and after the renovation, the differences in component parameters and the changes in engineering quantity, form a renovation task unit, and obtain the equipment operation parameters of the construction equipment. S2. Establish a graded carbon emission factor database, including static carbon emission factors of materials and construction condition carbon emission factors graded according to construction procedures, equipment types, energy types and equipment operating conditions. S3. Determine the carbon emission accounting boundary for each modification task unit based on the component modification status and the state engineering quantity, and limit the material changes, construction procedures and construction equipment included in the calculation. S4. Match the static carbon emission factor of the material with the material change based on the material information, determine the actual working condition of the equipment based on the equipment operating parameters, and match the carbon emission factor of the construction condition in combination with the construction procedure, construction equipment and actual working condition of the equipment; take the same transformation task unit as the associated object, merge and associate the matching results of the static carbon emission factor of the material and the carbon emission factor of the construction condition to determine the carbon emission of the material and the carbon emission of the construction. S5. Summarize the carbon emissions of materials and construction for each renovation task unit to obtain the carbon emission calculation results for the building decoration and renovation process.

2. The carbon emission calculation method for building decoration and renovation processes according to claim 1, characterized in that, In step S1, determining the component modification status includes: Establish the correspondence between components before and after the modification based on component identification; for components for which the correspondence cannot be established based on component identification, establish the correspondence based on component category, spatial location and geometric parameters; Components that only exist in the pre-renovation BIM model are identified as demolished, and components that only exist in the post-renovation BIM model are identified as newly added. For the corresponding components that exist both before and after the renovation, the components whose parameters and material information have not changed within the corresponding engineering scope are determined to be retained. When changes in component parameters or material information cover all corresponding quantities of work, the corresponding component is identified as a replacement component. When changes in component parameters or material information only cover a portion of the corresponding engineering quantity, the corresponding component is identified as a partial modification state, and the part that has changed is identified as the scope of the partial modification. For components whose geometric range changes before and after the modification, the parts that were unique before the modification are identified as the parts to be demolished, and the parts that were unique after the modification are identified as the parts to be added.

3. The carbon emission calculation method for building decoration and renovation processes according to claim 2, characterized in that, In step S1, the determination of the state engineering quantity includes: For components that exist only in the pre-renovation BIM model, all their quantities are defined as demolition quantities; for components that exist only in the post-renovation BIM model, all their quantities are defined as new quantities. For components that have a corresponding relationship before and after the renovation, their geometric ranges are superimposed to determine the spatial overlap area, the area unique before the renovation, and the area unique after the renovation. The quantities of work in the overlapping spatial areas where the component parameters and material information have not changed are defined as the quantities of work in the retained state; the quantities of work in the unique areas before the renovation are defined as the quantities of work in the demolition state; and the quantities of work in the unique areas after the renovation are defined as the quantities of work in the newly added state. When the changes in component parameters or material information in the spatially overlapping area cover the entire spatially overlapping area, the engineering quantity of the spatially overlapping area is determined as the engineering quantity of the replacement state. When the changes only cover a portion of the overlapping spatial area, the engineering quantity of the changed portion is determined as the engineering quantity of the partial renovation state.

4. The carbon emission calculation method for building decoration and renovation processes according to claim 1, characterized in that, In step S2, establishing a graded carbon emission factor database includes: Establish a material factor index and a construction condition factor index. The material factor index is associated with the static carbon emission factor of the material according to the material category, material specification and unit of measurement. The construction condition factor index is associated with the carbon emission factor of the construction condition according to the construction procedure, equipment type, energy type and equipment condition.

5. The carbon emission calculation method for building decoration and renovation processes according to claim 1, characterized in that, In step S3, determining the carbon emission accounting boundary for each transformation task unit includes: For the retained state, the existing material usage of the original component is excluded from the material change, and the material change, construction procedures and construction equipment corresponding to the materials consumed in this construction associated with the retained component are included in the carbon emission calculation; For projects in the demolition phase, the demolition construction procedures and equipment shall be included in the calculation of the demolition work volume according to the demolition phase. For newly added statuses, the quantities of new materials, installation procedures, and construction equipment shall be included in the calculation based on the quantities of the newly added status. For replacement or partial renovation, the demolished and newly added parts are determined separately. The construction procedures and equipment corresponding to the demolished part and the material changes, construction procedures and equipment corresponding to the newly added part are included in the carbon emission calculation.

6. The carbon emission calculation method for building decoration and renovation processes according to claim 1, characterized in that, In step S4, determining the actual operating conditions of the equipment based on the equipment operating parameters includes: The equipment operating parameters include operating power, rated power, operating time, and energy consumption. For construction equipment in operation, the equipment load rate is determined based on the ratio of operating power to rated power. Set a first load threshold and a second load threshold greater than the first load threshold, and define the operating states of the equipment load rate as low load condition, normal load condition and high load condition respectively when the load rate is less than the first load threshold, not less than the first load threshold and less than the second load threshold, and not less than the second load threshold.

7. The carbon emission calculation method for building decoration and renovation processes according to claim 1, characterized in that, In step S4, the fusion association includes: Set a task identifier for each renovation task unit, and use the task identifier as a common association field to establish a material-side matching relationship with material information, material change amount and matched material static carbon emission factor, and establish a construction-side matching relationship with construction procedure, construction equipment, actual equipment working condition and matched construction working condition carbon emission factor, and associate the material-side matching relationship and construction-side matching relationship with the same renovation task unit. The carbon emissions of the material are determined based on the material change and the corresponding static carbon emission factor of the material, and the carbon emissions of the construction are determined based on the energy consumption in the equipment operating parameters and the corresponding carbon emission factor of the construction conditions.

8. The carbon emission calculation method for building decoration and renovation processes according to claim 6, characterized in that, In step S4, matching the carbon emission factors for the construction conditions includes: The operation process of the construction equipment is divided into continuous working condition periods according to the collection time sequence of the equipment operating parameters. When the equipment load rate moves from the load range corresponding to one working condition to the load range corresponding to another working condition, the current working condition period ends and the next working condition period is established. The carbon emission factor for each construction condition is matched according to the actual operating conditions of the equipment for each working period. The carbon emission amount for construction is determined based on the energy consumption and the corresponding carbon emission factor for each working period. The carbon emission amounts for construction in each working period are then summed to obtain the carbon emission amount for the construction equipment.

9. The carbon emission calculation method for building decoration and renovation processes according to claim 1, characterized in that, In step S5, the summary includes: The carbon emissions of materials and construction corresponding to the same renovation task unit are combined to obtain the carbon emissions of the task unit. Based on the component identification and construction procedures associated with each renovation task unit, the carbon emissions at the component level and the carbon emissions at the procedure level are summarized separately. Finally, the carbon emissions of each renovation task unit are summarized to obtain the carbon emission calculation results of the building decoration and renovation project.

10. A carbon emission measurement system for building decoration and renovation processes, applied to the carbon emission measurement method for building decoration and renovation processes as described in any one of claims 1-9, characterized in that, include: The BIM processing module is used to construct the pre-renovation BIM model and the post-renovation BIM model. Based on the component correspondence, component parameter differences and changes in engineering quantity, it determines the component renovation status and status engineering quantity, forms renovation task units with associated material information, construction procedures and construction equipment, and obtains the operating parameters of construction equipment. The factor library management module is used to establish a graded carbon emission factor library, which includes static carbon emission factors of materials and carbon emission factors of construction conditions classified by construction process, equipment type, energy type and equipment operating condition. The accounting boundary determination module is used to determine the material changes, construction procedures and construction equipment included in the calculation of each modification task unit based on the component modification status and the status engineering quantity. The fusion calculation module is used to match the static carbon emission factor of the material with the material change amount, determine the actual working condition of the equipment based on the operating parameters of the construction equipment and match the carbon emission factor of the construction condition, and fuse the matching results of the two types of factors with the transformation task unit as the associated object to determine the carbon emission of the material and the carbon emission of the construction. The summary module is used to summarize the carbon emissions of materials and construction of each renovation task unit, and obtain the carbon emission calculation results of the building decoration and renovation process.