Information-based low-voltage construction progress dynamic management and control method and system
By dividing the building's low-voltage electrical construction into spatial construction units and establishing a low-voltage endpoint topology, and performing event matching and state frontier control, the problem of spatial location and endpoint identity mismatch of construction events was solved, enabling dynamic and accurate control of construction progress and improving construction efficiency and accuracy.
Patent Information
- Application Number
- CN202611349105.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-02
- Publication Date
- 2026-11-24
AI Technical Summary
In existing technologies, the spatial location or endpoint identity of construction events during low-voltage electrical construction on building floors is prone to mismatch, leading to the formation of incorrect progress units. Furthermore, correcting these errors requires recalculating all unrelated work surfaces, affecting the accuracy and efficiency of the construction progress.
An information-based dynamic management and control method for low-voltage electrical construction progress is adopted. By acquiring construction design data, spatial data, and planning data, spatial construction units are divided, low-voltage endpoint topology is established, and spatial boundaries and endpoint topology are matched during construction event collection. Only events that pass the match are written into the valid sequence, generating a construction state frontier. The state frontier is then propagated along the shared endpoint relationships and work surface adjacency identifiers. Affected units are locally recalculated, and a new version of the construction plan is generated.
It effectively avoids misalignment of construction events or incorrect entry of events into the wrong schedule, ensures the accuracy of construction status, reduces repeated verification of irrelevant work surfaces, and improves the accuracy and efficiency of construction progress.
Smart Images

Figure CN123159673A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the fields of building information system construction management and low-voltage engineering on-site control technology, and in particular to a method and system for dynamically correcting the progress of low-voltage construction and controlling the work surface by utilizing spatial construction units, low-voltage endpoint topology, on-site construction events and construction status frontier. Background Technology
[0002] Network, video surveillance, access control, intercom, information dissemination, and other low-voltage electronic systems in building floors are typically installed in sections along corridors, ceilings, pipe shafts, and equipment rooms. After completing pipeline laying, cable installation, endpoint splicing, equipment installation, and link testing on-site, construction personnel usually report construction events via mobile terminals, location marker reading devices, or testing equipment. Construction management personnel then update the task status according to the construction plan for each floor, room, pipe shaft, and equipment room. Because adjacent rooms, floors above and below, and the same pipe shaft may contain cables, conduits, and equipment ports with identical appearances, on-site location recording is easily affected by indoor positioning drift, inconsistent floor references, location marker reading deviations, and incorrect endpoint connections.
[0003] Existing online inspection solutions for low-voltage cabling can link construction status with spatial or spatiotemporal information, continuous data acquisition results, and logical topology to determine the compliance and abnormal risks of cabling construction. Existing digital construction management solutions can establish a network of process nodes, perform continuity and consistency verification based on construction timestamps, and trace and adjust thresholds for abnormal nodes. Other low-voltage construction management solutions utilize 3D environment modeling, cabling diagram scanning, and on-site projection to help construction personnel view cabling information. These solutions process on-site data from the perspectives of quality inspection, process management, or drawing display, but there is no unified admission criteria regarding whether construction events simultaneously belong to a designated spatial construction unit and a designated endpoint pair before entering the progress sequence. Based solely on spatial location, endpoint events from the same manhole or adjacent rooms may be classified into incorrect units; based solely on endpoint identifiers, it cannot be ruled out that construction personnel may have read the same type of endpoint on the wrong work surface.
[0004] Once an error event is written into the construction plan, subsequent processes may open work surfaces based on the incorrect completion status, and the problem may not be exposed until the cable testing or equipment commissioning phase. When correcting the error event, if all construction units are recalculated, unaffected work surfaces will repeatedly enter the pending verification state, and completed on-site confirmations will be repeatedly overwritten. Therefore, a dynamic progress control method for building low-voltage electrical construction objects is needed to simultaneously correct the spatial identity and endpoint topology identity of the construction event before it changes the progress status, and to restrict the state change to the actually affected work surfaces and their dependent units. Summary of the Invention
[0005] To address the problems in existing technologies where construction events can easily enter incorrect progress units due to mismatches in spatial location or endpoint identity, and where error correction leads to the recalculation of unrelated work surfaces, this invention provides an information-based dynamic management and control method and system for low-voltage electrical construction progress. This ensures that the spatial attribution of construction events, the attribution of low-voltage electrical lines, pre-state verification, work surface control, and plan version updates are transmitted along the same technical data link.
[0006] To achieve the above objectives, the present invention adopts the following technical solution:
[0007] In a first aspect, the present invention provides an information-based method for dynamic management and control of low-voltage electrical construction progress, comprising: acquiring low-voltage electrical construction design data, construction area spatial data, and construction plan data; dividing the construction area into multiple spatial construction units; and establishing a unit record for each spatial construction unit, including spatial boundaries, low-voltage electrical system identifiers, start endpoint identifiers, end endpoint identifiers, and a sequence of preceding construction states; connecting the start endpoint identifiers and end endpoint identifiers to form a low-voltage electrical endpoint topology based on the pipeline connection relationship and equipment installation relationship of the low-voltage electrical system, and associating the sequence of preceding construction states with the low-voltage electrical endpoint topology; collecting construction events from at least one of on-site construction terminals, point identifier reading devices, cable testing equipment, and debugging equipment, wherein the construction events include event type, event time, construction location, start endpoint identifier, end endpoint identifier, and test status; matching the construction location of the construction event with the spatial boundary, and matching the start endpoint identifier and end endpoint identifier of the construction event with the low-voltage electrical endpoint topology, wherein only when the spatial boundary matching is successful and the endpoint topology matching is successful... Only approved construction events are written into the valid event sequence of the corresponding spatial construction unit. Construction events that fail to pass both types of matching are marked as pending verification or blocked, and their advancement to the construction state frontier of the corresponding spatial construction unit is prohibited. The valid event sequence is verified according to the order of the preceding construction state sequence, generating verified, pending verification, or blocked states. The first state in each spatial construction unit that fails the preceding state verification is determined as the construction state frontier. The construction state frontier is propagated along the shared endpoint relationship and the spatial construction unit relationship with the work surface adjacency identifier to form an affected construction unit set. Work surface release command, work surface lock command, and construction task adjustment command are generated based on the affected construction unit set. After the work surface release command or work surface lock command is executed on site, the newly collected construction events are written into the valid event sequence. Only the affected construction unit set and its subsequent dependent construction units are re-verified for the construction state frontier and construction tasks. The verified states of unaffected construction units are retained, and a new construction plan version and status record are generated.
[0008] Furthermore, the pre-construction state sequence is composed of at least three of the following in sequence according to the construction plan: work preparation state, pipeline laying state, cable laying state, endpoint connection state, equipment installation state, and link testing state. The construction events in the effective event sequence are respectively bound to the states in the pre-construction state sequence, and the pass status output by the cable testing equipment or debugging equipment is used as the status verification result in the state that requires testing, so that endpoint connection or link testing events without testing basis cannot directly skip the pre-test state.
[0009] Furthermore, spatial boundary matching includes converting the coordinates of the on-site construction terminal, point marker, or cable testing equipment to a unified coordinate system for the construction area, determining whether the construction location is within the spatial boundary, and verifying the floor marker, room marker, or manhole marker; endpoint topology matching includes verifying whether the starting endpoint marker and the ending endpoint marker constitute an endpoint pair in the unit record, and verifying whether there is a pipeline connection path between the endpoint pairs that is consistent with the weak electronic system marker, so that spatial location and line identity together become valid conditions for the construction event.
[0010] Furthermore, when verifying the valid event sequence according to the order of the preceding construction state sequence, the valid events of the same spatial construction unit are arranged according to the event time; for repeated events of the same state and the same endpoint pair, they are selected according to the test state, event source and event time; when the event time is earlier than the completion time of the preceding state, the preceding event is missing or the event state is rolled back, the event is marked as a pending verification state and the construction state front is prohibited from crossing the corresponding state; when the test state is failed, the corresponding spatial construction unit is marked as a blocked state, so that late, repeated, missing and failed events have different processing states before entering the site control.
[0011] Furthermore, the shared endpoint relationships and working face adjacency identifiers form a directed front propagation graph. The endpoint edges of the directed front propagation graph are composed of the termination endpoint identifiers and the starting endpoint identifiers of adjacent spatial construction units, and the working face edges are composed of the adjacency relationships of spatial boundaries and the identifiers of the same construction channel. The construction state front is propagated to the target spatial construction unit only when both the endpoint edges and the working face edges pass the relationship verification and the previous construction state of the source spatial construction unit has been verified. The propagation stops when the isolation identifier of the target spatial construction unit is locked, so that the front does not spread along units with only similar names or spatial proximity relationships.
[0012] Furthermore, the work surface release instruction includes the spatial construction unit identifier, the permitted construction status, the result of the pre-construction status verification, and the construction plan version identifier. The work surface lock instruction includes the spatial construction unit identifier, the reason for locking, the endpoint or spatial location that needs to be re-collected, and the verification action. The on-site construction terminal opens the permitted construction status according to the work surface release instruction, and prohibits entry into the subsequent construction status and displays the verification action according to the work surface lock instruction, so that the status judgment generated by the server is converted into an open or prohibit action that can be executed by the on-site terminal.
[0013] Furthermore, when re-verifying only the affected construction unit set and its subsequent dependent construction units, spatial construction units that generate new construction events, have changed status verifications, or fail to execute control commands are treated as change units. These change units are then extended downstream along the working face adjacency relationship, shared endpoint relationship, and construction plan dependency relationship to form the affected construction unit set. Within the affected construction unit set, the construction status frontier and task time window are updated, and the valid event sequences, verified statuses, and planned time windows of unaffected construction units are directly inherited to the new construction plan version, ensuring that local corrections do not overwrite the existing verification results of unrelated working faces.
[0014] Furthermore, when the construction location matching passes but the endpoint topology matching fails, an endpoint verification instruction is generated; when the endpoint topology matching passes but the construction location matching fails, a spatial verification instruction is generated; when the cable testing equipment outputs a test failure status, a cable retest instruction is generated; after a new construction event formed by verification or retesting passes both spatial boundary matching and endpoint topology matching, the corresponding pending verification status or blocking status is removed and the construction status frontier is re-verified, so that abnormal events must pass through the original identity correction entry to resume progress.
[0015] Furthermore, during network outages, on-site construction terminals and cable testing equipment cache construction events according to local event sequence numbers. The cached construction events retain event time, construction location, endpoint identifier, and test status. After network recovery, the server performs continuity and duplicate event checks according to event sequence number and event time. The cached construction events that pass the checks are incorporated into the valid event sequence. Before synchronization is completed, the construction status of the affected construction units remains unchanged, so that offline acquisition will not prematurely open subsequent work surfaces when the server lacks a complete event sequence.
[0016] Secondly, this invention provides an information-based dynamic management and control system for low-voltage electrical construction progress, including a construction data modeling module, an endpoint topology construction module, a field event acquisition module, a dual-anchor matching module, a state front determination module, a work surface control module, and a local recalculation and version management module. The construction data modeling module receives low-voltage electrical construction design data, construction area spatial data, and construction plan data, and generates spatial construction units and unit records. The endpoint topology construction module generates low-voltage electrical endpoint topology based on pipeline connection relationships and equipment installation relationships, and associates the preceding construction state sequence with the low-voltage electrical endpoint topology. The field event acquisition module receives construction events output by field construction terminals, point identification reading devices, cable testing equipment, or debugging equipment. The dual-anchor matching module performs spatial edge judgment on construction events. The system performs boundary matching and endpoint topology matching, and writes construction events that pass both matching into the valid event sequence. The state front determination module verifies the valid event sequence according to the preceding construction state sequence, and generates verified states, pending verification states, blocked states, and the construction state front. The working face control module generates working face release instructions, working face locking instructions, and construction task adjustment instructions based on the construction state front and the set of affected construction units, and sends them to the on-site construction terminal. The local recalculation and version management module receives new construction events and control instruction execution results, forms a set of affected construction units, re-verifies the construction state front and construction tasks for the set of affected construction units and their subsequent dependent construction units, retains the verified states of unaffected construction units, and generates a new construction plan version and status record.
[0017] Compared with existing technologies, this invention has the following advantages: Taking spatial construction units, low-voltage endpoint pairs, and on-site construction terminals as specific objects, under restricted conditions caused by indoor positioning drift, endpoint confusion, or test failures, spatial boundary matching and endpoint topology matching are used together as admission conditions for valid event sequences. Its direct effect is to prevent misaligned events or incorrect endpoint events from entering the valid event sequence; state changes manifest as the corresponding unit entering a pending verification state or a blocked state, or the construction state front stopping or moving along a controlled relationship; data changes manifest as partial updates to the valid event sequence, the set of affected construction units, and the construction plan version; signal changes manifest as field changes in work surface release commands, lock commands, verification commands, or retest commands; timing changes manifest as not opening subsequent construction states when the preceding state is not completed or the event sequence is not verified; its subsequent use is to provide executable open, prohibit, rescan, and retest actions to the on-site construction terminal. Therefore, events where the spatial location falls into an adjacent room, floor, or shaft but the endpoint does not belong to the designated line will not be considered valid progress, and events where the endpoint is correct but the construction location falls on the wrong work surface will not advance that work surface. Subsequent processes will not be opened ahead of schedule simply because of a time record.
[0018] This invention uses shared endpoint relationships and working face adjacency identifiers simultaneously for state front propagation. The front propagates only along edges with both line connections and field accessibility, and isolating the working face can cut off the propagation path. Therefore, an anomaly at a well endpoint or equipment port will not spread to the entire layer due to long-distance topological connections alone; the impact range of the front is limited to truly adjacent working faces with construction dependencies, ensuring that control commands are accurately delivered to the field terminals.
[0019] This invention performs partial recalculation only on the changed unit and its downstream dependent units after correcting construction events, and inherits the valid event sequences, verified statuses, and planned time windows of unaffected units to the new construction plan version. The new version generated by the management server retains the historical verification results of unchanged units, and records the frontier, task adjustments, and control execution results of affected units. On-site, only locked or pending verification work surfaces need to be re-collected, without having to reconfirm the completed work surfaces of the entire building.
[0020] This invention integrates spatial verification, endpoint verification, cable retesting, and network recovery synchronization back into the same dual-anchor verification entry point. Abnormal events cannot bypass identity verification to directly unlock; offline cached events are not advanced to the affected frontier until the sequence number and time continuity checks are completed. Therefore, traceable status transmission is maintained between on-site data acquisition, construction status, work surface control, and plan version. The effectiveness comes from the coordinated efforts of low-voltage construction objects, endpoint connection relationships, and on-site control actions, without relying on untested efficiency ratios or error data. Attached Figure Description
[0021] Figure 1 This is a flowchart illustrating the information-based dynamic control method for low-voltage electrical construction progress according to the present invention. Detailed Implementation
[0022] The technical solution of the present invention will be further described below with reference to the accompanying drawings. It should be understood that the described embodiments are for illustrating the present invention, and not for limiting the scope of protection of the present invention.
[0023] In a building low-voltage electrical construction scenario, the construction management server communicates with on-site construction terminals, point marker reading devices, cable testing equipment, and equipment debugging terminals. The construction management server stores spatial data for building floors, rooms, corridors, pipe shafts, and equipment rooms; it also stores design data for network, video surveillance, access control, intercom, information dissemination, and other low-voltage electronic systems; and it maintains the planned status and dependencies for each construction work area. On-site construction personnel use the on-site construction terminals to read point markers or receive output from testing equipment during pipeline laying, cable installation, endpoint splicing, equipment installation, or link testing. The construction management server updates the construction status based on these on-site actions and sends control results back to the on-site construction terminals, indicating whether continued construction is permitted or a work stoppage for verification is required.
[0024] Construction design data can come from construction drawings, equipment lists, cable inventories, and port tables, and must at least record the identification of low-voltage electronic systems, pipeline connection paths, equipment ports, start and end point identifications, and planned construction status. Spatial data records the project's unified coordinate system, floor reference, room boundaries, corridor boundaries, shaft boundaries, equipment room boundaries, and fixed reference points used for on-site positioning. Construction schedule data records the planned start and end times, preceding state sequences, construction task time windows, and dependencies for spatial construction units. All three types of data use the same project identifier and floor reference when imported to avoid the floor numbers in the design drawings, spatial data, and on-site terminal reports being independent.
[0025] The construction management server divides the construction area into multiple spatial construction units based on the actual construction work surface. In one example, a continuous laying area from a pipe shaft to an adjacent room in a corridor forms one spatial construction unit, a vertical laying section inside the pipe shaft forms another spatial construction unit, and the connecting area from the cabinet port to the equipment port in the equipment room forms a third spatial construction unit. Each spatial construction unit has a unit identifier that is not shared with other units, and stores spatial boundaries, floor identifiers, room or pipe shaft identifiers, low-voltage electronic system identifiers, start endpoint identifiers, end endpoint identifiers, and a sequence of previous construction states. Spatial boundaries can be represented by closed planar areas or by a combination of floor, room, pipe shaft, and corridor segment identifiers; when both representations exist simultaneously, the server simultaneously verifies the geometric boundaries and identifier fields.
[0026] Low-voltage endpoints are the actual start and end points in cable, conduit, or equipment connections. An endpoint record must include at least an endpoint identifier, a low-voltage system identifier, an endpoint type, the floor level, the spatial location, and the connected object. Endpoint types can be cabinet ports, patch panel ports, camera ports, access control ports, network access point ports, or equipment debugging ports. The construction management server uses endpoint records as topology vertices and conduit connections, cable connections, endpoint connections, and equipment installation relationships as topology edges, forming a low-voltage endpoint topology. For each spatial construction unit, the server extracts endpoint pairs consisting of a start endpoint identifier and an end endpoint identifier from the topology and saves the continuous connection path between endpoint pairs. If an endpoint pair spans multiple spatial construction units, it saves the corresponding local endpoint pairs and path segments for each unit according to the actual conduit segmentation relationship.
[0027] The system also maintains adjacency identifiers between spatial construction units. These identifiers are not simply based on distance or name similarity, but rather on accessibility relationships defined in the design documents, such as adjacent spatial boundaries, connectivity via the same construction passage, vertical connectivity via the same manhole, or general accessibility. The server stores the starting unit, target unit, adjacency direction, construction passage identifier, and isolation status for each adjacency relationship. Equipment rooms requiring isolation, enclosed manholes, or work surfaces with safety barriers are marked with a locked isolation identifier; two units with spatial proximity but no construction passage or endpoint connection are not linked by a controlled adjacency edge.
[0028] On-site construction events are generated by one or more of the following: on-site construction terminals, point identification reading devices, cable testing equipment, and equipment debugging terminals. Events generated by on-site construction terminals carry at least the on-site terminal identifier, event type, event time, on-site event sequence number, floor identifier, room or shaft identifier, and construction location. Events generated by point identification reading devices carry the endpoint identifier being read and the reading location. Events generated by cable testing equipment carry the testing equipment identifier, starting endpoint identifier, ending endpoint identifier, test time, and test status. Events generated by equipment debugging terminals carry the equipment endpoint, debugging object, and debugging status. The server assembles combinable records into a single construction event according to the same acquisition cycle, the same on-site terminal identifier, and the same endpoint pair. Single-end reads that have not yet acquired another endpoint record are only saved as pending pairing records and are not directly written into the valid event sequence.
[0029] The construction management server first transforms the coordinates of the on-site construction terminals, point marker reading devices, and cable testing equipment to the project's unified coordinate system. The transformation process uses floor references and fixed on-site reference points, preserving the original coordinates, transformed coordinates, floor markers, and coordinate sources. For on-site construction terminals without continuous coordinate output, the server uses the room or manhole marker selected by the terminal and the most recent valid positioning record to form the construction location, and writes the positioning source into the construction event. For cable testing equipment, the server uses the endpoint positions of the testing equipment and the endpoints of the tested cable to jointly form the construction location. If coordinate transformation fails, the floor reference is missing, or the location source is invalid, the server does not treat this event as a spatial boundary matching success event.
[0030] In spatial boundary matching, the server determines whether the construction location of a construction event is within the spatial boundary of the target spatial construction unit, and verifies the floor identifier, room identifier, pipe shaft identifier, and low-voltage electronic system identifier. The construction location of a cable laying event can be formed by the line sampling location or the locations of both ends of the line; when the line crosses the unit boundary, the server splits the event into spatial construction units with corresponding endpoint path segments according to the designed pipeline segments. Spatial boundary matching fails if only the floor is the same but the room, pipe shaft, or path segment is inconsistent. The spatial matching result saves three intermediate states: successful, unsuccessful, and pending supplementation, and associates them with the coordinate source and identifier verification results.
[0031] To allow spatial verification results to directly participate in the access judgment of construction events, in one example, passing is recorded as 1 and failing as 0, and the spatial boundary matching result is represented as follows:
[0032] ;
[0033] In the formula, Indicates a construction event With spatial construction unit Spatial matching results; The location of the construction work. For spatial construction units Spatial boundaries, and These are the floor identifiers for the event and the unit, respectively. and These are designated for room, pipe shaft, or corridor sections. and These are the weak electronic system identifiers for events and units, respectively. The value is 1 if the condition is met, and 0 otherwise. This way, even if the locations fall on the same floor, as long as the spatial identifier or system identifier is inconsistent, If the value is still 0, the server will not treat the event as a space access record for the target unit.
[0034] In endpoint topology matching, the server first verifies whether the start and end endpoint identifiers of the construction event constitute an endpoint pair stored in the target space construction unit. Then, it checks the existence of a pipeline connection path between the two ends along the low-voltage endpoint topology and verifies whether the low-voltage system identifier of the path matches the unit record. Endpoint topology matching fails if the endpoint identifier exists but the connection path is broken, the endpoint pair belongs to another low-voltage system, the endpoint type is incompatible with the event type, or the endpoint is in a locked / isolated state. The server writes the space boundary matching result and the endpoint topology matching result into the correction state of the same construction event. Only when both matchings pass does the construction event enter the valid event sequence of the corresponding space construction unit; events that pass only one matching enter the pending verification state.
[0035] Consistent spatial identity does not prove that the line identity is also correct. Therefore, the server continues to record endpoint topology matching results for the same construction event.
[0036] ;
[0037] In the formula, Indicates an event With unit Endpoint topology matching results; and These are the start and end endpoints of the event record, respectively. For unit The set of endpoint pairs that are saved. This represents a continuous topological path from the starting endpoint to the ending endpoint. and The weak electronic system identifiers for events and units are still represented separately; when the path is empty or the endpoint pair is not present... China Times, Setting it to 0, an empty path is denoted in the formula as... .
[0038] The server reads two matching values from the same event record simultaneously and writes the dual-anchor admission flag as follows:
[0039] ;
[0040] In the formula, Indicates an event Allow write to cell A valid sequence of events; only and When both are 1, Only 1. For example, if the endpoint identifier is read correctly but the actual location falls into an adjacent room, It can be 1 and The value is 0, so the event remains in the pending verification state.
[0041] The sequence of preceding construction states in the construction plan describes the changes in the on-site state of a spatial construction unit from work surface preparation to link availability. In one embodiment, the state sequence sequentially includes work surface preparation, pipeline laying, cable laying, endpoint connection, equipment installation, and link testing. For units that only include some of these processes, the server stores no fewer than three states with sequential relationships according to the actual design and construction plan. Each state is bound to an event type and preceding state that can prove its completion. The link testing state is also bound to the test pass status output by the cable testing equipment or equipment debugging terminal. Thus, reading the point identifier can only prove that the endpoint has been read and cannot replace evidence of endpoint connection or link testing completion.
[0042] The construction management server arranges construction events, calibrated by dual anchors, according to event time and on-site event sequence, and verifies each event item according to the preceding construction state sequence. After an event passes spatial and endpoint calibration, and its preceding state has been verified, the server marks the corresponding state as verified. If the spatial or endpoint identity of an event still needs verification, the preceding event is missing, or the event sequence cannot be confirmed, it is marked as pending verification. If the test state is failed, the endpoint path is broken, or the event clearly conflicts with the unit design, it is marked as blocked. For each spatial construction unit, the server finds the first state that fails the preceding state verification from the preceding construction state sequence and identifies that state and its corresponding task as the construction state frontier. When the frontier is in the workface preparation state, the workface remains locked; when the frontier is in the equipment installation state and the preceding endpoint connection has been verified, the workface can proceed to equipment installation.
[0043] To ensure that the judgment of "the first failed prerequisite state" falls on the state sequence number, the server can represent the construction state frontier as follows:
[0044] ;
[0045] In the formula, Representation unit The first state number that fails verification in the preceding construction state sequence. For the first The verification flag for each state is set as follows: 1 for verified, 0 for unverified or failed. When all states have been verified, the server marks the unit as completed and stops marking it as such. Progress on the follow-up status.
[0046] Once the construction state frontier is determined, the server determines whether it needs to be propagated along the controlled adjacency relationships. The starting point of propagation is the construction unit in the space where the frontier is located, and the propagation direction is determined by the endpoint connection direction and the construction plan dependency direction. The server only sends the frontier change to the target unit when the target unit and the source unit share an endpoint relationship, have a verified working face adjacency identifier, and the source unit's preceding construction state has been verified; propagation stops at the target unit if it has a locked isolation identifier, or if the endpoint edge or working face edge verification fails. The server thus forms a set of affected construction units, which includes at least the unit where the event or state change occurred, downstream units reachable along the controlled relationships, and task units whose construction plans explicitly depend on these units.
[0047] Controlled propagation does not spread along all adjacent cells, but instead uses shared endpoints, working face channels, source states, and target lock states as admission conditions simultaneously:
[0048] ;
[0049] In the formula, The frontier is represented by the source unit. To the target unit Access markers for dissemination For a set of shared endpoint relation edges, This is the set of adjacent edges of the working face that have passed the verification. The source cell's pre-state has been verified. The isolation flag is locked for the target cell; 0 indicates that it is not locked. All four conditions must be met simultaneously before the server writes the frontier changes to the target cell.
[0050] The server generates workface control results based on the construction status frontier and the set of affected construction units. Units whose frontier status has been verified and whose endpoint edges and workface edges have passed verification generate a workface release command. This command carries the unit identifier, the permitted construction status, the frontier status verification result, and the construction plan version identifier. Units whose spatial or endpoint calibration fails, tests fail, frontier status is missing, or propagation encounters an isolation marker generate a workface lock command. This command carries the unit identifier, the reason for locking, the endpoint or spatial location that needs to be re-collected, and the verification action. Construction task adjustment commands record the original planned time window, the new time window, the reason for adjustment, and the new construction plan version identifier for the affected tasks. Upon receiving a release command, the on-site construction terminal opens the permitted entry status; upon receiving a lock command, it prohibits entry into subsequent states and sends the terminal execution results back to the server.
[0051] After the control command is executed, new construction events generated by the on-site construction terminal or testing equipment undergo coordinate transformation, spatial boundary matching, and endpoint topology matching again. The server merges the new events with the original valid event sequences, redetermines the changed units and their downstream dependent units, and only verifies the construction state frontier, task time window, and control execution results within the affected construction unit set. The valid event sequences, verified states, and planned time windows of unaffected spatial construction units are directly inherited to the new construction plan version, and the inheritance source and local change content are saved in the version record. After the server sends the new version to the on-site terminal, the terminal verifies subsequent commands with the new version identifier to prevent the release commands of the old version from overwriting the locked state of the new version.
[0052] Normal Process: During construction of a corridor unit and an equipment room unit on a floor, construction personnel first read the starting endpoint identifier in the corridor unit and the ending endpoint identifier in the equipment room. The cable testing equipment then outputs the same endpoint pair and a test pass status. After the server transforms the two locations to the same floor coordinate system, it confirms that the line location is within the boundary of the corridor unit and the equipment room unit, and also confirms that the endpoint pair belongs to the same low-voltage electronic system and that there is a continuous path in the topology. After the work surface preparation, pipeline laying, cable laying, and endpoint connection events pass the pre-verification, the equipment installation becomes the construction state frontier of this unit, and the server opens the equipment installation status to the on-site construction terminals. After the equipment installation event and the link test pass event are written back, the frontier moves to the next planned state; if the adjacent unit shares endpoints with the equipment room and the work surface channel passes verification, the frontier propagates to the adjacent unit.
[0053] Anomaly Flow: Construction workers read an endpoint identifier with the same appearance in a room adjacent to the target room. The location reported by the field terminal falls within the boundary of the adjacent room, but the endpoint identifier belongs to the target unit. The server can identify that the endpoint topology match is successful but the spatial boundary match is unsuccessful. It saves the event in a pending verification state and does not write it into the valid event sequence of the target unit. The construction front of the target unit remains in its original state, and the subsequent equipment installation work surface is not released. Another anomaly is that the spatial location is located in the target manhole, but the termination endpoint output by the test equipment belongs to another weak electronic system. The server marks this event as blocked, generates an endpoint verification command, and stops the front propagation along the controlled adjacency relationship. When the test equipment outputs a failure status, the server generates a cable retest command and simultaneously locks the equipment installation tasks that depend on the test link.
[0054] Recovery Process: On-site construction personnel reread the manhole endpoints and equipment room endpoints according to the endpoint verification instructions. The cable testing equipment reconnects to the actual endpoints and outputs a test pass status. The server re-executes spatial boundary matching and endpoint topology matching. Only when both matchings pass and the endpoint paths are continuous is the new event written into the valid event sequence, and the pending verification or blocking status is lifted. The server treats the unit that caused the anomaly as the change unit, forming a new affected set along shared endpoints, work surface adjacencies, and construction plan dependencies, and updates the construction state frontier and task time window within this set; other floor units that have not experienced events or state changes continue to inherit the previously verified status. After receiving the new plan version, the on-site construction terminal reopens the unlocked construction state, and subsequent events still use the new version identifier for feedback.
[0055] Furthermore, in one embodiment, the pre-construction state sequence is configured in the order of work area preparation, pipeline laying, cable laying, endpoint connection, equipment installation, and link testing. On-site construction events are bound to construction states as work area confirmation events, pipeline laying events, cable laying events, endpoint connection events, equipment installation events, and testing events. The construction management server saves the allowed pre-construction states and completion conditions for each type of event. For link testing events, in addition to double-anchor matching success, the test pass status returned by the cable testing equipment and the test equipment endpoint pairs are also checked. If the testing equipment only returns detection data without a pass status, the event enters a pending verification state and cannot skip the link testing state. This process gives clear state meanings to on-site actions at different construction stages, and subsequent work area release uses the state verified by the pre-construction conditions rather than simply the number of data collections.
[0056] Furthermore, in one embodiment, spatial boundary matching is accomplished using three types of information: floor reference, fixed reference point, and spatial identifier. The server first selects the corresponding floor reference based on the coordinate source of the field terminal or testing equipment, then transforms the coordinates to the project's unified coordinate system. Subsequently, it checks whether the coordinates fall within the closed spatial boundary and verifies the floor, room, pipe shaft, and construction passage identifiers. Endpoint topology matching first searches for endpoint pairs from the endpoint records, then verifies path continuity along the connection path of the same low-voltage electronic system. When one endpoint is within the spatial boundary while the other is outside the design path, the server does not substitute one pass result for the dual-anchor result. Both spatial and endpoint results are written to the correction status, allowing anomaly commands to indicate the spatial or endpoint locations that need to be re-acquired.
[0057] Furthermore, in one embodiment, the server sorts valid events within the same spatial construction unit according to event time and on-site event sequence number, and identifies duplicate events for the same state, the same endpoint pair, and the same on-site terminal. The selection order of duplicate events consists of test state, event source, and event time: events with a test passed state take precedence over events without a test state; under the same test state, records with a clear event source and consecutive event sequence numbers are retained; if multiple records still exist, the record with the later time and no state rollback is used. If the event time is earlier than the completion time of the preceding state, the preceding event is missing, or the state rollbacks from verified, the server retains the record but marks it as pending verification, prohibiting the construction state front from crossing this state. In this way, delayed reporting and duplicate reporting will not change the established state order.
[0058] Furthermore, in one embodiment, the server establishes a directed frontier propagation graph with spatial construction units as nodes. The shared relationship between the terminating endpoint identifier and the starting endpoint identifier of another unit is written as endpoint edges, spatial boundary adjacency and the same construction passage identifier are written as working face edges, and construction plan dependencies are saved as task edges. The server propagates the frontier along the common direction of the endpoint edges and working face edges. Propagation does not occur if the preceding state of the source unit is not verified, and propagation stops when the isolation identifier of the target unit is locked. If an endpoint edge passes but a working face edge does not, the server only retains the endpoint relationship for verification and does not send the frontier to the target unit; if a working face edge passes but an endpoint edge does not, a releaseable downstream state is not formed. This directed propagation graph simultaneously incorporates line connectivity and site accessibility conditions into the influence range determination.
[0059] Furthermore, in one embodiment, the workface release command, workface locking command, and construction task adjustment command are all generated by the server according to the same construction plan version. The release command's fields include unit identifier, allowed entry status, pre-entry status verification result, endpoint pair identifier, and version identifier; the locking command's fields include unit identifier, locking reason, failed space or endpoint anchor point, required verification action, and version identifier; the task adjustment command's fields include task identifier, affected reason, original time window, adjusted time window, and downstream dependent units. After receiving the command, the on-site construction terminal writes the allowed status to its local construction list. When encountering a prohibited subsequent status, it stops submitting that status event and sends back the execution success, execution failure, or terminal disconnection result to the server. The server treats the execution failure result as a change event and triggers a local recalculation.
[0060] Furthermore, in one embodiment, local recalculation forms relational closures starting from change units. Change units are formed when new construction events enter the valid event sequence, when the results of double-anchor correction change, when the state changes from verified to pending verification or blocked, or when workface control commands fail to execute. The server first extends along endpoint edges and workface edges, then extends along construction plan dependencies to downstream tasks, stopping when it encounters unrelated connections, locked isolation boundaries, or verified units unaffected by dependencies. Within the affected set, the construction state frontier, task time windows, and release / lock states are redefined, while valid event sequences and verified states outside the set are copied to the new construction plan version. Both the old and new versions simultaneously save change units, extended edges, inherited units, and control execution results for field terminals to verify the source of commands.
[0061] During partial recalculation, the server needs to know which units are actually affected by the changes, rather than recalculating the entire building. The affected set can be written as:
[0062] ;
[0063] In the formula, This is the set of affected construction units that need to be re-verified. This refers to the set of change units that have experienced new events, changes in correction results, changes in status, or failures in control execution. For the set of edges with dependencies in the construction plan, This represents the set of cells reachable from the changed cell along endpoint edges, working face edges, and planning dependency edges. Used to preserve the changed unit itself. The server is in the collection. The construction status front, task time window, and release / lock status are redefined internally; the verified status and valid event sequence outside the set are carried over from the previous plan version.
[0064] Furthermore, in one embodiment, the server selects a recovery action based on the specific failure location of the dual-anchor calibration. When spatial boundary matching passes but endpoint topology matching fails, the server sends an endpoint verification command to the on-site construction terminal, instructing it to reread the starting endpoint, ending endpoint, or endpoint in the connection path; when endpoint topology matching passes but spatial boundary matching fails, the server sends a spatial verification command, instructing it to reselect a floor, room, manhole, or fixed reference point; when the cable testing equipment returns to a failure state, the server sends a cable retest command, requiring the re-establishment of a test connection on the same endpoint pair. New events generated by verification or retesting still require both types of matching to pass simultaneously before the server releases the pending verification or blocking state. If continuous verification still fails, the server retains the locked state and writes the reason for the anomaly into the status record, bypassing the dual-anchor calibration without manually inputting a completion mark.
[0065] Furthermore, in one embodiment, when the on-site construction terminal and cable testing equipment experience a network outage with the server, they write construction events into a local cache queue. The cache records retain the local event sequence number, event time under the device clock, construction location, floor or space identifier, start endpoint identifier, end endpoint identifier, event type, and test status, and save the previous local event sequence number for each record. After the network is restored, the server first checks whether the local event sequence numbers are consecutive, whether the event time has been rolled back, and whether the record duplicates existing events on the server, and then performs spatial boundary matching and endpoint topology matching. Cache records that fail continuity or duplication checks enter a pending verification state; only records that pass all checks are merged into the valid event sequence. Before cache synchronization is complete, the server keeps the construction status front edge of the affected construction unit unchanged to prevent unconfirmed events during the offline period from prematurely opening subsequent work surfaces.
[0066] In a common implementation, state sequence refinement, coordinate and endpoint dual-anchor correction, event timing verification, controlled propagation, terminal control, local recalculation, and anomaly recovery can all be applied to the same building low-voltage electrical construction scenario. On-site events first generate identity correction results for spatial construction units and endpoint pairs, then enter the preceding state sequence; the construction state leading edge generated by the state sequence limits the propagation range, and the propagation results form work surface release or lock commands; the command execution results and new events return to the identity correction entry point. The above processing is progressive, with the result of the previous processing becoming the entry condition for the next processing; they are not independent management modules coexisting.
[0067] In another common implementation, if both the spatial boundary and endpoint topology pass verification but the test state fails, the test failure directly creates a blocking state. This blocking state stops propagating along the controlled adjacency graph and triggers a cable retest. After the retest passes, the new event returns to the dual-anchor calibration and state sequence verification. Only after the affected set is locally recalculated will the field terminal open subsequent states according to the new version. This path connects the detection results, propagation restrictions, field actions, and recovery results to the same state chain, ensuring that the verified states of unaffected floors are not cleared due to local test failures.
[0068] In an embodiment of an information-based dynamic management and control system for low-voltage electrical construction progress, the construction data modeling module receives construction drawings, spatial data, and construction plan data, and establishes spatial construction units, unit records, construction status sequences, and plan dependencies; the endpoint topology construction module receives endpoint records, pipeline connection relationships, and equipment installation relationships, and generates low-voltage endpoint topology and endpoint pairs; the field event acquisition module receives construction events generated by field construction terminals, point identification reading devices, cable testing equipment, and equipment debugging terminals through wired or wireless communication interfaces, and retains the event time and local event sequence number; the dual-anchor matching module performs coordinate transformation, spatial boundary matching, endpoint topology matching, and dual result recording for the events.
[0069] The state front determination module receives valid event sequences and preceding construction state sequences, and forms verified states, pending verification states, blocked states, and construction state fronts according to event time, event number, and test status. The work face control module receives the construction state front and the set of affected construction units, generates work face release commands, work face lock commands, and construction task adjustment commands, and sends them to the on-site construction terminal. The local recalculation and version management module receives new construction events, verification or retest results, and control command execution results, and forms an affected set along shared endpoints, work face adjacencies, and plan dependencies. Within the set, it re-verifies and generates a new construction plan version, while inheriting verified states outside the set. Data is transmitted between modules through unit identifiers, endpoint pair identifiers, event numbers, and construction plan version identifiers, thus ensuring that the state output by the server can be reflected back to the specific work face on site.
[0070] The aforementioned modules can be implemented by software programs running on the construction management server, local programs in the field terminals, and communication components connected to the testing equipment. The field terminals can be mobile computing devices; the point identification reading devices can be barcode scanners, RFID, or contact readers capable of outputting endpoint identifiers and reading locations; the cable testing equipment can be testing instruments capable of outputting the tested endpoint pairs, test time, and test status; and the equipment debugging terminal can be debugging equipment capable of outputting device port information and debugging status. Different devices can access the same data interface as long as they can provide the event fields and status feedback required by this method; device brand, communication protocol, coordinate acquisition method, and database type are not necessary limitations.
[0071] Without altering the relationships of dual-anchor correction, construction state front, controlled propagation, and local recalculation, spatial data for the construction area can be provided by two-dimensional floor plans, engineering databases with spatial boundaries, or site identification tables; construction plan data can be provided by structured task tables or plan records in the construction management server. For site environments lacking continuous positioning, the server uses fixed reference points, floor markers, and room or shaft markers to establish the construction location; if the testing equipment cannot temporarily output endpoint pairs, the server saves single-end test records as pending pairing records, performing topology matching only after obtaining the other endpoint record. Any alternative input must retain four types of information—spatial identity, endpoint identity, event sequence, and test state—to rejoin the same state verification process.
[0072] The technical effect of this invention stems from the fact that the spatial identity and line identity of the same construction event jointly enter the valid event sequence: when the site location falls into an adjacent room, floor, or pipe shaft but the endpoint pair does not belong to the designated line, the event remains in a pending verification state; when the endpoint pair belongs to the designated line but the construction location is incorrect, the event also cannot advance to the target work surface; when the test fails, the blocking state restricts the front-end propagation and drives retesting. Valid events formed after verification or retesting propagate locally along the controlled adjacency relationship, and the verified state of unaffected units is retained in the local recalculation. Based on this, the on-site construction terminal only opens the construction state that has been pre-verified, and the construction management server forms a new construction plan version with change and inheritance relationships, completing the closed loop between building low-voltage construction events, work surface control, and dynamic progress data.
[0073] From the perspectives of specific objects, constrained states, direct effects, state changes, data changes, signal changes, temporal changes, and subsequent uses, the spatial construction unit and its endpoint pairs are the specific objects affected by this method. A single-anchor event entering an incorrect unit represents a constrained state. Dual-anchor matching directly alters the validity state of the construction event. The state frontier and plan version change temporally with the occurrence of valid events. Release or lock signals are sent to the on-site construction terminal, and the new state record continues to be used for verification in subsequent construction tasks. The aforementioned causal chain is formed by the spatial boundary, endpoint topology, and preceding state sequence, and its effectiveness is not based on unprovided efficiency ratios, accuracy rates, or experimental data.
Claims
1. A method for dynamic control of low-voltage electrical construction progress using information technology, characterized in that, include: Acquire low-voltage electrical construction design data, construction area spatial data, and construction plan data; divide the construction area into multiple spatial construction units; and establish a unit record for each spatial construction unit, including spatial boundaries, low-voltage electrical system identifiers, start endpoint identifiers, end endpoint identifiers, and a sequence of previous construction states. Based on the pipeline connection relationship and equipment installation relationship of the low-voltage electronic system, the starting endpoint identifier and the ending endpoint identifier are connected to form a low-voltage endpoint topology, and the preceding construction state sequence is associated with the low-voltage endpoint topology; Construction events are collected from at least one of the following: on-site construction terminal, point marker reading device, cable testing equipment, and debugging equipment. The construction events include event type, event time, construction location, start endpoint marker, end endpoint marker, and test status. The construction location of the construction event is matched with the spatial boundary, and the start endpoint identifier and end endpoint identifier of the construction event are matched with the weak current endpoint topology. Only construction events that pass the spatial boundary matching and the endpoint topology matching are written into the valid event sequence of the corresponding spatial construction unit. Construction events that fail to pass both the spatial boundary matching and the endpoint topology matching simultaneously are marked as pending verification or blocked, and are prohibited from advancing the construction state frontier of the corresponding spatial construction unit. The valid event sequence is verified according to the order of the aforementioned pre-construction state sequence, and verified state, pending verification state, or blocked state is generated. The first state in each spatial construction unit that fails the pre-construction state verification is determined as the construction state frontier. The construction state frontier is propagated along the shared endpoint relationship and the spatial construction unit relationship with the working face adjacency identifier to form an affected construction unit set, and a working face release command, a working face locking command and a construction task adjustment command are generated based on the affected construction unit set; After executing the working face release command or the working face lock command on site, the newly collected construction events are written into the valid event sequence. Only the affected construction unit set and its subsequent dependent construction units are re-verified for the construction status frontier and construction tasks. The verified status of unaffected construction units is retained, and a new construction plan version and status record are generated.
2. The information-based low-voltage electrical construction progress dynamic control method according to claim 1, characterized in that, The pre-construction status sequence is composed of at least three items in the following order according to the construction plan: work surface preparation status, pipeline laying status, cable laying status, endpoint connection status, equipment installation status, and link testing status. The construction events in the effective event sequence are respectively bound to the states in the preceding construction state sequence, and the pass status output by the cable testing equipment or debugging equipment is used as the state verification result in the state that needs to be tested.
3. The information-based low-voltage electrical construction progress dynamic control method according to claim 1, characterized in that, The spatial boundary matching includes: converting the coordinates of the on-site construction terminal, the coordinates of the point marker, or the coordinates of the cable testing equipment to a unified coordinate system of the construction area, determining whether the construction location is within the spatial boundary, and verifying the floor marker, room marker, or pipe shaft marker. The endpoint topology matching includes: verifying whether the starting endpoint identifier and the ending endpoint identifier constitute an endpoint pair in the unit record, and verifying whether there is a pipeline connection path between the endpoint pairs that is consistent with the weak electronic system identifier.
4. The information-based low-voltage electrical construction progress dynamic control method according to claim 1, characterized in that, The step of verifying the valid event sequence according to the order of the prior construction status sequence includes: arranging valid events of the same spatial construction unit according to the event time; For repeated events with the same state and the same endpoint pair, select according to test state, event source, and event time; When the event time is earlier than the completion time of the preceding state, the preceding event is missing, or the event state is rolled back, the event is marked as a state to be verified and the construction state front is prohibited from crossing the corresponding state. When the test status is failed, the corresponding spatial construction unit will be marked as blocked.
5. The information-based low-voltage electrical construction progress dynamic control method according to claim 1, characterized in that, The shared endpoint relationship and the working face adjacency identifier form a directed front propagation graph. The endpoint edges of the directed front propagation graph are composed of the termination endpoint identifier and the starting endpoint identifier of the adjacent spatial construction unit. The working face edge is composed of the adjacency relationship of the spatial boundary and the identifier of the same construction channel. The construction state front edge is propagated to the target space construction unit only when both the endpoint edge and the working surface edge pass the relationship verification and the previous construction state of the source space construction unit has been verified, and the propagation stops when the isolation identifier of the target space construction unit is locked.
6. The information-based low-voltage electrical construction progress dynamic control method according to claim 1, characterized in that, The work surface release command includes the spatial construction unit identifier, the allowed construction status, the pre-state verification result, and the construction plan version identifier. The work surface lock command includes the spatial construction unit identifier, the lock reason, the endpoint or spatial location that needs to be re-collected, and the verification action. The on-site construction terminal opens the allowed construction state according to the working face release command, and prohibits entry into the subsequent construction state according to the working face lock command and displays the verification action.
7. The information-based low-voltage electrical construction progress dynamic control method according to claim 1, characterized in that, The re-verification of only the affected construction unit set and its subsequent dependent construction units includes: taking the spatial construction units that generate new construction events, whose status verification changes, or whose control commands fail to be executed as change units, and extending them downstream along the working face adjacency relationship, shared endpoint relationship, and construction plan dependency relationship to form the affected construction unit set; Update the construction status frontier and task time window within the affected construction unit set, and directly inherit the valid event sequence, verified status, and planned time window of the unaffected construction units to the new construction plan version.
8. The method for dynamic control of information-based low-voltage electrical construction progress according to claim 1, characterized in that, When the construction location matches successfully but the endpoint topology matches unsuccessfully, an endpoint verification instruction is generated. When the endpoint topology match passes but the construction location match fails, a spatial verification instruction is generated. When the cable testing equipment outputs a test failure status, a cable retest command is generated; After a new construction event is generated through review or retesting, and both spatial boundary matching and endpoint topology matching are performed, the corresponding pending verification state or blocking state is released and the construction state frontier is re-verified.
9. The information-based low-voltage electrical construction progress dynamic control method according to claim 1, characterized in that, During network outages, on-site construction terminals and cable testing equipment cache construction events according to local event sequence numbers. The cached construction events retain event time, construction location, endpoint identifier, and test status. After the network is restored, the server performs continuity and duplicate event checks according to the event sequence number and the event time, merges the cached construction events that pass the checks into the valid event sequence, and keeps the construction status of the affected construction units unchanged before the synchronization is completed.
10. An information-based dynamic control system for low-voltage electrical construction progress, used to execute the information-based dynamic control method for low-voltage electrical construction progress as described in any one of claims 1 to 9, characterized in that, include: The construction data modeling module is used to receive low-voltage construction design data, construction area spatial data, and construction plan data, and generate multiple spatial construction units and their unit records. The endpoint topology construction module is used to generate a low-voltage endpoint topology based on pipeline connection relationships and equipment installation relationships, and associate the previous construction state sequence with the low-voltage endpoint topology. The on-site event acquisition module is used to receive construction events from at least one of the following: on-site construction terminal, point marker reading device, cable testing equipment, and debugging equipment; The dual-anchor matching module is used to perform spatial boundary matching and endpoint topology matching on the construction events, and write the construction events that pass the dual matching into the valid event sequence; The state front determination module is used to verify the valid event sequence according to the preceding construction state sequence, and generate verified state, unverified state, blocked state and construction state front. The working face control module is used to generate working face release commands, working face locking commands, and construction task adjustment commands based on the construction state front and the set of affected construction units, and send them to the on-site construction terminal. The local recalculation and version management module is used to receive new construction events and control command execution results, form the set of affected construction units, re-verify the construction status frontier and construction tasks of the set of affected construction units and their subsequent dependent construction units, retain the verified status of unaffected construction units, and generate a new construction plan version and status record.