An intelligent optimization method for power supply and demand based on RPA in extreme weather
By using an RPA protocol conversion engine and artificial intelligence models, the problems of data acquisition lag and slow response speed of power systems under extreme weather conditions have been solved. Real-time processing and dynamic optimization of multi-source heterogeneous data have been achieved, improving the response speed and control accuracy of power systems under extreme weather conditions.
Patent Information
- Application Number
- CN202510671392.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-05-23
- Publication Date
- 2026-11-24
AI Technical Summary
Existing technologies suffer from problems such as data collection lag, protocol interoperability issues, and slow response speed in responding to power supply and demand imbalances under extreme weather conditions, and cannot meet the requirements for rapid response at the minute level.
The RPA protocol conversion engine enables real-time acquisition and protocol conversion of multi-source heterogeneous data. Combined with an artificial intelligence load forecasting and power generation capacity degradation assessment model, a multi-strategy collaborative optimization and feedback iteration mechanism is constructed to generate dynamic adjustment instructions. Relying on the direct instruction connection channel between RPA and the industrial control system, millisecond-level protocol conversion and secure execution are achieved.
It significantly improves the efficiency and compatibility of power system data acquisition under extreme weather conditions, dynamically tracks load fluctuations and changes in power generation capacity, quickly generates optimization instructions, shortens the recovery time of supply and demand imbalance, reduces the risk of human error, and improves the success rate of control instruction execution.
Smart Images

Figure CN123159702A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of power system planning technology, and in particular to an intelligent optimization method for power supply and demand in extreme weather based on RPA. Background Technology
[0002] In addressing power supply and demand imbalances caused by extreme weather, existing technologies primarily employ a coordinated regulation strategy involving power generation, grid, load, and storage, optimizing resource allocation through planning models. Typical solutions include static load forecasting based on historical data, manually setting thresholds to trigger backup power switching, and manual dispatching commands relying on SCADA systems. While these methods can alleviate supply and demand imbalances to some extent, they have significant shortcomings in real-time data acquisition, protocol compatibility with heterogeneous multi-source equipment, and dynamic response speed, making it difficult to meet the minute-level rapid response requirements in sudden disaster scenarios such as typhoons and rainstorms.
[0003] Chinese patent application CN119944764A discloses a resource planning method and system for source-grid-load-storage regulation to meet supply demands during extreme weather. It generates a distribution network planning scheme for industrial parks by constructing a mixed-integer linear programming model. However, this patent has the following limitations: (1) It relies on manually preset operating constraints and does not integrate RPA technology to achieve real-time automatic acquisition and protocol conversion of meteorological data, load data, and equipment status data, resulting in data updates lagging behind the speed of disaster evolution; (2) It uses an offline planning model for solution and lacks an AI-based load forecasting and dynamic prediction module for power generation capacity decline, making it impossible to dynamically correct regulation strategies based on real-time disaster paths; (3) The planning scheme is limited to the resource allocation stage and does not establish an execution feedback mechanism that directly connects RPA and the industrial control system, resulting in the optimization strategy not being converted into executable instructions and calibrated in real time. This makes the scheme prone to strategy execution deviations and response delays in actual extreme weather scenarios. Summary of the Invention
[0004] This invention aims to alleviate the imbalance between power supply and demand under extreme weather conditions. By using an RPA protocol conversion engine to connect multi-source heterogeneous data from meteorology, load, and power generation equipment in real time, it solves the problems of data acquisition lag and protocol interoperability in disaster scenarios. At the same time, it constructs an AI-based dynamic load demand prediction and power generation capacity decline assessment model, which breaks through the limitations of traditional static planning models in adapting to dynamic disaster paths. It also designs a multi-strategy collaborative optimization and feedback iteration mechanism to generate dynamic adjustment instructions to adapt to real-time power shortages. Finally, relying on the direct command connection channel between RPA and industrial control systems, it achieves millisecond-level protocol conversion and secure execution, thereby eliminating response delays and execution errors caused by manual intervention and comprehensively improving the elastic regulation capability and supply-demand balance accuracy of the power system under extreme weather conditions.
[0005] This invention proposes an intelligent optimization method for power supply and demand in extreme weather based on RPA. The method includes: when a meteorological disaster warning signal determines that the disaster level has reached a preset threshold, multi-protocol data is collected through an RPA protocol conversion engine; the collected data is input into a load demand prediction model and a power generation capacity decline prediction model to generate a power gap assessment result; if the power gap assessment result exceeds a safety threshold, a dynamic optimization strategy is generated based on the comparison between the assessment result and the threshold; the optimization strategy is converted into industrial control protocol instructions and executed through an RPA control module; the strategy execution intensity is adjusted based on feedback data of grid frequency deviation rate and voltage fluctuation amplitude; if the grid parameters have not recovered to stability, data collection and strategy optimization are retried.
[0006] As a preferred embodiment, when the meteorological disaster warning signal determines that the disaster level has reached a preset threshold, the method obtains and parses real-time disaster path data from the meteorological bureau's API interface through the RPA protocol conversion engine; and calculates the affected area of power facilities based on the movement speed and coverage of the disaster center.
[0007] Preferably, this method reads the Modbus-TCP protocol port of the smart meter through the RPA protocol conversion engine, and extracts minute-level load fluctuation data within a preset area based on the protocol parsing results.
[0008] As a preferred method, this approach connects to the IEC61850 protocol channel of the new energy unit through an RPA protocol conversion engine, and generates an adjustable output curve for the photovoltaic / wind turbine unit based on the equipment status word and analog data.
[0009] As a preferred approach, this method generates future load forecasts using an LSTM neural network based on meteorological disaster path data and historical load curves; and dynamically adjusts the model weight coefficients based on residual analysis of the forecasts and real-time load data.
[0010] As a preferred approach, this method constructs a random forest regression model based on the disaster intensity coefficient and the unit operating status parameters; and calculates the dispatchable capacity decay curve of photovoltaic / wind turbine units based on the equipment availability decay gradient.
[0011] As a preferred approach, when the power shortage assessment result exceeds the safety threshold, the method prioritizes initiating virtual power plant dispatch instructions based on the shortage level; if the shortage continues to expand, a demand response incentive scheme is superimposed and an execution priority sequence is generated.
[0012] As a preferred approach, this method optimizes the ratio of charging and discharging power of energy storage power stations to the output of distributed power sources using a particle swarm optimization algorithm, and generates an execution sequence after performing security verification of scheduling instructions through a digital twin platform.
[0013] Preferably, this method converts the optimization strategy into IEC 60870-5-104 protocol instructions; the instructions are sent to the substation automation system through the protocol parsing engine, and the consistency between the control instructions and the equipment status words is verified before execution.
[0014] As a preferred embodiment, this method reduces the virtual power plant dispatch power adjustment step size according to gradient rules based on whether the grid frequency deviation rate and voltage fluctuation amplitude exceed the preset deviation threshold; when the time of exceeding the standard of the grid frequency deviation rate or voltage fluctuation amplitude exceeds the preset time, it triggers full-process data re-acquisition and strategy iterative optimization.
[0015] The present invention has the following beneficial effects: 1. By using the RPA protocol conversion engine, the system can automatically collect and standardize heterogeneous data from meteorological, load, and power generation equipment, significantly improving the efficiency and compatibility of multi-protocol data collection in extreme weather scenarios and solving the problem of data synchronization lag in traditional manual methods.
[0016] 2. The dual-model collaborative architecture based on artificial intelligence for load demand forecasting and power generation capacity decline forecasting effectively improves the dynamic tracking capability of load fluctuations and power generation capacity changes, and breaks through the limitations of static models in adapting to the dynamic evolution of disaster paths.
[0017] 3. Through a multi-strategy dynamic fusion mechanism of virtual power plant scheduling, demand response incentives, and backup power activation, optimized instructions adapted to real-time power shortages can be generated quickly, significantly shortening the recovery time from supply and demand imbalances.
[0018] 4. By leveraging the deep integration of the RPA protocol conversion engine with industrial control protocols, the system achieves automated parsing and security verification of scheduling instructions, significantly improving the success rate of control instruction execution and effectively reducing the risk of human error.
[0019] 5. A dynamic calibration mechanism is constructed based on real-time feedback data of power grid operating parameters, which significantly shortens the strategy optimization iteration cycle and improves the system's adaptive learning efficiency in continuous disaster events. Attached Figure Description
[0020] Figure 1 This is a schematic diagram of the method flow of the present invention.
[0021] Figure 2 This is a schematic diagram of the RPA instruction execution and feedback process of the present invention. Detailed Implementation
[0022] Example 1 according to Figure 1 As shown, this invention proposes an intelligent optimization method for power supply and demand in extreme weather based on RPA.
[0023] When the meteorological disaster early warning system detected that the typhoon's path was approaching the coastal areas, the National Meteorological Center pushed real-time disaster evolution data to the power dispatch center through a dedicated API interface. The RPA protocol conversion engine automatically parsed the JSON-formatted meteorological reports, overlaid a power grid topology map using a geographic information system, and dynamically calculated the coordinate set of transmission and transformation facilities within a 50-kilometer radius of the disaster center. At the same time, distributed acquisition terminals deployed in the 220 kV substation transmitted real-time operating data of the line temperature measurement devices to the RPA engine through the OPC UA protocol, forming a thermal map of equipment vulnerability.
[0024] Smart meter clusters upload minute-level load fluctuation data to edge computing nodes via the Modbus-TCP protocol, while the RPA protocol conversion engine simultaneously captures the list of interruptible loads from industrial and commercial users. The new energy monitoring platform transmits DC-side voltage anomaly alarm information from photovoltaic arrays via the IEC 61850 protocol channel. The RPA engine automatically extracts fault codes from string inverters and, combined with meteorological satellite cloud image motion vectors, predicts the solar intensity attenuation curve for the next two hours.
[0025] The load demand forecasting module initiates time series analysis using an LSTM neural network, inputting historical load curves and real-time electricity consumption data into a bidirectional gated recurrent unit for feature extraction. The model dynamically adjusts the hidden layer weight matrix to generate load forecasts for the next three hours in 15-minute increments. The residual analysis module compares these forecasts with actual sampled data from smart meters, triggering an online learning mechanism to update the convolutional kernel parameters. Simultaneously, the power generation capacity assessment unit constructs a random forest regression model, calculating the power generation efficiency degradation gradient function based on wind turbine pitch angle adjustment logs and photovoltaic panel cleanliness index.
[0026] When the predicted power shortage exceeds the regional reserve capacity threshold, the multi-strategy collaborative optimization engine initiates the virtual power plant scheduling priority algorithm. The particle swarm optimization module traverses the SOC state matrix of the energy storage power station, simulating the impact of different charging and discharging strategies on the main grid frequency in the digital twin platform, and generating a power adjustment scheme that balances economy and safety. The demand response incentive decision tree synchronously analyzes the historical response records of industrial and commercial users, and generates a time-of-use pricing gradient table through a contract matching algorithm.
[0027] The RPA control module converts the optimization strategy into control command frames conforming to the IEC 60870-5-104 protocol. Before issuing the command, it verifies the device status words of the substation automation system through a security verification engine. The protocol conversion middleware automatically encapsulates GOOSE messages and transmits them to the distribution automation terminal via an encrypted tunnel. The execution feedback unit monitors the grid frequency deviation rate in real time. When it detects that the tie-line power oscillation exceeds a preset threshold, it immediately activates a gradient decay mechanism to reduce the virtual power plant regulation step size.
[0028] The digital twin platform synchronously constructs a three-dimensional power grid situational sandbox, aligning real-time collected line temperature, transformer load rate, and meteorological radar echo data in time and space. When an abnormal icing growth rate is detected on a 110 kV line, the automatic activation plan of the standby automatic transfer switch is triggered, and a black start support request is sent to the surrounding microgrids via the RPA engine. The multi-source data fusion module continuously integrates SCADA system alarm information and UAV inspection images, using image recognition technology to locate the coordinates of damaged towers.
[0029] During the strategy execution phase, the load aggregation platform sequentially issues air conditioning group control commands according to a preset priority sequence, and the building energy management system automatically adjusts the chilled water circulation pump frequency. The RPA engine simultaneously intervenes in the communication management unit of the electric vehicle charging pile, batch modifying charging power limits via the DL / T645 protocol. Upon receiving the AGC adjustment command, the energy storage power station's power conversion system completes the charging / discharging mode switch within 200 milliseconds and feeds back the actual output curve to the energy management system through the CIM model.
[0030] The dynamic calibration module continuously receives phasor measurement data from the PMU device. When a voltage sag is detected to last for more than 300 milliseconds, a strategy reassessment process is immediately triggered. The machine learning model recalculates the disaster impact radius based on the new meteorological heat map and updates the attenuation coefficient of the power generation capacity prediction curve. The iterative optimization engine initiates a multi-objective genetic algorithm to generate a corrected scheme that includes the start-up and shutdown sequence of the diesel generators, while ensuring the N-1 safety criterion of the hub substation.
[0031] The protocol adaptation middleware automatically detects the communication protocol version of the target device before each command is issued. When it detects that the station-side relay protection device has been upgraded to IEC 61850 version 2, it dynamically loads the corresponding MMS service mapping table. The security verification unit uses an asymmetric encryption algorithm to digitally sign control commands and filters abnormal operation requests through a whitelist mechanism. The execution log analysis module constructs a correlation graph between operation commands and changes in grid parameters, providing reinforcement learning samples for subsequent strategy optimization.
[0032] Example 2 according to Figure 2 As shown, this invention proposes an intelligent optimization method for power supply and demand in extreme weather based on RPA.
[0033] When the typhoon warning level is upgraded to red, the RPA protocol conversion engine automatically activates multi-threaded data acquisition tasks. It captures the typhoon eye's latitude and longitude and movement vector data through the meteorological bureau's dedicated API interface, parses the wind speed and precipitation intensity fields in the JSON message, and simultaneously accesses the CIM / E model file of the provincial dispatch master station. It then dynamically overlays the power grid topology to generate a heat map of the affected substation coordinates. Smart meter clusters deployed in coastal industrial parks upload minute-level load curves via the Modbus-TCP protocol. The RPA engine calls a Python script to parse the register address mapping table, extract the impact load characteristic values of the precision manufacturing production line, and simultaneously poll the IEC 61850-MMS communication channel of the wind farm's SCADA system to obtain the wind turbine yaw system status word and converter DC bus voltage alarm information, automatically generating the unit's adjustable capacity decay curve.
[0034] The load forecasting center uses an LSTM neural network for time-series analysis, fusing the predicted typhoon path trajectory with historical load curves from disaster periods through convolutional features to output the load demand fluctuation band for the next three hours. The power generation capacity assessment module simultaneously runs a random forest regression model, calculating the probability of water accumulation on photovoltaic panel surfaces based on the radar echo intensity matrix, and generating a photovoltaic output degradation gradient function by combining inverter fault logs. When the system detects that the predicted power shortage in a 220 kV power supply area exceeds the spinning reserve capacity, the multi-objective optimization engine immediately activates the virtual power plant dispatch plan. The particle swarm optimization algorithm simulates the impact of different charging and discharging strategies of the energy storage power station on the main grid frequency in the digital twin platform, generating a power adjustment scheme that balances economy and safety, and generating a time-of-use pricing incentive gradient table through a contract matching algorithm.
[0035] The RPA control module invokes the protocol conversion middleware to encapsulate the energy storage charging and discharging commands in the optimization strategy into ASDU data units conforming to the IEC60870-5-104 protocol. After adding a timestamp and CRC checksum, the data is sent to the substation automation system via an encrypted fiber optic channel. Before execution, the safety verification engine compares the control point number with the circuit breaker open / closed status in the equipment ledger. If the target bay is found to be under maintenance, the system automatically switches to the standby feeder control command. The protocol parser synchronously listens to the DL / T645-2007 protocol response frames from the distribution terminal and captures the reactive power compensation switching feedback signals of the intelligent capacitor bank in real time, forming a time-stamped execution log.
[0036] The power grid dynamic sensing unit collects phasor measurement data of tie lines through PMU devices, and calculates the inertial response characteristic curve of the regional power grid using a frequency tracking algorithm. When the frequency deviation rate of a certain 110 kV hub substation is detected to continuously exceed the threshold, the gradient attenuation controller immediately reduces the virtual power plant adjustment step size according to the exponential curve, and sends an air conditioning group control mode switching command to the building energy management system through the OPC UA protocol. The digital twin platform synchronously reconstructs the three-dimensional power grid situation, overlays the weather radar reflectivity layer and UAV inspection images, and when the risk of fallen trees is identified in a certain transmission corridor, it automatically generates the automatic transfer switch activation sequence and quickly blocks the reclosing function of adjacent feeders through GOOSE messages.
[0037] During the strategy execution phase, the load aggregator platform sends a demand response invitation to the commercial complex via the MQTT protocol. The building automation system adjusts the output curve of the ice storage chiller unit, and the RPA engine simultaneously intervenes in the CAN bus of the charging pile management system to modify the power limit parameters of the DC fast charging piles. After receiving the AGC adjustment command, the energy storage power station completes the grid connection mode switch within a few hundred milliseconds and simultaneously feeds back the actual output fluctuation band to the energy management system. The dynamic calibration module continuously receives the 1kHz sampling data stream from the synchronous phasor measurement device. When the duration of the voltage sag event exceeds the limit, the strategy rollback mechanism is immediately triggered to restore the control parameters of the previous version and start full data re-acquisition.
[0038] The iterative optimization engine invokes a reinforcement learning model, using the latest grid frequency recovery rate as the reward function to recalculate the collaborative weighting coefficients of the virtual power plant and demand response. The digital certificate management system verifies the re-optimization strategy through multi-signature verification and then distributes it to each edge computing node via the IEC 62351 secure communication protocol, forming a new generation of control command sets. After the typhoon passes, the self-healing control module automatically checks the equipment status and topology connections, generates a grid reconfiguration plan, and pushes it to the dispatcher's workstation via an SVG graphical interface, completing the full lifecycle management of this closed-loop control.
[0039] When meteorological satellites detect strong convective clouds moving towards areas with high load density, the RPA protocol conversion engine activates its emergency plan. It reads real-time telemetry data from the distribution network automation terminal via the OPC DA interface and analyzes the freezing index and conductor galloping alarm signals in the DNP3.0 protocol. Simultaneously, the new energy monitoring platform pushes Modbus-TCP device status messages from the photovoltaic power station. The RPA script automatically identifies abnormal insulation impedance alarms from string inverters and, combined with a satellite cloud image inversion model, predicts the irradiance attenuation trend for the next hour. The load forecasting center invokes a bidirectional GRU neural network, integrating commercial complex passenger flow forecast data with real-time air conditioning load curves to dynamically correct the peak and valley characteristics of cooling load demand in office buildings.
[0040] The power generation capacity assessment unit connects to the hydropower plant's water situation monitoring system, analyzes the IEC60870-5-101 protocol data frames from the reservoir water level sensor, and generates a dispatchable capacity confidence interval by combining it with unit vibration monitoring data. When the multi-source data fusion platform determines that a power supply shortage will occur in a high-tech industrial park, the virtual power plant dispatch engine immediately activates the pre-set emergency response strategy, calls the quantum genetic algorithm to simulate the coordinated regulation scheme of distributed power sources and energy storage in the digital twin environment, and generates an optimized instruction set containing time constraints.
[0041] The RPA control module loads the IEC 61850-8-1 mapping template, converts energy storage charging and discharging commands into MMS service requests, adds SAML security assertions, and then sends them to the prefabricated energy storage substation via the station control layer network. The execution verification unit synchronously listens for GOOSE subscription messages from the relay protection equipment. When a transient fault is detected on a 35 kV feeder, the power regulation command issuance time is automatically delayed until reclosing is successful. The protocol adaptation middleware dynamically switches communication protocol versions. When it identifies an older substation using the IEC 60870-5-103 protocol, it calls the legacy system compatibility module for command translation.
[0042] The dynamic sensing network collects end-voltage harmonic distortion rate data through the advanced measurement system of smart meters, and the power quality analysis algorithm identifies a voltage dip event caused by a semiconductor manufacturing line. The adaptive regulator immediately initiates a multi-level response mechanism, first adjusting the compensation capacity of the SVG static var generator, and simultaneously sending lighting dimming commands to the smart building via the DDS data distribution service. When the PMU device detects an abnormal decrease in the regional power grid's inertial time constant, the virtual synchronous machine control algorithm automatically enhances the damping characteristic simulation function of the energy storage converter and verifies transient stability using the CIGRE standard model.
[0043] The strategy iteration module continuously receives tower tilt images captured by the drone inspection system. When the visual recognition algorithm determines that a transmission channel has a risk of tree obstruction, it automatically generates a temporary line load rate limiting strategy. The re-optimization engine calls a federated learning framework to conduct distributed training with multiple substation edge computing nodes while ensuring data privacy, generating dynamic adjustment parameters that adapt to local weather changes. The end-to-end traceability system associates and stores the version number, timestamp, and execution effect of each strategy iteration, forming an auditable decision chain, and uses blockchain technology to ensure the immutability of the operation logs.
[0044] When a snow and ice disaster warning is triggered, the RPA protocol conversion engine activates the cold wave response mode, accesses the day-ahead clearing results of the electricity market trading platform via the IEC 62325 protocol, and simultaneously collects the heat-to-power ratio adjustment margin data of the heating units. The distribution IoT gateway uploads oil temperature monitoring data from the transformer substations via the LoRaWAN protocol. The RPA script parses the ASCII-formatted load curve messages to identify the cluster response characteristics of the electric heating load. The new energy power prediction system calls high-resolution snowfall forecast data from the WRF meteorological model and combines it with a historical icing event database to generate a snow cover prediction surface for photovoltaic modules.
[0045] The load demand forecasting module incorporates a graph convolutional neural network to perform spatial correlation analysis between the community population heat map and the heating load growth trend, outputting refined load forecast zones for each zone. The power generation capacity assessment unit connects to the gas turbine's OPCDA server, reads combustion chamber pressure oscillation spectrum data, and combines this with the LNG receiving terminal's gasification rate to generate confidence intervals for the unit's ramp-up capability. When the supply and demand balance analysis system determines that a certain energy hub will experience a hard power supply gap, the multi-strategy optimization engine immediately activates the black-start contingency plan, calling a mixed-integer programming algorithm to simulate multi-energy complementary schemes in the digital twin platform.
[0046] The RPA control module loads the function block library of the IEC 61131-3 standard, converting the microgrid grid connection instructions in the optimization strategy into PLC executable code, which is then distributed to the prefabricated control cabinet via PROFINET industrial Ethernet. The security verification engine synchronously verifies the digital certificate chain of the FTU terminal; when an expired certificate is detected for a ring main unit DTU device, a temporary token mechanism is automatically activated to complete authentication. When the protocol conversion middleware identifies that an older distribution terminal uses the DNP3.0 protocol, it dynamically loads the legacy system compatibility layer to reconstruct the data frame, ensuring the integrity and timing consistency of the control instructions.
[0047] The power grid status sensing unit captures the icing growth rate of transmission lines using a traveling wave ranging device, and the mechanical load assessment algorithm predicts the conductor sag change trend. When the equivalent icing thickness of a 500 kV line exceeds the design value, the adaptive protection setting management system immediately adjusts the range of distance protection stage I and pushes parameter update instructions to the wide-area measurement system via the IEEE C37.118 protocol. The dynamic stability control module synchronously adjusts the inertial response coefficient of the pumped storage unit, and combines it with the emergency power support function of the HVDC converter station to construct a multi-dimensional defense system.
[0048] The strategy iteration engine continuously receives online monitoring data on insulator pollution levels. When the ultraviolet imaging analysis system detects corona discharge in a substation bushing, it automatically generates a temporary load factor limiting strategy. The full-scenario simulation platform uses a multibody dynamics model to simulate the impact of different de-icing schemes on the transient stability of the power grid, outputting the optimal DC de-icing device startup sequence. The post-disaster recovery module reconstructs the 3D geographic information of damaged lines using a BIM model, combines it with a drone swarm path planning algorithm to generate the optimal emergency repair resource scheduling plan, and pushes visual operation guidance to on-site personnel through AR glasses.
[0049] Example 3 During the implementation of the energy digital economy platform, the virtual power plant aggregates distributed photovoltaic (PV) power, energy storage devices, and adjustable load resources to construct a dynamic response network, achieving optimized power supply and demand balance under extreme weather conditions. The platform utilizes edge computing nodes deployed within industrial park substations to collect real-time data on wind turbine speeds, PV inverter output curves, and cold chain cold storage temperatures, transmitting this data to the regional energy dispatch center via a 5G private network. During peak summer electricity consumption periods, the system automatically triggers a flexible load control strategy for chiller units, shifting the energy storage cycle of chilled water storage tanks from peak to off-peak hours. Simultaneously, it coordinates with the central air conditioning system of commercial complexes to raise the return water temperature setpoint by 2°C, forming a cross-business load collaborative response.
[0050] The demand response module integrates the parsing function of the electric vehicle charging pile group control protocol and develops a blockchain-based response quantity confirmation algorithm. When the power grid experiences a shortage of backup capacity, the platform pushes tiered incentive signals to registered users. Smart charging piles dynamically adjust charging power based on battery health status and embed an RFID authentication mechanism in charging gun plugging and unplugging events. For data center uninterruptible power supply systems, a state-of-charge prediction model for lithium iron phosphate battery packs is deployed. Combined with data from data center temperature and humidity sensors, a feasible time window for backup power to participate in frequency regulation is generated, maximizing the regulation potential while ensuring the reliability of power supply to critical loads.
[0051] The integrated smart energy system implements multi-energy flow coupling engineering in coastal industrial parks, constructing a ground-source heat pump group control system and a rooftop photovoltaic integrated monitoring platform. By deploying fiber optic temperature measurement devices and steam flow meters in the heating pipelines, a digital twin of the heating network is built to simulate heat loss distribution under different pressure conditions in real time. In regional applications, a cross-enterprise waste heat trading matching engine is developed to match the sintering waste heat of steel plants with the heat demand of distillation towers in chemical plants in time and space, and to achieve interconnection of medium- and low-temperature heating networks within a 6-kilometer radius using relay pump stations.
[0052] The platform's data acquisition layer employs a heterogeneous protocol conversion gateway, compatible with 17 industrial communication protocols including Modbus, IEC104, and DL / T645, and features a built-in message integrity verification module to prevent data tampering. In the Binhai New Area demonstration project, explosion-proof certified wireless vibration sensors are deployed to monitor stress changes on the outer wall of LNG storage tanks. Combined with typhoon path forecast data from the meteorological bureau, a knowledge graph for early warning of tank structural safety is established. For the unique environment of hospital operating rooms, a low-power wireless sensor network conforming to medical EMC standards is developed to achieve correlation analysis between the energy consumption of operating room purification air conditioning units and indoor bacterial counts.
[0053] The system communication architecture adopts a layered encryption design. An industrial firewall is deployed at the plant level to isolate the OT network, while quantum key distribution technology is used at the master station to ensure the security of scheduling command transmission. A time-series database compression algorithm with independent intellectual property rights has been developed, increasing the compression ratio of second-level sampled data to 1:15 and supporting multi-dimensional feature retrieval of historical load curves. In the mobile application development, AR remote maintenance functionality is integrated, allowing maintenance personnel to overlay a 3D model of the internal wiring of the distribution cabinet with real-time infrared thermal imaging data through the HUD interface on a smart safety helmet.
[0054] The control strategy generation module incorporates a federated learning framework, allowing participating companies to jointly train the load prediction model without leaving the data domain. A virtual synchronous machine coordination control algorithm based on digital twins is developed to smoothly adjust virtual inertia parameters during microgrid grid-to-grid switching. For hydrogen-electricity coupling scenarios, a power coordination control logic for the electrolyzer array and fuel cell power station is designed, and a dynamic optimization model for hydrogen production efficiency and electricity price fluctuations is established to achieve dual optimization of renewable energy consumption and hydrogen energy economics.
[0055] The platform's security protection system has passed Level 3 Information Security Protection Certification, and a host hardening system has been deployed to perform vulnerability scanning and baseline configuration verification on 1200 servers. A data lineage tracing mechanism covering the entire business chain has been established, and blockchain notarization technology is used to record version change information during data cleaning and transformation. Regarding user privacy protection, k-anonymity-based electricity data anonymization processing has been implemented, and a differential privacy algorithm has been developed to generate regional aggregated load reports, ensuring that individual electricity usage patterns are untraceable.
[0056] The operation and maintenance management subsystem integrates an AIoT device health assessment model to predict the lifespan of smart meter terminals and provide replacement warnings. A self-learning work order dispatch engine has been developed, dynamically optimizing emergency repair route planning by combining GIS map data with a skills matrix for technical personnel. In the construction of the training base, a VR simulation training platform is deployed to recreate complex substation fault scenarios. Trainees can practice switching operations of disconnecting switches using motion capture gloves, and the system automatically generates an operation standardization assessment report.
[0057] This embodiment forms a complete solution in key technologies such as multi-energy complementary coordinated control, plug-and-play heterogeneous equipment, and secure and reliable data flow. Actual engineering verification shows that the system has significant effects in improving energy utilization efficiency, enhancing grid resilience, and promoting the consumption of clean energy, providing a replicable and scalable technical paradigm for the construction of new power systems.
Claims
1. An RPA-based intelligent optimization method for power supply and demand in extreme weather, characterized in that, The method includes: When a meteorological disaster warning signal determines that the disaster level has reached a preset threshold, multi-protocol data is collected through the RPA protocol conversion engine. The collected data is then input into the load demand prediction model and the power generation capacity decline prediction model to generate a power gap assessment result. If the power gap assessment result exceeds the safety threshold, a dynamic optimization strategy is generated based on the comparison between the assessment result and the threshold. The RPA control module converts the optimization strategy into industrial control protocol instructions and executes them. It adjusts the strategy execution intensity based on feedback data of grid frequency deviation rate and voltage fluctuation amplitude. If the grid parameters do not return to stability, data acquisition and strategy optimization are retried.
2. The intelligent optimization method for power supply and demand in extreme weather based on RPA according to claim 1, characterized in that, When the meteorological disaster warning signal determines that the disaster level has reached a preset threshold, the method obtains and parses real-time disaster path data from the meteorological bureau's API interface through the RPA protocol conversion engine; and calculates the affected area of power facilities based on the movement speed and coverage of the disaster center.
3. A method for intelligent optimization of power supply and demand in extreme weather based on RPA according to claim 1 or 2, characterized in that, The method reads the Modbus-TCP protocol port of the smart meter through the RPA protocol conversion engine, and extracts minute-level load fluctuation data within a preset area based on the protocol parsing results.
4. A method for intelligent optimization of power supply and demand in extreme weather based on RPA according to claim 1 or 2, characterized in that, The method accesses the IEC61850 protocol channel of the new energy unit through the RPA protocol conversion engine, and generates the adjustable output curve of the photovoltaic / wind turbine unit based on the equipment status word and analog data.
5. The intelligent optimization method for power supply and demand in extreme weather based on RPA according to claim 1, characterized in that, The method generates future load forecasts using an LSTM neural network based on meteorological disaster path data and historical load curves; and dynamically adjusts the model weight coefficients based on residual analysis of the forecasts and real-time load data.
6. The intelligent optimization method for power supply and demand in extreme weather based on RPA according to claim 1, characterized in that, The method constructs a random forest regression model based on the disaster intensity coefficient and the unit operating status parameters; and calculates the dispatchable capacity decay curve of photovoltaic / wind turbine units based on the equipment availability decay gradient.
7. A method for intelligent optimization of power supply and demand in extreme weather based on RPA according to claim 1, 5, or 6, characterized in that, When the power shortage assessment result exceeds the safety threshold, the method prioritizes the initiation of virtual power plant dispatch instructions based on the shortage level; if the shortage continues to expand, a demand response incentive scheme is superimposed and an execution priority sequence is generated.
8. The intelligent optimization method for power supply and demand in extreme weather based on RPA according to claim 1, characterized in that, The method optimizes the ratio of charging and discharging power of energy storage power stations to the output of distributed power sources using a particle swarm optimization algorithm, and generates an execution sequence after the scheduling instructions are securely verified by a digital twin platform.
9. The intelligent optimization method for power supply and demand in extreme weather based on RPA according to claim 1, characterized in that, The method converts the optimization strategy into IEC 60870-5-104 protocol instructions; the instructions are sent to the substation automation system through the protocol parsing engine, and the consistency between the control instructions and the equipment status words is verified before execution.
10. A method for intelligent optimization of power supply and demand in extreme weather based on RPA according to claim 1, 8, or 9, characterized in that, The method reduces the virtual power plant dispatch power adjustment step size according to gradient rules based on whether the grid frequency deviation rate and voltage fluctuation amplitude exceed the preset deviation threshold; when the grid frequency deviation rate or voltage fluctuation amplitude exceeds the preset duration, it triggers full-process data re-acquisition and strategy iterative optimization.
Citation Information
Patent Citations
Source network load storage regulation resource planning method and system for supply guarantee demand in extreme weather
CN119944764A