Multi-project parallel conflict detection and scheduling method based on resource load analysis

By standardizing resource data and constructing a dynamic load model, combined with a gradient threshold system and adaptive scheduling, the problems of resource load assessment bias and low conflict detection accuracy in multi-project parallel operations are solved, achieving accurate detection and efficient scheduling of resource load.

CN123159764APending Publication Date: 2026-11-24HUANENG INFORMATION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611330604.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-31
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing technologies for resource scheduling in multi-project parallel operations suffer from problems such as large discrepancies between resource load assessment results and actual on-site operating conditions, poor accuracy of conflict detection, and strong blindness in scheduling behavior, making them unsuitable for the needs of high-density multi-project parallel operations.

Method used

By standardizing, denoising, and timing-calibrating multi-project parallel resource data, a dynamic resource load quantification model is constructed. A three-level gradient threshold system is used for conflict detection, and adaptive scheduling suggestions are generated based on conflict level and load margin to achieve resource load diversion and task transfer.

Benefits of technology

It achieves accurate restoration of resource load status, accurately detects conflict levels, improves the adaptability and feasibility of scheduling schemes, avoids secondary conflicts, and improves the accuracy and efficiency of resource scheduling.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123159764A_ABST
    Figure CN123159764A_ABST
Patent Text Reader

Abstract

This application provides a method for multi-project parallel conflict detection and scheduling based on resource load analysis, covering the field of resource scheduling. The method includes the following steps: S1: Standardized acquisition, noise reduction, and time-series calibration of multi-project parallel resource data; S2: Construction of a dynamic resource load quantification model based on the standardized dataset; S3: Automatic detection of resource conflicts based on gradient thresholds and comprehensive load values; S4: Generation of adaptive scheduling suggestions based on conflict level and load margin. This application employs a three-level gradient threshold system to achieve hierarchical and accurate detection of resource conflicts, differing from the traditional coarse judgment method using a single threshold. It can accurately distinguish the conflict type and severity level of manpower conflicts and equipment conflicts, while precisely identifying the corresponding project, time period, and resource information, forming a complete conflict detail dataset. This makes the conflict detection results more accurate and provides targeted support for scheduling operations.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of resource scheduling, and more specifically, to a method for detecting and scheduling multi-project parallel conflicts based on resource load analysis. Background Technology

[0002] In the field of resource scheduling for multi-project parallel operations, existing conventional scheduling methods generally adopt a crude processing logic based on static work hour statistics. Traditional technologies rely solely on fixed work hour occupancy ratios to determine resource usage status, failing to incorporate the real-time operating status of the resource pool and the saturation characteristics of overlapping multi-project operations to construct a dynamic load evaluation system. This results in significant deviations between resource load assessment results and actual on-site operating conditions. Furthermore, traditional conflict detection modes use only a single fixed criterion, failing to differentiate the severity of resource conflicts and easily leading to missed or false detections, resulting in poor conflict detection accuracy. In addition, existing technologies conduct conflict detection and resource scheduling independently, lacking quantifiable priority determination criteria in the scheduling process, leading to a strong degree of arbitrariness in the overall scheduling behavior. Summary of the Invention

[0003] The purpose of this invention is to solve the problem that the current parallel conflicts of human and equipment resources are difficult to resolve effectively, and are prone to secondary resource conflicts, making it unable to adapt to the high-density multi-project parallel operation scheduling requirements.

[0004] To achieve the above-mentioned objectives and improve the above-mentioned problems, this invention provides a multi-project parallel conflict detection and scheduling method based on resource load analysis, comprising the following steps: S1: Standardized collection, noise reduction and time series calibration of multi-project parallel resource data. Targeted collection of project work hour data and resource pool data. After abnormal data noise reduction and cleaning, unified statistical dimensions and precise time series alignment, a unique standardized resource dataset is generated. S2: Based on a standardized dataset, a dynamic resource load quantification model is constructed. Using the dynamic resource load calculation formula, the daily comprehensive load value of each human and equipment resource is quantified, thus building a dynamic resource load quantification model that can be updated in real time. The formula is: ; in Let i be the daily comprehensive load value of the i-th resource; This is the resource duration weighting coefficient; The daily usage hours / runtime of the i-th resource; The maximum available working hours per day for the i-th resource / rated operating time; Add weighting coefficients to the project; This represents the saturation value corresponding to the number of parallel projects that the i-th resource can undertake per day. S3: Automatic detection of resource conflicts based on gradient thresholds and comprehensive load values. Based on the daily comprehensive load value of resources output by S2, a fixed three-level gradient load threshold system is preset. S4: Adaptive scheduling suggestions are generated based on conflict level and load margin. The scheduling priority of each conflicting resource is quantified by the scheduling priority calculation formula, and resource load distribution and matching are completed according to the priority ranking. The formula is as follows: ; in: Let be the scheduling priority value of the i-th conflicting resource; This is the weighting factor for the remaining load; This refers to the conflict level weighting coefficient; This represents the resource conflict level score.

[0005] As a preferred technical solution of this application, step S1 specifically includes: S101: Dual-dimensional core data targeted collection, targeting multi-project parallel operation scenarios, fixedly collects two types of basic data: project work hour data and resource pool data; S102: Global data noise reduction and dimension unification, performing anomaly removal processing on collected project time data and resource pool data; S103: Time series benchmark alignment calibration, using the natural complete working day as the sole time series benchmark, aligns and matches the time nodes of all project sub-processes and the time nodes of all resource occupancy one by one.

[0006] As a preferred technical solution of this application, in S101, the project time data specifically includes the subdivided process rated time of each parallel project, the process consumed time, the process remaining time to be executed, the process start time node, and the process end time node. The resource pool data specifically includes the daily available working hours of all on-duty human resources, human resource skill matching tags, the daily rated operating time of all in-use equipment resources, the real-time occupancy period of equipment, and the maximum load limit of equipment operating conditions.

[0007] As a preferred technical solution of this application, in S2, the daily time sequence after S1 calibration is used as a fixed calculation cycle. For each human resource and equipment resource in the standardized resource dataset, the total working time data of its corresponding parallel project is bound to establish a dual-dimensional calculation benchmark, namely the resource time occupation dimension and the multi-project superposition saturation dimension. S202: The dynamic resource load calculation formula performs a double weighting operation of duration weight and project superposition weight to characterize the true comprehensive load status of the i-th resource in a single-day multi-project parallel scenario.

[0008] As a preferred technical solution of this application, step S3 specifically includes: S301: Fixed gradient threshold system preset, based on the rated performance limit of human and equipment resources, preset three-level load conflict judgment thresholds; S302: Accurate Conflict Classification Detection and Data Collection, which integrates the resources calculated by S2. The gradient threshold system is aligned one by one to complete the comparison and judgment.

[0009] As a preferred technical solution of this application, the specific threshold standard in S301 is as follows: A value between 0.7 and 0.85 is considered a minor conflict threshold. A value between 0.85 and 0.95 is considered a moderate conflict threshold. The threshold for severe conflict is between 0.95 and 1.0.

[0010] As a preferred technical solution of this application, in step S302, if human resources If the conflict falls within any conflict threshold range, a human conflict is determined to have occurred; if the equipment... If a conflict falls within any conflict threshold range, a device conflict is determined to occur. Simultaneously, the levels of the three-level load conflict determination are quantified and assigned values, defining resource conflict level scores: a fixed value of 0.3 for minor conflicts, a fixed value of 0.6 for moderate conflicts, and a fixed value of 1.0 for severe conflicts. Finally, conflict type, conflict level, resource conflict level score, corresponding project and time sequence information are collected to generate a structured conflict detail dataset.

[0011] As a preferred technical solution of this application, step S4 specifically includes: S401: Scheduling priority quantification calculation: Based on the remaining load of resources and the resource conflict level score, the scheduling priority calculation formula is used to complete the priority quantification and sorting. S402: Resource load matching and scheduling without secondary conflicts, sorted from high to low according to the scheduling priority value of each conflicting resource. S403: Standardized scheduling suggestions are output in a structured manner, providing dedicated resource scheduling suggestions.

[0012] As a preferred technical solution of this application, in S402, load diversion scheduling is performed on high-priority conflicting resources first, and for manpower conflicts, manpower with the same skill tag and sufficient low load margin in the resource pool is selected to share the excessive process tasks. In response to equipment conflicts, select idle equipment resources of the same type and with low load within the resource pool to transfer excess operation tasks.

[0013] Compared with the prior art, the beneficial effects of the present invention are as follows: In the scheme of this application: 1. It can accurately reproduce the actual load status of manpower and equipment resources in multi-project parallel scenarios, and capture the implicit load increment brought about by the superposition of multiple projects. It solves the technical shortcomings of traditional technology in underestimating the actual load of resources and being unable to adapt to parallel operation scenarios. It makes the resource load quantification results fit the actual on-site operation conditions, and provides a reliable quantitative basis for subsequent conflict classification detection. 2. A three-level gradient threshold system is adopted to achieve hierarchical and accurate detection of resource conflicts, which is different from the coarse judgment method of traditional single threshold. It can accurately distinguish the conflict type and severity level of manpower conflicts and equipment conflicts, and accurately locate the corresponding project, time period and resource information of the conflict, forming a complete conflict detail dataset, which makes the conflict detection results more accurate and provides targeted support for scheduling operations; 3. It can prioritize scheduling based on the urgency of conflicts and the remaining resource load status, and perform targeted load diversion and task transfer of manpower and equipment resources. At the same time, it can avoid secondary conflicts by combining project schedule constraints. Based on this, the adaptability and implementability of the scheduling solution can be greatly improved. Attached Figure Description Figure 1 A flowchart of the multi-project parallel conflict detection and scheduling method based on resource load analysis provided in this application. Detailed Implementation

[0014] To enable those skilled in the art to better understand the present invention, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort should fall within the scope of protection of the present invention.

[0015] To enable those skilled in the art to better understand the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings.

[0016] It should be noted that, unless otherwise specified, the embodiments and features and technical solutions in the present invention can be combined with each other.

[0017] It should be noted that similar labels and letters in the following figures indicate similar items. Therefore, once an item is defined in one figure, it does not need to be further defined and explained in subsequent figures.

[0018] Please refer to Figure 1 A multi-project parallel conflict detection and scheduling method based on resource load analysis includes the following steps: S1: Standardized collection, noise reduction and time series calibration of multi-project parallel resource data. Targeted collection of project work hour data and resource pool data. After abnormal data noise reduction and cleaning, unified statistical dimensions and precise time series alignment, a unique standardized resource dataset is generated. S2: Based on a standardized dataset, a dynamic resource load quantification model is constructed. Through a dynamic resource load calculation formula, integrating resource duration occupancy percentages and the saturation characteristics of multiple projects, the daily comprehensive load value of each human and equipment resource is quantified. This constructs a dynamic resource load quantification model that can be updated in real time. The formula is: ; in This is the daily comprehensive load value of the i-th resource (unitless, fixed range 0-1, the larger the value, the higher the resource load). This is the resource duration weighting coefficient (fixed preset 0.6, representing the basic impact weight of resource duration occupancy on load). The daily usage hours / running time (in hours) of the i-th resource in dataset S1. The maximum available man-hours / rated operating time of the i-th resource in the S1 dataset per day (in hours). Add a weighting coefficient to the project (fixed preset 0.4, representing the weight of the load increment caused by the parallel superposition of multiple projects). The saturation value (range 0-1, derived from the project working hour data in the first step) corresponding to the number of parallel projects undertaken by the i-th resource per day is calculated by substituting into this formula one by one to obtain the real-time comprehensive load value of all resources, thus completing the construction of the dynamic resource load quantification model. S3: Automatic resource conflict detection based on gradient threshold and comprehensive load value. Based on the daily comprehensive load value of resources output by S2, a fixed three-level gradient load threshold system is preset. By comparing the load value with the threshold, the system automatically distinguishes and determines the type and level of human conflict and equipment conflict, locks the project, time period and resource information corresponding to the conflict, and generates a conflict detail dataset to provide a targeted basis for subsequent intelligent scheduling. S4: Adaptive scheduling suggestions are generated based on conflict level and load margin. The scheduling priority of each conflicting resource is quantified by the scheduling priority calculation formula, and resource load distribution and matching are completed according to the priority ranking. The formula is as follows: ; in: The scheduling priority value of the i-th conflicting resource (unitless, the larger the value, the higher the scheduling priority); The remaining load weighting coefficient (fixed preset 0.7, representing the weight of the impact of remaining available load on scheduling priority); The conflict level weighting coefficient (fixed preset at 0.3, representing the weight of the impact of conflict severity on scheduling priority). Resource conflict level scores are assigned (minor conflict is assigned a fixed value of 0.3, moderate conflict is assigned a fixed value of 0.6, and severe conflict is assigned a fixed value of 1.0).

[0019] Furthermore, S1 specifically includes: S101: Dual-dimensional core data targeted collection, targeting multi-project parallel operation scenarios, fixedly collects two types of basic data: project work hour data and resource pool data; S102: Global data noise reduction and dimension unification. It performs anomaly removal processing on the collected project work hour data and resource pool data, deletes invalid abnormal data that exceeds the project duration or the rated performance of resources, and unifies the statistical dimension of all data. It converts all work hours, equipment running time and resource availability time data into the standard unit of daily hours, completely eliminates the differences in statistical caliber between different projects and different manpower, equipment and resources, and ensures that the data calculation benchmark is consistent. S103: Time series benchmark alignment and calibration. Using the natural complete working day as the sole time series benchmark, the time nodes of all project sub-processes and the time nodes of all resources are aligned and matched one by one to achieve a one-to-one correspondence between the time of process operation and the time of resource occupation. Finally, a standardized resource dataset with unified time series, unified dimensions, and valid data is generated, completing the basic data preprocessing.

[0020] Furthermore, in S101, the project time data specifically includes the rated time of each parallel project's subdivided process, the time consumed by the process, the remaining time to be executed by the process, the start time node of the process, and the end time node of the process. The resource pool data specifically includes the daily available working hours of all on-duty human resources, human resource skill matching tags, the daily rated operating time of all in-use equipment resources, the real-time occupancy period of equipment, and the maximum load limit of equipment operating conditions.

[0021] Furthermore, in S2, the daily time series calibrated in S1 is used as a fixed calculation cycle. For each human resource and equipment resource in the standardized resource dataset, the total working hours of the corresponding parallel project are bound to establish a two-dimensional calculation benchmark, namely the resource time occupancy dimension and the multi-project superposition saturation dimension. The error defects of single-dimensional calculation are corrected by weighted fusion of the two dimensions. S202: The dynamic resource load calculation formula performs a double weighting operation of duration weight and project superposition weight to characterize the true comprehensive load status of the i-th resource in a single-day multi-project parallel scenario.

[0022] Furthermore, S3 specifically includes: S301: Fixed gradient threshold system preset, based on the rated performance limit of human and equipment resources, preset three-level load conflict judgment thresholds to form a standardized gradient threshold system, without dynamic random threshold adjustment; S302: Accurate Conflict Classification Detection and Data Collection, which integrates the resources calculated by S2. The gradient threshold system is aligned one by one to complete the comparison and judgment.

[0023] Furthermore, in S301, the specific threshold standards are as follows: A value between 0.7 and 0.85 is considered a minor conflict threshold. A value between 0.85 and 0.95 is considered a moderate conflict threshold. The threshold for severe conflict is between 0.95 and 1.0.

[0024] Furthermore, in S302, if human resources... If the conflict falls within any conflict threshold range, a human conflict is determined to have occurred; if the equipment... If a conflict falls within any conflict threshold range, a device conflict is determined to occur. At the same time, the parallel project number, conflict occurrence time period, and unique resource number corresponding to the conflict are accurately identified. The corresponding conflict level is matched synchronously, and the level of the three-level load conflict determination is quantified and assigned values. Resource conflict level scores are defined as follows: minor conflict is assigned a fixed value of 0.3, moderate conflict is assigned a fixed value of 0.6, and severe conflict is assigned a fixed value of 1.0. Finally, the conflict type, conflict level, resource conflict level score, corresponding project and time sequence information are collected to generate a structured conflict detail dataset.

[0025] Furthermore, S4 specifically includes: S401: Scheduling priority quantification calculation: Based on the remaining load of resources and the resource conflict level score, the scheduling priority calculation formula is used to complete the priority quantification and sorting. S402: Resource load matching and scheduling without secondary conflicts, sorted from high to low according to the scheduling priority value of each conflicting resource. S403: Standardized scheduling suggestions are output in a structured manner, integrating the generated structured conflict details dataset, scheduling priorities, load balancing scheduling that prioritizes high-priority conflicting resources, and the schedule constraints known in S101 and S402, to output dedicated resource scheduling suggestions.

[0026] Furthermore, in S402, load diversion scheduling is prioritized for high-priority conflicting resources. For manpower conflicts, manpower with the same skill tag and sufficient low load margin within the resource pool is selected to share the excessive process tasks. To address equipment conflicts, idle equipment resources of the same type and with low load within the resource pool are selected to transfer tasks exceeding the standard. During the scheduling process, the project schedule node data collected by S1 is bound throughout the entire process to strictly avoid secondary resource conflicts caused by overlapping work sequence.

[0027] In this invention, unless otherwise explicitly specified and limited, the terms "installation," "connection," "linking," and "fixing," etc., should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral part; they can refer to a mechanical connection, an electrical connection, or a connection that allows communication between them; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal communication of two components or the interaction between two components, unless otherwise explicitly limited. Those skilled in the art can understand the specific meaning of the above terms in this invention according to the specific circumstances.

[0028] Obviously, the embodiments described above are merely some embodiments of the present invention, not all embodiments. The accompanying drawings show preferred embodiments of the present invention, but do not limit the patent scope of the present invention. The present invention can be implemented in many different forms; rather, these embodiments are provided to provide a more thorough and complete understanding of the disclosure of the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing specific embodiments, or make equivalent substitutions for some of the technical features. Any equivalent structures made using the content of this specification and drawings, directly or indirectly applied to other related technical fields, are similarly within the patent protection scope of this invention.

Claims

1. A multi-project parallel conflict detection and scheduling method based on resource load analysis, characterized in that, The following steps are included: S1: Standardized collection, noise reduction and time series calibration of multi-project parallel resource data. Targeted collection of project work hour data and resource pool data. After abnormal data noise reduction and cleaning, unified statistical dimensions and precise time series alignment, a unique standardized resource dataset is generated. S2: Based on a standardized dataset, a dynamic resource load quantification model is constructed. Using the dynamic resource load calculation formula, the daily comprehensive load value of each human and equipment resource is quantified, thus building a dynamic resource load quantification model that can be updated in real time. The formula is: ; in Let i be the daily comprehensive load value of the i-th resource; This is the resource duration weighting coefficient; The daily usage hours / runtime of the i-th resource; The maximum available working hours per day for the i-th resource / rated operating time; Add weighting coefficients to the project; This represents the saturation value corresponding to the number of parallel projects that the i-th resource can undertake per day. S3: Automatic detection of resource conflicts based on gradient thresholds and comprehensive load values. Based on the daily comprehensive load value of resources output by S2, a fixed three-level gradient load threshold system is preset. S4: Adaptive scheduling suggestions are generated based on conflict level and load margin. The scheduling priority of each conflicting resource is quantified by the scheduling priority calculation formula, and resource load distribution and matching are completed according to the priority ranking. The formula is as follows: ; in: Let be the scheduling priority value of the i-th conflicting resource; This is the weighting factor for the remaining load; This refers to the conflict level weighting coefficient; This represents the resource conflict level score.

2. The multi-project parallel conflict detection and scheduling method based on resource load analysis according to claim 1, characterized in that, Specifically, S1 includes: S101: Dual-dimensional core data targeted collection, targeting multi-project parallel operation scenarios, fixedly collects two types of basic data: project work hour data and resource pool data; S102: Global data noise reduction and dimension unification, performing anomaly removal processing on collected project time data and resource pool data; S103: Time series benchmark alignment calibration, using the natural complete working day as the sole time series benchmark, aligns and matches the time nodes of all project sub-processes and the time nodes of all resource occupancy one by one.

3. The multi-project parallel conflict detection and scheduling method based on resource load analysis according to claim 2, characterized in that, In S101, the project time data specifically includes the subdivided process rated time of each parallel project, the time consumed by the process, the remaining time to be executed by the process, the process start time node, and the process end time node. The resource pool data specifically includes the daily available working hours of all on-duty human resources, human resource skill matching tags, the daily rated operating time of all in-use equipment resources, the real-time occupancy period of equipment, and the maximum load limit of equipment operating conditions.

4. The multi-project parallel conflict detection and scheduling method based on resource load analysis according to claim 2, characterized in that, In S2, the daily time series calibrated by S1 is used as a fixed calculation cycle. For each human resource and equipment resource in the standardized resource dataset, the total working hours of the corresponding parallel project are bound to establish a two-dimensional calculation benchmark, namely the resource time occupation dimension and the multi-project superposition saturation dimension. S202: The dynamic resource load calculation formula performs a double weighting operation of duration weight and project superposition weight to characterize the true comprehensive load status of the i-th resource in a single-day multi-project parallel scenario.

5. The multi-project parallel conflict detection and scheduling method based on resource load analysis according to claim 3, characterized in that, Specifically, S3 includes: S301: Fixed gradient threshold system preset, based on the rated performance limit of human and equipment resources, preset three-level load conflict judgment thresholds; S302: Accurate Conflict Classification Detection and Data Collection, which integrates the resources calculated by S2. The gradient threshold system is aligned one by one to complete the comparison and judgment.

6. The multi-project parallel conflict detection and scheduling method based on resource load analysis according to claim 5, characterized in that, In S301, the specific threshold standard is as follows: A value between 0.7 and 0.85 is considered a minor conflict threshold. A value between 0.85 and 0.95 is considered a moderate conflict threshold. The threshold for severe conflict is between 0.95 and 1.

0.

7. The multi-project parallel conflict detection and scheduling method based on resource load analysis according to claim 5, characterized in that, In S302, if human resources If the conflict falls within any conflict threshold range, a human conflict is determined to have occurred; if the equipment... If a conflict falls within any conflict threshold range, a device conflict is determined to occur. Simultaneously, the levels of the three-level load conflict determination are quantified and assigned values, defining resource conflict level scores: a fixed value of 0.3 for minor conflicts, a fixed value of 0.6 for moderate conflicts, and a fixed value of 1.0 for severe conflicts. Finally, conflict type, conflict level, resource conflict level score, corresponding project and time sequence information are collected to generate a structured conflict detail dataset.

8. The multi-project parallel conflict detection and scheduling method based on resource load analysis according to claim 7, characterized in that, Specifically, S4 includes: S401: Scheduling priority quantification calculation: Based on the remaining load of resources and the resource conflict level score, the scheduling priority calculation formula is used to complete the priority quantification and sorting. S402: Resource load matching and scheduling without secondary conflicts, sorted from high to low according to the scheduling priority value of each conflicting resource. S403: Standardized scheduling suggestions are output in a structured manner, providing dedicated resource scheduling suggestions.

9. The multi-project parallel conflict detection and scheduling method based on resource load analysis according to claim 8, characterized in that, In S402, load diversion scheduling is performed on high-priority conflicting resources. For manpower conflicts, manpower with the same skill tag and sufficient low load margin in the resource pool is selected to share the excessive process tasks. In response to equipment conflicts, select idle equipment resources of the same type and with low load within the resource pool to transfer excess operation tasks.