Distributed photovoltaic grid-connected adaptability evaluation method based on multi-scene joint probability

By employing a multi-scenario joint probability assessment method, a security constraint and economic benefit model with explicit confidence levels is established. This addresses the issues of overly conservative assessment results and poor economic efficiency in distributed photovoltaic grid integration, achieving synergistic optimization and efficient solution of security and economy.

CN123159774APending Publication Date: 2026-11-24STATE GRID HUNAN ELECTRIC POWER CO LTD ELECTRIC POWER SCI RES INST +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611344545.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-01
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing technologies for assessing the adaptability of distributed photovoltaic (PV) grid integration suffer from rigid constraints that lead to overly conservative assessment results, an inability to accurately quantify safety risks, a lack of systematic evaluation of economic benefits, low solution efficiency, and difficulty in guaranteeing global optimality.

Method used

We adopt a multi-scenario joint probability approach to establish a probabilistic security constraint model with explicit confidence level and a comprehensive economic benefit constraint model. We transform the problem into a convex optimization problem through convex relaxation techniques and solve it using an efficient numerical algorithm.

Benefits of technology

It achieves a flexible balance between safety and economy, accurately quantifies safety margin, improves solution efficiency and accuracy, and provides a scientific and reliable evaluation method.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123159774A_ABST
    Figure CN123159774A_ABST
Patent Text Reader

Abstract

This invention discloses a distributed photovoltaic (PV) grid-connection adaptability assessment method based on multi-scenario joint probability. The method includes: acquiring distribution network operating parameters; clustering distributed power source output data and load data to generate multiple typical scenarios and construct a joint scenario set; establishing a probabilistic security constraint model, describing the safe operating boundary with an explicit confidence level; establishing a comprehensive economic benefit constraint model, where the economic benefit constraint includes at least grid connection revenue, grid loss cost, and curtailment penalty cost components; and using the maximization of distributed power source access capacity as the optimization objective, solving the power flow equations using second-order cone relaxation under the condition of satisfying the constraint model to obtain the grid-connection adaptability assessment results. This method overcomes the overly conservative shortcomings of traditional rigid constraints, achieving synergistic optimization of security, economy, and computational efficiency, and providing reliable technical support for distributed PV planning in distribution networks.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of distribution network planning technology, and in particular to a method for evaluating the grid-connected adaptability of distributed photovoltaic power based on multi-scenario joint probability. Background Technology

[0002] With the deepening implementation of the "dual carbon" goals, the installed capacity of new energy power generation, represented by distributed photovoltaic (PV), has continued to grow rapidly and has become an important component of the new power system. At the same time, large-scale distributed PV grid connection has profoundly changed the traditional unidirectional radial power supply structure of the distribution network, bringing a series of problems such as node voltage exceeding limits, line power flow backflow, transmission congestion, and local absorption difficulties, posing a severe challenge to the safe and stable operation of the distribution network. Therefore, how to scientifically assess the grid adaptability of the distribution network to distributed PV during the planning and operation phases, and quantitatively determine the maximum permissible capacity for PV, has become a key technical problem that urgently needs to be solved.

[0003] Currently, there are some research results on the adaptability assessment and access capacity calculation for distributed photovoltaic (PV) grid integration. In terms of scenario construction, a typical approach is to obtain historical solar irradiance and load data for the distribution network area, and then use clustering algorithms to cluster the time-series curves of PV output and load into several typical operating scenarios and their probabilities. Based on this, a joint scenario set of PV and load is constructed to cover various operating conditions throughout the year. Commonly used clustering methods include K-means clustering and its improved algorithms, such as using the silhouette coefficient or elbow method to determine the optimal number of clusters to improve the rationality of scenario division. Regarding evaluation models, existing methods typically aim to maximize the capacity of distributed PV grid integration, establishing optimization models with power flow equation constraints and safety constraints such as node voltage and branch current. The maximum access capacity of PV is obtained by solving the model. To address the randomness of PV output and load, some methods introduce probabilistic constraints, such as calculating the comprehensive voltage compliance rate based on the probability statistics of voltage exceedances in multiple scenarios, and using a compliance rate not lower than the assessment indicator as a constraint. In terms of solution techniques, existing methods employ a variety of solution strategies, including genetic algorithms and half-step repetitive power flow methods.

[0004] However, the above-mentioned existing technical solutions still have the following shortcomings:

[0005] In handling safety constraints, existing methods mostly employ rigid constraints (such as mandatory voltage upper and lower limits) or compliance rate constraints based on statistics of the number of times limits are exceeded. Rigid constraints require that limits not be exceeded at any time. Due to the extremely low probability of extreme operating conditions in distribution networks, this often leads to overly conservative assessment results, severely limiting the effective integration of distributed photovoltaic systems. On the other hand, compliance rate constraints based on statistics of the number of times limits are ex-post statistical assessments. They cannot be explicitly expressed in optimization models as probabilistic constraints with clear confidence level requirements, lack rigorous mathematical forms, and are difficult to accurately quantify the decision-maker's tolerance for different levels of safety risks.

[0006] In setting evaluation objectives, most existing methods only take maximizing photovoltaic (PV) grid connection capacity as a single goal, lacking a systematic assessment of the comprehensive economic benefits of distributive PV grid connection. Distributed PV grid connection involves multiple economic factors, including grid connection revenue, changes in grid losses, and construction and operation costs. Simply pursuing capacity maximization may lead to poor overall economic efficiency. In particular, appropriate curtailment can significantly improve the distribution network's ability to absorb distributed PV, but existing methods lack in-depth modeling of the quantitative trade-off between the economic benefits of curtailment and the cost of curtailment penalties, making it difficult to achieve an optimal balance between security and economy.

[0007] In terms of solution efficiency, the adaptive assessment of distributed photovoltaic grid connection is essentially a large-scale non-convex nonlinear optimization problem. This problem size increases dramatically, especially when considering multiple scenarios throughout the year, source-load uncertainties, and various control measures. Existing methods, such as heuristic methods like genetic algorithms or half-step repetitive power flow methods, suffer from low solution efficiency, lack of convergence guarantee, and difficulty in ensuring global optimality. These methods fail to meet the computational efficiency and solution accuracy requirements of real-world large-scale distribution network planning scenarios. Summary of the Invention

[0008] To address the shortcomings of the prior art, this invention proposes a distributed photovoltaic (PV) grid-connection adaptability assessment method based on multi-scenario joint probability. This method overcomes the deficiencies of traditional rigid constraints and statistical qualification rate indicators by establishing a probabilistic security constraint model with explicit confidence levels, achieving precise quantification of safety margins. Furthermore, it constructs a comprehensive economic benefit constraint model encompassing multiple economic components such as grid connection revenue, grid loss costs, construction and operation costs, and curtailment penalty costs, achieving synergistic optimization of distributed PV access security and economy. Finally, by introducing convex relaxation techniques, the original non-convex problem is transformed into a convex optimization problem, which is solved using efficient numerical algorithms. This significantly improves computational efficiency while ensuring solution accuracy, providing scientific and reliable technical support for the grid-connection adaptability assessment of distributed PV in distribution networks.

[0009] To achieve the above-mentioned technical objectives, the present invention provides the following technical solution:

[0010] This invention proposes a distributed photovoltaic grid-connection adaptability assessment method based on multi-scenario joint probability, comprising:

[0011] A distributed photovoltaic grid-connected adaptability assessment method based on multi-scenario joint probability, characterized by comprising:

[0012] Obtain the operating parameters of the distribution network, including distributed generation output data and load data;

[0013] Multiple operating scenarios are constructed based on the operating parameters, and the probability of occurrence of each operating scenario is determined.

[0014] A probabilistic security constraint model for the distribution network is established, which is used to describe the safe operation boundary of the distribution network in probabilistic form.

[0015] A comprehensive economic benefit constraint model for the distribution network is established. This model is used to characterize the economic feasibility conditions of the distribution network after the integration of distributed power sources.

[0016] With the goal of maximizing the capacity of distributed generation access in the distribution network, the optimization objective is solved under the conditions of satisfying the probabilistic security constraint model and the comprehensive economic benefit constraint model, so as to obtain the evaluation results of the grid adaptability of the distribution network to distributed generation.

[0017] Furthermore, the constraints in the probabilistic security constraint model are expressed in the form of chance constraints:

[0018] ;

[0019] in, A vector of decision variables; A vector of random variables; For the first One safety constraint function; This is the preset confidence level; This represents the probability that an event is true.

[0020] Among them, confidence level The value ranges from 0.95 to 0.99.

[0021] Furthermore, the probabilistic security constraint model includes at least one of the following constraints:

[0022] Node voltages will be subject to constraints:

[0023] ;

[0024] Branch current opportunity constraints:

[0025] ;

[0026] and at least one of the following: power exchange constraints at the distribution gateway interface:

[0027] ;

[0028] ;

[0029] in, For nodes voltage amplitude, These are the minimum and maximum allowable values ​​for the node voltage, respectively. branch road The current amplitude, These are the minimum and maximum allowable values ​​for the branch current, respectively. This is a preset confidence level, typically set to 0.95~0.99; This represents the probability that an event is true. These are the active and reactive power exchanged between the distribution gateway and the upstream power grid, respectively. These are the corresponding upper and lower limits; This is the preset confidence level.

[0030] Furthermore, multiple operational scenarios are constructed based on operational parameters, and the probability of occurrence for each operational scenario is determined, including:

[0031] Clustering was performed on the output data and load data of distributed power sources to obtain multiple typical power source scenarios and multiple typical load scenarios, and the occurrence probability of each typical power source scenario and each typical load scenario was determined.

[0032] Multiple typical power supply scenarios and multiple typical load scenarios are combined to generate multiple joint operation scenarios;

[0033] Based on the occurrence probabilities of typical power supply scenarios and typical load scenarios, the joint probability of each joint operation scenario is determined:

[0034] ;

[0035] And it satisfies:

[0036]

[0037] in, For the first The probability of occurrence of a typical power supply scenario; For the first The probability of a typical load scenario occurring; For the first A typical power supply scenario and the first The joint probability of a combined operation scenario formed by a combination of typical load scenarios; This represents the total number of typical power supply scenarios; This represents the total number of typical load scenarios.

[0038] Furthermore, the comprehensive economic benefit constraint model includes at least one of the following economic components:

[0039] Solar grid connection revenue :

[0040] ;

[0041] in, For grid connection electricity price; This represents the total number of typical power supply scenarios; This represents the total number of typical load scenarios; For joint scenarios At any moment The actual grid-connected power of photovoltaic power, This represents the probability of this joint scenario occurring;

[0042] Network loss cost :

[0043] ;

[0044] ;

[0045] in, These represent the grid loss costs before and after photovoltaic (PV) grid connection; For network loss costs; The cost coefficient per unit of network loss electricity. It is the collection of all branches of the distribution network; branch road exist The current amplitude at a given moment; For time step;

[0046] Construction and maintenance costs of distributed power sources :

[0047] ;

[0048] ;

[0049] in, This refers to the total installed capacity of distributed photovoltaic power. Cost of photovoltaic construction per unit capacity; The discount rate; The expected economic payback period for a photovoltaic unit; Annual maintenance fee rate;

[0050] Energy storage construction costs :

[0051] ;

[0052] in, Total energy storage capacity; Cost of building energy storage per unit capacity; For the lifespan of energy storage devices;

[0053] Demand response compensation cost :

[0054] ;

[0055] in, These are peak electricity prices and off-peak electricity prices; For a moment Transferred load power;

[0056] Cost of power curtailment :

[0057] ;

[0058] in, The penalty price per unit of abandoned electricity; This refers to the amount of abandoned electricity.

[0059] The comprehensive economic benefit constraint model is used to limit the annual comprehensive return. Non-negative:

[0060] .

[0061] Furthermore, it also includes assessments of power curtailment:

[0062] The difference between the theoretical maximum output of distributed generation and the actual grid-connected power is defined as the curtailed power. :

[0063] ;

[0064] in, For joint scenarios At any moment The theoretical maximum output of distributed power sources; This represents the total installed capacity of distributed power sources.

[0065] According to the power of abandoned electricity Calculate the total curtailment rate :

[0066] ;

[0067] in, For joint scenarios The probability of occurrence;

[0068] Use the curtailment rate as an evaluation metric, and / or include the cost of curtailment penalties. Incorporating comprehensive economic benefit constraints into the model; curtailment penalty costs :

[0069] ;

[0070] in, The penalty price per unit of abandoned electricity.

[0071] Furthermore, the power flow equations of the distribution network are subjected to second-order cone relaxation treatment, including:

[0072] Define the auxiliary variable of the square of the node voltage. Branch current square auxiliary variable The non-convex constraints in the DistFlow power flow equations are:

[0073] ;

[0074] Relaxation is a second-order cone inequality:

[0075] ;

[0076] in, For nodes The voltage amplitude; branch road Current amplitude; Corresponding to branch roads Active power and reactive power flowing through; This represents the Euclidean norm of a vector.

[0077] Furthermore, the convex optimization problem is solved, including:

[0078] Transform the objective function and constraints into the standard second-order cone programming form:

[0079] ;

[0080] in, It is a second-order cone; To optimize the objective coefficient vector; A vector of decision variables; This is the constraint matrix; To constrain the right-hand vector;

[0081] The interior point method is used to iteratively solve the standard second-order cone programming form to obtain the optimal access capacity of each distributed power source access node.

[0082] Furthermore, it also includes:

[0083] Configure the distribution network with flexible regulation resources, including energy storage devices and / or transferable loads;

[0084] Establish an operational constraint model for flexibly adjusting resources:

[0085] The operational constraints for energy storage are:

[0086] ;

[0087] ;

[0088] ;

[0089] ;

[0090] in, For nodes Energy storage at time Storage capacity; For time step; These are energy storage charging efficiency and discharging efficiency, respectively. These are charging power and discharging power, respectively. These are the lower and upper limits of the state of charge, respectively; This refers to the rated capacity of the energy storage. These are the maximum charging and discharging power, respectively.

[0091] The timing transfer constraints for transferable loads are:

[0092] ;

[0093] ;

[0094] The operational constraint model of flexible resource adjustment is used as one of the constraints of the optimization objective;

[0095] in, For a moment Transferred load power; This represents the maximum transferred load power.

[0096] Furthermore, the distributed power source is a distributed photovoltaic power source, and the distribution network is a radial distribution network; the evaluation results include the optimal distributed power source access capacity, annual comprehensive revenue value, and / or curtailment rate of each node.

[0097] The present invention provides a distributed photovoltaic grid-connected adaptability assessment method based on multi-scenario joint probability, which has the following advantages compared with the prior art:

[0098] (1) The method introduces a chance constraint modeling approach, which expresses the security constraints in an explicit probabilistic form. This allows decision-makers to flexibly set the confidence level according to actual engineering needs, achieving a flexible balance between security and economy, and avoiding excessive restrictions on the evaluation results due to extremely low probability events. It overcomes the shortcomings of traditional methods that use rigid voltage and current upper and lower limit constraints, which lead to overly conservative evaluation results due to extremely low probability extreme operating conditions, severely limiting the rigid constraints on the effective access of distributed photovoltaic power.

[0099] (2) The method described above constructs a complete economic model that includes grid connection revenue, grid loss cost, construction and operation and maintenance cost, energy storage cost, demand response cost, and curtailment penalty cost. By quantitatively linking the curtailment rate index with the curtailment penalty cost, this invention effectively solves the problem of balancing the economics of curtailment.

[0100] (3) The method uses a second-order cone relaxation technique to transform the original non-convex problem into a convex optimization problem, enabling large-scale problems to obtain the global optimal solution in polynomial time. This provides efficient and reliable computational support for actual power distribution network planning and significantly improves the solution efficiency and accuracy. It overcomes the shortcomings of existing methods that use heuristic methods such as genetic algorithms, which have low solution efficiency, no guarantee of convergence, and difficulty in guaranteeing global optimality. Attached Figure Description

[0101] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0102] Figure 1 This is a flowchart of the distributed photovoltaic grid-connected adaptability assessment method based on multi-scenario joint probability provided in the embodiments of the present invention. Detailed Implementation

[0103] To make the objectives, technical solutions, and advantages of this invention clearer, the technical solutions of this invention will be described in detail below. Obviously, the described embodiments are merely some embodiments of this invention, and not all embodiments. Based on the embodiments of this invention, all other implementation methods obtained by those skilled in the art without creative effort are within the scope of protection of this invention.

[0104] Example 1

[0105] This embodiment provides a method for evaluating the grid-connected adaptability of distributed photovoltaic (PV) power grids based on multi-scenario joint probability. The method constructs a set of joint probability scenarios covering various operating conditions throughout the year, establishes a probabilistic security constraint model and a comprehensive economic benefit constraint model with explicit confidence levels, and solves the problem with the goal of maximizing the distributed PV access capacity, thereby achieving a comprehensive and accurate evaluation of the grid-connected adaptability of distributed PV power grids.

[0106] like Figure 1 As shown, the method in this embodiment mainly includes the following steps:

[0107] S1: Obtain the operating parameters of the distribution network, including distributed generation output data and load data.

[0108] The operating parameters include distributed photovoltaic power output data, load data, distribution network topology information, distributed photovoltaic access node information, and load node information.

[0109] Specifically, obtain historical hourly solar irradiance data for the area where the distribution network to be evaluated is located throughout the year. and historical load power data Each of these forms a daily sequence vector of light intensity. and load power daily sequence vector .,in, .

[0110] At the same time, basic data such as line impedance parameters, node load parameters, and transformer parameters of the distribution network are obtained for subsequent power flow calculations.

[0111] S2: Construct multiple operating scenarios based on operating parameters and determine the probability of occurrence of each operating scenario.

[0112] This embodiment employs an improved K-means clustering algorithm to cluster daily light intensity and daily load power sequences, respectively, generating typical scenarios and calculating their probabilities. The specific process includes:

[0113] S21: An improved K-means clustering algorithm is used to analyze the daily light intensity series. Clustering is performed. The silhouette coefficient is introduced to determine the optimal number of clusters. .

[0114] Sample points The formula for calculating the profile coefficient is:

[0115] ;

[0116] in, For sample points The average distance to other points in the same cluster. For sample points The minimum average distance to all points in other clusters.

[0117] The average profile coefficient for all sample points is:

[0118] ;

[0119] Choose to The largest K value is taken as the optimal number of clusters. By iteratively calculating the average silhouette coefficient corresponding to different K values, the K value corresponding to the largest value is selected as the optimal number of clusters.

[0120] Cluster the daily light intensity series into A typical scenario, each typical scenario It has a 24-hour time-series output curve And calculate the probability of this scenario occurring. ,in This represents the number of original scenes belonging to this cluster. Total number of scenes .

[0121] S22: Using the same method as in S21, analyze the daily load power sequence. Clustering is performed, and the optimal number of clusters is determined using the silhouette coefficient. The daily load power series is clustered into A typical scenario, each typical scenario It has a 24-hour time series curve The probability of occurrence is .

[0122] S23: Combine typical light intensity scenarios and typical load power scenarios using a Cartesian product to generate... A typical joint operation scenario. Each joint scenario probability for:

[0123] ;

[0124] And it satisfies:

[0125] ;

[0126] This joint scenario set covers a variety of typical operating conditions and their probability distributions throughout the year, serving as the basis for subsequent adaptive assessments.

[0127] S3: Establish a probabilistic security constraint model for the distribution network. The probabilistic security constraint model is used to describe the safe operation boundary of the distribution network in probabilistic form.

[0128] This embodiment uses chance constraints to describe the safe operation boundary of the distribution network, expressing the safety requirements of node voltage and branch current in probabilistic form.

[0129] First, an evaluation model is established with the objective of maximizing the total grid-connected capacity of distributed photovoltaic power. The objective function is:

[0130] ;

[0131] in, For nodes Configured distributed photovoltaic capacity, This represents the total number of nodes in the distribution network that are allowed to connect to distributed photovoltaic systems.

[0132] Opportunity constraints are introduced to address the uncertainties in photovoltaic output and load power, allowing short-term overruns under low-probability events:

[0133] Node voltages will be subject to constraints:

[0134] ;

[0135] Branch current opportunity constraints:

[0136] ;

[0137] in, For nodes voltage amplitude, These are the minimum and maximum allowable values ​​for the node voltage, respectively. branch road The current amplitude, These are the minimum and maximum allowable values ​​for the branch current, respectively. This is a preset confidence level, typically set to 0.95~0.99; This represents the probability that an event will occur.

[0138] Power distribution gateway switching power constraints:

[0139] ;

[0140] ;

[0141] in, These are the active and reactive power exchanged between the distribution gateway and the upstream power grid, respectively. These are the corresponding upper and lower limits; This is the preset confidence level.

[0142] The DistFlow branch power flow equations are used to describe the steady-state power flow in a distribution network. For branches in a radial distribution network... At any moment have:

[0143] ;

[0144] in, They are nodes At any moment The voltage amplitude; Branch roads Resistance, impedance; Branch roads Active power and reactive power flowing through the first end; They are nodes The injected active power and reactive power are equal to the distributed photovoltaic output of the node minus the load power. branch road The current amplitude.

[0145] S4: Establish a comprehensive economic benefit constraint model for the distribution network. The comprehensive economic benefit constraint model is used to characterize the economic feasibility conditions of the distribution network after the integration of distributed power sources.

[0146] This embodiment establishes a comprehensive economic benefit model that includes multiple economic components such as photovoltaic grid connection revenue, grid loss cost, photovoltaic construction and operation and maintenance cost, energy storage construction cost, demand response compensation cost, and curtailment penalty cost, with the constraint that the annual comprehensive revenue is non-negative.

[0147] Total annual income Represented as:

[0148] ;

[0149] The definitions and calculation formulas for each revenue component are as follows:

[0150] (1) Revenue from photovoltaic grid connection :

[0151] ;

[0152] in, For grid connection electricity price, For joint scenarios At any moment The actual grid-connected power of photovoltaic power, This represents the probability of this joint scenario occurring.

[0153] (2) Network loss cost :

[0154] ;

[0155] ;

[0156] in, These represent the grid loss costs before and after photovoltaic grid connection; For network loss costs; The cost coefficient per unit of network loss electricity. It is the collection of all branches of the distribution network; branch road exist The current amplitude at a given moment; For time step.

[0157] (3) Photovoltaic construction and operation and maintenance costs :

[0158] The average annual construction and operation and maintenance cost of photovoltaic units is calculated using the equivalent annual cost method, which converts the one-time construction investment into equivalent costs for each year within the planning period, and adds the annual operation and maintenance costs:

[0159] ;

[0160] ;

[0161] in, The total installed capacity of distributed photovoltaic power is equal to the sum of the installed capacities of all accessible nodes. The cost per unit capacity of photovoltaic construction includes all costs for photovoltaic modules, inverters, brackets, and installation. This is the discount rate, typically ranging from 0.05 to 0.10. The expected economic payback period for a photovoltaic unit is typically 20 to 25 years. The annual operation and maintenance fee rate (dimensionless) represents the proportion of annual operation and maintenance costs to the initial construction investment, and is usually taken as 0.01~0.03.

[0162] (4) Energy storage construction cost (When energy storage is configured):

[0163] ;

[0164] in, Total energy storage capacity; Cost of building energy storage per unit capacity; This refers to the lifespan of energy storage devices.

[0165] (5) Demand response compensation costs (When using demand response):

[0166] ;

[0167] in, These are peak electricity prices and off-peak electricity prices; For a moment Transferred load power.

[0168] (6) Cost of power curtailment penalty :

[0169] ;

[0170] in, The penalty price per unit of abandoned electricity; This refers to the amount of abandoned electricity.

[0171] The overall economic benefit constraint is:

[0172] ;

[0173] This constraint ensures that distributed photovoltaic (PV) grid connection schemes are economically feasible within the planning period.

[0174] Preferably, it further includes S4~5-1: configuring the flexibility adjustment resources of the distribution network, the flexibility adjustment resources including energy storage devices and / or transferable loads; establishing an operation constraint model of the flexibility adjustment resources, the operation constraint model including energy storage charging and discharging power constraints, energy storage state of charge constraints and / or time-series transfer constraints of transferable loads; and using the operation constraint model of the flexibility adjustment resources as one of the constraints of the optimization objective.

[0175] In practice, to enhance the adaptability of the distribution network to distributed photovoltaic power, this embodiment introduces active control measures, including reactive power regulation and active power regulation.

[0176] S4~5-1-1: Reactive power regulation. Based on real-time monitoring of the grid connection point voltage, the photovoltaic inverter is controlled to absorb or generate reactive power, employing a segmented control strategy.

[0177] ;

[0178] in, For real-time monitoring of grid connection point voltage; Dead zone boundary for reactive power regulation ( ); For the inverter's maximum reactive power capacity, satisfy , This refers to the rated capacity of the inverter. This is the maximum active power output of the inverter.

[0179] Reactive power regulation can output zero reactive power when the voltage is normal, provide reactive power support when the voltage is low, and absorb reactive power when the voltage is high, thereby suppressing voltage overshoot caused by excessive photovoltaic output.

[0180] S4~5-1-2: Active power regulation (energy storage configuration). Configure electrochemical energy storage devices to charge when photovoltaic output is sufficient and discharge when output is insufficient, thus smoothing out net load fluctuations.

[0181] The operational constraints for energy storage are:

[0182] ;

[0183] ;

[0184] ;

[0185] ;

[0186] in, For nodes Energy storage at time Storage capacity; For time step; These are energy storage charging efficiency and discharging efficiency, respectively. These are charging power and discharging power, respectively. These are the lower and upper limits of the state of charge, respectively; This refers to the rated capacity of the energy storage. These are the maximum charging and discharging power, respectively.

[0187] S4~5-1-3: Active power regulation (demand response). A response model based on time-of-use pricing is adopted to shift transferable loads from off-peak solar power output periods to peak periods, thereby improving solar power integration efficiency.

[0188] The timing transfer constraints for transferable loads are:

[0189] ;

[0190] ;

[0191] That is, the algebraic sum of the transferred loads throughout the day is zero (keeping the total electricity consumption constant), and the amount transferred at any given moment does not exceed the preset maximum transfer power. .

[0192] Preferably, it further includes S4~5-2: determining the difference between the theoretical maximum output of the distributed power source and the actual grid-connected power as the curtailed power; calculating the curtailment rate and curtailment penalty cost based on the curtailed power; outputting the curtailment rate as an evaluation indicator, and / or incorporating the curtailment penalty cost into the comprehensive economic benefit constraint model.

[0193] In the specific implementation of this embodiment, in each joint scenario In the middle, let the theoretical maximum photovoltaic output be Actual grid power The abandoned power is:

[0194] ;

[0195] Total curtailment rate Defined as:

[0196] ;

[0197] The curtailment rate is output as one of the evaluation indicators, and the cost of curtailment penalty is incorporated into the comprehensive economic benefit constraint model.

[0198] S5: Taking the maximization of distributed generation access capacity of the distribution network as the optimization objective, under the conditions of satisfying the probabilistic security constraint model and the comprehensive economic benefit constraint model, the optimization objective is solved to obtain the grid adaptability assessment results of the distribution network to distributed generation.

[0199] The comprehensive optimization model is as follows:

[0200] ;

[0201] The constraints include:

[0202] .

[0203] To improve solution efficiency, this embodiment applies convex relaxation to the non-convex quadratic equality constraints in the power flow equations. The specific process is as follows:

[0204] Define the auxiliary variable of the square of the node voltage. Auxiliary variable: square of branch current The non-convex constraints in the DistFlow power flow equations are:

[0205] ;

[0206] Relaxation is a second-order cone inequality:

[0207] ;

[0208] in, Let represent the Euclidean norm of the vector. This relaxation is exact under the condition that the objective function is convex and the constraint set is conical, i.e., the equality holds at the optimal solution.

[0209] The original non-convex problem is transformed into the following second-order cone programming problem:

[0210] ;

[0211] ;

[0212] The interior-point method is used to solve the above second-order cone programming model. The objective function and constraints are transformed into the standard second-order cone programming form:

[0213] ;

[0214] in, It is a second-order cone; To optimize the objective coefficient vector; A vector of decision variables; This is the constraint matrix; To constrain the vector on the right.

[0215] The optimal distributed photovoltaic (PV) grid connection capacity for each node is obtained by iteratively solving a numerical optimization algorithm based on the primal-dual interior-point method. Total revenue Total curtailment rate Including voltage and current distribution in various scenarios, thereby enabling a comprehensive assessment of the distribution network's adaptability to distributed photovoltaic grid connection.

[0216] Example 2

[0217] The main difference between this embodiment and Embodiment 1 is that the distribution network in this embodiment is not equipped with energy storage devices, nor are demand response measures adopted. In this case, only reactive power regulation strategies are implemented in S4~5-1. , .

[0218] Due to a lack of energy storage and demand response capabilities, the adaptability of distribution networks to distributed photovoltaic (PV) power is relatively reduced. The maximum grid-connected capacity is obtained by solving for this. Smaller than Example 1, with better overall economic benefits This is also correspondingly reduced. This embodiment is mainly used to evaluate the baseline adaptability of the distribution network to distributed photovoltaics without configuring flexibility resources.

[0219] Example 3

[0220] The main difference between this embodiment and Embodiment 1 is that the confidence level in this embodiment is... This means adopting a higher level of security confidence.

[0221] A higher confidence level implies stricter safety constraints, requiring the system to guarantee that safety indicators such as voltage and current do not exceed limits with a 99% probability. Therefore, the calculated photovoltaic grid connection capacity is relatively conservative, but the safety margin for grid operation is higher.

[0222] This embodiment is applicable to regional power distribution networks with high requirements for power supply reliability, such as power distribution areas containing important users.

[0223] Example 4

[0224] The main difference between this embodiment and Embodiment 1 is that the abandoned electricity penalty price in this embodiment... Setting it to a low value (0.1 yuan / kWh) is far below the grid connection price. .

[0225] A lower curtailment penalty price means a lower economic cost for appropriate solar curtailment, and the optimization model tends to allow more curtailment in exchange for larger photovoltaic grid connection capacity. The solution results show that the maximum grid connection capacity in this embodiment is higher than that in Embodiment 1, but the curtailment rate is lower. The corresponding increase.

[0226] This embodiment quantifies the impact of the economic trade-off between curtailment and photovoltaic grid connection capacity by adjusting the curtailment penalty price, providing a decision-making reference for distribution network planning under different curtailment tolerance levels.

[0227] Example 5

[0228] The main difference between this embodiment and embodiment 1 is that the scene clustering in this embodiment adopts a method of clustering each season separately.

[0229] Specifically, the annual data is clustered according to the four seasons of spring, summer, autumn, and winter, and the optimal number of clusters is determined independently for each season. and Each season's combined scene set is generated separately.

[0230] Significant differences exist in light intensity and load characteristics across seasons: summer sees high light intensity but also high load (air conditioning load), while winter sees low light intensity but may still have a relatively high load (heating load). Separate clustering can more accurately reflect the operational characteristics of each season and improve assessment precision.

[0231] In this embodiment, the total number of joint scenarios throughout the year is the sum of the number of joint scenarios in each season:

[0232] ;

[0233] Probability of joint scenarios in each season:

[0234] ;

[0235] in, This represents the total number of days in the season.

[0236] It is understood that the same or similar parts in the above embodiments can be referred to each other, and the contents not described in detail in some embodiments can be referred to the same or similar contents in other embodiments.

[0237] Although embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and should not be construed as limiting the present invention. Those skilled in the art can make changes, modifications, substitutions and variations to the above embodiments within the scope of the present invention.

Claims

1. A distributed photovoltaic grid-connected adaptability assessment method based on multi-scenario joint probability, characterized in that, include: Obtain the operating parameters of the distribution network, including distributed generation output data and load data; Multiple operating scenarios are constructed based on the operating parameters, and the probability of occurrence of each operating scenario is determined. A probabilistic security constraint model for the distribution network is established, which is used to describe the safe operation boundary of the distribution network in probabilistic form. A comprehensive economic benefit constraint model for the distribution network is established. This model is used to characterize the economic feasibility conditions of the distribution network after the integration of distributed power sources. With the goal of maximizing the capacity of distributed generation access in the distribution network, the optimization objective is solved under the conditions of satisfying the probabilistic security constraint model and the comprehensive economic benefit constraint model, so as to obtain the evaluation results of the grid adaptability of the distribution network to distributed generation.

2. The method according to claim 1, characterized in that, The constraints in the probabilistic security constraint model are expressed in the form of chance constraints: ; in, A vector of decision variables; A vector of random variables; For the first One safety constraint function; This is the preset confidence level; This represents the probability that an event is true. Among them, confidence level The value ranges from 0.95 to 0.

99.

3. The method according to claim 1, characterized in that, The probabilistic security constraint model includes at least one of the following constraints: Node voltages will be subject to constraints: ; Branch current opportunity constraints: ; and at least one of the following: power exchange constraints at the distribution gateway interface: ; ; in, For nodes voltage amplitude, These are the minimum and maximum allowable values ​​for the node voltage, respectively. branch road The current amplitude, These are the minimum and maximum allowable values ​​for the branch current, respectively. This is a preset confidence level, typically set to 0.95~0.99; This represents the probability that an event is true. These are the active and reactive power exchanged between the distribution gateway and the upstream power grid, respectively. These are the corresponding upper and lower limits; This is the preset confidence level.

4. The method according to claim 1, characterized in that, Multiple runtime scenarios are constructed based on runtime parameters, and the probability of occurrence for each scenario is determined, including: Clustering was performed on the output data and load data of distributed power sources to obtain multiple typical power source scenarios and multiple typical load scenarios, and the occurrence probability of each typical power source scenario and each typical load scenario was determined. Multiple typical power supply scenarios and multiple typical load scenarios are combined to generate multiple joint operation scenarios; Based on the occurrence probabilities of typical power supply scenarios and typical load scenarios, the joint probability of each joint operation scenario is determined: ; And it satisfies: ; in, For the first The probability of occurrence of a typical power supply scenario; For the first The probability of a typical load scenario occurring; For the first A typical power supply scenario and the first The joint probability of a combined operation scenario formed by a combination of typical load scenarios; This represents the total number of typical power supply scenarios; This represents the total number of typical load scenarios.

5. The method according to claim 1, characterized in that, The comprehensive economic benefit constraint model includes at least one of the following economic components: Solar grid connection revenue : ; in, For grid connection electricity price; This represents the total number of typical power supply scenarios; This represents the total number of typical load scenarios; For joint scenarios At any moment The actual grid-connected power of photovoltaic power, This represents the probability of this joint scenario occurring; Network loss cost : ; ; in, These represent the grid loss costs before and after photovoltaic (PV) grid connection; For network loss costs; The cost coefficient per unit of network loss electricity. It is the collection of all branches of the distribution network; branch road exist The current amplitude at a given moment; For time step; Construction and maintenance costs of distributed power sources : ; ; in, This refers to the total installed capacity of distributed photovoltaic power. Cost of photovoltaic construction per unit capacity; The discount rate; The expected economic payback period for a photovoltaic unit; Annual maintenance fee rate; Energy storage construction costs : ; in, Total energy storage capacity; Cost of building energy storage per unit capacity; For the lifespan of energy storage devices; Demand response compensation cost : ; in, These are peak electricity prices and off-peak electricity prices; For a moment Transferred load power; Cost of power curtailment : ; in, The penalty price per unit of abandoned electricity; This refers to the amount of abandoned electricity. The comprehensive economic benefit constraint model is used to limit the annual comprehensive return. Non-negative: 。 6. The method according to claim 1, characterized in that, It also includes power curtailment assessment: The difference between the theoretical maximum output of distributed generation and the actual grid-connected power is defined as the curtailed power. : ; in, For joint scenarios At any moment The theoretical maximum output of distributed power sources; This represents the total installed capacity of distributed power sources. According to the power of abandoned electricity Calculate the total curtailment rate : ; in, For joint scenarios The probability of occurrence; Use the curtailment rate as an evaluation metric, and / or include the cost of curtailment penalties. Incorporating comprehensive economic benefit constraints into the model; curtailment penalty costs : ; in, The penalty price per unit of abandoned electricity.

7. The method according to claim 1, characterized in that, The power flow equations of the distribution network are subjected to second-order cone relaxation treatment, including: Define the auxiliary variable of the square of the node voltage. Branch current square auxiliary variable The non-convex constraints in the DistFlow power flow equations are: ; Relaxation is a second-order cone inequality: ; in, For nodes The voltage amplitude; branch road Current amplitude; Corresponding to branch roads Active power and reactive power flowing through; This represents the Euclidean norm of a vector.

8. The method according to claim 7, characterized in that, Solving convex optimization problems includes: Transform the objective function and constraints into the standard second-order cone programming form: ; in, It is a second-order cone; To optimize the objective coefficient vector; A vector of decision variables; This is the constraint matrix; To constrain the right-hand vector; The interior point method is used to iteratively solve the standard second-order cone programming form to obtain the optimal access capacity of each distributed power source access node.

9. The method according to claim 1, characterized in that, Also includes: Configure the distribution network with flexible regulation resources, including energy storage devices and / or transferable loads; Establish an operational constraint model for flexibly adjusting resources: The operational constraints for energy storage are: ; ; ; ; in, For nodes Energy storage at time Storage capacity; For time step; These are energy storage charging efficiency and discharging efficiency, respectively. These are charging power and discharging power, respectively. These are the lower and upper limits of the state of charge, respectively; This refers to the rated capacity of the energy storage. These are the maximum charging and discharging power, respectively. The timing transfer constraints for transferable loads are: ; ; The operational constraint model of flexible resource adjustment is used as one of the constraints of the optimization objective; in, For a moment Transferred load power; This represents the maximum transferred load power.

10. The method according to claim 1, characterized in that, The distributed power source is a distributed photovoltaic power source, and the distribution network is a radial distribution network; the evaluation results include the optimal distributed power source access capacity, annual comprehensive revenue value and / or curtailment rate of each node.