A method for verifying an ANFO delay material

By acquiring and updating relevant data for safety production license extension applications, unifying time benchmarks, and adjusting verification personnel and configuration requirements, the problem of discrepancies between verification results and actual conditions during the extension application process was resolved, resulting in more accurate and efficient verification.

CN123160100APending Publication Date: 2026-11-24WUHAN SHAOBO INFORMATION CONSULTING CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202611403102.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-10
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

In the current process of applying for the renewal of safety production licenses, verifying the materials based on their status at the time of application can easily lead to discrepancies between the verification results and the actual status after the approval process, resulting in staffing shortages and an increased likelihood of subsequent corrections.

Method used

By obtaining data on licenses, personnel qualifications, social insurance, certifications, and approval time for enterprise extension applications, recording the period, update time, and source according to the entity identifier, refreshing overdue data, unifying the time benchmark, determining the time range for licensing decisions, and adjusting the verification personnel and configuration requirements based on the approval process and historical processing time, re-verification is conducted when changes occur.

Benefits of technology

This improved the accuracy and consistency of verification materials for the extension of safety production licenses, reduced omissions due to data changes, and enhanced verification efficiency and the orderly processing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123160100A_ABST
    Figure CN123160100A_ABST
Patent Text Reader

Abstract

This invention relates to the field of government data processing technology and discloses a method for verifying materials for the extension of safety production licenses. The method first acquires data on enterprise licenses, personnel qualifications, social insurance, enterprise qualifications, and licensing procedures. It then updates the relevant data according to the data update cycle and determines the time frame for the licensing decision by combining the work calendar, historical processing time, pending status, and correction time. The method then correlates the personnel qualification period, social insurance status, and qualification changes with the time frame, verifies the number of personnel and configuration requirements for different personnel categories and job types, and handles matters with approaching deadlines, pending status, or insufficient personnel. When materials are corrected or personnel or qualification status changes, the affected data is re-verified, thereby improving the accuracy and efficiency of verifying materials for the extension of safety production licenses.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of government data processing technology, specifically a method for verifying materials for granting extensions. Background Technology

[0002] When construction companies apply for the renewal of their safety production licenses, they typically need to verify materials such as the license's validity period, relevant personnel qualification certificates, social insurance payment status, company qualifications, and staffing levels to determine whether the company meets the relevant requirements for the renewal application. Existing material verification methods usually involve reading and comparing document information, personnel information, and company-submitted information when the application materials are submitted or accepted, and judging whether the materials are complete, the documents are valid, and the staffing meets regulations based on the data obtained at that time. For example, authorized Chinese invention patent application CN116681628B discloses a business license data processing method and system based on deep learning, which improves the accuracy of license information extraction and data completion by processing and verifying business license images. Another example is authorized Chinese invention patent application CN112215225B, which discloses a KYC document verification method based on computer vision technology, which verifies document information through document image preprocessing and feature point comparison. These technologies can improve the efficiency of license information reading, recognition, and verification, but they mainly focus on processing the licenses or identity information obtained during verification.

[0003] However, the application process for extending a safety production license typically involves a certain approval process from submission of materials to the issuance of the license decision. During this period, issues such as material supplementation and review waiting may occur, extending the actual approval time. Furthermore, personnel qualification certificates may expire, social insurance payment status may change, and changes in enterprise qualifications may alter corresponding personnel requirements. Simultaneously, different business systems have different update cycles for licenses, social insurance, and personnel information, meaning the data obtained at the time of application may have changed during the subsequent approval process. Therefore, relying solely on the status of the application materials at the time of submission can easily lead to situations where the application met the requirements, but the personnel qualifications, social insurance status, or personnel configuration no longer meet the requirements at the time of the license decision. This results in the initial verification results failing to accurately reflect the actual situation after the approval process, increasing the possibility of overlooking personnel configuration gaps and subsequent corrections. Therefore, accurately determining whether an enterprise still meets the personnel configuration requirements at the time of the license decision based on changes in relevant materials and personnel status during the approval process is a technical problem that needs to be addressed in the current verification process for safety production license extension materials. Summary of the Invention

[0004] To address the shortcomings of existing technologies, this invention provides a method for verifying safety-permitted materials, which solves the problems mentioned in the background section.

[0005] To achieve the above objectives, the present invention provides the following technical solution:

[0006] Obtain data on licenses, personnel qualifications, social insurance, certifications, and approval time for enterprise extension applications, and record the duration, update time, and source by entity identifier;

[0007] Overdue data is refreshed according to the data source update cycle, the time base of natural days and working days is unified, and the time range corresponding to the permit decision is determined based on the approval process, historical processing time, pending status and correction time.

[0008] By mapping the eligibility period and social insurance status of personnel to the aforementioned time range, the personnel eligible to participate in the verification are determined;

[0009] The qualification change status is matched with the time range to determine the personnel configuration requirements, and the available personnel are checked against the configuration requirements according to personnel category and job type.

[0010] Arrange rectification for matters with approaching deadlines, questionable status, or insufficient personnel; when corrections, changes in personnel status, or qualification status occur, re-verify from the affected step.

[0011] Furthermore, obtain data on the company's licenses, personnel qualifications, social insurance, certifications, and approval time for the extension application, including:

[0012] Based on enterprise identifiers, enterprise information is matched from different data sources; based on personnel identity identifiers, personnel qualification information, social insurance information, and enterprise personnel information are matched.

[0013] The information includes the validity period of the license, the qualification period of personnel and their corresponding job types, social insurance payment records, enterprise qualifications and qualification change status, as well as the processing steps, processing time, historical processing time and current pending data for the licensing matters.

[0014] Furthermore, the record period, update time, and source are categorized by subject identifier, including:

[0015] The date field format should be standardized according to the field descriptions of each data source, while retaining the original field format.

[0016] When the same data has multiple sources, the data to be used is determined according to the preset data source order;

[0017] When data from different sources differs and such differences affect whether personnel should be included or personnel allocation requirements, the corresponding data will be marked as pending confirmation.

[0018] Record the data source, the data source's most recent update time, the time this data was read, and the data version;

[0019] When data returned from the same data source changes, a new data version is created while the original data version is retained.

[0020] Furthermore, overdue data is refreshed according to the data source update cycle, and the time base for calendar days and working days is unified, including:

[0021] Read the current work calendar of the application location, determine the corresponding Gregorian calendar date for the processing period of the permit matter based on the work calendar, record the expiration of personnel qualifications, changes in social insurance status, changes in enterprise qualification status, and material supplementation time according to natural days, and convert them into the corresponding Gregorian calendar date;

[0022] The update cycle of each data source is determined based on the data interface description, data synchronization configuration, or operation records;

[0023] When the data update time exceeds the corresponding update cycle, the corresponding data is retrieved again;

[0024] When the status of personnel qualifications, social insurance, enterprise qualifications, or other data that affects verification changes, a new data version shall be created.

[0025] If re-acquiring fails, other data sources will be called to retrieve the corresponding data according to the preset data source order.

[0026] Furthermore, the time frame corresponding to the licensing decision is determined based on the approval process, historical processing time, pending status, and time for correction, including:

[0027] Select historical cases that have the same processing steps and procedures as the current licensing matter, sort them according to the actual processing time, and obtain the corresponding earlier and later processing times;

[0028] The actual or expected date of acceptance is used as the starting date. The processing time is mapped to the specific Gregorian calendar date according to the working calendar of the application location. The earlier and later dates of the permit decision are adjusted based on the current pending status and the time for correction.

[0029] When actual rectification occurs, the earlier date and the later date of the licensing decision shall be re-determined based on the actual elapsed time of the rectification.

[0030] If historical application data is insufficient, waiting time cannot be determined, or there are anomalies in the historical records, the later date of the permit decision shall be determined based on the currently applicable processing period.

[0031] Furthermore, by mapping the eligibility period and social insurance status to the aforementioned time frame, the personnel eligible for verification are identified, including:

[0032] Obtain personnel qualification records and social insurance records according to personnel identification, and read the corresponding personnel category or special operation type;

[0033] The start and end dates of the qualification certificate are matched with the time frame of the licensing decision, and the personnel relationship is verified according to the month of payment and the paying unit.

[0034] When a qualification certificate matching the corresponding personnel category or job type covers the time range and the personnel relationship conforms to the current verification rules, the corresponding personnel will be marked as eligible personnel.

[0035] When the same person holds multiple qualification certificates, each qualification certificate shall be evaluated separately.

[0036] If the eligibility status or personnel relationship cannot be confirmed, the corresponding personnel record will be marked as pending confirmation.

[0037] Furthermore, by mapping the qualification change status to the aforementioned time range, personnel allocation requirements are determined, including:

[0038] Obtain the company's current qualifications, ongoing qualification changes, and current valid staffing standards;

[0039] Compare the expected completion date or effective date of the qualification change with the time frame of the licensing decision;

[0040] Obtain the personnel configuration requirements before and after the qualification change, and compare them item by item according to personnel category and special operation type;

[0041] If the expected completion date or effective date cannot be determined, the higher value among the required number of personnel for the same personnel category or job type shall be used, and the qualification change status and personnel configuration standard version shall be recorded.

[0042] Furthermore, the available personnel and configuration requirements are checked according to personnel category and job type, including:

[0043] The number of personnel who can be counted should be counted separately according to personnel category and special operation type, and compared with the corresponding personnel configuration requirements item by item;

[0044] Different personnel categories and different job types should be checked separately, and personnel from other categories or job types should not be used to supplement the list;

[0045] Personnel awaiting confirmation are recorded separately and are not included in the already confirmed count.

[0046] When the number of eligible personnel is lower than the staffing requirements, the number of missing personnel shall be determined based on the difference between the two.

[0047] When the status of personnel qualifications or enterprise qualifications changes, the number of personnel and personnel configuration requirements for the corresponding personnel category or job type shall be re-verified according to the changed status.

[0048] Furthermore, rectification measures will be arranged for matters with approaching deadlines, questionable status, or insufficient personnel, including:

[0049] For situations where the qualification certificate cannot cover the time frame of the licensing decision, the personnel's qualifications or social insurance are pending confirmation, or the number of people that can be included does not exceed the personnel configuration requirements, separate handling items shall be formed;

[0050] Based on the later date of the permit decision, the latest date for initiating the process is determined by deducting the processing time and time leeway for the corresponding matters.

[0051] The processing items are sorted according to the latest start date. If the dates are the same, the processing order is determined based on the availability of personnel and the processing time of the corresponding items.

[0052] Furthermore, when corrections, personnel status, or qualification status change, verification will be re-evaluated from the affected step, including:

[0053] When material corrections actually occur, the time range of the permit decision is updated based on the actual correction time, and the personnel qualifications and personnel configuration data affected by the change in the time range are re-verified;

[0054] When there is a resignation of an employee, a change in the social insurance payment unit, a change in the employee's eligibility status, or the addition of a new employee, the corresponding eligibility data and social insurance data of the employee will be re-acquired.

[0055] When the enterprise's qualification status, expected completion date, or effective date changes, the personnel allocation requirements should be re-determined.

[0056] When enterprises submit new personnel qualification certificates, social insurance materials or other relevant materials, the corresponding items should be re-verified based on the updated data.

[0057] Compared with the prior art, the present invention provides a method for verifying safety-delayed materials, which has the following beneficial effects:

[0058] 1. This invention, by linking enterprise safety production licenses, personnel qualifications, social insurance, enterprise qualifications, and licensing data, re-acquires the data that needs updating according to the update cycle of different data sources, and determines the time range for licensing decisions by combining the application location's work calendar, historical processing time, current pending status, and material supplementation time. Based on this, it correlates the validity period of personnel qualifications, social insurance status, and changes in enterprise qualifications with the time range for licensing decisions, verifies the number of personnel that can be counted and the personnel configuration requirements according to personnel categories and special operation types, and re-verifies the affected data when materials are supplemented, personnel leave, social insurance payment units change, personnel qualification status changes, or enterprise qualifications change. This reduces deviations caused by verifying only static data at the time of application submission, and avoids missing personnel configuration changes due to personnel qualification expiration, changes in personnel relationships, qualification adjustments, and inconsistent update times of different data sources during the approval period. This ensures that the verification results correspond to the actual status during the licensing process and at the time of the licensing decision, improving the accuracy and consistency of verification of materials for safety production license extensions.

[0059] 2. This invention, by forming corresponding processing items based on the validity period of personnel qualification certificates, social insurance status, and personnel allocation, uses the later date of the permit decision as a benchmark, combined with the processing time and time leeway for each item to determine the latest processing start date, and determines the processing order according to the latest processing start date, personnel shortage, and processing time. When an enterprise supplements personnel qualification certificates or social insurance materials, or when there are changes in materials, personnel status, or enterprise qualifications, only the data affected by the changes is re-acquired and verified. Data whose versions have not changed and still meet the current verification conditions are continued to be used. At the same time, the current status and actual processing status of each processing item are recorded, thereby facilitating the orderly handling of problems related to personnel qualifications, social insurance, and personnel allocation before the permit decision is made, reducing the repeated acquisition and verification of unchanged data, reducing the amount of repetitive processing during the permit processing period, and improving the efficiency of processing and dynamic review of extension application materials. Attached Figure Description

[0060] Figure 1 This is a schematic diagram of the process for verifying materials for safety permit extension according to the present invention;

[0061] Figure 2 This is a schematic diagram of the multi-source data acquisition and correlation processing flow of the present invention;

[0062] Figure 3 This is a schematic diagram illustrating the determination of the time range for data updates and licensing decisions in this invention.

[0063] Figure 4 This is a schematic diagram illustrating the joint verification of the qualifications and social insurance of the personnel involved in this invention.

[0064] Figure 5 This is a schematic diagram illustrating the personnel configuration verification process in the event of a change in the qualifications of this invention.

[0065] Figure 6 This is a schematic diagram illustrating the closed-loop process of generating and re-verifying changes to the processing items in this invention. Detailed Implementation

[0066] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0067] Example 1: Figure 1 - Figure 6 A method for verifying application materials for extension of security permits is presented, including:

[0068] Obtain data on licenses, personnel qualifications, social insurance, certifications, and approval time for enterprise extension applications, and record the duration, update time, and source by entity identifier;

[0069] Overdue data is refreshed according to the data source update cycle, the time base of natural days and working days is unified, and the time range corresponding to the permit decision is determined based on the approval process, historical processing time, pending status and correction time.

[0070] By mapping the eligibility period and social insurance status of personnel to the aforementioned time range, the personnel eligible to participate in the verification are determined;

[0071] The qualification change status is matched with the time range to determine the personnel configuration requirements, and the available personnel are checked against the configuration requirements according to personnel category and job type.

[0072] Arrange rectification for matters with approaching deadlines, questionable status, or insufficient personnel; when corrections, changes in personnel status, or qualification status occur, re-verify from the affected step.

[0073] This embodiment is applicable to the verification of application materials for the extension of the safety production license of construction enterprises before its expiration. It can also be used for verification before the licensing authority accepts the application, review during the extension application process, and batch verification of enterprises to be extended by the government service platform. The method can be executed by a server, government cloud platform, licensing authority business system or other electronic equipment with data processing, data storage and data interaction functions.

[0074] Electronic devices can acquire data submitted by enterprises and, depending on the data access situation, obtain the data required for verification from electronic certificate systems, construction market supervision systems, social insurance systems, market entity registration systems, relevant issuing authority systems, and licensing matters processing systems. For materials for which structured data cannot be directly obtained, electronic files submitted by enterprises can be read and information such as enterprise identity, personnel identity, certificate number, qualification category, job type, start date, end date, and enterprise qualifications can be obtained.

[0075] The electronic device uses the same enterprise and its associated personnel as the verification objects. Through enterprise identification and personnel identification, it establishes a corresponding relationship between licenses, personnel qualifications, social insurance, enterprise qualifications and permit processing data from different data sources. Among them, the time when the data source was last maintained, synchronized or returned the corresponding record status is used as the data source's most recent update time; the time when the electronic device performs the current data reading is used as the current data reading time; the range of possible dates for the permit decision determined based on the permit processing status is used as the permit decision time range, which includes the earlier date and the later date of the permit decision.

[0076] Personnel who can be included in the personnel configuration verification according to the corresponding personnel category or special operation type are recorded as eligible personnel; records whose qualifications, social insurance, enterprise qualifications or other verification status cannot be determined based on the currently obtained data are marked as pending confirmation.

[0077] The data update cycle, historical data observation period, number of historical samples, correction time, time margin, anomaly check time, interface re-access time, and review cycle involved in this embodiment are primarily determined based on the update instructions of the corresponding data interface, data synchronization configuration, the processing period for matters published by the licensing authority, the processing period for matters published by the relevant issuing authority, and the actual historical processing records of similar matters. When actual business data can be obtained, the corresponding parameters are determined using the actual business data. The specific values ​​given below are used to illustrate a feasible parameter setting method and are not intended to be fixed values ​​that must be used in different regions or different business systems.

[0078] Specifically, such as Figure 2 As shown: When an enterprise submits an application for extension of its safety production license, the licensing authority conducts pre-acceptance verification, an application under processing requires re-verification, or electronic equipment obtains information about the enterprise to be processed according to the verification task, it begins to process the data of the target enterprise and its related personnel. The electronic equipment first obtains the main identity information of the target enterprise and determines the enterprise identifier used for matching enterprise identities between different data sources. The enterprise identifier can be the unified social credit code. For example, when the enterprise name changes but the unified social credit code does not change, the data before and after the enterprise name change is still associated according to the unified social credit code.

[0079] For personnel information, a personnel identifier that can correspond to the same natural person among personnel qualification certificates, social insurance records, and enterprise personnel materials is used for association; when identity document information can be obtained in accordance with the law, personnel can be matched based on the identity document number; when identity information needs to be protected, personnel identity identifiers that have been de-identified can be used; records with the same name in different data sources but which cannot be confirmed to belong to the same person through other identity information are not directly merged.

[0080] After the enterprise and personnel identities are linked, the electronic device acquires license data, personnel qualification data, social insurance data, enterprise qualification data, and data on the processing of licensing matters. Among them, the license data includes at least the original safety production license number, start date, end date, current status, and the last update time of the data source. The personnel qualification data includes at least the personnel identifier, qualification category, certificate number, certificate start date, certificate end date, issuing authority, current status, and the last update time of the data source. For special operation personnel, the job information corresponding to the personnel qualification is also acquired so that subsequent personnel configuration verification can be carried out according to the specific job.

[0081] Social insurance data should include at least the following fields: personnel identification, month of payment, paying unit, data period, and the most recent update time of the data source. The corresponding records should be saved in chronological order of the months of payment to reflect the changes in a person's social insurance records over a continuous period, and should not replace existing monthly records with a single current status.

[0082] Enterprise qualification data should include at least the following fields: current qualification category, qualification status, validity period, and ongoing qualification change matters. The qualification change matters can be additions, upgrades, downgrades, or cancellations. For ongoing qualification changes, if the corresponding data source can provide relevant data, fields such as acceptance date, current processing status, and expected completion date can also be obtained.

[0083] The data for handling licensing matters should include at least the fields of handling steps and public processing period; when historical case data is available, the actual time taken for historical cases with the same handling process as the current licensing matter should also be obtained; when the current processing status is available, the current number of pending cases or data that reflects the current waiting status should also be obtained.

[0084] After obtaining the above data, the data format is standardized according to the field descriptions of each data source; date fields with different names but the same time meaning are converted into unified fields; date fields with different time meanings are saved separately and not directly merged; for example, the issuance date, effective date, and validity period start date are only standardized when the corresponding data source clearly indicates that their time meanings are the same, otherwise they are saved separately.

[0085] For the expiration date and expiry date, the certificate termination date is determined according to the field definition of the corresponding data source. For example, when the data source defines the expiry date as the date on which the certificate is no longer valid, the last valid date is determined according to the date meaning specified by the data source. When the expiration date indicates the last valid date of the certificate, this date is used as the termination date. After the field conversion is completed, the original field name, original field value and data source are saved at the same time so that the converted data can correspond to the original data.

[0086] The most recent update time of the data source is the most recent maintenance time, most recent synchronization time, or status update time returned by the external data source, and is not replaced by the upload time of the materials uploaded by the enterprise or the data reading time of this session; the electronic device records the data reading time of this session separately, which is used to determine whether the current data needs to be retrieved again in the future.

[0087] When the same license, the same personnel qualification certificate, or the same enterprise qualification status can be obtained from multiple data sources, the order of adoption shall be determined according to the verifiability of the data sources. The data sources may be, in order, structured data directly returned by the electronic certificate data source, structured data returned by the competent authority or industry regulatory platform, electronic certificate documents submitted by the enterprise, and data filled in by the enterprise. In actual use, the above order can be adjusted according to the local data access situation, but the same data source rules shall be adopted for the same type of data in the same verification process.

[0088] When data returned by different data sources are consistent, the data with the highest sort order is used, and data from other sources is saved as a verification record. When data returned by different data sources differ, but the difference does not change whether personnel can be included or the personnel configuration requirements, the data to be used is determined according to the established data source order, and the fields with differences, their corresponding field values, and data sources are saved.

[0089] When differences between different data sources may alter whether personnel can be included or change the company's personnel configuration requirements, the corresponding record will be marked as pending confirmation, and data from the top-ranked data sources will be retrieved again. If the differences cannot be eliminated after re-retrieval, automatic judgment of that data will be suspended, and manual confirmation will be required.

[0090] For cases where the date field is missing, the certificate number is missing, or the person's identity cannot be uniquely matched, the missing information will not be supplemented based on experience; for example, if a certificate number has been obtained but the certificate expiration date has not been obtained, the obtained certificate data will be saved and the certificate period will be marked as pending confirmation; when the social insurance record only contains the person's name and cannot be uniquely matched to the target person through other identity information, the person association will not be directly established based on the same name.

[0091] When the original data source is temporarily inaccessible, record the data source and access time of the failed access, and obtain other sources that can provide the same data according to the established data source order; if other sources still cannot obtain the data that would affect whether personnel can be included or the personnel configuration requirements, mark the corresponding record as pending confirmation.

[0092] For cross-regional certificates with different field names, date formats, or qualification category names, establish field correspondences based on the data interface specifications or certificate field specifications of the corresponding regions, and convert data in different formats into a unified format; the format conversion does not change the original content returned by the data source, and at the same time saves the original fields, the converted fields, and the source region.

[0093] After completing the above processing, each record should include at least the following fields: enterprise identifier or personnel identifier, data category, start date, end date, last update time of the data source, data source, data read time and data version; when the current status returned by the same data source changes, a new data version should be created and the original data version should be saved.

[0094] For the same person holding multiple qualification certificates of different categories, each qualification certificate shall be stored separately and associated with the person; for the same qualification of the same person with both old and new certificates, the start date, end date and current status of the old and new certificates shall be stored separately; the license, personnel qualification, social insurance, enterprise qualification and permit processing data generated by the above processing shall be used for subsequent data update judgment and determination of the time range of permit decisions.

[0095] Specifically, such as Figure 3 As shown: The electronic device reads the current working calendar of the application location and determines the corresponding working days, statutory holidays, and adjusted working days for each Gregorian calendar date based on the working calendar; the processing period for permit matters calculated in working days is determined according to the working calendar, while the time calculated in calendar days is directly mapped to the Gregorian calendar date; the permit processing period calculated in working days is determined sequentially from the working days in the application location's working calendar; the actual time elapsed for personnel qualification certificate expiration, changes in social insurance status, changes in enterprise qualification status, and material corrections is determined according to calendar days; thus, the permit processing period and changes in material status are uniformly mapped to specific Gregorian calendar dates, without using a fixed ratio to convert between working days and calendar days.

[0096] The acquired data is checked for updates; the update cycle of each data source is determined primarily based on the corresponding data interface description, data synchronization configuration, or continuous operation records; the electronic device compares the current data reading time with the most recent update time of the data source, and if the time interval between the two exceeds the update cycle of the corresponding data source, the data is reacquired.

[0097] For social insurance data that is generated and collected monthly, for example, the update and inspection cycle can be selected as 30 calendar days; 30 days corresponds to the general time scale of monthly data updates and is used for regular inspection of monthly collected data; considering that there is actually a difference between the 28th and 31st of a calendar month, when the social insurance data source can provide a clear monthly collection date, the actual collection date is used to determine whether data needs to be re-acquired, and the 30-day period is not fixed for judgment.

[0098] For personnel assessment qualification data and special operation qualification data that can be synchronized on a daily or several days basis, for example, the update inspection cycle can be selected as 3 calendar days; 3 days is suitable for data environments where qualification status can be synchronized within several days, and its source is the synchronization cycle of the corresponding qualification data interface or the actual operation record; when the actual synchronization cycle is different from 3 days, the actual synchronization cycle of the data source is used.

[0099] For electronic certificate data that is synchronized daily or in near real-time, for example, the update check cycle can be selected as 1 calendar day; 1 day is applicable when electronic certificate data is updated at least once a day; when the current status can be obtained in real time, the data can be directly retrieved again during verification; when the interface has a clear synchronization cycle, the synchronization cycle is adopted.

[0100] If the data is within the corresponding update cycle, continue using the current data version; if the update cycle is exceeded, re-acquire the data from the original data source; if, after re-acquiring, data affecting subsequent verification, such as certificate expiration date, social insurance records, qualification status, and enterprise qualification status, remain unchanged, update the data source with the most recent update time; if the above data changes, create a new data version; if re-acquiring fails and missing data affects whether personnel can be included or personnel configuration requirements, acquire data from other sources according to the established data source order.

[0101] After the data update is completed, the time range for the licensing decision is determined based on the data of the licensing matters. If sufficient historical data of similar cases cannot be obtained, the actual acceptance date is used as the starting date. If the case has not yet been formally accepted but needs to be verified in advance, the expected acceptance date is used as the starting date, and the later date of the licensing decision is determined based on the processing period currently published or legally applicable in the application location and the work calendar of the application location. The above methods can be used to determine the later date of the licensing decision when historical case data is insufficient, the current waiting time cannot be reliably determined, or historical data is abnormal.

[0102] When similar historical case data is available, case data with the same processing steps and procedures as the current licensing matter should be selected from the historical records; the historical data observation period can be selected as the most recent 12 months; 12 months covers a complete year and can include statutory holidays such as Spring Festival and National Day, as well as the impact of changes in the number of cases within the year on the actual processing time; when the processing steps, public processing period or processing procedures of the licensing matter change during the said period, only similar case data after the change takes effect should be used, and data under different processing rules should not be mixed.

[0103] The number of historical samples used to determine the time range of the licensing decision should be sufficient to compare changes in actual processing time. For example, the minimum sample size can be 30 cases. 30 cases are used to reduce the excessive impact of a single abnormal case on earlier and later dates when the number of historical samples is small. In actual use, as the number of similar historical cases increases, the earlier and later dates formed before and after the addition of new samples can be compared. When the earlier and later processing times remain stable after continuing to add samples, the corresponding sample size is used as the historical sample size for the current licensing matter. If the number of valid historical samples is less than 30 or less than the sample size determined by the above method, the later date of the licensing decision is determined by the processing period currently published or legally applicable in the application location.

[0104] When historical samples meet the usage conditions, similar historical cases are arranged from shortest to longest actual processing time. The processing time in the middle position after sorting is taken as the usual processing time, and the earlier and later processing times are obtained from the earlier and later positions, respectively. The earlier and later positions are determined according to the actual processing time range that the historical cases need to cover, and the sample positions used are saved so that the same historical samples can obtain the same results again by using the same positions. Starting from the current actual acceptance date or the expected acceptance date, the earlier and later processing times are obtained by corresponding to the earlier and later processing times according to the working calendar of the application location.

[0105] When the current number of pending tasks or the current processing status can be obtained, the later date of the permit decision can be adjusted based on the current waiting situation. When electronic devices obtain historical pending data for the same permit item and the same processing stage, after excluding records that can be confirmed to be caused by system failure, data migration, or other abnormal reasons, the normal pending quantity range is determined by the actual distribution of the remaining historical pending data. When the current pending quantity is within this range, the waiting time is not increased. When the current pending quantity exceeds this range and the processing system can provide a corresponding waiting time, the actual waiting time is included in the later date of the permit decision. When a reliable waiting time cannot be obtained, the number of waiting days is not set by the user, and the permit decision time range is still determined according to the processing period or historical processing time.

[0106] After determining the time frame for the basic permit decision, the time changes caused by material corrections are handled. When similar historical correction records are available, the correction time is the actual number of calendar days elapsed from the issuance of the correction notice to the completion of material corrections and re-entry into the corresponding processing stage. Historical records can be obtained separately for the delivery time of the correction notice, the time for the company to prepare materials, and the waiting time for the corrected materials to re-enter the processing stage. The actual time spent in each stage is recorded separately, and the correction time is determined based on the consecutive natural time elapsed in each stage.

[0107] When historical data for corrections is insufficient, the correction time can be determined based on the actual time required for the delivery of the correction notice, the preparation of the correction materials by the enterprise, and the re-entry of the correction materials into the processing stage. For example, the correction time can be selected as 15 calendar days. 15 days represents a period of natural time occupied by the above continuous processing, and its determination is based on the three time components of the notice delivery, material preparation, and re-entry into the processing stage. When the application location's handling rules, historical correction records, or the application system can provide the actual correction time, the corresponding actual time should be used. When actual correction has already occurred, the time range for the permit decision should be updated with the actual correction notice time and the correction completion time, and the estimated correction time should not continue to be used.

[0108] Once the timeframe for the licensing decision is established, an anomaly check is performed on the time data. First, the later date of the licensing decision is compared with the processing period currently published or legally applicable in the application location, as well as the normal processing time for similar historical cases. If the timeframe exceeds the above-mentioned timeframe, the application location's work calendar, original date, correction records, and historical case data are checked for errors, duplicates, or abnormal records.

[0109] For example, a period exceeding 180 calendar days from the current date to the later date of the permit decision can be used as a further anomaly check condition; 180 days does not represent the statutory processing period for extensions of safety production permits, but is used to identify data records that significantly deviate from the normal processing time; the condition for using this value is that the publicly announced processing period in the application location and the normal longest processing time for similar historical cases are both significantly shorter than 180 days, and the value is verified based on the actual historical case records in the local area; when the anomaly check condition is met, the date data, duplicate correction records, and abnormal historical cases are re-examined; after excluding abnormal data, the time range of the permit decision is re-determined; if a reliable time range still cannot be formed, the later date of the permit decision is determined based on the currently published or legally applicable processing period in the application location.

[0110] After completing the above processing, the saved time verification data shall include at least the earlier date of the permit decision, the later date of the permit decision, the working calendar version of the application location, the historical sample period, the number of historical samples, the correction time, and the corresponding data source. The updated personnel qualification data, social insurance data, and enterprise qualification data shall be correlated with the time verification data for subsequent verification of personnel qualification status and personnel configuration.

[0111] Specifically, such as Figure 4 As shown: Electronic devices obtain the personnel qualification records and social insurance records that have been updated and checked according to the personnel identification, and obtain the personnel category or special operation type corresponding to the personnel.

[0112] For personnel qualification certificates with clearly defined start and end dates, the certificate's validity period is compared with the time frame of the licensing decision. If the certificate's start date is no later than the earlier date of the licensing decision, and the certificate's end date is later than the later date of the licensing decision, the certificate is determined to cover the time frame of the licensing decision. If the certificate's end date falls between the earlier and later dates of the licensing decision, the certificate is determined to have expired within the time frame of the licensing decision. If the certificate's end date is earlier than the earlier date of the licensing decision, the certificate is determined not to cover the time frame of the licensing decision. For certificates with a start date later than the earlier date of the licensing decision, the actual effective date of the certificate within the time frame of the licensing decision should also be determined, and qualifications that have not yet taken effect should not be considered valid qualifications prior to that date.

[0113] If, after the permit decision is made, there are still subsequent steps in the actual processing of the application, such as certificate issuance, delivery, or other steps that require natural time, a time leeway can be set based on the actual processing situation of similar cases in the past. The time leeway is determined based on the actual natural day difference between the permit decision date and the completion date of the corresponding subsequent step in similar cases in the past. After setting the time leeway, the certificate expiration date is further compared with the date after extending the time leeway from the later date of the permit decision to determine whether the certificate validity period can cover the corresponding period.

[0114] For example, if the historical records of similar cases in the application location indicate that it typically takes 10 to 20 calendar days from the issuance of the permit decision to the completion of the corresponding subsequent steps, a time leeway of 10 to 20 calendar days can be selected, with 15 calendar days taken as the midpoint of this range. The 10 to 20 days should be determined based on the corresponding date difference in the actual historical cases in the application location. If the actual period reflected in the historical cases is not within the above range, it should be adjusted according to the actual date difference. If the actual processing procedure does not involve certificate issuance, delivery, or other subsequent steps, this time leeway should not be set.

[0115] For individuals who have submitted applications for extension, review, or renewal but have not yet obtained a new certificate, obtain data such as the acceptance date, current processing status, and expected completion date for the relevant certificate matters. If a new certificate has been obtained from the issuing authority or other data source that can confirm the qualification status, read the start and end dates of the new certificate and compare them with the end date of the original certificate. If the start date of the new certificate is not later than the first calendar day after the end date of the original certificate, confirm that there is no gap in dates between the old and new certificates. If the start date of the new certificate is later than the first calendar day after the end date of the original certificate, save the uncovered date range between the two certificates. If it can only be confirmed that the application for extension, review, or renewal has been accepted, but the effective date of the new certificate cannot be confirmed, mark the corresponding qualification as pending confirmation and do not directly use the application acceptance status as the basis for the continued validity of the qualification.

[0116] For social insurance data, the corresponding records are obtained in chronological order of personnel identification and payment month. Social insurance records must include at least the following fields: personnel identification, payment month, payment unit, data period, and the most recent update time of the data source. Electronic devices compare the most recent social insurance record with the update cycle of the corresponding data source. If the most recent record is still within the normal update cycle, social insurance is not directly considered interrupted because the data for the next month has not yet been generated. If no new record is obtained after the corresponding update cycle has expired, social insurance data is re-obtained according to the aforementioned data update rules.

[0117] The period of continuous social insurance contributions shall be determined in accordance with the verification rules currently implemented by the licensing authority at the place of application. For example, if the verification rules require verification of social insurance records for a certain number of consecutive months, the contribution records for the most recent consecutive months shall be obtained in accordance with the number of months specified in the rules, and the corresponding relationship between the contributing unit and the applicant enterprise shall be verified month by month. If the verification rules do not specify a fixed number of consecutive months, the continuous contribution months shall not be set by the applicant.

[0118] For retirees, employees of restructured enterprises, employees of head offices and branches, and situations where the licensing rules explicitly allow for the use of other materials to prove the relationship between personnel, obtain the supporting data that corresponds to the relevant personnel identifier; if the supporting data complies with the verification rules currently implemented in the application location, determine the relationship between personnel according to the corresponding rules; if the supporting data is missing, contradictory, or cannot be confirmed to correspond with the target personnel, mark the relevant personnel relationship as pending confirmation.

[0119] After verifying the personnel qualifications and social insurance data, the qualification status and personnel relationship of the same person are matched. If the validity period of the qualification certificate held by the person can cover the time range of the licensing decision, and the social insurance record or other personnel relationship proof recognized by the licensing rules meets the corresponding verification requirements, the person is determined to be a person who can be included.

[0120] If a person's qualifications meet the requirements but their social insurance is pending confirmation, they will not be included in the confirmed number of eligible personnel. If a person's social insurance meets the requirements but their qualification certificate expires within the time frame of the licensing decision, the certificate's expiration date and corresponding expiration status will be retained, but the person will not be considered as someone who can continuously cover the entire time frame of the licensing decision. If a person's qualifications or social insurance can be clearly determined to be non-compliant with the verification requirements, they will not be included in the corresponding personnel category or job type.

[0121] If the same person holds multiple qualification certificates of different categories, they shall be verified separately according to the personnel category or job type corresponding to each qualification certificate. For example, if one qualification certificate meets the requirements of the target job type while another qualification certificate belongs to a different job type, only the qualification that matches the target job type shall be used for the corresponding personnel configuration verification, and other categories of qualifications shall not be used to replace the target qualification.

[0122] After the above processing is completed, the personnel verification record will include at least the following fields: personnel identification, personnel category, job type, start date of qualification certificate, end date of qualification certificate, qualification status, social insurance status, whether the personnel are eligible for inclusion, and the reason for pending confirmation. These fields will be linked to the corresponding time range of the licensing decision and will be used to verify the personnel configuration according to the enterprise's qualifications and personnel categories in the future.

[0123] Specifically, such as Figure 5 As shown: Electronic devices acquire the enterprise's current qualification status, ongoing qualification changes, the time frame of the license decision, and the currently valid personnel configuration standards for the application location; the personnel configuration standards include at least the following fields: qualification category, personnel category, special operation type, required number of personnel, effective date, and rule version; when the personnel configuration standards change, the currently applicable rule version is determined according to its effective date, and the rule version used in this verification is saved.

[0124] If the company does not have any ongoing qualification changes, the personnel configuration requirements for each personnel category and job type shall be determined based on the current valid qualifications and their corresponding personnel configuration standards.

[0125] When an enterprise has matters involving the addition or upgrading of qualifications, or other matters that may increase staffing requirements, it shall obtain the estimated completion date of the qualification change and compare the estimated completion date with the earlier and later dates of the licensing decision. If the estimated completion date is no later than the earlier date of the licensing decision, the staffing requirements shall be determined according to the staffing standards corresponding to the changed qualification. If the estimated completion date is later than the later date of the licensing decision, the staffing requirements shall be determined according to the staffing standards corresponding to the currently valid qualification. If the estimated completion date is later than but no later than the earlier date of the licensing decision, the staffing requirements corresponding to the qualifications before and after the change shall be obtained separately, and compared item by item according to personnel category and job type. The higher value among the required number of personnel for the same personnel category or job type shall be used for verification.

[0126] For example, if a certain personnel category requires 3 people before the qualification change and 5 people after the qualification change, the personnel category will be verified according to 5 people; if another personnel category requires 5 people before the qualification change and 4 people after the qualification change, the personnel category will still be verified according to 5 people. The above 3, 5 and 4 people are only used to illustrate the handling method of comparing personnel configuration requirements under different qualification statuses. The actual number of people is obtained from the current effective personnel configuration standards of the licensing authority or competent department of the application location and is not considered as a fixed number.

[0127] For ongoing matters involving qualification downgrades, cancellations, or other matters that may reduce staffing requirements, staffing requirements will continue to be determined based on the qualification status before the change, until the effective date of the qualification change can be confirmed. If the effective date of the qualification change has been confirmed from the competent authority or other valid data sources, the effective date will be compared with the time range of the licensing decision. If the effective date is not later than the earlier date of the licensing decision, staffing requirements will be determined based on the qualification status after the change. If the effective date is later than the later date of the licensing decision, staffing requirements will still be determined based on the qualification status before the change. If the effective date is within the time range of the licensing decision, the corresponding staffing requirements before and after the change will be obtained separately, and compared item by item according to personnel category and job type, using the higher value among the corresponding required number of personnel for verification.

[0128] When a company has two or more qualification changes at the same time, obtain the expected completion date or the confirmed effective date for each qualification change and compare each date with the time range of the licensing decision. Based on the possible qualification statuses within the time range of the licensing decision, obtain the corresponding personnel configuration standards and compare them item by item according to personnel category and job type. Use the higher value among the required number of personnel for the same personnel category or job type for verification.

[0129] When a qualification change is in the processing stage but the expected completion date or effective date cannot be obtained, obtain the personnel configuration standards corresponding to the current qualification and the qualification to be changed, and compare them item by item according to personnel category and job type. For the same personnel category or job type, use the higher value of the required number of personnel under the two qualification statuses, and mark the qualification change item as pending confirmation. After obtaining the expected completion date or effective date, redetermine the personnel configuration requirements according to the updated qualification status.

[0130] After determining the personnel allocation requirements, obtain the aforementioned countable personnel according to personnel category and special operation type; the main person in charge of the enterprise, project manager, full-time safety production management personnel, etc., are counted separately according to their respective personnel categories, and the number of personnel from other personnel categories exceeding the requirements is not used to supplement the target personnel category; special operation personnel are counted separately according to their corresponding job type, and personnel from other job types are not used to supplement the personnel requirements of the target job type.

[0131] For each personnel category or job type, compare the number of people who can be counted with the corresponding staffing requirements; if the number of people who can be counted is higher than the staffing requirements, save the number of people who can be counted and the corresponding staffing requirements; if the number of people who can be counted is equal to the staffing requirements, record that there is no surplus of personnel for that personnel category or job type; if the number of people who can be counted is lower than the staffing requirements, determine the number of missing personnel based on the difference between the staffing requirements and the number of people who can be counted; personnel in the pending confirmation status are recorded separately, and are not included in the confirmed number of people who can be counted until their qualification status or personnel relationship is confirmed.

[0132] When the status of an individual's qualifications or the status of an enterprise's qualifications change within the time frame of the licensing decision, the number of people who can be counted and the personnel configuration requirements before and after the change shall be determined according to the date of the change, and the corresponding personnel categories or job types shall be verified; therefore, the status of a single individual or a single qualification at the time of application submission shall not be used to replace the status that may actually occur within the time frame of the licensing decision.

[0133] Staffing standards should be obtained first from the licensing authority, industry regulatory authority, or data source that can provide currently valid rules. If currently valid staffing standards cannot be obtained, the current rule data should be obtained again. If the applicable standard still cannot be confirmed after obtaining the new standard, the corresponding staffing requirements should be marked as pending confirmation. Historical standards that have expired or whose validity cannot be confirmed should not be used to make a judgment on compliance.

[0134] After completing the above processing, the resulting personnel configuration verification record will include at least the following fields: enterprise qualification category, qualification status, qualification change items, expected completion date or effective date, personnel configuration standard version, personnel category, special operation type, personnel configuration requirements, number of personnel that can be counted, number of personnel missing, reason for confirmation, earlier date of permit decision and later date of permit decision. The personnel configuration verification record will be linked with the corresponding enterprise and personnel data for subsequent determination of personnel qualifications, social insurance or personnel configuration matters that need to be processed.

[0135] Specifically, such as Figure 6As shown: Based on the aforementioned verification results of personnel qualifications, social insurance, and staffing, matters requiring further processing are determined; when personnel qualification certificates cannot cover the entire time range of licensing decisions, personnel qualifications or social insurance are pending confirmation, the number of personnel eligible for inclusion in a certain personnel category or job type is equal to or lower than the corresponding staffing requirements, or when the ongoing enterprise qualification change may increase staffing requirements, corresponding processing matters are formed.

[0136] For personnel qualification certificates that need to be extended, reviewed, or renewed before the licensing decision is made, obtain the processing period currently published by the relevant issuing authority; if a true historical processing record of similar matters can be obtained, the processing period can also be verified based on the actual historical processing time; use the later date of the licensing decision as the time benchmark for the corresponding matter to be completed, and deduct the processing time required backward; if it is necessary to reserve subsequent processing time based on historical processing data, deduct the corresponding time margin backward, and the resulting date is the latest processing start date.

[0137] For example, if the actual time from the issuance of the permit decision to the completion of the certificate, delivery, or other subsequent procedures in similar historical cases is mainly distributed between 10 and 20 calendar days, the time margin can be selected as 10 to 20 calendar days, and 15 calendar days can be taken as the midpoint of this range. When using 15 calendar days, the latest date of the permit decision is used as the benchmark. First, the processing time currently published by the issuing authority or verified by historical cases is deducted backward, and then 15 calendar days are deducted backward to obtain the latest processing start date. When the actual time range of historical cases is not within 10 to 20 days, the time margin is adjusted according to the corresponding historical date difference, and 15 days is not fixed.

[0138] When social insurance is in a pending confirmation state, the time to re-acquire the social insurance status is determined based on the actual reporting cycle, data collection cycle, and most recent update time of the corresponding social insurance data source; if the social insurance data source has a clearly defined data formation date or update date, it is processed according to that actual date, and no additional fixed waiting time is set.

[0139] When the number of personnel eligible for inclusion in a certain personnel category or job type is lower than the corresponding staffing requirements, a processing item shall be formed according to the specific personnel category or job type, and the actual number of missing personnel shall be recorded; different personnel categories and different special operation jobs shall be processed separately, and the shortage of the target personnel category or job type shall not be made up by the number of personnel in other personnel categories or other jobs exceeding the requirements.

[0140] When multiple processing items are generated, they are arranged in order of their latest start date, with the earlier date being processed first. If the latest start dates are the same, priority is given to processing items that have already resulted in the number of eligible employees falling below the staffing requirements, followed by items where the number of eligible employees equals the staffing requirements or where the qualification certificates will expire within the time frame of the licensing decision. If they are still the same, they are arranged in order of their actual processing time from longest to shortest.

[0141] When the same person has both eligibility and social insurance issues, the corresponding processing items are recorded separately and linked through the person's identifier; if either eligibility or social insurance fails to meet the verification requirements, the person will not be reclassified as an eligible person; the eligible status of the person will be updated only after all relevant items have been re-verified and meet the requirements.

[0142] After an enterprise submits new personnel qualification certificates, social insurance materials, or other data for processing the aforementioned matters, it does not directly mark the corresponding matters as completed. Instead, it re-acquires the corresponding data according to the data type and re-verifies it according to the aforementioned data source, data update, and time judgment rules. After re-determining the time range for the licensing decision, it then verifies the personnel qualifications, social insurance, and staffing status. When the issues corresponding to the original matters have been resolved, it updates the status of the matters.

[0143] When material corrections are actually required during the permit processing period, data such as the date of the correction notice, the date of submission of the correction materials, and the date of completion of the corrections that can be obtained are obtained, and the time range of the permit decision is updated with the actual correction time. If the earlier or later date of the permit decision changes as a result, the qualifications and staffing of personnel affected by the date change are re-verified. Records that have no impact on the new time range of the permit decision and whose data version has not changed can continue to be used without indiscriminate duplication of verification.

[0144] When a departure, change of social insurance payment unit, change of personnel qualification certificate status, or addition of personnel is detected, the personnel qualification and social insurance data of the corresponding personnel are re-acquired according to the corresponding personnel identifier, and their inclusion status is re-determined; when the enterprise qualification status, expected completion date of qualification, or effective date of qualification changes, but the personnel data remains unchanged, the personnel configuration requirements are re-determined according to the updated enterprise qualification; when data conflicts occur between different data sources that may change the inclusion status or personnel configuration requirements of personnel, the corresponding data is re-acquired according to the aforementioned data source rules.

[0145] When an external data source experiences a timeout or temporary communication failure, the original data source can be re-accessed using progressively increasing time intervals. For example, if the calling rules of the corresponding interface allow, the re-access interval can be selected as 5 seconds, 15 seconds, and 45 seconds, and three re-accesses can be performed sequentially. The 5-second interval is used to quickly retry due to short-term network fluctuations, and the subsequent 15-second and 45-second intervals are gradually extended to reduce the access pressure on the external interface caused by continuous calls. The above times should simultaneously meet the minimum continuous access interval specified by the data interface and the waiting time allowed for a single verification task. If the retry interval is clearly specified in the interface description, the time specified by the interface shall be used. If data cannot be obtained after continuous re-access, other sources that can provide the same data shall be accessed in the order of the aforementioned data sources.

[0146] For matters that have been verified once but are still in the application preparation or permit processing period, they can be re-verified at certain time intervals. Under normal circumstances, for example, the review period can be selected as 7 calendar days. 7 days is shorter than the monthly update cycle that social insurance data generated monthly usually corresponds to, and it can check the personnel qualifications and electronic certificate status again within a week. It is suitable for situations where there are no certificates that are about to expire or matters that need to be confirmed.

[0147] If a personnel qualification certificate expires before the next review date, the personnel qualification or enterprise qualification is pending confirmation, or the external data source has returned new status data, the review will not wait for the 7-day review cycle and will be re-verified directly based on the changed data. If the actual data source has a clear update cycle, the review cycle can be adjusted according to the actual update frequency of each data source, and the 7-day period will not be fixed.

[0148] After the license review is completed, the actual processing data for this license matter is saved. The actual processing data includes at least the fields such as the actual time spent in each processing step, the date of the notice of correction, the date of completion of correction, the actual date of the license decision, and the corresponding data version, and is used to update the historical processing data of similar license matters.

[0149] For example, the observation period for historical cases can be selected as the most recent 12 months; using 12 months can cover a complete year, so that historical data includes holidays such as Spring Festival and National Day, as well as the actual processing situation under different case volume conditions within the year; after newly completed similar cases are added to the historical data, records with an observation period of more than 12 months are removed; when the processing stage, public processing period or processing rules of the licensing matter change, only similar cases after the change takes effect are used, and data under different processing rules are not mixed.

[0150] The processing record should include at least the following fields: enterprise identifier, personnel identifier, personnel category, job type, matter type, reason for occurrence, personnel configuration requirements, number of personnel that can be counted, number of personnel missing, corresponding processing time, remaining time, latest processing start date, current status, data source, and last update time. For enterprise qualification matters that do not involve personnel, the personnel identifier, personnel category, and job type fields may not be recorded. For certificate or social insurance matters that do not involve the number of personnel, the personnel configuration requirements, number of personnel that can be counted, and number of personnel missing may not be recorded.

[0151] Through the above processing, the verification time for personnel qualifications, social insurance, and staffing is kept in line with the actual processing time of licensing matters. When there are changes in materials, personnel status, personnel qualifications, or enterprise qualifications, only the data affected by the changes is re-acquired and verified, avoiding the continued use of expired historical statuses. At the same time, the duplication of data that has not changed is reduced, thereby improving the time consistency between different data sources and the traceability of verification results.

[0152] Example 2: Based on Example 1, the specific application process of a method for verifying safety permit extension materials is further explained:

[0153] To further illustrate the operation of this invention, we take the application for renewal of a safety production license by construction company A as an example. The following dates, number of personnel, and processing time are used to illustrate the processing relationship between various types of data. In actual application, the processing period for licensing matters, personnel configuration requirements, data update cycle, personnel qualification processing time, and other business parameters are determined based on the currently effective business rules, data interface descriptions, and similar historical processing records of the application location.

[0154] In this embodiment, August 3, 2026 is taken as the acceptance date for Enterprise A's application for extension of its safety production license; the electronic device obtains Enterprise A's unified social credit code and associates it with the enterprise's declaration data, electronic certificate data, enterprise qualification data, and licensing matters processing data; at the same time, based on the personnel identity information, the personnel qualification certificates, social insurance records, and enterprise personnel materials are associated with the corresponding personnel.

[0155] The obtained license data should include at least the following fields: license number, start date, end date, current status, and the most recent update time of the data source; personnel qualification data should include at least the following fields: personnel identifier, personnel category, qualification category, certificate number, certificate start date, certificate end date, issuing authority, and the most recent update time of the data source; social insurance data should include at least the following fields: personnel identifier, payment month, payment unit, data period, and the most recent update time of the data source; and enterprise qualification data should include at least the following fields: current qualification category, qualification status, validity period, and ongoing qualification change matters.

[0156] The last updated data for the electronic safety production license was August 2, 2026; the last updated social insurance data was July 10, 2026; the last updated data for some personnel qualifications was July 30, 2026; and the data was retrieved on August 3, 2026.

[0157] According to the data interface description used in this embodiment, electronic certificate data is updated at least once a day, personnel qualification data can be synchronized within a few days, and social insurance data is formed and collected monthly. Therefore, the update and inspection cycle for electronic certificate data can be selected as 1 calendar day, the update and inspection cycle for personnel qualification data can be selected as 3 calendar days, and the update and inspection cycle for social insurance data can be selected as 30 calendar days. Among them, 1 day corresponds to the data interface that is updated daily, 3 days corresponds to the qualification data that can be synchronized within a few days, and 30 days corresponds to the data formed monthly. If the data interface has specified other synchronization cycles, the cycle actually specified by the interface shall be adopted.

[0158] The electronic equipment compares the current data retrieval time with the most recent update time of each data source; the electronic safety production license data is 1 day away from the current data retrieval time, which has not exceeded the corresponding update cycle, so the current data will continue to be used; the social insurance data is 24 days away from the current data retrieval time, which has not exceeded the 30-day monthly update inspection cycle, so the social insurance will not be directly deemed interrupted because the social insurance data for August 2026 has not yet been formed; for personnel qualification data that is more than 3 days away from the current data retrieval time, the current record will be retrieved again from the corresponding data source.

[0159] When retrieving a person's qualification data, if the external interface times out on the first attempt, it can be accessed again according to the continuous access interval allowed by the interface. For example, in this embodiment, the re-access interval can be selected as 5 seconds, 15 seconds, and 45 seconds. After the first failure, wait 5 seconds to access again, and if it still fails, wait 15 seconds to access again. If the current qualification data has been obtained on the second re-access, the access after 45 seconds will not be executed. By using a gradually increasing time interval, the continuous calls to the external interface can be reduced while handling short-term communication failures. If the interface has specified a retry time or call frequency, it shall be executed according to the interface specification.

[0160] After the data update is completed, the electronic device obtains the current working calendar and permit processing data of the application location; the permit processing time is calculated according to the working days in the application location's working calendar; the time for personnel qualification certificate expiration, social insurance status changes, enterprise qualification status changes, and material correction is determined according to the calendar days and finally converted into specific Gregorian calendar dates.

[0161] This embodiment obtains 46 historical cases with the same processing procedure as the current licensing matter within the past 12 months; the past 12 months cover a complete year, which may include statutory holidays and the impact of different numbers of cases within the year on the actual processing time; the minimum number of historical samples used to determine the time range of the licensing decision can be selected, for example, 30 cases, which is used to reduce the impact of a single abnormal case on the time judgment when the sample size is small; this embodiment obtains 46 valid historical cases, which exceeds the above minimum sample size, therefore, the historical cases are used to determine the time range of the licensing decision.

[0162] The electronic device arranges 46 historical cases in ascending order of actual processing time. Based on the location of the historical samples used in this case, the earliest processing time is 16 working days, the usual processing time is 21 working days, and the latest processing time is 26 working days. The 16 working days, 21 working days, and 26 working days mentioned are the processing times obtained by sorting the historical cases in this embodiment, and are not considered as fixed license processing periods.

[0163] At the same time, the current number of pending tasks is obtained and compared with the historical pending task data of the same licensing items and the same processing steps; in this embodiment, the current number of pending tasks is within the normal range of the historical number of pending tasks, so no additional waiting time is added.

[0164] The application acceptance date is August 3, 2026. The dates are converted to 16 and 26 working days based on the actual working calendar of the application location. For example, if the earlier date of the permit decision is calculated to be August 25, 2026, and the later date is September 8, 2026, the permit decision period is from August 25, 2026 to September 8, 2026. The specific dates are based on the calculation results of the application location's working calendar, which includes actual working days, statutory holidays, and adjusted workdays.

[0165] After determining the timeframe for the licensing decision, the validity period of each employee's qualification certificate in Company A is compared with the aforementioned timeframe.

[0166] Company A has three full-time safety production management personnel: A, B, and C. A's qualification certificate expires on May 31, 2027; B's qualification certificate expires on March 31, 2027; and C's qualification certificate expires on September 12, 2026. The starting date of all three certificates is no later than August 25, 2026. Since the expiration dates of all three certificates are later than the latest date of the current licensing decision, September 8, 2026, the qualification certificates of all three personnel currently cover the time frame of the licensing decision.

[0167] Company A has two other employees, D and E, who are intended to be included in the same special operation category. D's corresponding qualification certificate expires on April 30, 2027, and his social insurance relationship complies with the current verification rules. Although E holds a valid qualification certificate for the corresponding job, the latest social insurance record shows that his paying unit has changed to another company. After confirming that the social insurance record is currently valid data, E's personnel relationship does not comply with the rules adopted in this verification. Therefore, E will not be included in the confirmed number of employees for this job category.

[0168] For A, B, C, and D, the electronic device checks their social insurance records in chronological order of payment months. The payment unit for the most recent record is Company A, and the current social insurance data update cycle is still within the normal period. Therefore, the relevant personnel relationships will continue to be confirmed in accordance with the currently effective social insurance verification rules of the application location. If the normal data formation time for the next month has not yet arrived, social insurance will not be considered interrupted because the records for the next month have not yet been returned.

[0169] While verifying the personnel status, the electronic equipment obtains data on a qualification upgrade that Company A is currently processing, with the expected completion date of the qualification upgrade being September 2, 2026. Since September 2, 2026 falls within the licensing decision period from August 25, 2026 to September 8, 2026, the applicable personnel configuration standards before and after the qualification upgrade are obtained respectively.

[0170] This embodiment is derived from the currently valid personnel allocation standards of the application location: a certain type of full-time safety production management personnel requires 2 people before qualification upgrade and 3 people after qualification upgrade; the above-mentioned special operation type requires 1 person before qualification upgrade and 2 people after qualification upgrade; the number of people mentioned only represents the data obtained from the currently valid personnel allocation standards in this embodiment, used to illustrate the verification process under the condition of qualification change, and is not used as a fixed number of people requirement in other regions or other licensing matters.

[0171] Since the qualification upgrade is expected to be completed within the time frame of the licensing decision, the required number of personnel for the same personnel category or job type before and after the qualification upgrade will be compared separately. The required number of full-time safety production management personnel is 2 and 3 respectively, so it will be verified as 3 people. The required number of personnel for the corresponding special operation jobs is 1 and 2 respectively, so it will be verified as 2 people. Different personnel categories will be counted separately, and the number of personnel exceeding the requirements of other personnel categories will not be used to make up the difference. Different special operation jobs will also be counted separately.

[0172] Within the current timeframe for the permit decision, the qualifications and relationships of personnel A, B, and C all meet the verification requirements. Therefore, the number of full-time safety production management personnel that can be counted is 3, which is equal to the corresponding personnel configuration requirement of 3. Among the target special operation jobs, only D can be confirmed to meet the requirements, so the number of personnel that can be counted is 1, which is 2 fewer than the personnel configuration requirement. It is determined that there is a shortage of 1 person for this job.

[0173] The electronic equipment records that there is a shortage of 1 person for this special operation and forms a corresponding handling item; for full-time safety production management personnel, although the current number of 3 people can meet the personnel configuration requirement of 3 people, there is no surplus personnel. At the same time, C's qualification certificate will expire on September 12, 2026. Therefore, C's certificate expiration date is saved and his qualification status is reassessed when the time range of the permit decision changes.

[0174] During the licensing process, the licensing authority issued a notice to supplement materials on August 12, 2026. Company A completed the supplementation on August 20, 2026, and re-entered the corresponding processing stage. After the actual supplementation has occurred, the previously estimated supplementation time will no longer be used. Instead, the actual date of the supplementation notice and the date of completion of the supplementation will be used to update the licensing process time.

[0175] After recalculating based on the actual correction time and the working calendar of the application location, for example, the earlier date of the permit decision is adjusted from August 25, 2026 to September 2, 2026, and the later date of the permit decision is adjusted from September 8, 2026 to September 16, 2026, thus forming a new time range for the permit decision.

[0176] If the timeframe of a licensing decision changes, only the data affected by the date change should be re-verified; for data whose version has not changed and whose validity period still covers the new timeframe of the licensing decision, the current record can continue to be used.

[0177] At this point, C's qualification certificate expires on September 12, 2026, earlier than the later date of the new licensing decision, September 16, 2026. Therefore, C's qualification certificate does not cover the entire timeframe of the new licensing decision. A and B's qualification certificates still cover the timeframe of the new licensing decision, and the two continue to be countable personnel.

[0178] Suppose that C submitted an application for extension or review of qualification certificate on August 18, 2026, but the data source can only confirm that the application has been accepted and cannot yet obtain the starting date of the new certificate. Therefore, C's qualification will not be directly determined to remain valid after September 12, 2026 based on the acceptance status, but will be marked as pending confirmation. After the new certificate is obtained, the starting date of the new certificate and the expiration date of the original certificate will be used to determine whether there are any dates between the two certificates that are not covered by the valid qualification.

[0179] Since C cannot be counted as a person who can cover the entire time frame of the licensing decision, the number of full-time safety production management personnel who can be counted has been reduced from 3 to 2. However, the personnel configuration requirement determined according to the qualification upgrade is still 3 people. Therefore, this personnel category has a personnel shortage of 1 person.

[0180] For the qualification certificate extension that needs to be processed by C, the electronic device obtains the processing time currently published by the relevant issuing authority or the actual historical processing time of similar matters; for example, in this embodiment, the processing time for obtaining the corresponding qualification certificate is 12 calendar days; the 12 days is the processing time obtained from the corresponding business data in this embodiment, and is not a fixed processing period.

[0181] Meanwhile, historical data from similar cases show that the actual date difference between the issuance of the permit decision and the completion of the relevant certificate issuance, delivery, or other subsequent procedures is mainly between 10 and 20 calendar days. Therefore, the time margin can be selected as 10 to 20 calendar days, and this embodiment uses 15 calendar days; 15 days is the midpoint of the above-mentioned historical date range; when the actual date difference of historical cases is not within 10 to 20 days, the time margin is determined based on the actual historical data.

[0182] Using the later date of the new licensing decision, September 16, 2026, as the time base for completing the corresponding processing, subtracting 12 calendar days for the qualification certificate processing time, and then subtracting another 15 calendar days for the time leeway, we get August 20, 2026, as the latest processing start date for the corresponding matter in this embodiment; based on this date, it can be determined that this matter needs to be processed with priority.

[0183] In response to the shortage of one person in the target special operation category, Company A supplemented the personnel with person A. After obtaining the personnel qualification and social insurance data of person A, the verification was carried out again according to the current permit decision time range. The data source returned that the expiration date of person A's target operation qualification certificate was December 31, 2027. The certificate was already effective, the social insurance payment unit was Company A, and it met the personnel relationship verification rules currently implemented in the application location. Therefore, person A was identified as an eligible personnel for this operation. At this time, the number of eligible personnel for this operation was two, namely person D and person A, which was equal to the personnel allocation requirement of two people, and the original personnel shortage was eliminated.

[0184] In the case of a shortage of one full-time safety production management personnel, Company A supplements personnel with G. After re-obtaining data confirmation, the expiration date of G's qualification certificate is October 31, 2027, and his social insurance relationship complies with the current verification rules. Therefore, G is identified as a personnel eligible for inclusion in this personnel category. At this time, the three personnel of Company A, Company B, and Company G can cover the new permit decision time range, which is equal to the personnel allocation requirement of three people, and the aforementioned personnel shortage is eliminated. The qualification extension of Company C is still kept as a separate record, but the current personnel allocation result no longer depends on whether Company C has completed the extension.

[0185] During the permit processing period, the relevant status can be rechecked at certain time intervals. For ordinary records that do not have certificates nearing expiration or pending confirmation status, for example, the review period can be selected as 7 calendar days. 7 days is shorter than the monthly data generation cycle of social insurance and can be used to recheck the status of personnel qualifications and electronic certificates within one week. When the personnel qualification certificate will expire before the next review date, the personnel qualification or enterprise qualification is pending confirmation, or the external data source has returned a new status, the data that has changed can be re-verified directly without waiting for 7 days. When the actual data interface has specified the update cycle, the review time can be adjusted according to its actual update frequency.

[0186] On September 10, 2026, the competent authority returned data indicating that the qualification upgrade of Enterprise A had taken effect; the electronic equipment obtained the actual effective date and compared it with the time range of the current licensing decision, confirming that the qualification upgrade had occurred within that time range. Therefore, the personnel configuration standard was verified again according to the upgraded standard; at this time, there were 3 full-time safety production management personnel (A, B, and G) and 2 target special operation personnel (D and F), all of whom met the personnel requirements obtained from the current effective personnel configuration standard.

[0187] For the time frame of the licensing decision, anomaly checks can also be conducted. For example, if the publicly available processing period in the application location and the normal longest processing time for similar historical cases are both significantly shorter than 180 calendar days, a period exceeding 180 calendar days from the current date to the later date of the licensing decision can be used as a further anomaly check condition. 180 days is not considered the statutory processing period for the extension of the safety production license; it is only used to identify possible erroneous dates, duplicate correction records, or abnormal historical data. In this embodiment, the later date of the licensing decision is September 16, 2026, which does not meet the above-mentioned anomaly check condition.

[0188] The final licensing decision for this matter was made on September 14, 2026. After the licensing matter is completed, the actual processing data will be saved, including at least the actual acceptance date, the actual time spent in each processing step, the date of the notice of correction, the date of completion of correction, the actual date of the licensing decision, and the corresponding data version.

[0189] The actual permit decision date of September 14, 2026 falls within the previously determined period from September 2, 2026 to September 16, 2026. Therefore, this actual processing record will be added to the same type of historical case data. The historical data observation period can be selected as the most recent 12 months. After a new case is added, records that have exceeded the 12-month observation period will be removed. When the processing stage, public processing period, or processing rules of the permit matter change, only similar cases after the change takes effect will be retained for subsequent time determination. Data under different processing rules will not be mixed.

[0190] As can be seen from the above operation process, this invention does not only verify the personnel qualifications, social insurance, and enterprise qualification status obtained at the time of the extension application submission, but also determines whether the data needs to be re-acquired based on the actual update cycle of different data sources, and determines the time range for the permission decision by combining the work calendar of the application location, historical processing time, current processing status, and actual rectification status; within this time range, the validity period of personnel qualifications, social insurance status, changes in enterprise qualifications, and corresponding personnel configuration requirements are verified accordingly.

[0191] When actual corrections cause the licensing decision timeframe to be extended, the qualifications of personnel who originally covered the licensing decision timeframe may no longer be covered by the updated timeframe. When a company's qualifications change within the licensing decision timeframe, the corresponding personnel configuration requirements may also change. By re-verifying the data affected by these changes and determining personnel gaps and handling matters based on the updated personnel qualifications, social insurance, and personnel configuration, the verification results can be aligned with the actual status during the licensing process. This reduces the chances that personnel qualification expiration, changes in personnel relationships, or insufficient personnel configuration may go undetected if verification is based solely on the status at the time of application submission.

[0192] The above description is merely a specific embodiment of this application, but the scope of protection of this application is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the scope of the technology disclosed in this application should be included within the scope of protection of this application. Therefore, the scope of protection of this application should be determined by the scope of the claims.

[0193] In conclusion, the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

Claims

1. A method for verifying materials for extension of safety permits, characterized in that, include: Obtain data on licenses, personnel qualifications, social insurance, certifications, and approval time for enterprise extension applications, and record the duration, update time, and source by entity identifier; Overdue data is refreshed according to the data source update cycle, the time base of natural days and working days is unified, and the time range corresponding to the permit decision is determined based on the approval process, historical processing time, pending status and correction time. By mapping the eligibility period and social insurance status of personnel to the aforementioned time range, the personnel eligible to participate in the verification are determined; The qualification change status is matched with the time range to determine the personnel configuration requirements, and the available personnel are checked against the configuration requirements according to personnel category and job type. Arrange rectification for matters with approaching deadlines, questionable status, or insufficient personnel; when corrections, changes in personnel status, or qualification status occur, re-verify from the affected step.

2. The method for verifying safety permit extension materials according to claim 1, characterized in that, Obtain data on the company's licenses, personnel qualifications, social insurance, certifications, and approval time for the extension application, including: Based on enterprise identifiers, enterprise information is matched from different data sources; based on personnel identity identifiers, personnel qualification information, social insurance information, and enterprise personnel information are matched. The information includes the validity period of the license, the qualification period of personnel and their corresponding job types, social insurance payment records, enterprise qualifications and qualification change status, as well as the processing steps, processing time, historical processing time and current pending data for the licensing matters.

3. The method for verifying safety permit extension materials according to claim 1, characterized in that, Records are kept according to the subject identifier, including the record period, update time, and source, including: The date field format should be standardized according to the field descriptions of each data source, while retaining the original field format. When the same data has multiple sources, the data to be used is determined according to the preset data source order; When data from different sources differs and such differences affect whether personnel should be included or personnel allocation requirements, the corresponding data will be marked as pending confirmation. Record the data source, the data source's most recent update time, the time this data was read, and the data version; When data returned from the same data source changes, a new data version is created while the original data version is retained.

4. The method for verifying safety permit extension materials according to claim 1, characterized in that, Refresh overdue data according to the data source update cycle, and unify the time base for calendar days and working days, including: Read the current work calendar of the application location, determine the corresponding Gregorian calendar date for the processing period of the permit matter based on the work calendar, record the expiration of personnel qualifications, changes in social insurance status, changes in enterprise qualification status, and material supplementation time according to natural days, and convert them into the corresponding Gregorian calendar date; The update cycle of each data source is determined based on the data interface description, data synchronization configuration, or operation records; When the data update time exceeds the corresponding update cycle, the corresponding data is retrieved again; When the status of personnel qualifications, social insurance, enterprise qualifications, or other data that affects verification changes, a new data version shall be created. If re-acquiring fails, other data sources will be called to retrieve the corresponding data according to the preset data source order.

5. The method for verifying safety permit extension materials according to claim 1, characterized in that, The time frame for the permit decision is determined based on the approval process, historical processing time, pending status, and required corrections, including: Select historical cases that have the same processing steps and procedures as the current licensing matter, sort them according to the actual processing time, and obtain the corresponding earlier and later processing times; The actual or expected date of acceptance is used as the starting date. The processing time is mapped to the specific Gregorian calendar date according to the working calendar of the application location. The earlier and later dates of the permit decision are adjusted based on the current pending status and the time for correction. When actual rectification occurs, the earlier date and the later date of the licensing decision shall be re-determined based on the actual elapsed time of the rectification. If historical application data is insufficient, waiting time cannot be determined, or there are anomalies in the historical records, the later date of the permit decision shall be determined based on the currently applicable processing period.

6. The method for verifying safety permit extension materials according to claim 1, characterized in that, By mapping the eligibility period and social insurance status to the aforementioned time range, the personnel eligible to participate in the verification are determined, including: Obtain personnel qualification records and social insurance records according to personnel identification, and read the corresponding personnel category or special operation type; The start and end dates of the qualification certificate are matched with the time frame of the licensing decision, and the personnel relationship is verified according to the month of payment and the paying unit. When a qualification certificate matching the corresponding personnel category or job type covers the time range and the personnel relationship conforms to the current verification rules, the corresponding personnel will be marked as eligible personnel. When the same person holds multiple qualification certificates, each qualification certificate shall be evaluated separately. If the eligibility status or personnel relationship cannot be confirmed, the corresponding personnel record will be marked as pending confirmation.

7. The method for verifying safety permit extension materials according to claim 1, characterized in that, By mapping the qualification change status to the aforementioned time range, personnel allocation requirements are determined, including: Obtain the company's current qualifications, ongoing qualification changes, and current valid staffing standards; Compare the expected completion date or effective date of the qualification change with the time frame of the licensing decision; Obtain the personnel configuration requirements before and after the qualification change, and compare them item by item according to personnel category and special operation type; If the expected completion date or effective date cannot be determined, the higher value among the required number of personnel for the same personnel category or job type shall be used, and the qualification change status and personnel configuration standard version shall be recorded.

8. The method for verifying safety permit extension materials according to claim 1, characterized in that, Verify available personnel and configuration requirements by personnel category and job type, including: The number of personnel who can be counted should be counted separately according to personnel category and special operation type, and compared with the corresponding personnel configuration requirements item by item; Different personnel categories and different job types should be checked separately, and personnel from other categories or job types should not be used to supplement the list; Personnel awaiting confirmation are recorded separately and are not included in the already confirmed count. When the number of eligible personnel is lower than the staffing requirements, the number of missing personnel shall be determined based on the difference between the two. When the status of personnel qualifications or enterprise qualifications changes, the number of personnel and personnel configuration requirements for the corresponding personnel category or job type shall be re-verified according to the changed status.

9. The method for verifying safety permit extension materials according to claim 1, characterized in that, Arrange rectification for matters with approaching deadlines, questionable status, or insufficient personnel, including: For situations where the qualification certificate cannot cover the time frame of the licensing decision, the personnel's qualifications or social insurance are pending confirmation, or the number of people that can be included does not exceed the personnel configuration requirements, separate handling items shall be formed; Based on the later date of the permit decision, the latest date for initiating the process is determined by deducting the processing time and time leeway for the corresponding matters. The processing items are sorted according to the latest start date. If the dates are the same, the processing order is determined based on the availability of personnel and the processing time of the corresponding items.

10. The method for verifying safety permit extension materials according to claim 1, characterized in that, When corrections, personnel status, or qualification status change, re-verification is required from the affected step, including: When material corrections actually occur, the time range of the permit decision is updated based on the actual correction time, and the personnel qualifications and personnel configuration data affected by the change in the time range are re-verified; When there is a resignation of an employee, a change in the social insurance payment unit, a change in the employee's eligibility status, or the addition of a new employee, the corresponding eligibility data and social insurance data of the employee will be re-acquired. When the enterprise's qualification status, expected completion date, or effective date changes, the personnel allocation requirements should be re-determined. When enterprises submit new personnel qualification certificates, social insurance materials or other relevant materials, the corresponding items should be re-verified based on the updated data.

Citation Information

Patent Citations

  • A KYC certificate verification method based on computer vision technology

    CN112215225B

  • A Deep Learning-Based Method and System for Processing Business License Data

    CN116681628B