A multi-dimensional management and control analysis method for power grid resource full-factor project
By constructing a knowledge graph of deviation driving factors in power grid projects and performing multi-level reasoning, the problems of low efficiency and superficial results in deviation analysis of power grid projects are solved, and automated positioning and intelligent management from deviation phenomena to root causes are realized.
Patent Information
- Application Number
- CN202611415474.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-13
- Publication Date
- 2026-11-24
AI Technical Summary
Existing technologies are inefficient in deviation analysis of power grid projects, making it difficult to accurately and quickly locate the hidden fundamental driving factors across stages and elements. They also lack the ability to automatically extract unstructured text and reason about causal logic connections, resulting in superficial analysis results and an inability to achieve intelligent attribution from the perspective of full-element linkage.
By collecting multi-dimensional management and control data throughout the entire lifecycle of power grid projects, semantic extraction of unstructured text and fusion of structured data are performed to construct a knowledge graph of deviation driving factors for power grid projects. Using a multi-layered reasoning mechanism of graph structure and semantic matching, a deep search is conducted along the causal relationship path. The coherence is verified by combining contextual semantics and time attributes to locate the key fundamental driving factors.
It enables automated, in-depth diagnosis from deviation phenomena to root causes, generates transparent, structured diagnostic reports, provides precise control solutions, realizes full-element linkage analysis and knowledge reuse, and improves the level of intelligence in project management.
Smart Images

Figure CN123160104A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of data analysis technology, specifically to a multi-dimensional management and control analysis method for all elements of power grid resources. Background Technology
[0002] Power grid infrastructure and technological upgrading projects are crucial supports for the development of the power system, characterized by large-scale investment, long construction periods, and complex resource elements. A typical power transmission and transformation project often encompasses multiple stages, including planning, design, civil engineering, electrical installation, and commissioning, involving the coordination of all elements such as personnel, equipment, materials, machinery, funds, and the environment. During project implementation, deviations such as schedule delays, cost overruns, and quality defects frequently occur. The causes of these deviations are not isolated but are hidden in a large number of project management process documents, such as construction logs, supervision reports, design change orders, meeting minutes, and meteorological records. These documents, accumulated in unstructured text form, contain information on the actual status, abnormal events, and related impacts during project execution, constituting an important source of original data for tracing the causes of deviations. However, due to the complexity of power grid projects, deviations are often caused by the interaction of multiple factors, and there are causal transmission relationships between the driving factors across stages and elements, making accurate and rapid identification of the root cause a long-standing management challenge.
[0003] However, existing technologies for handling deviation analysis in power grid projects mainly rely on manual, item-by-item checks by project personnel. This method requires manually sifting through massive amounts of unstructured documents, comparing schedules, cost ledgers, and text records one by one, and inferring possible causal relationships based on personal experience. This manual diagnostic model is not only extremely inefficient but also highly dependent on the individual's knowledge level and experience accumulation, resulting in shallow analysis results that often only discover surface causes and fail to uncover the hidden, fundamental driving factors in cross-departmental and cross-stage interactions. Furthermore, existing project management focuses on the statistical reporting of structured data and lacks the ability to automatically extract and correlate semantic knowledge such as causal logic, temporal dependencies, and influence intensity contained in unstructured text. It cannot construct a complete causal evidence chain from deviation phenomena to underlying root causes, nor can it achieve intelligent attribution and knowledge reuse from a perspective of full-element linkage. Summary of the Invention
[0004] The purpose of this invention is to overcome the shortcomings of existing technologies and provide a multi-dimensional management and analysis method for all elements of power grid resource projects. This invention extracts semantics from unstructured texts such as construction logs and supervision reports at each stage of a power grid project and integrates them with structured progress and cost data to dynamically construct a knowledge graph of deviation driving factors for the power grid project. This makes the discrete and implicit causal logic explicit and structured. By using a multi-layer reasoning mechanism based on graph structure and semantic matching, a deep search is performed along the causal relationship path in the knowledge graph. The coherence is verified by combining the contextual semantics and time attributes of the project at that time, thereby locating the key fundamental driving factors that lead to deviations. This technology realizes causal tracing thinking, gets rid of the inefficiency and experience limitations of manual document review, and achieves automated deep diagnosis from deviation phenomena to root causes, ensuring that the analysis results are both logically rigorous and consistent with the actual state of the project.
[0005] To solve the above-mentioned technical problems, this invention provides the following technical solution: a multi-dimensional management and control analysis method for all elements of power grid resources, the specific steps of which are as follows: S100 collects multi-dimensional management and control data of all stages of the power grid project life cycle in real time, including structured progress data, cost data and quality inspection data, as well as unstructured construction logs, supervision reports, design change orders, meeting minutes and meteorological and environmental data, and cleans and preprocesses the unstructured text data in segments. S200. Semantic extraction is performed on the preprocessed unstructured text data to identify all elements of the power grid project and the multi-dimensional semantic relationships between entities. Structured data is integrated to dynamically construct a knowledge graph of deviation driving factors of the power grid project, with deviation event entities as the core and related to risk factor entities and fundamental driving factor entities along the relationship path. S300 calculates the deviation index of project progress and cost in real time. When the deviation index of any dimension exceeds the corresponding dynamic threshold, the deviation event entity corresponding to the activity task that caused the deviation is used as the trigger node to start the semantic reasoning diagnosis process. S400. Starting from the trigger node, perform multi-level reasoning based on graph structure and semantic matching on the knowledge graph of deviation driving factors of power grid project: define deviation pattern subgraph, obtain candidate causal paths through subgraph matching search, perform semantic matching and conflict detection on each candidate causal path, calculate the comprehensive score of the path and combine it with time attribute verification to locate the set of key fundamental driving factors. S500: Based on the set of key fundamental driving factors and the corresponding causal propagation paths, extract relevant document evidence, generate a structured diagnostic report, and retrieve matching recommended control solutions from the knowledge graph of deviation driving factors of power grid projects, push them to the relevant responsible entities, and carry out multi-dimensional closed-loop control.
[0006] Furthermore, in S200, the full-element entities of the power grid project specifically include: project phase entities, activity task entities, personnel entities, equipment entities, material entities, funding entities, environmental entities, deviation event entities, risk factor entities, and fundamental driving factor entities; the multi-dimensional semantic relationships include: compositional relationships, dependency relationships, causal relationships, temporal relationships, and influence degree relationships; among them, causal relationships and influence degree relationships both have causal strength weight attributes used for path comprehensive scoring in step S400, and all entities have start time attributes and end time attributes.
[0007] Furthermore, in S200, the specific steps for dynamically constructing the knowledge graph of power grid project deviation drivers are as follows: A pre-trained language model BERT-BiLSTM-CRF, incorporating a dictionary from the power sector, is used to perform entity recognition on the preprocessed unstructured text data. A relational classification model based on entity-to-context encoding is then used to extract causal relationships and influence degree relationships, resulting in triples. These triples are then written into a graph database after entity disambiguation and coreference resolution, dynamically updating the knowledge graph of power grid project deviation drivers. The causal strength weight assigned to each extracted causal relationship edge is calculated using the following formula: In the formula, Let be the causal strength weight of the causal relationship edge from entity i to entity j. The harmonic factor has a value range of 0-1. Let represent the statistical frequency of the causal relationship from entity i to entity j in historical project data. The maximum value among all causal frequencies is used for normalization. The cosine similarity function is used. The semantic vector representing the causal relationship from entity i to entity j is generated by the context encoder in the relation classification model. This is the contextual semantic vector of the project phase in which the current deviation event occurs. It is obtained by aggregating and encoding all document text within the project phase entity using a pre-trained language model.
[0008] Furthermore, in S300, the deviation index includes the schedule deviation index. and cost deviation index Schedule Deviation Index and cost deviation index The result is obtained through a set of formulas, which are: The dynamic threshold is adaptively adjusted based on the project's stage and risk appetite coefficient. > Progress threshold or When the cost threshold is reached, the deviation event entity associated with the activity task that caused the deviation will be used as the trigger node to start the semantic reasoning diagnosis process.
[0009] Furthermore, in S400, the specific steps of multi-layer reasoning based on graph structure and semantic matching are as follows: S401. Define the deviation pattern subgraph. The structure of the deviation pattern subgraph consists of deviation phenomenon nodes, direct cause nodes, intermediate event nodes, and root cause nodes, forming a progressive four-layer causal reasoning framework. S402. Using the trigger node of S300 as the deviation phenomenon node, perform a heuristic path search based on subgraph isomorphism on the knowledge graph of deviation driving factors of power grid project. By matching the relationship types in the mapping relationship and the multi-semantic relationship, retrieve the instantiated path that conforms to the subgraph structure of the deviation pattern and form a candidate causal path set. S403. For each candidate causal path in the candidate causal path set, extract the description text and relation type of all entity nodes on the candidate causal path, concatenate them into a causal semantic chain in natural language form, and perform semantic coherence matching and context conflict detection on the causal semantic chain.
[0010] Furthermore, in S403, the semantic coherence matching of the causal semantic chain is achieved through a path comprehensive scoring function, the expression of which is: Here, Score(path) is the comprehensive score calculated for a candidate causal path, used to measure the reasonableness of the candidate causal path as an explanation for the root cause of the bias, where path is a candidate causal path in the set of candidate causal paths. The harmonic factor used to balance semantic matching and causal strength has a value range of [0.5, 0.8]. Sim is a semantic similarity function used to calculate the similarity between two input semantic vectors. Emb(chain) is the causal chain semantic vector obtained by inputting the causal semantic chain of the candidate causal path path into the pre-trained language model. Emb(ctx) is the context semantic vector of the current deviation event. The context semantic vector is obtained by inputting meteorological description text, resource input records and construction log fragments within a preset time window before and after the trigger diagnosis time into the pre-trained language model for encoding. The causal strength weight of the k-th causal edge on the candidate causal path is determined by... Calculations show that This represents a chain multiplication operation on the causal strength weights of all n causal edges along the candidate causal path. The total number of causal relationship edges contained in the candidate causal path is denoted as 'path'. After calculating the Score(path) value for each candidate causal path, the root cause nodes pointed to by the top K candidate causal paths with the highest Score(path) values and that pass the time attribute verification are selected to form the set of key fundamental driving factors.
[0011] Furthermore, in S403, the specific rules for time attribute verification are as follows: traverse each pair of entity nodes with a direct causal relationship on the candidate causal path, requiring that the end time attribute of the entity node as the cause must be earlier than or equal to the start time attribute of the entity node as the result; otherwise, it is determined to be a timing conflict, and the candidate causal path is removed from the candidate causal path set; after completing the time attribute verification, set the causal strength weight threshold ε, and retain only each causal relationship edge on the candidate causal path.
[0012] Furthermore, in S500, the generated structured diagnostic report includes: a basic description of the deviation event, a list of key fundamental driving factors obtained from the diagnosis, a complete causal propagation path from the fundamental driving factors to the deviation phenomenon drawn in the form of a directed graph, source document evidence fragments and location links associated with each causal link in the complete causal propagation path, an analysis of the correlation impact of the deviation event on subsequent activities and resources, and a list of recommended control measures generated based on the knowledge graph matching of deviation driving factors in the power grid project.
[0013] Furthermore, in S500, the recommended method for generating the control measures list is as follows: based on the type tags of key fundamental driving factor entities and the project stage to which they belong, the control measures entities with the highest historical similarity are retrieved from the knowledge graph of deviation driving factors in the power grid project, and a list of control schemes arranged in descending order of priority is generated; during the push process, the structured diagnostic report and the list of control schemes are distributed to the corresponding responsible parties based on the responsibility attribution analysis of key fundamental driving factors.
[0014] Compared with existing technologies, this multi-dimensional management and control analysis method for all elements of power grid resources has the following advantages: I. This invention extracts semantics from unstructured text such as construction logs and supervision reports at each stage of a power grid project and integrates them with structured progress and cost data to dynamically construct a knowledge graph of deviation drivers for the power grid project. This makes the discrete and implicit causal logic explicit and structured. By utilizing a multi-layered reasoning mechanism based on graph structure and semantic matching, a deep search is performed along the causal relationship path in the knowledge graph. The coherence is verified by combining the contextual semantics and time attributes of the project at that time, thereby locating the key fundamental drivers of deviations. This technology realizes causal tracing thinking, gets rid of the inefficiency and experience limitations of manually reviewing documents, and achieves automated deep diagnosis from deviation phenomena to root causes, ensuring that the analysis results are both logically rigorous and consistent with the actual state of the project.
[0015] Second, this invention generates a structured diagnostic report by structurally integrating the root cause factors, complete causal propagation paths, and source document evidence fragments for each causal link obtained from the diagnosis. This makes the root cause tracing results highly transparent and interpretable. At the same time, based on the type and stage of the root cause factors, it retrieves the most similar historical control measure instances from the knowledge graph, generates priority-ranked recommended control schemes, and pushes them to relevant responsible parties. This process realizes a closed-loop link from deviation monitoring and intelligent diagnosis to precise governance, and enables linkage analysis among all elements, reuse of knowledge and experience, and rapid response through multi-terminal collaboration. This transforms project management from a passive response to a proactive and systematic intelligent decision support.
[0016] Other advantages, objectives and features of the invention will be set forth in part in the description which follows, and in part will be apparent to those skilled in the art from the following examination or study, or may be learned from the practice of the invention. Attached Figure Description
[0017] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the accompanying drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are merely some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without any creative effort.
[0018] Figure 1 This is a flowchart of the multi-dimensional management and control analysis method for all elements of power grid resources in this invention; Figure 2 This is a framework diagram for constructing a knowledge graph of the driving factors of power grid project deviations in this invention; Figure 3 This is a framework diagram for multi-layered causal reasoning and root cause localization of knowledge graphs of power grid project deviation driving factors in this invention. Detailed Implementation
[0019] To further illustrate the technical means and effects of the present invention in achieving its intended purpose, the following detailed description of the specific implementation methods, structures, features, and effects of the present invention, in conjunction with the accompanying drawings and preferred embodiments, is provided below.
[0020] Example 1
[0021] In the scenario of full life-cycle management of a newly built substation infrastructure project in a 110kV suburban industrial park, this embodiment uses a multi-dimensional control and analysis method for all elements of power grid resources to carry out multi-dimensional deviation management and root cause diagnosis. The newly built substation in the suburban industrial park, which was initiated and constructed by the power supply company, is selected as the implementation carrier. This project is a conventional power grid infrastructure project with an overall construction period of 12 months. The project is divided into five major implementation stages: preliminary design, civil construction, primary electrical equipment installation, secondary system commissioning, and final acceptance. The project participants include six types of responsible entities: construction management unit, civil construction team, electrical installation unit, third-party supervision agency, equipment and material supplier, and on-site quality supervision unit. During the entire project life cycle, structured metering data and massive amounts of unstructured documents are continuously generated. This embodiment relies on the enterprise's internal project management server and on-site digital project management platform to complete the full-process deployment. The hardware adopts a conventional industrial-grade server cluster, and the software is equipped with a graph database, a pre-trained model deployment environment, and a data preprocessing engine.
[0022] Comprehensive control over data collection and unstructured text preprocessing
[0023] The project's multi-dimensional management and control data is collected in real time through two data links. The first link collects structured data, with the project management platform periodically extracting progress data, cost data, and quality inspection data. The progress data includes the planned completion percentage and the actual completion percentage of each sub-item of the project. The cost data includes the budgeted cost of each sub-item and the actual expenses incurred at each stage. The quality inspection data consists of the results of third-party quality tests conducted after the civil engineering foundation and electrical equipment were brought to the site. The second link captures unstructured heterogeneous data by connecting to the supervision office system, the on-site construction ledger system, and the regional meteorological monitoring platform. This automatically collects five types of unstructured documents: daily construction logs, stage supervision reports, project design change orders, weekly project meeting minutes, and daily meteorological and environmental records of the project area. Preprocessing tasks are performed on the collected unstructured raw text, such as... Figure 1 As shown, the preprocessing stage is divided into two detailed steps: text cleaning and text segmentation. The text cleaning stage removes meaningless garbled characters, duplicate notes, blank fields, and redundant comments in the document, as well as typos and irrelevant punctuation generated during the conversion of scanned documents to text. The text segmentation stage breaks down the document according to the business semantic boundaries, using a single design change item, a single day's construction content, or a single meeting agenda as the smallest segmentation unit. Long documents are broken down into independent short sentence text blocks. The segmented text is uniformly stored in the text cache database to provide a regular data source for subsequent entity and relation extraction.
[0024] Construction and dynamic updating of a knowledge graph of driving factors for deviations in power grid projects
[0025] Entity recognition is achieved using a pre-trained language model BERT-BiLSTM-CRF that integrates a professional dictionary for the power industry. Before recognition, incremental fine-tuning was performed using thousands of historical documents on substation infrastructure and construction specifications for the power industry. At the same time, a self-built professional dictionary for substation infrastructure was embedded into the word embedding layer of the pre-trained language model. The dictionary includes professional terms in fields such as civil construction, power equipment, and power grid materials, which solves the problem of recognition bias in power professional terms. The BiLSTM bidirectional long short-term memory network is responsible for extracting contextual features from segmented text. By relying on forward and backward bidirectional sequence reading, the semantic relationship between words before and after is captured, avoiding the problem of semantic fragmentation of long-distance words in long texts. The CRF conditional random field layer receives the output feature vectors and uses a sequence labeling algorithm to define the initial boundary and entity category of entities, accurately identifying entities in project stages, activities and tasks, personnel, equipment, materials, funds, environment, deviation events, risk factors, and fundamental driving factors. After entity recognition is completed, a relation classification model with independent encoding of entity context is used to extract multivariate semantic relations. The extracted objects include five types of semantic relations: composition, dependency, causality, temporality, and degree of influence. During the operation, the relation classification model concatenates and encodes the original context statements of the two entities to be judged, distinguishes different relation types based on the features of the encoding vector, and outputs triple data of entity-semantic relation-entity. After obtaining the batch of triples, entity disambiguation and coreference resolution are carried out in sequence. Entity disambiguation is used for entities with the same name but different targets, and the entity affiliation is distinguished based on the project number and bid section information. For example, the main transformer equipment with the same name is divided into independent entities according to the main transformer No. 1 and main transformer No. 2. Coreference resolution is used to resolve the reference content of abbreviations and pronouns in the unified document, and maps the reference descriptions of the construction team, our supplier, etc. to the corresponding entity names.
[0026] The processed compliance triples are batch-written into the Neo4j graph database to complete the construction of a knowledge graph of deviation drivers for power grid projects. During project operation, dynamic incremental updates are implemented as new data is added. For the causal strength weights attached to causal relationship edges, the harmonic factor is fixed at 0.6 during implementation. Based on the historical project database of substations of the same voltage level within the unit over the past five years, the frequency of corresponding causal relationships is statistically analyzed. Frequency normalization is performed using the highest frequency of all causal relationships. Then, the weights are comprehensively calculated by combining the relation semantic vector and the cosine similarity of the project stage context encoding vector. Finally, a causal strength weight is assigned to each causal relationship edge, using the following formula: In the formula, Let be the causal strength weight of the causal relationship edge from entity i to entity j. The harmonic factor has a value range of 0-1. Let represent the statistical frequency of the causal relationship from entity i to entity j in historical project data. The maximum value among all causal frequencies is used for normalization. The cosine similarity function is used. The semantic vector representing the causal relationship from entity i to entity j is generated by the context encoder in the relation classification model. The contextual semantic vector for the current deviation event is obtained by aggregating and encoding all document text within the project stage entity using a pre-trained language model. Furthermore, all entities within the power grid project deviation driving factor knowledge graph are uniformly labeled with their own start and end time attributes, thus fully constructing a project deviation driving knowledge graph centered on the deviation event and relating it to risk factors and fundamental driving factors. Figure 2 As shown.
[0027] Real-time calculation and diagnosis triggering of multidimensional deviation index
[0028] Based on the collected structured data, the schedule deviation index (SV) and cost deviation index (CV) are calculated in real time. and cost deviation index The result is obtained through a set of formulas, which are: ; Implement dynamic threshold adaptive configuration according to the characteristics of project phases, when > Progress threshold or When the cost threshold is reached, the deviation event entity associated with the activity task that caused the deviation is used as the trigger node. In this embodiment, the construction risk preference during the civil construction phase of the project is at a medium level, and the electrical equipment installation phase involves the arrival of valuable primary equipment. The corresponding dimensional threshold is automatically adapted according to the current stage of the project. Within the third month of the civil construction accounting cycle of this project, the civil engineering foundation sub-item project is calculated. If the project exceeds the preset dynamic threshold for progress, a civil engineering foundation construction delay deviation event entity will be generated for the corresponding delayed item. This deviation event entity will be automatically locked as the diagnostic trigger node, and the semantic reasoning diagnostic process will be initiated.
[0029] Multi-layered causal reasoning based on graph structure and semantic matching
[0030] The first step is to pre-solidify a four-layer progressive deviation pattern subgraph architecture. The subgraph node hierarchy from top to bottom is deviation phenomenon node, direct cause node, intermediate event node, and root cause node. Adapting to the causal transmission logic of the power grid project, after mapping the trigger node to the deviation phenomenon node, path retrieval is carried out in the already constructed knowledge graph of deviation driving factors of the power grid project. During the retrieval, entity type and multi-relationship category are matched simultaneously to filter out multiple candidate causal paths that conform to the four-layer subgraph topology structure and summarize them to form a set of candidate causal paths. For each candidate causal path in the candidate causal path set, all entity text descriptions and edge relationship types on the candidate causal path are extracted and concatenated according to natural language word order to generate a complete causal semantic chain. When performing path comprehensive scoring calculation, a harmonic factor of 0.7 is selected to balance semantic and causal weights. On the one hand, the causal semantic chain, construction logs and meteorological data within the deviation event time window are respectively fed into the pre-trained language model to generate two sets of semantic vectors, and semantic matching scores are obtained through similarity calculation. On the other hand, the weights of all causal edges of a single path are continuously multiplied to obtain the path causal weight product. The two results are weighted according to the harmonic factor ratio to obtain the single path comprehensive score, which is implemented through the path comprehensive scoring function. The expression of the path comprehensive scoring function is as follows: Here, Score(path) is the comprehensive score calculated for a candidate causal path, used to measure the reasonableness of the candidate causal path as an explanation for the root cause of the bias, where path is a candidate causal path in the set of candidate causal paths. The harmonic factor used to balance semantic matching and causal strength has a value range of [0.5, 0.8]. Sim is a semantic similarity function used to calculate the similarity between two input semantic vectors. Emb(chain) is the causal chain semantic vector obtained by inputting the causal semantic chain of the candidate causal path path into the pre-trained language model. Emb(ctx) is the context semantic vector of the current deviation event. The context semantic vector is obtained by inputting meteorological description text, resource input records and construction log fragments within a preset time window before and after the trigger diagnosis time into the pre-trained language model for encoding. The causal strength weight of the k-th causal edge on the candidate causal path is determined by... Calculations show that This represents a chain multiplication operation on the causal strength weights of all n causal edges along the candidate causal path. This represents the total number of causal relationship edges contained in the candidate causal path; After scoring, a dual filtering rule is initiated. The first layer is time attribute verification, checking the time parameters of each pair of entity nodes with a direct causal relationship on the candidate causal path. If the end time of the cause entity node is later than the start time of the result entity node, a time sequence conflict is determined, and the candidate causal path is directly removed from the candidate causal path set. The second layer filters according to a fixed causal strength weight threshold of 0.15, deleting invalid paths in the candidate causal path where the causal strength weight of any causal relationship edge is lower than the causal strength weight threshold. After two rounds of filtering, the root cause nodes pointed to by the top three candidate causal paths with the highest comprehensive path score and passing the time attribute verification are selected, forming the set of key fundamental driving factors, such as... Figure 3 As shown.
[0031] Structured diagnostic report generation and closed-loop management solution push
[0032] Based on the selected set of key fundamental driving factors and the corresponding complete causal propagation chain, a structured diagnostic report is automatically generated. The structured diagnostic report fills in six parts item by item. The first part fills in the basic overview of this civil engineering delay deviation event. The second part lists all the key fundamental driving factors located by reasoning. The third part derives a directed causal topology diagram from the fundamental factors to the deviation phenomenon. The fourth part marks the original document source, document storage location link and key evidence fragments corresponding to each causal link. The fifth part analyzes the chain impact of the fundamental driving factors on the subsequent sub-item schedule and material allocation. The sixth part is a list of recommended control measures generated based on the knowledge graph matching of the deviation driving factors of the power grid project. During the control plan generation phase, the entity classification tags of key driving factors and their respective civil construction phases are used as search keywords. Highly similar control measures already implemented in historical substation projects of the same type are retrieved from the power grid project deviation driving factor knowledge graph. These measures are then sorted from highest to lowest priority. Based on the identified responsibility relationships, the diagnostic report and control plan list are automatically split and pushed to the project material specialist terminal, the on-site construction manager terminal, and the project general contractor terminal. Each responsible person implements corrective measures based on the pushed content, provides on-site feedback on the corrective results after completion, and the corrective data is then fed back to update the power grid project deviation driving factor knowledge graph, completing a closed-loop control process.
[0033] In summary, in the actual engineering project scenario of a newly built 110kV suburban substation, a knowledge graph of deviation driving factors for power grid projects was constructed by relying on multi-source data collection and professional domain-optimized entity extraction models. Abnormal events were automatically triggered by quantifying deviation indicators, and root cause intelligent location was achieved by using four-layer subgraph matching, semantic scoring, and temporal verification. Finally, diagnostic files were output and control suggestions were accurately distributed to the corresponding responsible positions, realizing the practical application of multi-dimensional deviation control in power grid infrastructure projects.
[0034] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention in any way. Although the present invention has been disclosed above with reference to preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art can make some modifications or alterations to the above-disclosed technical content to create equivalent embodiments without departing from the scope of the present invention. Any simple modifications, equivalent changes and alterations made to the above embodiments based on the technical essence of the present invention without departing from the scope of the present invention shall still fall within the scope of the present invention.
Claims
1. A method for multi-dimensional management and control analysis of all-factor projects of power grid resources, characterized in that, The specific steps of this method are as follows: S100 collects multi-dimensional management and control data of all stages of the power grid project life cycle in real time, including structured progress data, cost data and quality inspection data, as well as unstructured construction logs, supervision reports, design change orders, meeting minutes and meteorological and environmental data, and cleans and preprocesses the unstructured text data in segments. S200. Semantic extraction is performed on the preprocessed unstructured text data to identify all elements of the power grid project and the multi-dimensional semantic relationships between entities. Structured data is integrated to dynamically construct a knowledge graph of deviation driving factors of the power grid project, with deviation event entities as the core and related to risk factor entities and fundamental driving factor entities along the relationship path. S300 calculates the deviation index of project progress and cost in real time. When the deviation index of any dimension exceeds the corresponding dynamic threshold, the deviation event entity corresponding to the activity task that caused the deviation is used as the trigger node. S400. Starting from the trigger node, perform multi-level reasoning based on graph structure and semantic matching on the knowledge graph of deviation driving factors of power grid project: define deviation pattern subgraph, obtain candidate causal paths through subgraph matching search, perform semantic matching and conflict detection on each candidate causal path, calculate the comprehensive score of the path and combine it with time attribute verification to locate the set of key fundamental driving factors. S500: Based on the set of key fundamental driving factors and the corresponding causal propagation paths, extract relevant document evidence, generate a structured diagnostic report, and retrieve matching recommended control solutions from the knowledge graph of deviation driving factors of power grid projects, push them to the relevant responsible entities, and carry out multi-dimensional closed-loop control. 2.The grid resource all-element project multi-dimensional management and control analysis method according to claim 1, characterized in that, In S200, the full-element entities of the power grid project specifically include: project phase entities, activity task entities, personnel entities, equipment entities, material entities, funding entities, environmental entities, deviation event entities, risk factor entities, and fundamental driving factor entities; the multi-dimensional semantic relationships include: composition relationships, dependency relationships, causal relationships, temporal relationships, and influence degree relationships; among them, causal relationships and influence degree relationships both have causal strength weight attributes, and all entities have start time attributes and end time attributes.
3. The multi-dimensional management and control analysis method for all elements of power grid resources according to claim 1, characterized in that, In step S200, the specific steps for dynamically constructing a knowledge graph of power grid project deviation drivers are as follows: A pre-trained language model incorporating a power domain dictionary is used to perform entity recognition on the pre-processed unstructured text data, and a relation classification model is used to extract causal relationships and influence degree relationships to obtain triples; the triples are then written into a graph database after entity disambiguation and coreference resolution, dynamically updating the knowledge graph of power grid project deviation drivers; the causal strength weight assigned to each extracted causal relationship edge is calculated using the following formula: In the formula, Let be the causal strength weight of the causal relationship edge from entity i to entity j. The harmonic factor has a value range of 0-1. Let represent the statistical frequency of the causal relationship from entity i to entity j in historical project data. It is the maximum value among all causal relationships. The cosine similarity function is used. Let be the semantic vector representing the causal relationship from entity i to entity j. This is the contextual semantic vector of the project phase in which the current deviation event occurs.
4. The multi-dimensional management and control analysis method for all elements of power grid resources according to claim 1, characterized in that, In S300, the deviation index includes the schedule deviation index. and cost deviation index Schedule Deviation Index and cost deviation index The result is obtained through a set of formulas, which are: ; The dynamic threshold is adaptively adjusted based on the project's stage and risk appetite coefficient. > Progress threshold or When the cost threshold is reached, the deviation event entity associated with the activity task that caused the deviation will be used as the trigger node to start the semantic reasoning diagnosis process.
5. The multi-dimensional management and control analysis method for all elements of power grid resources according to claim 1, characterized in that, In S400, the specific steps of multi-layer reasoning based on graph structure and semantic matching are as follows: S401. Define the deviation pattern subgraph. The structure of the deviation pattern subgraph consists of deviation phenomenon nodes, direct cause nodes, intermediate event nodes, and root cause nodes, forming a progressive four-layer causal reasoning framework. S402. Using the trigger node as the deviation phenomenon node, perform a heuristic path search based on subgraph isomorphism on the knowledge graph of deviation driving factors of power grid projects. By matching the relationship types in the mapping relationship and the multi-semantic relationship, retrieve the instantiated path that conforms to the subgraph structure of the deviation pattern and form a candidate causal path set. S403. For each candidate causal path in the candidate causal path set, extract the description text and relation type of all entity nodes on the candidate causal path, concatenate them into a causal semantic chain in natural language form, and perform semantic coherence matching and context conflict detection on the causal semantic chain.
6. The multi-dimensional management and control analysis method for all elements of power grid resources according to claim 5, characterized in that, In step S403, the semantic coherence matching of the causal semantic chain is achieved through a path comprehensive scoring function, the expression of which is: Wherein, Score(path) is the comprehensive score of a candidate causal path calculated for that candidate causal path, and path is a candidate causal path in the set of candidate causal paths. is a harmonic factor used to balance semantic matching and causal strength, with a value range of [0.5, 0.8]. Sim is the semantic similarity function. Emb(chain) is the causal chain semantic vector obtained after inputting the causal semantic chain of the candidate causal path path into the pre-trained language model. Emb(ctx) is the context semantic vector of the current biased event. The causal strength weight of the k-th causal edge on the candidate causal path is determined by... Calculations show that This represents a chain multiplication operation on the causal strength weights of all n causal edges along the candidate causal path. The total number of causal relationship edges contained in the candidate causal path is denoted as 'path'. After calculating the Score(path) value for each candidate causal path, the root cause nodes pointed to by the top K candidate causal paths with the highest Score(path) values and that pass the time attribute verification are selected to form the set of key fundamental driving factors.
7. The multi-dimensional management and control analysis method for all elements of power grid resources according to claim 6, characterized in that, In S403, the specific rule for time attribute verification is as follows: traverse each pair of entity nodes with a direct causal relationship on the candidate causal path, and require that the end time attribute of the entity node as the cause must be earlier than or equal to the start time attribute of the entity node as the result; otherwise, it is determined to be a timing conflict, and the candidate causal path is removed from the candidate causal path set. After completing the time attribute verification, set the causal strength weight threshold ε, and retain only the causal strength weight of each causal relationship edge on the candidate causal path. Candidate causal paths are all greater than ε, where ε is 0.
15.
8. The multi-dimensional management and control analysis method for all elements of power grid resources according to claim 1, characterized in that, In S500, the generated structured diagnostic report includes: a basic description of the deviation event, a list of key fundamental driving factors obtained from the diagnosis, a complete causal propagation path from the fundamental driving factors to the deviation phenomenon drawn in the form of a directed graph, source document evidence fragments and location links associated with each causal link in the complete causal propagation path, an analysis of the correlation impact of the deviation event on subsequent activities and resources, and a list of recommended control measures generated based on the knowledge graph matching of deviation driving factors in the power grid project.
9. The multi-dimensional management and control analysis method for all elements of power grid resources according to claim 8, characterized in that, In S500, the recommended method for generating the list of control measures is as follows: based on the type label of the key fundamental driving factor entity and the project stage to which it belongs, the control measure entity with the highest historical similarity is retrieved in the knowledge graph of deviation driving factors of power grid projects, and a list of control schemes arranged in descending order of priority is generated. The push process involves analyzing the responsibility attribution of key fundamental driving factors and distributing structured diagnostic reports and control plan lists to the relevant responsible parties.