Multi-dimensional fault grading operation and maintenance method and system for wind farm based on hierarchical scheduling architecture

By using a hierarchical scheduling architecture and AI intelligent analysis, the fault characteristic parameters of wind farms are collected in real time, the fault level is calculated, and optimal scheduling is performed according to the level. This solves the problems of resource waste and delays in the existing wind farm fault scheduling, and realizes efficient and economical fault handling and dynamic adjustment of maintenance plans.

CN123160141APending Publication Date: 2026-11-24HUNAN UNIV OF SCI & TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611654440.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-10-26
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing wind farm fault dispatching methods ignore the differences in the severity of wind turbine faults, the weight of downtime losses, weather and terrain constraints, and the dynamic deterioration characteristics of faults. This leads to minor faults consuming a large amount of resources, major faults delaying maintenance, fault escalation, and even unit scrapping, making it impossible to form a closed-loop optimization.

Method used

A multi-dimensional fault classification and maintenance method for wind farms based on a hierarchical scheduling architecture is adopted. Fault characteristic parameters are collected in real time through SCADA system, wind turbine sensors and maintenance terminals. Basic fault hazard score, downtime loss score and scheduling constraint score are calculated, normalized and nonlinear power operation is performed to classify fault levels, and strict hierarchical optimization scheduling is performed according to level to match maintenance resources. Combined with AI intelligent analysis module to predict the remaining life of components and failure probability, maintenance plan is dynamically adjusted.

Benefits of technology

It enables accurate fault classification, reasonable allocation of maintenance resources, and dynamic adjustment of maintenance plans, reducing wind turbine downtime losses and operation and maintenance costs, improving fault response speed and path economy, and ensuring that high-risk faults are handled first.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123160141A_ABST
    Figure CN123160141A_ABST
Patent Text Reader

Abstract

The application discloses a wind farm multi-dimensional fault grading operation and maintenance method and system based on a hierarchical scheduling architecture, relates to the technical field of intelligent operation and maintenance of wind farms, and comprises the following steps: collecting fault characteristic parameters, calculating a basic fault danger score, a shutdown loss score and a scheduling constraint score, performing normalization and nonlinear power operation aggregation on three-dimensional scores to obtain a fault comprehensive priority score, and dividing the fault into four grades; dividing independent node sets according to the grades, and executing strict step-by-step optimization scheduling; matching maintenance teams, vehicles, hoisting equipment and spare parts according to the optimization results; and calculating a virtual age after maintenance according to complete maintenance or incomplete maintenance, combining an AI intelligent analysis module to predict residual life and fault probability, and dynamically adjusting a proactive maintenance plan. The application solves the problems of major fault delay, resource waste and disconnection between passive maintenance and proactive maintenance, and reduces wind turbine shutdown loss and operation and maintenance risk.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of intelligent operation and maintenance technology for wind farms, specifically to a multi-dimensional fault classification and operation and maintenance method and system for wind farms based on a hierarchical scheduling architecture. Background Technology

[0002] Existing onshore wind farm fault dispatching methods mostly employ genetic algorithms, ant colony algorithms, bee colony algorithms, and other hybrid algorithms. However, these algorithms only aim for the shortest maintenance path and the optimal distance, excessively pursuing the highest profit, ignoring the differences in the severity of wind turbine faults, the weight of downtime losses, weather and terrain constraints, and the dynamic deterioration characteristics of faults. Furthermore, they lack a priority determination mechanism in the allocation of maintenance resources, which easily leads to problems such as minor faults consuming a large amount of resources, major faults delaying maintenance, fault escalation, and even unit scrapping, resulting in heavy losses in wind farm power generation and high operation and maintenance costs.

[0003] Specifically, existing technologies have the following shortcomings: they only use distance or cost as optimization objectives, ignoring the differences in the severity of wind turbine failures, the weight of downtime losses, weather and terrain constraints, and the dynamic deterioration characteristics of failures. The allocation of maintenance resources lacks a priority determination mechanism, easily leading to minor faults consuming large amounts of resources, major faults delaying maintenance, fault escalation, and even unit scrapping. Scoring methods often use linear weighted summation, which easily dilutes the scores of high-risk faults by lower-scoring dimensions, resulting in the downgrading of high-risk faults. Furthermore, the equipment lifespan is not dynamically adjusted after maintenance, and passive maintenance and proactive preventative maintenance are disconnected, failing to form a closed-loop optimization.

[0004] Therefore, a multi-dimensional fault classification and maintenance method and system for wind farms based on a hierarchical scheduling architecture is needed to achieve accurate fault classification, reasonable allocation of maintenance resources, and dynamic adjustment of maintenance plans. Summary of the Invention

[0005] The technical problem to be solved by the present invention is to address the shortcomings of the existing technology by providing a multi-dimensional fault classification and maintenance method and system for wind farms based on a hierarchical scheduling architecture.

[0006] To achieve the above objectives, the technical solution adopted by the present invention is as follows: The multi-dimensional fault classification and operation and maintenance method for wind farms based on a hierarchical scheduling architecture includes the following steps: Step S1: Collect the core characteristic parameters of the faulty wind turbine in real time through the wind farm SCADA system, wind turbine sensors and operation and maintenance terminals, and construct a fault characteristic dataset; Step S2: Based on the fault feature dataset, calculate the basic fault hazard score, downtime loss score, and scheduling constraint score. Divide each of the basic fault hazard score, downtime loss score, and scheduling constraint score by 100 to obtain three normalized scores. Subtract each normalized score from 1 to obtain three remainders. Exponenterate each of the three remainders with the corresponding weight coefficient as the exponent, and multiply the three exponentiation results to obtain a product. Subtract the product from 1, and finally multiply by 100 to obtain the comprehensive fault priority score. Divide the faults into four levels according to the comprehensive fault priority score. Step S3: Divide the faulty wind turbines into four independent node sets according to the fault level, and perform strict hierarchical optimization scheduling. Only after all path planning and scheduling of the previous level faults have been completed will the path optimization of the next level fault be started. Step S4: Based on the optimization results, schedule maintenance resources and match maintenance teams, work vehicles, hoisting equipment and spare parts; Step S5: After the repair is completed, calculate the virtual age after maintenance based on whether the repair method is complete or incomplete. Step S6: Input the virtual age after maintenance into the AI ​​intelligent analysis module to predict the remaining lifespan and failure probability of the component, and adjust the proactive maintenance plan accordingly.

[0007] Further, in step S1, the fault feature dataset includes: Basic fault indicators include turbine start / stop status, faulty components, fault alarm codes, and initial fault level; Loss weighting indicators include unit capacity, outage duration, unit outage power generation loss, and fault propagation risk coefficient; Dispatch constraints include on-site wind speed, precipitation, temperature, terrain and road conditions, road accessibility, maintenance team qualifications, spare parts inventory status, and the availability of hoisting equipment.

[0008] Furthermore, the downtime loss is determined based on the downtime, the current rated power of the wind turbine, the current economic loss per unit of electricity of the wind turbine, the rated power of the largest unit in the wind farm, and the highest economic loss per unit of electricity of the wind farm. The downtime loss is calculated by multiplying the downtime by the current rated power of the wind turbine, then by the current economic loss per unit of electricity of the wind turbine, dividing by the product of the rated power of the largest unit in the wind farm, 24, 1000, and the highest economic loss per unit of electricity of the wind farm, and then multiplying by 100. When the downtime loss is greater than 100, it is calculated as 100.

[0009] Furthermore, in step S2, the fault level classification rule is as follows: When the overall fault priority score is greater than or equal to 80, it is classified as a Level I critical fault and is subject to unconditional priority scheduling. When the overall fault priority score is greater than or equal to 60 and less than 80, it is classified as a Level II critical fault and is subject to second-priority scheduling. When the overall fault priority score is greater than or equal to 40 and less than 60, it is classified as a Level III emergency fault and is subject to regular orderly scheduling. When the overall fault priority score is less than 40, it is classified as a Level IV minor fault and is batch merged and scheduled.

[0010] Furthermore, in step S3, the strict step-by-step optimization scheduling includes: A comprehensive weight matrix is ​​constructed, the elements of which are obtained by multiplying the normalized value of the inter-node travel time and the normalized value of the inter-node travel distance by the time weight coefficient and the mileage weight coefficient respectively, and then summing them. Construct an inspection coverage matrix. When the actual travel distance between nodes is less than or equal to the inspection coverage threshold, the element of the inspection coverage matrix is ​​equal to 1 minus the ratio of the actual travel distance between nodes to the inspection coverage threshold. When the actual travel distance between nodes is greater than the inspection coverage threshold, the element of the inspection coverage matrix is ​​0. Level I faults aim for the shortest possible time, Level II faults aim for the optimal balance between time and mileage, Level III faults aim for the shortest possible driving mileage, and Level IV faults aim for the optimal inspection coverage.

[0011] Furthermore, in step S3, the ant colony algorithm is used for path optimization within the same level; when node j belongs to the set of nodes to be visited, the state transition probability of an ant moving from node i to node j is equal to the product of the information heuristic factor of the pheromone concentration raised to the power of the expected heuristic factor of the heuristic function raised to the power of the power of the power of the heuristic factor, divided by the sum of the corresponding products of all nodes to be visited; when node j does not belong to the set of nodes to be visited, the state transition probability is 0. The hierarchical heuristic functions are as follows: the heuristic function for level I faults is equal to the reciprocal of the normalized value of the inter-node travel time; the heuristic function for level II faults is equal to the reciprocal of the elements of the comprehensive weight matrix; the heuristic function for level III faults is equal to the reciprocal of the normalized value of the inter-node travel distance; and the heuristic function for level IV faults is equal to the ratio of the elements of the inspection coverage matrix to the normalized value of the inter-node travel distance.

[0012] Furthermore, in step S5, the method for determining the virtual age after maintenance is as follows: When the repair method is full repair, the virtual age after maintenance is 0; When the maintenance method is incomplete maintenance, the virtual age after maintenance is equal to the virtual age before maintenance multiplied by 1 minus the age reduction rate, then multiplied by an exponential term, and finally the load aging increment is added; the exponential term is based on the natural constant and uses the negative value of the product of the maintenance effect decay coefficient and the number of similar incomplete maintenance as the exponent. The load aging increment is obtained by integrating the ratio of the actual load power of the component to the rated load power of the component over time.

[0013] Furthermore, in step S6, the AI ​​intelligent analysis module receives the virtual age after maintenance, combines SCADA real-time data and historical maintenance records, calculates the predicted value of the remaining life of the component and its confidence interval, and performs a quantitative analysis of the cost-effectiveness of different maintenance schemes to generate the optimal maintenance strategy recommendation. The proactive maintenance plan dynamically adjusts the timing, target, and content of preventive maintenance based on the virtual age and remaining life prediction after maintenance.

[0014] A multi-dimensional fault classification and operation and maintenance system for wind farms based on a hierarchical scheduling architecture is provided to implement any of the aforementioned multi-dimensional fault classification and operation and maintenance methods for wind farms based on a hierarchical scheduling architecture, including: The data acquisition module is used to collect the core characteristic parameters of the faulty wind turbine through the SCADA system, wind turbine sensors and operation and maintenance terminals; The fault classification module is used to calculate the basic fault hazard score, downtime loss score, and scheduling constraint score. It calculates the comprehensive fault priority score by normalizing the scores of the three dimensions and aggregating them through nonlinear power operations, and classifies the faults into Level I, Level II, Level III, and Level IV. The fault classification and optimization module is used to divide the set of independent nodes according to the fault level and perform strict hierarchical optimization scheduling. The resource scheduling module is used to match maintenance teams, work vehicles, hoisting equipment and spare parts based on the optimization results; The lifespan adjustment module is used to calculate the virtual age after maintenance based on whether the maintenance is complete or incomplete. The AI ​​intelligent analysis module is used to predict the remaining lifespan and failure probability of components based on the virtual age after maintenance. The proactive maintenance adjustment module is used to dynamically adjust the proactive maintenance plan based on the output of the AI ​​intelligent analysis module.

[0015] Compared with the prior art, the beneficial effects of the present invention are as follows: 1. This invention calculates the comprehensive priority score of faults by normalizing the scores of three dimensions and using nonlinear exponentiation. An increase in the score of any dimension will significantly increase the total score through multiplication. Low-scoring dimensions will not linearly dilute high-scoring dimensions, thereby avoiding the downgrading of high-risk faults in the scoring and ensuring priority response to Level I and Level II high-risk faults.

[0016] 2. This invention adopts a virtual age formula after maintenance, and takes into account the diminishing effect of multiple incomplete repairs and the cumulative aging of load, so as to more accurately reflect the true aging degree of the components. The virtual age after maintenance is fed back to the AI ​​intelligent analysis module to realize the closed-loop linkage between passive maintenance and proactive preventive maintenance, thereby reducing the total downtime economic loss and operation and maintenance costs.

[0017] 3. This invention performs hierarchical optimization according to a strict priority of Level I > Level II > Level III > Level IV. The next level of optimization is only started after all path planning and scheduling of the previous level of faults have been completed. Different optimization objectives, heuristic functions and ant colony parameters are set for different levels to balance the response speed of high-risk faults and the path economy of low-risk faults, effectively reducing the number of algorithm convergence iterations.

[0018] 4. This invention integrates component aging data, equipment operating status, and maintenance resource configuration information from multiple dimensions through an AI intelligent analysis module. Combined with historical maintenance records and environmental parameters, it calculates the predicted remaining lifespan of components and its confidence interval in real time, and performs cost-benefit quantitative analysis on different maintenance schemes to generate optimal maintenance strategy recommendations. Attached Figure Description

[0019] Other features, objects, and advantages of the invention will become more apparent from the following detailed description of non-limiting embodiments with reference to the accompanying drawings: Figure 1 This is a flowchart illustrating an embodiment of the present invention; Figure 2 This is a schematic diagram of the system modules according to an embodiment of the present invention; Figure 3 This is a comparison chart of the average response times of four types of faults according to an embodiment of the present invention; Figure 4 This is a comparison chart of the core scheduling indicators in embodiments of the present invention; Figure 5 This is a comparison chart of the algorithm iterative convergence characteristics of embodiments of the present invention; Figure 6 This is a comparison diagram of the scheduling trajectories in an embodiment of the present invention. Detailed Implementation

[0020] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be described in detail below with reference to the accompanying drawings and specific embodiments.

[0021] Current wind farm maintenance and operation methods emphasize the balance between cost and power generation, aiming to find the optimal solution to help companies maximize profits. However, sometimes the optimal maintenance plan can delay the repair time of certain high-risk faults. This method seriously ignores the fact that if wind turbines experience certain major faults and cannot be repaired in time, it may lead to catastrophic wind farm accidents such as explosions or collapses. Once such accidents occur, they will not only negatively impact costs and power generation, but also pose a serious threat and damage to surrounding property, including other wind turbines, vehicles, buildings, and the lives of people in the surrounding area.

[0022] The purpose of this invention is to provide a multi-dimensional fault classification and maintenance method and system for wind farms based on a hierarchical scheduling architecture. This method addresses the problem by achieving accurate fault classification, rational allocation of maintenance resources, and dynamic adjustment of maintenance plans. It resolves the pain points of major fault delays, resource waste, and fault propagation, minimizing wind turbine downtime losses and maintenance risks, and helping wind farm-related companies maximize their profits. Specific objectives include: Construct a multi-dimensional fault priority scoring model that integrates risk level, downtime loss, and scheduling constraints to prevent high-risk faults from being diluted. A normalized and non-linear power calculation aggregation scoring formula is adopted to ensure that an increase in the score of any dimension can significantly increase the total score, thus prioritizing high-risk faults. The selection process is based on a strict priority system of Level I > Level II > Level III > Level IV, and skipping levels is prohibited. Different optimization objectives, heuristic functions, and ant colony parameters are set for different levels to balance the response speed of high-risk faults and the path economy of low-risk faults. The virtual age formula after maintenance is adopted to dynamically adjust the component lifespan, taking into account the effect decay and load aging accumulation after multiple incomplete repairs. By using an AI-powered intelligent analysis module, resources can be precisely matched and passive and proactive maintenance can be linked in a closed loop, reducing total downtime economic losses and operation and maintenance costs.

[0023] like Figure 1 As shown, the multi-dimensional fault classification and maintenance method for wind farms based on a hierarchical scheduling architecture includes the following steps: Step S1: Collect the core characteristic parameters of the faulty wind turbine in real time through the wind farm SCADA system, wind turbine sensors and operation and maintenance terminals, and construct a fault characteristic dataset; Step S2: Based on the fault feature dataset, calculate the basic fault hazard score, downtime loss score, and scheduling constraint score. Divide each of the basic fault hazard score, downtime loss score, and scheduling constraint score by 100 to obtain three normalized scores. Subtract each normalized score from 1 to obtain three remainders. Exponenterate each of the three remainders with the corresponding weight coefficient as the exponent, and multiply the three exponentiation results to obtain a product. Subtract the product from 1, and finally multiply by 100 to obtain the comprehensive fault priority score. Divide the faults into four levels according to the comprehensive fault priority score. Step S3: Divide the faulty wind turbines into four independent node sets according to the fault level, and perform strict hierarchical optimization scheduling. Only after all path planning and scheduling of the previous level faults have been completed will the path optimization of the next level fault be started. Step S4: Based on the optimization results, schedule maintenance resources and match maintenance teams, work vehicles, hoisting equipment and spare parts; Step S5: After the repair is completed, calculate the virtual age after maintenance based on whether the repair method is complete or incomplete. Step S6: Input the virtual age after maintenance into the AI ​​intelligent analysis module to predict the remaining lifespan and failure probability of the component, and adjust the proactive maintenance plan accordingly.

[0024] like Figure 2 As shown, a multi-dimensional fault classification and operation and maintenance system for wind farms based on a hierarchical scheduling architecture is used to implement any of the aforementioned multi-dimensional fault classification and operation and maintenance methods for wind farms based on a hierarchical scheduling architecture, including: The data acquisition module is used to collect the core characteristic parameters of the faulty wind turbine through the SCADA system, wind turbine sensors and operation and maintenance terminals; The fault classification module is used to calculate the basic fault hazard score, downtime loss score, and scheduling constraint score. It calculates the comprehensive fault priority score by normalizing the scores of the three dimensions and aggregating them through nonlinear power operations, and classifies the faults into Level I, Level II, Level III, and Level IV. The fault classification and optimization module is used to divide the set of independent nodes according to the fault level and perform strict hierarchical optimization scheduling. The resource scheduling module is used to match maintenance teams, work vehicles, hoisting equipment and spare parts based on the optimization results; The lifespan adjustment module is used to calculate the virtual age after maintenance based on whether the maintenance is complete or incomplete. The AI ​​intelligent analysis module is used to predict the remaining lifespan and failure probability of components based on the virtual age after maintenance. The proactive maintenance adjustment module is used to dynamically adjust the proactive maintenance plan based on the output of the AI ​​intelligent analysis module.

[0025] The data acquisition module is connected to the fault classification module and the AI ​​intelligent analysis module; the fault classification module is connected to the classification and optimization module; the classification and optimization module is connected to the resource scheduling module; the resource scheduling module is connected to the AI ​​intelligent analysis module and the life adjustment module; the AI ​​intelligent analysis module is connected to the proactive maintenance and adjustment module and the resource scheduling module; and the life adjustment module is connected to the AI ​​intelligent analysis module, forming a closed-loop data flow.

[0026] The data acquisition module collects the core characteristic parameters of faulty wind turbines in real time through the wind farm SCADA system, wind turbine sensors, and operation and maintenance terminals, and constructs a fault characteristic dataset, which specifically includes: 1. Basic fault indicators: wind turbine start-up and shutdown status, faulty components (gearbox, generator, blades, pitch system, main control system, electrical system, etc.), fault alarm codes, and initial fault level; 2. Loss weighting indicators: unit capacity, downtime, unit power generation loss during downtime, and fault propagation risk coefficient; 3. Dispatch constraints: On-site weather conditions such as wind speed, precipitation, and temperature; terrain and road conditions; road accessibility; maintenance team qualifications; spare parts inventory status; and the positioning of hoisting equipment.

[0027] The fault classification module constructs a fault priority scoring model based on the collected fault characteristics, calculates the comprehensive fault score through a quantitative formula, and then divides it into four levels (I, II, III, IV).

[0028] Basic Fault Hazard Classification The scoring system is based on the faulty component, alarm level, and safety risk, with a value range of 0-100. Critical component failures are scored 80-100 points, while minor component warnings are scored 0-20 points. The basic fault hazard score directly reflects the degree of danger inherent in the fault itself.

[0029] The specific formula for downtime loss is as follows:

[0030] in, Indicates the loss due to downtime. Indicates the duration of downtime. This indicates the current rated power of the wind turbine unit. This indicates the unit price of economic loss per unit of electricity generated by the wind turbine. This indicates the maximum rated power of the units in the wind farm. This represents the highest unit price of economic loss per unit of electricity among the units in the wind farm. When the downtime loss score is greater than 100, it is calculated as 100. The downtime loss score is calculated based on the maximum unit power and the highest unit price of economic loss per unit of electricity in the entire wind farm, representing the percentage of loss incurred by the current wind turbine during its downtime. The downtime loss scores for wind turbines with different power ratings and electricity prices are differentiated, with higher downtime loss scores for high-power, high-electricity-price turbines and lower downtime loss scores for low-power, low-electricity-price turbines.

[0031] Scheduling constraints The value ranges from 0 to 100, and is scored in reverse based on weather maintainability, terrain accessibility, and spare parts availability. The better the conditions, the higher the score. For example, when the weather is sunny, the roads are clear, and spare parts are plentiful, the scheduling constraint score is close to 100; when there is heavy rain, roads are blocked, and spare parts are scarce, the scheduling constraint score is close to 0.

[0032] The specific formula for the comprehensive fault priority score is as follows:

[0033] in, This represents the overall fault priority score, with a value ranging from 0 to 100. Indicates the basic fault risk level. Indicates the loss due to downtime. Indicates scheduling constraints. This represents a fixed weighting coefficient, typically taken as... .

[0034] The overall priority score for a fault is determined by normalizing the scores of the three dimensions, exponentiating them with the corresponding weight coefficients, and then combining the results. An increase in the score of any dimension will significantly increase the total score. Low-scoring dimensions will not linearly dilute high-scoring dimensions, thus ensuring that high-risk faults are not downgraded in the scoring.

[0035] The fault level is determined using a piecewise function, specifically including: Level I (Critical Fault, Highest Priority): S≥80, High Risk, High Loss, Unconditional Priority Dispatch. The wind turbine is already shut down and there are significant safety hazards, such as nacelle fire, blade breakage, gearbox seizure, or main shaft damage. Failure to repair in time will directly lead to the complete scrapping of the unit, causing personal injury or secondary grid accidents. The judgment logic is as follows: severe failure of key core components, exponentially increasing downtime losses, high risk of fault propagation, and unacceptable operation with defects. Level II (Critical Fault, Second Highest Priority): 60≤S<80, High Risk, Medium to Low Loss, Second Priority Dispatch. The wind turbine is shut down but there is no immediate safety risk; the fault is in a core component (e.g., abnormal generator windings, damaged pitch drive, inverter failure). Delayed repairs will significantly increase repair costs, prolong downtime, and exacerbate component wear. The judgment logic is as follows: major component fault, moderate downtime loss, low risk of spillover, and inability to operate at reduced load. Level III (Emergency Fault, Normal Priority): 40≤S<60, low risk, high loss, normal and orderly dispatch. Wind turbines can operate with reduced load due to defects. Minor component anomalies (such as sensor drift, cooling system failure, control cabinet alarms), while posing no safety risk, continuously reduce power generation efficiency and require repair within 3 working days. The judgment logic is as follows: minor component failure, minor downtime loss, no risk of propagation, and compensable by reduced load. Level IV (Minor Fault, Low Priority): S<40, low risk, low loss, batch scheduling. Only parameter warnings and false alarms for non-critical components, not affecting normal wind turbine power generation and safe operation. Can be batch repaired, wait for spare parts window, or handled during regular inspections. The judgment logic is as follows: non-core component warnings, negligible downtime losses, and zero risk of spread.

[0036] Starting from any maintenance station as the global dispatching point, independent sets of fault nodes are divided into four categories: I, II, III, and IV. A strict hierarchical maintenance mechanism is implemented, with strategy optimization for the next level of faults only initiated after all path planning and dispatching for the current level of faults have been completed. Cross-level skipping and mixed optimization are strictly prohibited to thoroughly ensure priority order. Customized constraints and optimization objectives are set for each level of fault, preserving the core priority of fault maintenance while achieving a precise balance between maintenance efficiency and cost through hierarchical optimization.

[0037] First, it is clearly defined that different levels of faults have different constraint rules. Second, it is clearly defined that different fault levels must strictly follow the priority scheduling rules, namely Level I > Level II > Level III > Level IV, and cross-level optimization is prohibited. Finally, for each level of fault, a multi-objective heuristic function, dedicated parameters, and pheromone update rules are customized, abandoning the single distance-oriented approach. This approach retains the priority advantage, solving the most dangerous and urgent tasks most quickly and efficiently, while using optimization algorithms to optimize the maintenance path for faults of the same level, reducing idle mileage and time consumption, and is fully compatible with the four-level fault classification system.

[0038] For different levels of faults, the optimization objectives are set differently: Level I aims for the fastest arrival, Level II aims for the shortest time, Level III aims for the shortest mileage, and Level IV aims for the best batch inspection, taking into account both scheduling efficiency and operation and maintenance costs.

[0039] Using a specific maintenance station as the global common starting point, the faulty fans are divided into four independent level node sets according to the fault classification results.

[0040] Constructing a hierarchical multi-objective foundation matrix, specifically including: The time consumption matrix represents the actual travel time from node i to j, taking into account road conditions, speed limits, terrain, and weather, and is adapted to the Level I shortest travel time target.

[0041] The distance matrix, representing the actual travel distance from node i to j, is adapted to the Level III shortest mileage target. The specific formula for the comprehensive weight matrix is ​​as follows:

[0042] in, Represents the comprehensive weight matrix. This represents the combined weight from node i to node j. This represents the normalized value of the actual travel time from node i to j. This represents the normalized value of the actual travel distance from node i to j. This represents the time-mileage weighting factor, taken as... .

[0043] The specific formula for the inspection coverage matrix is:

[0044] in, Represents the inspection coverage matrix. This represents the inspection coverage correlation degree from node i to node j. This represents the actual travel distance from node i to node j. This indicates the inspection coverage threshold, which is usually set to 5km. The value can be adjusted according to the wind turbine layout density in the wind farm; the higher the density, the smaller the threshold.

[0045] The hierarchical optimization target locking specifically includes: Level I: shortest time consumption, with the time consumption matrix as the core; Level II: optimal balance between time consumption and mileage, with the comprehensive weight matrix as the core; Level III: shortest travel mileage, with the distance matrix as the core; Level IV: optimal inspection route, with the inspection coverage matrix as the core, allowing detours.

[0046] The specific differential assignment of parameters for hierarchical ant colonies includes: Number of ants: approximately 1.5 times the number of faulty fans, balancing optimization accuracy and computational speed; Information heuristic factor: typically ranging from 1.0 to 4.0, representing the weight of pheromone influence on path selection; Expected heuristic factor: typically ranging from 3.0 to 4.5, representing the weight of the influence of path distance (or time) on path selection; Pheromones evaporation coefficient: The value is generally 0.5 to balance global exploration and local development and avoid premature convergence; Initial pheromone concentration: uniformly assigned a value of 0.1 to ensure fairness in initial path selection; Maximum number of iterations: The value ranges from 100 to 200 to meet the convergence requirements and avoid invalid iterations; Convergence threshold: If the optimal path remains unchanged for 30 consecutive iterations, it is considered converged and the optimization process is terminated.

[0047] For the different optimization objectives of the four types of faults, customized parameter combinations are used to guide the ants to converge toward the corresponding objectives by different information heuristic factors, iteration numbers, and convergence thresholds. The specific parameters are shown in Table 1. Table 1:

[0048] Among these features, the differentiated assignment strictly adheres to the general standard range of the ant colony algorithm and the actual operation and maintenance of small and medium-sized wind farms. It sets the base number of faulty wind turbines based on the fault distribution pattern (the fewest in Level I and the most in Level IV), and the number of ants is calculated by rounding down to the number of faulty turbines by 1.5 times, balancing optimization accuracy and computational efficiency. The gradients of the information heuristic factor and the expected heuristic factor are adapted to the hierarchical objectives. Level I critical faults prioritize timeliness and increase the expected heuristic factor value to weaken pheromone dependence. Level III faults prioritize path accumulation and increase the information heuristic factor value to strengthen path inheritance. Level IV faults balance inspection flexibility and use mild parameters. The pheromone evaporation coefficient and the initial pheromone concentration are uniformly set to standard values ​​to ensure a balance between global exploration and local development. The maximum number of iterations increases gradient with the number of faults, and the convergence threshold is uniformly set to 30 consecutive iterations without updating the optimal solution, which satisfies the convergence requirements and eliminates invalid iterations, fully aligning with the core logic of hierarchical scheduling and the actual operation scenarios of wind farms.

[0049] Abandoning the traditional single heuristic model of ant colonies, we customize exclusive heuristic functions for optimization goals at each level. When ants move between faulty nodes, they strictly follow the state transition probability formula of the corresponding level to achieve targeted optimization.

[0050] The state transition probability represents the probability that an ant will move from node i to node j. Unvisited nodes are included in the selection range, while visited nodes are removed. The specific formula is as follows:

[0051] in, Let represent the probability that ant k moves from node i to node j. Indicates pheromone concentration. Represents a heuristic function. Represents information heuristic factors, Represents the expected heuristic factor. Represents the set of nodes that ant k needs to visit; The hierarchical heuristic function differentiation is defined as follows: Level I (Shortest processing time): The shorter the time taken, the stronger the inspiration and attraction, forcing ants to prioritize the shortest path. Level II (Optimal Balance): Balancing efficiency and cost; Level III (shortest mileage): The shorter the distance, the higher the heuristic weight, thus achieving optimal mileage. Level IV (Optimal Inspection): It takes into account both coverage and distance, and prioritizes nodes with high coverage correlation to facilitate batch maintenance.

[0052] To avoid premature convergence and local optima in the algorithm, a two-layer pheromone update rule with global and local parameters is adopted, combined with a hierarchical evaporation coefficient, to achieve dynamic regulation of pheromones and ensure a balance between optimization accuracy and convergence speed.

[0053] Each time an ant completes a node transfer, it immediately performs a local evaporation update on the current path to weaken the pheromone residue on poor-quality paths. The specific formula is as follows:

[0054] in, This indicates the pheromone volatility coefficient for the corresponding level. This represents the initial pheromone concentration, uniformly assigned a value of 0.1 to ensure fairness in path exploration during the initial iteration.

[0055] After a single iteration, pheromone enhancement is performed only on the current optimal path to strengthen the guiding role of high-quality paths. The specific formula is as follows:

[0056] in, This represents the pheromone enhancement coefficient, uniformly assigned a value of 100. This represents the objective function value of the current optimal path. Level I uses the total time, Level II uses the weighted composite value, Level III uses the total mileage, and Level IV uses the coverage-weighted value. This indicates that after this iteration, in order to strengthen high-quality paths, an additional amount of pheromone is added to the path.

[0057] Based on the above, the optimization process for each level of fault is as follows: The first step is initialization. Load the set of faulty nodes of the corresponding level, the multi-objective matrix, and the specific parameters; set the initial pheromone concentration and the iteration counter; and place the ants at the starting point of the repair station. The second step is node traversal. Based on the state transition probability of the corresponding level, the ants sequentially traverse the faulty nodes to be visited until all nodes have been visited, generating a single path. The third step is objective function calculation. Calculate the objective function value for each path and record the optimal path and optimal value for the current iteration. The fourth step is pheromone updating. Following local and global update rules, the pheromone concentration of each path is updated, and inferior paths are eliminated. Step 5, convergence determination. Determine whether the maximum number of iterations or the convergence threshold has been reached. If not, increment the iteration counter by 1 and return to the node traversal steps; if the threshold is met, terminate the iteration and output the optimal maintenance path for that level.

[0058] Only after all path planning and dispatching for a fault of this level have been completed can the optimization process for the next level of fault begin.

[0059] After obtaining the optimal repair plan through the grading and optimization module, repair resources such as personnel, vehicles, and parts are allocated. Here, the AI ​​intelligent analysis module analyzes the data before assigning specific repair tasks. The AI ​​intelligent analysis module mainly considers who should be assigned the repair task, what kind of vehicle is needed, and what parts need to be brought. For example, in personnel allocation, priority is given to those with available time, followed by those with similar or identical repair experience to help resolve the repair more efficiently, and finally, factors such as gender and age are considered.

[0060] After maintenance, the equipment's lifespan is adjusted based on the type of maintenance, and the proactive maintenance plan is dynamically adjusted accordingly. Here, maintenance methods are directly divided into complete repair and incomplete repair. Complete repair refers to replacing all parts with brand new ones, while incomplete repair involves repairing parts that are already in use.

[0061] The specific formula for virtual age after maintenance is as follows:

[0062] in, This represents the virtual age of component z after maintenance in wind turbine f. Indicates the fan number. Indicates the component number. Indicates the virtual age before maintenance. This represents the age reduction rate, with critical components taking 0.90 ≤ q ≤ 0.95 and minor components taking 0.80 ≤ q ≤ 0.89. This represents the attenuation coefficient of the repair effect, with a value ranging from 0.01 to 0.1. Indicates the number of times the same type of incomplete repair has been performed. The formula for representing the load aging increment is as follows:

[0063] in, Indicates the start time of the statistics. Indicates the current moment. Represents the integral variable. This represents the actual load power of component z. This indicates the rated load power of component z.

[0064] The virtual age after maintenance is determined by the virtual age before maintenance, the age reduction rate, the number of similar incomplete repairs, the repair effectiveness attenuation coefficient, and the load aging increment. The age reduction rate characterizes the degree to which this incomplete repair reduces component aging; the number of similar incomplete repairs and the repair effectiveness attenuation coefficient together reflect the decreasing trend in repair effectiveness after multiple incomplete repairs; the load aging increment is determined by the integral of the ratio of the component's actual load power to its rated load power over time, characterizing the additional aging caused by load accumulation during operation. This virtual age more accurately reflects the true aging degree of the component, providing a reliable basis for proactive maintenance planning.

[0065] The results from this module, after being processed by the AI ​​intelligent analysis module, enable dynamic adjustments to proactive maintenance plans. For example, if a wind turbine component was originally scheduled for preventative maintenance a month later, but lifespan prediction reveals that its lifespan is shortening, the preventative maintenance plan can be scheduled in advance.

[0066] The AI ​​intelligent analysis module is the core analysis and decision support unit of the entire wind farm maintenance and operation system. It runs through the process of resource scheduling and proactive maintenance plan adjustment, receives output data from multiple modules, and completes comprehensive judgment and optimization analysis.

[0067] This module first integrates component aging data from the lifespan adjustment module and equipment operating status and maintenance resource configuration information from the resource scheduling module from multiple dimensions. Through a constructed deep learning model, it extracts features and recognizes patterns in the data to identify key factors affecting component lifespan and potential failure risks. Simultaneously, by combining historical maintenance records, environmental parameters, and other external data, a dynamic evaluation model is established to calculate the predicted remaining lifespan and its confidence interval for each wind turbine component in real time. Based on this, the module can quantitatively analyze the cost-effectiveness of different maintenance schemes, including factors such as maintenance time windows, resource input, and downtime losses. Through a multi-objective optimization algorithm, it generates optimal maintenance strategy recommendations, providing a scientific basis for subsequent proactive maintenance adjustment modules to ensure that wind farm operation and maintenance achieve efficient resource utilization and precise control of maintenance costs while guaranteeing safe equipment operation.

[0068] During the resource scheduling phase, this module receives the optimal maintenance path and scheduling plan output by the grading and optimization module. Combined with the actual maintenance resource reserves of the wind farm, it accurately matches and allocates various resources such as maintenance personnel, work vehicles, and spare parts. Regarding personnel allocation, the module prioritizes screening maintenance personnel currently without work assignments and with available time. Then, based on their past maintenance experience, it prioritizes matching personnel with experience in repairing similar or identical faults. It also comprehensively considers objective factors such as age and gender to ensure the efficiency and rationality of the maintenance team's operations. In equipment and spare parts allocation, it matches suitable maintenance vehicles and hoisting equipment according to the fault type and maintenance requirements, while verifying spare parts inventory status to ensure timely supply of necessary spare parts and avoid maintenance delays due to resource mismatch.

[0069] During the proactive maintenance plan adjustment phase, this module receives data such as the virtual age and remaining lifespan of components from the lifespan adjustment module. Combined with real-time equipment operation data collected by the wind farm's SCADA system and sensors, it continuously analyzes and predicts the operating status, aging trends, and failure probabilities of various wind turbine components. Through big data analysis and algorithm modeling, the module can identify abnormal trends in component operation, predict potential failure risks, and scientifically optimize the proactive maintenance plan in conjunction with the wind farm's overall operation and maintenance planning and resource allocation schedule.

[0070] In addition, the AI ​​intelligent analysis module will also collect and analyze relevant data from the entire maintenance and operation process, summarize maintenance patterns, resource allocation efficiency, and operation and maintenance costs for different types of faults, provide data support for subsequent fault classification, grading and optimization, and realize the self-optimization and iteration of the entire operation and maintenance system.

[0071] The core design purpose of the proactive maintenance and adjustment module is to achieve effective linkage between passive fault maintenance and proactive preventive maintenance in wind farms, enabling the two maintenance modes to connect and exchange data, thereby strengthening the pertinence and effectiveness of proactive maintenance and further enhancing the practical application value of the entire operation and maintenance system.

[0072] This module relies heavily on various data output from the life adjustment module and AI intelligent analysis module in the passive maintenance process, including the repair methods of faulty components, virtual age after maintenance, component aging trends, and fault risk prediction results. It fully integrates the actual operating status of equipment and fault repair information obtained in passive maintenance into the formulation and adjustment of proactive maintenance plans.

[0073] Through this collaborative design, proactive maintenance is no longer based on fixed-cycle routine planning. Instead, it dynamically optimizes the timing, targets, and content of preventative maintenance by combining the actual fault repair status of equipment and changes in component aging, making proactive maintenance plans more aligned with the real operational needs of the equipment. Simultaneously, the effective combination of these two maintenance modes allows the entire operation and maintenance system to both quickly respond to sudden fault repair needs and proactively avoid potential faults through precise proactive maintenance. This ensures the system fully leverages its capabilities in both reactive and proactive prevention, maximizing the overall operational efficiency of the wind farm.

[0074] Results of the implementation of the plan: The specific parameter assignments for the scheme are shown in Table 1. Q is uniformly assigned a value of 100. The following are the scheduling simulations of three sets of algorithms under the same conditions: 1. Option A is a traditional algorithm, namely the classic ant colony algorithm based purely on distance. It only aims to minimize the total distance and does not distinguish between fault priorities.

[0075] 2. Option B is a rule-based algorithm, i.e., a pure priority-based greedy scheduling. It strictly follows the order of I, II, III, IV for repairs, but within the same priority level, it adopts the nearest principle (greedy algorithm).

[0076] 3. Solution C, the solution of this patent, is a combination of multi-dimensional ranking and differentiated ant colony optimization. It strictly implements step-by-step optimization and uses an ant colony algorithm with customized parameters within the same level.

[0077] The simulation environment is built using Python. First, a synthetic dataset containing wind turbine coordinates (x, y) and fault characteristics (randomly assigned components, downtime, etc.) is randomly generated using NumPy. Then, a main scheduling framework is written, calling both the standard ant colony algorithm and the ant colony algorithm proposed in this patent, which is optimized using a hierarchical classification approach. Finally, a data comparison chart is plotted.

[0078] Table 2 shows a comparison of the average response times of the three scheduling algorithms for four types of faults: Table 2:

[0079] 1. Compare the average response times of the three scheduling algorithms under four types of faults, specifically as follows: Figure 3 As shown.

[0080] Depend on Figure 3 It can be seen that for Level I fault response time, scheme C is much better than scheme A and about the same as scheme B; for Level II fault response time, scheme C is much better than scheme A and slightly better than scheme B; for Level III fault response time, scheme C is better than scheme A but better than scheme B; for Level IV fault response time, scheme C is better than scheme A but better than scheme B.

[0081] This demonstrates that the patented solution, namely Solution C, effectively meets our goal of resolving Level I and Level II faults more quickly and efficiently. Furthermore, in resolving Level III and Level IV faults, it also outperforms general optimizations of ant colony algorithms in terms of fault response time.

[0082] 2. Conduct a three-way comparison of core scheduling indicators, specifically as follows: Figure 4 As shown.

[0083] Depend on Figure 4 It is evident that in terms of total mileage, Scheme C is superior to Scheme A but inferior to Scheme B; while in terms of total economic loss, Scheme C outperforms both Scheme A and Scheme B. Therefore, Scheme C, as presented in this patent, effectively achieves the goal of reducing total economic loss. Although its total mileage is relatively high, in actual wind farm management, ensuring the safe and stable operation of wind turbines and avoiding serious economic losses are more crucial.

[0084] 3. Compare the iterative convergence characteristics of the algorithms, specifically as follows: Figure 5 As shown.

[0085] Depend on Figure 5 It is evident that, in terms of algorithmic convergence characteristics, for the comprehensive iterative value of optimization within the same level, Scheme C outperforms Scheme B and is far superior to Scheme A. Therefore, this patented scheme (i.e., Scheme C) effectively reduces the number of iterations required for algorithm convergence and lowers the computational load.

[0086] 4. Compare the scheduling trajectories, comparing scheme B and scheme C, such as... Figure 6 As shown.

[0087] from Figure 6 It can be seen that the trajectory of Scheme B lacks global planning and suffers from route intersections and detours; the trajectory of Scheme C, on the other hand, has clear path hierarchy and is globally optimal. It should be noted that a comparison with the planned path of Scheme A is not discussed here, because Scheme A itself only aims at the shortest path and does not consider other benefits, and its final path is basically optimal, so comparing its trajectory diagrams is not very meaningful.

[0088] From the above, we can conclude that, firstly, this patented solution (i.e., Solution C) overcomes the fatal flaw of the traditional algorithm (compared to Solution A). Traditional Algorithm A simply pursues the shortest total mileage (115.5km), resulting in an average response time of up to 4.65 hours for the most dangerous Level I faults. This misguided scheduling method leads to a total downtime economic loss of up to 1.856 million yuan. The solution of this invention, through hierarchical optimization, compresses the Level I fault response time to 0.84 hours, improving economic loss mitigation efficiency by 81.9%.

[0089] Secondly, this patented solution addresses the resource waste inherent in pure priority scheduling (compared to Algorithm B). While conventional priority algorithm B can respond quickly to Level I faults, its lack of global path planning within the same level results in blindly greedy scheduling, leading to a surge in total mileage to 245.8 km and wasting vehicle and human resources. The algorithm in this invention utilizes a customized multi-objective matrix, considering the weights of the time-consuming and distance matrices, optimizing and controlling the total mileage within a reasonable range of 138.2 km while prioritizing high-risk faults.

[0090] Third, this patented solution improves the algorithm's convergence performance. In terms of computational performance, because this invention sets differentiated parameters for different levels of faults, such as the information heuristic factor and the expectation heuristic factor, it effectively avoids the problems of traditional ant colony algorithms easily getting trapped in local optima and having slow convergence speed. Under the unified test conditions set by this solution, the algorithm of this invention only requires 42 iterations to converge, significantly better than the 75 iterations of the traditional algorithm, fully demonstrating its computational efficiency in large-scale node scheduling scenarios in wind farms.

[0091] Finally, this embodiment selects the ant colony algorithm as the optimization engine within the same level. If other algorithms such as genetic algorithms are used, the above-mentioned time consumption matrix, distance matrix, comprehensive weight matrix, and inspection coverage matrix can be used as inputs to the fitness function, and the corresponding fitness expression and selection, crossover, and mutation strategies can be set according to the hierarchical objectives. The hierarchical scheduling effect can also be achieved, basically achieving similar optimization, providing assistance for wind farm maintenance work, and has good universality.

[0092] The examples described herein are merely preferred embodiments of the invention and are not intended to limit the concept and scope of the invention. Any modifications and improvements made by those skilled in the art to the technical solutions of the invention without departing from the design concept of the invention should fall within the protection scope of the invention.

Claims

1. A multi-dimensional fault classification and maintenance method for wind farms based on a hierarchical scheduling architecture, characterized in that, Includes the following steps: Step S1: Collect the core characteristic parameters of the faulty wind turbine in real time through the wind farm SCADA system, wind turbine sensors and operation and maintenance terminals, and construct a fault characteristic dataset; Step S2: Based on the fault feature dataset, calculate the basic fault hazard score, downtime loss score, and scheduling constraint score. Divide each of the basic fault hazard score, downtime loss score, and scheduling constraint score by 100 to obtain three normalized scores. Subtract each normalized score from 1 to obtain three remainders. Exponenterate each of the three remainders with the corresponding weight coefficient as the exponent, and multiply the three exponentiation results to obtain a product. Subtract the product from 1, and finally multiply by 100 to obtain the comprehensive fault priority score. Divide the faults into four levels according to the comprehensive fault priority score. Step S3: Divide the faulty wind turbines into four independent node sets according to the fault level, and perform strict hierarchical optimization scheduling. Only after all path planning and scheduling of the previous level faults have been completed will the path optimization of the next level fault be started. Step S4: Based on the optimization results, schedule maintenance resources and match maintenance teams, work vehicles, hoisting equipment and spare parts; Step S5: After the repair is completed, calculate the virtual age after maintenance based on whether the repair method is complete or incomplete. Step S6: Input the virtual age after maintenance into the AI ​​intelligent analysis module to predict the remaining lifespan and failure probability of the component, and adjust the proactive maintenance plan accordingly.

2. The wind farm multi-dimensional fault classification and maintenance method based on a hierarchical scheduling architecture according to claim 1, characterized in that, In step S1, the fault feature dataset includes: Basic fault indicators include turbine start / stop status, faulty components, fault alarm codes, and initial fault level; Loss weighting indicators include unit capacity, outage duration, unit outage power generation loss, and fault propagation risk coefficient; Dispatch constraints include on-site wind speed, precipitation, temperature, terrain and road conditions, road accessibility, maintenance team qualifications, spare parts inventory status, and the availability of hoisting equipment.

3. The wind farm multi-dimensional fault classification and maintenance method based on a hierarchical scheduling architecture according to claim 2, characterized in that, The downtime loss is determined based on the downtime, the current rated power of the wind turbine, the current economic loss per unit of electricity of the wind turbine, the rated power of the largest unit in the wind farm, and the highest economic loss per unit of electricity of the wind farm. The downtime loss is calculated by multiplying the downtime by the current rated power of the wind turbine, then by the current economic loss per unit of electricity of the wind turbine, dividing by the product of the rated power of the largest unit in the wind farm, 24, 1000, and the highest economic loss per unit of electricity of the wind farm, and then multiplying by 100. When the downtime loss is greater than 100, it is calculated as 100.

4. The wind farm multi-dimensional fault classification and maintenance method based on a hierarchical scheduling architecture according to claim 3, characterized in that, In step S2, the fault level classification rule is as follows: When the overall fault priority score is greater than or equal to 80, it is classified as a Level I critical fault and is subject to unconditional priority scheduling. When the overall fault priority score is greater than or equal to 60 and less than 80, it is classified as a Level II critical fault and is subject to second-priority scheduling. When the overall fault priority score is greater than or equal to 40 and less than 60, it is classified as a Level III emergency fault and is subject to regular orderly scheduling. When the overall fault priority score is less than 40, it is classified as a Level IV minor fault and is batch merged and scheduled.

5. The wind farm multi-dimensional fault classification and maintenance method based on a hierarchical scheduling architecture according to claim 4, characterized in that, In step S3, the strict step-by-step optimization scheduling includes: A comprehensive weight matrix is ​​constructed, the elements of which are obtained by multiplying the normalized value of the inter-node travel time and the normalized value of the inter-node travel distance by the time weight coefficient and the mileage weight coefficient respectively, and then summing them. Construct an inspection coverage matrix. When the actual travel distance between nodes is less than or equal to the inspection coverage threshold, the element of the inspection coverage matrix is ​​equal to 1 minus the ratio of the actual travel distance between nodes to the inspection coverage threshold. When the actual travel distance between nodes is greater than the inspection coverage threshold, the element of the inspection coverage matrix is ​​0. Level I faults aim for the shortest possible time, Level II faults aim for the optimal balance between time and mileage, Level III faults aim for the shortest possible driving mileage, and Level IV faults aim for the optimal inspection coverage.

6. The multi-dimensional fault classification and maintenance method for wind farms based on a hierarchical scheduling architecture as described in claim 5, characterized in that, In step S3, the ant colony algorithm is used to optimize the path within the same level. When node j belongs to the set of nodes to be visited, the state transition probability of an ant moving from node i to node j is equal to the product of the information heuristic factor of the pheromone concentration raised to the power of the expected heuristic factor of the heuristic function raised to the power of the power of the heuristic factor, divided by the sum of the corresponding products of all nodes to be visited. When node j does not belong to the set of nodes to be visited, the state transition probability is 0. The hierarchical heuristic functions are as follows: the heuristic function for level I faults is equal to the reciprocal of the normalized value of the inter-node travel time; the heuristic function for level II faults is equal to the reciprocal of the elements of the comprehensive weight matrix; the heuristic function for level III faults is equal to the reciprocal of the normalized value of the inter-node travel distance; and the heuristic function for level IV faults is equal to the ratio of the elements of the inspection coverage matrix to the normalized value of the inter-node travel distance.

7. The wind farm multi-dimensional fault classification and maintenance method based on a hierarchical scheduling architecture according to claim 6, characterized in that, In step S5, the virtual age after maintenance is determined as follows: When the repair method is full repair, the virtual age after maintenance is 0; When the maintenance method is incomplete maintenance, the virtual age after maintenance is equal to the virtual age before maintenance multiplied by 1 minus the age reduction rate, multiplied by an exponential term, and finally added to the load aging increment. The exponent term has a natural constant as its base and uses the negative value of the product of the maintenance effect decay coefficient and the number of incomplete maintenance of the same type as its exponent. The load aging increment is obtained by integrating the ratio of the actual load power of the component to the rated load power of the component over time.

8. The multi-dimensional fault classification and maintenance method for wind farms based on a hierarchical scheduling architecture as described in claim 7, characterized in that, In step S6, the AI ​​intelligent analysis module receives the virtual age after maintenance, combines SCADA real-time data and historical maintenance records, calculates the predicted value of the remaining life of the component and its confidence interval, and performs a quantitative analysis of the cost-effectiveness of different maintenance schemes to generate the optimal maintenance strategy recommendation. The proactive maintenance plan dynamically adjusts the timing, target, and content of preventive maintenance based on the virtual age and remaining life prediction after maintenance.

9. A wind farm multi-dimensional fault classification and operation and maintenance system based on a hierarchical scheduling architecture, used to implement the wind farm multi-dimensional fault classification and operation and maintenance method based on a hierarchical scheduling architecture as described in any one of claims 1-8, characterized in that, include: The data acquisition module is used to collect the core characteristic parameters of the faulty wind turbine through the SCADA system, wind turbine sensors and operation and maintenance terminals; The fault classification module is used to calculate the basic fault hazard score, downtime loss score, and scheduling constraint score. It calculates the comprehensive fault priority score by normalizing the scores of the three dimensions and aggregating them through nonlinear power operations, and classifies the faults into Level I, Level II, Level III, and Level IV. The fault classification and optimization module is used to divide the set of independent nodes according to the fault level and perform strict hierarchical optimization scheduling. The resource scheduling module is used to match maintenance teams, work vehicles, hoisting equipment and spare parts based on the optimization results; The lifespan adjustment module is used to calculate the virtual age after maintenance based on whether the maintenance is complete or incomplete. The AI ​​intelligent analysis module is used to predict the remaining lifespan and failure probability of components based on the virtual age after maintenance. The proactive maintenance adjustment module is used to dynamically adjust the proactive maintenance plan based on the output of the AI ​​intelligent analysis module.