Method and system for dynamic management and control of engineering whole-process cost based on multi-source data fusion

By using multi-source data fusion technology, multilayer perceptron, graph convolutional network and bidirectional Mamba-2 text encoder to generate modal tokens, construct engineering cost association graph, and apply coded virtual intervention, the problem of cross-stage object connection and multimodal fusion in the dynamic control of engineering cost throughout the whole process is solved, and the unified representation and refined control of cost status are realized.

CN123160215APending Publication Date: 2026-11-24GUANGDONG JIANWEI ENG CONSULTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611391707.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-09
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing methods for dynamic cost control throughout the entire engineering process have limitations in cross-stage object integration, multimodal deep feature extraction, reliable fusion of conflicting modes, and separation of control and natural cost drift.

Method used

Modal tokens are generated based on multilayer perceptron, graph convolutional network, bidirectional Mamba-2 text encoder and convolutional neural network. Modal weights are generated through modal credibility gating network. Engineering cost correlation graph is constructed, coded virtual intervention is applied, cost control response matrix is ​​generated, and prediction results are corrected by engineering constraints and contract constraints. Target control measures are selected.

Benefits of technology

It achieves object-level and periodic-level alignment of different modal information, improves the completeness, accuracy and traceability of cost status identification, reduces the impact of modal missing, temporal misalignment and information conflict, and enhances the enforceability of control measures and the dynamic adaptability of cost prediction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123160215A_ABST
    Figure CN123160215A_ABST
Patent Text Reader

Abstract

This invention relates to the field of engineering cost management, providing a method and system for dynamic control of engineering costs throughout the entire process based on multi-source data fusion. The method involves acquiring original cost datasets, establishing a cross-stage cost object chain, and forming cost evidence units. Modal tokens are generated, and modal weights are generated through a gating network. These weights are then propagated via bidirectional Mamba-2 propagation and gating merging to form multimodal cost state fingerprints. An engineering cost correlation graph is constructed using cost evidence units as nodes. Virtual interventions are applied to control variables, propagating their influence along the engineering cost correlation graph. Response coefficients are calculated using modal credibility weights to generate a cost control response matrix. The theoretical impact of existing control measures is deducted to obtain the natural cost drift sequence. Predictive results are output through a gating cyclic unit prediction network and corrected using engineering and contract constraints. The candidate control measure with the smallest expected settlement cost deviation is selected as the target control measure. This effectively improves the accuracy and adaptability of cost control throughout the entire process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of engineering cost management technology, and in particular relates to a method and system for dynamic control of engineering cost throughout the entire process based on multi-source data fusion. Background Technology

[0002] Construction cost management spans the entire process of a construction project, from investment decision-making, design, bidding, construction, to final settlement. Its core task is to accurately estimate, control, and calculate project costs at each stage. With the continuous expansion of construction scale and the increasing complexity of construction models, construction cost management is shifting from traditional phased, static accounting to a more comprehensive, dynamic, and refined approach. At each stage of a construction project, cost information includes not only structured numerical data such as investment estimates, budgets, bills of quantities, bid prices, and progress measurements, but also spatial topological information from building information models, textual semantic information from contracts and change orders, and image information from the construction site. These information differ significantly in data structure, semantic hierarchy, and time scale. Traditional methods struggle to uniformly correlate the status of the same project content at different stages and in different modalities, leading to difficulties in timely detection of cost risks, difficulty in tracing change orders, and frequent settlement disputes.

[0003] Currently, the main methods for dynamic cost control throughout the entire project process include the following: Firstly, there is the dynamic cost management method based on Building Information Modeling (BIM). This method establishes a three-dimensional parametric model to link design components with cost information, enabling dynamic linkage between investment estimation, bill of quantities preparation, construction phase cost monitoring, and final settlement review. This type of method is relatively mature and offers a high degree of visualization. However, it typically relies on a single BIM software platform, and the lack of unified data standards between different software programs leads to poor data interoperability among design, cost, and construction parties. Furthermore, BIM modeling costs are high, making it uneconomical for small and medium-sized projects, and cost updates after changes often lag behind the actual project progress.

[0004] Secondly, there is the cost-schedule joint control method based on Earned Value Management (EVM). This method calculates cost performance indices and schedule performance indices using three indicators: planned value, earned value, and actual cost, monitoring project cost and schedule deviations under a unified monetary scale. Existing technologies decompose the core calculation parameters of EVM into the individual component models within the BIM parametric model, linking the EVM calculation formulas with the construction progress data, work completion data, and cost data of the component models to construct a dynamic calculation system. This method offers simple indicators and is easy to summarize. However, because cost expenditures substitute for physical progress, it leads to distorted schedule measurement. Furthermore, traditional EVM ignores the critical path relationships between activities, failing to effectively identify delayed tasks, and the schedule performance index tends to become ineffective at the end of the project, making it difficult to reflect the true schedule risks in a timely manner.

[0005] Engineering cost prediction methods based on Back Propagation Neural Network (BPNN) or Radial Basis Function Neural Network (RBFNN) collect historical engineering cost samples and use neural networks to establish a nonlinear mapping relationship between engineering features and costs for investment estimation or settlement cost prediction. However, these methods typically use structured numerical fields as uniform input, making it difficult to extract deep features from BIM spatial topology, contract and change document semantics, and construction site images. Even when data from different sources are directly spliced, reliability differences caused by missing modalities, temporal misalignments, and cross-modal conflicts are not distinguished. When using cross-modal fusion based on global attention, the growth of the joint sequence increases the computational load, and it is difficult to directly apply modal credibility to the cross-modal state transmission process. Furthermore, these methods lack separation between the effects of control measures and the influence of non-control factors, making it difficult for prediction results to directly support traceable dynamic management.

[0006] In summary, existing dynamic cost control for the entire engineering process still has limitations in terms of cross-stage object integration, multimodal deep feature extraction, reliable fusion of conflict modes, and separation of control from natural cost drift. Summary of the Invention

[0007] To address the problems existing in the prior art, this invention provides a method for dynamic cost control throughout the entire engineering process based on multi-source data fusion, comprising the following steps: Step S1: Divide the cost control cycle based on the project stage nodes and the occurrence time of cost events, and obtain the original cost dataset within the cost control cycle; establish a cross-stage cost object chain with project functional items, design components, bill of quantities items, construction tasks, and settlement items as cost objects for different project stages; attach cost evidence to the corresponding cross-stage cost object chain to form a cost evidence unit; the cost evidence includes contract terms, design changes, site instructions, material procurement records, progress measurement data, construction site images, and payment records; Step S2: Modal tokens are generated using a multilayer perceptron, graph convolutional network, bidirectional Mamba-2 text encoder, and convolutional neural network. The modal tokens are then attached to the cost evidence unit. Modal weights are generated using a modal credibility gating network. The credibility weighted token, modal type encoding, object location encoding, and learnable fusion token are combined into a joint sequence. This sequence is then processed by bidirectional Mamba-2 selective state propagation and gating merging to form a multimodal cost state fingerprint. Simultaneously, an engineering cost association graph is constructed using the cost evidence unit as nodes. Step S3: Apply coded virtual intervention to the control variables in the engineering cost digital mapping space; propagate the impact of the virtual intervention along the engineering cost correlation graph, and calculate the response coefficient of each control variable to the cost status component in combination with the modal confidence weight to generate the cost control response matrix; use the cost control response matrix to subtract the theoretical impact of the existing control measures on the cost status component from the actual cost status component changes to obtain the natural cost drift sequence. Step S4: Input the natural cost drift sequence and multimodal cost status fingerprint within the cost control cycle into the gated cyclic unit prediction network, and correct the prediction results using engineering constraints and contract constraints; generate multiple sets of candidate control measures based on the prediction results and the cost control response matrix; select the candidate control measure with the smallest expected settlement cost deviation as the target control measure and send it to the engineering management end.

[0008] Specifically, the method for obtaining the original cost dataset in step S1 is as follows: Acquire multi-source data within the cost control period. The multi-source data includes investment estimation data, building information model data, budget data, bill of quantities data, bid price data, progress measurement data, on-site implementation data, construction site image data, and final settlement data. The cost control period includes the decision-making stage, design stage, bidding stage, construction stage, and settlement stage. The multi-source data is uniformly encoded, timestamp aligned, and missing value marked to form the original cost dataset.

[0009] Based on the above scheme, the method for establishing the cross-stage cost object chain is as follows: The cost objects for different engineering stages in the cost control cycle are defined as engineering function items, design components, bill of quantities items, construction tasks, and settlement items. The engineering part identifier, professional category code, engineering quantity source mark, and occurrence timestamp of the cost object are extracted. Based on the project location identifier, professional category code, project quantity source mark and occurrence time stamp, establish the correspondence between the same project content in different project stages; Based on the aforementioned correspondence, cost objects are linked in chronological order to form a cross-stage cost object chain.

[0010] Based on the above scheme, the modal tokens include numerical field tokens, BIM component tokens, text semantic tokens, and site image area tokens; the generation of modal tokens in step S2 and the attachment of the modal tokens to the cost evidence unit include: The numerical fields of investment estimates, budgets, bills of quantities, bid prices, progress measurement, material procurement, payment records, and final settlement are combined into a structured numerical mode. The structured numerical mode is then input into a multilayer perceptron for encoding to obtain numerical field tokens. Components in the building information model are used as nodes, and the spatial adjacency and professional connection relationships between components are used as edges. These are then input into a graph convolutional network for encoding to obtain BIM component tokens. The contract terms, design changes, and site approvals are combined into a contract and change text modal, which is then input into a bidirectional Mamba-2 text encoder for encoding to obtain a text semantic token. The construction site image is input into a convolutional neural network to obtain a convolutional feature map, and each spatial region in the convolutional feature map is converted into a site image region token. Based on the cross-stage cost object chain and cost control cycle, modal tokens of the same project content are linked to the same cost evidence unit.

[0011] Furthermore, step S2 also includes: For each modality in the same cost evidence unit, the data integrity, temporal consistency with the current cost control cycle, and cross-modal consistency are calculated to form a modal reliability vector; the modal reliability vector is then normalized using Softmax to obtain the modal credibility weight, wherein the modalities include structured numerical modalities, BIM spatial structure modalities, contract and change text modalities, and construction site image modalities; The modal tokens are multiplied by their corresponding modal confidence weights, and modal type codes and object location codes are superimposed on them to form a joint token sequence together with the learnable fusion tokens; The combined token sequence is input into the Mamba-2 selective state space module in its original and reverse order, respectively, to obtain the forward state sequence and the reverse state sequence. The bidirectional fusion gate is calculated based on the forward state sequence and the reverse state sequence. The forward state and the reverse state are gated and merged. The merged state at the position of the fusion token is taken as the multimodal cost state fingerprint. Using the multimodal cost status fingerprint as nodes, we establish connections between cross-stage mapping relationships, construction sequence relationships, material sharing relationships, and contract clause relationships to form an engineering cost association graph.

[0012] Specifically, applying coded virtual intervention to the control variables in step S3 includes: In the digital mapping space formed by the multimodal cost status fingerprint and the engineering cost correlation diagram, multiple sets of coded virtual interventions are applied to the control variables. Each set of codes records the controlled variable being intervened, the direction of intervention, and the magnitude of intervention. The control variables include procurement batches, material procurement time, construction sequence, resource input, and design scheme replacement parameters. The impact of virtual intervention on related cost evidence units is propagated based on the engineering cost correlation diagram, and the intervention results are recorded. The intervention results include changes in the amount of work, material costs, time-related costs, and change claim amounts before and after the intervention.

[0013] Specifically, the generation of the natural cost drift sequence in step S3 includes: Based on the cost control response matrix and the implemented control measures, the theoretical impact of the control measures on the cost status component is calculated; the control measures include adjustments to procurement batches, material procurement time, construction sequence, resource input, and design scheme replacement. The remaining change is obtained by subtracting the theoretical influence from the actual observed changes in the cost status components; Based on the aforementioned cost control cycle, the remaining changes are smoothed over time and outliers are removed to obtain the natural cost drift sequence.

[0014] Furthermore, in step S4, the natural cost drift sequence and multimodal cost status fingerprint within the cost control cycle are input into the gated recurrent unit prediction network, and the prediction results are corrected using engineering constraints and contractual constraints. Specifically, this includes: The natural cost drift sequence and multimodal cost status fingerprint within the continuous cost control cycle are input into the gated recurrent unit prediction network. The time-series characteristics of cost status changes with the cost control cycle are extracted through the gated recurrent unit, and the project quantity drift, material cost drift, schedule-related cost drift and change claim amount drift of the next cost control cycle are predicted and output. The cost drift prediction results were revised based on constraints of quantity conservation, cost aggregation, contract price adjustment, payment ratio, and construction sequence.

[0015] Based on the above scheme, the generation of target control measures in step S4 includes: Based on the cost drift prediction results and cost control response matrix of the cost control cycle, multiple sets of candidate control measures are generated within the feasible value range of the control variables; the control variables include procurement batches, material procurement time, construction sequence, resource input, and design scheme replacement parameters. The cost status components after the implementation of candidate control measures are deduced through the cost control response matrix, and the expected settlement cost is calculated. The cost status components include the quantity of work, material costs, time-related costs, and change claim amounts. Calculate the deviation between the estimated settlement cost and the contract target cost for each candidate control measure, and form a candidate measure comparison table; Remove candidate control measures that do not meet the contractual conditions and construction feasibility constraints, select the candidate control measure with the smallest expected settlement cost deviation as the target control measure, and send it to the corresponding project management terminal.

[0016] On the other hand, the present invention provides a dynamic cost control system for the entire engineering process based on multi-source data fusion, comprising: The data acquisition and cost object chain construction unit is used to divide the cost control cycle based on the engineering stage nodes and the occurrence time of cost events, and obtain the original cost dataset within the cost control cycle; it establishes a cross-stage cost object chain with engineering functional items, design components, bill of quantities items, construction tasks and settlement items as cost objects for different engineering stages; and it attaches cost evidence to the corresponding cross-stage cost object chain to form a cost evidence unit; the cost evidence includes contract terms, design changes, site instructions, material procurement records, progress measurement data, construction site images and payment records; The multimodal fusion and state fingerprint construction unit is used to generate modal tokens through a multilayer perceptron, graph convolutional network, bidirectional Mamba-2 text encoder and convolutional neural network, and attach the modal tokens to the cost evidence unit; generate modal weights through a modal credibility gating network, and combine credibility weighted tokens, modal type encoding, object location encoding and learnable fusion tokens into a joint sequence, and form a multimodal cost state fingerprint through bidirectional Mamba-2 selective state propagation and gating merging; at the same time, construct an engineering cost association graph with the cost evidence unit as nodes. The virtual intervention and cost response construction unit is used to apply coded virtual intervention to control variables in the engineering cost digital mapping space; the virtual intervention effect is propagated along the engineering cost correlation graph, and the response coefficient of each control variable to the cost status component is calculated by combining modal confidence weights to generate a cost control response matrix; the theoretical impact of existing control measures on the cost status component is deducted from the actual cost status component changes using the cost control response matrix to obtain the natural cost drift sequence; The cost forecasting and target control measures output unit inputs the natural cost drift sequence and multimodal cost status fingerprint within the cost control cycle into the gated loop unit prediction network, and corrects the prediction results using engineering constraints and contract constraints; generates multiple sets of candidate control measures based on the prediction results and the cost control response matrix; selects the candidate control measure with the smallest expected settlement cost deviation as the target control measure, and sends it to the project management end.

[0017] Compared with the prior art, the present invention has the following beneficial effects: 1. This invention completes the object-level and periodic-level alignment of different modal information based on the cross-stage cost object chain, and dynamically adjusts the modal weights based on data integrity, temporal consistency and cross-modal consistency through a modal credibility gating network, thereby reducing the impact of modal missing, temporal misalignment and information conflict on the fusion results; 2. By forming a multimodal cost status fingerprint through bidirectional Mamba-2 selective state propagation and gating merging, a unified representation of heterogeneous cost information throughout the entire project process can be achieved, improving the completeness, accuracy, and traceability of cost status identification; 3. Based on the cost control response matrix, the theoretical impact of existing control measures is deducted from the actual cost status changes to obtain the natural cost drift sequence, thereby separating the effect of control measures from the impact of non-control factors, and providing a quantitative and traceable basis for identifying the causes of cost changes and deducing candidate control measures; 4. This invention constructs a closed loop for cost prediction, measure deduction, and feedback correction that coordinates engineering constraints and contractual constraints, thereby improving the feasibility of control measures, the dynamic adaptability of cost prediction, and the level of refinement of cost control throughout the entire process. Attached Figure Description

[0018] Figure 1 A flowchart illustrating the overall process of dynamic cost control for the entire engineering project. Figure 2 This is a flowchart illustrating the specific steps of S1 in this invention. Figure 3 This is a flowchart illustrating step S2 of the present invention. Figure 4 This is a flowchart illustrating step S3 of the present invention. Figure 5This is a comparison chart of the multimodal fusion performance and robustness of missing modes in this invention; Figure 6 A schematic diagram showing the drift separation results of natural cost before and after deducting the control effect; Figure 7 A schematic diagram illustrating the simulation and closed-loop feedback correction results of target control measures. Detailed Implementation

[0019] The invention will be further described below with reference to specific embodiments.

[0020] This invention provides a method for dynamic cost control throughout the entire engineering process based on multi-source data fusion, such as... Figure 1 As shown, it includes the following steps: Step S1: Divide the cost control cycle based on the project stage nodes and the occurrence time of cost events, and obtain the original cost dataset within the cost control cycle; establish a cross-stage cost object chain with project functional items, design components, bill of quantities items, construction tasks, and settlement items as cost objects for different project stages; attach cost evidence to the corresponding cross-stage cost object chain to form cost evidence units; cost evidence includes contract terms, design changes, site instructions, material procurement records, progress measurement data, construction site images, and payment records; like Figure 2 As shown, step S1 includes: S1-1: Division of cost control cycles and acquisition of original cost datasets. The specific method is as follows: Acquire multi-source data within the cost control period; the cost control period is divided according to the project stage nodes and the occurrence time of cost events, and each cost control period corresponds to multiple consecutive time windows of the decision-making stage, design stage, bidding stage, construction stage and settlement stage; the multi-source data is acquired from the project investment management system, BIM collaboration platform, cost consulting database, bidding electronic trading platform, construction progress management system, on-site IoT acquisition equipment and construction site image acquisition equipment, including investment estimation data in the decision-making stage, building information model data and budget data in the design stage, bill of quantities data and bid price data in the bidding stage, progress measurement data, on-site implementation data and construction site image data in the construction stage, and final settlement data in the settlement stage.

[0021] The above multi-source data are uniformly encoded, timestamp aligned, and missing values ​​marked to form the original cost dataset.

[0022] Furthermore, S1-2: Establish a cross-stage cost object chain, including: The cost objects for different engineering stages in the cost control cycle are defined as engineering functional items, design components, bill of quantities items, construction tasks, and settlement items. The engineering part identifier, professional category code, engineering quantity source mark, and occurrence timestamp of each cost object are extracted. Based on the consistency of engineering part identification, the correspondence of professional category codes, the traceability of engineering quantity source markings, and the chronological logic of occurrence timestamps, establish the correspondence of the same engineering content in different engineering stages. Based on the correspondence, cost objects are linked in chronological order to form a cross-stage cost object chain. Each node in the chain carries the cost object identifier of the project content in a single stage, and each edge in the chain carries the stage transition relationship and version information.

[0023] Furthermore, S1-3: Based on the cross-stage cost object chain, a cost evidence unit is formed; specifically including: Based on each cross-stage cost object chain, identify the contract terms, design changes, site instructions, material procurement, progress measurement, construction site images, and payment records involved; The above records are linked to the corresponding cross-stage cost object chain according to time sequence and correlation strength, so that each record can be traced back to the specific cost object through engineering part, professional category and time; The completed cross-stage cost object chain and associated records are encapsulated into cost evidence units.

[0024] Step S2: Modal tokens are generated using a multilayer perceptron, graph convolutional network, bidirectional Mamba-2 text encoder, and convolutional neural network. The modal tokens are then attached to the cost evidence unit. Modal weights are generated using a modal credibility gating network. The credibility weighted token, modal type encoding, object location encoding, and learnable fusion token are combined into a joint sequence. This sequence is then processed by bidirectional Mamba-2 selective state propagation and gating merging to form a multimodal cost state fingerprint. Simultaneously, an engineering cost association graph is constructed using the cost evidence unit as a node.

[0025] Modal tokens include numerical field tokens, BIM component tokens, text semantic tokens, and site image area tokens.

[0026] like Figure 3 As shown, step S2 includes: S2-1: Modal state encoding generates modal tokens, which are then attached to the cost evidence unit; the extraction of modal tokens includes: The numerical fields of investment estimates, budgets, bill of quantities, bid prices, progress measurement, material procurement, payment records and final settlement are combined into a structured numerical mode. The structured numerical mode is then input into a multilayer perceptron for encoding to obtain numerical field tokens. Components in the building information model are used as nodes, and the spatial adjacency and professional connection relationships between components are used as edges. These are then input into a graph convolutional network for encoding to obtain BIM component tokens. The contract terms, design changes, and site approvals are combined into a contract and change text modal, which is then input into a bidirectional Mamba-2 text encoder for encoding to obtain a text semantic token. The construction site image is input into a convolutional neural network to obtain a convolutional feature map, and each spatial region in the convolutional feature map is converted into a site image region token.

[0027] Furthermore, attaching the modal token to the cost evidence unit includes: Based on the cross-stage cost object chain and cost control cycle, modal tokens belonging to the same project content are linked to the same cost evidence unit; modal tokens are converted into modal tokens of the same dimension through four independent linear projection layers:

[0028] Where m represents the mode. Indicates the token position within the modality. This represents a modal token after unifying the dimensions. Indicates the first In the first cost evidence unit The first class modality Each encoded feature, and Indicates the first Linear projection parameters of the modality.

[0029] S2-2: Perform cross-modal state fusion, including: For each modality within the same cost evidence unit, calculate data completeness, temporal consistency with the current cost control cycle, and cross-modal consistency to form a modal reliability vector. Cross-modal consistency refers to the consistency between this modality and other modalities in the description of the same quantity, cost, and schedule status. Modalities include structured numerical modalities, BIM spatial structural modalities, contract and change text modalities, and construction site image modalities. The modal reliability vector is input into a shared gating network, and the modal reliability weights are obtained by Softmax normalization:

[0030] in, Represents the modal confidence weight. Represents the modal reliability vector. Indicates a shared gated network. This represents the modal index during the credibility normalization process. Each modal token is multiplied by its corresponding modal confidence weight, and then the modal type code and object location code are added to form a joint token sequence together with the learnable fusion token:

[0031] in, Indicates the first A combined token sequence for each cost evidence unit This indicates that a learning fusion token is available. Indicates modal type encoding, Indicates the object's location encoding. Traversing the four modalities, Iterate through the token positions within the corresponding modality; Inputting the combined token sequence into the Mamba-2 selective state space module in its original and reverse order respectively yields the forward and reverse state sequences:

[0032]

[0033] in, and These represent the forward and reverse Mamba-2 selective state space modules, respectively. This indicates a token sequence reversal operation. and These represent the forward state sequence and the reverse state sequence, respectively. Calculate the bidirectional fusion gate based on the forward and reverse state sequences: , and Indicates the bidirectional fusion gate parameters. Represents the Sigmoid function; The forward and reverse states are gated and merged, and the merged state at the fusion token position is taken as the multimodal cost state fingerprint:

[0034]

[0035] in, This represents element-wise multiplication. This represents the state sequence after gating merging. This indicates the state of the location of the fusion token in the state sequence. Indicates the first Multimodal cost status fingerprint of each cost evidence unit.

[0036] Furthermore, using the multimodal cost status fingerprint as nodes, we establish connections between cross-stage mapping relationships, construction sequence relationships, material sharing relationships, and contract clause relationships to form an engineering cost relationship graph.

[0037] Step S2 also includes: using the actual observed engineering quantity, material cost, schedule-related cost and change claim amount in the historical cost control cycle as monitoring signals, and jointly updating the four types of modal encoders, linear projection layer, modal credibility gating network, bidirectional Mamba-2 selective state space module and bidirectional fusion gate through backpropagation.

[0038] Step S2 aligns the object-level and periodic-level information of different modalities based on the cross-stage cost object chain. Through a modal credibility gating network, the credibility weights of each modality are dynamically adjusted according to data integrity, temporal consistency, and cross-modal consistency to reduce the impact of modal missingness, temporal misalignment, and information conflict on the fusion results. Furthermore, bidirectional Mamba-2 selective state propagation and gating merging are used to form a multimodal cost status fingerprint, thereby realizing a unified representation of heterogeneous cost information throughout the entire project process and improving the completeness, accuracy, and traceability of cost status identification.

[0039] To quantitatively characterize the impact of control variables on cost status using multimodal fusion results, this invention includes step S3: applying coded virtual intervention to control variables in the engineering cost digital mapping space; propagating the virtual intervention impact along the engineering cost correlation graph; and calculating the response coefficients of each control variable to the cost status component in combination with modal confidence weights to generate a cost control response matrix; and using the cost control response matrix to subtract the theoretical impact of existing control measures on the cost status component from the actual cost status component changes to obtain the natural cost drift sequence. like Figure 4 As shown, step S3 includes: S3-1: Apply coded virtual interventions to control variables, including: In the digital mapping space formed by multimodal cost status fingerprints and engineering cost correlation diagrams, feasible intervention ranges that conform to engineering conditions and contract conditions are established for control variables, and multiple sets of coded virtual interventions are applied to control variables; each set of codes records the controlled variable being intervened, the direction of intervention, and the magnitude of intervention; control variables include procurement batches, material procurement time, construction sequence, resource input, and design scheme replacement parameters; The impact of virtual intervention on related cost evidence units is propagated based on the engineering cost correlation diagram, and the intervention results are recorded, including changes in the amount of work, material costs, time-related costs, and change claim amounts before and after the intervention.

[0040] S3-2: Generate the cost control response matrix; including: Based on the controlled variables, intervention direction and intervention extent recorded in each group of codes, the changes in engineering quantity, material cost, schedule-related cost and change claim amount generated after the intervention propagation are collected, and the independent state changes corresponding to each control variable are separated. Based on the modal credibility weights of each cost evidence unit, the response coefficients of the control variables to the cost status components are calculated; the response coefficients are summarized with the five types of control variables as rows and the four types of cost status components as columns to generate a cost control response matrix.

[0041] The above-mentioned S3-2 generates a cost control response matrix, which enables complete and consistent cost evidence units of multimodal evidence to make a high contribution to the response coefficient.

[0042] S3-3: Generate the natural cost drift sequence; including: Based on the cost control response matrix and the actual extent of implemented adjustments to procurement batches, material procurement times, construction sequences, resource inputs, and design scheme replacements, the theoretical impact of existing control measures on the cost status component is calculated. The theoretical impact is subtracted from the actual observed changes in the cost status component to obtain the remaining changes after eliminating the influence of existing control measures; Based on the cost control cycle, the remaining changes are smoothed over time and outliers are removed to obtain the natural cost drift sequence, which is used to characterize the cost status changes caused by non-controlled factors such as external market and geological conditions.

[0043] Step S3 applies coded virtual interventions, including variable identifiers, intervention directions, and intervention magnitudes, to procurement batches, material procurement times, construction sequences, resource inputs, and design scheme replacement parameters in a unified and integrated feature space. It then extrapolates the impact of the interventions on related cost evidence units along the engineering cost correlation diagram. Finally, it uses the cost control response matrix to deduct the theoretical impact of existing control measures from the actual cost status changes, obtaining the natural cost drift sequence. This achieves the separation of the effects of control measures from the impact of non-control factors, providing a quantitative and traceable basis for identifying the causes of cost changes and extrapolating candidate control measures.

[0044] To achieve cost prediction and target control measures output, this invention executes step S4, which involves inputting the natural cost drift sequence and multimodal cost status fingerprint within the cost control cycle into the gated recurrent unit prediction network, and correcting the prediction results using engineering constraints and contract constraints; generating multiple sets of candidate control measures based on the prediction results and the cost control response matrix; selecting the candidate control measure with the smallest expected settlement cost deviation as the target control measure, and sending it to the engineering management end.

[0045] Step S4 includes: S4-1: Cost Prediction and Constraints; specifically including: The natural cost drift sequence and multimodal cost status fingerprint within the continuous cost control cycle are input into the gated cyclic unit prediction network. The time-series characteristics of cost status changes with the cost control cycle are extracted through the gated cyclic unit, and the cost drift prediction results are output: the drift of the project quantity, material cost, schedule-related cost, and change claim amount in the next cost control cycle. The cost drift prediction results were revised based on constraints of quantity conservation, cost aggregation, contract price adjustment, payment ratio, and construction sequence.

[0046] S4-2: Generate candidate control measures; including: Based on the cost drift prediction results and cost control response matrix of the cost control cycle, multiple sets of candidate control measures are generated within the feasible intervention range of the control variables; the control variables include procurement batches, material procurement time, construction sequence, resource input and design scheme replacement parameters; The cost status components after the implementation of candidate control measures are deduced through the cost control response matrix, and the expected settlement cost is calculated. The cost status components include the quantity of work, material costs, time-related costs, and change claim amount. Calculate the deviation between the estimated settlement cost and the contract target cost for each candidate control measure, and form a candidate measure comparison table.

[0047] S4-3: Generate target control measures and provide feedback for correction; including: Remove candidate control measures that do not meet the contract conditions and construction feasibility constraints, compare the expected settlement cost deviations of the remaining candidate control measures, select the candidate control measure with the smallest expected settlement cost deviation as the target control measure, and send it to the corresponding project management terminal; The residual effect of the measures is calculated based on the actual cost status changes after implementation. The cost control response matrix is ​​corrected using this residual. The causes of cost changes and the location of cost risks are determined based on the multimodal cost status fingerprint and the project cost correlation diagram. Finally, the causes of cost changes, the location of cost risks, the estimated settlement cost, the target control measures, and the cost control results after the implementation of the measures are output.

[0048] Based on the same technical concept, this invention also provides a dynamic cost control system for the entire engineering process based on multi-source data fusion, comprising: The data acquisition and cost object chain construction unit is used to divide the cost control cycle based on the project stage nodes and the occurrence time of cost events, and obtain the original cost dataset within the cost control cycle; it establishes a cross-stage cost object chain with engineering functional items, design components, bill of quantities items, construction tasks and settlement items as cost objects for different project stages; and it links cost evidence to the corresponding cross-stage cost object chain to form a cost evidence unit; the cost evidence includes contract terms, design changes, site instructions, material procurement records, progress measurement data, construction site images and payment records; The multimodal fusion and state fingerprint construction unit is used to generate modal tokens through a multilayer perceptron, graph convolutional network, bidirectional Mamba-2 text encoder and convolutional neural network, and attach the modal tokens to the cost evidence unit; modal weights are generated through a modal credibility gating network, and credibility weighted tokens, modal type encoding, object location encoding and learnable fusion tokens are combined into a joint sequence, which is then transformed into a multimodal cost state fingerprint through bidirectional Mamba-2 selective state propagation and gating merging; at the same time, an engineering cost association graph is constructed with the cost evidence unit as nodes. The virtual intervention and cost response construction unit is used to apply coded virtual intervention to control variables in the engineering cost digital mapping space; the virtual intervention effect is propagated along the engineering cost correlation graph, and the response coefficient of each control variable to the cost status component is calculated by combining modal confidence weights to generate a cost control response matrix; the theoretical impact of existing control measures on the cost status component is deducted from the actual cost status component changes using the cost control response matrix to obtain the natural cost drift sequence; The cost forecasting and target control measures output unit inputs the natural cost drift sequence and multimodal cost status fingerprint within the cost control cycle into the gated loop unit prediction network, and corrects the prediction results using engineering constraints and contract constraints; generates multiple sets of candidate control measures based on the prediction results and the cost control response matrix; selects the candidate control measure with the smallest expected settlement cost deviation as the target control measure, and sends it to the project management end.

[0049] The implementation method of the dynamic cost control system for the entire project is the same as that of the above method, and will not be described in detail here.

[0050] To verify the effectiveness of the dynamic cost control method for the entire engineering process of this invention, 36 anonymized simulation samples of public building projects were constructed. These projects included office, teaching and research, medical, and commercial buildings, with contract target costs ranging from 68 million to 315 million yuan. Each project was divided into 24 cost control cycles, generating a total of 4320 cost evidence units according to the cross-stage cost object chain. Each evidence unit contained four modalities: structured numerical data, BIM spatial structure, contract and change texts, and construction site images, and was linked to contract clauses, design changes, site approvals, material procurement, progress measurement, and payment records. Training, validation, and test sets were divided by project to avoid adjacent cycles of the same project entering different datasets simultaneously. The following three core validation tasks were included: First, we will verify the fusion effect of cross-stage cost object chains, modal credibility gating, and bidirectional Mamba-2 on structured numerical data, BIM spatial structure, contract and change texts, and construction site images, as well as their robustness under missing, misaligned, and conflicting modal conditions.

[0051] First, the object chain construction accuracy and cost prediction error of different methods are compared on the complete test set. Then, the modality missing rate is gradually increased, and temporal misalignment and cross-modal conflict are introduced to test the stability under low-quality evidence conditions. Figure 5 As shown, Rule represents the rule-matching method, BPNN is the traditional backpropagation neural network, Concat-Transformer is the direct concatenation of various modal features before inputting into the standard Transformer encoder, No-gate is a modality-free confidence gating, and Proposed is the present invention. The object chain F1 score of the method of the present invention reaches 0.957, which is 0.115 higher than that of the rule-matching method; the MAPE (mean absolute percentage error of settlement cost) for settlement cost prediction is 2.78%, which is 1.48 percentage points lower than that of the Concat-Transformer method. As the modality missing rate increases from 0% to 40%, the MAPE of the method of the present invention only increases from 2.78% to 3.89%, while the No-gate method and the direct concatenation Transformer method increase to 6.46% and 7.34%, respectively. This proves that the cross-stage cost object chain, modality confidence gating, and bidirectional Mamba-2 play an indispensable role in the present invention.

[0052] Second, verify the ability of the coded virtual intervention and cost control response matrix to separate existing control effects from natural cost drift; such as Figure 6As shown, the actual cost status changes abruptly in the 5th, 6th, 11th, 12th, 17th, 18th, and 22nd control cycles due to adjustments in procurement timing, construction sequence, or resource input. This invention utilizes a cost control response matrix to calculate the theoretical effect of existing measures and subtracts this effect from the actual changes, resulting in a natural drift curve that remains consistent with the reference natural drift.

[0053] Third, verify the closed-loop control effect of candidate control measures under contract and engineering constraints, target measure selection, and feedback and correction after measure implementation. For example... Figure 7 As shown, M1-M5 are control measures. M2 and M5 have smaller prediction deviations, but they do not meet the contract price lock-in window and design function index constraints, respectively. Among the remaining feasible candidate control measures, M4 has the smallest expected settlement cost deviation, at 580,000 yuan. M4 was selected as the target control measure, and the cost decreased by 81.3% after the control measures were implemented. After multiple feedback corrections, the residual effect of the measures decreased from 186,000 yuan to 39,000 yuan, a decrease of 79.0%; the predicted MAPE decreased from 3.64% to 2.69% during the same period. The results show that feedback corrections can reduce the mismatch of the response matrix caused by changes in different project stages, material markets, and construction organization, and enable the results of the target measures to be continuously updated with new evidence.

[0054] In general, various exemplary embodiments of the present invention can be implemented in hardware or dedicated circuitry, software, firmware, logic, or any combination thereof. Some aspects can be implemented in hardware, while others can be implemented in firmware or software that can be executed by a controller, microprocessor, or other computing device. When aspects of embodiments of the present invention are illustrated or described as block diagrams, flowcharts, or represented using certain other images, it will be understood that the blocks, apparatuses, systems, techniques, or methods described herein can be implemented as non-limiting examples in hardware, software, firmware, dedicated circuitry or logic, general-purpose hardware or controllers or other computing devices, or certain combinations thereof.

[0055] The above description is merely a preferred embodiment of this application and is not intended to limit this application. Various modifications and variations can be made to this application by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the protection scope of this application.

[0056] While the specific embodiments of the present invention have been described above, they are not intended to limit the scope of protection of the present invention. Those skilled in the art should understand that various modifications or variations that can be made by those skilled in the art without creative effort based on the technical solutions of the present invention are still within the scope of protection of the present invention.

Claims

1. A multi-source data fusion-based engineering whole-process cost dynamic management and control method, characterized in that, Includes the following steps: Step S1: Divide the cost control cycle based on the project stage nodes and the occurrence time of cost events, and obtain the original cost dataset within the cost control cycle; establish a cross-stage cost object chain with project functional items, design components, bill of quantities items, construction tasks, and settlement items as cost objects for different project stages; attach cost evidence to the corresponding cross-stage cost object chain to form a cost evidence unit; the cost evidence includes contract terms, design changes, site instructions, material procurement records, progress measurement data, construction site images, and payment records; Step S2: Modal tokens are generated using a multilayer perceptron, graph convolutional network, bidirectional Mamba-2 text encoder, and convolutional neural network. The modal tokens are then attached to the cost evidence unit. Modal weights are generated using a modal credibility gating network. The credibility weighted token, modal type encoding, object location encoding, and learnable fusion token are combined into a joint sequence. This sequence is then processed by bidirectional Mamba-2 selective state propagation and gating merging to form a multimodal cost state fingerprint. Simultaneously, an engineering cost association graph is constructed using the cost evidence unit as nodes. Step S3: Apply coded virtual intervention to the control variables in the engineering cost digital mapping space; propagate the impact of the virtual intervention along the engineering cost correlation graph, and calculate the response coefficient of each control variable to the cost status component in combination with the modal confidence weight to generate the cost control response matrix; By using the cost control response matrix to subtract the theoretical impact of existing control measures on the cost status components from the actual cost status component changes, the natural cost drift sequence is obtained. Step S4: Input the natural cost drift sequence and multimodal cost status fingerprint within the cost control cycle into the gated cyclic unit prediction network, and correct the prediction results using engineering constraints and contract constraints; generate multiple sets of candidate control measures based on the prediction results and the cost control response matrix; select the candidate control measure with the smallest expected settlement cost deviation as the target control measure and send it to the engineering management end.

2. The method for dynamic cost control of the entire engineering process based on multi-source data fusion as described in claim 1, characterized in that, The method for obtaining the original cost dataset in step S1 is as follows: Acquire multi-source data within the cost control period. The multi-source data includes investment estimation data, building information model data, budget data, bill of quantities data, bid price data, progress measurement data, on-site implementation data, construction site image data, and final settlement data. The cost control period includes the decision-making stage, design stage, bidding stage, construction stage, and settlement stage. The multi-source data is uniformly encoded, timestamp aligned, and missing value marked to form the original cost dataset.

3. The method for dynamic cost control of the entire engineering process based on multi-source data fusion according to claim 2, characterized in that, The method for establishing the cross-stage cost object chain is as follows: The cost objects for different engineering stages in the cost control cycle are defined as engineering function items, design components, bill of quantities items, construction tasks, and settlement items. The engineering part identifier, professional category code, engineering quantity source mark, and occurrence timestamp of the cost object are extracted. Based on the project location identifier, professional category code, project quantity source mark and occurrence time stamp, establish the correspondence between the same project content in different project stages; Based on the aforementioned correspondence, cost objects are linked in chronological order to form a cross-stage cost object chain.

4. The method for dynamic cost control of the entire engineering process based on multi-source data fusion according to claim 1, characterized in that, The modal tokens include numerical field tokens, BIM component tokens, text semantic tokens, and site image area tokens; The step S2, which involves generating a modal token and attaching it to the cost evidence unit, includes: The numerical fields of investment estimates, budgets, bills of quantities, bid prices, progress measurement, material procurement, payment records, and final settlement are combined into a structured numerical mode. The structured numerical mode is then input into a multilayer perceptron for encoding to obtain numerical field tokens. Components in the building information model are used as nodes, and the spatial adjacency and professional connection relationships between components are used as edges. These are then input into a graph convolutional network for encoding to obtain BIM component tokens. The contract terms, design changes, and site approvals are combined into a contract and change text modal, which is then input into a bidirectional Mamba-2 text encoder for encoding to obtain a text semantic token. The construction site image is input into a convolutional neural network to obtain a convolutional feature map, and each spatial region in the convolutional feature map is converted into a site image region token. Based on the cross-stage cost object chain and cost control cycle, modal tokens of the same project content are linked to the same cost evidence unit.

5. The method for dynamic cost control of the entire engineering process based on multi-source data fusion according to claim 4, characterized in that, Step S2 further includes: For each modality in the same cost evidence unit, the data integrity, temporal consistency with the current cost control cycle, and cross-modal consistency are calculated to form a modal reliability vector; the modal reliability vector is then normalized using Softmax to obtain the modal credibility weight, wherein the modalities include structured numerical modalities, BIM spatial structure modalities, contract and change text modalities, and construction site image modalities; The modal tokens are multiplied by their corresponding modal confidence weights, and modal type codes and object location codes are superimposed on them to form a joint token sequence together with the learnable fusion tokens; The combined token sequence is input into the Mamba-2 selective state space module in its original and reverse order, respectively, to obtain the forward state sequence and the reverse state sequence. The bidirectional fusion gate is calculated based on the forward state sequence and the reverse state sequence. The forward state and the reverse state are gated and merged. The merged state at the position of the fusion token is taken as the multimodal cost state fingerprint. Using the multimodal cost status fingerprint as nodes, we establish connections between cross-stage mapping relationships, construction sequence relationships, material sharing relationships, and contract clause relationships to form an engineering cost association graph.

6. The method for dynamic cost control of the entire engineering process based on multi-source data fusion according to claim 1, characterized in that, The step S3, which involves applying coded virtual intervention to the control variables, includes: In the digital mapping space formed by the multimodal cost status fingerprint and the engineering cost correlation diagram, multiple sets of coded virtual interventions are applied to the control variables. Each set of codes records the controlled variable being intervened, the direction of intervention, and the magnitude of intervention. The control variables include procurement batches, material procurement time, construction sequence, resource input, and design scheme replacement parameters. The impact of virtual intervention on related cost evidence units is propagated based on the engineering cost correlation diagram, and the intervention results are recorded. The intervention results include changes in the amount of work, material costs, time-related costs, and change claim amounts before and after the intervention.

7. The method for dynamic cost control of the entire engineering process based on multi-source data fusion according to claim 1, characterized in that, The generation of the natural cost drift sequence in step S3 includes: Based on the cost control response matrix and the implemented control measures, the theoretical impact of the control measures on the cost status component is calculated; the control measures include adjustments to procurement batches, material procurement time, construction sequence, resource input, and design scheme replacement. The remaining change is obtained by subtracting the theoretical influence from the actual observed changes in the cost status components; Based on the aforementioned cost control cycle, the remaining changes are smoothed over time and outliers are removed to obtain the natural cost drift sequence.

8. The method for dynamic cost control of the entire engineering process based on multi-source data fusion according to claim 1, characterized in that, Step S4 involves inputting the natural cost drift sequence and multimodal cost status fingerprint within the cost control cycle into the gated recurrent unit prediction network, and using engineering constraints and contractual constraints to correct the prediction results. Specifically, this includes: The natural cost drift sequence and multimodal cost status fingerprint within the continuous cost control cycle are input into the gated recurrent unit prediction network. The time-series characteristics of cost status changes with the cost control cycle are extracted through the gated recurrent unit, and the project quantity drift, material cost drift, schedule-related cost drift and change claim amount drift of the next cost control cycle are predicted and output. The cost drift prediction results were revised based on constraints of quantity conservation, cost aggregation, contract price adjustment, payment ratio, and construction sequence.

9. The method for dynamic cost control of the entire engineering process based on multi-source data fusion according to claim 8, characterized in that, The generation of target control measures in step S4 includes: Based on the cost drift prediction results and cost control response matrix of the cost control cycle, multiple sets of candidate control measures are generated within the feasible value range of the control variables; the control variables include procurement batches, material procurement time, construction sequence, resource input, and design scheme replacement parameters. The cost status components after the implementation of candidate control measures are deduced through the cost control response matrix, and the expected settlement cost is calculated. The cost status components include the quantity of work, material costs, time-related costs, and change claim amounts. Calculate the deviation between the estimated settlement cost and the contract target cost for each candidate control measure, and form a candidate measure comparison table; Remove candidate control measures that do not meet the contractual conditions and construction feasibility constraints, select the candidate control measure with the smallest expected settlement cost deviation as the target control measure, and send it to the corresponding project management terminal.

10. A dynamic cost control system for the entire engineering process based on multi-source data fusion, characterized in that, include: The data acquisition and cost object chain construction unit is used to divide the cost control cycle based on the engineering stage nodes and the occurrence time of cost events, and obtain the original cost dataset within the cost control cycle; it establishes a cross-stage cost object chain with engineering functional items, design components, bill of quantities items, construction tasks and settlement items as cost objects for different engineering stages; and it attaches cost evidence to the corresponding cross-stage cost object chain to form a cost evidence unit; the cost evidence includes contract terms, design changes, site instructions, material procurement records, progress measurement data, construction site images and payment records; The multimodal fusion and state fingerprint construction unit is used to generate modal tokens through a multilayer perceptron, graph convolutional network, bidirectional Mamba-2 text encoder and convolutional neural network, and attach the modal tokens to the cost evidence unit; generate modal weights through a modal credibility gating network, and combine credibility weighted tokens, modal type encoding, object location encoding and learnable fusion tokens into a joint sequence, and form a multimodal cost state fingerprint through bidirectional Mamba-2 selective state propagation and gating merging; at the same time, construct an engineering cost association graph with the cost evidence unit as nodes. The virtual intervention and cost response building unit is used to apply coded virtual intervention to control variables in the digital mapping space of engineering cost; the virtual intervention effect is propagated along the engineering cost correlation graph, and the response coefficient of each control variable to the cost status component is calculated by combining modal confidence weights to generate a cost control response matrix; By using the cost control response matrix to subtract the theoretical impact of existing control measures on the cost status components from the actual cost status component changes, the natural cost drift sequence is obtained. The cost forecasting and target control measures output unit inputs the natural cost drift sequence and multimodal cost status fingerprint within the cost control cycle into the gated loop unit prediction network, and corrects the prediction results using engineering constraints and contract constraints; generates multiple sets of candidate control measures based on the prediction results and the cost control response matrix; selects the candidate control measure with the smallest expected settlement cost deviation as the target control measure, and sends it to the project management end.