A digital geological reverse updating method based on precise real-time positioning of excavators

By using excavators for precise real-time positioning and multi-source data fusion, the open-pit mine geological model can be updated and adaptively calibrated in real time, solving the problems of geological model lag and error accumulation in existing technologies and providing real-time and accurate digital geological support.

CN123160804APending Publication Date: 2026-11-24YULIN UNIVERSITY
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202611161721.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-03
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing open-pit mine geological model update technologies cannot respond to mining changes in real time. They rely on a single data source, lack full-process collaboration, and have fixed parameters that lack adaptive correction, resulting in serious error accumulation and making it difficult to achieve the leap from offline planning to online dynamic control.

Method used

By using excavators for precise real-time positioning and integrating multi-source heterogeneous data from loading equipment, a spatiotemporally synchronized ore blending unit attribute iterative update algorithm is constructed using real-time topology calculation and 3D geological modeling. This enables real-time reduction, incremental reconstruction, and dynamic evolution of all attributes of the geological model.

Benefits of technology

It enables real-time updates of the geological model, accurately tracks subtle topographic changes caused by shoveling, adaptively calibrates parameters, and ensures that the model's accuracy increases rather than decreases as mining progresses, providing real-time and accurate digital geological support.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123160804A_ABST
    Figure CN123160804A_ABST
Patent Text Reader

Abstract

This invention discloses a digital geological reverse update method based on precise real-time positioning of excavators, comprising the following steps: Step 1: Deploying system hardware and building the overall architecture to form a multi-source heterogeneous raw data stream; Step 2: Integrating the data into enhanced excavator loading points with unified spatiotemporal labels; Step 3: Implementing surface geometric updates and constructing a virtual sampling point network; Step 4: Performing iterative calculations of inverse distance weighted interpolation driven by residual diagnosis, outputting an updated geological block model; Step 5: Generating a deviation diagnosis report to achieve long-term self-optimization of model accuracy; Step 6: Visual interaction and dynamic control application scenarios. This invention aims to solve the problems of traditional static geological models lagging behind production rhythm and lacking a two-way driving mechanism, achieving a leap from offline planning to online dynamic control, and providing real-time and accurate digital geological support for short-term ore quality optimization in open-pit mines.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of dynamic updating technology for polymetallic fine geological models in open-pit mines, specifically to a digital geological reverse updating method based on the precise real-time positioning of excavators. Background Technology

[0002] Digital geological models for open-pit mines are the core foundation for mine production planning, ore blending optimization, and intelligent scheduling. However, with the rapid advancement of mining operations, the spatial morphology and grade distribution of ore and rock undergo drastic changes, and existing geological model updating technologies still have significant shortcomings, making it difficult to meet the needs of refined dynamic ore blending.

[0003] A method for automatically updating the reserves of a ore body block model, with publication number CN104462649A, is proposed. This method updates the DEM grid elevation by periodically reading the excavator bucket coordinates and uses weighbridge data for comparison to correct the reserve statistics.

[0004] However, this method has the following limitations: (1) It adopts a "periodic reading" mechanism, which has a long update cycle and cannot respond to minute-level mining changes, so the model lags behind actual production; (2) The reserve statistics are based on whether the unit block has been completely excavated as the basis for binary judgment, which cannot simulate the gradual reduction of micro-topography caused by shoveling operations; (3) It only involves volume and reserve calculation, and does not inject the grade data of shoveling points into the model in reverse, so it cannot realize the dynamic evolution of geological attributes; (4) The error judgment adopts a fixed threshold and lacks adaptive parameter calibration based on measured data, so the error is easy to accumulate as mining progresses.

[0005] A precision loading system and method for open-pit mines, disclosed in CN111691888A, uses unmanned aerial vehicles (UAVs) to measure the coordinates of blast piles and combine this with grade analysis from boreholes to identify the grade of ore in a single bucket. However, the system's data flow is unidirectional (blast pile database → loading equipment). The load and actual grade data obtained after loading cannot be fed back to the geological model for correction, making it an open-loop control mode lacking a closed-loop feedback mechanism. Initial model deviations cannot be self-corrected using actual production data. Furthermore, its data source is limited to blast pile analysis, resulting in a relatively singular basis for model updates.

[0006] In summary, existing technologies suffer from several drawbacks, including a single data source lacking end-to-end collaboration, coarse and inefficient surface update algorithms, fixed parameters lacking adaptive correction, and open-loop systems leading to severe error accumulation. These shortcomings make it difficult for geological models to transition from offline planning to online dynamic control.

[0007] Therefore, there is an urgent need to develop a digital geological reverse update method that can integrate full-process production data, achieve fine dynamic reconstruction of the surface, and have the ability to adaptively calibrate parameters. Summary of the Invention

[0008] To overcome the above technical problems, the present invention aims to provide a digital geological reverse update method based on the precise real-time positioning of excavators. This method utilizes high-precision real-time spatial pose data of loading equipment, integrates full-process production measurement and grade detection data, and constructs an iterative update algorithm library for ore blending unit attributes under spatiotemporal synchronization constraints. Through the coupling of real-time topology calculation and a 3D geological modeling engine, the geological model can achieve real-time reduction, incremental reconstruction, and dynamic evolution representation of all attributes during the mining process. The present invention aims to solve the problems of traditional static geological models lagging behind production rhythm and lacking a two-way driving mechanism, realizing a leap from offline planning to online dynamic control, and providing real-time and accurate digital geological support for short-term ore quality optimization in open-pit mines.

[0009] To achieve the above objectives, the technical solution adopted by the present invention is as follows: A digital geological reverse update method based on precise real-time positioning of excavators includes the following steps; Step 1: Deploy system hardware and build overall architecture. Real-time data collection is carried out through the perception layer devices, including bucket tip coordinate sequence, loading action status, truck load and trajectory, and crushing station grade detection data. The data is then aggregated through the transmission layer to the computing layer to form a multi-source heterogeneous raw data stream. Step 2: Perform spatiotemporal registration and correlation on the multi-source heterogeneous data obtained in Step 1, and integrate the scattered loading action state coordinates, truck load and crushing station grade detection data into an enhanced loading point with a unified spatiotemporal label. Step 3: Using the enhanced shovel-mounted point integrated in Step 2 as the driving source, based on the digital surface model, perform Z-value replacement within the dynamic search radius and reconstruction of the local constrained Delaunay triangulation network to realize surface geometry update and construction of the virtual sampling point network, and drive the ore blending unit to gradually reduce the area and evolve in a grade-volume co-evolution. Step 4: Adaptive update of geological attributes based on virtual sampling point network. Based on the virtual sampling point network generated after surface geometry update, the original exploration boreholes are used as the main data source and virtual sampling points are used as the auxiliary data source. Residual diagnosis-driven inverse distance weighted interpolation iterative calculation is performed, and the power exponent, search radius and data source weight are dynamically adjusted to output the updated geological block model. Step 5: Based on the updated geological block model, summarize the deviation between the model's predicted grade and the actual grade entering the mill by shift, generate a deviation diagnosis report, and correct the data fusion weights, regional interpolation strategies, and initial prior parameters of the iteration accordingly to achieve long-term self-optimization of model accuracy. Step Six: Visual Interaction and Dynamic Control Application Scenarios. Based on the final updated model, perform 3D dynamic rendering and spatiotemporal evolution playback. Call the mixed integer linear programming solver to automatically generate a ore blending scheme that meets multiple constraints, and send scheduling instructions to the equipment terminal in real time. At the same time, retain the manual intervention interface to realize closed-loop control of human-machine collaboration.

[0010] Step one specifically involves: Step 1.1: Sensing Layer Device Configuration: A high-precision GNSS-RTK receiver (positioning accuracy ±2cm), boom angle sensor, stick angle sensor, and hydraulic pressure sensor are installed on a hydraulic excavator or electric shovel; through sensor fusion calculation, the three-dimensional coordinates of the bucket tip in the mining area coordinate system are obtained in real time. The loading action states include three stages: digging (the bucket cuts into the ore pile, and the hydraulic pressure suddenly increases), lifting (the bucket is fully loaded and lifted away from the digging face, and the boom angle increases), and slewing (the bucket rotates in the unloading direction, and the boom angle changes). The continuous detection and judgment of the above action states is the logical basis for determining the start and end times of a loading event. Install on-board weighing systems (accuracy ±1%) and positioning terminals on mining dump trucks to record load data and driving trajectory in real time; install online grade analyzers (such as X-ray fluorescence spectrometers) at the feed inlet of crushing stations, or establish rapid testing channels in laboratories to obtain ore grade data in real time and automatically add timestamps; The multi-source heterogeneous data collected by the aforementioned sensing layer specifically includes: the bucket tip coordinate sequence from excavators / electric shovels. (Including timestamps), boom and stick attitude angles and hydraulic pressure values ​​(used to determine the loading operation status); load data from dump trucks. and location trajectory Grade testing data from crushing plants or laboratories and its detection time The above data forms the original basis for subsequent data fusion; Step 1.2: Transport Layer Network Construction: By utilizing the existing industrial Ethernet private network in the mine, a high-bandwidth, low-latency data transmission channel is established to transmit the multi-source heterogeneous data collected in step 1.1 to the data center in real time with millisecond-level latency, ensuring that subsequent processing can obtain timely and complete raw data streams; Step 1.3: Deployment of the Computation Layer and Application Layer: A high-performance server cluster is deployed to run the core algorithm modules, including a multi-source data fusion engine, a surface dynamic reconstruction engine, a geological attribute interpolation engine, and a residual diagnosis and parameter calibration module. The functions and interrelationships of each module are as follows: (1) Multi-source data fusion engine: Receives the raw data stream transmitted in step 1.2, performs time synchronization (NTP protocol), outlier removal, loading event matching and transport chain tracking, integrates the scattered loading coordinates, load and grade data into an enhanced loading point with a unified spatiotemporal label, and outputs it to the surface dynamic reconstruction engine. (2) Surface dynamic reconstruction engine: Driven by enhanced shovel points, it performs Z-value replacement and local constrained Delaunay triangulation reconstruction within the dynamic search radius of the digital surface model, and outputs the updated surface model and the virtual sampling point network converted from the triangulation vertices for the geological attribute interpolation engine to call. (3) Geological attribute interpolation engine: The original exploration boreholes are the main data source and the virtual sampling points are the auxiliary data source. The residual diagnosis-driven inverse distance weighted interpolation iterative calculation is performed to output the updated geological block model (including the spatial coordinates and grade attributes of each block). (4) Residual diagnosis and parameter calibration module: monitors the residual between the measured value of the newly inserted virtual sampling point and the predicted value of the point in the output of the geological attribute interpolation engine, and dynamically adjusts the interpolation power exponent, search radius and data source weight accordingly, and sends the calibrated optimal parameters back to the geological attribute interpolation engine for use in the next iteration; The multi-source data fusion engine, the surface dynamic reconstruction engine, the geological attribute interpolation engine, and the output update model run in a serial cascade manner. The residual diagnosis and parameter calibration module provides horizontal services to the geological attribute interpolation engine and forms an internal feedback loop with it. At the same time, a 3D visualization terminal is configured as the application layer interface to display the real-time updated digital geological model, ore blending suggestions and deviation analysis reports to the dispatch center and geological technicians. At this point, step one has completed the setup of the computing environment from data acquisition and transmission. The final output of step 1.3 is: the enhanced shovel loading point dataset after fusion processing (for use in step two). This output is transmitted to the data fusion processing flow of step two through the internal data bus.

[0011] Step two specifically involves: Step 2.1: Multi-source heterogeneous data acquisition and preprocessing: The system receives the excavator bucket tip coordinate sequence transmitted in step one in real time. ( (timestamps) and truck load data and location trajectory Crushing station grade testing data and its detection time ; The received raw data is preprocessed as follows: (1) Eliminate obvious outliers (such as coordinates exceeding the mining area or load exceeding the rated load by 200%, etc.). (2) Perform preliminary sorting and caching according to a unified timestamp to form a temporary dataset indexed by device ID, including excavator event sequences. Truck load and trajectory sequence Grade detection sequence The preliminary sorting results after preprocessing are output to step 2.2; Step 2.2: Spatiotemporal registration and data association: Based on the temporary dataset indexed by device ID formed after preprocessing in step 2.1, the following operations are further performed: First, time synchronization is performed, with all devices using the NTP protocol to unify the time base and eliminate clock drift errors; then, spatial association logic is executed. (1) Loading event matching: in the excavator event sequence During loading, when the system detects that the bucket posture has switched from "digging" to "lifting" and then completed the "slewing" action (based on a combined threshold determination using the boom angle sensor and stick angle sensor), the system records the moment of this loading event. and location ; (2) Transport chain tracking: The system subsequently Within a time frame (e.g., 5-10 minutes), in the truck location trajectory dataset Search in the middle Nearby and load data Gradually increase the number of trucks to full load. The load capacity of the truck Associate this loading action with the loading event log and write the association result to the loading event log. (3) Taste traceability: based on truck Based on its travel trajectory and speed, the time it takes to arrive at the crushing station can be estimated. The system will Quality detection data near the time (From the quality detection sequence) (This is a direct quote from a historical text, likely related to a specific action or process.) The output of step 2.2 is a set of loading event records that has completed loading event matching, transport chain tracking, and quality backtracking association. This set of records is passed to step 2.3 to generate enhanced loading points. Step 2.3: Generate enhanced shovel loading points: Based on the association results from the previous step, a data point containing complete attributes is generated for each loading action. These are enhanced shovel points, which will directly drive the surface geometry update in step three.

[0012] Step three specifically involves: Step 3.1: Dynamic Search and Z-Value Replacement: For each newly generated enhanced shovel point The system treats it as a source of mining disturbance and sets a dynamic search radius. , The value is taken as 1.5 times the bucket width (for example, if the bucket width is 3 meters, then...). (meters), the radius can be adaptively adjusted according to the equipment model; In Center of the circle Within a circular region of radius , retrieve the set of all triangulated vertices in the original digital terrain model. ; set All vertices in Coordinates are updated to reflect the current excavation depth. This step simulates the immediate reduction effect after the bucket removes soil, resulting in an updated... Local vertex set after value ; Step 3.2: Local triangulation reconstruction: To avoid computational delays caused by global reconstruction, the system only reconstructs the affected local regions, using the updated local vertex set output in step 3.1. Based on this, the constrained Delaunay triangulation algorithm is used to reconstruct the triangulation topology of the region, ensuring that the new landform is continuous and free of self-intersections; unaffected areas remain unchanged, thus achieving millisecond-level incremental reconstruction; the reconstructed triangulation provides the geometric carrier for subsequent attribute mapping. Step 3.3: Attribute mapping from shovel loading points to triangular mesh nodes: The enhanced shovel point generated in step 2.3 Spatially associate the triangular mesh obtained in step 3.2 with the following: (1) If the distance between the point and the existing triangulation vertex is less than the threshold (such as the bucket radius), then the grade value of the point is directly set. Assign to the corresponding vertex; (2) If the point is located inside the triangular mesh, the grade value is distributed to the three vertices of the mesh through centroid coordinate interpolation; through mapping, each vertex of the triangular mesh not only records the spatial coordinates, but also accumulates the grade attribute and the number of samplings, forming a set of triangular mesh vertices with attributes; Step 3.4: Generation of virtual sampling points based on the vertices of the triangular mesh: The triangular mesh vertex set with effective grade attributes obtained in the previous step is converted into virtual sampling points in the geological database; each virtual sampling point contains spatial coordinates. Grade values ​​(weighted average of cumulative grades at vertices) and confidence levels (a combined weight based on the number of samplings and equipment accuracy) are equivalent to the sampling input of exploration boreholes in geological attribute interpolation calculations. As the loading operation progresses, the lowered vertices are continuously assigned new data, forming a dynamically encrypted virtual sampling point network, providing an important data source for the attribute update in step four. Step 3.5: Partial reduction and qualitative-quantitative synergistic analysis of ore blending unit based on triangular mesh reduction: The system maintains the initial attribute parameters for each ore mixing unit (such as a blasting block segment), including the initial volume. Initial average grade An initial ore and rock distribution model; simultaneously, each ore blending unit consists of a set of triangular mesh panels, and the system records the set of triangular mesh panels contained in that unit. ; (1) Volume-driven partial reduction: As the loading operation proceeds, the Z-value replacement operation in step 3.1 continuously lowers the elevation of the triangular mesh vertices; when the average elevation of a certain triangular mesh facet is lower than the set threshold of the bottom plate of the ore mixing unit, the system determines that the ore body represented by the facet has been completely removed, marks it as "reduced", and removes it from the triangular mesh facet set of the unit; the system calculates the cumulative volume of the reduced facets in real time. ,when When a certain percentage threshold (such as 10%, 30%, 50%, 70%, 90%) of the unit is reached, a partial reduction operation is triggered: the volume block segment corresponding to that percentage is removed from the geological model, and the predicted average grade and ore-rock ratio of the remaining area are dynamically updated according to the grade distribution of the reduced area. (2) Deviation correction for production data calibration: The system compares the cumulative ore output from the two sources in real time; model estimates Calculated based on the cumulative volume of the reduced triangular mesh panels; actual measured cumulative volume in production. Based on the conversion of truck weighing weight to volume ( (mean density of the ore). When the deviation between the two exceeds a set threshold (e.g., 5%), the system determines that there is an estimation error (e.g., fluctuation in bucket filling coefficient, terrain reconstruction deviation) and performs the following calibration: Based on the actual cumulative production volume, the volume estimation coefficient of the remaining triangular mesh is corrected in reverse. Simultaneously adjust the volume calculation parameters (such as bucket filling rate) for subsequent loading operations to make the model converge to the measured data; The correction amount is proportionally allocated to the triangular mesh area currently being reduced, achieving fine spatial calibration; (3) Unit complete elimination judgment: When the following conditions are met simultaneously, the ore blending unit is judged to have been completely mined, and it is completely removed from the model and its boundary is closed: The set of triangular mesh faces contained in this unit is now empty (i.e., all faces have been eliminated). (The model estimates the volume to be close to the total volume). (The actual cumulative weight measured during production is close to the total weight). At this point, step three has completed the surface geometry update and the construction of the virtual sampling point network, providing a complete data input and computational foundation for the adaptive geological attribute update in step four.

[0013] Step four specifically involves: Step 4.1: Initialization of inverse distance weighted interpolation based on dynamic weights: The attribute iteration update algorithm library is invoked, using the original exploration boreholes as the main data source and the virtual sampling points generated in step 3.4 as the auxiliary data source. Inverse distance weighted interpolation is performed, and the interpolation formula is as follows: The parameters in the formula are defined as follows: The interpolation point refers to the coordinates of the center point of the unit block in the geological block model that currently needs to be assigned a grade value. ; The total number of sampling points involved in the interpolation calculation is determined by the number of valid sampling points within the current search radius $R$ (search radius). The initial value is set to 50 meters; for specific values, please refer to step 4.2 for adaptive adjustment. : No. Measured grade values ​​at each sampling point (unit: %) Interpolation point With the The three-dimensional Euclidean distance between each sampling point ; : Power exponent, controls the distance decay rate (initial value) (For specific values, see step 4.2 for adaptive adjustment). : No. The weight coefficient of each sampling point, and the distance of The weight is inversely proportional to the power of the distance; the closer the distance, the greater the weight. Interpolation point The predicted grade value at that point is the interpolation result output by the formula.

[0014] The initial weights of virtual sampling points can be initially set based on their data confidence (such as equipment accuracy and laboratory error), with higher confidence sampling points assigned higher weight coefficients; this step outputs the initial interpolated geological block model and the predicted values ​​of each sampling point. Step 4.2: Residual Diagnosis and Adaptive Calibration of Weight Parameters: First, calculate the measured values ​​of the newly inserted virtual sampling points. Compared with the original model's predicted value at this location The residuals between For the residual set Spatial statistical analysis was performed, and the following adaptive adjustments were made based on the residual distribution characteristics: (1) Power exponent Dynamic adjustment: If the residuals exhibit significant spatial fluctuations in a local region (i.e., the measured values ​​deviate significantly from the predicted values), it indicates that the current interpolation method is insufficiently fitted to local details; the system automatically increases the power exponent. (For example, adjust from 2 to 3 or 4) to enhance the influence weight of nearby sampling points and improve local fitting ability; if the residual distribution is relatively smooth, it indicates that the model is overfitting local noise, so appropriately reduce the weight. Values ​​that enhance the smoothing effect of sampling points at long distances; (2) Dynamic adjustment of search radius: If the residuals exhibit systematic deviations over a large range (e.g., continuous overestimation or underestimation), it indicates that the current search radius has failed to effectively capture the global spatial trend; the system automatically expands the interpolation search radius (e.g., from 50 meters to 80 meters) to include more distant sampling points; conversely, if the residuals exhibit local random fluctuations, the search radius is reduced (e.g., from 50 meters to 30 meters) to enhance the expressive power of local features. The adjustment range of the search radius is usually controlled between 50% and 150% of the initial value; (3) Sampling point weight adaptive: Based on the historical residual performance of a certain type of data source (such as a specific loading equipment or a specific batch of tests), the system automatically reduces the weight coefficient of data sources with larger deviations, and conversely increases their confidence level. Specifically, the system groups and calculates the absolute value of the average residual by data source type, and adjusts the weight coefficient accordingly. ,in The learning rate is set between 0.1 and 0.3. The mean absolute residual of this data source. This represents the maximum grade; the calibrated parameters output in this step ( , , This will be used for the next round of interpolation; Step 4.3: Iterative revaluation: Using the new parameters calibrated in step 4.2, inverse distance weighted interpolation is re-executed to generate an updated geological block model. The system can set a maximum number of iterations (e.g., 5 times) or a residual convergence threshold (e.g., average relative error less than 2%). When the condition is met, iteration stops, and the final updated model is output. This process enables the model to self-evolve, and the output results will be used for closed-loop feedback in step five.

[0015] Step five specifically involves: Step 5.1: Generate Deviation Diagnosis Report: The system summarizes the differences between the model-predicted grade and the actual grade fed into the concentrator for all updated areas within a shift (8 hours) or day, and generates a deviation diagnosis report to identify whether there are systematic deviations (such as a continuous overestimation of 0.5%) or local anomalies; this report serves as the basis for the next step of correction. Step 5.2: Closed-loop feedback correction: (1) Data weight correction: If a systematic bias is found in the data of a certain type of equipment (such as the weighing of a specific batch of trucks), the system will automatically reduce the registration weight of such data in the data fusion step, or mark it as needing calibration; (2) Interpolation strategy correction: If the residual diagnosis shows that a certain geological structure (such as a fault zone) frequently has update errors, the system will automatically switch the interpolation strategy in that area (such as increasing the power exponent). (To enhance local fitting, or to reduce the search radius to eliminate distant interference points). (3) Parameter memory and inheritance: The optimal parameters (optimal power exponent) after this round of calibration are stored in memory. Optimal search radius Optimal weights for each data source This information is saved as the initial prior value for the next round of updates, enabling the accumulation and transmission of knowledge.

[0016] Step six specifically involves: Step 6.1: Multi-dimensional dynamic visualization rendering: The final updated model output from step 4.3 is loaded into the 3D engine. Users can dynamically replay the reduction process of the landform and the evolution trajectory of the internal grade distribution over the past 24 hours by sliding the timeline. They can intuitively view the dynamic evolution effect of all attributes. The system overlays the standard deviation (degree of variation) generated by interpolation onto the solid model in the form of a semi-transparent heat map. High variance areas indicate high uncertainty in geological inference, while low variance areas indicate high data confidence, helping geologists identify areas that need to be further explored. Meanwhile, the real-time location and status (idle / loaded / transporting) of excavators and trucks on site are mapped onto the 3D scene in the form of dynamic icons and spatially overlaid with the current geological model to achieve real-time synchronous display of the status of people, machines and environment; this visualization interface provides intuitive spatial information for subsequent ore blending decisions; Step 6.2: Automatic generation of intelligent ore blending scheme: Users input daily production constraints on the interactive terminal, including the target grade range for selected products. Upper limit of harmful elements Maximum ore extraction limits in each mining area and the processing capacity of the crushing station The system calls the mixed integer linear programming (MILP) solver in the background, takes the latest updated block model grade data as input, and executes the following algorithm to calculate the optimal ore blend combination: (1) Objective function construction: The objective function is established with the goal of minimizing the weighted sum of energy consumption and cost of transportation throughout the mine: in, For shovel loading point To the unloading point The transportation distance (calculated based on real-time traffic conditions). Assignment variable (i.e., the first) (Mineral output) The cost per unit of ore is the transportation cost. (2) Constraint embedding: Grade constraint: Use the grade values ​​of the block model updated in step four. Ensure that the average grade of the mixed ore falls within the target range: Production capacity constraints: The ore output of each mining area must not exceed the minimum value of equipment capacity and remaining stockpile capacity. Total output balance: Ensure that the total output meets the throughput requirements of the crushing plant; (3) Dynamic weight adjustment and solution: The algorithm traverses all currently exploitable ore blending units. If a sudden change in the measured grade of a certain area is detected (such as a high-grade anomaly area found after residual calibration, i.e.) The system automatically adds a mining priority weighting coefficient for that area to the objective function. The mining plan is adjusted in real time. The solver generates the optimal solution matrix after convergence; (4) Issuance of instructions: The calculated optimal solution is converted into specific ore blending instructions, including instructions for each shovel loading point. Recommended mining output The matching truck ID list and recommended driving routes are sent in real time to the excavator's onboard terminal and the dispatch center's large screen via the mining private network, achieving millisecond-level penetration from "model update" to "production execution". Step 6.3: Deviation Early Warning and Manual Intervention Mechanism: The system continuously monitors the real-time deviation between the grade predicted by the model and the grade detected online at the crushing station; When the deviation exceeds the set threshold for three consecutive shifts, the system automatically pops up a prompt, suggesting that geologists check the data quality of the virtual sampling points; when the deviation exceeds the safety boundary or a potential risk of waste rock contamination is detected, the system automatically locks the ore extraction command of the relevant ore blending unit, forcibly suspends operations in that area, and notifies the dispatcher for manual verification; geological experts can manually delineate abnormal areas on the 3D interface, correct local lithological boundaries, or remove erroneous data points; after receiving the manual correction command, the system immediately triggers the re-interpolation process, recalculates the model attributes of the affected area, and pushes the correction results back to the ore blending module, forming a closed-loop optimization of human-machine collaboration.

[0017] The beneficial effects of this invention are: This invention integrates data from the entire "mining-transporting-unloading" process in time and space, tracing back the excavator loading coordinates, truck load, and crushing station grade along the time chain to each loading point, generating an enhanced loading point. This allows model updates to be directly based on actual production data, solving the problem of lag in traditional methods that rely on discrete drilling.

[0018] In terms of geometric updates, this invention uses the loading point as a local disturbance source, employing Z-value replacement within a dynamic search radius and incremental Delaunay reconstruction. It only updates the affected triangular mesh area, avoiding global recalculation and achieving second-level surface reduction to accurately track subtle terrain changes caused by loading. Simultaneously, the ore blending unit is decomposed into a set of facets, with each facet being reduced to drive a gradual evolution of volume and grade. Furthermore, the volume coefficient is corrected inversely by linking the truck's weighing weight, suppressing estimation errors caused by fluctuations in the filling rate.

[0019] In terms of attribute updates, this invention utilizes the residual spatial distribution between the measured and predicted values ​​of virtual sampling points to dynamically adjust the interpolation exponent, search radius, and data source weights—enhancing control of nearby samples when local fluctuations are severe and expanding the search range when there are systematic deviations—making the interpolation strategy adapt to the heterogeneity of the ore body and avoiding false fluctuations or excessive smoothing caused by fixed parameters.

[0020] In long-term operation, this invention uses the actual grade of the material entering the mill as a benchmark, diagnoses the source of deviations according to shifts and corrects data weights and regional strategies, and inherits the optimal parameters of each round to the next round, ensuring that the model accuracy does not decrease but increases as mining progresses; the updated model is immediately connected to the ore blending optimization algorithm, automatically generates scheduling instructions and issues them for execution under multiple constraints, forming a complete closed loop from perception, updating to decision-making, providing real-time and accurate geological support for intelligent ore blending in open-pit mines. Attached Figure Description

[0021] Figure 1This is a flowchart of the overall technical roadmap.

[0022] Figure 2 This is a schematic diagram of a partial update of the slope top surface. Detailed Implementation

[0023] The present invention will now be described in further detail with reference to the accompanying drawings.

[0024] A digital geological reverse update method based on precise real-time positioning of excavators includes the following steps; Step 1: System Hardware Deployment and Overall Architecture Setup This step aims to build the physical foundation for an open-pit mine digital geological reverse update system based on mining conditions, model bias, and dynamic correction closed-loop feedback. It mainly includes the deployment of the perception layer, transmission layer, computing layer, and application layer.

[0025] Step 1.1: Sensing Layer Device Configuration: On intelligent loading equipment, a high-precision GNSS-RTK receiver (positioning accuracy ±2cm), boom angle sensor, stick angle sensor, and hydraulic pressure sensor are installed on hydraulic excavators or electric shovels. Through multi-sensor fusion calculation, the three-dimensional coordinates of the bucket tip in the mining area coordinate system are obtained in real time. The loading and unloading status (digging, hoisting, slewing) is monitored. On intelligent transportation equipment, onboard weighing systems (accuracy ±1%) and positioning terminals are installed on mining dump trucks to record load data and driving trajectory in real time. At quality inspection points, online grade analyzers (such as X-ray fluorescence spectrometers) are installed at the crushing station inlet, or a rapid testing channel is established in the laboratory to acquire ore grade data in real time and automatically timestamp it.

[0026] Step 1.2: Transport Layer Network Construction: By utilizing the mine's dedicated network to establish a high-bandwidth, low-latency data transmission channel, the multi-source heterogeneous data collected by the aforementioned sensing layer is transmitted to the data center in real time with millisecond-level latency.

[0027] Step 1.3: Deployment of the Computation Layer and Application Layer: A high-performance server cluster is deployed to run core algorithm modules, including a multi-source data fusion engine, a surface dynamic reconstruction engine, a geological attribute interpolation engine, and a residual diagnosis and parameter calibration module. Simultaneously, a 3D visualization terminal is configured as the application layer interface to display real-time updated digital geological models, ore blending suggestions, and deviation analysis reports to the dispatch center and geological technicians.

[0028] Step Two: Data Fusion Processing Based on the Entire "Collection-Transportation-Unloading" Process: This step details how to transform scattered device data into a standardized data stream that can be used for model updates, addressing the problem of a single data source lacking collaboration.

[0029] Step 2.1: Multi-source heterogeneous data acquisition and preprocessing: The system collects the coordinate sequence of the excavator's bucket tip in real time. ,in Use timestamps; synchronously collect truck load data. and location trajectory ; Collect grade testing data from the crushing station and its detection time .

[0030] Step 2.2: Spatiotemporal registration and data association: First, time synchronization is performed, with all devices using the NTP protocol to unify the time base and eliminate clock drift errors. Then, spatial association logic is executed. (1) Loading event matching: When the excavator bucket completes a digging action and is lifted to the unloading height, the system records the moment. and location .

[0031] (2) Transport chain tracking: The system subsequently Within a time frame (e.g., 5-10 minutes), the search will be located in... Nearby trucks with a sudden increase in load The load capacity of the truck This is related to the shovel loading operation.

[0032] (3) Taste traceability: based on truck Based on its travel trajectory and speed, the time it takes to arrive at the crushing station can be estimated. The system will Quality detection data near the time The process is traced back to the initial shovel loading action.

[0033] Step 2.3: Generate enhanced shovel loading points: This ultimately forms data points containing complete attributes. This refers to the "enhanced shovel loading point," which serves as the direct input for subsequent model updates.

[0034] Step 3: Real-time reduction of the surface model, triangular mesh reconstruction, and progressive reduction of ore-mixing units: This step details how to use real-time loading data to geometrically update the surface model and achieve partial reduction and attribute evolution of ore blending units based on triangular mesh topology.

[0035] Step 3.1: Dynamic Search and Z-Value Replacement: For each newly generated enhanced shovel point The system treats it as a "mining disturbance source." A dynamic search radius is set. In this step, The value is taken as 1.5 times the bucket width (for example, if the bucket width is 3 meters, then...). (meters), this radius can be adaptively adjusted according to the equipment model. Center of the circle Within a circular region of radius , retrieve the set of all triangulated vertices in the original digital terrain model. . Set All vertices in Coordinates are updated to reflect the current excavation depth. (Or the local bottom elevation calculated by interpolation based on the bucket posture). This step simulates the immediate reduction effect after the bucket removes soil, achieving real-time reduction of the ground surface.

[0036] Step 3.2: Local triangulation reconstruction: To avoid computational delays caused by global reconstruction, the system only reconstructs the affected local regions. A constrained Delaunay triangulation algorithm is employed, using the updated vertex set... Based on this, the triangular network topology within the region is reconstructed to ensure the new landform is continuous and free of self-intersections. Unaffected areas remain unchanged, thus achieving millisecond-level incremental reconstruction.

[0037] Step 3.3: Attribute mapping from shovel loading points to triangular mesh nodes: The enhanced shovel point generated in step 2.3 Spatially correlate it with the triangular mesh it belongs to: (1) If the distance between the point and the existing triangulation vertex is less than the threshold (such as the bucket radius), then the grade value of the point is directly set. Assign to the corresponding vertex; (2) If the point is located inside the triangular mesh, the grade value is distributed to the three vertices of the mesh by interpolation of the centroid coordinates.

[0038] Through the above mapping, each vertex of the triangulation not only records spatial coordinates... It also accumulates the quality attribute values ​​and sampling times of the points, forming a "set of vertices of a triangular mesh with attributes".

[0039] Step 3.4: Generation of virtual sampling points based on the vertices of the triangular mesh: The vertices with effective grade attributes in the triangulation network vertex set are converted into "virtual sampling points" in the geological database. Each virtual sampling point contains spatial coordinates. The grade value (a weighted average of the cumulative grades at the vertices) and confidence level (a combined weight based on the number of samplings and equipment accuracy) are equivalent to the sampling input from exploration boreholes in geological attribute interpolation calculations. As the loading operation progresses, the vertices of the triangular mesh that have been lowered are continuously assigned new grade data, forming a dynamic sampling network that is encrypted in real time as the mining process proceeds.

[0040] Step 3.5: Partial reduction and qualitative-quantitative synergistic analysis of ore blending unit based on triangular mesh reduction: The system maintains the initial attribute parameters for each ore mixing unit (such as a blasting block segment), including the initial volume. Initial average grade An initial ore and rock distribution model is established. Simultaneously, each ore blending unit consists of a set of triangular mesh panels, and the system records the set of triangular mesh panels contained in that unit. .

[0041] (1) Volume-driven partial reduction: As the loading operation progresses, the Z-value replacement operation in step 3.1 continuously lowers the elevation of the triangular mesh vertices. When the average elevation of a certain triangular mesh facet is lower than the set threshold of the bottom plate of the ore-mixing unit, the system determines that the ore body represented by the facet has been completely removed, marks it as "reduced," and removes it from the triangular mesh facet set of that unit. The system calculates the cumulative volume of the reduced facets in real time. ,when When a certain percentage threshold (e.g., 10%, 30%, 50%, 70%, 90%) is reached in the overall unit, a partial reduction operation is triggered: the volumetric block corresponding to that percentage is removed from the geological model, and the predicted average grade and ore-rock ratio of the remaining area are dynamically updated based on the grade distribution of the reduced area. This process reflects the gradual evolutionary law of "quantitative change (gradual reduction of triangular mesh panels) → qualitative change (change in the distribution of remaining grades)".

[0042] (2) Deviation correction for production data calibration: The system compares the cumulative ore output from the two sources in real time. Model estimation quantity Calculated based on the cumulative volume of the reduced triangular mesh panels; actual measured cumulative volume in production. Based on the conversion of truck weighing weight to volume ( (This represents the average density of the ore).

[0043] When the deviation between the two exceeds a set threshold (e.g., 5%), the system determines that there is an estimation error (e.g., fluctuation in bucket filling coefficient, terrain reconstruction deviation) and performs the following calibration: Based on the actual cumulative production volume, the volume estimation coefficient of the remaining triangular mesh is corrected in reverse. Simultaneously adjust the volume calculation parameters (such as bucket filling rate) for subsequent loading operations to make the model converge to the measured data; The correction amount is proportionally allocated to the triangular mesh area that is currently being reduced, achieving fine spatial calibration.

[0044] (3) Unit complete elimination judgment: When the following conditions are met simultaneously, the ore blending unit is judged to have been completely mined, and it is completely removed from the model and its boundary is closed: The set of triangular mesh faces contained in this unit is now empty (i.e., all faces have been eliminated). (The model estimates the volume to be close to the total volume). (The actual cumulative weight measured during production is close to the total weight).

[0045] Step 4: Adaptive update of geological attributes based on virtual sampling point network: This step details how to use new data to revise the geological grade model and achieve dynamic evolution of all elements of the model through parameter adaptive calibration.

[0046] Step 4.1: Initialization of inverse distance weighted interpolation based on dynamic weights: The attribute iteration update algorithm library is invoked, using the original exploration boreholes as the primary data source and the newly generated virtual sampling points as the secondary data source, to perform inverse distance weighted interpolation. The interpolation formula is as follows: in For the point to be interpolated and the first Spatial distance between sampling points The exponent is the power (initially taken as...) The weights of virtual sampling points can be initially set based on their data confidence level (such as equipment accuracy and test error), with sampling points having higher confidence levels being assigned higher weight coefficients.

[0047] Step 4.2: Residual Diagnosis and Adaptive Calibration of Weight Parameters: First, calculate the measured values ​​of the newly inserted virtual sampling points. Compared with the original model's predicted value at this location The residuals between For the residual set Spatial statistical analysis was performed, and the following adaptive adjustments were made based on the residual distribution characteristics: (1) Power exponent Dynamic adjustment: If the residuals exhibit significant spatial fluctuations in local areas (i.e., large deviations between measured and predicted values), it indicates that the current interpolation method is insufficiently fitted to local details. The system automatically increases the power exponent. (For example, adjust from 2 to 3 or 4) to enhance the influence weight of nearby sampling points and improve local fitting ability; if the residual distribution is relatively smooth, it indicates that the model is overfitting local noise, so appropriately reduce the weight. This value enhances the smoothing effect of sampling points at long distances.

[0048] (2) Dynamic adjustment of the search radius: If the residuals exhibit systematic deviations over a large range (e.g., continuous overestimation or underestimation), it indicates that the current search radius has failed to effectively capture the global spatial trend. The system automatically expands the interpolation search radius (e.g., from 50 meters to 80 meters) to include more distant sampling points; conversely, if the residuals exhibit local random fluctuations, the search radius is reduced (e.g., from 50 meters to 30 meters) to enhance the expressive power of local features. The adjustment range of the search radius is usually controlled between 50% and 150% of the initial value.

[0049] (3) Sampling point weight adaptive: Based on the historical residual performance of a certain type of data source (such as a specific loading equipment or a specific batch of tests), the system automatically reduces the weight coefficient of data sources with larger deviations, and conversely increases their confidence level. Specifically, the system groups and calculates the absolute value of the average residual by data source type, and adjusts the weight coefficient accordingly. ,in The learning rate is set between 0.1 and 0.3. The mean absolute residual of this data source. This represents the maximum grade.

[0050] Step 4.3: Iterative revaluation: Using the new calibrated parameters (power exponent) Search radius Sampling point weights The inverse distance weighted interpolation is re-executed to generate an updated geological block model. The system allows setting a maximum number of iterations (e.g., 5) or a residual convergence threshold (e.g., average relative error less than 2%). When the condition is met, iteration stops, and the final updated model is output. This process enables the model to "self-evolve," adapting to local heterogeneous changes in the ore body.

[0051] Step 5: Closed-loop feedback mechanism for mining conditions, model deviations, and dynamic correction: This step describes the system's long-term self-optimization capability, ensuring that the model's accuracy increases rather than decreases over time.

[0052] Step 5.1: Generate Deviation Diagnosis Report: The system summarizes the differences between the model-predicted grade and the actual grade fed into the concentrator in all updated areas within a shift (8 hours) or day, generates a deviation diagnosis report, and identifies whether there are systematic deviations (such as a continuous overestimation of 0.5%) or local anomalies.

[0053] Step 5.2: Closed-loop feedback correction: (1) Data weight correction: If a systematic bias is found in the data of a certain type of equipment (such as the weighing of a specific batch of trucks), the system will automatically reduce the registration weight of such data in the data fusion step, or mark it as "needs calibration".

[0054] (2) Interpolation strategy correction: If the residual diagnosis shows that a certain geological structure (such as a fault zone) frequently has update errors, the system will automatically switch the interpolation strategy in that area (such as increasing the power exponent). To enhance local fitting, or to reduce the search radius to eliminate distant interference points.

[0055] (3) Parameter memory and inheritance: The optimal parameters (optimal power exponent) after this round of calibration are stored in memory. Optimal search radius Optimal weights for each data source This information is saved as the initial prior value for the next round of updates, enabling the accumulation and transmission of knowledge.

[0056] Step Six: Visual Interaction and Dynamic Control Application Scenarios; This step details how the system provides users with a visual interactive interface and supports dynamic production control based on the updated digital geological model, demonstrating the final application of the technical solution.

[0057] Step 6.1: Multi-dimensional dynamic visualization rendering: The updated geological block model, as described above, is loaded into the 3D engine. Users can dynamically replay the surface morphology reduction process and the evolution trajectory of internal grade distribution over the past 24 hours by sliding the timeline, intuitively viewing the dynamic evolution effect of all attributes. The system overlays the interpolated standard deviation (degree of variation) onto the solid model as a semi-transparent heatmap. High variance areas indicate high uncertainty in geological inferences, while low variance areas indicate high data confidence, assisting geologists in identifying areas requiring further exploration. Simultaneously, the real-time location and status (idle / loaded / transporting) of excavators and trucks on site are mapped onto the 3D scene as dynamic icons and spatially overlaid with the current geological model, achieving real-time synchronous display of the human-machine-environment status.

[0058] Step 6.2: Automatic generation of intelligent ore blending scheme: Users input daily production constraints on the interactive terminal, including the target grade range for selected products. Upper limit of harmful elements Maximum ore extraction limits in each mining area and the processing capacity of the crushing station The system calls the mixed integer linear programming (MILP) solver in the background, takes the latest updated block model grade data as input, and executes the following algorithm to calculate the optimal ore blend combination: (1) Objective function construction: The objective function is established with the goal of minimizing the weighted sum of energy consumption and cost of transportation throughout the mine: in, For shovel loading point To the unloading point The transportation distance (calculated based on real-time traffic conditions). Assignment variable (i.e., the first) (Mineral output) The cost per unit of ore is the transportation cost. (2) Constraint embedding: Grade constraint: Use the grade values ​​of the block model updated in step four. Ensure that the average grade of the mixed ore falls within the target range: Production capacity constraints: The ore output of each mining area must not exceed the minimum value of equipment capacity and remaining stockpile capacity. Total output balance: Ensure that the total output meets the throughput requirements of the crushing plant; (3) Dynamic weight adjustment and solution: The algorithm traverses all currently exploitable ore blending units. If a sudden change in the measured grade of a certain area is detected (such as a high-grade anomaly area found after residual calibration, i.e.) The system automatically adds a mining priority weighting coefficient for that area to the objective function. The mining plan is adjusted in real time. The solver generates the optimal solution matrix after convergence; (4) Issuance of instructions: The calculated optimal solution is converted into specific ore blending instructions, including instructions for each shovel loading point. Recommended mining output The matching truck ID list and recommended driving routes are sent in real time to the excavator's onboard terminal and the dispatch center's large screen via the mining private network, achieving millisecond-level penetration from "model update" to "production execution". Step 6.3: Deviation Early Warning and Manual Intervention Mechanism: The system continuously monitors the real-time deviation between the "model-predicted grade" and the "online detected grade at the crushing station." When the deviation exceeds the set threshold for three consecutive shifts, the system automatically pops up a prompt, suggesting that geologists check the data quality of the virtual sampling points. When the deviation exceeds the safety boundary or a potential risk of waste rock contamination is detected, the system automatically locks the ore extraction instructions of the relevant blending unit, forcibly suspends operations in that area, and notifies the dispatcher for manual verification. Geological experts can manually delineate abnormal areas on the 3D interface, correct local lithological boundaries, or remove erroneous data points. Upon receiving a manual correction instruction, the system immediately triggers a re-interpolation process, recalculates the model attributes of the affected area, and pushes the correction results back to the blending module, forming a closed-loop optimization through human-machine collaboration.

[0059] Through the description of this step, the present invention not only realizes the automated updating of geological models, but also constructs a complete intelligent operation chain from data perception to model evolution and then to decision control, truly transforming real-time synchronous and fully dynamic geological data into actual productivity of mine production.

[0060] Simulation applications: This embodiment uses a large open-pit copper-molybdenum polymetallic mine as the application scenario. The mine has an annual stripping and mining volume of approximately 50 million tons, a daily ore processing capacity of approximately 150,000 tons, a mining area of ​​approximately 4.5 square kilometers, and a mining depth of approximately 350 meters. The mine's existing main loading equipment consists of 8 hydraulic excavators (bucket width 3.2 meters, bucket capacity 12 cubic meters) and 4 electric shovels. The transportation fleet consists of 45 mining dump trucks (load capacity 100 tons), equipped with 3 online grade analyzers (X-ray fluorescence spectrometers) at the feed inlets of the crushing stations. The mine's original digital geological model is based on 89 exploration boreholes, with block model unit dimensions of 10m × 10m × 10m. The ore blending units are divided according to blasted blocks, with an average unit volume of approximately 30,000 cubic meters.

[0061] The following is in conjunction with the appendix Figure 1 The technical route and process shown Figure 2 The schematic diagram of the partial update of the slope top surface is shown in the figure, which details the specific execution process of this embodiment.

[0062] Step 1 Execution: GNSS-RTK receivers (positioning accuracy ±2cm), boom angle sensors, stick angle sensors, and hydraulic pressure sensors were installed on each excavator and electric shovel. After multi-sensor fusion calculation, the bucket tip positioning accuracy reached ±3cm, and the accuracy rate of loading action status recognition reached 98.5%. All dump trucks were equipped with onboard weighing systems (accuracy ±0.8%) and positioning terminals. The X-ray fluorescence spectrometer at the crushing station inlet outputs grade detection data every 30 seconds, with a detection accuracy of ±0.05 percentage points. A dedicated mining network was used to control data transmission latency to within 50 milliseconds. A high-performance server cluster was configured with 8 computing nodes, a total memory of 512GB, and 4 GPU accelerator cards, supporting the real-time operation of core algorithm modules.

[0063] Step Two Execution Status: On the first day of system launch, a total of 127,643 excavator bucket tip coordinate sequences, 2,856 truck load data, and 8,923 online grade detection data from the crushing station were collected. After unifying the time base through the NTP protocol, the spatiotemporal registration success rate reached 96.2%. In a typical loading event, at 09:23:17 AM, the system recorded that excavator No. 3 completed a loading action at coordinates (E45231.8, N38972.5, Z124.3). Subsequently, within 5 minutes and 42 seconds, the system detected that the load of truck No. 17, located within a 15-meter radius of that location, suddenly increased from 12.3 tons to 107.8 tons, successfully linking the load data to the loading point. Based on the trajectory and speed of truck No. 17, it was calculated that the truck arrived at the crushing station at 09:41:05 AM. The system automatically matched the grade detection value (Cu grade 0.682%) near that moment, tracing back to the initial loading action. A total of 2,847 enhanced shovel loading points were generated on that day, and each data point contained complete attributes (x, y, z, W, G).

[0064] Step 3 Execution Status: The system used a dynamic search radius of 1.5 times the bucket width of 3.2 meters (i.e., 4.8 meters) to perform Z-value replacement operations on each enhanced shovel loading point. A total of 43,892 triangulation vertices were updated daily, with 2,847 local triangulation reconstructions, and an average reconstruction time of approximately 120 milliseconds per operation. During the mining of ore blending unit B-07 (initial volume 32,460 cubic meters, initial average Cu grade 0.571%), the system tracked the reduction progress of the 1,847 triangulation facets contained in the unit in real time. When the cumulative volume of the reduced facets reached 30.2% of the total unit volume (approximately 9,800 cubic meters), the system automatically triggered a partial reduction operation: removing the volume segment corresponding to this proportion from the geological model and updating the predicted average grade of the remaining area from 0.571% to 0.593%. The system simultaneously compared the volume estimated by the model with the volume converted from the truck's weighbridge, and found that the cumulative deviation for the day was +4.2% (the model estimate was slightly higher than the actual measurement). It automatically corrected the volume estimation coefficient of the remaining triangular mesh to 0.958 and reduced the bucket filling rate from 92% to 88%.

[0065] Step 4 Execution Status: Based on the 2847 virtual sampling points generated on the same day (converted from triangulation vertices), the system performed inverse distance weighted interpolation, using the original 89 exploration boreholes as the main data source and the virtual sampling points as the auxiliary data source. After the initial interpolation, the residuals between the measured values ​​and the model predictions of the newly inserted virtual sampling points were calculated. Significant spatial fluctuations in the residuals were found in a local area (near the F12 fault zone) (mean absolute residual 0.087 percentage points). The system automatically increased the power exponent k from 2 to 3.2 and reduced the search radius from 50 meters to 35 meters. After three iterations of reestimation, the mean relative error converged from the initial 3.6% to 1.8%, meeting the convergence threshold (less than 2%), and the updated block model was output. The updated model showed that the Cu grade in the remaining area of ​​unit B-07 increased by approximately 0.022 percentage points compared to before the update, confirming a grade enrichment trend in this area.

[0066] Step 5 Execution Status: The system summarizes deviation reports by shift. The first shift (08:00-16:00) involved 12 ore blending units in the updated area. The model predicted a weighted average grade for the mill feed of 0.623%, while the actual weighted average grade detected online at the crushing station was 0.615%, resulting in a system deviation of +0.008 percentage points (approximately +1.3%), which is within the normal fluctuation range and did not trigger correction. After 7 consecutive days of operation, the system diagnostic report showed that the associated data of excavator No. 3 had a systematic overestimation deviation (average +0.031 percentage points), and automatically lowered the weight coefficient of the data source for this equipment from 1.00 to 0.82. At the same time, for the F12 fault zone area, the system saved the optimal power exponent k_best=3.2 and the optimal search radius R_best=35 meters as the initial prior values ​​for the next round of updates.

[0067] Step Six Execution Status: On the 3D visualization terminal, the dispatchers replayed the surface reduction process of Unit B-07 over the past 24 hours by sliding the timeline—the number of triangular mesh patches gradually decreased from 1,847 to 893, and the grade distribution heat map gradually changed from an initial uniform blue (0.55%-0.60%) to an enriched area dominated by red (0.62%-0.68%). On the same day, during the ore blending scheme generation phase, the system used the updated block model as input. Under constraints (target Cu grade of 0.60%-0.65%, maximum As content of 0.08%, and maximum ore output limits for each mining area), it invoked a mixed integer programming algorithm to automatically output the optimal ore blending combination: It recommended an ore output of 2800 tons / hour for unit B-07, 1900 tons / hour for unit B-12, and 1300 tons / hour for unit C-03. It also specified that excavators No. 3, 5, and 7 be combined with trucks No. 12, 18, 23, and 31 for transportation, shortening the total transportation distance by approximately 2.7 kilometers / hour compared to the manual method. The ore blending instructions were transmitted to each equipment terminal in real time via the mine's dedicated network.

[0068] Implementation Results: After six months of continuous operation at the mine, statistical data showed that the geological model update cycle was shortened from the traditional "weekly" (average 7 days) to "minute-level" (average 3.5 minutes); the average absolute error of model grade prediction decreased from 0.087 percentage points to 0.032 percentage points; the standard deviation of feed grade fluctuation decreased from 0.071 percentage points to 0.039 percentage points; and the time for generating ore blending schemes was reduced from approximately 2 hours of manual compilation to approximately 45 seconds of automatic calculation by the system. This system effectively supported the mine's shift from an "experience-driven" to a "data-driven" production management model, significantly improving resource utilization and production efficiency.

Claims

1. A digital geological reverse update method based on precise real-time positioning of excavators, characterized in that, Includes the following steps; Step 1: Deploy system hardware and build overall architecture. Real-time data collection is carried out through the perception layer devices, including bucket tip coordinate sequence, loading action status, truck load and trajectory, and crushing station grade detection data. The data is then aggregated through the transmission layer to the computing layer to form a multi-source heterogeneous raw data stream. Step 2: Perform spatiotemporal registration and correlation on the multi-source heterogeneous data obtained in Step 1, and integrate the scattered loading action state coordinates, truck load and crushing station grade detection data into an enhanced loading point with a unified spatiotemporal label. Step 3: Using the enhanced shovel-mounted point integrated in Step 2 as the driving source, based on the digital surface model, perform Z-value replacement within the dynamic search radius and reconstruction of the local constrained Delaunay triangulation network to realize surface geometry update and construction of the virtual sampling point network, and drive the ore blending unit to gradually reduce the area and evolve in a grade-volume co-evolution. Step 4: Adaptive update of geological attributes based on virtual sampling point network. Based on the virtual sampling point network generated after surface geometry update, the original exploration boreholes are used as the main data source and virtual sampling points are used as the auxiliary data source. Residual diagnosis-driven inverse distance weighted interpolation iterative calculation is performed, and the power exponent, search radius and data source weight are dynamically adjusted to output the updated geological block model. Step 5: Based on the updated geological block model, summarize the deviation between the model's predicted grade and the actual grade entering the mill by shift, generate a deviation diagnosis report, and correct the data fusion weights, regional interpolation strategies, and initial prior parameters of the iteration accordingly to achieve long-term self-optimization of model accuracy. Step Six: Visual Interaction and Dynamic Control Application Scenarios. Based on the final updated model, perform 3D dynamic rendering and spatiotemporal evolution playback. Call the mixed integer linear programming solver to automatically generate a ore blending scheme that meets multiple constraints, and send scheduling instructions to the equipment terminal in real time. At the same time, retain the manual intervention interface to realize closed-loop control of human-machine collaboration.

2. The digital geological reverse update method based on precise real-time positioning of excavators according to claim 1, characterized in that, Step one specifically involves: Step 1.1: Install a high-precision GNSS-RTK receiver, boom angle sensor, stick angle sensor, and hydraulic pressure sensor on a hydraulic excavator or electric shovel; through sensor fusion calculation, obtain the three-dimensional coordinates of the bucket tip in the mining area coordinate system in real time. The loading action status includes three stages: digging, lifting, and slewing. The continuous detection and judgment of the above action status is the logical basis for determining the start and end times of a loading event. Install on-board weighing systems and positioning terminals on mining dump trucks to record load data and driving trajectory in real time; install online grade analyzers at the feed inlet of crushing stations, or establish rapid testing channels in laboratories to obtain ore grade data in real time and automatically add timestamps. The multi-source heterogeneous data collected by the aforementioned sensing layer specifically includes: the bucket tip coordinate sequence from excavators / electric shovels. Boom and stick attitude angles and hydraulic pressure values; load data from dump trucks. and location trajectory Grade testing data from crushing plants or laboratories and its detection time ; Step 1.2: Utilize the existing industrial Ethernet private network in the mine to establish a high-bandwidth, low-latency data transmission channel, and transmit the multi-source heterogeneous data collected in Step 1.1 to the data center in real time with millisecond-level latency to ensure that subsequent processing can obtain timely and complete raw data streams; Step 1.3: Deploy a high-performance server cluster and run the core algorithm modules, including the multi-source data fusion engine, the surface dynamic reconstruction engine, the geological attribute interpolation engine, and the residual diagnosis and parameter calibration module; the functions and interrelationships of each module are as follows: (1) The multi-source data fusion engine receives the raw data stream transmitted in step 1.2, performs time synchronization, outlier removal, loading event matching and transport chain tracking, integrates the scattered loading coordinates, load and grade data into an enhanced loading point with a unified spatiotemporal label, and outputs it to the surface dynamic reconstruction engine. (2) The surface dynamic reconstruction engine uses the enhanced shovel point as the driving source to perform Z value replacement and local constrained Delaunay triangulation reconstruction within the dynamic search radius of the digital surface model, and outputs the updated surface model and the virtual sampling point network converted from the triangulation vertices for the geological attribute interpolation engine to call. (3) The geological attribute interpolation engine uses the original exploration boreholes as the main data source and virtual sampling points as the auxiliary data source, performs inverse distance weighted interpolation iterative calculation driven by residual diagnosis, and outputs the updated geological block model. (4) The residual diagnosis and parameter calibration module monitors the residual between the measured value of the newly inserted virtual sampling point and the predicted value of the point in the output of the geological attribute interpolation engine. Based on this, it dynamically adjusts the interpolation power exponent, search radius and data source weight, and sends the calibrated optimal parameters back to the geological attribute interpolation engine for use in the next iteration. The multi-source data fusion engine, the surface dynamic reconstruction engine, the geological attribute interpolation engine, and the output update model run in a serial cascade manner. The residual diagnosis and parameter calibration module provides horizontal services to the geological attribute interpolation engine and forms an internal feedback loop with it. At the same time, a 3D visualization terminal is configured as the application layer interface to display the real-time updated digital geological model, ore blending suggestions and deviation analysis reports to the dispatch center and geological technicians. The final output of step 1.3 is: the enhanced shovel point dataset after fusion processing.

3. The digital geological reverse update method based on precise real-time positioning of excavators according to claim 2, characterized in that, Step two specifically involves: Step 2.1: The system receives the excavator bucket tip coordinate sequence transmitted in Step 1 in real time. ( (timestamps) and truck load data and location trajectory Crushing station grade testing data and its detection time ; The received raw data is preprocessed as follows: (1) Remove obvious outliers; (2) Perform preliminary sorting and caching according to a unified timestamp to form a temporary dataset indexed by device ID, including excavator event sequences. Truck load and trajectory sequence Grade detection sequence ; The preliminary sorting results after preprocessing are output to step 2.2; Step 2.2: Based on the temporary dataset indexed by device ID formed after preprocessing in Step 2.1, perform the following operations: First, time synchronization is performed, with all devices using the NTP protocol to unify the time base and eliminate clock drift errors; then, spatial association logic is executed. (1) Loading event matching: in the excavator event sequence During loading, when the system detects that the bucket posture has switched from "digging" to "lifting" and then completed the "slewing" action, the system records the moment of this loading event. and location ; (2) Transport chain tracking: The system subsequently Within a time period, in the truck location trajectory dataset Search in the middle Nearby and load data Gradually increase the number of trucks to full load. The load capacity of the truck Associate this loading action with the loading event log and write the association result to the loading event log. (3) Taste traceability: based on truck Based on its travel trajectory and speed, the time it takes to arrive at the crushing station can be estimated. The system will Quality detection data near the time Tracing back to the initial shovel loading action; The output of step 2.2 is a set of loading event records that has completed loading event matching, transport chain tracking, and quality backtracking association. This set of records is passed to step 2.3 to generate enhanced loading points. Step 2.3: Based on the association results from the previous step, generate data points containing complete attributes for each loading action. These are enhanced shovel points, which will directly drive the surface geometry update in step three.

4. The digital geological reverse update method based on precise real-time positioning of excavators according to claim 3, characterized in that, Step three specifically involves: Step 3.1: For each newly generated enhanced shovel point The system treats it as a source of mining disturbance and sets a dynamic search radius. This radius is adaptively adjusted according to the equipment model; In Center of the circle Within a circular region of radius , retrieve the set of all triangulated vertices in the original digital terrain model. ; set All vertices in Coordinates are updated to reflect the current excavation depth. ; updated Local vertex set after value ; Step 3.2: The system only reconstructs the affected local regions, using the updated local vertex set output in Step 3.

1. Based on this, the constrained Delaunay triangulation algorithm is used to reconstruct the triangulation topology of the region, ensuring that the new landform is continuous and non-self-intersecting; unaffected areas remain unchanged; and the reconstructed triangulation provides a geometric basis for subsequent attribute mapping. Step 3.3: Apply the enhanced shovel point generated in Step 2.3 Spatially associate the triangular mesh obtained in step 3.2 with the following: (1) If the distance between the point and the existing triangular mesh vertex is less than the threshold, then the grade value of the point is directly set. Assign to the corresponding vertex; (2) If the point is located inside the triangular mesh, the grade value is distributed to the three vertices of the mesh through centroid coordinate interpolation; through mapping, each vertex of the triangular mesh not only records the spatial coordinates, but also accumulates the grade attribute and the number of samplings, forming a set of triangular mesh vertices with attributes; Step 3.4: Convert the triangular mesh vertex set with effective grade attributes obtained in the previous step into virtual sampling points in the geological database; each virtual sampling point contains spatial coordinates. Grade values ​​and confidence levels are equivalent to the sampling input of exploration boreholes in geological attribute interpolation calculations; as the loading operation progresses, the lowered vertices are continuously assigned new data, forming a dynamically encrypted virtual sampling point network; Step 3.5: The system maintains the initial attribute parameters of each ore blending unit, including the initial volume. Initial average grade An initial ore and rock distribution model; simultaneously, each ore blending unit consists of a set of triangular mesh panels, and the system records the set of triangular mesh panels contained in that unit. ; (1) When the average elevation of a certain triangular mesh facet is lower than the set threshold of the bottom plate of the ore-mixing unit, the system determines that the ore body represented by the facet has been completely removed, marks it as "reduced", and removes it from the triangular mesh facet set of the unit; the system calculates the cumulative volume of the reduced facets in real time. ,when When a certain percentage threshold of the unit is reached, a partial reduction operation is triggered: the volume block segment corresponding to that percentage is removed from the geological model, and the predicted average grade and ore-rock ratio of the remaining area are dynamically updated according to the grade distribution of the reduced area. (2) The system compares the cumulative ore output from the two sources in real time; the model estimates the output. Calculated based on the cumulative volume of the reduced triangular mesh panels; actual measured cumulative volume in production. Based on the conversion of truck weighing weight into volume, The average density of the ore; When the deviation between the two exceeds a set threshold, the system determines that there is an estimation error and performs the following calibration: Based on the actual cumulative production volume, the volume estimation coefficient of the remaining triangular mesh is corrected in reverse. Simultaneously adjust the volume calculation parameters for subsequent loading operations to make the model converge to the measured data; The correction amount is proportionally allocated to the triangular mesh area currently being reduced, achieving fine spatial calibration; (3) When the following conditions are met simultaneously, the ore blending unit is determined to have been completely mined, and it is completely removed from the model and its boundary is closed: The set of triangular meshes contained in this unit is now empty; ; ;。 5. The digital geological reverse update method based on precise real-time positioning of excavators according to claim 4, characterized in that, Step four specifically involves: Step 4.1: Call the attribute iteration update algorithm library, using the original exploration boreholes as the main data source and the virtual sampling points generated in Step 3.4 as the auxiliary data source, and perform inverse distance weighted interpolation. The interpolation formula is as follows: The parameters in the formula are defined as follows: The interpolation point refers to the coordinates of the center point of the unit block in the geological block model that currently needs to be assigned a grade value. ; The total number of sampling points involved in the interpolation calculation is determined by the number of valid sampling points within the current search radius $R$. : No. Measured grade values ​​at each sampling point; Interpolation point With the The three-dimensional Euclidean distance between each sampling point ; : Power exponent, controls the rate of distance decay; : No. The weight coefficient of each sampling point, and the distance of The weight is inversely proportional to the power of the distance; the closer the distance, the greater the weight. Interpolation point The predicted grade value at that point is the interpolation result output by the formula. The initial weights of virtual sampling points can be initially set based on their data confidence levels, with higher confidence levels assigned higher weight coefficients. This step outputs the initial interpolated geological block model and the predicted values ​​for each sampling point. Step 4.2: First, calculate the measured values ​​of the newly inserted virtual sampling points. Compared with the original model's predicted value at this location The residuals between For the residual set Spatial statistical analysis was performed, and the following adaptive adjustments were made based on the residual distribution characteristics: (2) Power exponent Dynamic adjustment: If the residuals exhibit significant spatial fluctuations in a local region, it indicates that the current interpolation method is insufficiently fitted to local details; the system automatically increases the power exponent. To enhance the influence weight of nearby sampling points and improve local fitting ability; if the residual distribution is relatively smooth, it indicates that the model is overfitting local noise, in which case the weight should be appropriately reduced. Values ​​that enhance the smoothing effect of sampling points at long distances; (2) Dynamic adjustment of search radius: If the residual shows a systematic deviation over a large range, it indicates that the current search radius has failed to effectively capture the global spatial trend; the system automatically expands the interpolation search radius to include more distant sampling points; Conversely, if the residuals exhibit local random fluctuations, the search radius should be reduced to enhance the expressive power of local features; the adjustment range of the search radius is usually controlled between 50% and 150% of the initial value. (3) Adaptive sampling point weights: Based on the historical residual performance of a certain type of data source, the weight coefficient of the data source with larger deviation is automatically reduced, and the confidence level of the data source with smaller deviation is increased. Specifically, the system groups and calculates the absolute value of the average residual according to the data source type, and adjusts the weighting coefficients accordingly. ,in The learning rate is set between 0.1 and 0.

3. The mean absolute residual of this data source. This represents the maximum grade; the calibrated parameters output in this step ( , , This will be used for the next round of interpolation; Step 4.3: Re-execute inverse distance weighted interpolation using the new parameters calibrated in Step 4.2 to generate an updated geological block model. The system can set a maximum number of iterations or a residual convergence threshold. When the conditions are met, the iteration stops and the final updated model is output.

6. The digital geological reverse update method based on precise real-time positioning of excavators according to claim 5, characterized in that, Step five specifically involves: Step 5.1: The system summarizes the differences between the model-predicted grade and the actual grade fed into the concentrator for all updated areas within the time period, on a shift or daily basis, and generates a deviation diagnosis report to identify whether there are systematic deviations or local anomalies; this report serves as the basis for the next step of correction. Step 5.2: (1) Data weight correction: If a certain type of equipment data is found to cause systematic deviation, the system will automatically reduce the registration weight of that type of data in the data fusion step, or mark it as needing calibration; (2) Interpolation strategy correction: If the residual diagnosis shows that a certain geological structure frequently has update errors, the system will automatically switch the interpolation strategy in that area; (3) Parameter memory and inheritance: The optimal parameters after this round of calibration are saved as the initial prior values ​​for the next round of updates, so as to realize the accumulation and inheritance of knowledge.

7. The digital geological reverse update method based on precise real-time positioning of excavators according to claim 6, characterized in that, Step six specifically involves: Step 6.1: Load the final updated model output from Step 4.3 into the 3D engine. Users can dynamically replay the reduction process of the landform and the evolution trajectory of the internal grade distribution over the past 24 hours by sliding the timeline, and intuitively view the dynamic evolution effect of all attributes. The system will overlay the standard deviation generated by interpolation onto the solid model in the form of a semi-transparent heat map. High variance areas indicate high uncertainty in geological inference, while low variance areas indicate high data confidence, helping geologists identify areas that need to be further explored. At the same time, the real-time location and status of excavators and trucks on site are mapped onto the three-dimensional scene in the form of dynamic icons, and spatially overlaid with the current geological model to achieve real-time synchronous display of the status of people, machines and environment; Step 6.2: The user inputs the production constraints for the day on the interactive terminal, including the target selection range for the selected grades. Upper limit of harmful elements Maximum ore extraction limits in each mining area and the processing capacity of the crushing station The system calls the mixed-integer linear programming solver in the background, takes the latest updated block model grade data as input, and executes the following algorithm to calculate the optimal ore blend combination: (1) To minimize the weighted sum of energy consumption and cost of transportation throughout the mine, the objective function is established as follows: in, For shovel loading point To the unloading point The transportation distance For assigning variables, The cost per unit of ore is the transportation cost. (2) Grade constraint: using the grade values ​​of the block model updated in step four. Ensure that the average grade of the mixed ore falls within the target range: Production capacity constraints: The ore output of each mining area must not exceed the minimum value of equipment capacity and remaining stockpile capacity. Total output balance: Ensure that the total output meets the throughput requirements of the crushing plant; (3) The algorithm traverses all currently exploitable ore blending units. If a sudden change in the measured grade of a certain area is detected, the system automatically adds the mining priority weight coefficient of that area to the objective function. The mining plan can be adjusted in real time; the solver generates the optimal solution matrix after convergence; (4) Transform the calculated optimal solution into specific ore blending instructions, including each shovel loading point. Recommended mining output The matching truck ID list and recommended driving routes are sent in real time to the excavator's onboard terminal and the dispatch center's large screen via the mining private network; Step 6.3: The system continuously monitors the real-time deviation between the model-predicted grade and the grade detected online at the crushing station; when the deviation exceeds the set threshold for three consecutive shifts, the system automatically pops up a prompt, suggesting that geologists check the data quality of the virtual sampling points; when the deviation exceeds the safety boundary or a potential risk of waste rock contamination is detected, the system automatically locks the ore discharge instructions of the relevant ore blending unit, forcibly suspends operations in that area, and notifies the dispatcher for manual verification; geological experts can manually delineate abnormal areas on the 3D interface, correct local lithological boundaries, or remove erroneous data points; After receiving a manual correction instruction, the system immediately triggers a re-interpolation process to recalculate the model attributes of the affected area and pushes the correction results back to the ore blending module, forming a closed-loop optimization through human-machine collaboration.

Citation Information

Patent Citations

  • Automatic updating method of ore body block model reserves

    CN104462649A

  • Accurate shovel loading system and method for open-pit mine

    CN111691888A