An anchor structure for installing a reactor foundation guide rail
The combined design of guide rails, transverse tie rods, traveling wheels and rail clamps solves the problem of inconvenient installation and maintenance of reactor foundations, and realizes controlled installation, accurate positioning and efficient maintenance, which is suitable for heavy-duty reactors.
Patent Information
- Application Number
- CN202611195963.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-07
- Publication Date
- 2026-11-24
AI Technical Summary
The existing reactor foundations have low alignment efficiency during installation and maintenance, and are inconvenient to install, especially for large equipment, where it is difficult to control the accuracy of hoisting and positioning, and it is difficult to adjust the position.
An anchoring structure for reactor foundation guide rail installation is adopted, which includes a combination design of guide rail, transverse tie rod, traveling wheel, rail clamp and lifting block to form an overall frame structure. Controlled installation and positioning are achieved through the cooperation of traveling wheel and guide rail. The guide rail is locked by rail clamp and anchor bolt is fixed to the top surface of foundation. Windproof cap and edge sealing structure are set to improve maintenance convenience.
It improves the convenience of reactor installation and maintenance, reduces the number of repeated hoisting and adjustment, improves installation efficiency and accuracy, ensures the stability and integrity of the guide rail, reduces the risk of wind and sand erosion, and facilitates later maintenance.
Smart Images

Figure CN123162005A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the technical field of reactor foundation structure, specifically relating to a reactor foundation guide rail installation and anchoring structure. Background Technology
[0002] Currently, the foundations for 500kV high-voltage shunt reactors in China typically use pre-embedded steel plates or conventional anchor bolts for equipment fixation. Equipment installation mainly relies on hoisting for direct placement, which presents inconveniences for installation and maintenance. This is especially true for large and heavy equipment such as three-phase integrated reactors (the overall length and width of which are both over 8 meters, and the weight exceeds 200 tons), where hoisting and placement accuracy is difficult to control, and adjusting and aligning the position after placement is very difficult and inefficient. Summary of the Invention
[0003] The technical problem to be solved by the present invention is to provide a guide rail installation and anchoring structure for reactor foundations, which solves the problems of low alignment efficiency, inconvenience of installation and maintenance when installing reactors in existing reactor foundations, so that the reactor can be installed in a controlled manner along the track, accurately aligned, locked on the track and finally positioned, improving the convenience of installation and subsequent maintenance, and is especially suitable for larger and heavier three-phase integrated reactors.
[0004] According to the technical solution of the present invention, the present invention provides a reactor foundation guide rail installation anchoring structure, including a reactor foundation and a reactor disposed above the reactor foundation; two parallel guide rails are disposed on the upper surface of the reactor foundation, and the two guide rails are connected by transverse tie rods, wherein multiple transverse tie rods are distributed along the length of the guide rails so that the guide rails and transverse tie rods form an integral frame structure; the bottom of the reactor is a reactor base, and two rows of running wheels are distributed on the bottom surface of the reactor base, the two rows of running wheels being correspondingly located at... Two guide rails are provided; at least two rail clamps are installed on each guide rail, the rail clamps are adjacent to the traveling wheels, and at least two rail clamps are located on both sides of the traveling wheels to limit the displacement of the reactor along the length of the guide rail; at least four lifting blocks are provided protruding around the lower part of the reactor, the line connecting the four lifting blocks is located directly below the center of mass of the reactor, and the orthographic projection of the bottom surface of the four lifting blocks on the reactor foundation is all within the range of the upper surface of the reactor foundation, so that a lifting device can be placed between the bottom surface of the lifting blocks and the upper surface of the reactor foundation.
[0005] In some implementations, a row of guide rail anchors is provided on both sides of each guide rail, wherein each guide rail anchor has its lower section embedded and fixed in the reactor foundation, and its upper section extends upward from the upper surface of the reactor foundation; a connecting plate is installed and fixed on the upper section of the guide rail anchor, and the connecting plate is connected to the guide rail.
[0006] In some implementations, a pad is provided between each guide rail and the reactor foundation. The lateral width of the pad covers the guide rail and the connecting plates on both sides of the guide rail. Both the pad and the connecting plates have through holes to allow the guide rail anchor bolts to pass through. The upper end of the guide rail anchor bolt has an external thread and is threaded with an anchor bolt nut to lock and fix the pad, the connecting plate and the reactor foundation.
[0007] In some implementations, a windproof cap is detachably provided at the upper end of the guide rail anchor bolt, and the exposed external thread of the guide rail anchor bolt and the anchor bolt nut are both located inside the windproof cap.
[0008] In some embodiments, the windproof cap is an integrated cover that is closed at the top and open at the bottom. The lower end of the windproof cap is installed and fixed to the outside of the anchor bolt nut by a snap-fit method, and the upper part of the windproof cap covers the exposed external thread of the upper end of the guide rail anchor bolt.
[0009] In some implementations, sealing structures are provided at the ends of the guide rails, the edges of the connecting plates, and the reactor base.
[0010] In some embodiments, both ends of the transverse tie rod have external threads, and a through hole is provided in the middle of the guide rail to allow the end of the transverse tie rod to pass through. The end of the transverse tie rod is threaded with a tie rod nut to lock and fix the transverse tie rod to the guide rail.
[0011] In some implementations, each row of running wheels consists of three wheels, for a total of six running wheels, which are symmetrically arranged relative to the bottom surface of the reactor base.
[0012] In some embodiments, the traveling wheel is a double-rimmed traveling wheel with an annular guide groove on the traveling wheel, and the top of the guide rail is located in the guide groove in a matching manner.
[0013] In some implementations, the reactor is a heavy-duty reactor with a total weight of 200 tons or more.
[0014] Compared with the prior art, the beneficial technical effects of the present invention are as follows: In the reactor foundation guide rail installation and anchoring structure of the present invention, a traveling wheel is provided at the bottom of the reactor, and a guide rail is provided on the top surface of the reactor foundation. Therefore, the reactor can be controlled and adjusted along the guide rail to enter the installation position, making installation and alignment more convenient, reducing the number of repeated hoisting and adjustment, and increasing efficiency. At the same time, multiple transverse tie rods are provided between the two guide rails, so that the two guide rails are no longer independent components, but form an integral track frame, which makes the track gauge more stable, straightness easier to control, and the integrity and installation accuracy of the guide rail better. Furthermore, after the reactor is in place, the guide rail is clamped by a rail clamp to achieve rail locking, and the guide rail is fixed to the top surface of the foundation by means of anchor bolts, for example. The installation system has a clear division of labor and a clear structural relationship, which is more suitable for the foundation installation of heavy wheeled equipment. In addition, more preferably, windproof caps are provided at the exposed parts of the anchor bolts, and sealing structures are provided at the ends of the guide rails and at local gaps, which effectively prevents wind and sand, and is more conducive to the later maintenance of exposed steel parts and local openings. Attached Figure Description
[0015] Figure 1 This is a top view of the reactor foundation of the present invention.
[0016] Figure 2 This is a schematic diagram of the main structure of the reactor of the present invention.
[0017] Figure 3 yes Figure 2 A bottom view of the reactor base, running wheels, and lifting block.
[0018] Figure 4 yes Figure 1 A cross-sectional structural diagram of the guide rail and guide rail anchor bolts.
[0019] Figure 5 yes Figure 1 A cross-sectional structural diagram of the guide rail and transverse tie rod.
[0020] Figure 6 This is a schematic diagram of the windproof hood portion in a preferred embodiment of the present invention.
[0021] Explanation of reference numerals in the attached figures: 1. Reactor foundation; 2. Reactor; 3. Guide rail; 4. Lateral tie rod; 5. Reactor base; 6. Running wheel; 7. Rail clamp; 8. Lifting block; 9. Guide rail anchor bolt; 10. Connecting plate; 11. Pad plate; 12. Windproof cap; 13. Guide groove. Detailed Implementation
[0022] This invention provides a guide rail installation and anchoring structure for reactor foundations, more specifically, a guide rail installation and anchoring structure suitable for three-phase integrated high-voltage parallel reactor foundations, typically for use in 500 kV step-up substations. Its main purpose is to solve the problems of low alignment efficiency, inconvenience in installation and maintenance of existing reactor foundations, enabling controlled installation, accurate alignment, rail locking, and final positioning of the reactor along the track, thus improving the convenience of installation and subsequent maintenance.
[0023] Please see Figures 1 to 5 The present invention provides a reactor foundation guide rail installation anchoring structure, including a reactor foundation 1 and a reactor 2 disposed above the reactor foundation 1; during installation, the reactor 2 is moved to a set position on the reactor foundation 1 and finally fixed.
[0024] Two parallel guide rails 3 are provided on the upper surface of the reactor foundation 1. The two guide rails 3 are connected by transverse tie rods 4. Multiple transverse tie rods 4 are distributed along the length of the guide rails 3 to form an integral frame structure. More specifically, the guide rails 3 and the transverse tie rods 4 are perpendicular to each other along their length. This frame structure of the guide rail assembly ensures that the guide rails 3 are straight and the spacing is stable, improving installation accuracy.
[0025] The bottom of the reactor 2 is the reactor base 5. Two rows of traveling wheels 6 are distributed on the bottom surface of the reactor base 5. The two rows of traveling wheels 6 are located on two guide rails 3 respectively, so that the reactor 2 can move along the guide rails 3 and is stably supported by the traveling wheels 6 and the guide rails 3. Through the cooperation of the traveling wheels 6 and the guide rails 3, the installation and alignment can be decomposed into two steps. The first step is to place the reactor 2 on the guide rails 3 (usually by hoisting, for which the reactor 2 has a hoisting component, which is the existing technology). The second step is to fine-tune the position of the reactor 2 (if necessary). This improves the installation efficiency and facilitates the adjustment of the position of the reactor 2.
[0026] At least two rail clamps 7 are installed on each guide rail 3, adjacent to the traveling wheel 6, with at least two rail clamps 7 located on both sides of the traveling wheel 6 to restrict the displacement of the reactor 2 along the length of the guide rail 3. More specifically, for example, rail clamps 7 are provided on both sides of each traveling wheel 6. The rail clamps 7 are existing technology or devices that can achieve the same function, capable of clamping and fixing to the guide rail 3, thus achieving the positioning and fixing effect of locking the traveling wheel 6 and preventing the reactor 2 from moving after the position of the reactor 2 is determined.
[0027] At least four lifting blocks 8 are protruding around the lower part of the reactor 2. The line connecting the four lifting blocks 8 is located directly below the center of mass of the reactor 2, and the orthographic projection of the bottom surface of the four lifting blocks 8 onto the reactor foundation 1 is all within the range of the upper surface of the reactor foundation 1, so that a lifting device (such as a hydraulic jack) can be placed between the bottom surface of the lifting blocks 8 and the upper surface of the reactor foundation 1. More specifically, the bottom surface of the lifting blocks 8 is parallel to the upper surface of the reactor foundation 1, for example, both are horizontal. The lifting blocks 8 and the lifting device are used for auxiliary adjustment, that is, when necessary, the reactor 2 can be slightly lifted to facilitate hoisting and movement or to clear debris between the traveling wheels 6 and the guide rail 3. When not adjusting or undergoing maintenance, the lifting device is removed (the lifting device is only used as a tool).
[0028] Please see Figure 1 , Figure 4 More specifically, each guide rail 3 has a row of guide rail anchors 9 on both sides. Each guide rail anchor 9 has its lower section embedded and fixed within the reactor foundation 1, and its upper section extending upwards from the upper surface of the reactor foundation 1. A connecting plate 10 is installed and fixed to the upper section of the guide rail anchor 9, and the connecting plate 10 is connected to the guide rail 3. Specifically, as... Figure 4 In the illustrated embodiment, the guide rail 3 is an existing steel rail (the guide rail 3 has a rail head, a rail web, and a rail bottom; more specifically, the guide rail 3 is, for example, a P50 guide rail). The connecting plate 10 also has a welded or integrally formed pressure plate portion on the side facing the guide rail 3. The pressure plate portion presses against the bottom of the guide rail 3, or in other words, the pressure plate portion forms a matching groove to accommodate the bottom of the rail, thereby fixing the guide rail 3 by the pressing action of the pressure plate portion. In other feasible embodiments, the connecting plate 10 and the guide rail 3 are welded or integrally formed.
[0029] Furthermore, a pad 11 is provided between each guide rail 3 and the reactor foundation 1. The lateral width of the pad 11 covers the guide rail 3 and the connecting plates 10 on both sides of the guide rail 3. Both the pad 11 and the connecting plates 10 have through holes to allow the guide rail anchor bolts 9 to pass through. The upper end of the guide rail anchor bolt 9 has external threads and is threaded with an anchor bolt nut (and a washer) to lock and fix the pad 11, the connecting plates 10 and the reactor foundation 1. The pad 11 provides a larger contact area, reducing the pressure on the reactor foundation 1, and is more suitable for heavy-duty reactor equipment. At the same time, this solution fixes the guide rail assembly, the pad 11, the connecting plates 10 and the guide rail anchor bolts 9 into a whole, ensuring the integrity and stability of the guide rail assembly and the reactor foundation 1.
[0030] Please see Figure 6Preferably, the present invention also supplements key exposed and gap locations with simple windproof and sandproof structures, including detachable windproof caps 12. A windproof cap 12 is detachably installed on the upper end of the guide rail anchor bolt 9, with the exposed external threads of the guide rail anchor bolt 9 and the anchor bolt nut located inside the windproof cap 12. More specifically, the windproof cap 12 is an integrated cover with a closed top and an open bottom. The lower end of the windproof cap 12 is installed and fixed to the outside of the anchor bolt nut via a snap-fit mechanism (the size of the opening of the windproof cap 12 matches the outer surface of the anchor bolt nut, thus ensuring a stable fit and locking onto the nut). The upper part of the windproof cap 12 covers the exposed external threads of the guide rail anchor bolt 9. The windproof cap 12 reduces the entry of wind and sand into the exposed threads of the anchor bolt and the area of the anchor bolt nut, reducing the risk of sand accumulation, corrosion, and jamming, and facilitating subsequent disassembly and maintenance.
[0031] Furthermore, the windproof and sandproof structure also includes edge sealing structures at the ends of the guide rail 3, the edges of the connecting plate 10, and the reactor foundation 1. The edge sealing structure is existing technology, but it is not used as a means of windproofing the reactor. The edge sealing structure is mainly set at local gaps, which also serves to reduce the entry of wind and sand, reduce the risk of sand accumulation and jamming, and facilitate later cleaning, disassembly, and maintenance.
[0032] Given the low-temperature and corrosive environment of the project site, the foundation design principles require that the equipment foundation be equipped with anchor bolts, and that bolts, nuts, washers, and steel components be hot-dip galvanized for corrosion protection; the corrosion level of the foundation soil should be determined based on geotechnical data (e.g., considering XA2). These conditions dictate that this installation system, in addition to meeting the equipment installation requirements, should also consider the sand protection and durability requirements for exposed steel components and localized gaps.
[0033] Please see Figure 5 In a specific embodiment, both ends of the transverse tie rod 4 have external threads. The transverse tie rod 4 is, for example, round steel. The middle part (rail web) of the guide rail 3 has a through hole so that the end of the transverse tie rod 4 can pass through. The end of the transverse tie rod 4 is threaded with a tie rod nut (and a washer) to lock the transverse tie rod 4 and the guide rail 3 together, and at the same time maintain the track gauge. Figure 5 In the illustrated embodiment, tie rod nuts are provided only on the outer side of the web of the two guide rails 3, thus limiting the distance between the two guide rails 3 by tension. In other feasible embodiments, tie rod nuts are also provided on the inner side of the web of the two guide rails 3.
[0034] Please see Figure 3 Preferably, each row of traveling wheels 6 consists of three wheels, for a total of six traveling wheels 6, symmetrically arranged relative to the bottom surface of the reactor base 5. It should be noted that the symmetry of the six traveling wheels 6 relative to the reactor base 5 evenly distributes the load, ensuring a stable fit between the reactor base 5 and the guide rail 3; while the lifting blocks 8 are located on the front and rear sides of the reactor 2 (…). Figure 3(The middle section consists of the upper and lower sides). During the lifting process, the overall center of gravity of the reactor 2 must be considered to ensure stable lifting. Therefore, the lifting block 8 is not necessarily symmetrical with respect to the reactor base 5. Figure 3 (The middle part is asymmetrical).
[0035] Please see Figure 3 Preferably, the traveling wheel 6 is a double-rimmed traveling wheel with an I-shaped cross-section. The traveling wheel 6 has an annular guide groove 13 (a guide groove that mates with the head of the guide rail is formed between the two rims). The top of the guide rail 3 (the head of the rail) is located in the guide groove 13, thereby forming a limiting effect. In the mating state, the traveling wheel 6 is restricted to moving along the length of the guide rail 3, but cannot move in a direction perpendicular to the length of the guide rail 3 (the traveling wheel 6 can also move in the vertical direction during hoisting or jacking adjustment).
[0036] As a supplementary explanation, reactor 2 is a heavy-duty reactor with a total weight of over 200 tons (heavy-duty three-phase integrated high-voltage parallel reactor, more specifically 233 tons). The present invention is particularly suitable for such heavy and large equipment, can meet the corresponding load requirements, and is easy to install and maintain.
[0037] The following is a further explanation using a specific embodiment. A three-phase integrated high-voltage reactor device is used in the AIS area of the 500kV side of a certain project's 500kV substation. This device weighs approximately 233t, has six traveling wheels at the bottom, and four 50T jacking work positions (jacking blocks). The device's planar dimensions are approximately 7690mm × 2800mm. Due to its large weight, the installation process requires high precision in placement, alignment, and positioning. Guide rails are installed on the top surface of the reactor foundation (main foundation), with a row of pre-embedded anchor bolts on each side of the guide rails to secure them. The guide rails consist of two P50 guide rails, with six transverse tie rods between them. This solution differs from conventional high-resistance foundations that directly use embedded parts or simple anchor bolts to fix the equipment. Instead, it forms a track installation system that is compatible with wheeled heavy equipment to facilitate installation and maintenance. This allows the reactor equipment to be guided, aligned, and accurately positioned along the track and locked on the track. At the same time, simple wind and sand protection structures are preferably set at the exposed anchor bolt locations and local gaps to improve the convenience of later maintenance.
[0038] One basic working principle of this scheme is as follows: First, the reactor is hoisted to its foundation, ensuring accurate positioning, with particular emphasis on aligning the running wheels with the guide rails. After the reactor is lowered onto the guide rails, the coordinated running wheels and guide rail assemblies allow for controlled placement and alignment along the track. A transverse tie rod is installed between the two guide rails, forming an integral track frame to ensure track gauge, straightness, and overall stability. Once the reactor is in place, rail clamps are installed near the running wheels (or pre-installed as accessories on both sides of the running wheels) to clamp the rail head or web of the guide rails, locking the reactor relative to the guide rails. The guide rails are then fixed to the top surface of the foundation using anchor bolts, thus forming a connection and positioning relationship between the reactor, rail clamps, guide rails, and reactor foundation, creating an installation and anchoring system of "guide rail placement and alignment, rail clamp locking on the rails, and foundation anchor bolt fixing of the guide rails." This structural design reduces the workload of repeatedly lifting heavy equipment and repeatedly drilling holes, thus improving installation efficiency.
[0039] As a supplementary explanation, for heavy equipment, the guide rails serve as auxiliary limiting and guiding mechanisms during installation, positioning, and fine-tuning. The lifting device can be used in conjunction with a crane to facilitate hoisting. When the crane moves the reactor, the reactor's bottom running wheels engage with the guide rails. After the running wheels are on the rails and bear the load, even if the crane's running path slightly deviates from the length direction of the guide rails, the reactor will always move along the guide rails. Besides the installation process, the guide rails also provide greater convenience for subsequent maintenance. For example, the reactor can be moved horizontally to expose the bottom or side space for maintenance work. When restoring the reactor to its original position, adjustment only needs to be made in one direction (i.e., the length direction of the guide rails), thus significantly improving maintenance efficiency.
[0040] In summary, the reactor foundation guide rail installation and anchoring structure of the present invention features running wheels at the bottom of the reactor and guide rails on the top surface of the reactor foundation. This allows for controlled adjustment along the guide rails to position the reactor in the installation location, making installation and alignment easier, reducing the number of repeated hoisting adjustments, and increasing efficiency. Simultaneously, multiple transverse tie rods are installed between the two guide rails, transforming them from independent components into an integral track frame. This results in more stable track gauge, easier straightness control, and better overall integrity and installation accuracy of the guide rails. Furthermore, after the reactor is in place, the guide rails are clamped by rail clamps to achieve on-rail locking. The guide rails are fixed to the top surface of the foundation using, for example, anchor bolts. The installation system has a clear division of labor and structural relationship, making it more suitable for the foundation installation of heavy-duty wheeled equipment. More preferably, windproof caps are installed at the exposed anchor bolt locations, and sealing structures are provided at the ends of the guide rails and at local gaps, effectively preventing wind and sand damage and facilitating later maintenance of exposed steel components and local openings.
[0041] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, and not to limit them; obviously, the described embodiments are some embodiments of the present invention, but not all embodiments; based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention; in the absence of conflict, the embodiments and features in the embodiments of the present invention can be combined with each other; modifications to the technical solutions described in the foregoing embodiments, or equivalent substitutions for some of the technical features, do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A reactor foundation guide rail mounting anchor structure, characterized by, Includes a reactor foundation (1) and a reactor (2) disposed on the reactor foundation (1); Two parallel guide rails (3) are provided on the upper surface of the reactor foundation (1). The two guide rails (3) are connected by a transverse tie rod (4). The transverse tie rod (4) consists of multiple rods distributed along the length of the guide rails (3) so that the guide rails (3) and the transverse tie rods (4) form an integral frame structure. The bottom of the reactor (2) is the reactor base (5), and two rows of running wheels (6) are distributed on the bottom surface of the reactor base (5). The two rows of running wheels (6) are located on two guide rails (3) respectively. At least two rail clamps (7) are installed on each guide rail (3). The rail clamps (7) are adjacent to the running wheel (6), and at least two rail clamps (7) are located on both sides of the running wheel (6) to limit the displacement of the reactor (2) along the length of the guide rail (3). At least four lifting blocks (8) are provided protruding around the lower part of the reactor (2). The line connecting the four lifting blocks (8) is located directly below the center of mass of the reactor (2), and the orthographic projection of the bottom surface of the four lifting blocks (8) on the reactor base (1) is located within the range of the upper surface of the reactor base (1), so that a lifting device can be placed between the bottom surface of the lifting blocks (8) and the upper surface of the reactor base (1).
2. The reactance base guide rail mounting anchor structure of claim 1, wherein, Each guide rail (3) has a row of guide rail anchors (9) on both sides. Each guide rail anchor (9) has its lower section embedded and fixed in the reactor foundation (1) and its upper section extending upward from the upper surface of the reactor foundation (1). A connecting plate (10) is installed and fixed on the upper section of the guide rail anchor (9), and the connecting plate (10) is connected to the guide rail (3).
3. The reactance base guide rail mounting anchor structure of claim 2, wherein, A pad (11) is provided between each guide rail (3) and the reactor foundation (1). The lateral width of the pad (11) covers the guide rail (3) and the connecting plates (10) on both sides of the guide rail (3). The pad (11) and the connecting plate (10) have through holes so that the guide rail anchor bolts (9) can pass through. The upper end of the guide rail anchor bolt (9) has external threads and is threaded with anchor bolt nuts to lock and fix the pad (11), the connecting plate (10) and the reactor foundation (1).
4. The reactance base guide rail mounting anchor structure of claim 3, wherein, A windproof cap (12) is detachably provided at the upper end of the guide rail anchor (9), and the exposed external thread and anchor nut at the upper end of the guide rail anchor (9) are located inside the windproof cap (12).
5. The reactance base guide rail mounting anchor structure of claim 4, wherein, The windproof cap (12) is an integrated cover with a closed top and an open bottom. The lower end of the windproof cap (12) is installed and fixed to the outside of the anchor bolt nut by a snap-fit method. The upper part of the windproof cap (12) covers the exposed external thread of the upper end of the guide rail anchor bolt (9).
6. The reactance base guide rail mounting anchor structure of claim 2, wherein, Sealing structures are provided at the ends of the guide rail (3), the edges of the connecting plate (10), and the reactor foundation (1).
7. The reactor foundation guide rail mounting anchor structure of any one of claims 1 to 6, wherein, Both ends of the transverse tie rod (4) have external threads. The guide rail (3) has a through hole in the middle so that the end of the transverse tie rod (4) can pass through. The end of the transverse tie rod (4) is threaded with a tie rod nut to lock the transverse tie rod (4) and the guide rail (3) together.
8. The reactance base guide rail mounting anchor structure of any one of claims 1 to 6, wherein, Each row of running wheels (6) consists of three wheels, for a total of six running wheels (6) which are symmetrically arranged relative to the bottom surface of the reactor base (5).
9. The reactance base guide rail mounting anchor structure of any one of claims 1 to 6, wherein, The running wheel (6) is a double-rimmed running wheel with an annular guide groove (13) on the running wheel (6), and the top of the guide rail (3) is located in the guide groove (13) in a matching manner.
10. The reactor foundation guide rail mounting anchor structure of any one of claims 1 to 6, wherein, The reactor (2) is a heavy-duty reactor with a total weight of more than 200 tons.