A transformer area line loss positioning method based on electric energy metering box data acquisition

By performing time-stamp alignment and power difference recalculation on the node-level data in low-voltage distribution areas, combined with micro-feature fingerprinting and physical verification, the problems of line loss location offset and unclear responsibility attribution were solved, achieving more accurate line loss location and trend identification.

CN123162804APending Publication Date: 2026-11-24ANHUI MINGDU QUNQIAO ELECTRIC POWER EQUIP
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202611118268.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-07-27
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

In low-voltage distribution areas, the different data sources of the main meter node, branch nodes, incoming line nodes of the electricity metering box, and household meter nodes lead to problems such as time stamp misalignment, communication delay, and data disorder, resulting in line loss location deviation and unclear responsibility attribution. In particular, the slow deterioration trend within the acceptable range of the comprehensive line loss rate is difficult to identify.

Method used

By acquiring node-level data of the transformer area, time-scale alignment is performed based on the micro-feature fingerprints of the reference node curve and the downstream node curve, the section power difference is recalculated, and by combining transient changes in electrical quantities and physical rationality verification, pseudo-loss and real loss are distinguished, multiple types of cause evidence are compared, and responsibility components and attribution credibility are output.

Benefits of technology

It reduces interference in line loss calculation, improves the accuracy of line loss location and the credibility of responsibility attribution, can identify slow deterioration trends within the acceptable range of comprehensive line loss rate in advance, and enhances the verifiability of location results and the continuity of anomaly handling.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123162804A_ABST
    Figure CN123162804A_ABST
Patent Text Reader

Abstract

This invention relates to the field of electrical variable measurement and transformer area line loss monitoring technology, and discloses a method for locating transformer area line losses based on data collected from electricity metering boxes. The method first acquires node-level data for the main meter node, branch nodes, electricity metering box incoming nodes, and household meter nodes in the transformer area, and forms a node-level cache according to node roles and upstream / downstream connections. It then performs time-stamp alignment of the node-level data based on micro-feature fingerprints, recalculates the segment power difference of each link segment according to the synchronous time grid, and distinguishes between pseudo-loss components and actual loss components by combining time-stamp offset, transient change amplitude of electrical quantities, and physical rationality verification results. Finally, it performs multi-type cause evidence comparison on the actual loss components, outputting link segment location results and responsibility labels, thereby reducing the interference of time-stamp misalignment on line loss calculation and improving the accuracy of transformer area line loss location and responsibility attribution.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of electrical variable measurement and transformer area line loss monitoring technology, specifically a method for locating transformer area line losses based on data collected from electricity metering boxes. Background Technology

[0002] Low-voltage distribution transformer area line loss management typically requires analyzing the loss situation at different levels within the transformer area based on electricity data collected from various sources, including the main meter, branch nodes, electricity metering boxes, and individual meters. Existing technologies include, for example, the authorized Chinese invention patent application CN117851908B, which discloses an improved online low-voltage transformer area electricity meter malfunction monitoring method and device. This method primarily monitors electricity meter malfunctions through transformer area identification, user data preprocessing, and the application of energy conservation equations. Another example is the authorized Chinese invention patent application CN106992517B, which discloses a power line loss analysis method, device, and system. This method primarily acquires power data sets of the target area through a data acquisition terminal and calculates theoretical and actual line losses using a power network model to generate a line loss analysis report. These solutions can, to a certain extent, identify abnormal line losses, meter malfunctions, or high-loss areas within transformer areas. However, in actual low-voltage distribution areas, the main meter node, branch nodes, incoming nodes of the electricity metering box, and household meter nodes typically transmit data via different acquisition devices, communication links, or business systems. These nodes are prone to issues such as local clock drift, inconsistent freeze times, different transmission cycles, communication delays, and data out-of-order processing. If the upstream and downstream electricity amounts are directly subtracted based on the original timestamps of each node, the inaccurate electricity difference caused by timestamp misalignment can easily be compounded by actual losses due to line heat loss, metering errors, mismatched records, reverse power flow from distributed photovoltaic systems, abnormal contact, and pending electricity theft verification. This leads to misalignment in the location of line losses between branch sections, metering box sections, and meter sections. The shift in timing can lead to unclear attribution of responsibility. Furthermore, when the overall line loss rate of a distribution area is still within the acceptable management range, the deterioration of losses caused by the slow increase in contact resistance, the gradual drift of metering errors, or the long-term slight anomalies in local branches usually does not easily trigger conventional threshold alarms, resulting in a lag in anomaly detection. Therefore, there is an urgent need for a distribution area line loss location method that can combine data collected by the power metering box and its upstream and downstream nodes to perform time-scale alignment of multi-node data, recalculation of section power consumption, differentiation between pseudo-loss and actual loss, and hierarchical link location. This would reduce the interference of time-scale misalignment on line loss calculation, improve the accuracy of distribution area line loss location and responsibility attribution, and enable early identification of slow deterioration trends within the acceptable range. Summary of the Invention

[0003] To address the shortcomings of existing technologies, this invention provides a method for locating line losses in transformer substations based on data collected from electricity metering boxes, thus solving the problems mentioned in the background section.

[0004] To achieve the above objectives, the present invention provides the following technical solution: A method for locating line losses in power distribution areas based on data collected from electricity metering boxes includes: Obtain node-level data for the main meter node, branch nodes, incoming nodes of electricity metering boxes, and household meter nodes in the distribution area, and form a node-level cache according to node roles and upstream and downstream connection relationships; Time-scale alignment is performed based on the micro-feature fingerprints of the reference node curve and the downstream node curve to obtain the time-scale offset and the aligned time series; The aligned time series is resampled according to the synchronous time grid, and the segment power difference of the branch segment, meter box segment and meter segment is recalculated according to the upstream and downstream connection relationship; The pseudo-loss component and the real loss component are determined based on the power difference of the section, the time offset, the transient change amplitude of the electrical quantity, and the physical rationality verification results. The actual loss component is compared with multiple types of causal evidence to obtain the responsibility component and attribution credibility. The link segment location results are output based on the responsibility component and attribution credibility, and written into the responsibility label.

[0005] In one possible implementation, the node-level data includes node identifier, node role, acquisition time or local clock stamp, uploaded batch number, power data, and electrical quantity data; the data collected by the power metering box is generated by the integrated metering unit on the incoming side of the power metering box, the box status acquisition unit, the box communication unit, or the household meter group corresponding to the power metering box, and includes one or more of the following: incoming three-phase voltage, three-phase current, phase angle, power factor, neutral current, active power, reactive power, reverse active power, open cover status, tilt status, temperature, humidity, communication status, power outage and restoration events, time difference alarm, and uploaded batch number.

[0006] In one possible implementation, the time-scale alignment based on the micro-feature fingerprint of the reference node curve and the downstream node curve includes: using the substation master table node or the upstream branch node as the reference node, extracting micro-feature segments representing the same electrical disturbance from the reference node curve; comparing the micro-feature segments with candidate segments in the downstream node curve; if the candidate segments meet the similarity threshold, the direction consistency threshold, and the time range threshold, determining the candidate segments as the physical disturbance segments corresponding to the micro-feature segments; and determining the time-scale offset of the downstream node relative to the reference node based on the time difference between the micro-feature segments and the physical disturbance segments.

[0007] In another possible implementation, when multiple micro-feature fragments exist within the same time-scale alignment window, multiple candidate time-scale offsets are determined, and the final time-scale offset is selected by combining the historical offset range, the number of corresponding fragments, and the physical orientation consistency. If no micro-feature fragments satisfying the similarity threshold, orientation consistency threshold, and time range threshold are found, a temporary time-scale offset is determined based on the uploaded batch number, the receiving time, the node's local clock stamp, and the most recent valid offset, and the corresponding node is marked as a low-confidence alignment node.

[0008] In one possible implementation, the resampling of the aligned time series according to the synchronous time grid includes: resampling the active power curve, reactive power curve, and reverse active power curve after time-scale alignment, so that the power values ​​of each node correspond to the same grid boundary; for the cumulative power field, determining the power increment within the grid based on the difference between the cumulative values ​​at the grid start point and the grid end point; for the power curve, calculating the power based on the sampling points and sampling intervals within the grid; and for the reverse active power, retaining the direction indicators of the forward and reverse power.

[0009] In one possible implementation, the recalculation of the segment power difference of the branch segment, metering box segment, and metering segment according to the upstream and downstream connection relationship includes: determining the segment power difference of the branch segment based on the difference between the branch outlet power corresponding to the main meter node of the transformer area and the downstream total power of the branch node; determining the segment power difference of the metering box segment based on the difference between the feed-out power corresponding to the branch node and the power of the incoming node of the power metering box; and determining the segment power difference of the metering segment based on the difference between the power of the incoming node of the power metering box and the total power of the household meter nodes within the power metering box.

[0010] In one possible implementation, determining the pseudo-loss component and the real loss component includes: when the voltage, current, phase angle, and neutral current within the current synchronization time grid are in a stable range and the time scale offset is below the offset threshold, determining the portion of the segment power difference that meets the physical rationality verification as the real loss component; when there are rapid fluctuations within the current synchronization time grid and the time scale offset exceeds the offset threshold, determining the pseudo-loss component based on the offset direction, offset duration, curve change direction, and transient change amplitude of electrical quantities, and determining the segment power difference after deducting the pseudo-loss component as the real loss component to be verified; the physical rationality verification includes energy direction verification, historical load condition verification, and link upstream and downstream consistency verification.

[0011] In one possible implementation, the comparison of evidence for multiple causes of the actual loss component includes: comparing the actual loss component, node state quantities, archive data, event records, and physical rationality verification results based on evidence conditions for line-related, metering error-related, file mismatch-related, photovoltaic-related, electricity theft pending verification, and contact anomaly-related types, respectively; the evidence condition table corresponding to each type of cause includes a trigger field, anomaly amplitude threshold, duration threshold, associated time window, applicable link segment, applicable operating condition, exclusion conditions, and output label; when the credibility of evidence for any cause category reaches the corresponding threshold, the cause category is determined as a candidate for responsibility label.

[0012] In another possible implementation, if the credibility of evidence for multiple cause categories reaches the corresponding threshold, the primary responsibility category and the secondary responsibility category are output; if the credibility of evidence for all cause categories does not reach the corresponding threshold, an unknown cause label or a label pending verification is output; among them, the meter section refers to metering error type, file mismatch type, and electricity theft pending verification type evidence; the meter box section refers to contact abnormality type, neutral wire abnormality, and box internal temperature and humidity evidence; and the branch section refers to line type and photovoltaic type evidence.

[0013] In one possible implementation, the output link segment location result and its writing to a responsibility tag include: summarizing the actual loss components of branch segments, metering box segments, and metering segments according to the evaluation cycle, as well as the responsibility components of each cause; determining the anomaly concentration judgment conditions based on the link segment actual loss component ranking, responsibility component proportion, historical normal range, and comparison results with adjacent link segments; if a branch segment meets the anomaly concentration judgment conditions, locating to the corresponding branch node and its downstream range; if a metering box segment within a corresponding branch meets the anomaly concentration judgment conditions, locating to the corresponding electricity metering box incoming node and its internal meter group; if a metering segment within a corresponding electricity metering box meets the anomaly concentration judgment conditions, locating to the corresponding meter node or meter group.

[0014] Optionally, the method further includes: forming actual loss curves for branch segments, metering box segments, and metering segments based on actual loss components within multiple assessment periods; when the overall line loss rate is within the management acceptable range, selecting a sliding observation window to align the actual loss curves with the load cycle, seasonal cycle, and historical similar cycles; determining a trend warning threshold based on the management acceptable range, historical load loss fluctuation bands, and the number of consecutive increases within the observation window; outputting a degradation warning level when the actual loss curve meets the trend warning threshold; and for link segments with low-confidence alignment, missing fill ratios exceeding the corresponding thresholds, or physical rationality verification failures, including the link segment in a pending review state or extending the observation state.

[0015] Optionally, the method further includes: in the case of missing data, performing supplementary collection, temporary filling, link segment masking, or extending the evaluation period; in the case of abnormal timescale offset, performing coarse alignment, using the most recent valid offset, reselecting the reference node, or triggering terminal time synchronization verification; in the case of physical rationality verification failure, removing abnormal grids, retaining the original curves, and outputting labels to be verified; in the case of attribution credibility being lower than the corresponding threshold, extending the observation window, outputting unknown cause labels, or transferring to manual confirmation; and updating the credibility of responsibility labels in subsequent evaluation periods based on at least one of the following write-back information: governance work orders, file corrections, on-site verification results, parameter updates, and label self-verification.

[0016] Compared with existing technologies, the present invention provides a method for locating line losses in power distribution areas based on data collected from power metering boxes, which has the following advantages: 1. This invention acquires node-level data from the main meter node, branch nodes, incoming nodes of the electricity metering box, and household meter nodes in a distribution area, and forms a node-level cache according to node roles and upstream and downstream connections, enabling node data from different sources to be processed under the same distribution area link relationship; it performs time-scale alignment based on the micro-feature fingerprints of the reference node curve and the downstream node curve, and recalculates the segment power difference of the branch segment, metering box segment, and meter segment according to the synchronous time grid, enabling upstream and downstream power data to be compared under a unified time reference; by combining the segment power difference, time-scale offset, transient change amplitude of electrical quantity, and physical rationality verification results to distinguish between pseudo-loss components and real loss components, and comparing real loss components with multiple types of causal evidence, it can reduce the interference of inconsistent acquisition times of multiple nodes, different transmission cycles, communication delays, and data disorder on line loss calculation, reduce the situation of unclear line loss location offset and responsibility attribution between branch segments, metering box segments, and meter segments, and help to identify the slow deterioration trend when the comprehensive line loss rate is within the management qualified range in advance.

[0017] 2. This invention, by performing supplementary data collection, coarse alignment, link segment shielding, extending the assessment period, and outputting labels pending verification or transferring to manual confirmation in cases of missing data, abnormal timescale offsets, failed physical rationality verification, or attribution credibility below the corresponding threshold, and updating the credibility of responsibility labels in subsequent assessment periods based on governance work orders, file corrections, on-site verification results, parameter updates, and write-back information in label self-verification, can avoid directly outputting definitive location conclusions when data quality is insufficient, timescale relationships are abnormal, or evidence support is insufficient, thereby improving the verifiability of transformer area line loss location results, the continuity of the anomaly handling process, and the accuracy of responsibility label updates. Attached Figure Description

[0018] Figure 1 This is a schematic diagram of the transformer area line loss location system architecture of the present invention; Figure 2 This is a flowchart of the transformer area line loss location method of the present invention; Figure 3 This is a schematic diagram of multi-node timescale alignment according to the present invention; Figure 4 This is a schematic diagram of the decomposition of the segmental power difference and pseudo-real loss in this invention; Figure 5 This is a schematic diagram illustrating the comparison of evidence from multiple causes in this invention; Figure 6 This is a schematic diagram illustrating the trend observation of the present invention; Figure 7 This is a diagram showing the state transition between abnormal degradation and closed-loop write-back in this invention. Figure 8 This is a schematic diagram of the process for a method to locate line loss in a transformer area based on data collected from an energy metering box, according to the present invention.

[0019] The system includes: 101. Main meter node for the distribution area; 102. Branch node; 103. Incoming line node for electricity metering box; 104. Household meter node; 105. Main execution entity; 106. Master station system; 110. Data access module; 120. Micro-feature alignment module; 130. Section electricity recalculation module; 140. Loss decomposition module; 150. Evidence attribution module; 160. Hierarchical positioning module; 170. Trend observation module; 180. Anomaly closed-loop module; 201. Reference curve; 202. Downstream curve; 203. Micro-feature fragment; 204. Timescale offset; 301, Segment power difference; 302, False loss component judgment path; 303, Actual loss component judgment path; 304, Physical verification; 401, Line type; 402, Metering error type; 403, File mismatch type; 404, Photovoltaic type; 405, Electricity theft pending verification type; 406, Contact abnormality type; 501, Actual loss curve; 502, Qualified interval; 503, Observation window; 504, Warning level; 601, Normal processing; 602, Low confidence; 603, Pending verification; 604, Manual takeover; 605, Closed loop completion. Detailed Implementation

[0020] The embodiments of this application are described below with reference to the accompanying drawings. The described embodiments are intended to enable those skilled in the art to understand and implement the technical solutions of this application, and are not intended to limit the scope of protection of this application. Unless otherwise specified, the data sources, processing steps, judgment conditions, exception handling methods, and feedback update methods in the embodiments of this application can be combined with each other. The same or similar reference numerals in the accompanying drawings represent the same or similar technical objects, and the method step numbers are only for ease of description and should not be construed as limiting a unique execution order between steps.

[0021] Figure 1 - Figure 8A flowchart illustrating a method for locating line losses in power distribution areas based on data collected from electricity metering boxes is provided, including: In the process of managing line losses in low-voltage distribution transformer areas, conventional methods typically calculate the comprehensive line loss rate based on the frozen electricity of the transformer area's main meter and individual meters, or compare the difference between the actual and theoretical line losses with a preset threshold, and then output suspected abnormal causes based on a preset cause database. This type of method can play a certain role when the overall loss of the transformer area is high, a single meter is obviously inaccurate, or the file relationship is obviously incorrect. However, in actual low-voltage transformer areas, the main meter node, branch nodes, electricity meter box incoming nodes, and individual meter nodes often receive data from different acquisition devices, different communication links, or different business systems. Each node may have local clock drift, differences in freezing time, different uploading cycles, communication delays, and data out of order. Especially under conditions of rapid load fluctuations, daytime reverse power flow of distributed photovoltaic systems, user start-up and shutdown of high-power equipment, changes in contact status within the meter box, or lag in the household transformer relationship file, if the upstream and downstream electricity is directly subtracted based on the original timestamp of the node, it is easy to mistake the electricity difference caused by the time stamp misalignment as the actual line loss, causing the line loss positioning between branch sections, meter box sections, and meter sections to be offset. Meanwhile, factors contributing to losses, such as line heat loss, metering errors, mismatched records, reverse power flow from distributed photovoltaic systems, pending electricity theft investigations, and abnormal contact, may coexist. If these factors are investigated sequentially in a fixed order, the judgment of a previous cause can easily influence the judgment of a subsequent cause, leading to unclear attribution of responsibility. Furthermore, when the overall line loss rate remains within the acceptable management range, slow increases in contact resistance, gradual drift in metering errors, or long-term minor anomalies in local branches causing loss degradation are usually unlikely to trigger conventional threshold alarms, easily resulting in delayed anomaly detection. Based on the above problems, this application aims to... The physical time correspondence between multiple nodes is determined based on electrical quantities, status quantities, archive data, and time-stamped auxiliary quantities of the power metering box and its upstream and downstream nodes. Among them, the time-stamped auxiliary quantities include at least the node local clock stamp, freeze time, upload batch number, and reception time. By distinguishing between pseudo loss components introduced by time-stamp misalignment and real loss components formed by actual operational anomalies, and outputting verifiable loss location results, responsibility labels, and slow degradation early warning results on the branch section, metering box section, and meter section, the risks of line loss location deviation, responsibility attribution confusion, and abnormal delayed reporting can be reduced.

[0022] The processing mechanism of this application is as follows: the main executing entity receives electrical quantities, status quantities, archive data, and time-stamped auxiliary quantities generated by the main meter node, branch nodes, electricity metering box incoming nodes, and household meter nodes according to their node roles, and binds each node's data with node identifiers, node roles, transmission batches, and upstream and downstream connection relationships. Based on this, the main executing entity uses the main meter node or an upstream stable node as a reference node to extract micro-feature segments that can characterize the same electrical disturbance from curves such as voltage waveforms, current waveforms, phase angles, and neutral currents, and determines the time correspondence between the downstream node curve and the reference node curve based on these micro-feature segments. After completing time-stamp alignment, the main executing entity resamples the electricity curves within a unified synchronous time grid to obtain the segment electricity of the branch section, metering box section, and meter section, respectively. The difference is further analyzed by combining the node timescale offset, the transient change amplitude of electrical quantities, and the physical rationality verification results. The power difference in the section is divided into a pseudo-loss component introduced by the misalignment of the data collection timescale and a real loss component formed by actual operational anomalies. For the real loss component, the main executing entity compares the evidence conditions according to different physical causes to obtain the responsibility component, the primary responsibility category, the secondary responsibility category, and the attribution credibility of each link segment. The loss location results, responsibility labels, slow degradation warnings, and anomaly handling records are written back to the main station system or governance system. By reviewing the changes in responsibility components in subsequent evaluation cycles, the label credibility, timescale parameters, judgment conditions, or review status can be updated. This allows the line loss location to be determined from the overall line loss rate of the transformer area to the hierarchical location of branch segments, metering box segments, and meter segments, providing traceable data for subsequent governance.

[0023] The data collected by the electricity metering box in this application can be generated by the integrated metering unit on the incoming side of the electricity metering box, the box status acquisition unit, the box communication unit, or the household meter group corresponding to the electricity metering box; the data collected by the electricity metering box can include at least one or more of the following fields: incoming three-phase voltage, three-phase current, phase angle, power factor, neutral current, active power, reactive power, reverse active power, open cover status, tilt status, temperature, humidity, communication status, power outage and restoration events, time difference alarm, and uploaded batch number; the above fields can be selected and enabled according to the actual configuration of the on-site metering equipment and acquisition terminal; when the corresponding acquisition item is not configured on-site, the corresponding judgment condition can be disabled, or the corresponding abnormal type can be used as a manual verification item; the main meter node of the distribution area can be the low-voltage side outgoing line of the distribution transformer or The main switch of the transformer substation is used to measure the electricity entering the substation; the branch node can be a low-voltage branch box, cable junction box, integrated distribution cabinet, or a data acquisition node at the branch of a low-voltage feeder; the electricity metering box incoming node can be a node formed by an integrated metering unit or equivalent data acquisition device on the incoming side of the metering box; the household meter node can be a terminal metering node formed by a single household smart electricity meter or a group of household meters; the hierarchical link can include the branch segment between the main metering node of the transformer substation and the branch node, the metering box segment between the branch node and the electricity metering box incoming node, and the meter segment between the electricity metering box incoming node and the household meter node; for transformer substations without independent branch nodes, the upstream link segment can be formed from the main metering node of the transformer substation to the electricity metering box incoming node, and the downstream link segment can be formed from the electricity metering box incoming node to the household meter node.

[0024] In this application, time-scale alignment based on micro-feature fingerprints refers to determining the time-scale offset of a downstream node relative to a reference node by utilizing the corresponding changes in voltage waveforms, current waveforms, phase angles, or neutral current curves of the same electrical disturbance in upstream and downstream nodes, rather than solely relying on the node's original local clock stamp or network time synchronization results. The micro-feature fingerprint can be represented by a micro-feature record, which may include at least the following fields: voltage instantaneous drop start point, drop amplitude, recovery slope, phase angle disturbance start and end points, neutral current abrupt change point, current amplitude change direction, and time interval between adjacent change segments. The above fields can be selected based on the node's sampling capability, electrical quantity acquisition accuracy, and on-site disturbance characteristics. When a node does not have the capability to acquire complete waveforms, frozen power increment changes, load power changes, or power abrupt change segments in the transmitted batch can also be used as auxiliary alignment criteria.

[0025] The synchronization time grid refers to the time reference used to unify the resampling of multi-node power curves after time-scale alignment is completed. The step size of the synchronization time grid can be configured according to the node uploading cycle, communication protocol, acquisition equipment capability, master station processing capability, and line loss management accuracy. For example, for low-voltage distribution areas using conventional frozen power acquisition, the synchronization time grid step size can be selected as 15 minutes; for distribution areas with high-frequency acquisition capabilities at the incoming or branch nodes of the power metering box, the synchronization time grid step size can be selected as 5 minutes or 1 minute. The above 15 minutes, 5 minutes, and 1 minute values ​​match the common frozen acquisition cycle, minute-level acquisition cycle, and sampling capability of the incoming side monitoring unit in low-voltage distribution areas. In actual use, adjustments can be made according to the capabilities of the on-site acquisition terminal, the communication link carrying capacity, and the master station data processing strategy. Pseudo-loss components refer to those caused by node time-scale misalignment, freezing, etc. The difference in power consumption in a section introduced by junction offset, transmission cycle difference, communication delay, or data lateness is not directly caused by actual line consumption or metering anomalies. The actual loss component refers to the loss component formed by actual operational reasons such as line heat loss, metering error, abnormal contact resistance, file mismatch, reverse power flow of distributed photovoltaic, and electricity theft pending review. For the actual loss component, evidence comparison conditions can be set according to different cause categories, and corresponding responsibility components and credibility can be generated to avoid the result of the previous type of judgment covering the result of the next type of judgment due to fixed order of investigation. The trend observation aligned with the load cycle refers to comparing the actual loss curve with the load cycle, seasonal cycle, or historical similar cycle when the comprehensive line loss rate does not exceed the management qualified range, in order to observe whether the actual loss is slowly rising, continuously offset, or periodically deviating and expanding.

[0026] like Figure 1 As shown, the transformer area line loss location system provided in this application may include a transformer area main meter node 101, branch nodes 102, electricity meter box incoming node 103, household meter node 104, main execution entity 105, and main station system 106. The main execution entity 105 may be at least one of the following: transformer area intelligent fusion terminal, distributed monitoring terminal, transformer area fusion host, synchronous line loss management platform server, distribution IoT main station server, or marketing information system server. The main execution entity 105 may receive data from each node through high-speed power line carrier, low-power wireless, RS485 bus, optical fiber, power wireless private network, or public network security channel, and output line loss location results, responsibility tags, abnormal records, and parameter update records to the main station system 106. The main station system 106 may include one or more of the following: synchronous line loss system, marketing information system, distribution IoT main station, transformer area archive system, and management work order system. The main execution unit 105 may include a data access module 110, a micro-feature alignment module 120, a section power recalculation module 130, a loss decomposition module 140, an evidence attribution module 150, a hierarchical positioning module 160, a trend observation module 170, and an anomaly closed-loop module 180. The data access module 110 receives data from the main meter node 101, branch nodes 102, power meter box incoming nodes 103, and household meter nodes 104, and establishes a node-level cache. The data in the node-level cache includes at least the following fields: node identifier, node role, acquisition time, upload batch number, power data, and electrical quantity data. The micro-feature alignment module 120 extracts micro-feature fingerprints from voltage waveforms, current waveforms, phase angles, or neutral current curves, and determines the time-scale offset of downstream nodes relative to the reference node. The section power recalculation module 130 is used to perform synchronization... Within the inter-grid, the power curves that have completed time-stamp alignment are resampled, and the segment power differences of branch sections, metering box sections, and meter sections are recalculated; the loss decomposition module 140 is used to distinguish between pseudo-loss components and actual loss components based on the segment power difference, time-stamp offset, transient change amplitude of electrical quantities, and physical rationality verification results; the evidence attribution module 150 is used to compare multiple types of causal evidence for actual loss components to obtain responsibility components, primary responsibility categories, secondary responsibility categories, and attribution credibility; the hierarchical positioning module 160 is used to output loss positioning results and responsibility labels on branch sections, metering box sections, and meter sections; the trend observation module 170 is used to observe the actual loss trend aligned by load cycle when the comprehensive line loss rate is within the management qualified range; the anomaly closed-loop module 180 is used to perform data supplementation, low-confidence output, link segment shielding, manual takeover, work order write-back, and label self-verification; In one optional deployment method, the data access module 110, micro-feature alignment module 120, and section power recalculation module 130 can be deployed within the intelligent fusion terminal of the distribution area. This allows for the completion of raw data caching, timescale offset determination, and section power recalculation on the distribution area side, reducing the real-time processing pressure on the main station side for a large number of raw curves. The loss decomposition module 140, evidence attribution module 150, hierarchical positioning module 160, trend observation module 170, and anomaly closed-loop module 180 can be deployed on the main station system 106 side. This allows for the combination of cross-distribution area historical operation records, distribution area archive data, and governance work order data to perform loss attribution. The method includes cause and trend observation and closed-loop write-back; in another optional deployment method, the main execution entity 105 can also be implemented by the synchronous line loss management platform server. After the data of each node is uniformly sent to the main station, the main station completes time stamp alignment, section power recalculation, loss decomposition and attribution location; the above deployment methods can be selected according to the capabilities of the transformer area acquisition equipment, the carrying capacity of the communication link and the processing capacity of the main station. As long as the corresponding transmission relationship between the original data frame, time stamp alignment result, section power difference, pseudo loss component, real loss component, responsibility label and write-back record can be maintained, the transformer area line loss location method of this application can be realized.

[0027] like Figure 2 As shown, the method provided in this application may include the following processing: S101, the main execution entity 105 acquires node-level data of the main meter node 101, branch node 102, electricity meter box incoming node 103, and household meter node 104, and establishes a node-level cache bound to node roles and upstream and downstream connection relationships; S102, the main execution entity 105 performs time-scale alignment on downstream nodes based on the micro-feature fingerprints in the reference node curve and downstream node curve, obtaining the time-scale offset and the aligned time series; S103, the main execution entity 105 resamples the aligned time series according to the synchronous time grid, and recalculates the segment electricity difference of the branch segment, meter box segment, and meter segment according to the upstream and downstream connection relationships; S104, the main execution entity 105 performs calibration based on the segment electricity difference, time-scale offset, transient change amplitude of electrical quantity, and physical rationality. The results are verified to identify the pseudo-loss component and the actual loss component; S105, the main execution entity 105 compares the actual loss component with multiple types of causal evidence to obtain the responsibility component, dominant responsibility category, secondary responsibility category, and attribution credibility of each causal category; S106, the main execution entity 105 summarizes the actual loss component and responsibility component on the layered link according to the evaluation cycle, outputs the link segment location result, and writes it into the responsibility label; S107, when the comprehensive line loss rate is within the management qualified range, the main execution entity 105 performs trend observation of the actual loss curve aligned with the load cycle and generates a slow degradation warning; S108, the main execution entity 105 performs abnormal degradation and closed-loop write-back according to the data missing, time stamp abnormality, physical verification abnormality, low attribution credibility, or responsibility label self-verification failure, and feeds back the handling results to the subsequent evaluation cycle; In S101, after the main execution entity 105 enters the running state, it can first read the transformer area archive data. The transformer area archive data includes at least the transformer area number, transformer area master meter node identifier, branch node identifier, electricity meter box number, household meter number, meter box belonging branch, household-transformer relationship, upstream and downstream connection relationship, transformer ratio, metering equipment level, distributed photovoltaic user identifier, and historical governance records. The main execution entity 105 establishes a node role table and a link segment table based on the transformer area archive data, so that subsequent processing can distinguish whether the data comes from the upstream master meter, low-voltage branch, electricity meter box incoming side, or household meter end. Each frame of node-level data includes at least the node identifier, node role, and sampling information. The data includes fields such as time of collection or local clock stamp, batch number of uploaded data, power data, and electrical quantity data. For nodes with waveform or near real-time acquisition capabilities, node-level data can also include fields such as instantaneous three-phase voltage values, instantaneous three-phase current values, phase angle, power factor, and neutral current. For nodes that only have the ability to upload frozen power, node-level data can at least include fields such as frozen power, freezing time, local clock stamp, and batch number of uploaded data. Through the binding of the above fields, the main execution entity 105 can uniformly incorporate data uploaded by different acquisition systems into the same area node connection relationship for processing, avoiding object confusion caused by simply merging based on meter number or acquisition terminal address. The main execution entity 105 can establish node-level caches according to the assessment cycle. The assessment cycle can be a daily assessment cycle, a shift assessment cycle, an hourly assessment cycle, or other cycles configured by the governance system. Its specific length can be determined based on the main station line loss statistics cycle, the on-site collection cycle, governance response requirements, and historical data storage capacity. The node-level cache can store data within one or more time-scale alignment windows. The length of the time-scale alignment window can be determined based on the node upload cycle, the frequency of micro-feature occurrence, and the load fluctuation of the distribution area. For example, when most nodes use 15-minute frozen power uploads, the time-scale alignment window can cover several 15-minute grids. When the integrated metering unit on the incoming side of the power metering box can upload minute-level or second-level curves, the time-scale alignment window can be shortened accordingly. The aforementioned 15-minute interval matches the common frozen power acquisition cycle, and the minute-level or second-level curve matches the acquisition terminal or the integrated metering unit on the incoming side of the metering box with high-frequency sampling capabilities. The window length, cache depth, and missing ratio threshold can be configured based on equipment specifications, communication link quality, historical operation records, and on-site test results. In the anomaly handling of S101, when a node is briefly missing within a single time grid, the data access module 110 can mark the node as needing to be supplemented and send a supplementary data collection request to the communication acquisition channel. The supplementary data collection time can be configured according to the communication protocol, the response capability of the acquisition terminal, and the master station acquisition strategy. When the missing proportion of the same node exceeds a preset proportion within an evaluation cycle, the main execution entity 105 can block the link segment corresponding to the node in the subsequent segment power recalculation to prevent missing data from being mistakenly identified as actual loss. The missing proportion threshold can be determined based on the stability of the communication link, the node uploading cycle, the historical supplementary data collection success rate, and the fault tolerance requirements of the governance system. This threshold is used to distinguish between short-term missing data, continuous missing data, and high proportion missing data within a cycle. When the loss occurs only in a single grid, supplementary sampling or temporary filling can be triggered; when the loss ratio exceeds the threshold, the corresponding link segment can be blocked or a low-reliability result can be output; when a node is continuously disconnected for more than a preset number of evaluation cycles, for example, when it is continuously disconnected for more than 3 evaluation cycles, the abnormal closed-loop module 180 can set the node status to long-term disconnection, generate a maintenance work order or manual review task, and retain the last valid data, the start time of disconnection, and the link segment loss status before and after disconnection; the 3 evaluation cycles here are optional examples, and their setting is based on the fact that continuous short-cycle disconnection usually exceeds the range of normal communication jitter. The actual number can be adjusted according to the collection cycle, communication link stability, and on-site operation and maintenance response requirements. In S102, the micro-feature alignment module 120 can use the voltage waveform of the main meter node 101 of the distribution area as a reference curve; when the curve of the main meter node 101 of the distribution area is unavailable or of low quality, the upstream branch node 102, which is closer to the target link segment, can also be selected as a reference node; for the evaluation of meter segments inside the metering box, the incoming node 103 of the power metering box can also be used as a reference node for the household meter node 104; the main execution entity 105 can record the selection results of the reference node according to the evaluation scope and node data quality, which is convenient for subsequent traceability; The micro-feature alignment module 120 extracts micro-feature segments that characterize the same electrical disturbance from the reference curve. These micro-feature segments can include at least fields or curve segments such as the voltage instantaneous drop start point, drop duration, recovery process, recovery slope, phase angle disturbance, neutral current abrupt change, and current amplitude change. These micro-feature segments are not abstract model features, but rather physical change segments in the electrical quantity curve that can be directly identified and recorded. For example, when a user's high-power load starts, the relevant upstream and downstream nodes typically experience similar voltage drops and current rises; when a branch load is disconnected, the relevant nodes typically experience current amplitude decreases and voltage recovery; when the neutral contact state changes, the relevant link segment may experience neutral current changes. The micro-feature alignment module 120 can then reference the micro-feature segments... The segment is used as the comparison object. A sliding comparison is performed on the same-dimensional or related-dimensional curves of branch node 102, power meter box inlet node 103 and household meter node 104. The segment that meets the similarity threshold, directional consistency threshold and time range threshold is selected as the corresponding physical event. The time difference of the corresponding physical event is used to determine the time scale offset of the downstream node relative to the reference node. The similarity threshold is used to determine whether the change shape of the upstream and downstream curves corresponds to the same disturbance. The directional consistency threshold is used to exclude segments with opposite directions, such as voltage rise and voltage drop. The time range threshold is used to limit the maximum allowable offset of the candidate segment relative to the reference segment. The above thresholds can be configured according to the sampling period, communication delay records, historical reliable alignment results, node crystal oscillator drift and field test results.

[0028] like Figure 3 As shown, the multi-node time-scale alignment diagram may include a reference curve 201, a downstream curve 202, a micro-feature segment 203, and a time-scale offset 204. The reference curve 201 may be the voltage curve, phase angle curve, or other curves that can reflect upstream electrical disturbances at the main meter node 101 of the distribution area. The downstream curve 202 may be the electrical quantity curve corresponding to the reference curve 201 in the branch node 102, the incoming line node 103 of the energy metering box, or the household meter node 104. The micro-feature segment 203 may be represented by a micro-feature record, which includes at least the disturbance start time, disturbance end time, change direction, change amplitude, duration, and the type of electrical quantity. The micro-feature alignment module 120 compares the micro-feature segment 203 in the reference curve 201 with the candidate segment in the downstream curve 202. When the candidate segment meets the similarity threshold, direction consistency threshold, and time range threshold, the candidate segment is determined as the physical disturbance segment corresponding to the micro-feature segment 203, and the time-scale offset 204 is determined based on the time difference between the two. When multiple micro-feature fragments 203 exist within the same time-scale alignment window, the micro-feature alignment module 120 can determine multiple candidate time-scale offsets respectively, and select the final time-scale offset by combining the historical offset range, the number of corresponding fragments, and the consistency of physical direction. The historical offset range can be determined based on the node's historical alignment log, sampling period, communication delay record, and time synchronization error record. If the differences between multiple candidate time-scale offsets are large, or if the candidate fragments cannot stably fall within the historical offset range, the micro-feature alignment module 120 can output a low-confidence alignment identifier and transfer the corresponding link segment to a pending review or downgrade processing state, instead of directly outputting a deterministic positioning result.

[0029] In one optional implementation, the micro-feature alignment module 120 can extract micro-feature fragments according to preset rules. The preset rules can be determined based on equipment calibration results, historical operation records, field test data, or manual configuration. For example, when the voltage change amplitude exceeds the normal fluctuation range of the corresponding node, the duration meets the sampling period requirements, and the voltage rise direction matches the load change direction, it can be identified as a voltage disturbance fragment. When the phase angle experiences a disturbance synchronized with the current amplitude change in a short period of time, it can be identified as a phase disturbance fragment. When the neutral current exhibits a continuous step change, it can be identified as a neutral current change fragment. The aforementioned micro-feature fragments can be represented by micro-feature records, which at least include fields such as the disturbance start time, disturbance end time, change direction, change amplitude, duration, and the type of electrical quantity to which they belong. This method is suitable for nodes with high sampling quality, such as the transformer substation main meter node 101 and the power metering box incoming node 103. When some downstream nodes lack the capability to acquire complete waveforms, the micro-feature alignment module 120 can use correlated data for alignment. For example, the reference node can use a voltage instantaneous change segment, and the downstream node can use a frozen power increment change, load power change, or a power mutation segment in the transmitted batch for correspondence. In this case, it is not required that the reference node and the downstream node have completely identical data types; as long as they can correspond to the same electrical disturbance, they can be used to determine the time correspondence. If no micro-feature segment that meets the similarity threshold, direction consistency threshold, and time range threshold is found, the micro-feature alignment module 120 can use... A coarse alignment method is used. The coarse alignment method can determine the temporary time stamp offset based on the uploaded batch sequence number, the receiving time of the main execution entity 105, the node's local clock stamp, and the most recent valid offset, and mark the corresponding node as a low-confidence alignment node. The low-confidence alignment node can enter the subsequent synchronization time grid for recalculation, but its confidence needs to be reduced during loss decomposition and responsibility attribution, or only a label to be verified can be output. Through this processing, the continuity of the line loss analysis process can be maintained in the case of communication anomalies, nodes that have just been powered on, few micro-features, or long-term stable load, while avoiding the use of low-confidence results as deterministic location conclusions. In the anomaly handling corresponding to S102, when the timescale offset exceeds the node's upload interval, exceeds the historical offset change range, or shows a significant jump within adjacent windows, the micro-feature alignment module 120 can trigger a timescale offset anomaly alarm; the anomaly closed-loop module 180 can record information such as the reference curve, downstream curve, candidate micro-feature segments, candidate timescale offsets, and final alignment status, facilitating subsequent verification; when multiple consecutive windows of the same node fail to achieve reliable alignment, the main execution entity 105 can set the node to coarse alignment observation state or manual verification state; through the above processing, timescale alignment no longer relies solely on the node's local clock, but combines electrical quantity physical changes, node roles, and link segment connection relationships, providing a basis for subsequent pseudo-loss component identification; In the processing corresponding to S103, the section power recalculation module 130 determines the synchronization time grid based on the time sequence after each node completes time-scale alignment and the upstream and downstream connection relationship, and recalculates the section power difference within the synchronization time grid. For distribution areas with only 15 minutes of frozen power, the step size of the synchronization time grid can be selected as 15 minutes. For distribution areas with minute-level acquisition capabilities for the incoming node 103 of the power meter box and the branch node 102, the step size of the synchronization time grid can be selected as 5 minutes or 1 minute. For the scenario where the household meter node 104 only has low-frequency frozen data, a coarser grid can be used in the meter section, and a finer grid can be used in the branch section and the meter box section. The grid type used in each link section is recorded in the output results. The above 15 minutes, 5 minutes, and 1 minute are matched with the common freezing acquisition cycle, minute-level acquisition cycle, and sampling capability of the incoming side monitoring unit in low-voltage distribution areas. The actual grid step size can be adjusted according to the acquisition terminal capability, communication link carrying capacity, master station storage capacity, and line loss management accuracy. The section power recalculation module 130 can resample the active power curve, reactive power curve, and reverse active power curve after time-scale alignment, so that the power values ​​of each node correspond to the same grid boundary. For the cumulative power field, the power increment within the grid can be determined based on the difference between the cumulative values ​​of the grid start and end points. For the power curve, the power can be calculated according to the sampling points and sampling intervals within the grid. For reverse active power, the direction indicators of forward and reverse power can be retained to avoid mistakenly merging the reverse power flow during distributed photovoltaic grid connection into the reduction of ordinary load. The resampled power record includes at least the following fields: node identifier, grid start point, grid end point, power increment, power direction indicator, data source identifier, and data reliability indicator. The section power recalculation module 130 calculates the section power difference for branch sections, metering box sections, and metering sections according to the upstream and downstream connection relationships. The section power difference for branch sections can be obtained from the difference between the power output of the branch corresponding to the main meter node 101 of the transformer substation and the downstream aggregated power of the branch node 102. The section power difference for metering box sections can be obtained from the difference between the power output of the branch node 102 and the power output of the power metering box incoming node 103. The section power difference for metering sections can be obtained from the difference between the power output of the power metering box incoming node 103 and the power output of the metering box. The difference between the total electricity consumption of the household meter nodes 104 in the box can be obtained; for the transformer area without independent branch nodes 102, the difference in electricity consumption of the upstream section can be calculated based on the connection relationship between the transformer area main meter node 101 and the electricity meter box incoming node 103, and the difference in electricity consumption of the downstream section can be calculated based on the connection relationship between the electricity meter box incoming node 103 and the household meter nodes 104; for the transformer area with a large number of household meter nodes 104 and short-term missing data of individual meters, the data can be summarized by household meter group or meter box first, and then the difference in electricity consumption of the meter section can be calculated. In the anomaly handling corresponding to S103, when a node is missing in a single grid, the segment power recalculation module 130 can temporarily fill the gap by using historical statistical values ​​of the same day and time period, the median of the statistical values ​​of the same time period over the most recent several days, or the most recent valid value, and record the filling source and filling identifier. The specific number of days over the most recent several days can be determined according to the load cycle of the transformer area, the integrity of historical data, and the storage cycle of the master station. For example, in a residential transformer area with a stable daily load pattern, the data of the same time period over the most recent 7 days can be used as a reference. 7 days matches the common weekly cycle pattern of residential load. In practice, 14 days, 30 days, or other cycles can also be selected according to data integrity and management requirements. For the filling data, the loss decomposition module 140 can reduce the credibility of the corresponding grid. If the missing proportion of the same node exceeds the preset threshold, or the filling data continuously covers multiple key grids, the anomaly closed-loop module 180 can shield the link segment corresponding to the node and output the downgraded location result or the status pending review, so as to avoid the missing data being mistakenly identified as the real segment power difference. In the processing corresponding to S104, the loss decomposition module 140 distinguishes between pseudo loss components and real loss components for the segment power difference. like Figure 4As shown, the segment power difference 301 enters the pseudo loss component judgment path 302 and the real loss component judgment path 303. The judgment results of the two are processed by physical verification 304 to form data that can be used for location and attribution. The loss decomposition module 140 can statistically analyze the transient change amplitudes such as voltage amplitude range, current amplitude range, phase angle range, power factor change and neutral current range for each time grid, and read the time scale offset obtained in S102. When the grid is in steady state and the time scale offset is lower than the offset threshold, the part of the segment power difference 301 that meets the physical rationality verification can be used as the real loss component. The steady state can be determined based on the normal fluctuation range of voltage, current, phase angle and neutral current under historical load conditions. The offset threshold can be determined based on the sampling period, freeze time deviation and historical alignment log. When the load within the grid changes rapidly and there is a significant timescale offset between upstream and downstream nodes, the loss decomposition module 140 can determine the pseudo-loss component introduced by the timescale misalignment based on the timescale offset direction, offset duration, curve change direction, and transient change amplitude. The segment power difference after deducting the pseudo-loss component is used as the actual loss component to be verified. The rapid fluctuation threshold can be determined based on the change amplitude of electrical quantities caused by the start-up and shutdown of high-power loads, changes in distributed photovoltaic output, or historical load abrupt changes. Through this processing, the non-real difference caused by the timescale misalignment can be separated from the real energy loss, so that subsequent positioning and attribution are based on physically consistent data.

[0030] In the loss decomposition process, the loss decomposition module 140 can process the segment power difference 301 according to the state interval. If the voltage, current, phase angle, and neutral current in the current synchronization time grid are all in a stable range, and the time scale offset is lower than the offset threshold, then the part of the segment power difference 301 that meets the physical rationality verification is taken as the actual loss component. The stable range can be determined based on the normal fluctuation range of electrical quantities under historical load conditions, and the offset threshold can be determined based on the equipment sampling period, freeze time deviation, and historical offset records. If there is rapid fluctuation in the current synchronization time grid, and the time scale offset exceeds the offset threshold, then the pseudo loss component is determined based on the offset direction, offset duration, curve change direction, and transient change amplitude. For branch sections, the consistency between the current amplitude change and the total downstream power consumption of the branch node can be compared. For metering box sections, the voltage waveform, neutral current, and temperature and humidity conditions inside the box of the incoming node 103 of the power metering box can be compared. For metering sections, the consistency between the total power consumption of the household meter node 104, the reverse power consumption of a single meter, and the batches of power transmitted by the household meter can be compared. For areas with a high proportion of distributed photovoltaic access, when processing the power difference in sections, the loss decomposition module 140 can retain the forward active power and the reverse active power separately, and separately mark the difference in upstream and downstream power direction caused by the reverse power flow during the daytime photovoltaic output period, so that such differences can be included in the subsequent photovoltaic reverse power flow evidence comparison process.

[0031] Physical verification 304 can include energy direction verification, historical load condition verification, and upstream and downstream link consistency verification. Energy direction verification is used to determine whether the actual loss component has an abnormal negative value that does not match the direction of power flow. Historical load condition verification is used to determine whether the current actual loss component deviates significantly from the normal range under similar load, similar temperature, or similar time period. Upstream and downstream link consistency verification is used to determine whether the loss distribution between branch sections, metering box sections, and meter sections conforms to the node connection relationship and load distribution law. When the actual loss component has an abnormal value that does not match the direction of power flow, deviates significantly from the historical load condition in terms of order of magnitude, or fails to meet the upstream and downstream energy balance relationship, the loss decomposition module 140 can trigger a physical rationality alarm and set the corresponding synchronization time grid to a pending review state or a rejection state. Through this processing, the section power difference will not be directly used as a responsibility conclusion, but will first undergo time scale influence separation and physical rationality constraints, thereby reducing the positioning error caused by acquisition deviation, freezing misalignment, or data delay.

[0032] In the evidence attribution process, the evidence attribution module 150 compares multiple types of causal evidence for the actual loss component. like Figure 5As shown, the evidence attribution module 150 can set evidence channels such as line type 401, metering error type 402, file mismatch type 403, photovoltaic type 404, electricity theft pending verification type 405, and contact anomaly type 406. Each evidence channel reads the actual loss component, node status quantity, file data, event record, and physical verification result, and generates the corresponding cause category's responsibility component and evidence credibility. The evidence channels are not eliminated one by one in a fixed order, nor are the unexplained parts of the previous evidence channel forcibly assigned to the next evidence channel. Instead, multiple cause categories' responsibility components are output in the same link segment and the same evaluation cycle. Then, the hierarchical positioning module 160 determines the dominant responsibility category and the secondary responsibility category.

[0033] Line-related type 401 can be judged based on current magnitude, load duration, link segment length, line specifications, ambient temperature, and historical load loss relationship; metering error type 402 can be judged based on meter level, calibration records, transformer ratio, meter events, metering device inaccuracy alarms, and long-term deviations under similar loads; file mismatch type 403 can be judged based on household-transformer relationship, meter box branch affiliation, node connection relationship, transformer area change records, and correlation with user electricity consumption curves; photovoltaic type 404 can be judged based on distributed photovoltaic user identification, daytime reverse active power, inverter grid connection period, and alternation of forward and reverse power; electricity theft pending verification type 405 can be judged based on events such as opening cover, strong magnetic field events, neutral wire abnormality, phase wire reverse connection, reverse wiring, and load changes. Anomalies and sudden changes in electricity consumption curves are used for judgment. This type of output is for on-site verification or manual confirmation and should not be used to form a final conclusion based on a single data point. Contact anomaly type 406 can be judged based on the temperature, humidity, neutral current, terminal temperature rise, load current, and duration inside the metering box. When a metering box section continuously experiences abnormal temperature rise or abnormal neutral current without a significant increase in load, accompanied by an increase in the actual loss component, the responsibility component for contact anomalies can be increased. The above events or states can come from smart meter event records, electricity metering box status acquisition units, photovoltaic user files, inverter grid connection records, or main station side event records. When the corresponding acquisition items are not configured on-site, the corresponding evidence conditions can be omitted, or the corresponding anomaly type can be used as a manual review item.

[0034] The evidence attribution module 150 can configure an evidence condition table for each type of cause. The evidence condition table can be determined based on equipment calibration results, historical operation records, on-site test results, industry experience, and manual configuration. The evidence condition table should include at least the following fields: trigger field, abnormal amplitude threshold, duration threshold, associated time window, applicable link segment, applicable operating condition, exclusion condition, and output label. The abnormal amplitude threshold is used to determine whether a certain state quantity deviates significantly from the historical normal range. The duration threshold is used to exclude instantaneous disturbances. The associated time window is used to determine whether the actual loss component belongs to the same abnormal process as the opening event, abnormal temperature rise, abnormal neutral current, reverse active power change, or file change record. The evidence credibility threshold can be determined based on historical review accuracy, similar transformer area management records, and on-site data. The calibration results are determined; when the credibility of evidence for a certain cause category reaches the corresponding threshold, that cause category can be used as a candidate for responsibility label; when multiple cause categories reach the corresponding threshold, the dominant responsibility category and the secondary responsibility category can be output; when none of the cause categories reach the corresponding threshold, an unknown cause label or a label pending review can be output; the evidence attribution module 150 can also set different evidence reference orders according to the link segment location, for example, the meter segment should focus on referencing evidence of metering error, file mismatch, and electricity theft pending review, the meter box segment should focus on referencing evidence of contact anomaly, neutral wire anomaly, and box temperature and humidity, and the branch segment should focus on referencing evidence of line type and photovoltaic reverse power flow; when the evidence strength of multiple cause categories is close, the evidence attribution module 150 can output a composite responsibility label.

[0035] In the hierarchical location processing, the hierarchical location module 160 summarizes the actual loss components of branch segments, metering box segments, and metering segments, as well as the responsibility components of each inducing factor, according to the evaluation cycle, and generates the link segment loss distribution and link segment location results within the transformer area. The hierarchical location module 160 can first determine whether there is an abnormal concentration of actual loss in a branch segment. If the actual loss component of a certain branch segment exceeds the historical normal range, and its responsibility component ratio is higher than that of other link segments in the same layer, it can be determined that the branch segment is significantly abnormal and located to the corresponding branch node 102 and its downstream range. The historical normal range can be based on the historical data under the same load, the same season, or the same operating mode. Section loss records are determined; within the corresponding branch, the hierarchical positioning module 160 continues to determine whether there is an abnormal concentration of actual losses in the metering box section; if a certain metering box section is obviously abnormal, it is located to the corresponding electricity metering box incoming node 103 and its internal meter group; within the metering box, the hierarchical positioning module 160 continues to determine whether there is an abnormal concentration of actual losses in the metering section; if a certain metering node 104 or meter group contributes significantly, it is located to the metering section; this hierarchical positioning method can first determine the level of the abnormality, and then refine the responsible objects within that level, reducing the positioning deviation of jumping directly from the overall line loss rate of the transformer area to the individual meter.

[0036] The hierarchical positioning module 160 can write the positioning results to the link segment governance log. The governance log includes at least the following fields: evaluation period, link segment identifier, upstream node identifier, downstream node identifier, actual loss component, pseudo loss component, primary responsibility category, secondary responsibility category, attribution credibility, data quality identifier, and suggested review action. The responsibility label can include line type, metering error type, file mismatch type, photovoltaic reverse power flow type, electricity theft pending review type, contact anomaly type, composite responsibility type, unknown cause type, and low credibility pending review type. For link segments with attribution credibility that meets the requirements and physical verification that passes, the hierarchical positioning module 160 can output a deterministic positioning result. For link segments with low data quality, physical verification failure, or multiple evidence channels conflicting, the hierarchical positioning module 160 can output a pending review label and record the uncertain reasons. When facing different business systems, the positioning results can be output in the form of a list of suspicious points, loss distribution, trend status, anomaly level, file correction suggestions, or collection of operation and maintenance records, but all of the above output forms originate from the same positioning processing process.

[0037] In the trend observation process, when the overall line loss rate is still within the acceptable management range, the trend observation module 170 performs trend observation of the actual loss component aligned with the load cycle. like Figure 6 As shown, the trend observation diagram may include the actual loss curve 501, the qualified interval 502, the observation window 503, and the early warning level 504. The qualified interval 502 can be configured according to the power supply unit's synchronous line loss management rules, transformer area type, historical operating level, and industry experience. For example, for a certain type of low-voltage transformer area, the management reference interval for the comprehensive line loss rate can be selected as 0% to 7%. This interval matches the synchronous line loss management requirements, transformer area type, and historical operating level of the low-voltage transformer area. In actual use, the management rules configured by the power supply unit or project site shall prevail. The trend observation module 170 does not stop processing because the comprehensive line loss rate is within the qualified interval 502. Instead, it continues to read the actual loss curve 501 of the branch section, meter box section, and meter section, and selects the short-term, medium-term, or long-term sliding observation window 503 to align the actual loss curve 501 with the load cycle, seasonal cycle, and historical similar cycle to determine whether there is a continuous increase, a periodic deviation expansion, or a gradual increase in loss under the same load conditions.

[0038] The duration of observation window 503 can be configured based on the daily assessment cycle of the transformer area, seasonal load fluctuations, governance review cycle, and historical data storage capacity. For example, the short-term observation window can be selected as 30 days, the medium-term observation window as 90 days, and the long-term observation window as 180 days. Among them, 30 days corresponds to the monthly operation observation cycle, 90 days corresponds to the quarterly operation observation cycle, and 180 days corresponds to the semi-annual operation observation cycle. In actual use, the above observation window durations can be adjusted according to the power supply unit's management cycle, the seasonality of transformer area load, and data accumulation. The trend warning threshold can be determined based on the comprehensive line loss management qualified range, the historical loss fluctuation band of the same load, and the number of continuous increases in the short-term, medium-term, and long-term observation windows. If the actual loss component in the current observation window 503 continues to increase relative to the same historical period, but the comprehensive line loss rate has not yet exceeded the qualified range 502, the trend observation module 170 can output a low-level degradation. Warnings can be issued as follows: If the upward trend persists and is expected to approach the acceptable range boundary in subsequent evaluation periods, a medium-level degradation warning can be issued; if the upward trend is significant, multiple observation windows point to the same link segment, and are accompanied by evidence such as contact anomalies, metering drift, or reverse photovoltaic power flow, a high-level degradation warning can be issued; for link segments with low-confidence alignment, excessively high missing fill ratios, or failed physical verification, the trend observation module 170 may temporarily withhold trend warnings and instead include them in the pending review or extend the observation period; the trend observation module 170 can also observe trends separately according to responsibility labels. For example, for contact anomaly type responsibility labels, the focus is on observing the synchronous rise of the actual loss component and temperature rise state of the metering box segment under the same load conditions; for metering error type responsibility labels, the focus is on observing the long-term stable directional deviation of the meter segment; for line type responsibility labels, the focus is on observing the actual loss changes related to load current changes.

[0039] In the abnormal closed-loop processing, the abnormal closed-loop module 180 performs degradation and closed-loop writeback according to the abnormal state in the processing process; like Figure 7As shown, the state transition diagram for abnormal degradation and closed-loop writeback can include normal processing (601), low confidence (602), pending review (603), manual takeover (604), and closed-loop completion (605). Normal processing (601) indicates that the data quality, time-stamp alignment, physical verification, and attribution confidence all meet the requirements. Low confidence (602) indicates that a node or link segment has short-term data loss, coarse alignment, high fill ratio, or insufficient micro-features, but limited output is still possible. Pending review (603) indicates that physical rationality verification failed, attribution evidence conflicted, responsibility label self-verification failed, or the abnormality persists, requiring on-site or back-end review. Manual takeover (604) indicates situations involving pending review of electricity theft, reverse wiring, highly sensitive metering anomalies, long-term disconnection, or inconsistent multiple reviews, requiring manual confirmation before a definitive conclusion can be output. Closed-loop completion (605) indicates that the governance work order, on-site review, or file correction has been completed, and the review results in the next evaluation cycle meet expectations.

[0040] The anomaly closed-loop module 180 can perform corresponding processing actions for different anomalies. For missing data, the anomaly closed-loop module 180 can trigger supplementary sampling, temporary filling, link segment shielding, or extend the evaluation cycle. For time scale offset anomalies, the anomaly closed-loop module 180 can roll back to coarse alignment, use the most recent valid offset, reselect the reference node, or trigger terminal time synchronization verification. For physical verification failure, the anomaly closed-loop module 180 can remove the abnormal grid, retain the original curve, and output a label to be verified. For low attribution confidence, the anomaly closed-loop module 180 can extend the observation window, output an unknown cause label, or transfer to manual confirmation. For output results involving electricity theft verification type 405, reverse wiring, or transformer polarity anomalies, the evidence attribution module 150 can only generate a label to be verified, evidence fragments, and verification suggestions, and the final handling conclusion is formed after manual verification.

[0041] Closed-loop write-back can include governance work order write-back, file correction write-back, on-site verification result write-back, parameter update write-back, and tag self-verification write-back. Governance work order write-back should include at least the work order number, link segment identifier, handling action, handling time, and handling result. File correction write-back can record corrections to household transformer relationships, meter box affiliation branches, or transformer ratios. On-site verification result write-back can record terminal tightening, meter replacement, line inspection, photovoltaic grid connection verification, or electricity theft verification results. Parameter update write-back can update micro-feature thresholds, offset change ranges, missing proportion thresholds, evidence condition tables, and trend observation windows. Tag self-verification write-back can be performed within the next evaluation cycle. Check if the corresponding responsibility component has decreased; if the decrease in responsibility component after handling reaches the preset decrease threshold, and the actual loss component returns to the historical normal range, then increase the credibility of the responsibility label and change the status to closed loop completion 605; the decrease threshold can be determined based on the historical fluctuation range of the actual loss component of the same link segment before and after governance, on-site verification experience, and similar fault handling records; if the responsibility component does not decrease to the expected range, or abnormally transfers to other link segments, then decrease the credibility of the label and trigger re-attribution or manual takeover 604; through the above closed loop mechanism, a one-time location conclusion can be transformed into a verifiable, rewritable, and updatable governance process.

[0042] In this application, various thresholds, limits, and interval conditions can be configured by the main execution entity 105 or the main station system 106. During configuration, factors such as equipment calibration results, communication protocols, node sampling cycles, historical operation records, on-site test results, statistical records of similar transformer areas, and manual review experience can be comprehensively considered. Threshold configuration records can include at least the following fields: threshold name, applicable object, applicable link segment, configuration basis, triggering condition, processing action, update time, and effective status. By saving the above fields, the usage scenario and adjustment basis of each threshold can be clearly defined, avoiding misjudgment caused by using only fixed values ​​for judgment. The aforementioned thresholds, limits, and interval conditions can be used in data access, time-scale alignment, segment power recalculation, loss decomposition, evidence attribution, hierarchical location, trend observation, and closed-loop self-verification processes, respectively. Specifically, the missing proportion threshold distinguishes between short-term missing data, continuous missing data, and high-proportion missing data within the evaluation period; the similarity threshold, directional consistency threshold, and time range threshold are used to filter candidate segments that correspond to the same electrical disturbance; the stable interval, rapid fluctuation threshold, and offset threshold are used to determine whether there are pseudo-loss components introduced by time-scale misalignment in the segment power difference; and the abnormal amplitude threshold, duration threshold, associated time window, and evidence credibility threshold are used to determine whether a certain cause category can be used as a basis for determining whether it is a valid cause. Candidates for responsibility labels; the criteria for judging anomalies can be determined based on the ranking of actual loss components of the link segment, the proportion of responsibility components, the historical normal range, and the comparison results of adjacent link segments; the trend warning threshold can be determined based on the management qualified range, the historical loss fluctuation band under the same load, and the number of times it rises continuously within the observation window; the threshold for the decrease can be determined based on the historical fluctuation range of the actual loss components of the same link segment before and after the treatment, on-site verification experience, and records of handling similar faults; by setting various thresholds corresponding to specific processing links, triggering conditions, and processing actions, different transformer areas can adjust them according to their own equipment conditions, communication quality, and operating rules, thereby improving the reliability and verifiability of line loss location results.

[0043] The implementation of the method in this application is explained below with reference to a specific application scenario; a low-voltage distribution area may include one main meter node 101, two branch nodes 102, multiple electricity metering box incoming nodes 103, and several household meter nodes 104. Residential users and commercial users within the distribution area are mixed-connected, and some users are configured with distributed photovoltaic systems; the node configuration of this distribution area is only used to illustrate the data relationship between various types of nodes and does not require all distribution areas to use the same number of nodes; in scenarios with corresponding data acquisition capabilities, the main meter node 101 can be configured to collect data every 15 minutes. The system transmits frozen electricity and collects high-frequency voltage curves; branch node 102 can transmit branch-side electricity or electrical quantity data every 5 minutes; electricity meter box incoming node 103 can transmit incoming-side three-phase voltage, three-phase current, and neutral current every 1 minute; household meter node 104 can transmit frozen electricity every 15 minutes; the above 15 minutes, 5 minutes, and 1 minute intervals are respectively matched with the transmission cycle, communication protocol, and acquisition accuracy of the corresponding acquisition equipment, and can be adjusted according to the capabilities of the on-site acquisition terminal, the carrying capacity of the communication link, and the main station processing strategy during actual use; The main execution entity 105 loads the distribution area wiring and attribution file during the daily assessment cycle, and identifies the branch to which each electricity meter box incoming node 103 belongs and the corresponding household meter node 104 within that electricity meter box based on the file. The distribution area wiring and attribution file may include at least the following fields: distribution area number, distribution area main meter node identifier, branch node identifier, electricity meter box number, household meter number, meter box branch, household-transformer relationship, upstream and downstream connection relationship, transformer ratio, and distributed photovoltaic user identifier. During the evening peak load start-up period, the micro-feature alignment module 120 can obtain the data from the distribution area main meter node 101. Voltage drop and voltage recovery segments are extracted from the voltage curve, and corresponding segments are searched in the curves of a certain branch node 102 and the related power meter box inlet node 103. When the corresponding segments meet the similarity threshold, direction consistency threshold, and time range threshold, the micro-feature alignment module 120 determines that the power meter box inlet node 103 has a recordable time-stamp offset relative to the transformer area master meter node 101. The time-stamp offset record may include at least the following fields: reference node identifier, downstream node identifier, disturbance start time, disturbance end time, candidate offset, final time-stamp offset, and alignment confidence. The section power recalculation module 130 aligns the data of the incoming node 103 of the power metering box to the synchronous time grid based on the time scale offset, and recalculates the section power difference of the corresponding branch section, metering box section, and meter section respectively; the loss decomposition module 140, combined with the rapid load change and time scale offset in the current time grid, determines the part of the difference introduced by the time scale misalignment as the pseudo loss component, and takes the remaining part after deducting the time scale influence as the actual loss component to be verified; after physical rationality verification, the evidence attribution module 150 compares the actual loss component of the metering box section with the box... Data such as internal temperature, neutral current, and load duration; if the increase in the actual loss component of the metering box section corresponds to the increase in internal temperature, abnormal neutral current, and load duration, but has a weaker correspondence with photovoltaic reverse active power, abnormal household transformer relationship, or meter malfunction events, then contact anomaly type 406 can be identified as the primary responsibility category, and a metering box section review recommendation can be generated; the review recommendation record can at least include the link segment identifier, electricity metering box number, primary responsibility category, related evidence field, attribution credibility, recommended review action, and generation time; On-site personnel inspected the electricity metering box according to the review recommendations and tightened the abnormal terminals. In the next evaluation cycle, if the actual loss component of the metering box section drops to the historical normal range and the contact anomaly responsibility component drops simultaneously, the anomaly closed-loop module 180 will write back the work order handling result and the tag self-verification result to the main station system 106 and improve the credibility of the responsibility tag. This scenario shows that the method of this application can first distinguish between pseudo loss components and actual loss components when the load fluctuates rapidly and the node time scale is offset, and then output a verifiable metering box section positioning result in combination with the metering box status data, thereby reducing the risk of misjudging the collection time scale misalignment as real line loss.

[0044] In another operating scenario, multiple distributed photovoltaic (PV) users are connected to a low-voltage branch. During midday when sunlight is strong, the output of the distributed PV increases, and some meter nodes 104 may experience an increase in reverse active power. Consequently, the forward active power at the incoming node 103 of the electricity metering box decreases, creating a reverse power flow indicator. In this scenario, the section power recalculation module 130 retains the direction indicators for both forward and reverse active power. The loss decomposition module 140 does not directly classify the PV reverse power flow into the ordinary actual loss component, but instead treats it as a change in power direction that needs to be identified separately. The evidence attribution module... 150 can compare daytime reverse active power, distributed photovoltaic user identification, inverter grid connection time, and alternation of forward and reverse power as photovoltaic type 404 evidence; if the actual loss component of a certain branch segment is mainly concentrated during the sunshine period and has a corresponding relationship with the change of reverse active power, then the hierarchical positioning module 160 can output a photovoltaic reverse power flow type responsibility label or photovoltaic metering verification suggestion; if the branch segment also has abnormal household transformer relationship, abnormal meter box belonging branch, or unsynchronized user file change, then a composite responsibility label of photovoltaic reverse power flow type and file mismatch type can be output.

[0045] In another operational scenario, the overall line loss rate of a certain transformer area has remained within the acceptable range of 502 for a long period. However, the actual loss component of a certain metering box section continues to rise under similar load conditions within the medium-term observation window. After comparing the actual loss curve 501 of this metering box section with historical similar cycles, the trend observation module 170 can find that its deterioration trend has slightly increased within the short-term observation window and is more stable within the medium-term observation window, but has not yet broken through the acceptable range of 502. The short-term and medium-term observation windows can be configured according to the power supply unit's daily assessment cycle, governance review cycle, and historical data storage capacity. For example, the short-term observation window... The window can be set to 30 days, or 90 days for the medium-term observation period. The 30-day window matches the monthly operation observation cycle, and the 90-day window matches the quarterly operation observation cycle. In actual use, the window can be adjusted according to the load pattern of the transformer area and the management cycle. The abnormal closed-loop module 180 generates a preventive review suggestion based on the intermediate warning level 504 output by the trend observation module 170. After the on-site review finds that the terminals in the metering box are slightly loose and tightens them, if the actual loss component falls back to the historical normal range in the next evaluation cycle, the trend observation module 170 will lift the warning, and the abnormal closed-loop module 180 will write the handling result and the review result into the main station system 106.

[0046] In some embodiments, the main execution entity 105 can form an output level based on data integrity, alignment reliability, physical verification results, and attribution reliability. The output level can include definitive output, low reliability output, pending verification output, and manual takeover output. Definitive output is applicable to link segments with complete data, reliable time-stamp alignment, passed physical verification, and clear evidence attribution results. Low reliability output is applicable to link segments with a small amount of missing data, coarse alignment, or data filling, but which can still form limited reference results. Pending verification output is applicable to link segments with conflicting evidence channels, abnormal actual loss components but unclear causes, or abnormal trend observations but insufficient evidence. Manual takeover output is applicable to link segments involving pending verification of electricity theft, highly sensitive metering anomalies, long-term disconnection, continuous physical verification failures, or multiple tag self-verification failures. The output level record can include at least the following fields: link segment identifier, output level, data integrity identifier, alignment reliability, physical verification results, attribution reliability, reason for pending verification, and generation time. Through output level control, the main execution entity 105 can avoid outputting definitive responsibility conclusions when the data is unreliable or the evidence is insufficient, thereby improving the engineering usability and verifiability of line loss location results.

[0047] In some embodiments, the section power recalculation module 130 can recalculate for different power types separately. For residential and general commercial loads, active power can be the main recalculation object, with reactive power, power factor, and current changes as auxiliary states. For areas with many reactive power compensation devices, reactive power changes can be included in physical rationality verification. For distributed photovoltaic access areas, forward active power and reverse active power can be recorded separately, and different attribution paths can be entered according to the power flow direction identifier. The power recalculation record can include at least the following fields: node identifier, link segment identifier, grid start point, grid end point, active power increment, reactive power increment, reverse active power increment, power direction identifier, and data credibility identifier. By processing different power types separately, synchronous time grid recalculation can adapt to general load areas, areas with many reactive power compensation devices, and distributed photovoltaic access areas, rather than relying solely on a single power field for judgment.

[0048] In some embodiments, the main execution entity 105 can perform field verification in the data access module 110. The field verification content may include at least the following items: whether the node identifier exists, whether the node role is consistent with the file, whether the timestamp falls within the evaluation period, whether the uploaded batch is continuous, whether the accumulated electricity has abnormally rolled back, whether the reverse active power direction identifier exists, whether the transformer ratio is available, and whether the binding relationship between the meter box and the household meter is complete. When the field verification fails, the data access module 110 may refuse to let the data frame enter the node-level cache as deterministic data, but may save it as an abnormal original frame for subsequent manual tracing or background review. The abnormal original frame may include at least the following fields: original node identifier, original acquisition time, reception time, abnormal field, abnormal type, uploaded batch sequence number, and storage time. Through the above field verification, object mismatch, time abnormality, batch abnormality, and electricity abnormality can be identified in the data access stage, avoiding the amplification of erroneous fields into erroneous location conclusions in subsequent processing.

[0049] In some embodiments, the abnormal closed-loop module 180 can process changes in transformer area wiring relationships or user affiliation. When a transformer area experiences user migration, meter box adjustment, branch renovation, or correction of user-transformer relationships, the main execution entity 105 can read the change time point from the main station system 106 and re-divide the evaluation cycle based on this change time point. Data before and after the change are not directly mixed into the statistics of the same link segment, but the segment power is recalculated separately based on the connection relationship before and after the change. If the change time point is unclear, the main execution entity 105 can determine the time range to be reviewed based on the file update time, on-site work order time, power curve correlation change, and node affiliation change record, and output a low-confidence result or a result to be reviewed within this range. The change processing record can include at least the fields of change object, connection relationship before change, connection relationship after change, change time point, data recalculation range, time range to be reviewed, and processing status. Through this processing, the impact of changes in transformer area wiring relationships or delayed user affiliation files on line loss location results can be reduced.

[0050] In some embodiments, the main execution entity 105 can specifically identify freeze misalignment. When the same node or the same type of node exhibits a fixed-direction freeze time offset within multiple consecutive evaluation windows, and this offset has a stable relationship with the node's local clock stamp, the receiving time of the main execution entity 105, or the uploaded batch sequence number, the micro-feature alignment module 120 can record this phenomenon as a freeze misalignment identifier. The freeze misalignment identifier can serve as one of the important sources of pseudo-loss components, used to distinguish between systematic acquisition deviations and real line loss anomalies. The freeze misalignment record can include at least the following fields: node identifier, node type, freeze time, receiving time, uploaded batch sequence number, offset direction, offset duration, number of continuous windows, and alignment reliability. If the freeze misalignment persists and affects multiple link segments, the anomaly closed-loop module 180 can output acquisition strategy review suggestions or terminal time synchronization review suggestions. Through this processing, misjudgments of line loss caused by fixed freeze offset, communication delays, or terminal time synchronization anomalies can be reduced.

[0051] In some embodiments, the main execution entity 105 can store raw data, processing procedures, and output results in layers; the raw layer can store node-level raw data frames, receiving time, upload batches, and field verification results; the alignment layer can store reference nodes, micro-feature fragments, candidate timescale offsets, final timescale offsets, and alignment confidence; the recalculation layer can store synchronization time grids, resampled power, and segment power differences; the decomposition layer can store pseudo-loss components, actual loss components, and physical verification results; the attribution layer can store each cause responsibility component, dominant responsibility category, and attribution confidence; the closed-loop layer can store responsibility labels, work order records, on-site verification results, and label self-verification results; the layered storage records can include at least fields such as data level, link segment identifier, node identifier, evaluation period, data source, processing result, confidence identifier, and update time; through layered storage, the processing relationship between the raw collected data and the final positioning result can be preserved, which is convenient for subsequent auditing, verification, parameter adjustment, and fault tracing.

[0052] In some embodiments, when the main execution entity 105 is implemented collaboratively by the edge terminal and the master station server, the edge terminal can prioritize data access, field verification, micro-feature extraction, preliminary timescale offset determination, and segment power recalculation, and upload the processed alignment results, segment power difference, and abnormal fragments to the master station server. The uploaded record can include at least the following fields: transformer area number, link segment identifier, node identifier, synchronization time grid, timescale offset, segment power difference, abnormal fragment identifier, and upload time. The master station server can combine cross-cycle historical records, transformer area archive data, and work order feedback data to perform loss decomposition, evidence attribution, trend observation, and closed-loop write-back. This collaborative approach can reduce communication link pressure and improve the edge side's response capability to timescale anomalies and data loss. If the edge terminal's processing capability is insufficient, data caching and preliminary field verification can be performed only on the edge side, with the master station server centrally completing the subsequent processing.

[0053] In some embodiments, the main execution entity 105 can set a recovery strategy. When communication is restored, the data access module 110 can receive late data and determine whether the late data belongs to the current evaluation period or a historical evaluation period based on the uploaded batch number and the original acquisition time. For data that can still be used to complete the current evaluation period, the segment power recalculation module 130 can re-execute the resampling of the relevant grid and the segment power difference calculation, and update the data reliability identifier of the corresponding link segment. For data belonging to a historical evaluation period, the abnormal closed-loop module 180 can save it as verification data without directly overwriting the results that have already been closed-looped. If re-evaluation is necessary, the corresponding evaluation period can be recalculated after manual confirmation. The recovery record can include at least the fields of interruption start time, interruption end time, late data batch, original acquisition time, evaluation period, processing method, and verification status. Through this recovery strategy, the impact of communication delays, out-of-order uploads, and re-transmissions on line loss location results can be reduced.

[0054] Through the above implementation methods, this application can uniformly access and verify the data of the main meter node 101, branch node 102, electricity meter box incoming node 103, and household meter node 104 based on node roles and upstream and downstream connection relationships, reducing misjudgments of line loss caused by node mismatch, incorrect file relationships, or confusion of collection objects; by using time-scale alignment based on micro-feature fingerprints and synchronous time grid recalculation, the impact of freeze time offset, communication delay, data lateness, and rapid load fluctuations on the section power difference can be reduced; by distinguishing between pseudo-loss components and actual loss components, loss positioning can be based on data that is closer to the actual operating state; by comparing and positioning multiple types of evidence separately and in layers, the dominant responsibility category, secondary responsibility category, and pending review status can be output when multiple actual loss causes coexist; by trend observation and closed-loop write-back, slow degradation when the comprehensive line loss rate is still within the qualified range can be detected in advance, and the responsibility label can be verified and updated using the on-site governance results.

[0055] It should be noted that this application uses a method for locating line losses in transformer substations based on data collected from electricity metering boxes as the subject of this description. The main execution entity 105, data access module 110, micro-feature alignment module 120, section power recalculation module 130, loss decomposition module 140, evidence attribution module 150, hierarchical location module 160, trend observation module 170, and anomaly closed-loop module 180 are used to illustrate that this method can be executed by a specific terminal, server, platform, or a combination thereof. The above functional modules can be implemented by hardware circuits, software programs executed by processors, embedded control programs, or functional units in the main station side business system. The data transmitted between the functional modules can include at least the original data frame, time-stamp alignment result, section power difference, pseudo-loss component, actual loss component, responsibility label, review status, and write-back record. The setting of the above execution entity and functional modules should not be construed as a limitation on the specific equipment form or deployment location.

[0056] The node type, acquisition cycle, synchronization time grid, observation window, qualified interval, threshold condition, evidence condition, and output label in the above embodiments can all be configured according to the scale of the transformer substation, communication link quality, acquisition equipment capability, metering equipment level, distributed photovoltaic grid connection ratio, historical operation records, and on-site test results. Different transformer substations can select corresponding data fields, judgment conditions, and processing actions according to their own operating conditions. As long as time-scale alignment, section power recalculation, loss decomposition, responsibility attribution, hierarchical positioning, and closed-loop write-back can be completed based on the data of the power metering box and its upstream and downstream nodes, they are all optional implementation methods disclosed in this application. The scope of protection of this application shall be determined by the claims.

[0057] The above description is merely a specific embodiment of this application, but the scope of protection of this application is not limited thereto. Any variations or substitutions that can be easily conceived by those skilled in the art within the scope of the technology disclosed in this application should be included within the scope of protection of this application. Therefore, the scope of protection of this application should be determined by the scope of the claims.

[0058] In conclusion, the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

Claims

1. A method for locating line loss in a transformer substation based on data collected from an electricity metering box, characterized in that, include: Obtain node-level data for the main meter node, branch nodes, incoming nodes of electricity metering boxes, and household meter nodes in the distribution area, and form a node-level cache according to node roles and upstream and downstream connection relationships; Time-scale alignment is performed based on the micro-feature fingerprints of the reference node curve and the downstream node curve to obtain the time-scale offset and the aligned time series; The aligned time series is resampled according to the synchronous time grid, and the segment power difference of the branch segment, meter box segment and meter segment is recalculated according to the upstream and downstream connection relationship; The pseudo-loss component and the real loss component are determined based on the power difference of the section, the time offset, the transient change amplitude of the electrical quantity, and the physical rationality verification results. The actual loss component is compared with multiple types of causal evidence to obtain the responsibility component and attribution credibility. The link segment location results are output based on the responsibility component and attribution credibility, and written into the responsibility label.

2. The method for locating line loss in a transformer area based on data collected by an energy metering box according to claim 1, characterized in that, The node-level data includes node identifier, node role, collection time or local clock stamp, uploaded batch number, power data and electrical quantity data; The data collected by the electricity metering box is generated by the integrated metering unit on the incoming side of the electricity metering box, the status acquisition unit inside the box, the communication unit inside the box, or the meter group corresponding to the electricity metering box. The data collected by the power metering box includes one or more of the following: three-phase voltage, three-phase current, phase angle, power factor, neutral current, active power, reactive power, reverse active power, open cover status, tilt status, temperature, humidity, communication status, power outage and restoration events, time difference alarms, and uploaded batch number.

3. The method for locating line loss in a transformer area based on data collected by an energy metering box according to claim 1, characterized in that, Time-scale alignment is performed based on the micro-feature fingerprints of the reference node curve and the downstream node curve, including: Using the main node of the transformer area or the upstream branch node as a reference node, extract micro-feature segments representing the same electrical disturbance from the reference node curve; The micro-feature fragments are compared with candidate fragments in the downstream node curves; If the candidate fragment satisfies the similarity threshold, the orientation consistency threshold, and the time range threshold, the candidate fragment is determined as the physical perturbation fragment corresponding to the micro-feature fragment; The timescale offset of the downstream node relative to the reference node is determined based on the time difference between the micro-feature fragment and the physical perturbation fragment.

4. The method for locating line loss in a transformer area based on data collected by an energy metering box according to claim 3, characterized in that, When multiple micro-feature fragments exist within the same time-scale alignment window, multiple candidate time-scale offsets are determined, and the final time-scale offset is selected by combining the historical offset range, the number of corresponding fragments, and the consistency of physical orientation. If no micro-feature fragments satisfying the similarity threshold, direction consistency threshold, and time range threshold are found, the temporary time stamp offset is determined based on the uploaded batch number, the receiving time, the node's local clock stamp, and the most recent valid offset, and the corresponding node is marked as a low-confidence alignment node.

5. The method for locating line loss in a transformer area based on data collected by an energy metering box according to claim 1, characterized in that, Resampling the aligned time series according to the synchronous time grid includes: The active power curve, reactive power curve and reverse active power curve after time-scale alignment are resampled so that the power values ​​of each node correspond to the same grid boundary. For the cumulative power field, the power increment within the grid is determined based on the difference between the cumulative values ​​at the grid start and grid end points; For the power curve, the power is calculated based on the sampling points and sampling intervals within the grid. For reverse active power, retain the direction indicators for both forward and reverse power.

6. The method for locating line loss in a transformer area based on data collected by an energy metering box according to claim 1, characterized in that, The section electricity difference of branch sections, metering box sections, and metering sections is recalculated according to the upstream and downstream connection relationship, including: The section power difference of the branch segment is determined based on the difference between the branch outlet power of the corresponding branch node in the total meter of the distribution area and the downstream total power of the branch node. The section power difference of the metering box section is determined based on the difference between the power output of the corresponding branch node and the power output of the incoming node of the power metering box. The section power difference of the metering segment is determined by the difference between the power consumption at the incoming node of the power metering box and the total power consumption at the household meter nodes inside the power metering box.

7. The method for locating line loss in a transformer area based on data collected by an energy metering box according to claim 1, characterized in that, Determining the pseudo-loss components and the real loss components includes: If the voltage, current, phase angle and neutral current within the current synchronization time grid are in a stable range and the time scale offset is below the offset threshold, the portion of the segment power difference that meets the physical rationality check is determined as the actual loss component. When there are rapid fluctuations within the current synchronization time grid and the time scale offset exceeds the offset threshold, the pseudo loss component is determined based on the offset direction, offset duration, curve change direction, and transient change amplitude of electrical quantity, and the segment power difference after deducting the pseudo loss component is determined as the real loss component to be verified. The physical rationality verification includes energy direction verification, historical load condition verification, and upstream and downstream consistency verification of the link.

8. The method for locating line loss in a transformer area based on data collected by an energy metering box according to claim 1, characterized in that, The actual loss component is compared with multiple types of causal evidence, including: Based on the evidence conditions of line type, metering error type, file mismatch type, photovoltaic type, electricity theft pending verification type and contact anomaly type, the actual loss component, node state quantity, file data, event record and physical rationality verification results are compared; The evidence condition table for each type of trigger includes the trigger field, abnormal amplitude threshold, duration threshold, associated time window, applicable link segment, applicable working condition, exclusion condition, and output label; If the credibility of evidence for any cause category reaches the corresponding threshold, that cause category is identified as a candidate for liability label.

9. A method for locating line loss in a transformer area based on data collected by an energy metering box, as described in claim 8, is characterized in that... When the credibility of evidence for multiple causal categories reaches the corresponding threshold, output the primary liability category and the secondary liability category; If the credibility of evidence for all cause categories fails to reach the corresponding threshold, output an unknown cause label or a label pending verification. Among them, the meter section refers to evidence of metering error, file mismatch, and electricity theft pending verification; the meter box section refers to evidence of abnormal contact, abnormal neutral wire, and temperature and humidity inside the box; and the branch section refers to evidence of line type and photovoltaic type.

10. The method for locating line loss in a transformer substation based on data collected from an energy metering box according to claim 1, characterized in that, Output the link segment location results and write them to the responsibility label, including: The actual loss components of the branch section, meter box section, and meter section, as well as the responsibility components of each inducing factor, are summarized according to the assessment cycle. The criteria for judging anomalies are determined based on the sorting of actual loss components of the link segment, the proportion of responsible components, the historical normal range, and the comparison results of adjacent link segments. If the branch segment meets the abnormal concentration judgment condition, locate the corresponding branch node and its downstream range; If the metering box section within the corresponding branch meets the abnormal concentration judgment conditions, locate the incoming node of the corresponding electricity metering box and the customer meter group inside the box. If the meter section inside the corresponding electricity metering box meets the abnormality concentration judgment conditions, the location is determined to the corresponding household meter node or household meter group.

11. The method for locating line loss in a transformer area based on data collected by an energy metering box according to claim 1, characterized in that, The method further includes: The actual loss curves for the branch section, meter box section, and meter section are generated based on the actual loss components within multiple evaluation periods. When the overall line loss rate is within the acceptable management range, a sliding observation window is selected to align the actual loss curve with the load cycle, seasonal cycle, and historical similar cycles. The trend warning threshold is determined based on the management qualified range, the historical loss fluctuation band under the same load, and the number of times the value rises continuously within the observation window. If the actual loss curve meets the trend warning threshold, output the degradation warning level; For link segments with low-confidence alignment, missing fill ratios exceeding the corresponding thresholds, or physical rationality verification failures, the link segment will be placed in a pending review state or the observation state will be extended.

12. The method for locating line loss in a transformer area based on data collected by an energy metering box according to claim 1, characterized in that, The method further includes: In the event of missing data, measures such as supplementary data collection, temporary filling, link segment blocking, or extending the evaluation period should be implemented. In the event of timescale offset anomalies, perform coarse alignment, use the most recent valid offset, reselect the reference node, or trigger terminal time synchronization verification. If the physical rationality check fails, remove the abnormal meshes, retain the original curves, and output the labels to be reviewed. If the attribution confidence is below the corresponding threshold, extend the observation window, output unknown cause labels, or request manual confirmation. The credibility of the responsibility label is updated based on at least one of the following write-back information: governance work order, file correction, on-site verification results, parameter update, and label self-verification.

Citation Information

Patent Citations

  • Power line loss analysis methods, devices and systems

    CN106992517B

  • An improved method and device for monitoring inaccuracy of electric energy meters in online low-voltage areas

    CN117851908B