Air conditioning load cluster control system based on power regulation
By generating orthogonal power identification sequences and verifying execution status, the problem of inaccurate response identification in the air conditioning load cluster control system is solved, and accurate adjustment and dynamic capacity management of the air conditioning load cluster are realized.
Patent Information
- Application Number
- CN202611342138.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-01
- Publication Date
- 2026-11-24
AI Technical Summary
Existing air conditioning load cluster control systems struggle to identify the actual response of each control group from the aggregated power of the distribution branches, resulting in inaccurate determination of adjustable capacity and an inability to promptly redistribute unadjusted power when the control group fails to effectively execute load control commands.
By generating mutually orthogonal power identification sequences with zero cross-correlation within a preset response delay range, converting them into identification control commands, collecting and matching aggregated power change sequences, verifying the execution reliability status, and reallocating the unfinished regulation power.
It enables accurate response identification and dynamic capacity determination for each control group, improves the accuracy, continuity and reliability of air conditioning load cluster regulation, and solves the power redistribution problem when the control group fails to execute.
Smart Images

Figure CN123162908A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of air conditioning load control technology, specifically to an air conditioning load cluster control system based on power regulation. Background Technology
[0002] With the increasing peak-to-valley difference in the power grid and the rising proportion of renewable energy integration, air conditioning loads, due to their large number, fast response speed, and thermal energy storage characteristics, are gradually becoming an important regulatory resource for demand response. By grouping and controlling air conditioning load clusters and allocating power according to the power grid's target regulation power, support can be provided for power grid peak shaving and power balance.
[0003] Existing air conditioning load cluster control mainly relies on rated power, historical models, or terminal feedback to estimate adjustable capacity. It is difficult to distinguish the actual response of each control group from the aggregated power of the common distribution branch. When the control terminal communication is abnormal or the air conditioner does not execute the command, problems such as distorted capacity estimation, ineffective power allocation, and failure to complete the grid target power adjustment are likely to occur.
[0004] Therefore, this application proposes an air conditioning load cluster control system based on power regulation that can identify the actual response of each control group from the aggregated power change, verify the execution reliability state, and redistribute the unregulated power. Summary of the Invention
[0005] The purpose of this invention is to provide an air conditioning load cluster control system based on power regulation, in order to solve the technical problems mentioned in the background art, namely, that existing air conditioning load cluster control systems are unable to identify the actual response of each control group from the aggregated power of the distribution branch, resulting in inaccurate determination of adjustable capacity, and are unable to redistribute the unregulated power in a timely manner when the control group fails to effectively execute the load control command.
[0006] To achieve the above objectives, the present invention provides the following technical solution: an air conditioning load cluster control system based on power regulation, comprising: Adjustment sequence generation module: Based on the power grid target adjustment power, the air conditioning load cluster is grouped to obtain each control group, and a power identification sequence that is mutually orthogonal and has zero cross-correlation within a preset response time delay range is generated for each control group. The power identification sequence is then converted into the identification control command of the corresponding control group. Aggregated power acquisition module: Acquires aggregated power of the distribution branch supplying power to the air conditioning load cluster before and during the execution of identification control commands, forming an aggregated power change sequence; Physical execution verification module: Within the preset response delay range, each power identification sequence is matched with the aggregated power change sequence. The response power of each control group is extracted based on the relevant peak value. When the absolute value of the relevant peak value reaches the execution threshold, the corresponding control group is marked as the execution trust state, and the absolute value of the response power is determined as the adjustable capacity of the corresponding control group. Power redistribution module: Allocates grid target regulating power according to the adjustable capacity of control groups in the execution trusted state and issues load control commands. When the relevant peak value corresponding to any control group does not reach the execution threshold, the uncompleted regulating power corresponding to the control group is redistributed to the other control groups in the execution trusted state.
[0007] Preferably, the specific process of grouping the air conditioning load clusters is as follows: The terminal identifier, rated input power, and control availability status of each air conditioning load in the air conditioning load cluster are obtained. The control availability status is used to characterize whether the air conditioning load can receive and execute identification control commands. Air conditioning loads with control availability status that are controllable are selected and grouped according to the principle of balanced rated input power, so that the deviation between the total rated input power of each control group is within the preset grouping deviation threshold, and a control group identifier is configured for each control group.
[0008] Preferably, the specific process of generating power identification sequences for each control group is as follows: The sequence length and zero-correlation region width of the power identification sequence are determined based on the number of control groups and the preset response delay range. A sequence matrix with a number of rows not less than the number of control groups is constructed. Row vectors corresponding to each control group are selected from the sequence matrix. Power identification sequences for each control group are generated according to the order of sequence elements in the row vectors. The autocorrelation value of any power identification sequence is zero except for zero time offset in the zero-correlation region, and the cross-correlation value of any two power identification sequences in the zero-correlation region is zero.
[0009] Preferably, the specific process of converting the power identification sequence into the identification control command of the corresponding control group is as follows: According to the arrangement order of each sequence element in the power identification sequence, corresponding instruction time slots are set for each control group. The power adjustment direction within the corresponding instruction time slot is determined according to the symbol of the sequence element, and the target power change is determined in combination with the preset identification amplitude. The control group identifier, execution time, duration and target power change are encapsulated into an identification control instruction and sent to the corresponding control group, so that each control group can synchronously adjust the air conditioning operating frequency and start / stop permission status according to the instruction time slot within the same identification cycle.
[0010] Preferably, the specific process for forming the polymerization power change sequence is as follows: Before the control command is executed, the aggregated power of the distribution branch supplying power to the air conditioning load cluster is collected to determine the reference power. According to the sampling interval corresponding to the command time slot, the aggregated power during the execution of the control command is collected. The difference between the collected aggregated power and the reference power is calculated and arranged in the order of sampling time to form an aggregated power change sequence.
[0011] Preferably, the specific process of performing correlation matching between each power identification sequence and the aggregated power change sequence is as follows: Each power identification sequence and the aggregated power change sequence are initially aligned according to the execution time of the identification control command. Within a preset response delay range limited by the width of the zero correlation region, the time correspondence positions of the power identification sequence and the aggregated power change sequence are changed sequentially according to the sampling interval to compensate for the time delay between the identification control command and the aggregated power response. At each time correspondence position, the power identification sequence element and the aggregated power change sequence element corresponding to the time are multiplied and accumulated to obtain the multiplicative sum. The sum of squares of each sequence element in the power identification sequence is calculated to obtain the sequence energy. The ratio of the multiplicative sum to the sequence energy is determined as the correlation power value at the corresponding time position. The correlation power value with the largest absolute value is selected from each correlation power value as the correlation peak value, and the absolute value of the correlation peak value is taken as the response power of the corresponding control group.
[0012] Preferably, the specific process of marking the corresponding control group as having a trusted execution state is as follows: Based on the aggregated power of the distribution branch before the control command is executed, the power fluctuation amplitude of the distribution branch is obtained. Combined with the measurement error of the aggregated power acquisition module, the execution threshold is determined. The absolute value of the relevant peak value corresponding to each control group is compared with the execution threshold. If the relevant peak value reaches the execution threshold, the corresponding control group is marked as a reliable execution state. If the relevant peak value does not reach the execution threshold, the corresponding control group is marked as an unreliable execution state.
[0013] Preferably, the specific process of determining the response power as the adjustable capacity of the corresponding control group is as follows: Extract the response power corresponding to the control group in the trusted execution state, determine the absolute value of the response power as the adjustable capacity of the corresponding control group, associate and store the adjustable capacity with the group identifier, power adjustment direction and acquisition time of the corresponding control group, and update the adjustable capacity with the re-extracted response power after the corresponding control group executes the identification control command again.
[0014] Preferably, the specific process of allocating the target regulating power of the power grid and issuing load control commands is as follows: The adjustable capacity of control groups that are consistent with the adjustment direction of the grid target adjustment power and are in a reliable execution state is summarized to obtain the cluster adjustable capacity. When the cluster adjustable capacity is not less than the grid target adjustment power, the grid target adjustment power is allocated according to the proportion of the adjustable capacity of each control group to the cluster adjustable capacity, and the adjustment power allocated to each control group does not exceed the corresponding adjustable capacity. Load control instructions are generated based on the control group identifier, the allocated adjustment power, the power adjustment direction and the execution period, and the load control instructions are sent to the corresponding control group.
[0015] Preferably, the specific process of redistributing the incompletely regulated power is as follows: After the load control command is executed, the aggregated power change sequence is re-formed, and physical execution verification is performed on each control group. When the absolute value of the relevant peak value corresponding to any control group does not reach the execution threshold, the control group is marked as an untrusted execution state, the regulation power allocated to the control group is determined as the uncompleted regulation power, and the current load control command is stopped from being issued to the control group. The remaining adjustable capacity is determined based on the difference between the adjustable capacity and the allocated regulation power of the other control groups in the trusted execution state. The uncompleted regulation power is redistributed according to the remaining adjustable capacity, the corresponding load control command is updated, and physical execution verification is performed again on the updated load control command.
[0016] Compared with the prior art, the beneficial effects of the present invention are: 1. This invention obtains the terminal identifier, rated input power, and controllable availability status of each air conditioning load, filters controllable air conditioning loads and evenly divides them into control groups, generates mutually orthogonal power identification sequences for each control group with zero cross-correlation in the zero correlation region, and converts them into synchronously executed identification control commands. This enables the configuration of mutually distinguishable power response characteristics for different control groups, solves the problem that the common power distribution branch can only reflect the total power of the air conditioning load cluster and is difficult to distinguish the actual response of each control group, and provides a reliable basis for subsequently identifying the physical response of each control group from the aggregated power. 2. This invention determines the reference power by collecting the aggregated power of the distribution branch before the identification control command is executed, and collects the aggregated power during the execution period according to the sampling interval corresponding to the command time slot. The collected aggregated power is subtracted from the reference power and arranged sequentially, thus forming an aggregated power change sequence corresponding to the power identification sequence time. This solves the problem that after each control group executes the identification control command synchronously, stable power consumption, natural start-stop of air conditioning, and measurement errors are mixed into the collected results, causing the power response characteristics to be masked. It reduces the influence of fixed power components on response identification and improves the effectiveness of aggregated power data. 3. This invention achieves physical verification of the reliable state and adjustable capacity of each control group by performing correlation matching between each power identification sequence and the aggregated power change sequence within a preset response delay range, extracting the response power of each control group based on the correlation peak, and determining the execution threshold by combining the power fluctuation amplitude and measurement error of the distribution branch. This solves the problem that after the aggregated power change sequence is formed, the responses of each control group are still superimposed and there is a response delay, making it difficult to determine the source of the response and whether the response is real and effective. It can accurately identify the control group that actually performs the control and dynamically determine the adjustable capacity based on the actual response. 4. This invention allocates the target regulation power of the power grid according to the adjustable capacity of the control group in the trusted execution state, performs physical execution verification again after the load control command is executed, and redistributes the unfinished regulation power of the untrusted control group according to the remaining adjustable capacity. This realizes the closed-loop allocation and dynamic compensation of the target regulation power of the power grid, solves the problem that the control group may still be unable to complete the allocated regulation power due to communication interruption, change of operating status or command execution failure after the initial physical verification is completed, avoids invalid control groups from continuously occupying regulation tasks, and improves the regulation accuracy, continuity and reliability of air conditioning load clusters. Attached Figure Description
[0017] Figure 1 This is a flowchart of the modules of the present invention; Figure 2 This is a flowchart of the power allocation process of the present invention. Detailed Implementation
[0018] Please see Figure 1 and Figure 2 The present invention provides an embodiment of an air conditioning load cluster control system based on power regulation, comprising a regulation sequence generation module, which groups the air conditioning load cluster according to the power grid target regulation power to obtain each control group, generates mutually orthogonal power identification sequences for each control group and cross-correlation of zero within a preset response delay range, and converts the power identification sequences into identification control commands for the corresponding control group. Furthermore, in the adjustment sequence generation module, the specific process of grouping the air conditioning load cluster is as follows: obtain the terminal identifier, rated input power and control availability status of each air conditioning load. The terminal identifier is obtained from the equipment registration information generated when the air conditioning load is connected to the system. The rated input power is obtained from the air conditioning nameplate data or equipment file. The control availability status is determined based on the most recent communication heartbeat and instruction reception feedback of the air conditioning control terminal. When the air conditioning control terminal can establish a communication connection and return instruction reception feedback, the control availability status of the corresponding air conditioning load is determined to be controllable. Otherwise, it is determined to be uncontrollable. Air conditioning loads in the controllable state are screened and grouped according to the rated input power balance principle. In the adjustment sequence generation module, the specific process of grouping according to the principle of balanced rated input power is as follows: the number of control groups is determined based on the grid target adjustment power, the number of controllable air conditioning loads, and the number of available power identification sequences. The selected controllable air conditioning loads are arranged from largest to smallest according to their rated input power, and a corresponding number of empty control groups are established. The air conditioning loads are selected in sequence according to the arrangement order. The currently selected air conditioning load is assigned to the control group with the smallest total rated input power. The total rated input power of the control group is updated after each allocation. When the total rated input power of two or more control groups is the same, the allocation is carried out according to the arrangement order of the control group identifiers. Let the total rated input power of the g-th control group be P. g The control group includes m air conditioning loads, and the rated input power of each air conditioning load is p1 to p... m ,but: P g =p1+p2+...+p m ; Let P be the total maximum rated input power in each control group. 大 The minimum rated total input power is P 小 The average of the total rated input power of each control group is P. 均 If the total deviation of the rated input power of each control group is D, then: D = (P) 大 -P 小 ) / P 均 ; Set the preset grouping deviation threshold to 10%. When D is not greater than 10%, determine that each control group meets the rated input power balance requirement, complete the grouping of the air conditioning load cluster, and configure different control group identifiers for each control group. When D is greater than 10%, readjust the air conditioning load in each control group until D is not greater than 10%. In the adjustment sequence generation module, the specific process of generating the power identification sequence is as follows: During the system installation and commissioning phase, a test command is sent to the air conditioning load, and the time interval from the execution time of the test command to the corresponding change in the aggregated power of the distribution branch is recorded to obtain the historical response delay. The maximum response delay in the valid test record is recorded as T. max Let t be the length of the instruction time slot and z be the number of time slots corresponding to the preset response delay. Then: z=T max / t; The calculation result is rounded up. To ensure that different control groups can still be separated from the same aggregate power change sequence despite different response delays, the width of the zero correlation region is denoted as w. Then: w=2z; The sequence length L is determined based on the number of control groups, the number of time slots z corresponding to the preset response delay, and the width w of the zero correlation region. A sequence matrix is constructed, and row vectors corresponding to each control group are selected from the sequence matrix. The i-th and j-th power identification sequences are denoted as s. i and s j Let the time offset be denoted as d, and s i With s j The correlation value at time offset d is denoted as R. ij (d), then: R ij (d) = s i (1) ×s j (1-d)+s i(2) ×s j (2-d) + ... + s i (L)×s j (Ld); The sequence elements in the power identification sequence are numbered cyclically, and when the position of a sequence element exceeds the end of the sequence, it returns to the beginning of the sequence. When i equals j and d equals 0, R ij (d) = L; When i equals j and 0 < |d| ≤ w, R ij (d) = 0; When i is not equal to j and |d| ≤ w, R ij (d) = 0; The inner product of the different power identification sequences is zero at zero time offset, and the cross-correlation remains zero in the zero correlation region; In the adjustment sequence generation module, the specific process of converting the power identification sequence into identification control instructions is as follows: set corresponding instruction time slots according to the arrangement order of each sequence element, assign sequence element 1 to increase the air conditioner input power, assign sequence element -1 to decrease the air conditioner input power, and multiply the sequence element by the preset identification amplitude to obtain the target power change within the corresponding instruction time slot. Encapsulate the control group identifier, execution time, duration, and target power change into identification control instructions so that each control group can synchronously adjust the air conditioner operating frequency and start / stop permission status within the same identification cycle. The number of 1 and -1 in each power identification sequence is consistent, which is used to reduce the continuous impact of the identification process on the average power consumption of the air conditioner and the indoor temperature. For example, the power grid dispatch interface issues a target power reduction of 1.8kW. The air conditioning load cluster includes 13 air conditioners, one of which is determined to be uncontrollable due to a communication heartbeat timeout. The rated input power of the remaining 12 air conditioners is 5kW each. The 12 controllable air conditioners are divided into three control groups: G1, G2, and G3. Each control group includes 4 air conditioners, and the total rated input power of each group is 20kW. Therefore, D equals 0, and the maximum response delay T in the installation and commissioning record is 0.max If the instruction time slot length is 42 seconds and the instruction time slot length t is 60 seconds, then: z = 42 / 60, the result is rounded up to 1; w = 2 × 1 = 2; The power identification sequence has a sequence length L of 16, and the power identification sequences corresponding to the three control groups are as follows: G1: (1,-1,-1,-1,-1,1,-1,-1,1,-1,1,1,-1,1,1,1); G2: (1,-1,-1,-1,1,-1,1,1,1,-1,1,1,1,-1,-1,-1); G3: (1, 1, -1, 1, -1, -1, -1, 1, 1, 1, 1, -1, -1, -1, 1, -1); The aforementioned power identification sequence satisfies autocorrelation and cross-correlation conditions within a time offset of -2 to 2 command time slots. The preset identification amplitude is 2kW, which is determined based on the allowable short-term adjustment margin of the air conditioning load and the allowable power fluctuation range of the distribution branch. Each control group executes the corresponding identification control command synchronously at the same execution time and the same command time slot, thereby providing distinguishable power characteristics for separating the actual response of each control group from the aggregated power of the distribution branch.
[0019] Please see Figure 1 and Figure 2 The present invention provides an embodiment of an air conditioning load cluster control system based on power regulation, comprising an aggregated power acquisition module, which acquires the aggregated power of the power distribution branch supplying power to the air conditioning load cluster before and during the execution of the identification control command, forming an aggregated power change sequence; Furthermore, in the aggregated power acquisition module, the power distribution branch refers to the power distribution branch located on the common power supply path of each control group. That is, the power consumption of G1, G2 and G3 all pass through this power distribution branch. The aggregated power acquisition module is set at the common metering location of this power distribution branch, and the aggregated power of the air conditioning load cluster is obtained by the same power acquisition device, without the need to set up power acquisition devices in each control group separately. Before the identification control command is executed, the aggregated power of the distribution branch is continuously collected according to the preset sampling interval. The number of aggregated power samples obtained before execution is recorded as M, and each aggregated power sample is recorded as P. b (1) to P b (M), let the reference power be P0, then: P0=[P b (1) +P b (2) +...+P b (M)] / M; The average value of multiple aggregated power samples before execution is used as the reference power to reduce the impact of single measurement error and instantaneous power fluctuations caused by natural start-stop of air conditioning on the reference power. The metering clock of the power acquisition device is kept consistent with the execution clock of the identification control command, and the sampling interval corresponds to the command time slot, so that each aggregated power sample can correspond to a command time slot. During the execution of the identification control command, the aggregated power is recorded in the order of sampling time. The aggregated power collected in the nth command time slot is denoted as P(n), and the change in aggregated power in the nth command time slot is denoted as y(n). Then: y(n) = P(n) - P0; All aggregated power change values are arranged sequentially according to the sampling time to form an aggregated power change sequence. The aggregated power change sequence includes the power response generated by each control group executing the identification control command, as well as the power disturbance caused by the natural start and stop of the air conditioner, other load changes, and acquisition errors. Since each control group uses different power identification sequences with zero correlation zones, the response power of the corresponding control group can be extracted from the aggregated power change sequence through correlation matching. For example, before the three control groups execute the identification control command, the power acquisition device continuously acquires five aggregated power samples, which are 44.8kW, 45.1kW, 44.9kW, 45.0kW, and 45.2kW, respectively. Then: P0=(44.8+45.1+44.9+45.0+45.2) / 5=45.0kW; The aggregated power samples are directly sourced from the power acquisition devices at the common metering locations of the distribution branches. When the three control groups execute a power identification sequence of length 16, G1 generates a 1.8kW response with a response delay of 0 command time slots, G2 generates a 1.5kW response with a response delay of 1 command time slot, and G3 generates a 0.2kW response with a response delay of 0 command time slots. Therefore: y(n)=1.8×s1(n)+1.5×s2(n-1)+0.2×s3(n); The aggregated power collected sequentially from the distribution branches is as follows: (45.5, 44.9, 41.5, 41.9, 41.5, 48.1, 41.5, 44.9, 48.5, 44.9, 45.5, 48.1, 44.5, 48.1, 45.5, 45.1)kW; Subtract the baseline power of 45.0 kW from the polymerization power to form a sequence of polymerization power changes: (0.5, -0.1, -3.5, -3.1, -3.5, 3.1, -3.5, -0.1, 3.5, -0.1, 0.5, 3.1, -0.5, 3.1, 0.5, 0.1) kW; The aggregated power of the distribution branch is converted into an aggregated power variation sequence that varies around the reference power, thereby reducing the impact of stable power consumption on the relevant matching results.
[0020] Please see Figure 1 and Figure 2 The present invention provides an embodiment of an air conditioning load cluster control system based on power regulation, including a physical execution verification module. Within a preset response delay range, the physical execution verification module performs correlation matching between each power identification sequence and the aggregated power change sequence, extracts the response power of each control group based on the correlation peak value, and marks the corresponding control group as a reliable execution state when the absolute value of the correlation peak value reaches the execution threshold, and determines the absolute value of the response power as the adjustable capacity of the corresponding control group. Furthermore, in the physical execution verification module, the first sequence element of the power identification sequence is initially aligned with the first sequence element of the aggregated power change sequence according to the execution time of the identification control command. Then, within the preset response delay range limited by the width of the zero correlation zone, the time correspondence positions of the power identification sequence and the aggregated power change sequence are changed sequentially according to the sampling interval. Changing the time correspondence position is used to compensate for the time delay caused by the air conditioning control terminal receiving the command, the air conditioning changing its operating state, and the power response of the power distribution branch, without changing the original arrangement order of each sequence element in the power identification sequence. Let the i-th power identification sequence be s. i , will s i The sequence energy is denoted as E. i ,but: E i =s i (1) 2 +s i (2) 2 +...+s i (L) 2 ; s i The relevant power value at time offset d is denoted as C. i (d), then: C i (d) = [s i (1-d)×y(1)+s i (2-d)×y(2)+...+s i [(Ld)×y(L)] / E i ; Calculate the correlation power values for d from -z to z, and denote the maximum absolute value of each correlation power value as H. i and H iAs the response power of the corresponding control group, since the sequence energy is used to normalize the multiplicative summation, the relevant power value and the response power have the same power unit and can be directly used to determine the adjustable capacity. In the physical execution verification module, the execution threshold is determined based on the power fluctuation amplitude of the distribution branch and the measurement error of the power acquisition device before the identification control command is executed. Let F be the power fluctuation amplitude before the identification control command is executed, e be the measurement error of the power acquisition device, and T be the execution threshold. Then: T = F + e; Where F is the maximum value among the absolute values of the difference between each aggregated power sample and the reference power before execution, and e is determined according to the accuracy level, range and calibration record of the power acquisition device. When Hi is not less than T, it indicates that there is a physical power response in the aggregated power change sequence that matches the corresponding power identification sequence, and the corresponding control group is marked as a reliable execution state. When Hi is less than T, it indicates that the extracted response power does not exceed the natural power fluctuation and measurement error of the distribution branch, and the corresponding control group is marked as an unreliable execution state. For control groups in a reliable execution state, the absolute value of the relevant peak value is determined as the adjustable capacity of the corresponding control group. The adjustable capacity is then associated with and stored in relation to the control group identifier, power adjustment direction, and acquisition time. The adjustable capacity of the i-th control group is denoted as Q. i ,but: Q i =H i ; When the corresponding control group executes the identification control command again, Q is updated using the re-extracted response power. i This allows the adjustable capacity to be updated according to changes in the air conditioning's operating status and environmental conditions; For example, the sequence length L is 16, and each sequence element is either 1 or -1. Therefore, the sequence energy of each power identification sequence is: E i =1 2 +1 2 +...+1 2 =16; The preset response delay is -1 to 1 command time slot. Correlation matching is performed when d equals -1, 0, and 1 respectively. The aggregated power change sequence is calculated, and the three correlation power values of G1 are 0, 1.8kW, and 0, respectively. The three correlation power values of G2 are 0, 0, and 1.5kW, respectively. The three correlation power values of G3 are 0, 0.2kW, and 0, respectively. Therefore, the response delay of G1 is 0 command time slots and the response power is 1.8kW, the response delay of G2 is 1 command time slot and the response power is 1.5kW, and the response power of G3 is 0.2kW. The maximum deviation of the aggregated power sample from the reference power of 45.0kW before execution is 0.2kW, therefore F is 0.2kW. Based on the accuracy class of the power acquisition device and the current range, the measurement error e is determined to be 0.1kW. Therefore: T = 0.2 + 0.1 = 0.3 kW; The absolute values of the relevant peak values of G1 and G2 both reach the execution threshold, and are marked as execution reliable states, respectively. The adjustable capacities of G1 and G2 are determined to be 1.8kW and 1.5kW, respectively. The absolute value of the relevant peak value of G3 is less than the execution threshold, and G3 is marked as execution unreliable state. It does not participate in the allocation of the target power regulation of the power grid. It can verify whether each control group has generated a physical response based on the actual power change of the common distribution branch without obtaining the independent power measurement values of each control group.
[0021] Please see Figure 1 and Figure 2 The present invention provides an embodiment of an air conditioning load cluster control system based on power regulation, including a power redistribution module. The power redistribution module allocates the grid target regulation power according to the adjustable capacity of the control group in the execution trust state and issues load control commands. When the relevant peak value corresponding to any control group does not reach the execution threshold, the unfinished regulation power corresponding to the control group is redistributed to the other control groups in the execution trust state. Furthermore, in the power redistribution module, control groups whose power adjustment direction is consistent with the grid's target adjustment power and are in a reliable execution state are selected. The number of control groups in a reliable execution state is denoted as k, and the adjustable capacity of the i-th control group is denoted as Q. i Let Q be the adjustable capacity of the cluster. 总 ,but: Q 总 =Q1+Q2+...+Q k ; Let the target regulation power of the power grid be denoted as P. 目 When Q 总 Not less than P 目 At that time, the target regulating power of the power grid is allocated according to the proportion of the adjustable capacity of each control group to the total adjustable capacity of the cluster. The regulating power allocated to the i-th control group is denoted as A. i ,but: A i =P 目 ×Q i / Q 总 ; Among them, A i No more than Q i According to the control group identifier, A iThe system generates load control commands based on the power adjustment direction and execution period, and sends these commands to the corresponding control group. This allows the control group to adjust the air conditioning operating frequency and start / stop permission status to perform the corresponding power adjustment. The system uses adjustable capacity obtained through physical execution verification for allocation, avoiding the issuance of load control commands that exceed the current execution capacity of the control group based on the rated input power or historical estimated capacity. During the verification period after the load control command is executed, the system makes the corresponding control group execute the identification control command again, re-form the aggregated power change sequence and perform relevant matching. If the absolute value of the relevant peak value of any control group is less than the execution threshold, the control group is updated to the execution untrusted state, the current load control command is stopped from being issued to the control group, and the regulation power that has been allocated to the control group is determined as the incomplete regulation power. For the remaining control groups in the trusted execution state, the remaining adjustable capacity of the i-th control group is denoted as B. i ,but: B i =Q i -A i ; According to the proportion of the remaining adjustable capacity of each control group to the total remaining adjustable capacity, the unfinished adjustment power is redistributed, and it is ensured that the adjustment power after redistribution does not exceed the adjustable capacity of the corresponding control group. After the redistribution is completed, the corresponding load control command is updated, and physical execution verification is performed again, thus forming a closed-loop control process of power allocation, physical verification, failure elimination and power redistribution. For example, the target regulation power P of the power grid 目 To reduce the power consumption by 1.8kW, assuming G1 and G2 are in a trusted execution state, with corresponding adjustable capacities of 1.8kW and 1.5kW respectively, then: Q 总 =1.8 + 1.5 = 3.3 kW; The initial allocation adjustment powers corresponding to G1 and G2 are as follows: A1 = 1.8 × 1.8 / 3.3 = 0.98 kW; A2 = 1.8 × 1.5 / 3.3 = 0.82 kW; The system issues a load control command to G1 to reduce load by 0.98kW and to G2 to reduce load by 0.82kW. After the load control commands are executed, a communication interruption occurs at the air conditioning control terminal of G2. The re-extracted absolute value of the relevant peak value of G2 is 0.1kW, which is less than the execution threshold of 0.3kW. Therefore, G2 is marked as an unreliable execution state, and the 0.82kW allocated to G2 is determined as the unregulated power. At this time, the remaining adjustable capacity of G1 is: B1 = 1.8 - 0.98 = 0.82 kW; The remaining adjustable capacity of G1 equals the unregulated power. Therefore, 0.82kW is redistributed to G1, and the load control command of G1 is updated from a reduction of 0.98kW to a reduction of 1.80kW. The updated load control command does not exceed the adjustable capacity of G1. After another physical execution verification, the absolute value of the relevant peak value of G1 reaches the execution threshold, and it is confirmed that the distribution branch has completed the target power reduction of 1.8kW. Thus, even if G2 does not actually execute the load control command, the system can identify the failed control group based on the physical power response of the common distribution branch, and use the remaining adjustable capacity of the other control groups in the reliable execution state to compensate for the unregulated power.
[0022] Working principle: The system receives the target regulation power of the power grid, obtains the terminal identifier, rated input power and control availability status of each air conditioning load, filters controllable air conditioning loads and divides them equally into control groups. The regulation sequence generation module generates mutually orthogonal power identification sequences with zero cross-correlation in the zero correlation region according to the number of control groups and the preset response delay range. The power identification sequence is converted into identification control command so that each control group executes synchronously within the same identification period. The aggregated power acquisition module collects and identifies the aggregated power of the distribution branches before and during the execution of control commands. It forms an aggregated power change sequence based on the reference power. The physical execution verification module performs correlation matching between each power identification sequence and the aggregated power change sequence. It extracts the response power based on the relevant peak values and marks the control group whose absolute value of the relevant peak value reaches the execution threshold as a reliable execution state. The absolute value of the response power is determined as the adjustable capacity. The power redistribution module allocates the grid target adjustment power according to the adjustable capacity and issues load control commands. After the load control commands are executed, physical execution verification is performed again. When the absolute value of the relevant peak value of any control group does not reach the execution threshold, the control group is marked as an unreliable execution state, the current load control command is stopped, and the corresponding unfinished adjustment power is redistributed to the remaining control groups in the reliable execution state according to the remaining adjustable capacity, thus completing the closed-loop power adjustment of the air conditioning load cluster.
[0023] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the invention can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. Therefore, the embodiments should be considered in all respects as exemplary and non-limiting, and the scope of the invention is defined by the appended claims rather than the foregoing description. Thus, it is intended that all variations falling within the meaning and scope of equivalents of the claims be included within the present invention.
Claims
1. A power-regulated air conditioning load cluster control system, characterized in that: include: Adjustment sequence generation module: Based on the power grid target adjustment power, the air conditioning load cluster is grouped to obtain each control group, and a power identification sequence that is mutually orthogonal and has zero cross-correlation within a preset response time delay range is generated for each control group. The power identification sequence is then converted into the identification control command of the corresponding control group. Aggregated power acquisition module: Acquires aggregated power of the distribution branch supplying power to the air conditioning load cluster before and during the execution of identification control commands, forming an aggregated power change sequence; Physical execution verification module: Within the preset response delay range, each power identification sequence is matched with the aggregated power change sequence. The response power of each control group is extracted based on the relevant peak value. When the absolute value of the relevant peak value reaches the execution threshold, the corresponding control group is marked as the execution trust state, and the absolute value of the response power is determined as the adjustable capacity of the corresponding control group. Power redistribution module: Allocates grid target regulating power according to the adjustable capacity of control groups in the execution trusted state and issues load control commands. When the relevant peak value corresponding to any control group does not reach the execution threshold, the uncompleted regulating power corresponding to the control group is redistributed to the other control groups in the execution trusted state.
2. The air conditioning load cluster control system based on power regulation according to claim 1, characterized in that: The specific process for grouping air conditioning load clusters is as follows: The terminal identifier, rated input power, and control availability status of each air conditioning load in the air conditioning load cluster are obtained. The control availability status is used to characterize whether the air conditioning load can receive and execute identification control commands. Air conditioning loads with control availability status that are controllable are selected and grouped according to the principle of balanced rated input power, so that the deviation between the total rated input power of each control group is within the preset grouping deviation threshold, and a control group identifier is configured for each control group.
3. The air conditioning load cluster control system based on power regulation according to claim 2, characterized in that: The specific process for generating power identification sequences for each control group is as follows: The sequence length and zero-correlation region width of the power identification sequence are determined based on the number of control groups and the preset response delay range. A sequence matrix with a number of rows not less than the number of control groups is constructed. Row vectors corresponding to each control group are selected from the sequence matrix. Power identification sequences for each control group are generated according to the order of sequence elements in the row vectors. The autocorrelation value of any power identification sequence is zero except for zero time offset in the zero-correlation region, and the cross-correlation value of any two power identification sequences in the zero-correlation region is zero.
4. The air conditioning load cluster control system based on power regulation according to claim 3, characterized in that: The specific process of converting the power identification sequence into the corresponding control group identification control command is as follows: According to the arrangement order of each sequence element in the power identification sequence, corresponding instruction time slots are set for each control group. The power adjustment direction within the corresponding instruction time slot is determined according to the symbol of the sequence element, and the target power change is determined in combination with the preset identification amplitude. The control group identifier, execution time, duration and target power change are encapsulated into an identification control instruction and sent to the corresponding control group, so that each control group can synchronously adjust the air conditioning operating frequency and start / stop permission status according to the instruction time slot within the same identification cycle.
5. The air conditioning load cluster control system based on power regulation according to claim 1, characterized in that: The specific process for forming the polymerization power change sequence is as follows: Before the control command is executed, the aggregated power of the distribution branch supplying power to the air conditioning load cluster is collected to determine the reference power. According to the sampling interval corresponding to the command time slot, the aggregated power during the execution of the control command is collected. The difference between the collected aggregated power and the reference power is calculated and arranged in the order of sampling time to form an aggregated power change sequence.
6. The air conditioning load cluster control system based on power regulation according to claim 1, characterized in that: The specific process of performing correlation matching between each power identification sequence and the aggregated power change sequence is as follows: Each power identification sequence and the aggregated power change sequence are initially aligned according to the execution time of the identification control command. Within a preset response delay range limited by the width of the zero correlation region, the time correspondence positions of the power identification sequence and the aggregated power change sequence are changed sequentially according to the sampling interval to compensate for the time delay between the identification control command and the aggregated power response. At each time correspondence position, the power identification sequence element and the aggregated power change sequence element corresponding to the time are multiplied and accumulated to obtain the multiplicative sum. The sum of squares of each sequence element in the power identification sequence is calculated to obtain the sequence energy. The ratio of the multiplicative sum to the sequence energy is determined as the correlation power value at the corresponding time position. The correlation power value with the largest absolute value is selected from each correlation power value as the correlation peak value, and the absolute value of the correlation peak value is taken as the response power of the corresponding control group.
7. The air conditioning load cluster control system based on power regulation according to claim 1, characterized in that: The specific process of marking the corresponding control group as having a trusted execution state is as follows: Based on the aggregated power of the distribution branch before the control command is executed, the power fluctuation amplitude of the distribution branch is obtained. Combined with the measurement error of the aggregated power acquisition module, the execution threshold is determined. The absolute value of the relevant peak value corresponding to each control group is compared with the execution threshold. If the relevant peak value reaches the execution threshold, the corresponding control group is marked as a reliable execution state. If the relevant peak value does not reach the execution threshold, the corresponding control group is marked as an unreliable execution state.
8. The air conditioning load cluster control system based on power regulation according to claim 6, characterized in that: The specific process of determining the response power as the adjustable capacity of the corresponding control group is as follows: Extract the response power corresponding to the control group in the trusted execution state, determine the absolute value of the response power as the adjustable capacity of the corresponding control group, associate and store the adjustable capacity with the group identifier, power adjustment direction and acquisition time of the corresponding control group, and update the adjustable capacity with the re-extracted response power after the corresponding control group executes the identification control command again.
9. A power-regulated air conditioning load cluster control system according to claim 1, characterized in that: The specific process of allocating the target regulating power of the power grid and issuing load control commands is as follows: The adjustable capacity of control groups that are consistent with the adjustment direction of the grid target adjustment power and are in a reliable execution state is summarized to obtain the cluster adjustable capacity. When the cluster adjustable capacity is not less than the grid target adjustment power, the grid target adjustment power is allocated according to the proportion of the adjustable capacity of each control group to the cluster adjustable capacity, and the adjustment power allocated to each control group does not exceed the corresponding adjustable capacity. Load control instructions are generated based on the control group identifier, the allocated adjustment power, the power adjustment direction and the execution period, and the load control instructions are sent to the corresponding control group.
10. A power-regulated air conditioning load cluster control system according to claim 1, characterized in that: The specific process of redistributing the incomplete regulated power is as follows: After the load control command is executed, the aggregated power change sequence is re-formed, and physical execution verification is performed on each control group. When the absolute value of the relevant peak value corresponding to any control group does not reach the execution threshold, the control group is marked as an untrusted execution state, the regulation power allocated to the control group is determined as the uncompleted regulation power, and the current load control command is stopped from being issued to the control group. The remaining adjustable capacity is determined based on the difference between the adjustable capacity and the allocated regulation power of the other control groups in the trusted execution state. The uncompleted regulation power is redistributed according to the remaining adjustable capacity, the corresponding load control command is updated, and physical execution verification is performed again on the updated load control command.