Pumped storage power station emergency resource dynamic collaborative scheduling method and system

By constructing an emergency resource scheduling knowledge graph and using multi-objective constraint optimization, the problem of static and dynamic disconnect in emergency resource scheduling of pumped storage power stations is solved, realizing dynamic collaborative scheduling of resources across power stations and improving emergency response efficiency and collaborative efficiency.

CN123162948APending Publication Date: 2026-11-24GUANGDONG ENERGY GROUP GUIYANG PUMPED STORAGE POWER GENERATION CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611331259.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-31
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

The existing emergency resource scheduling of pumped storage power stations suffers from problems such as a disconnect between static plans and dynamic realities, a lack of overall optimization in resource scheduling, each power station operating independently, and resource misallocation, making it difficult to meet the needs of coordinated emergency response for modern pumped storage power station clusters.

Method used

By constructing an emergency resource scheduling knowledge graph, mapping and reasoning matching of situational feature information, and combining a multi-objective constraint optimization solution framework and reinforcement learning strategy, a final scheduling scheme is generated to achieve dynamic collaborative scheduling of resources across power plants.

Benefits of technology

It has improved the timeliness of emergency response, reduced human judgment bias, optimized resource allocation, enhanced emergency coordination efficiency, and ensured the safe and stable operation of the power system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123162948A_ABST
    Figure CN123162948A_ABST
Patent Text Reader

Abstract

This invention relates to the field of emergency management technology for energy and power systems, and particularly to a method and system for dynamic collaborative scheduling of emergency resources in pumped storage power stations. The method involves acquiring emergency resource status information and emergency event situation characteristics information of pumped storage power stations; constructing an emergency resource scheduling knowledge graph based on historical emergency response cases and expert knowledge; mapping situation characteristics to graph reasoning and matching; identifying historical case sets; and extracting resource allocation patterns and scheduling execution paths. Based on resource allocation patterns and status information, a multi-objective constraint optimization framework integrating timeliness, safety, stability, and cost constraints is constructed to iteratively generate candidate scheduling schemes. Reinforcement learning combined with exercise and real-world feedback data is used to evaluate and screen candidate schemes, outputting the final scheduling scheme. Based on this, resource scheduling instructions for collaborative units are generated and monitored, improving the efficiency and accuracy of dynamic collaborative scheduling of emergency resources and enhancing the emergency response capability of pumped storage power stations.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of emergency management technology for energy and power systems, and in particular to a method and system for dynamic collaborative scheduling of emergency resources for pumped storage power stations. Background Technology

[0002] Pumped storage power stations play a crucial role in power grid peak shaving and valley filling, as well as emergency backup. Their safe and stable operation directly impacts the reliability of the power system. These stations are typically located underground or semi-underground, involving special conditions such as high water pressure, high current, and complex geotechnical environments. In the event of sudden incidents such as equipment failure, flooding of the power plant, or transmission line anomalies, emergency response is challenging, and resource dispatching requirements are stringent. Current conventional practices rely on pre-established emergency management plans. Each power station's emergency command center issues dispatch instructions to its repair teams, backup equipment, and fire-fighting supplies according to the incident type and the procedures and authority stipulated in the plan. During dispatching, coordination primarily depends on the experience and judgment of on-site commanders, using traditional communication methods such as telephones and walkie-talkies. Resource status information is mostly summarized in manually entered reports, resulting in delayed updates and a lack of real-time updates.

[0003] At the inter-power station level, different pumped storage power stations typically allocate emergency resources based solely on their own risk assessments, lacking a unified resource information sharing mechanism and joint dispatch rules. In the event of major emergencies, temporary coordination methods are occasionally used to request support from neighboring power stations, but this support is often limited to a single resource category, lacking comprehensive consideration of resources such as repair capabilities, spare parts, and emergency power supplies across different power stations. While some power stations have deployed emergency management information systems, these systems are heavily focused on post-event recording and process approval, failing to effectively track dynamic information such as resource location, quantity, and status, and struggling to quickly generate adjustment plans based on changing event circumstances.

[0004] The main problems exposed by existing conventional practices are concentrated in two aspects: First, there is a significant disconnect between static plans and dynamic reality. The timing, scope, and evolution path of emergencies often exceed the pre-set scenarios, forcing commanders to rely on experience to adapt on the spot. Response speed and quality are highly dependent on individual capabilities, easily leading to resource misallocation or duplicate allocation. Second, resource scheduling lacks a holistic optimization awareness; each power station operates independently, and emergency resources cannot form complementary synergies within the region. Specific equipment urgently needed by one power station may be idle at neighboring stations, while resources that are far away or inaccessible are prioritized due to poor information flow, resulting in low overall emergency rescue efficiency. These shortcomings are particularly prominent in complex scenarios such as extreme weather and simultaneous disruptions to multiple stations, exposing the limitations of traditional manual decision-making and single-station closed scheduling models, making them unsuitable for the actual needs of coordinated emergency response in modern pumped storage power station clusters. Summary of the Invention

[0005] This invention provides a method and system for dynamic collaborative scheduling of emergency resources in pumped storage power stations, which can solve the problems in the prior art.

[0006] A first aspect of the present invention provides a method for dynamic collaborative scheduling of emergency resources for pumped storage power stations, comprising:

[0007] Acquire emergency resource status information and current emergency event situation characteristics information from multiple pumped storage power stations;

[0008] An emergency resource scheduling knowledge graph is constructed based on historical emergency response cases of pumped storage power stations and domain expert knowledge. The situation feature information is mapped to the emergency resource scheduling knowledge graph for reasoning and matching. A set of historical cases with semantic similarity to the current emergency event is identified, and the resource allocation mode and scheduling execution path for pumped storage power stations in the set of historical cases are extracted.

[0009] Based on the resource allocation mode and the emergency resource status information, a multi-objective constraint optimization solution framework is constructed. The solution framework integrates the emergency response time constraint of pumped storage power station, the safety constraint of hydraulic structure, the power grid stability constraint and the resource coordination cost constraint, and generates a set of candidate scheduling schemes through iterative optimization.

[0010] The candidate scheduling scheme set is evaluated and screened using reinforcement learning strategies. A state-action-reward mapping relationship is constructed based on the feedback data from emergency drills and actual combat response data of the pumped storage power station. The final scheduling scheme that adapts to the current emergency situation of the pumped storage power station is output through the update of strategy network parameters.

[0011] Based on the final scheduling scheme, resource scheduling instructions are generated for each pumped storage power station collaborative unit and their execution is monitored.

[0012] An emergency resource scheduling knowledge graph is constructed based on historical emergency response cases of pumped storage power stations and domain expert knowledge. The situational feature information is mapped to the emergency resource scheduling knowledge graph for reasoning and matching. The set of historical cases that are semantically similar to the current emergency event is identified, including:

[0013] Semantic analysis was performed on historical emergency response cases of pumped storage power stations to extract emergency event triggering conditions, resource scheduling response sequences and response effect evaluations, forming a set of case semantic triples.

[0014] Causal rules are extracted from domain expert knowledge to identify the association rules between event evolution paths and resource demands in emergency scenarios of pumped storage power stations. The causal rules are then fused and aligned with the set of semantic triples of the cases to construct an emergency resource scheduling knowledge graph containing entity nodes and multi-type relationship edges.

[0015] Multi-dimensional feature decomposition is performed on the situation characteristic information to generate a situation vector representation that includes event type features, equipment status features, and environmental impact features;

[0016] The situation vector representation is mapped to the entity node space of the emergency resource scheduling knowledge graph. An initial matching node set is determined by calculating the semantic distance between the situation vector representation and each entity node. Multi-level extended reasoning is performed along the relation edges of the initial matching node set. The comprehensive similarity score of historical cases is calculated based on the relation edge type weight and path connectivity. The set of historical cases with the highest score is then selected.

[0017] Causal rules are extracted from domain expert knowledge to identify the association rules between event evolution paths and resource demands in emergency scenarios of pumped storage power stations. These causal rules are then fused and aligned with the set of semantic triples for each case to construct an emergency resource scheduling knowledge graph containing entity nodes and various types of relational edges.

[0018] The domain expert knowledge is decomposed in a structured manner, and the condition trigger statements and resource configuration statements in the emergency scenario of pumped storage power station are extracted to form a mapping relationship between rule antecedents and rule consequents;

[0019] Based on the mapping relationship, the event evolution path is identified. By tracking the temporal dependency between the event state change in the rule antecedent and the derived event in the rule consequent, the evolution relationship edge between event nodes is constructed. Resource type identifier and resource quantity constraint in the rule consequent are extracted to establish the association rule edge between event nodes and resource demand nodes.

[0020] Semantically match the main entities in the case semantic triple set with the event nodes, and map the relation types in the case semantic triple set with the evolutionary relation edges and the association rule edges;

[0021] Based on the fusion and alignment of the semantic matching results and the type mapping results, when the case semantic triple and the causal rule point to the same event node, the weight parameters of the corresponding relation edge are updated by calculating the weighted fusion value of the case statistical frequency and the rule confidence. When the case semantic triple is missing a corresponding causal rule, the causal rule is added as a new relation edge, forming an emergency resource scheduling knowledge graph containing entity nodes and multiple types of relation edges.

[0022] Based on the resource allocation mode and the emergency resource status information, a multi-objective constraint optimization solution framework is constructed. This framework integrates constraints on the emergency response timeliness of pumped storage power stations, safety constraints on hydraulic structures, grid stability constraints, and resource coordination cost constraints. Through iterative optimization, a set of candidate scheduling schemes is generated, including:

[0023] Extract the resource allocation benchmark quantity and scheduling time sequence relationship from the resource allocation mode, and match and verify the resource allocation benchmark quantity with the real-time resource availability quantity in the emergency resource status information to determine the feasible boundary of resource scheduling.

[0024] Within the feasible boundary, a multi-objective constraint optimization solution framework is constructed. The emergency response time constraint of the pumped storage power station is set as the time difference constraint between the resource arrival time and the event handling time limit. The safety constraint of the hydraulic structure is set as the safety margin constraint between the reservoir water level change and the structural bearing limit. The grid stability constraint is set as the stability margin constraint between the unit output adjustment range and the grid frequency allowable deviation. The resource coordination cost constraint is set as the total cost constraint between the cross-power station dispatch distance and the number of resource calls. The verification priority of each constraint is determined according to the dispatch timing relationship.

[0025] The time difference constraint, the safety margin constraint, the stability margin constraint, and the total cost constraint are iteratively optimized. In each iteration, the degree of satisfaction of each constraint is checked according to the verification priority. When a constraint violation is detected, the corresponding resource allocation variable is adjusted and the scheduling scheme is updated within the feasible boundary. The scheduling scheme is output after all constraints are satisfied at the same time. The process is repeated to generate a set of candidate scheduling schemes.

[0026] The candidate scheduling scheme set is evaluated and screened using reinforcement learning strategies. A state-action-reward mapping relationship is constructed based on feedback data from emergency drills and real-world responses at the pumped storage power station. The final scheduling scheme, adapted to the current emergency situation of the pumped storage power station, is then output through strategy network parameter updates. This includes:

[0027] Extract the resource allocation sequence and scheduling execution time sequence of each scheduling scheme from the candidate scheduling scheme set, and convert the resource allocation sequence and scheduling execution time sequence into the action space representation form in the reinforcement learning environment;

[0028] Emergency event characteristics, resource scheduling response, and disposal effect evaluation are extracted from emergency drill feedback data and actual handling feedback data of pumped storage power stations. The emergency event characteristics are mapped into a state space expression form, the resource scheduling response is mapped into an action execution record, and the disposal effect evaluation is mapped into a reward signal value, thus establishing a state-action-reward mapping relationship.

[0029] Based on the state-action-reward mapping relationship, the candidate scheduling scheme set is evaluated by strategy evaluation. The action space expression of each scheduling scheme in the candidate scheduling scheme set is matched with the action execution record. The corresponding reward signal value is extracted according to the matching result to generate the cumulative reward evaluation value of each scheduling scheme.

[0030] The cumulative reward evaluation value is used as the training target of the policy network. By adjusting the policy network parameters, the deviation between the action distribution output by the policy network under the current state space expression form corresponding to the emergency situation of the pumped storage power station and the action space expression form of the scheduling scheme with the highest cumulative reward evaluation value is minimized. After the policy network parameters are updated, the action distribution output by the policy network is converted into the final scheduling scheme.

[0031] Based on the state-action-reward mapping relationship, the candidate scheduling scheme set is evaluated. The matching degree between the action space representation of each scheduling scheme in the candidate scheduling scheme set and the action execution record is calculated. Based on the matching degree result, the corresponding reward signal value is extracted, and the cumulative reward evaluation value for each scheduling scheme is generated, including:

[0032] Extract the resource scheduling action sequence of each scheduling scheme from the candidate scheduling scheme set, and expand the resource scheduling action sequence into an action space expression form according to the scheduling time sequence relationship;

[0033] Extract action execution records from the state-action-reward mapping relationship, and perform structured decomposition of the action execution records according to resource type and scheduling object to generate a set of action feature vectors;

[0034] The matching degree is calculated between the action space representation and the action feature vector set. The semantic similarity is measured between each action unit in the action space representation and each action feature vector in the action feature vector set. When the semantic similarity exceeds the matching threshold, the action unit and the action feature vector are determined to form a matching pair. The number of matching pairs formed by each scheduling scheme is counted.

[0035] Based on the number of matching pairs, the corresponding reward signal values ​​are extracted from the state-action-reward mapping relationship. The reward signal values ​​corresponding to each matching pair are then summed according to the scheduling timing relationship to generate the cumulative reward evaluation value for each scheduling scheme.

[0036] The generation and execution monitoring of resource scheduling instructions for each pumped storage power station collaborative unit based on the final scheduling scheme includes:

[0037] Extract the resource allocation target and scheduling timing constraints of each pumped storage power station collaborative unit from the final scheduling scheme, and generate resource scheduling instructions containing resource type identifier, scheduling quantity, arrival time limit and collaborative triggering conditions based on the resource allocation target and scheduling timing constraints.

[0038] The resource scheduling instructions are distributed to the corresponding pumped storage power station coordination units, and the resource scheduling progress information and coordination trigger condition satisfaction status of each coordination unit are collected during the execution of the instructions.

[0039] The execution process of the resource scheduling instruction is monitored based on the resource scheduling progress information and the status of the coordination triggering conditions.

[0040] A second aspect of the present invention provides a dynamic collaborative scheduling system for emergency resources of pumped storage power stations, comprising:

[0041] The information acquisition unit is used to acquire emergency resource status information and current emergency event situation characteristics information of multiple pumped storage power stations.

[0042] The knowledge graph unit is used to construct an emergency resource scheduling knowledge graph based on historical emergency response cases of pumped storage power stations and domain expert knowledge. The situation feature information is mapped to the emergency resource scheduling knowledge graph for reasoning and matching, to identify a set of historical cases that are semantically similar to the current emergency event, and to extract the resource allocation patterns and scheduling execution paths for pumped storage power stations from the set of historical cases.

[0043] The optimization solution unit is used to construct a multi-objective constraint optimization solution framework based on the resource allocation mode and the emergency resource status information. The solution framework integrates the emergency response time constraint of pumped storage power station, the safety constraint of hydraulic structure, the power grid stability constraint and the resource coordination cost constraint, and generates a set of candidate scheduling schemes through iterative optimization.

[0044] The strategy evaluation unit is used to evaluate and screen the candidate scheduling scheme set through reinforcement learning. It constructs a state-action-reward mapping relationship based on the feedback data of emergency drills and actual combat response data of pumped storage power stations, and outputs the final scheduling scheme that adapts to the current emergency situation of pumped storage power stations through strategy network parameter updates.

[0045] The scheduling execution unit is used to generate resource scheduling instructions for each pumped storage power station collaborative unit based on the final scheduling scheme and to monitor their execution.

[0046] A third aspect of the present invention provides an electronic device, comprising:

[0047] processor;

[0048] Memory used to store processor-executable instructions;

[0049] The processor is configured to invoke instructions stored in the memory to execute the aforementioned method.

[0050] A fourth aspect of the present invention provides a computer-readable storage medium having stored thereon computer program instructions that, when executed by a processor, implement the aforementioned method.

[0051] This system enables dynamic aggregation and precise matching of emergency resources for pumped storage power stations across regions, significantly improving emergency response timeliness. The fusion of multi-source emergency status information and situational characteristics transforms dispatching decisions from experience-driven to data- and knowledge-driven, enhancing the sensitivity to sudden events and the depth of semantic understanding. Knowledge graph reasoning and matching of historical cases extract resource allocation patterns and execution paths, providing highly reliable decision-making references for similar emergencies, reducing human judgment bias, and improving the efficiency and scientific rigor of initial response plan generation.

[0052] The multi-objective constraint optimization framework comprehensively balances timeliness, hydraulic structure safety, power grid stability, and coordination costs, generating a set of candidate solutions that meet complex engineering constraints and effectively avoiding secondary risks caused by a single objective. The iterative optimization mechanism adapts to dynamically changing emergency environments, ensuring the feasibility and robustness of the solutions. The reinforcement learning strategy evaluation, combined with exercise and real-world feedback data, constructs a state-action-reward mapping. Through policy network parameter updates, the scheduling scheme undergoes self-evolution, allowing the selected scheme to continuously approach the global optimum with the accumulation of historical experience, significantly reducing the probability of conflicts and coordination costs in cross-power station resource allocation.

[0053] The final dispatch plan is issued to each coordinating unit in the form of instructions, and the execution monitoring is integrated throughout the entire process to form a closed-loop management system. This mechanism ensures that resource dispatch instructions are traceable, verifiable, and adjustable, promptly captures execution deviations and supports rapid correction, effectively prevents response delays and resource mismatches, significantly improves the emergency coordination efficiency and success rate of pumped storage power stations under extreme conditions, strengthens the joint rescue capabilities of multiple stations, and provides solid support for ensuring the safe and stable operation of the power system and the safety of key projects. Attached Figure Description

[0054] Figure 1 This is a flowchart illustrating the dynamic collaborative scheduling method for emergency resources of pumped storage power stations according to an embodiment of the present invention.

[0055] Figure 2 This is a multi-dimensional radar image showing the emergency situation characteristics of a pumped storage power station according to an embodiment of the present invention.

[0056] Figure 3 This is a graph showing the comprehensive score of multi-objective constraint iterative optimization and the convergence of constraint violations in an embodiment of the present invention.

[0057] Figure 4 This is a flowchart illustrating the intelligent decision-making process for dynamic scheduling of emergency resources in a pumped storage power station, as described in an embodiment of the present invention. Detailed Implementation

[0058] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0059] The technical solution of the present invention will be described in detail below with reference to specific embodiments. These specific embodiments can be combined with each other, and the same or similar concepts or processes may not be described again in some embodiments.

[0060] Figure 1 This is a flowchart illustrating the dynamic collaborative scheduling method for emergency resources in pumped storage power stations according to an embodiment of the present invention.

[0061] The dynamic collaborative scheduling method for emergency resources of pumped storage power stations includes:

[0062] Acquire emergency resource status information and current emergency event situation characteristics information from multiple pumped storage power stations;

[0063] An emergency resource scheduling knowledge graph is constructed based on historical emergency response cases of pumped storage power stations and domain expert knowledge. The situation feature information is mapped to the emergency resource scheduling knowledge graph for reasoning and matching. A set of historical cases with semantic similarity to the current emergency event is identified, and the resource allocation mode and scheduling execution path for pumped storage power stations in the set of historical cases are extracted.

[0064] Based on the resource allocation mode and the emergency resource status information, a multi-objective constraint optimization solution framework is constructed. The solution framework integrates the emergency response time constraint of pumped storage power station, the safety constraint of hydraulic structure, the power grid stability constraint and the resource coordination cost constraint, and generates a set of candidate scheduling schemes through iterative optimization.

[0065] The candidate scheduling scheme set is evaluated and screened using reinforcement learning strategies. A state-action-reward mapping relationship is constructed based on the feedback data from emergency drills and actual combat response data of the pumped storage power station. The final scheduling scheme that adapts to the current emergency situation of the pumped storage power station is output through the update of strategy network parameters.

[0066] Based on the final scheduling scheme, resource scheduling instructions are generated for each pumped storage power station collaborative unit and their execution is monitored.

[0067] In one optional implementation, an emergency resource scheduling knowledge graph is constructed based on historical pumped storage power station emergency response cases and domain expert knowledge. The situational feature information is mapped to the emergency resource scheduling knowledge graph for reasoning and matching. The set of historical cases semantically similar to the current emergency event is identified, including:

[0068] Semantic analysis was performed on historical emergency response cases of pumped storage power stations to extract emergency event triggering conditions, resource scheduling response sequences and response effect evaluations, forming a set of case semantic triples.

[0069] Causal rules are extracted from domain expert knowledge to identify the association rules between event evolution paths and resource demands in emergency scenarios of pumped storage power stations. The causal rules are then fused and aligned with the set of semantic triples of the cases to construct an emergency resource scheduling knowledge graph containing entity nodes and multi-type relationship edges.

[0070] Multi-dimensional feature decomposition is performed on the situation characteristic information to generate a situation vector representation that includes event type features, equipment status features, and environmental impact features;

[0071] The situation vector representation is mapped to the entity node space of the emergency resource scheduling knowledge graph. An initial matching node set is determined by calculating the semantic distance between the situation vector representation and each entity node. Multi-level extended reasoning is performed along the relation edges of the initial matching node set. The comprehensive similarity score of historical cases is calculated based on the relation edge type weight and path connectivity. The set of historical cases with the highest score is then selected.

[0072] like Figure 2 As shown, the method includes:

[0073] This radar chart depicts the overall situation of emergency events at pumped storage power stations from five dimensions. The "Environmental Impact" dimension scores as high as 8.2, reflecting the significant constraints posed by external conditions such as heavy rainfall and low visibility on emergency response. The "Event Severity" score of 7.8 confirms the urgency of the unit's load shedding failure. The "Response Urgency" score of 9.1 indicates the need for immediate cross-station coordinated dispatch. The "Equipment Status" score of 6.4 indicates that the units and hydraulic facilities still have some margin, but close monitoring is still required. The "Resource Gap" score of 5.6 indicates that existing emergency resources basically meet initial needs, but will become insufficient as the event evolves. This radar chart visually reveals the imbalance between the dimensions—the environmental impact and urgency are high, while the equipment status and resource gap are relatively mild. This asymmetrical situation requires dispatch strategies to prioritize environmentally adaptable measures (such as enhanced drainage and anti-slip measures) and shorten the decision-making cycle, while rationally allocating repair resources to avoid excessive consumption. Through multi-dimensional quantitative comparison, this graph provides a clear goal orientation for subsequent knowledge graph reasoning and optimization, ensuring that the generated solutions can accurately target weak links and improve the pertinence and effectiveness of emergency response.

[0074] When performing semantic analysis on historical pumped-storage power station emergency response cases, it is necessary to identify and extract three core elements from the original case text: the initial conditions triggering the emergency response (such as specific event types like unit load shedding, powerhouse flooding, and dam leakage exceeding limits, along with the equipment operating parameters at the time of occurrence), the resource scheduling response sequence (including the allocation order, arrival time nodes, and coordination relationships of various emergency resources), and the evaluation of the response effect (covering quantitative indicators such as event control duration, degree of loss, and resource utilization rate). These three elements are organized into a set of case semantic triples, with each triple having a basic structure of "triggering condition—response action—response result," forming a structured case library that can be used for subsequent knowledge integration. The entity descriptions in the triples must retain domain-specific terminology unique to pumped-storage power stations, such as the water level difference between upper and lower reservoirs, unit operating condition switching status, and phase-shifting operation mode, to ensure that the semantic analysis results are highly consistent with the domain context.

[0075] Causal rule extraction of domain expert knowledge focuses on identifying the inherent logic of event evolution in emergency scenarios of pumped storage power stations. Expert knowledge is usually expressed in a condition-conclusion form, such as "When the water level of the upper reservoir is below the dead water level and the unit is in power generation mode, it is necessary to switch to pumping mode first and start the standby unit." This type of knowledge is formalized to extract the event evolution path (i.e., how one type of event triggers another type of event under specific conditions) and resource demand association rules (i.e., the types, quantities, and response time limits of resources required for a specific event type). When merging and aligning causal rules with the set of case semantic triples, entity semantic similarity is used as the matching basis. The condition nodes in the rules are matched with the triggering conditions in the triples, and the conclusion nodes in the rules are associated with the response actions in the triples. Thus, case experience and expert reasoning logic are simultaneously carried in a unified graph structure. The final emergency resource scheduling knowledge graph includes multiple types of entity nodes (emergency event nodes, resource type nodes, disposal action nodes, and evaluation indicator nodes) and multiple types of relationship edges (triggering relationships, demand relationships, execution relationships, and evaluation relationships). Each relationship edge in the graph is accompanied by a confidence weight, reflecting the strength of support for the association in historical cases and expert knowledge.

[0076] When performing multi-dimensional feature decomposition on the situational characteristics of current emergency events, the original situational description is decomposed into three feature subspaces: event type feature subspace (describing the event's category, severity level, and impact range), equipment status feature subspace (describing the current operating status and degree of deviation from normal values ​​of affected units, hydraulic structures, and electrical equipment), and environmental impact feature subspace (describing current hydrological and meteorological conditions, power grid load status, and accessibility of external support). The feature items within each subspace are numerically encoded. Discrete features (such as event category) are converted into one-hot encoded vectors, and continuous features (such as water level deviation) are normalized. Finally, the feature vectors from the three subspaces are concatenated to form a complete situational vector representation. This vector's dimensional design is consistent with the embedding space of entity nodes in the knowledge graph to support subsequent semantic distance calculations.

[0077] When mapping the situation vector representation to the entity node space of the emergency resource scheduling knowledge graph, a graph embedding method is used to pre-encode each entity node in the knowledge graph as a fixed-dimensional vector representation, ensuring that semantically similar nodes are close in the embedding space. The semantic distance between the situation vector and the embedding vectors of each entity node is calculated, using cosine similarity as a metric. Nodes with similarity exceeding a preset threshold are selected to form an initial matching node set. This initial matching node set typically corresponds to emergency event nodes or equipment status nodes in the knowledge graph that are directly related to the current situation.

[0078] When performing multi-level extension reasoning along the relational edges of the initial matching node set, the process starts from the initial matching node and expands outward layer by layer according to the relational edge type. The first layer of expansion extends along the "triggering relationship" edge to the subsequent event node, the second layer extends along the "demand relationship" edge to the corresponding resource type node, and the third layer extends along the "execution relationship" edge to the specific action node in the historical case. The weight of each extension path is determined by the type weight of each relational edge on the path and the path connectivity. The relational edge type weight reflects the importance of that type of relationship in emergency dispatch (triggering relationships have a higher weight than evaluation relationships), and the path connectivity is weighted by the inverse of the path length to avoid introducing noise into excessively long paths. For each historical case, the weights of all paths reaching the relevant nodes of that case are summarized, and a comprehensive similarity score is calculated. The calculation method is as follows:

[0079] ;

[0080] in, To reach the The set of all paths to a given historical case node. For path The product of the weights of each relation edge type. For path The connectivity weight (inversely proportional to path length). According to... The historical cases are sorted from highest to lowest score, and the highest-scoring cases are selected to form the final historical case set. The cases in this set have the highest semantic similarity to the current emergency situation in multiple dimensions such as event type, equipment status and environmental conditions, which can provide a reliable historical reference for subsequent resource allocation pattern extraction.

[0081] In practical applications, the construction and updating of knowledge graphs is a continuous iterative process. After each emergency response, the handling process and effect evaluation of the event are added to the graph in the form of new case semantic triples. At the same time, the confidence weights of the relevant relation edges are corrected according to the handling results, so that the graph can be continuously improved with the accumulation of practical experience, thereby improving the accuracy and reliability of subsequent reasoning and matching.

[0082] In one optional implementation, causal rules are extracted from domain expert knowledge to identify the association rules between event evolution paths and resource demands in emergency scenarios of pumped storage power stations. These causal rules are then fused and aligned with the set of case semantic triples to construct an emergency resource scheduling knowledge graph containing entity nodes and multiple types of relational edges.

[0083] The domain expert knowledge is decomposed in a structured manner, and the condition trigger statements and resource configuration statements in the emergency scenario of pumped storage power station are extracted to form a mapping relationship between rule antecedents and rule consequents;

[0084] Based on the mapping relationship, the event evolution path is identified. By tracking the temporal dependency between the event state change in the rule antecedent and the derived event in the rule consequent, the evolution relationship edge between event nodes is constructed. Resource type identifier and resource quantity constraint in the rule consequent are extracted to establish the association rule edge between event nodes and resource demand nodes.

[0085] Semantically match the main entities in the case semantic triple set with the event nodes, and map the relation types in the case semantic triple set with the evolutionary relation edges and the association rule edges;

[0086] Based on the fusion and alignment of the semantic matching results and the type mapping results, when the case semantic triple and the causal rule point to the same event node, the weight parameters of the corresponding relation edge are updated by calculating the weighted fusion value of the case statistical frequency and the rule confidence. When the case semantic triple is missing a corresponding causal rule, the causal rule is added as a new relation edge, forming an emergency resource scheduling knowledge graph containing entity nodes and multiple types of relation edges.

[0087] When structurally decomposing domain expert knowledge, it is necessary to extract conditional trigger statements and resource allocation statements from expert experience texts, taking into account the specific characteristics of emergency scenarios at pumped storage power stations. Conditional trigger statements typically appear in logical forms such as "when..." or "if...", describing the event state that triggers an emergency response, such as "when the upper reservoir water level exceeds the normal storage level and the flood discharge facilities malfunction." Resource allocation statements describe the type and quantity of resources that should be allocated under these conditions, such as "two mobile pumps and four hydraulic engineers need to be allocated." After annotating these two types of statements separately, a mapping relationship between rule antecedents and rule consequents is formed, that is, a structured rule pair with the event state description as the antecedent and the resource allocation requirement as the consequent. This decomposition process needs to cover multiple emergency scenarios, such as hydraulic structure hazards, electromechanical equipment failures, power grid disturbances, and personnel casualties, to ensure the coverage and professional depth of the rule base.

[0088] When identifying event evolution paths based on the above mapping relationship, the sequence of event state changes in the antecedents of rules is tracked to analyze the temporal dependencies between adjacent rules. For example, after the event "sluice gate jammed" appears in the antecedents of a rule, its derivative event "reservoir water level continues to rise" will appear as the antecedent of the subsequent rule. There is a clear temporal sequence relationship between the two. Based on this, an evolutionary relationship edge is constructed in the knowledge graph from the "sluice gate jammed" node to the "reservoir water level continues to rise" node, with the temporal dependency type and typical evolution time window marked on the edge. At the same time, resource type identifiers and resource quantity constraints are extracted from the consequents of rules. For example, "submersible pump" is used as the resource type identifier and "no less than 3 units" is used as the quantity constraint. An association rule edge is established in the knowledge graph from the event node to the corresponding resource demand node, carrying attribute information such as resource type, quantity lower limit, and priority. Through a systematic traversal of all rules, an event evolution network and resource demand association network covering typical emergency scenarios of pumped storage power stations are formed.

[0089] When semantically matching the subject entities and event nodes in the case semantic triple set, a matching method based on semantic vector similarity is adopted. The vector space distance between the subject entities in the case triple (e.g., "abnormal speed of Unit 1") and existing event nodes in the knowledge graph (e.g., "unit overspeed event") is calculated. A successful match is determined when the similarity exceeds a preset threshold. For the relation types in the case semantic triples, they are mapped and aligned with the type labels of evolutionary relation edges and association rule edges. For example, the "cause" relation in the case is mapped to the evolutionary relation edge type, and the "need" relation is mapped to the association rule edge type. This type mapping process establishes a unified representation of case knowledge and rule knowledge at the relation level, laying a structural foundation for subsequent fusion and alignment.

[0090] The fusion and alignment phase is a core step in constructing an emergency resource scheduling knowledge graph. When both the semantic triples of a case and the causal rules point to the same event node, the credibility of both knowledge sources needs to be comprehensively considered. The weight parameters of the corresponding relational edges are updated by calculating a weighted fusion value of the case statistical frequency and the rule confidence. Let the normalized value of the case statistical frequency be... The rule confidence level is The weighting coefficients are respectively and (satisfy Then the relation edge weight update value for:

[0091] ;

[0092] in and The value is dynamically adjusted based on the scale of case data and the quality of expert knowledge; it is appropriately increased when there are sufficient historical cases. When expert rules have been rigorously validated, the appropriate increase should be made. This weighted fusion mechanism enables the relation edge weights in the knowledge graph to simultaneously reflect the statistical regularities of historical experience and the causal judgments of domain experts, avoiding bias caused by a single source of knowledge.

[0093] When a semantic triple in a case contains a certain relationship, but a corresponding causal rule is lacking in the causal rule base, the relationship implied by the case triple is added to the knowledge graph as a new relation edge. For example, if a co-occurrence relationship between "abnormal vibration of pressure steel pipe" and "decrease in governor oil pressure" appears multiple times in historical cases, but the causal relationship between the two is not explicitly established in the expert rule base, then this relationship is added as a new relation edge in the form of case induction edges, labeled with the source type "case induction," the number of supporting cases, and the confidence interval. Conversely, when a causal rule points to a certain event node but there is a lack of corresponding cases in the case base, the rule is also added to the graph in the form of rule inference edges, labeled with the source type "expert rule" and the rule confidence level.

[0094] After the aforementioned steps of structured decomposition, evolutionary path identification, semantic matching, type mapping, and fusion alignment, an emergency resource scheduling knowledge graph is finally formed, containing entity nodes and multiple types of relationship edges. The entity nodes in the graph cover four categories: emergency event nodes, resource demand nodes, resource supply nodes, and disposal unit nodes; the relationship edges cover four categories: evolutionary relationship edges, association rule edges, case induction edges, and rule inference edges, with each type of relationship edge carrying weight parameters. The knowledge graph includes source type labeling and confidence information. It retains the statistical patterns of historical cases and incorporates the causal reasoning knowledge of domain experts, providing structured knowledge support for subsequent situation feature mapping and reasoning matching. This enables the rapid location of semantically similar historical handling paths and resource allocation patterns through graph reasoning when facing new types of emergency events.

[0095] In one optional implementation, a multi-objective constraint optimization solution framework is constructed based on the resource allocation mode and the emergency resource status information. This framework integrates constraints on the emergency response timeliness of pumped storage power stations, safety constraints on hydraulic structures, grid stability constraints, and resource coordination cost constraints. Through iterative optimization, a set of candidate scheduling schemes is generated, including:

[0096] Extract the resource allocation benchmark quantity and scheduling time sequence relationship from the resource allocation mode, and match and verify the resource allocation benchmark quantity with the real-time resource availability quantity in the emergency resource status information to determine the feasible boundary of resource scheduling.

[0097] Within the feasible boundary, a multi-objective constraint optimization solution framework is constructed. The emergency response time constraint of the pumped storage power station is set as the time difference constraint between the resource arrival time and the event handling time limit. The safety constraint of the hydraulic structure is set as the safety margin constraint between the reservoir water level change and the structural bearing limit. The grid stability constraint is set as the stability margin constraint between the unit output adjustment range and the grid frequency allowable deviation. The resource coordination cost constraint is set as the total cost constraint between the cross-power station dispatch distance and the number of resource calls. The verification priority of each constraint is determined according to the dispatch timing relationship.

[0098] The time difference constraint, the safety margin constraint, the stability margin constraint, and the total cost constraint are iteratively optimized. In each iteration, the degree of satisfaction of each constraint is checked according to the verification priority. When a constraint violation is detected, the corresponding resource allocation variable is adjusted and the scheduling scheme is updated within the feasible boundary. The scheduling scheme is output after all constraints are satisfied at the same time. The process is repeated to generate a set of candidate scheduling schemes.

[0099] like Figure 3 As shown, the method includes:

[0100] This line-bar chart illustrates the trends of "overall score" and "number of constraint violations" during the multi-objective constraint optimization iteration process. The horizontal axis represents the number of iterations (1 to 50), the left vertical axis represents the overall score (0 to 1), and the right vertical axis represents the number of constraint violations. The line chart shows that the overall score gradually increases from 0.52 in the first iteration to 0.92 in the 50th iteration, exhibiting a monotonically increasing and converging trend. The rate of increase slows down and stabilizes after the 20th iteration, indicating that the algorithm continuously improves the quality of the scheduling scheme within the feasible boundary. The bar chart reflects that the number of constraint violations rapidly decreases from the initial 12 to 0 after the 45th iteration, and remains at zero violations in subsequent iterations, demonstrating that the iterative optimization effectively satisfies the four types of constraints: timeliness, safety, stability, and cost. The two curves show a clear negative correlation—as the number of violations decreases, the overall score steadily increases, verifying that the adopted verification priority strategy (timeliness first, cost last) can guide the search direction towards a feasible and efficient region. The results demonstrate the robustness of the multi-objective optimization framework under complex constraints, and the final set of candidate solutions not only meets engineering safety requirements but also has high comprehensive performance.

[0101] When extracting resource allocation benchmark quantities from resource allocation patterns, it is necessary to perform structured parsing of the scheduling records in the historical case set, storing the historical configuration quantities and configuration sequence relationships of various emergency resources (including repair personnel, backup equipment, emergency supplies, technical support forces, etc.) in a standardized format. Resource allocation benchmark quantities reflect the scale of resource input repeatedly used in semantically similar historical cases. For example, in a certain type of hydraulic structure leakage incident, the number of submersible pumps, the amount of seepage prevention materials used, and the scale of professional and technical personnel commonly called in historical cases can all serve as benchmark reference values. The scheduling sequence relationship records the order in which various resources are deployed at different stages of the incident response, such as the phased deployment logic of initial reconnaissance forces, mid-term emergency repair main forces, and late-stage recovery support forces.

[0102] When matching and verifying the baseline resource allocation with the real-time availability of resources in the emergency resource status information, it is necessary to compare the difference between the baseline demand and the actual available resources of each pumped storage power station. If the current available resources of a power station are lower than the baseline, it is marked as a resource gap, triggering cross-power station collaborative scheduling logic; if the available resources meet the baseline demand, the resource is included in the feasible scheduling range. The matching and verification process also considers the geographical distribution of resources and the timeliness of transportation. Resources that are more than a reasonable transportation time limit away from the affected power station are not included in the effective feasible boundary, even if the quantity is sufficient. After the above verification, a set of feasible boundaries is formed with resource type as the dimension and the upper limit of available quantity as the constraint, providing a legitimate decision space for subsequent multi-objective constraint optimization.

[0103] When constructing a multi-objective constrained optimization solution framework within the feasible boundary, the emergency response time constraint is expressed as a time difference constraint between the actual arrival time of resources and the event handling time limit. Let resources... The estimated arrival time is The corresponding time limit for the handling process is Then the time constraint requirement This applies to all resources involved in the scheduling. The safety constraints on hydraulic structures are centered on the safety margin between the reservoir water level change and the structural bearing capacity limit, assuming the current water level change is... The maximum allowable water level change corresponding to the structural bearing capacity is Safety margin constraints ,in This is a safety margin factor, typically ranging from 0.7 to 0.9, with the specific value determined by the type of hydraulic structure and the current state of damage.

[0104] Grid stability constraints are expressed as the stability margin between the unit output adjustment range and the allowable deviation of the grid frequency. Let the unit output adjustment range be... The power grid frequency deviation is Stability margin constraints require and The combination does not exceed the boundary of safe and stable operation of the power grid, that is, it satisfies... ,in The upper limit of the allowable deviation of the power grid frequency is usually set according to the power grid dispatching regulations. The resource coordination cost constraint is measured by the weighted total of the inter-power station dispatching distance and the number of resource calls, assuming the [missing information - likely a typo]. The distance for the second cross-station dispatch is The cumulative number of calls is Total cost constraints ,in The cost discount factor for the number of calls. This represents the upper limit of the total cost. Based on the scheduling sequence, timeliness constraints are set as the highest verification priority, followed by safety margin constraints, then stability margin constraints, and finally, total cost constraints as the lowest priority, forming a hierarchical verification order.

[0105] The iterative optimization process checks the satisfaction of each constraint condition layer by layer according to the above verification priority. At the beginning of each iteration, the actual value of each constraint condition is calculated based on the current resource allocation variables and compared with the corresponding constraint threshold. If the timeliness constraint is violated, the resource scheduling path is adjusted first or a faster alternative resource is replaced, and the estimated resource arrival time is updated within the feasible boundary. If the timeliness constraint is satisfied but the safety margin constraint is violated, the reservoir scheduling operation plan is adjusted to reduce the water level change rate or implement water level control in stages, and the calculation is recalculated. And verify whether the safety margin has been restored to the compliance range.

[0106] Once the time constraint and safety margin constraint are both satisfied, the stability margin constraint is further tested. If the unit output adjustment scheme leads to... Exceeding If the output adjustment range is smoothed, large, rapid adjustments are broken down into multiple small, gradual adjustment steps, and the frequency deviation is reassessed. The total cost constraint is verified assuming the first three types of constraints are met. If the weighted total of the cross-site scheduling distance and the number of calls in the current scheme exceeds [the limit], [then the cost constraint is checked]. In such cases, priority should be given to calling resources from the nearest local site instead of resources from distant cross-site sites, or multiple small batch calls should be merged into a single large batch call to reduce the impact of resource consumption. The total cost should be reduced without violating the preceding constraints.

[0107] After each iteration completes all constraint checks and variable adjustments, the current solution is recorded as a candidate scheduling solution. If all constraints are satisfied simultaneously in this iteration, the solution is directly added to the candidate scheduling solution set. If constraints are violated and adjustments still fail to satisfy all constraints within the feasible boundary, the solution for this iteration is abandoned, and the iteration is restarted with a different initial resource allocation combination. Through multiple iterations starting with different initial conditions, candidate scheduling solutions that satisfy all constraints are gradually accumulated until the candidate set reaches a preset size, at which point a complete set of candidate scheduling solutions is output for subsequent reinforcement learning policy evaluation.

[0108] In one optional implementation, the candidate scheduling scheme set is evaluated and screened using reinforcement learning strategies. A state-action-reward mapping relationship is constructed based on feedback data from emergency drills and real-world responses at the pumped storage power station. The final scheduling scheme, adapted to the current emergency situation of the pumped storage power station, is then output through policy network parameter updates.

[0109] Extract the resource allocation sequence and scheduling execution time sequence of each scheduling scheme from the candidate scheduling scheme set, and convert the resource allocation sequence and scheduling execution time sequence into the action space representation form in the reinforcement learning environment;

[0110] Emergency event characteristics, resource scheduling response, and disposal effect evaluation are extracted from emergency drill feedback data and actual handling feedback data of pumped storage power stations. The emergency event characteristics are mapped into a state space expression form, the resource scheduling response is mapped into an action execution record, and the disposal effect evaluation is mapped into a reward signal value, thus establishing a state-action-reward mapping relationship.

[0111] Based on the state-action-reward mapping relationship, the candidate scheduling scheme set is evaluated by strategy evaluation. The action space expression of each scheduling scheme in the candidate scheduling scheme set is matched with the action execution record. The corresponding reward signal value is extracted according to the matching result to generate the cumulative reward evaluation value of each scheduling scheme.

[0112] The cumulative reward evaluation value is used as the training target of the policy network. By adjusting the policy network parameters, the deviation between the action distribution output by the policy network under the current state space expression form corresponding to the emergency situation of the pumped storage power station and the action space expression form of the scheduling scheme with the highest cumulative reward evaluation value is minimized. After the policy network parameters are updated, the action distribution output by the policy network is converted into the final scheduling scheme.

[0113] like Figure 4 As shown, the method includes:

[0114] Extracting the resource allocation sequence and execution time sequence of each scheduling scheme from the candidate scheduling scheme set is the foundation for constructing the reinforcement learning action space. The resource allocation sequence records the order and quantity combination of various emergency resources (including repair personnel, special equipment, spare parts, and technical support) allocated to each pumped storage power station collaborative unit; the scheduling execution time sequence describes the sequential relationship and concurrency constraints of each resource scheduling action on the time axis. When converting the above two types of information into an action space representation, each scheduling decision is represented by a discretized action vector. The vector dimension corresponds to the Cartesian product space of the resource type and the target site, and the value of the vector element represents the quantity or proportion of the resource allocated to the corresponding site at that time step. For scheduling actions with time dependencies, the execution constraints are encoded through a directed acyclic graph to ensure that the action space representation can completely preserve the execution logic of the original scheduling scheme.

[0115] Extracting effective training samples from emergency drill feedback data and actual response feedback data of pumped storage power stations requires structured parsing of the original records. Emergency event characteristics encompass multi-dimensional attributes such as event type coding, occurrence time, affected unit number, damage rating of hydraulic structures, power grid disturbance magnitude, and meteorological environmental parameters. These attributes are concatenated into a fixed-length feature vector and then mapped into a state-space representation. The resource scheduling response record contains the sequence of scheduling actions actually executed at each time step, which is mapped to action execution records after being aligned with the action space definition. The evaluation of the handling effect comprehensively considers four dimensions: the time taken to complete the handling of the incident, the restoration of the safety status of hydraulic structures, the speed of power grid frequency restoration, and the total cost of resource scheduling. The scalar reward signal value is obtained through weighted aggregation calculation. The weights of each dimension are determined according to the priority ranking in the emergency management regulations for pumped storage power stations. There is a distinction in sample weighting between drill data and actual combat data; actual combat data is given higher weight due to its authenticity, while drill data is included in the training set as supplementary samples because it covers a wider range of scenarios. These three types of mapping relationships together constitute a state-action-reward mapping relationship database, providing empirical sample support for subsequent strategy evaluation.

[0116] Based on the established state-action-reward mapping, a strategy evaluation is performed on each scheme in the candidate scheduling scheme set. The action space representation of each scheduling scheme is progressively matched with the action execution records in the mapping database. The matching degree uses cosine similarity to measure the directional consistency between action vectors, while a temporal alignment penalty term is introduced to constrain execution order deviations. For the action vector at a certain time step in the candidate scheme... The system retrieves the historical action execution record with the highest similarity to the cosine from the mapping relation database, extracts the corresponding reward signal value, and accumulates it by time step discount to obtain the cumulative reward evaluation value of the scheme. Discount factor The value range is set between 0.9 and 0.99 to balance the weights of immediate rewards and long-term benefits. After completing the above evaluation for all schemes in the candidate scheduling scheme set, according to... The scheduling schemes are sorted in descending order, and the one with the highest cumulative reward evaluation value is identified as the target reference for updating the policy network parameters.

[0117] The policy network adopts a multilayer perceptron structure, with the input layer receiving the state-space representation of the current emergency situation. The output layer generates a probability distribution that covers the entire action space. The action space representation of the scheduling scheme with the highest cumulative reward evaluation value is denoted as the target action sequence. The objective of updating the policy network parameters is to minimize the deviation between the output action distribution and the target action sequence. The loss function is defined as the cross-entropy between the two, i.e. ,in Indexing the action space dimension, For the target action sequence in the 1st The value of dimensionality is determined. The gradient of the loss function with respect to the parameters of each layer of the policy network is calculated using the backpropagation algorithm. An adaptive learning rate optimization method is used to update the network weights, and this process is iterated until the loss function converges to below a preset threshold. To prevent the policy network from overfitting to a single historical case pattern, random perturbations are applied to the state input during training, and entropy regularization constraints are applied to the output action distribution to encourage the policy network to maintain a certain degree of action diversity under similar situations.

[0118] After the policy network parameters are updated, the state-space representation of the current emergency situation will be displayed. Input the updated policy network and obtain the output action distribution. A greedy decoding process is used to decode the action distribution, selecting the action with the highest probability at each time step to generate a complete action sequence. This action sequence is then restored to a specific resource allocation scheme and scheduling execution sequence according to the inverse mapping rules defined in the action space, resulting in the final scheduling scheme. The final scheduling scheme clearly lists the types, quantities, and arrival deadlines of resources that each pumped storage power station collaborative unit should receive at each time step, and marks the dependencies between each scheduling action, providing a direct basis for subsequently generating resource scheduling instructions for each collaborative unit. For time steps where multiple candidate actions with similar probabilities exist in the action distribution, the second-best action is retained as an alternative to support dynamic switching in case of resource unavailability during the execution monitoring phase.

[0119] In one optional implementation, the candidate scheduling scheme set is evaluated based on the state-action-reward mapping relationship. The matching degree between the action space representation of each scheduling scheme in the candidate scheduling scheme set and the action execution record is calculated. Based on the matching degree result, the corresponding reward signal value is extracted to generate the cumulative reward evaluation value for each scheduling scheme, including:

[0120] Extract the resource scheduling action sequence of each scheduling scheme from the candidate scheduling scheme set, and expand the resource scheduling action sequence into an action space expression form according to the scheduling time sequence relationship;

[0121] Extract action execution records from the state-action-reward mapping relationship, and perform structured decomposition of the action execution records according to resource type and scheduling object to generate a set of action feature vectors;

[0122] The matching degree is calculated between the action space representation and the action feature vector set. The semantic similarity is measured between each action unit in the action space representation and each action feature vector in the action feature vector set. When the semantic similarity exceeds the matching threshold, the action unit and the action feature vector are determined to form a matching pair. The number of matching pairs formed by each scheduling scheme is counted.

[0123] Based on the number of matching pairs, the corresponding reward signal values ​​are extracted from the state-action-reward mapping relationship. The reward signal values ​​corresponding to each matching pair are then summed according to the scheduling timing relationship to generate the cumulative reward evaluation value for each scheduling scheme.

[0124] When evaluating a set of candidate scheduling schemes, it is necessary to extract a complete sequence of resource scheduling actions from each candidate scheme. Each candidate scheme describes a set of resource allocation decisions across time steps, including information such as which resources to schedule, which pumped storage power station to allocate to, and when to execute them. These decisions are then unfolded step by step according to their scheduling sequence, forming an action space representation indexed by time steps. Specifically, for each candidate scheme, its resource scheduling operations are arranged in the order of execution, with each time step corresponding to an action unit. This action unit includes attribute fields such as resource type identifier, target site number, scheduling quantity, and execution time, thereby transforming the scheduling decisions, originally existing as a whole scheme, into a structured sequence that can be compared step by step.

[0125] When extracting action execution records from the state-action-reward mapping relationship, it is necessary to structurally decompose each action execution entry recorded in the historical handling process. Action execution records cover the actual resource scheduling operations performed in historical emergency events. Each record contains information on resource type, scheduling object, execution sequence, and handling result. These records are grouped according to two dimensions: resource type and scheduling object. Historical execution operations of similar resources on similar scheduling objects are grouped together, and a unified action feature representation is extracted from each group to form a set of action feature vectors. The construction of action feature vectors comprehensively considers resource attributes (such as equipment type, rated capacity, response speed, etc.) and scheduling object attributes (such as site geographical location, equipment configuration status, current load level, etc.). These attributes are transformed into fixed-dimensional numerical vectors through encoding mapping for subsequent similarity measurement.

[0126] When calculating the matching degree between the action space representation of the candidate solution and the action feature vector set, for each action unit in the action space representation, semantic similarity is calculated sequentially with each action feature vector in the action feature vector set. The semantic similarity measure comprehensively considers the consistency between the action unit and the action feature vector in dimensions such as resource type, scheduling object, and execution attributes, and uses vector inner product normalization to obtain a similarity value between 0 and 1. When the semantic similarity between an action unit and an action feature vector exceeds a preset matching threshold, the action unit and the action feature vector are determined as a matching pair, and the historical reward signal value corresponding to the matching pair is recorded. After completing the above matching operation for the action units of all time steps in the candidate solution, the total number of matching pairs formed by the candidate solution is counted. The number of matching pairs reflects the overall fit between the candidate solution and historical successful handling experience.

[0127] In the process of extracting reward signal values ​​and generating cumulative reward evaluation values ​​based on the number of matching pairs, for all matching pairs formed for each candidate solution, the reward signal values ​​corresponding to each matching pair are read from the state-action-reward mapping relationship. The reward signal values ​​are derived from historical emergency drill feedback data and actual combat response feedback data, reflecting the effectiveness evaluation of the corresponding historical actions in actual response, including a comprehensive score from multiple dimensions such as the timeliness of response, the safety of hydraulic structures, the maintenance of power grid stability, and the control of resource coordination costs.

[0128] The reward signal values ​​corresponding to each matching pair are summed using a time-decay weighted sum based on the scheduling time sequence to generate the cumulative reward evaluation value for each candidate scheme. The core idea of ​​time-decay weighting is that the further the future time step is from the current decision time, the lower the contribution of its reward signal to the current scheme evaluation should be, so as to reflect the higher weight of the recent action effect in judging the merits of the scheme. Let the th... The reward signal value for each time step corresponding to the matched pair is The time step discount factor is (The range of values ​​is) The total number of time steps included in the candidate solutions is Then the cumulative reward evaluation value of the candidate solution Calculate as follows:

[0129] ;

[0130] in, For the first The decay weight of each time step decreases exponentially as the time step number increases, ensuring that the reward signal of earlier time steps carries a larger proportion in the cumulative evaluation. For time steps that do not form a matching pair, their corresponding reward signal value is set to 0, contributing nothing to the cumulative reward evaluation value. Through the above time-series decay weighted summation, each candidate scheme ultimately obtains a scalar cumulative reward evaluation value. This value comprehensively reflects the degree to which the scheme fits with historical successful handling experience and the expected handling effect throughout the scheduling timeline, providing a quantitative basis for the subsequent ranking and selection of candidate schemes.

[0131] In practical applications, the matching threshold setting has a significant impact on the number of matching pairs and the final cumulative reward evaluation value. An excessively high matching threshold will result in a large number of action units failing to form matching pairs, leading to a low cumulative reward evaluation value and insufficient discrimination; conversely, an excessively low matching threshold will introduce a large number of low-quality matching pairs, increasing noise in the reward signal. For emergency dispatch scenarios in pumped storage power stations, the matching threshold can be adaptively calibrated based on the distribution characteristics of action feature vectors in historical data. For example, a certain quantile of the similarity distribution within the action feature vector set can be used as a threshold reference, thereby maintaining sufficient matching coverage while ensuring matching accuracy. Furthermore, for cases where the same action unit and multiple action feature vectors exceed the matching threshold, the matching pair with the highest similarity is selected as the valid match, avoiding duplicate inclusion in the reward signal and ensuring the accuracy and reliability of the cumulative reward evaluation value calculation.

[0132] In one optional implementation, generating resource scheduling instructions for each pumped storage power station collaborative unit based on the final scheduling scheme and monitoring their execution includes:

[0133] Extract the resource allocation target and scheduling timing constraints of each pumped storage power station collaborative unit from the final scheduling scheme, and generate resource scheduling instructions containing resource type identifier, scheduling quantity, arrival time limit and collaborative triggering conditions based on the resource allocation target and scheduling timing constraints.

[0134] The resource scheduling instructions are distributed to the corresponding pumped storage power station coordination units, and the resource scheduling progress information and coordination trigger condition satisfaction status of each coordination unit are collected during the execution of the instructions.

[0135] The execution process of the resource scheduling instruction is monitored based on the resource scheduling progress information and the status of the coordination triggering conditions.

[0136] When extracting the resource allocation targets and scheduling timing constraints for each pumped storage power station collaborative unit from the final scheduling scheme, it is necessary to analyze the scheme structure and identify the resource type, quantity requirements, and positional relationship of each collaborative unit within the overall scheduling sequence. Scheduling timing constraints include the sequential dependencies and parallel triggering conditions between collaborative units; these constraints directly determine the generation logic of resource scheduling instructions. For collaborative units with dependencies, the triggering mechanism that requires preconditions to be met must be explicitly stated in the instructions; for collaborative units that can be executed in parallel, an independent triggering flag should be marked in the instructions to allow synchronous execution.

[0137] Resource scheduling instructions are generated at the level of collaborative units. Each instruction contains four core fields: resource type identifier, scheduling quantity, arrival time limit, and collaborative triggering condition. The resource type identifier uses a unified coding system to distinguish different categories such as personnel, equipment, materials, and technical support, ensuring that each collaborative unit can accurately identify the attributes of the required resources when receiving instructions. The scheduling quantity is determined based on the target resource allocation amount and verified in conjunction with the current resource availability status of each site to avoid generating instructions that exceed actual available capacity. The arrival time limit is set according to the time window in the scheduling sequence constraints, using critical nodes of emergency response as a benchmark, and reserving time for resource transfer and preparation to ensure that resources arrive within the specified time limit. The collaborative triggering condition describes the prerequisite states that must be met to initiate the execution of this instruction, including the completion status of other collaborative units, the reaching of specific monitoring quantities to a threshold, or the issuance of instructions from higher authorities, among other triggering forms. The triggering condition is embedded in the instruction in the form of a structured logical expression, facilitating automatic judgment by the execution end.

[0138] The generated resource scheduling instructions are distributed to each pumped storage power station's collaborative units through a unified instruction distribution channel. During the distribution process, each instruction is uniquely identified, its issuance timestamp is recorded, and a mapping relationship between instructions and collaborative units is established, forming a complete instruction ledger. After receiving an instruction, each collaborative unit performs a local judgment based on the collaborative trigger conditions in the instruction. If the trigger conditions are met, the unit automatically enters the execution state and sends instruction reception confirmation information back to the dispatch center. For instructions that cannot be confirmed in time due to communication anomalies, a retransmission mechanism is triggered, continuously attempting retransmissions within a specified number of attempts. If the number of retransmissions is exceeded, the unit is marked as abnormal and reported.

[0139] During command execution, resource scheduling progress information and the status of fulfilling coordination trigger conditions are continuously collected from each coordinating unit. Resource scheduling progress information includes resource departure status, en route location, estimated arrival time update, and actual arrival confirmation information, reported in real time through the field terminals or sensor networks of each coordinating unit. The status of fulfilling coordination trigger conditions is obtained by logically judging the field data reported by each coordinating unit. The judgment result is stored in Boolean form and compared with the trigger condition field of the corresponding command to determine whether each downstream command meets the activation conditions. The collection frequency of progress information and trigger status is dynamically adjusted according to the urgency of the emergency, shortening the collection interval during peak periods to improve monitoring timeliness.

[0140] Based on the collected resource scheduling progress information and the fulfillment status of collaborative triggering conditions, the instruction execution process is monitored in multiple dimensions. In terms of timeliness, the actual arrival time of resources in each collaborative unit is compared with the arrival time limit set in the instruction to calculate the timeliness deviation. Instructions with a risk of timeout are given early warning, triggering contingency plan adjustment procedures. In terms of collaboration, the trigger dependency links between collaborative units are tracked in real time. When the execution progress of a collaborative unit lags behind, its impact on downstream dependent units is assessed, and affected downstream instructions are reordered or resource substitutions are adjusted as necessary. In terms of completeness, the arrival rate of various resources is statistically analyzed. For resource types that fail to arrive on time, a source analysis is performed to identify whether the problem lies in the scheduling path, the resource's own status, or the instruction transmission. The analysis results are then fed back to the scheduling decision-making level.

[0141] When an execution deviation exceeding the preset tolerance range is detected during monitoring, an instruction revision process is initiated. Revisions may include adjusting the number of scheduled tasks, updating arrival time limits, changing resource source sites, or resetting collaborative triggering conditions. Revised instructions are issued incrementally, retaining the original instruction number and adding a revision version identifier to ensure that each collaborative unit can identify and replace the old version instructions. Revision records are fully preserved as a data source for post-event review and knowledge accumulation.

[0142] The entire execution monitoring process forms a closed loop: from instruction generation, distribution, and execution to deviation detection and revision, the status data of each link is continuously aggregated to the dispatch center, forming a dynamically updated execution status map. The execution status map uses each collaborative unit as a node and scheduling timing constraints as edges, reflecting the execution status and trigger condition fulfillment of each node in real time, providing dispatchers with an intuitive global monitoring view, and supporting dynamic decision-making and collaborative management during emergency response.

[0143] A second aspect of the present invention provides a dynamic collaborative scheduling system for emergency resources of pumped storage power stations, comprising:

[0144] The information acquisition unit is used to acquire emergency resource status information and current emergency event situation characteristics information of multiple pumped storage power stations.

[0145] The knowledge graph unit is used to construct an emergency resource scheduling knowledge graph based on historical emergency response cases of pumped storage power stations and domain expert knowledge. The situation feature information is mapped to the emergency resource scheduling knowledge graph for reasoning and matching, to identify a set of historical cases that are semantically similar to the current emergency event, and to extract the resource allocation patterns and scheduling execution paths for pumped storage power stations from the set of historical cases.

[0146] The optimization solution unit is used to construct a multi-objective constraint optimization solution framework based on the resource allocation mode and the emergency resource status information. The solution framework integrates the emergency response time constraint of pumped storage power station, the safety constraint of hydraulic structure, the power grid stability constraint and the resource coordination cost constraint, and generates a set of candidate scheduling schemes through iterative optimization.

[0147] The strategy evaluation unit is used to evaluate and screen the candidate scheduling scheme set through reinforcement learning. It constructs a state-action-reward mapping relationship based on the feedback data of emergency drills and actual combat response data of pumped storage power stations, and outputs the final scheduling scheme that adapts to the current emergency situation of pumped storage power stations through strategy network parameter updates.

[0148] The scheduling execution unit is used to generate resource scheduling instructions for each pumped storage power station collaborative unit based on the final scheduling scheme and to monitor their execution.

[0149] A third aspect of the present invention provides an electronic device, comprising:

[0150] processor;

[0151] Memory used to store processor-executable instructions;

[0152] The processor is configured to invoke instructions stored in the memory to execute the aforementioned method.

[0153] A fourth aspect of the present invention provides a computer-readable storage medium having stored thereon computer program instructions that, when executed by a processor, implement the aforementioned method.

[0154] This invention can be a method, apparatus, system, and / or computer program product. The computer program product may include a computer-readable storage medium having computer-readable program instructions loaded thereon for performing various aspects of the invention.

[0155] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, and not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some or all of the technical features; and these modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A method for dynamic coordinated dispatching of emergency resources of pumped storage power stations, characterized in that, include: Acquire emergency resource status information and current emergency event situation characteristics information from multiple pumped storage power stations; An emergency resource scheduling knowledge graph is constructed based on historical emergency response cases of pumped storage power stations and domain expert knowledge. The situation feature information is mapped to the emergency resource scheduling knowledge graph for reasoning and matching. A set of historical cases with semantic similarity to the current emergency event is identified, and the resource allocation mode and scheduling execution path for pumped storage power stations in the set of historical cases are extracted. Based on the resource allocation mode and the emergency resource status information, a multi-objective constraint optimization solution framework is constructed. The solution framework integrates the emergency response time constraint of pumped storage power station, the safety constraint of hydraulic structure, the power grid stability constraint and the resource coordination cost constraint, and generates a set of candidate scheduling schemes through iterative optimization. The candidate scheduling scheme set is evaluated and screened using reinforcement learning strategies. A state-action-reward mapping relationship is constructed based on the feedback data from emergency drills and actual combat response data of the pumped storage power station. The final scheduling scheme that adapts to the current emergency situation of the pumped storage power station is output through the update of strategy network parameters. Based on the final scheduling scheme, resource scheduling instructions are generated for each pumped storage power station collaborative unit and their execution is monitored.

2. The method according to claim 1, characterized in that, An emergency resource scheduling knowledge graph is constructed based on historical emergency response cases of pumped storage power stations and domain expert knowledge. The situational feature information is mapped to the emergency resource scheduling knowledge graph for reasoning and matching. The set of historical cases that are semantically similar to the current emergency event is identified, including: Semantic analysis was performed on historical emergency response cases of pumped storage power stations to extract emergency event triggering conditions, resource scheduling response sequences and response effect evaluations, forming a set of case semantic triples. Causal rules are extracted from domain expert knowledge to identify the association rules between event evolution paths and resource demands in emergency scenarios of pumped storage power stations. The causal rules are then fused and aligned with the set of semantic triples of the cases to construct an emergency resource scheduling knowledge graph containing entity nodes and multi-type relationship edges. Multi-dimensional feature decomposition is performed on the situation characteristic information to generate a situation vector representation that includes event type features, equipment status features, and environmental impact features; The situation vector representation is mapped to the entity node space of the emergency resource scheduling knowledge graph. An initial matching node set is determined by calculating the semantic distance between the situation vector representation and each entity node. Multi-level extended reasoning is performed along the relation edges of the initial matching node set. The comprehensive similarity score of historical cases is calculated based on the relation edge type weight and path connectivity. The set of historical cases with the highest score is then selected.

3. The method according to claim 2, characterized in that, Causal rules are extracted from domain expert knowledge to identify the association rules between event evolution paths and resource demands in emergency scenarios of pumped storage power stations. These causal rules are then fused and aligned with the set of semantic triples for each case to construct an emergency resource scheduling knowledge graph containing entity nodes and various types of relational edges. The domain expert knowledge is decomposed in a structured manner, and the condition trigger statements and resource configuration statements in the emergency scenario of pumped storage power station are extracted to form a mapping relationship between rule antecedents and rule consequents; Based on the mapping relationship, the event evolution path is identified. By tracking the temporal dependency between the event state change in the rule antecedent and the derived event in the rule consequent, the evolution relationship edge between event nodes is constructed. Resource type identifier and resource quantity constraint in the rule consequent are extracted to establish the association rule edge between event nodes and resource demand nodes. Semantically match the main entities in the case semantic triple set with the event nodes, and map the relation types in the case semantic triple set with the evolutionary relation edges and the association rule edges; Based on the fusion and alignment of the semantic matching results and the type mapping results, when the case semantic triple and the causal rule point to the same event node, the weight parameters of the corresponding relation edge are updated by calculating the weighted fusion value of the case statistical frequency and the rule confidence. When the case semantic triple is missing a corresponding causal rule, the causal rule is added as a new relation edge, forming an emergency resource scheduling knowledge graph containing entity nodes and multiple types of relation edges.

4. The method according to claim 1, characterized in that, Based on the resource allocation mode and the emergency resource status information, a multi-objective constraint optimization solution framework is constructed. This framework integrates constraints on the emergency response timeliness of pumped storage power stations, safety constraints on hydraulic structures, grid stability constraints, and resource coordination cost constraints. Through iterative optimization, a set of candidate scheduling schemes is generated, including: Extract the resource allocation benchmark quantity and scheduling time sequence relationship from the resource allocation mode, and match and verify the resource allocation benchmark quantity with the real-time resource availability quantity in the emergency resource status information to determine the feasible boundary of resource scheduling. Within the feasible boundary, a multi-objective constraint optimization solution framework is constructed. The emergency response time constraint of the pumped storage power station is set as the time difference constraint between the resource arrival time and the event handling time limit. The safety constraint of the hydraulic structure is set as the safety margin constraint between the reservoir water level change and the structural bearing limit. The grid stability constraint is set as the stability margin constraint between the unit output adjustment range and the grid frequency allowable deviation. The resource coordination cost constraint is set as the total cost constraint between the cross-power station dispatch distance and the number of resource calls. The verification priority of each constraint is determined according to the dispatch timing relationship. The time difference constraint, the safety margin constraint, the stability margin constraint, and the total cost constraint are iteratively optimized. In each iteration, the degree of satisfaction of each constraint is checked according to the verification priority. When a constraint violation is detected, the corresponding resource allocation variable is adjusted and the scheduling scheme is updated within the feasible boundary. The scheduling scheme is output after all constraints are satisfied at the same time. The process is repeated to generate a set of candidate scheduling schemes.

5. The method according to claim 1, characterized in that, The candidate scheduling scheme set is evaluated and screened using reinforcement learning strategies. A state-action-reward mapping relationship is constructed based on feedback data from emergency drills and real-world responses at the pumped storage power station. The final scheduling scheme, adapted to the current emergency situation of the pumped storage power station, is then output through strategy network parameter updates. This includes: Extract the resource allocation sequence and scheduling execution time sequence of each scheduling scheme from the candidate scheduling scheme set, and convert the resource allocation sequence and scheduling execution time sequence into the action space representation form in the reinforcement learning environment; Emergency event characteristics, resource scheduling response, and disposal effect evaluation are extracted from emergency drill feedback data and actual handling feedback data of pumped storage power stations. The emergency event characteristics are mapped into a state space expression form, the resource scheduling response is mapped into an action execution record, and the disposal effect evaluation is mapped into a reward signal value, thus establishing a state-action-reward mapping relationship. Based on the state-action-reward mapping relationship, the candidate scheduling scheme set is evaluated by strategy evaluation. The action space expression of each scheduling scheme in the candidate scheduling scheme set is matched with the action execution record. The corresponding reward signal value is extracted according to the matching result to generate the cumulative reward evaluation value of each scheduling scheme. The cumulative reward evaluation value is used as the training target of the policy network. By adjusting the policy network parameters, the deviation between the action distribution output by the policy network under the current state space expression form corresponding to the emergency situation of the pumped storage power station and the action space expression form of the scheduling scheme with the highest cumulative reward evaluation value is minimized. After the policy network parameters are updated, the action distribution output by the policy network is converted into the final scheduling scheme.

6. The method according to claim 5, characterized in that, Based on the state-action-reward mapping relationship, the candidate scheduling scheme set is evaluated. The matching degree between the action space representation of each scheduling scheme in the candidate scheduling scheme set and the action execution record is calculated. Based on the matching degree result, the corresponding reward signal value is extracted, and the cumulative reward evaluation value for each scheduling scheme is generated, including: Extract the resource scheduling action sequence of each scheduling scheme from the candidate scheduling scheme set, and expand the resource scheduling action sequence into an action space expression form according to the scheduling time sequence relationship; Extract action execution records from the state-action-reward mapping relationship, and perform structured decomposition of the action execution records according to resource type and scheduling object to generate a set of action feature vectors; The matching degree is calculated between the action space representation and the action feature vector set. The semantic similarity is measured between each action unit in the action space representation and each action feature vector in the action feature vector set. When the semantic similarity exceeds the matching threshold, the action unit and the action feature vector are determined to form a matching pair. The number of matching pairs formed by each scheduling scheme is counted. Based on the number of matching pairs, the corresponding reward signal values ​​are extracted from the state-action-reward mapping relationship. The reward signal values ​​corresponding to each matching pair are then summed according to the scheduling timing relationship to generate the cumulative reward evaluation value for each scheduling scheme.

7. The method according to claim 1, characterized in that, The generation and execution monitoring of resource scheduling instructions for each pumped storage power station collaborative unit based on the final scheduling scheme includes: Extract the resource allocation target and scheduling timing constraints of each pumped storage power station collaborative unit from the final scheduling scheme, and generate resource scheduling instructions containing resource type identifier, scheduling quantity, arrival time limit and collaborative triggering conditions based on the resource allocation target and scheduling timing constraints. The resource scheduling instructions are distributed to the corresponding pumped storage power station coordination units, and the resource scheduling progress information and coordination trigger condition satisfaction status of each coordination unit are collected during the execution of the instructions. The execution process of the resource scheduling instruction is monitored based on the resource scheduling progress information and the status of the coordination triggering conditions.

8. A dynamic collaborative scheduling system for emergency resources of pumped storage power stations, used to implement the method as described in any one of claims 1-7, characterized in that, include: The information acquisition unit is used to acquire emergency resource status information and current emergency event situation characteristics information of multiple pumped storage power stations. The knowledge graph unit is used to construct an emergency resource scheduling knowledge graph based on historical emergency response cases of pumped storage power stations and domain expert knowledge. The situation feature information is mapped to the emergency resource scheduling knowledge graph for reasoning and matching, to identify a set of historical cases that are semantically similar to the current emergency event, and to extract the resource allocation patterns and scheduling execution paths for pumped storage power stations from the set of historical cases. The optimization solution unit is used to construct a multi-objective constraint optimization solution framework based on the resource allocation mode and the emergency resource status information. The solution framework integrates the emergency response time constraint of pumped storage power station, the safety constraint of hydraulic structure, the power grid stability constraint and the resource coordination cost constraint, and generates a set of candidate scheduling schemes through iterative optimization. The strategy evaluation unit is used to evaluate and screen the candidate scheduling scheme set through reinforcement learning. It constructs a state-action-reward mapping relationship based on the feedback data of emergency drills and actual combat response data of pumped storage power stations, and outputs the final scheduling scheme that adapts to the current emergency situation of pumped storage power stations through strategy network parameter updates. The scheduling execution unit is used to generate resource scheduling instructions for each pumped storage power station collaborative unit based on the final scheduling scheme and to monitor their execution.

9. An electronic device, characterized in that, include: processor; Memory used to store processor-executable instructions; The processor is configured to invoke instructions stored in the memory to execute the method according to any one of claims 1 to 7.

10. A computer-readable storage medium having computer program instructions stored thereon, characterized in that, When the computer program instructions are executed by the processor, they implement the method described in any one of claims 1 to 7.