A new energy station scheduling risk avoidance decision-making method based on robust optimization
By using a robust optimization-based new energy power station scheduling method, and constructing a partially robust fuzzy set using unsupervised clustering and Wasserstein distance, combined with conditional risk value, the problem of lagging assessment risk handling and insufficient robustness in new energy power station scheduling is solved, thus achieving proactive risk avoidance and maximizing economic benefits.
Patent Information
- Application Number
- CN202611151977.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-31
- Publication Date
- 2026-11-24
AI Technical Summary
Existing new energy power plant scheduling methods fail to effectively integrate power grid scheduling assessment indicators with uncertainty modeling, resulting in delayed and passive handling of assessment risks. Traditional robust optimization methods do not make full use of historical data, leading to an excessively large range of uncertainty sets.
A robust optimization-based risk avoidance decision-making method for scheduling assessment of new energy power plants is adopted. Prediction error features are extracted by unsupervised clustering algorithm, a sub-robust fuzzy set is constructed, and a comprehensive assessment risk avoidance decision-making model is established by combining Wasserstein distance and conditional risk value. The strong dual strategy is adopted to transform it into a mixed integer linear programming problem, and the scheduling strategy is updated by rolling optimization.
This enables proactive risk avoidance in assessments under uncertainties in new energy output, improves the economic efficiency of power plants, reduces the passivity of assessment risks, and enhances the adaptability and compliance of dispatching strategies.
Smart Images

Figure CN123163041A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of power system optimization scheduling technology, specifically to a robust optimization-based decision-making method for risk avoidance in the scheduling assessment of new energy power plants. Background Technology
[0002] With the deepening of the global energy structure transformation, the installed capacity of new energy power generation such as wind power and photovoltaic power has continued to grow rapidly. New energy power plants have become an important part of the power system. However, the output of wind power and photovoltaic power is significantly affected by meteorological conditions, exhibiting strong randomness and intermittency, making power prediction errors difficult to avoid. At the same time, the grid dispatching agency's assessment requirements for the grid-connected operation of new energy power plants are becoming increasingly stringent. According to the relevant assessment standards issued by the National Energy Administration, the threshold for the accuracy of short-term power prediction of new energy power plants has been continuously raised, and deviation assessment costs have become the second largest operating cost for many new energy power plants. Assessment indicators typically include multiple dimensions such as day-ahead power prediction accuracy, real-time dispatch command deviation, regulation rate, regulation accuracy, and response time. Against this backdrop, how to formulate a reasonable dispatch plan to avoid assessment risks and improve the economic benefits of power plants under the influence of the uncertainty of new energy output has become a key technical challenge for the operation of new energy power plants.
[0003] Currently, optimization scheduling methods for handling the uncertainty of renewable energy output are mainly divided into two categories: stochastic programming and traditional robust optimization. Stochastic programming methods construct optimization models by assuming the probability distribution of renewable energy output, transforming uncertainty into expected values or chance constraints for processing. Traditional robust optimization methods, on the other hand, construct uncertainty sets to characterize the fluctuation range of renewable energy output and seek scheduling schemes that satisfy the constraints under all possible uncertainties. However, the above-mentioned existing technologies still have the following problems when dealing with the risk avoidance problem of renewable energy power plant scheduling assessment:
[0004] (1) Existing new energy power station dispatching methods mostly take economic efficiency as the sole optimization objective. Power grid dispatching assessment indicators are usually only treated as ex-post penalty items or evaluation indicators, and are not deeply integrated with uncertainty modeling in the optimization model of dispatching decision-making, resulting in delayed and passive assessment risk handling.
[0005] (2) Traditional robust optimization methods consider the fluctuation range of new energy output by constructing an uncertainty set. The optimization results require that the constraints are met under all possible uncertainties. However, such methods usually only construct the uncertainty set based on the upper and lower bounds of the prediction error, without making full use of the statistical information of historical data, resulting in an excessively large coverage of the uncertainty set. Summary of the Invention
[0006] The purpose of this invention is to provide a robust optimization-based decision-making method for risk avoidance in the scheduling assessment of new energy power plants, in order to solve the technical problems of lagging and passive risk handling in the prior art, and difficulty in balancing robustness and economy.
[0007] To solve the above-mentioned technical problems, the present invention specifically provides the following technical solution:
[0008] This invention provides a robust optimization-based risk avoidance decision-making method for scheduling assessment of new energy power plants, comprising the following steps:
[0009] The system acquires historical actual output data, historical forecast data, dispatch instructions issued by the power grid, and dispatch assessment rules of the power grid. Based on the historical actual output data and historical forecast data, it calculates a prediction error sequence and uses an unsupervised clustering algorithm to extract features from the prediction error sequence to obtain typical error distribution characteristics of the uncertainty of new energy output.
[0010] Based on the typical error distribution characteristics, a sub-Brubar fuzzy set is constructed using the Wasserstein distance data-driven method. The radius parameter of the sub-Brubar fuzzy set is a function of the risk aversion coefficient, which is used to adjust the radius parameter of the sub-Brubar fuzzy set to change the coverage of the uncertainty set.
[0011] A comprehensive assessment risk aversion decision-making model based on conditional risk value is established. The objective function is to maximize the total daily revenue of new energy power plants. A strong dual strategy is adopted to transform the fuzzy set containing nonlinear and uncertain constraints into an equivalent deterministic mixed integer linear programming problem.
[0012] An optimization solver is used to solve the mixed-integer linear programming problem, and a robust optimal scheduling strategy for new energy power plants under the worst-case power output fluctuation scenario is output. The scheduling strategy includes the grid-connected power plan of new energy in each time period, the charging and discharging power plan of the energy storage system, and the curtailment strategy of wind and solar power.
[0013] The robust optimal scheduling strategy is sent to the new energy power station monitoring and energy storage management module. In the next scheduling cycle, the updated ultra-short-term power prediction data is obtained, the sub-Bruker fuzzy set is updated on a rolling basis, and the robust optimal scheduling strategy is solved again.
[0014] As a preferred embodiment of the present invention, the method for extracting features from the prediction error sequence using an unsupervised clustering algorithm includes:
[0015] Using the magnitude of the prediction error and the time period as clustering feature dimensions, the K-means clustering algorithm is used to divide the prediction error sequence into K typical error scenario categories, with the value of K ranging from 5 to 20.
[0016] For each category, the probability of scenario occurrence, mean error vector, and covariance matrix of the corresponding category are calculated as typical error distribution characteristics of the uncertainty of new energy output.
[0017] As a preferred embodiment of the present invention, the method for constructing a split-Bruker bar fuzzy set using the Wasserstein distance data-driven method includes:
[0018] An empirical distribution is constructed based on N historical prediction error samples, with the empirical distribution as the center and the radius parameter as the boundary. Construct a Wasserstein fuzzy set with radius .
[0019] The Wasserstein fuzzy set is defined as all Wasserstein distances from the empirical distribution not exceeding a certain threshold. The set of probability distributions;
[0020] The Wasserstein distance is used to measure the degree of difference between any two probability distributions, and the radius parameter... The expression is:
[0021]
[0022] in, The risk aversion coefficient is set to a range of values. , For the number of historical samples, The confidence level is set to a range of values. ;
[0023] The risk aversion coefficient The larger the value of , the larger the radius of the fuzzy bar set. The larger the value, the wider the coverage of the uncertainty set.
[0024] As a preferred embodiment of the present invention, it includes:
[0025] In the comprehensive assessment risk avoidance decision-making model based on conditional value of risk, the objective function is to maximize the total daily revenue of the new energy power station. The total revenue includes electricity sales revenue minus energy storage operation costs and assessment penalty costs.
[0026] The assessment and penalty costs include the assessment and penalty costs for day-ahead forecast accuracy and the assessment and penalty costs for real-time dispatch instruction deviation.
[0027] The penalty cost for the day-ahead forecast accuracy assessment is determined based on the deviation between the day-ahead power forecast accuracy of the new energy power plant and the assessment threshold.
[0028] The penalty cost for deviation assessment of real-time dispatch instructions is determined based on the absolute deviation between the actual grid-connected power of the new energy power station and the dispatch plan power.
[0029] As a preferred embodiment of the present invention, a comprehensive assessment risk aversion decision-making model based on conditional value of risk is established, with the objective function being the maximization of the total daily revenue of the new energy power station, including:
[0030] The expression for the objective function is:
[0031]
[0032] in, This represents the total number of time periods within the scheduling cycle. For time period index, Uncertain variables in contributing to new energy sources The electricity price for period t. For time period t, under uncertain variables Grid-connected power under the achieved conditions The energy storage operating cost for time period t is calculated according to... Calculate, where, This is the depreciation cost factor per unit of energy storage. , These represent the charging power and discharging power of the energy storage system during time period t, respectively. For time period t, under uncertain variables The performance evaluation and penalty costs include day-ahead forecast accuracy evaluation and penalty for real-time dispatch instruction deviation.
[0033] The assessment and penalty costs The expression is:
[0034]
[0035] in, , These are the penalty coefficients for prediction accuracy and scheduling instruction deviation in time period t, respectively. For time period t, under uncertain variables The achieved daily forecast accuracy These are the forecast accuracy assessment thresholds issued by the power grid dispatching agency. For time period t, under uncertain variables Actual grid-connected power under the current conditions The planned grid-connected power for time period t;
[0036] The conditional value at risk (CVaR) of the assessment penalty cost is defined as follows:
[0037]
[0038] in, The confidence level is set to a range of values. , As an auxiliary variable, This represents the expectation operator under probability distribution P;
[0039] The conditional value of risk (CVaR) is added as a hard constraint to the comprehensive risk aversion decision-making model, satisfying the following:
[0040]
[0041] in, The maximum acceptable risk threshold is preset for new energy power plants.
[0042] As a preferred embodiment of the present invention, it includes:
[0043] In the objective function, the revenue from electricity sales is calculated as the product of the electricity price in each time period and the grid-connected power.
[0044] The energy storage operating cost Calculated by multiplying the energy storage charging and discharging power by the energy storage charging and discharging unit depreciation cost coefficient;
[0045] The assessment and penalty costs Calculated based on the sum of the prediction accuracy penalty and the scheduling instruction deviation penalty for each time period;
[0046] The objective function holds true for all probability distributions covered by the fuzzy set, and the goal is to find a robust optimal solution that maximizes profit under all possible distributions.
[0047] As a preferred embodiment of the present invention, the comprehensive assessment risk aversion decision model is set as a two-stage sub-Bruker optimization model, and its decision variable division includes:
[0048] The first-stage decision variable x includes the planned grid-connected power for each time period. And the binary variables of the charging and discharging states of the energy storage system at different times. , The decision variables in the first stage are uncertain variables. Determined before implementation, not subject to change. change;
[0049] Second-stage decision variables This includes the uncertainty variables in each time period. The adjustment of energy storage charging and discharging power under the following conditions , And the amount of wind and solar power curtailment The decision variables in the second stage are uncertain variables. Adjustments will be made based on the actual output after implementation.
[0050] As a preferred embodiment of the present invention, the constraints of the comprehensive assessment risk aversion decision-making model include:
[0051] The upper and lower limits of the total output of the power station are used to limit the grid-connected power in each time period from not exceeding the maximum output capacity of the power station and not being lower than the minimum technical output.
[0052] Energy storage system charging and discharging power constraints are used to limit the energy storage charging power from not exceeding the maximum charging power and the discharging power from not exceeding the maximum discharging power in each time period.
[0053] Energy storage system capacity constraints are used to limit the remaining energy storage capacity in each time period to be between the minimum remaining capacity and the maximum remaining capacity, while satisfying the recursive relationship of energy storage capacity.
[0054] The mutual exclusion constraint of charge and discharge states is used to restrict the energy storage system from being in both charging and discharging states at the same time.
[0055] Tie line transmission power constraint is used to limit the grid-connected power in each time period from not exceeding the maximum transmission capacity of the tie line;
[0056] Power balance constraint is used to constrain grid-connected power to equal the actual output of new energy sources plus the energy storage discharge power minus the energy storage charging power minus the amount of wind and solar curtailment.
[0057] As a preferred embodiment of the present invention, the method of transforming a fuzzy set containing nonlinear and uncertain constraints into an equivalent deterministic mixed-integer linear programming problem using a strong duality strategy includes:
[0058] The comprehensive assessment risk avoidance decision model based on conditional risk value is rewritten as a three-layer structure of min-max-min, where the outer layer min determines the first-stage scheduling plan, the middle layer max searches the probability distribution that maximizes the assessment risk in the sub-Bruker fuzzy set, and the inner layer min determines the second-stage adjustment amount.
[0059] By using a strong dual strategy, the optimal value function of the inner-layer min problem is replaced with a dual form, and the three-layer structure is reduced to a combination problem of single-layer maximization and outer-layer minimization.
[0060] The Big-M method is used to linearize the product terms of binary and continuous variables in the constraints;
[0061] The McCormick envelope method is used to relax the bilinear terms in the constraints, ultimately transforming the problem into an equivalent deterministic mixed-integer linear programming problem.
[0062] As a preferred embodiment of the present invention, the step of using an optimization solver to solve the mixed-integer linear programming problem, continuously updating the sub-Bruker fuzzy set, and resolving the robust optimal scheduling strategy includes:
[0063] The CPLEX optimization solver is used with the branch and bound method as the main framework, combined with the cutting plane method to add effective cutting constraints to the relaxation subproblem, and iteratively cuts the non-integer feasible region until the global optimal solution is obtained.
[0064] The robust optimal scheduling strategy includes wind and solar power curtailment strategies, which include optimized allocation schemes for wind and solar power curtailment in each time period.
[0065] At the beginning of each scheduling cycle, the updated ultra-short-term power prediction data is obtained. The remaining power of the energy storage system at the end of the previous scheduling cycle is used as the initial power of the current scheduling cycle. With the current scheduling cycle as the optimization window, the steps of extracting typical error distribution features, constructing a multi-bar fuzzy set, and solving the decision model are re-executed to obtain the robust optimal scheduling strategy for the current scheduling cycle.
[0066] The scheduling strategy for the first time period within the current scheduling cycle is issued and executed. When the next scheduling cycle arrives, the sliding optimization window is used to repeat the execution until the rolling optimization of all scheduling cycles is completed.
[0067] Compared with the prior art, the present invention has the following advantages:
[0068] This invention incorporates the conditional risk value of performance evaluation penalties as an independent hard constraint into a two-stage sparse robust optimization model. This directly limits the performance evaluation risk exposure under extreme tail scenarios, enabling scheduling strategies to proactively avoid performance evaluation risks before uncertainties materialize. This shifts performance evaluation risk management from reactive post-event response to proactive pre-event control. By organically integrating the Wasserstein distance data-driven method with CVaR risk measurement, it eliminates prior assumptions about the probability distribution of new energy output. The introduction of a risk aversion coefficient as an adjustment parameter for the fuzzy set radius achieves a flexible trade-off between robustness and economy, overcoming the overly conservative nature of traditional robust optimization. To address the high shortcomings, a combined strategy of clustering dimensionality reduction and strong duality transformation is used to accurately transform the complex min-max-min three-level blobs optimization model into a solvable mixed-integer linear programming problem. A complete closed-loop decision-making system coupled with a two-stage decision structure and rolling time-domain optimization is constructed. In each scheduling cycle, the fuzzy set and scheduling strategy are dynamically updated based on the latest ultra-short-term forecast data and the actual state of charge of energy storage. This forms a closed-loop rolling optimization of data update, model reconstruction, strategy solution and command issuance, enabling the scheduling strategy to continuously adapt to changes in uncertainty and maximize the total daily revenue of new energy power plants while ensuring compliance with assessment requirements. Attached Figure Description
[0069] To more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are merely exemplary, and those skilled in the art can derive other embodiments based on the provided drawings without creative effort.
[0070] Figure 1 The flowchart illustrates the risk avoidance decision-making method for scheduling and assessment of new energy power plants based on robust optimization, as provided in this embodiment of the invention. Detailed Implementation
[0071] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0072] like Figure 1 As shown, this invention provides a robust optimization-based risk avoidance decision-making method for new energy power plant scheduling assessment, comprising the following steps:
[0073] The system acquires historical actual output data, historical forecast data, dispatch instructions issued by the power grid, and dispatch assessment rules of the power grid. Based on the historical actual output data and historical forecast data, it calculates a prediction error sequence and uses an unsupervised clustering algorithm to extract features from the prediction error sequence to obtain typical error distribution characteristics of the uncertainty of new energy output.
[0074] In this embodiment, the historical actual output data comes from the new energy power station dispatch automation SCADA system. The SCADA system collects and records parameters such as voltage, current and power of core equipment such as wind turbines and photovoltaic inverters in real time. The data time resolution is usually 15 minutes or 5 minutes.
[0075] In this embodiment, the historical forecast data comes from the new energy power station new energy management system. The power forecast system combines meteorological data and historical data to forecast the power of wind power and photovoltaic power generation. The forecast data is collected in the form of FTP files, including power forecast data for the next 15 minutes to 4 hours and day-ahead power forecast data.
[0076] In this embodiment, the dispatch instructions issued by the power grid originate from the dispatch automation system of the power grid dispatching agency. The dispatch instructions are issued in the form of automatic generation control (AGC) instructions or dispatch plan curves and transmitted to the new energy power stations through the dispatch data network via communication protocols.
[0077] In this embodiment, the power grid dispatch assessment indicators are directly embedded into the core decision-making framework of the dispatch optimization model. By adding the conditional risk value (CVaR) of the assessment penalty cost as an independent constraint to the model, rather than just as the expected penalty term in the objective function, the dispatch strategy fully considers the tail risk under extreme assessment scenarios during the formulation stage. It can proactively avoid assessment risks before the uncertainty is realized, and significantly reduce the possibility of the station facing huge assessment fines in actual operation.
[0078] Based on the typical error distribution characteristics, a sub-Brubar fuzzy set is constructed using the Wasserstein distance data-driven method. The radius parameter of the sub-Brubar fuzzy set is a function of the risk aversion coefficient, which is used to adjust the radius parameter of the sub-Brubar fuzzy set to change the coverage of the uncertainty set.
[0079] In this embodiment, a data-driven method based on Wasserstein distance is used to construct a partially robust fuzzy set. This fully utilizes the complete distribution information contained in historical prediction error samples, eliminating the need for prior assumptions about the probability distribution of new energy output and avoiding decision-making errors caused by distribution assumption bias. Furthermore, by introducing a risk aversion coefficient λ as an adjustment parameter for the fuzzy set radius, decision-makers can flexibly adjust the coverage of the uncertain set according to actual operational needs. When λ is small, the uncertain set narrows, and the optimization result tends towards economic optimization; when λ is large, the uncertain set expands, and the optimization result tends towards robustness priority, achieving an adaptive trade-off between robustness and economy.
[0080] A comprehensive assessment risk aversion decision-making model based on conditional risk value is established. The objective function is to maximize the total daily revenue of new energy power plants. A strong dual strategy is adopted to transform the fuzzy set containing nonlinear and uncertain constraints into an equivalent deterministic mixed integer linear programming problem.
[0081] In this embodiment, a comprehensive risk aversion decision-making model based on conditional value of risk is established. A three-tiered (min-max-min) structure simultaneously optimizes the robustness of the planned scheme and the adaptability of the adjustment strategy. The first-stage decision is determined before the realization of uncertainty, ensuring the executability of the scheduling plan. The second-stage decision is flexibly adjusted based on actual output after the realization of uncertainty, ensuring the feasibility of system operation. Compared with existing single-layer stochastic programming or open-loop scheduling methods, the hierarchical decision-making structure adopted is more in line with the actual scheduling operations of new energy power plants, and can fully utilize the adjustment flexibility of the energy storage system while ensuring the executability of the plan.
[0082] An optimization solver is used to solve the mixed-integer linear programming problem, and a robust optimal scheduling strategy for new energy power plants under the worst-case power output fluctuation scenario is output. The scheduling strategy includes the grid-connected power plan of new energy in each time period, the charging and discharging power plan of the energy storage system, and the curtailment strategy of wind and solar power.
[0083] The robust optimal scheduling strategy is sent to the new energy power station monitoring and energy storage management module. In the next scheduling cycle, the updated ultra-short-term power prediction data is obtained, the sub-Bruker fuzzy set is updated on a rolling basis, and the robust optimal scheduling strategy is solved again.
[0084] In this embodiment, the rolling optimization mechanism can continuously track the changes in the prediction error of new energy output and continuously correct the plan deviation during the scheduling execution process, which significantly improves the adaptability of the scheduling strategy to uncertainty fluctuations.
[0085] The method for extracting features from the prediction error sequence using an unsupervised clustering algorithm includes:
[0086] Using the magnitude of the prediction error and the time period as clustering feature dimensions, the K-means clustering algorithm is used to divide the prediction error sequence into K typical error scenario categories, with the value of K ranging from 5 to 20.
[0087] For each category, the probability of scenario occurrence, mean error vector, and covariance matrix of the corresponding category are calculated as typical error distribution characteristics of the uncertainty of new energy output.
[0088] In this embodiment, the process of the K-means clustering algorithm is as follows:
[0089] The prediction error sequence forms the original dataset. Each sample point The feature vector is d-dimensional, where d is twice the number of scheduling period T. The first T dimensions are the prediction error magnitude of each period, and the last T dimensions are the one-hot encoded period identifier of the corresponding period. The Z-score standardization method is used to standardize the original dataset, converting each feature dimension into standard normal distribution data with a mean of 0 and a standard deviation of 1, so as to eliminate the difference in dimensions between the error magnitude and the period identifier.
[0090] K sample points were randomly selected from the standardized dataset as the initial cluster centers. The value of K ranges from 5 to 20. To improve the stability of the clustering results, the K-means++ initialization strategy is adopted, that is, the first cluster center is randomly selected, and each subsequent cluster center selects the sample point with the largest squared Euclidean distance from the selected center, so as to improve the representativeness of the initial center distribution.
[0091] For each sample point in the standardized dataset Calculate the Euclidean distance between the sample point and each cluster, and assign the sample point to the category of the nearest cluster center to form K clusters;
[0092] For each cluster, calculate the mean vector of all sample points in that cluster, and use it as the new cluster center;
[0093] Calculate the sum of changes in all cluster centers before and after this iteration. If it is less than the preset convergence threshold, or if the number of iterations reaches the preset maximum number of iterations, then terminate the iteration and output the final clustering result.
[0094] After iterative convergence, for each scenario category, the probability of that category appearing in historical samples is calculated; the mean vector and covariance matrix of all sample points within that category are calculated as typical error distribution features of new energy output uncertainty, which are used to construct Wasserstein fuzzy sets.
[0095] In this embodiment, the specific steps for extracting features from the prediction error sequence using the K-means clustering algorithm are as follows:
[0096] Using the prediction error amplitude and the time period as clustering feature dimensions, the difference between the actual output and the predicted output is expressed in per-unit value form. The rated capacity of the station is used as the basis for the prediction error amplitude, and the time period is divided into 15-minute units. A total of 96 time periods throughout the day are used as the time periods to construct the feature vector of each sample.
[0097] The K-means algorithm is used, with Euclidean distance as the similarity measure between samples, to divide the prediction error sequence into K typical error scenario categories;
[0098] The optimal K value was determined by using the silhouette coefficient in the range of [5,20]. The number of cluster categories K was set to a range of 5 to 20. If the K value is too small, it is difficult to characterize the multimodal features of the error distribution. If the K value is too large, it will lead to insufficient sample size for some categories and unreliable statistical features.
[0099] For each category, the probability of scenario occurrence, mean error vector, and covariance matrix of that category are calculated as typical error distribution characteristics of uncertainty in new energy output.
[0100] In this embodiment, the clustering dimensionality reduction strategy can effectively control the complexity of the fuzzy set, making the optimization model based on Wasserstein distance solvable in engineering practice. While maintaining the solution accuracy, it significantly shortens the calculation time and meets the timeliness requirements of daily rolling scheduling of new energy power stations.
[0101] The method for constructing split-Bruker bar fuzzy sets using the Wasserstein distance data-driven approach includes:
[0102] An empirical distribution is constructed based on N historical prediction error samples, with the empirical distribution as the center and the radius parameter as the boundary. Construct a Wasserstein fuzzy set with radius .
[0103] In this embodiment, an empirical distribution is constructed using historical prediction error samples, and a fuzzy set is directly generated in the probability distribution space using the Wasserstein distance as a metric. No prior assumptions need to be made about the functional form of the true distribution. This setting makes the construction process of the fuzzy set completely data-driven, avoiding model risks caused by improper selection of prior distribution.
[0104] The Wasserstein fuzzy set is defined as all Wasserstein distances from the empirical distribution not exceeding a certain threshold. The set of probability distributions;
[0105] The Wasserstein distance is used to measure the degree of difference between any two probability distributions, and the radius parameter... The expression is:
[0106]
[0107] in, The risk aversion coefficient is set to a range of values. , For the number of historical samples, The confidence level is set to a range of values. ;
[0108] In this embodiment, The range of confidence levels is based on the general settings for finite-sample performance guarantees in Wasserstein's finite-sample bar optimization. This represents the lower bound of the probability that the fuzzy set contains the true distribution. The higher the value, the larger the radius required to guarantee this confidence level, and the more conservative the decision.
[0109] In this embodiment, the radius parameter The process of obtaining the value includes:
[0110] Let the number of historical samples be N, and the empirical distribution be... The actual distribution is According to the finite sample set inequality of Wasserstein distance, for any confidence level There exists a constant C such that
[0111]
[0112] Among them, the risk aversion coefficient λ is introduced as a constant multiplication factor to adjust the degree of conservatism.
[0113] The specific data processing flow is as follows:
[0114] The historical dataset is divided into a training set and a validation set, and the candidate radius value set is... Solve the optimization problem separately, and select the radius value that minimizes the overall risk on the validation set as the final parameter;
[0115] The risk aversion coefficient The larger the value of , the larger the radius of the fuzzy bar set. The larger the value, the wider the coverage of the uncertainty set.
[0116] In this embodiment, The value of λ can be determined based on the historical assessment records and risk tolerance of the new energy power station. Data-driven optimization is carried out through k-fold cross-validation: the historical dataset is divided into a training set and a validation set, the optimization problem is solved for each set of candidate λ values, and the λ value with the lowest comprehensive assessment risk on the validation set is selected as the final parameter. The default value is λ=1.0.
[0117] In this embodiment, a risk aversion coefficient λ is introduced as a direct adjustment factor for the radius of the fuzzy set. The larger the value of λ, the wider the probability distribution covered by the Wasserstein sphere, and the stronger the protection against uncertainty in the optimization decision. This mechanism allows decision-makers to flexibly adjust the value of λ according to the risk tolerance and operation strategy of the new energy power station: when λ takes a smaller value, the fuzzy set narrows, and the optimization result tends to be more economically optimal; when λ takes a larger value, the fuzzy set widens, and the optimization result tends to prioritize robustness, thus realizing an explicit quantitative trade-off between robustness and economy.
[0118] In this embodiment, the data flow using the Wasserstein distance data-driven method is as follows:
[0119] Based on the acquired historical actual output data and historical forecast data of new energy power plants, the forecast error at each time point is calculated according to the time period alignment method, forming an original forecast error sample set. Where N is the total number of historical samples, and each sample Let T be a T-dimensional vector, where T is the number of time periods within the scheduling period, and the t-th element represents the prediction error value of the i-th historical sample in time period t. The prediction error is determined according to... calculate, For the i-th sample, the actual output during time period t. For the corresponding predicted output;
[0120] Z-score standardization is performed on each time period dimension in the constructed original prediction error sample set D to convert the prediction error data of each time period into standard normal distribution data with a mean of 0 and a standard deviation of 1, so as to eliminate the influence of the difference in units between different time periods on the distance measurement.
[0121] We will obtain K typical error scenario categories and their probability of occurrence. As input, the cluster centers of each category Represents the typical characteristics of all samples within this category, expressed as the probability of occurrence of each category. As the weights of the corresponding cluster centers, a weighted empirical distribution is constructed. ,in To cluster center The Dirac measure at the location; weighted cluster centers are used to replace the original samples to construct the empirical distribution, so that the number of support points of the empirical distribution is compressed from the number of original samples N to the number of clusters K;
[0122] For any two probability distributions P and Q defined on the space of values of uncertain variables, the Wasserstein distance between them is defined as:
[0123]
[0124] in, To be defined in the product space The joint probability distribution on, The marginal distributions are P and Q, respectively. for and The Euclidean norm between them;
[0125] Calculation using weighted empirical distribution The radius parameter of the Wasserstein fuzzy set at the center of the sphere Its expression is:
[0126]
[0127] in, The risk aversion coefficient ranges from 0.5 to 5.0, where N is the original number of historical samples. The confidence level ranges from 0.90 to 0.99; this radius parameter The risk aversion coefficient decreases as the number of historical samples N increases. It increases with the increase of confidence level. Increased as a result;
[0128] The constructed weighted empirical distribution Centered on the sphere, calculated Construct Wasserstein-partial Brønsted fuzzy sets with radius .
[0129] During the rolling optimization process, after obtaining updated ultra-short-term power prediction data and actual power output data, the new samples are added to the historical sample set, the total number of historical samples is updated, and the radius parameter is recalculated based on the updated N value. This enables the Wasserstein fuzzy set to shrink adaptively as data accumulates.
[0130] In this embodiment, a fuzzy set construction method based on Wasserstein distance is adopted. The statistical confidence of the empirical distribution is quantitatively characterized by the radius parameter θ. According to the large deviation theory, when the number of historical samples N is finite, the Wasserstein sphere centered on the empirical distribution and with radius θ contains the neighborhood range into which the real distribution falls with a high probability, providing decision-makers with a quantifiable statistical confidence guarantee.
[0131] include:
[0132] In the comprehensive assessment risk avoidance decision-making model based on conditional value of risk, the objective function is to maximize the total daily revenue of the new energy power station. The total revenue includes electricity sales revenue minus energy storage operation costs and assessment penalty costs.
[0133] In this embodiment, the assessment penalty cost for the day-ahead prediction accuracy and the assessment penalty cost for the real-time dispatch instruction deviation are directly embedded into the objective function. This establishes an explicit mathematical relationship between the assessment penalty and core dispatch variables such as grid-connected power plans and energy storage charging and discharging decisions for each time period. This allows the dispatch optimization process to "perceive" the direct impact of each decision on the assessment score and proactively seek dispatch schemes to reduce assessment penalties during the planning stage, fundamentally changing the ex-post passive nature of assessment risk management.
[0134] The assessment and penalty costs include the assessment and penalty costs for day-ahead forecast accuracy and the assessment and penalty costs for real-time dispatch instruction deviation.
[0135] The penalty cost for the day-ahead forecast accuracy assessment is determined based on the deviation between the day-ahead power forecast accuracy of the new energy power plant and the assessment threshold.
[0136] The penalty cost for deviation assessment of real-time dispatch instructions is determined based on the absolute deviation between the actual grid-connected power of the new energy power station and the dispatch plan power.
[0137] In this embodiment, when the prediction accuracy is lower than the assessment threshold, the penalty cost increases linearly with the decrease in accuracy; when the accuracy meets the target, the penalty is zero. This setting guides the optimization model to actively align the grid-connected power plan with the predicted power when formulating the day-ahead plan, avoiding assessment failure caused by deliberately deviating from the predicted value to obtain short-term economic benefits. The threshold segmentation structure of this invention is more in line with the actual design logic of the power grid assessment rules, so that the compliance of the scheduling strategy under the assessment framework is intrinsically guaranteed.
[0138] Establish a comprehensive risk aversion decision-making model based on conditional value of risk, with the objective function being the maximization of the total daily revenue of the new energy power plant, including:
[0139] The expression for the objective function is:
[0140]
[0141] in, This represents the total number of time periods within the scheduling cycle. For time period index, Uncertain variables in contributing to new energy sources The electricity price for period t. For time period t, under uncertain variables Grid-connected power under the achieved conditions The energy storage operating cost for time period t is calculated according to... Calculate, where, This is the depreciation cost factor per unit of energy storage. , These represent the charging power and discharging power of the energy storage system during time period t, respectively. For time period t, under uncertain variables The performance evaluation and penalty costs include day-ahead forecast accuracy evaluation and penalty for real-time dispatch instruction deviation.
[0142] In this embodiment, the expected penalty term in the objective function guides the optimization model to reduce the average assessment cost in normal scenarios, while the CVaR constraint term forces the model not to exceed the risk tolerance limit in extreme tail scenarios. The two work together to enable the model to pay attention to both the "high frequency and low loss" normal assessment deviations and prevent the "low frequency and high loss" extreme assessment events when making decisions, thus forming full spectrum coverage of assessment risks.
[0143] The assessment and penalty costs The expression is:
[0144]
[0145] in, , These are the penalty coefficients for prediction accuracy and scheduling instruction deviation in time period t, respectively. For time period t, under uncertain variables The achieved daily forecast accuracy These are the forecast accuracy assessment thresholds issued by the power grid dispatching agency. For time period t, under uncertain variables Actual grid-connected power under the current conditions The planned grid-connected power for time period t;
[0146] The conditional value at risk (CVaR) of the assessment penalty cost is defined as follows:
[0147]
[0148] in, The confidence level is set to a range of values. , As an auxiliary variable, This represents the expectation operator under probability distribution P;
[0149] In this embodiment, the β interval setting ensures that the optimization model's control granularity for assessment risks is precisely aligned with the actual threat level of the power grid assessment rules, avoiding extreme situations of excessive conservatism or insufficient protection.
[0150] In this embodiment, the CVaR of the assessment penalty cost is added to the model as an independent hard constraint, which directly limits the conditional expected value of the assessment penalty under the worst β quantile scenario to not exceed the preset threshold. This enables the optimization model to proactively reserve adjustment capacity for extreme scenarios when making decisions, fundamentally improving assessment risk management from "passively bearing average consequences" to "proactively managing extreme risks".
[0151] In this embodiment, the data processing flow of the comprehensive assessment risk avoidance decision-making model is as follows:
[0152] The system acquires historical actual output data, historical forecast data, dispatch instructions issued by the power grid, and power grid dispatch assessment rules of new energy power plants. Based on the historical actual output data and historical forecast data, it calculates the forecast error for each time period to form an original forecast error sequence. The Z-score standardization method is used to standardize the forecast error sequence to eliminate the impact of the difference in dimensions between different time periods on the subsequent cluster analysis.
[0153] Using the magnitude of the prediction error and the time period as clustering feature dimensions, the K-means clustering algorithm is used to divide the standardized prediction error sequence into K typical error scenario categories. For each category, the probability of scenario occurrence, the mean error vector, and the covariance matrix of that category are calculated. The probability of scenario occurrence, the mean error vector, and the covariance matrix are output as typical error distribution features of the uncertainty of new energy output.
[0154] Using each cluster center as a support point and the probability of occurrence of each category as the corresponding weight, a weighted empirical distribution is constructed; the Wasserstein distance is defined as a measure of the degree of difference between any two probability distributions, and the fuzzy set radius parameter is calculated.
[0155] Taking the maximization of the total daily revenue of new energy power stations as the objective function, the established comprehensive assessment risk avoidance decision model is rewritten into a three-layer structure of min-max-min. The three-layer structure is reduced to a combination problem of minimizing the outer layer and maximizing the middle layer. At the same time, through dual transformation, the probability distribution variables and expectation operators are eliminated, and the infinite-dimensional distribution optimization problem is transformed into a finite-dimensional deterministic programming problem. The CPLEX optimization solver is used with the branch and bound method as the main framework and the cutting plane method to perform global optimal solution and output a robust optimal scheduling strategy.
[0156] The robust optimal scheduling strategy is distributed to the new energy power plant monitoring system and the energy storage management system for execution. At the beginning of each scheduling cycle, updated ultra-short-term power prediction data is obtained. The remaining power of the energy storage system at the end of the previous scheduling cycle is used as the initial power of the current scheduling cycle. The current scheduling cycle is used as the optimization window, and the entire data processing process is re-executed to solve for the robust optimal scheduling strategy of the current cycle. The scheduling strategy for the first time period in the current cycle is distributed and executed. When the next scheduling cycle arrives, the optimization window slides until the rolling optimization of all scheduling cycles is completed.
[0157] The conditional value of risk (CVaR) is added as a hard constraint to the comprehensive risk aversion decision-making model, satisfying the following:
[0158]
[0159] in, The maximum acceptable risk threshold is preset for new energy power plants.
[0160] In this embodiment, the maximum tolerable assessment risk threshold preset for new energy power stations The method for determining it is as follows:
[0161] Historical assessment data of new energy power stations over the past 12 months were collected, and the monthly assessment penalty costs were calculated. The 90th percentile of the historical assessment penalty costs was used as the threshold. The baseline value is then adjusted upwards or downwards based on the risk tolerance of the site.
[0162] A certain percentage of the average daily electricity sales revenue of new energy power plants is used as the upper limit for assessing risk tolerance. It is usually set at 5% to 15% of the average daily electricity sales revenue. For power plants with strong risk tolerance, this percentage can be appropriately increased, while for power plants with poor performance records, this percentage should be appropriately reduced.
[0163] In scenarios where historical data is lacking, it is recommended to take... The default value is 10% of the daily electricity sales revenue corresponding to the rated capacity of the power station, which will be adjusted on a rolling basis according to the actual operating data.
[0164] include:
[0165] In the objective function, the revenue from electricity sales is calculated as the product of the electricity price in each time period and the grid-connected power.
[0166] The energy storage operating cost Calculated by multiplying the energy storage charging and discharging power by the energy storage charging and discharging unit depreciation cost coefficient;
[0167] The assessment and penalty costs Calculated based on the sum of the prediction accuracy penalty and the scheduling instruction deviation penalty for each time period;
[0168] The objective function holds true for all probability distributions covered by the fuzzy set, and the goal is to find a robust optimal solution that maximizes profit under all possible distributions.
[0169] In this embodiment, electricity sales revenue, energy storage operation costs, and assessment and penalty costs are uniformly incorporated into the objective function measured in monetary units. This achieves direct comparability and joint optimization of the three core decision dimensions in the operation of new energy power plants on the scale of economic value. This three-element unified framework transforms all physical quantities that were originally difficult to compare into economic quantities, eliminates the problem of subjective setting of weight coefficients in multi-objective optimization, and makes the optimization results have clear meaning.
[0170] The comprehensive assessment risk aversion decision-making model is set as a two-stage sub-Bruker optimization model, and its decision variables include:
[0171] The first-stage decision variable x includes the planned grid-connected power for each time period. And the binary variables of the charging and discharging states of the energy storage system at different times. , The decision variables in the first stage are uncertain variables. Determined before implementation, not subject to change. change;
[0172] Second-stage decision variables This includes the uncertainty variables in each time period. The adjustment of energy storage charging and discharging power under the following conditions , And the amount of wind and solar power curtailment The decision variables in the second stage are in the uncertainty variables Adjustments will be made based on the actual output after implementation.
[0173] In this embodiment, the hierarchical structure ensures that the scheduling plan is clearly executable in the day-ahead phase, while retaining room for flexible adjustment based on actual output in the real-time operation phase. The hierarchical decision-making structure satisfies the rigid commitment requirements of the scheduling plan while also taking into account the flexible adaptation requirements of operational adjustments.
[0174] The constraints of the comprehensive assessment risk aversion decision-making model include:
[0175] The upper and lower limits of the total output of the power station are used to limit the grid-connected power in each time period from not exceeding the maximum output capacity of the power station and not being lower than the minimum technical output.
[0176] Energy storage system charging and discharging power constraints are used to limit the energy storage charging power from not exceeding the maximum charging power and the discharging power from not exceeding the maximum discharging power in each time period.
[0177] Energy storage system capacity constraints are used to limit the remaining energy storage capacity in each time period to be between the minimum remaining capacity and the maximum remaining capacity, while satisfying the recursive relationship of energy storage capacity.
[0178] The mutual exclusion constraint of charge and discharge states is used to restrict the energy storage system from being in both charging and discharging states at the same time.
[0179] Tie line transmission power constraint is used to limit the grid-connected power in each time period from not exceeding the maximum transmission capacity of the tie line;
[0180] Power balance constraint is used to constrain grid-connected power to equal the actual output of new energy sources plus the energy storage discharge power minus the energy storage charging power minus the amount of wind and solar curtailment.
[0181] In this embodiment, a dynamic evolution relationship between the power of adjacent time periods is established through recursive equations, which ensures that the optimization model can accurately track the cumulative changes of energy storage power when formulating a full-day scheduling plan. This avoids infeasible solutions that violate physical laws, such as "continuing to discharge when the power is low" or "continuing to charge when the power is high". While ensuring the safe operation of the energy storage system at all times, this invention improves the engineering accuracy of power recursion through accurate modeling of efficiency parameters.
[0182] The method of employing a strong duality strategy to transform a fuzzy set containing nonlinear and uncertain constraints into an equivalent deterministic mixed-integer linear programming problem includes:
[0183] The comprehensive assessment risk avoidance decision model based on conditional risk value is rewritten as a three-layer structure of min-max-min, where the outer layer min determines the first-stage scheduling plan, the middle layer max searches the probability distribution that maximizes the assessment risk in the sub-Bruker fuzzy set, and the inner layer min determines the second-stage adjustment amount.
[0184] By using a strong dual strategy, the optimal value function of the inner-layer min problem is replaced with a dual form, and the three-layer structure is reduced to a combination problem of single-layer maximization and outer-layer minimization.
[0185] The Big-M method is used to linearize the product terms of binary and continuous variables in the constraints;
[0186] In this embodiment, Big-M exact linearization ensures that the energy storage state logic holds strictly in all scenarios, avoiding the risk that infeasible solutions due to relaxed constraints are incorrectly judged as feasible. At the same time, the Big-M constant adopts an upper bound value derived theoretically, achieving an optimal balance between numerical stability and computational efficiency.
[0187] The McCormick envelope method is used to relax the bilinear terms in the constraints, ultimately transforming the problem into an equivalent deterministic mixed-integer linear programming problem.
[0188] In this embodiment, the specific steps for transforming mixed-integer linear programming are as follows:
[0189] The comprehensive assessment risk avoidance decision model based on conditional risk value is rewritten as a three-layer structure of min-max-min, where the outer layer min determines the first-stage scheduling plan, the middle layer max searches the probability distribution that maximizes the assessment risk in the sub-Bruker fuzzy set, and the inner layer min determines the second-stage adjustment amount.
[0190] By utilizing the strong duality theory of linear optimization, the optimal value function of the inner-layer min problem is replaced with a dual form, and the three-layer structure is reduced to a combination problem of single-layer maximization and outer-layer minimization.
[0191] The Big-M method is used to linearize the product terms of binary and continuous variables in the constraints, for terms of the form... The product term, where b∈{0,1} are binary variables and x are continuous variables, introduces a large constant M, and adds constraints. , This transforms the nonlinear product terms into linear constraints.
[0192] The McCormick envelope method is used to relax and linearize the bilinear terms in the constraints, transforming the original nonlinear constraints into linear constraints for the bilinear terms.
[0193] In this embodiment, the exact dual transformation ensures the global optimality of the optimization solution and avoids the risk of suboptimal solutions brought about by approximation methods. This transformation makes the originally computationally unsolvable Bruker optimization problem theoretically solvable.
[0194] The process of solving the mixed-integer linear programming problem using an optimization solver, continuously updating the sub-Bruker fuzzy set, and resolving the robust optimal scheduling strategy includes:
[0195] The CPLEX optimization solver is used with the branch and bound method as the main framework, combined with the cutting plane method to add effective cutting constraints to the relaxation subproblem, and iteratively cuts the non-integer feasible region until the global optimal solution is obtained.
[0196] In this embodiment, the CPLEX optimization solver is used with the branch and bound method as the main framework. At the branch nodes, the simplex method is called to solve the relaxed linear programming subproblem to obtain the lower bound. At the same time, the cutting plane method is combined to add effective cutting constraints to the relaxed subproblem and iteratively prune the non-integer feasible region. This combined strategy organically combines the global search capability of branch and bound with the feasible region compaction capability of cutting plane: branch and bound ensures the global optimality of the solution, and cutting plane tightens the relaxed feasible region at each branch node to accelerate pruning. The combined strategy of this invention effectively reduces the size of the search tree and significantly reduces the solution time, so that the technical solution of this invention has an acceptable solution time in the actual deployment of large-scale new energy power plants.
[0197] The robust optimal scheduling strategy includes wind and solar power curtailment strategies, which include optimized allocation schemes for wind and solar power curtailment in each time period.
[0198] At the beginning of each scheduling cycle, the updated ultra-short-term power prediction data is obtained. The remaining power of the energy storage system at the end of the previous scheduling cycle is used as the initial power of the current scheduling cycle. With the current scheduling cycle as the optimization window, the steps of extracting typical error distribution features, constructing a multi-bar fuzzy set, and solving the decision model are re-executed to obtain the robust optimal scheduling strategy for the current scheduling cycle.
[0199] The scheduling strategy for the first time period within the current scheduling cycle is issued and executed. When the next scheduling cycle arrives, the sliding optimization window is used to repeat the execution until the rolling optimization of all scheduling cycles is completed.
[0200] In this embodiment, at the beginning of each scheduling cycle, the remaining power of the energy storage system at the end of the previous scheduling cycle is used as the initial power of the current scheduling cycle, realizing the closed-loop transfer of energy storage status. This setting ensures that each round of rolling optimization is based on the actual measured value of energy storage power rather than the predicted or estimated value, fundamentally eliminating the problem of open-loop planned power deviation caused by the hourly accumulation of prediction errors in the time dimension. The real state transfer mechanism of this invention ensures that each round of optimization starts from the actual physical state, ensuring the accuracy of the initial conditions of the optimization results and the feasibility of execution, and effectively avoiding the risk that the assessment constraints caused by the power base deviation will fail during real-time execution.
[0201] This invention incorporates the conditional risk value of performance evaluation penalties as an independent hard constraint into a two-stage sparse robust optimization model. This directly limits the performance evaluation risk exposure under extreme tail scenarios, enabling scheduling strategies to proactively avoid performance evaluation risks before uncertainties materialize. This shifts performance evaluation risk management from reactive post-event response to proactive pre-event control. By organically integrating the Wasserstein distance data-driven method with CVaR risk measurement, it eliminates prior assumptions about the probability distribution of new energy output. The introduction of a risk aversion coefficient as an adjustment parameter for the fuzzy set radius achieves a flexible trade-off between robustness and economy, overcoming the overly conservative nature of traditional robust optimization. To address the high shortcomings, a combined strategy of clustering dimensionality reduction and strong duality transformation is used to accurately transform the complex min-max-min three-level blobs optimization model into a solvable mixed-integer linear programming problem. A complete closed-loop decision-making system coupled with a two-stage decision structure and rolling time-domain optimization is constructed. In each scheduling cycle, the fuzzy set and scheduling strategy are dynamically updated based on the latest ultra-short-term forecast data and the actual state of charge of energy storage. This forms a closed-loop rolling optimization of data update, model reconstruction, strategy solution and command issuance, enabling the scheduling strategy to continuously adapt to changes in uncertainty and maximize the total daily revenue of new energy power plants while ensuring compliance with assessment requirements.
[0202] The above embodiments are merely exemplary embodiments of this application and are not intended to limit this application. The scope of protection of this application is defined by the claims. Those skilled in the art can make various modifications or equivalent substitutions to this application within its substance and scope of protection, and such modifications or equivalent substitutions should also be considered to fall within the scope of protection of this application.
Claims
1. A method for evaluating risk-averse decision-making of robust optimization-based new energy station scheduling, characterized in that, Includes the following steps: The system acquires historical actual output data, historical forecast data, dispatch instructions issued by the power grid, and dispatch assessment rules of the power grid. Based on the historical actual output data and historical forecast data, it calculates a prediction error sequence and uses an unsupervised clustering algorithm to extract features from the prediction error sequence to obtain typical error distribution characteristics of the uncertainty of new energy output. Based on the typical error distribution characteristics, a sub-Brubar fuzzy set is constructed using the Wasserstein distance data-driven method. The radius parameter of the sub-Brubar fuzzy set is a function of the risk aversion coefficient, which is used to adjust the radius parameter of the sub-Brubar fuzzy set to change the coverage of the uncertainty set. A comprehensive assessment risk aversion decision-making model based on conditional risk value is established. The objective function is to maximize the total daily revenue of new energy power plants. A strong dual strategy is adopted to transform the fuzzy set containing nonlinear and uncertain constraints into an equivalent deterministic mixed integer linear programming problem. An optimization solver is used to solve the mixed-integer linear programming problem, and a robust optimal scheduling strategy for new energy power plants under the worst-case power output fluctuation scenario is output. The scheduling strategy includes the grid-connected power plan of new energy in each time period, the charging and discharging power plan of the energy storage system, and the curtailment strategy of wind and solar power. The robust optimal scheduling strategy is sent to the new energy power station monitoring and energy storage management module. In the next scheduling cycle, the updated ultra-short-term power prediction data is obtained, the sub-Bruker fuzzy set is updated on a rolling basis, and the robust optimal scheduling strategy is solved again.
2. The robust optimization-based risk avoidance decision-making method for new energy power station scheduling assessment as described in claim 1, characterized in that, The method for extracting features from the prediction error sequence using an unsupervised clustering algorithm includes: Using the magnitude of the prediction error and the time period as clustering feature dimensions, the K-means clustering algorithm is used to divide the prediction error sequence into K typical error scenario categories, with the value of K ranging from 5 to 20. For each category, the probability of scenario occurrence, mean error vector, and covariance matrix of the corresponding category are calculated as typical error distribution characteristics of the uncertainty of new energy output.
3. The robust optimization-based risk avoidance decision-making method for new energy power station scheduling assessment as described in claim 1, characterized in that, The method for constructing split-Bruker bar fuzzy sets using the Wasserstein distance data-driven approach includes: constructing an empirical distribution based on N historical prediction error samples, constructing a Wasserstein fuzzy set with the empirical distribution as the center of the sphere, with a radius parameter as the radius, defining the Wasserstein fuzzy set as the set of all probability distributions with Wasserstein distance not exceeding from the empirical distribution; The Wasserstein distance is used to measure the difference between any two probability distributions, and the radius parameter The expression is: Wherein, is a risk aversion coefficient, and the value range is set to , is the number of historical samples, is a confidence level, and the value range is set to ; the greater the value of the risk aversion coefficient the greater the radius of the distribution robust fuzzy set the greater the coverage of the uncertainty set.
4. The method of claim 1, wherein, include: In the comprehensive assessment risk avoidance decision-making model based on conditional value of risk, the objective function is to maximize the total daily revenue of the new energy power station. The total revenue includes electricity sales revenue minus energy storage operation costs and assessment penalty costs. The assessment and penalty costs include the assessment and penalty costs for day-ahead forecast accuracy and the assessment and penalty costs for real-time dispatch instruction deviation. The penalty cost for the day-ahead forecast accuracy assessment is determined based on the deviation between the day-ahead power forecast accuracy of the new energy power plant and the assessment threshold. The penalty cost for deviation assessment of real-time dispatch instructions is determined based on the absolute deviation between the actual grid-connected power of the new energy power station and the dispatch plan power.
5. The robust optimization-based risk avoidance decision-making method for new energy power station scheduling assessment as described in claim 1, characterized in that, Establish a comprehensive risk aversion decision-making model based on conditional value of risk, with the objective function being the maximization of the total daily revenue of the new energy power plant, including: The expression for the objective function is: wherein, is the total number of time periods within a dispatch cycle, is the time period index, is the uncertainty variable of new energy output, is the electricity selling price of the t time period, is the grid-connected power of the t time period under the uncertainty variable realization, is the energy storage operation cost of the t time period, calculated according to wherein, is the unit depreciation cost coefficient of the energy storage, , are the charging power and discharging power of the energy storage system in the t time period, respectively, is the examination and punishment cost of the t time period under the uncertainty variable realization, including a day-ahead prediction accuracy examination and punishment item and a real-time dispatch instruction deviation examination and punishment item; The assessment and penalty costs The expression is: in, , These are the penalty coefficients for prediction accuracy and scheduling instruction deviation in time period t, respectively. For time period t, under uncertain variables The achieved daily forecast accuracy These are the forecast accuracy assessment thresholds issued by the power grid dispatching agency. For time period t, under uncertain variables Actual grid-connected power under the current conditions The planned grid-connected power for time period t; The conditional value at risk (CVaR) of the assessment penalty cost is defined as follows: in, The confidence level is set to a range of values. , As an auxiliary variable, This represents the expectation operator under probability distribution P; The conditional value of risk (CVaR) is added as a hard constraint to the comprehensive risk aversion decision-making model, satisfying the following: in, The maximum acceptable risk threshold is preset for new energy power plants.
6. The robust optimization-based risk avoidance decision-making method for new energy power station scheduling assessment as described in claim 5, characterized in that, include: In the objective function, the revenue from electricity sales is calculated as the product of the electricity price in each time period and the grid-connected power. The energy storage operating cost Calculated by multiplying the energy storage charging and discharging power by the energy storage charging and discharging unit depreciation cost coefficient; The assessment and penalty costs Calculated based on the sum of the prediction accuracy penalty and the scheduling instruction deviation penalty for each time period; The objective function holds true for all probability distributions covered by the fuzzy set, and the goal is to find a robust optimal solution that maximizes profit under all possible distributions.
7. The robust optimization-based risk avoidance decision-making method for new energy power station scheduling assessment as described in claim 1, characterized in that, The comprehensive assessment risk aversion decision-making model is set as a two-stage sub-Bruker optimization model, and its decision variables include: The first-stage decision variable x includes the planned grid-connected power for each time period. And the binary variables of the charging and discharging states of the energy storage system at different times. , The decision variables in the first stage are uncertain variables. Determined before implementation, not subject to change. change; Second-stage decision variables This includes the uncertainty variables in each time period. The adjustment of energy storage charging and discharging power under the following conditions , And the amount of wind and solar power curtailment The decision variables in the second stage are in the uncertainty variables Adjustments will be made based on the actual output after implementation.
8. The robust optimization-based risk avoidance decision-making method for new energy power station scheduling assessment as described in claim 1, characterized in that, The constraints of the comprehensive assessment risk aversion decision-making model include: The upper and lower limits of the total output of the power station are used to limit the grid-connected power in each time period from not exceeding the maximum output capacity of the power station and not being lower than the minimum technical output. Energy storage system charging and discharging power constraints are used to limit the energy storage charging power from not exceeding the maximum charging power and the discharging power from not exceeding the maximum discharging power in each time period. Energy storage system capacity constraints are used to limit the remaining energy storage capacity in each time period to be between the minimum remaining capacity and the maximum remaining capacity, while satisfying the recursive relationship of energy storage capacity. The mutual exclusion constraint of charge and discharge states is used to restrict the energy storage system from being in both charging and discharging states at the same time. Tie line transmission power constraint is used to limit the grid-connected power in each time period from not exceeding the maximum transmission capacity of the tie line; Power balance constraint is used to constrain grid-connected power to equal the actual output of new energy sources plus the energy storage discharge power minus the energy storage charging power minus the amount of wind and solar curtailment.
9. A robust optimization-based risk avoidance decision-making method for new energy power station scheduling assessment as described in claim 1, characterized in that, The method of employing a strong duality strategy to transform a fuzzy set containing nonlinear and uncertain constraints into an equivalent deterministic mixed-integer linear programming problem includes: The comprehensive assessment risk avoidance decision model based on conditional risk value is rewritten as a three-layer structure of min-max-min, where the outer layer min determines the first-stage scheduling plan, the middle layer max searches the probability distribution that maximizes the assessment risk in the sub-Bruker fuzzy set, and the inner layer min determines the second-stage adjustment amount. By using a strong dual strategy, the optimal value function of the inner-layer min problem is replaced with a dual form, and the three-layer structure is reduced to a combination problem of single-layer maximization and outer-layer minimization. The Big-M method is used to linearize the product terms of binary and continuous variables in the constraints; The McCormick envelope method is used to relax the bilinear terms in the constraints, ultimately transforming the problem into an equivalent deterministic mixed-integer linear programming problem.
10. A robust optimization-based decision-making method for risk avoidance in the scheduling assessment of new energy power stations, as described in claim 1, is characterized in that... At, The process of solving the mixed-integer linear programming problem using an optimization solver, continuously updating the sub-Bruker fuzzy set, and resolving the robust optimal scheduling strategy includes: The CPLEX optimization solver is used with the branch and bound method as the main framework, combined with the cutting plane method to add effective cutting constraints to the relaxation subproblem, and iteratively cuts the non-integer feasible region until the global optimal solution is obtained. The robust optimal scheduling strategy includes wind and solar power curtailment strategies, which include optimized allocation schemes for wind and solar power curtailment in each time period. At the beginning of each scheduling cycle, the updated ultra-short-term power prediction data is obtained. The remaining power of the energy storage system at the end of the previous scheduling cycle is used as the initial power of the current scheduling cycle. With the current scheduling cycle as the optimization window, the steps of extracting typical error distribution features, constructing a multi-bar fuzzy set, and solving the decision model are re-executed to obtain the robust optimal scheduling strategy for the current scheduling cycle. The scheduling strategy for the first time period within the current scheduling cycle is issued and executed. When the next scheduling cycle arrives, the sliding optimization window is used to repeat the execution until the rolling optimization of all scheduling cycles is completed.