A power distribution network planning adjustment method based on digital twinning

By constructing a digital twin model and multi-objective robust optimization, the problems of insufficient perception of actual operating status and multi-objective conflict in distribution network planning are solved, realizing high-precision, dynamically adaptive distribution network planning and improving the economy, reliability and renewable energy absorption capacity of the planning scheme.

CN123163045APending Publication Date: 2026-11-24KAIFENG POWER SUPPLY COMPANY STATE GRID HENAN ELECTRIC POWER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611242768.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-17
Publication Date
2026-11-24

AI Technical Summary

Technical Problem

Existing power distribution network planning methods lack the ability to accurately perceive and dynamically map the actual operating status, making it difficult to cope with the randomness of new energy output and the uncertainty of load fluctuations. The risk resistance and scenario adaptability of the planning schemes are insufficient, and the conflicts between multi-objective optimization objectives are difficult to coordinate, lacking a dynamic adjustment mechanism.

Method used

A digital twin model is constructed, which is combined with a load forecasting model and a distributed power generation output forecasting model. Through digital twin simulation and multi-objective robust optimization, the high-precision formulation and dynamic adaptive adjustment of the distribution network planning scheme are realized. Long short-term memory networks or gated cyclic units are used for prediction. Monte Carlo simulation is used to generate a variety of operating scenarios, and a closed-loop feedback mechanism is constructed for real-time adjustment.

Benefits of technology

It significantly improves the accuracy and resilience of power distribution network planning, achieves multi-objective synergistic optimization, enhances adaptability to uncertainties, and ensures the economy, reliability, and renewable energy absorption capacity of the planning scheme.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123163045A_ABST
    Figure CN123163045A_ABST
Patent Text Reader

Abstract

The application discloses a power distribution network planning adjustment method based on digital twinning, relates to the technical field of power distribution network planning, and comprises the following steps: acquiring physical topological structure, equipment parameters, historical operation data and geographic information data of a power distribution network, and constructing a digital twinning model; constructing a load prediction model and a distributed power output prediction model, generating a plurality of operation scene set based on a prediction result; performing digital twinning simulation on each operation scene set, obtaining network state distribution under different scenes, and quantifying system response characteristics under uncertainty; combining the network state distribution and the system response characteristics, constructing a multi-objective robust optimization model, taking economy, reliability, line loss and new energy consumption as optimization targets to solve a Pareto optimal solution set, and optimizing a power distribution network planning scheme; and feeding back actual operation data to the digital twinning model in real time, and realizing dynamic adjustment of the planning scheme. The application can effectively improve the precision, adaptability and dynamic adjustment capability of the power distribution network planning scheme.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of distribution network planning technology, specifically a distribution network planning and adjustment method based on digital twins. Background Technology

[0002] As a crucial link connecting the transmission network and end users in the power system, the rationality of the distribution network's planning directly impacts power supply reliability, economic operation, and the absorption capacity of new energy sources. In recent years, with the large-scale integration of distributed power sources and the continuous growth of new power loads, the structure and operating characteristics of the distribution network have undergone profound changes, making traditional distribution network planning methods inadequate for meeting the needs of new power system construction.

[0003] Currently, existing power distribution network planning methods have the following main shortcomings:

[0004] First, traditional planning methods rely heavily on historical statistical data and human experience for load forecasting and scheme formulation, lacking the ability to accurately perceive and dynamically map the actual operating status of the distribution network. As a result, there is a large deviation between the planning results and the actual operating status of the power grid, making it difficult to guide precise investment.

[0005] Second, most existing planning methods are based on deterministic scenarios for scheme design, failing to fully consider the coupled effects of multiple uncertain factors such as the randomness of new energy output, the uncertainty of load fluctuations, and the randomness of equipment failures. As a result, the planning schemes lack the ability to withstand risks and adapt to different scenarios.

[0006] Third, once a traditional power distribution network planning scheme is determined, it is usually implemented in a fixed manner. It lacks a closed-loop feedback mechanism for dynamic evaluation and rolling adjustment based on actual power grid operation data. There is a serious disconnect between planning and operation, and it is unable to respond to changes in the power grid operation status in a timely manner.

[0007] Fourth, distribution network planning involves multiple optimization objectives, such as economy, reliability, reduction of line losses, and absorption of renewable energy. These objectives often conflict with each other, and existing methods struggle to achieve effective coordination and trade-offs among these multiple objectives, resulting in a need to improve the overall performance of planning schemes. Therefore, we propose a distribution network planning adjustment method based on digital twins. Summary of the Invention

[0008] The technical problem to be solved by the present invention is to overcome the existing defects and provide a distribution network planning and adjustment method based on digital twins, which can realize the high-precision formulation and dynamic adaptive adjustment of distribution network planning schemes, effectively improve the economy, reliability and adaptability to uncertainty of the planning schemes, and effectively solve the problems in the background technology.

[0009] To achieve the above objectives, the present invention provides the following technical solution: a distribution network planning and adjustment method based on digital twins, comprising the following steps:

[0010] S1: Obtain the physical topology, equipment parameters, historical operating data and geographic information data of the distribution network, construct a digital twin model of the distribution network, the digital twin model includes a topology model and an electrical model, and perform synchronous power flow simulation on the power grid state variables, and perform error correction on the simulation results based on the measurement residuals;

[0011] S2: Construct a load forecasting model and a distributed generation output forecasting model, predict node load and distributed generation output based on grid state variables, and feed the forecast results back to the digital twin model; generate a set of multiple operating scenarios based on historical load data, historical distributed generation output data and the forecast results;

[0012] S3: Perform digital twin simulations on each set of operating scenarios to obtain the network state distribution under different scenarios and quantify the system response characteristics under uncertainty;

[0013] S4: Combining the network state distribution and the system response characteristics, construct a multi-objective robust optimization model, with economy, reliability, line loss and new energy consumption as multi-objective optimization objectives, solve the Pareto optimal solution set, and optimize the distribution network planning and equipment investment scheme;

[0014] S5: The actual power distribution network investment data and operating status are transmitted back to the digital twin model in real time to adjust the electrical model and the prediction model of the digital twin model, so as to realize the dynamic adjustment of the planning scheme.

[0015] Furthermore, the construction of the digital twin model in step S1 also includes: establishing a data assimilation interface between the digital twin model and the physical power distribution network, performing consistency verification on the topology model based on real-time measurement data, and correcting the boundary conditions and initial state of the electrical model according to the verification results.

[0016] Furthermore, the construction of the digital twin model in step S1 also includes: establishing a multi-year planning layer for the power distribution network based on GIS data, obtaining operational status data by combining the digital twin model, determining the areas that need adjustment through risk assessment, and updating the layer.

[0017] Furthermore, the load forecasting model and the distributed power generation output forecasting model described in step S2 are implemented using long short-term memory networks or gated cyclic units.

[0018] Furthermore, the generation of multiple operating scenario sets in step S2 adopts the Monte Carlo simulation method. The operating scenario set includes at least peak load scenario, low load scenario, high penetration of new energy scenario, low penetration of new energy scenario, fault state scenario and planned maintenance state scenario. The fault state scenario includes line N-1 interruption fault and transformer out of operation fault.

[0019] Furthermore, the digital twin simulation described in step S3 includes performing dynamic power flow simulation for each planning scheme under different operating scenarios, and calculating the line load rate, node voltage deviation and network loss index under each scenario to evaluate the adaptability and robustness of the planning scheme under uncertain conditions.

[0020] Furthermore, the objective function of the multi-objective robust optimization model described in step S4 includes economic objectives, reliability objectives, line loss objectives, and new energy consumption objectives.

[0021] Furthermore, the economic objective is to minimize the total cost of distribution network planning and equipment investment; the reliability objective is to minimize line overload risk and power supply reliability loss, wherein the power supply reliability loss is quantified by power outage loss or loss of the number of users when power is out; the line loss objective is to minimize distribution network losses; and the renewable energy absorption objective is to maximize the absorption capacity of distributed power sources.

[0022] Furthermore, the multi-objective robust optimization model described in step S4 adopts a sub-barrel optimization method with the objective of minimizing the worst-case expected cost, and is solved using a non-dominated sorting genetic algorithm with an elitist strategy or a multi-objective particle swarm optimization algorithm.

[0023] Furthermore, the dynamic adjustment in step S5 also includes: a preset deviation threshold, which automatically triggers the re-optimization and adjustment of the planning scheme when the deviation between the actual operating data and the predicted data exceeds the preset threshold.

[0024] Compared with the prior art, the beneficial effects of the present invention are as follows: This distribution network planning and adjustment method based on digital twins has the following advantages:

[0025] 1. This invention achieves accurate mapping and real-time synchronization between the physical entities and virtual models of the power distribution network by constructing a high-fidelity digital twin model. The planning scheme is driven by real operating data, which significantly improves the planning accuracy and can effectively guide precise investment.

[0026] 2. This invention generates a set of typical operating scenarios, including peak load, off-peak load, high penetration of renewable energy, low penetration of renewable energy, fault state, and planned maintenance state, through Monte Carlo simulation. Combined with digital twin simulation, it performs dynamic power flow simulation and performance evaluation for each planning scheme under all scenarios, fully quantifies the impact of uncertainties such as renewable energy output and load fluctuations on the operation of the distribution network, and significantly improves the risk resistance and scenario adaptability of the planning scheme.

[0027] 3. This invention achieves dynamic evaluation and rolling updates of planning schemes by transmitting actual power distribution network investment data and operating status back to the digital twin model in real time. When the deviation between actual operating data and predicted data exceeds a preset threshold, it automatically triggers re-optimization, thus constructing a closed-loop feedback mechanism between planning and operation, overcoming the defects of traditional planning schemes being rigidly executed.

[0028] 4. This invention constructs a multi-objective robust optimization model that includes economy, reliability, line loss, and new energy consumption. It adopts the sub-Bruker optimization method with the goal of minimizing the worst-case expected cost, and uses a non-dominated sorting genetic algorithm with an elitist strategy or a multi-objective particle swarm optimization algorithm to solve the Pareto optimal solution set. This achieves effective coordination and trade-offs among multiple conflicting objectives, and significantly improves the overall performance of the planning scheme.

[0029] 5. This invention achieves high-precision prediction of load and renewable energy output through Long Short-Term Memory Network (LSTM) or Gated Recurrent Unit (GRU), providing an accurate data foundation for digital twin simulation and multi-objective optimization, and effectively improving the renewable energy absorption capacity. Attached Figure Description

[0030] Figure 1 This is a flowchart illustrating the overall workflow of the digital twin-based power distribution network planning and adjustment method of this invention. Detailed Implementation

[0031] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0032] Please see Figure 1 This invention provides a technical solution: a distribution network planning and adjustment method based on digital twins, comprising the following steps:

[0033] S1: Acquire the physical topology, equipment parameters, historical operating data, and geographic information data of the distribution network, construct a digital twin model of the distribution network, including a topology model and an electrical model, and perform synchronous power flow simulation on the power grid state variables. Correct the simulation results based on measurement residuals. The construction of the digital twin model also includes: establishing a data assimilation interface between the digital twin model and the physical distribution network, performing consistency verification on the topology model based on real-time measurement data, and correcting the boundary conditions and initial state of the electrical model based on the verification results. The construction of the digital twin model also includes: establishing a multi-year planning layer of the distribution network based on GIS data, acquiring operating status data in conjunction with the digital twin model, determining the areas that need adjustment through risk assessment, and updating the layer.

[0034] S2: Construct load forecasting models and distributed generation output forecasting models. Predict node loads and distributed generation outputs based on grid state variables, and feed the forecast results back to the digital twin model. Based on historical load data, historical distributed generation output data, and forecast results, generate multiple sets of operating scenarios. The load forecasting model and distributed generation output forecasting model are implemented using long short-term memory networks or gated cyclic units. The Monte Carlo simulation method is used to generate multiple sets of operating scenarios. The set of operating scenarios includes at least peak load scenarios, off-peak load scenarios, high penetration scenarios of new energy sources, low penetration scenarios of new energy sources, fault scenarios, and planned maintenance scenarios. Fault scenarios include line N-1 interruption faults and transformer out-of-operation faults.

[0035] S3: Perform digital twin simulation for each set of operating scenarios to obtain the network state distribution under different scenarios, quantify the system response characteristics under uncertainty, and perform digital twin simulation, including dynamic power flow simulation for each planning scheme under different operating scenarios, and calculate the line load rate, node voltage deviation and network loss index under each scenario to evaluate the adaptability and robustness of the planning scheme under uncertainty conditions.

[0036] S4: Combining network state distribution and system response characteristics, a multi-objective robust optimization model is constructed. With economy, reliability, line loss, and renewable energy absorption as the multi-objective optimization objectives, the Pareto optimal solution set is obtained to optimize distribution network planning and equipment investment schemes. The objective functions of the multi-objective robust optimization model include economic objectives, reliability objectives, line loss objectives, and renewable energy absorption objectives. The economic objective is to minimize the total cost of distribution network planning and equipment investment; the reliability objective is to minimize line overload risk and power supply reliability loss, which is quantified by power outage loss or the loss of the number of users during power outages; the line loss objective is to minimize distribution network losses; and the renewable energy absorption objective is to maximize the absorption capacity of distributed power sources. The multi-objective robust optimization model adopts a sub-barrel optimization method with the objective of minimizing the worst-case expected cost, and uses a non-dominated sorting genetic algorithm with an elitist strategy or a multi-objective particle swarm optimization algorithm for solution.

[0037] S5: The actual power distribution network investment data and operating status are transmitted back to the digital twin model in real time to adjust the electrical model and prediction model of the digital twin model, so as to realize the dynamic adjustment of the planning scheme. The dynamic adjustment also includes: preset deviation threshold. When the deviation between the actual operating data and the prediction data exceeds the preset threshold, the planning scheme is automatically triggered to be re-optimized and adjusted.

[0038] The present invention provides the following embodiments:

[0039] Example 1

[0040] This embodiment uses the power distribution network of an industrial park as an example to verify the specific implementation effect of the load forecasting model and the distributed power generation output forecasting model in step S2 of the present invention. The industrial park covers an area of ​​approximately 8 square kilometers and includes 12 manufacturing plants, 3 commercial complexes, 2 research institutions, 10 10kV feeders, 65 distribution transformers, and a rooftop distributed photovoltaic installed capacity of approximately 4.5MW. The park's average annual load is approximately 8.5MW, and the peak summer load is approximately 12.3MW. Historical load data and photovoltaic output data from the past two years (January 2024 to December 2025) of the park were selected as the training set and validation set, respectively, with a sampling interval of 15 minutes, totaling approximately 70,080 data points.

[0041] I. Specific Implementation of the LSTM Prediction Model

[0042] A three-layer LSTM neural network was constructed, with 24 nodes in the input layer (corresponding to the past 24 time points, i.e., 6 hours of historical data), 128 nodes in the hidden layer, and 4 nodes in the output layer (corresponding to the next 4 time points, i.e., the predicted value for the next hour). The model was trained using the Adam optimizer with an initial learning rate of 0.001, a batch size of 64, and a maximum of 200 training epochs. An early stopping mechanism (patience=20, i.e., terminating training early when the validation set loss does not decrease for 20 consecutive epochs) was implemented to prevent overfitting. Input features included: historical load values, historical photovoltaic output values, hourly index (0-23), day of the week index (0-6), day type identifier (weekday / holiday), temperature, humidity, and light intensity. Temperature, humidity, and light intensity were based on the 1-hour forecast values ​​issued by the local meteorological bureau. The training and validation sets were split in an 8:2 ratio.

[0043] After training, the results were tested on the validation set. The mean absolute percentage error (MAPE) for predicting the load for the next hour was 3.87%, the MAPE for predicting photovoltaic output was 5.21%, and the root mean square error (RMSE) was 0.42MW (approximately 4.9% for an average load of 8.5MW) and 0.18MW (approximately 8.6% for an average photovoltaic output of approximately 2.1MW), respectively.

[0044] II. Specific Implementation of the GRU Prediction Model

[0045] A three-layer GRU neural network was constructed, with the model structure consistent with the aforementioned LSTM (24 nodes in the input layer, 128 nodes in the hidden layer, and 4 nodes in the output layer), using the same optimizer, learning rate, batch size, and upper limit for training epochs. The input features were identical to those of the LSTM model. Tested on the same validation set, the GRU model predicted a MAPE of 3.52% for the load forecast for the next hour and a MAPE of 4.83% for the photovoltaic output forecast, with RMSEs of 0.38MW (approximately 4.5% of the average load of 8.5MW) and 0.16MW (approximately 7.6% of the average photovoltaic output of approximately 2.1MW), respectively.

[0046] III. Comparison and Selection of the Two Models

[0047] Comparing training efficiency under the same hardware environment (NVIDIA RTX 3060 GPU, 12GB VRAM): LSTM training takes approximately 1.8 seconds per round, with a maximum of 200 rounds. Training was terminated early due to the validation set loss failing to improve for 20 consecutive rounds starting from round 158, resulting in 178 rounds of actual training and a total of approximately 320 seconds. GRU training takes approximately 1.5 seconds per round, also terminating early due to the validation set loss failing to improve for 20 consecutive rounds starting from round 145, resulting in 165 rounds of actual training and a total of approximately 248 seconds. GRU training efficiency is improved by approximately 22.5%. In terms of prediction accuracy, GRU slightly outperforms LSTM in both load forecasting and photovoltaic forecasting. Considering both training efficiency and prediction accuracy, the GRU model is the preferred deployment model for this park. However, it should be noted that for scenarios with longer time series characteristics (such as forecasting the next 24 hours) or larger data volumes (such as provincial power grid scale), LSTM may perform better in certain situations due to its more complex gating structure. Therefore, in practical applications, LSTM and GRU can be flexibly selected according to the specific scenario. This embodiment verifies that both models can effectively achieve high-precision prediction of load and photovoltaic output, and successfully feed the prediction results back to the digital twin model, providing an accurate data foundation for subsequent scenario generation and simulation.

[0048] Example 2

[0049] This embodiment takes the power distribution network of a new urban area as an example to explain in detail the specific quantification method of "power supply reliability loss" in step S4. The new area has a planned area of ​​12 square kilometers and a planned population of approximately 80,000. It contains 6 residential communities, 2 commercial centers, 3 schools, 1 hospital, 14 10kV feeders, and 85 distribution transformers.

[0050] I. Specific methods for quantifying power loss during power outages

[0051] Suppose that during a thunderstorm, a 10kV feeder (number F-07) in this new district trips due to a lightning strike, with the fault lasting for 2.5 hours (from 14:30 to 17:00). The load carried by this line is as follows: residential load approximately 2.8MW, commercial load approximately 1.2MW, public service load such as schools and hospitals approximately 0.5MW, and total load approximately 4.5MW.

[0052] The formula for calculating power loss during a power outage is:

[0053] Power outage energy loss (kWh) = Average load during the outage (kW) × Outage duration (h)

[0054] In this fault case: power loss due to residential load outage = 2.8MW × 2.5h = 7000kWh; power loss due to commercial load outage = 1.2MW × 2.5h = 3000kWh; power loss due to public service load outage = 0.5MW × 2.5h = 1250kWh. The total power loss due to this fault = 7000 + 3000 + 1250 = 11250kWh.

[0055] If this loss is converted into economic cost, calculated based on the local average electricity price of 0.65 yuan / kWh, then the economic cost of the power outage loss due to this fault is 11250 × 0.65 = 7312.5 yuan. If the line experiences similar faults 3 times a year, then the economic cost of the power outage loss for the whole year is 7312.5 × 3 ≈ 21937.5 yuan.

[0056] II. Specific methods for quantifying the loss of the number of users during power outages

[0057] The formula for calculating the number of users lost during a power outage is:

[0058] Loss of users due to power outage (users·h) = Number of users affected (users) × Duration of power outage (h)

[0059] In this fault case, line F-07 serves approximately 2,500 residential users, approximately 80 commercial users (based on legal entity metering points), and 4 public service users (3 schools and 1 hospital, each based on legal entity metering points). The power outage loss for residential users is 2,500 households × 2.5 hours = 6,250 households / hour; for commercial users, it is 80 households × 2.5 hours = 200 households / hour; and for public service users, it is 4 households × 2.5 hours = 10 households / hour. The total power outage loss due to this fault is 6,250 + 200 + 10 = 6,460 households / hour.

[0060] III. Application in Multi-Objective Robust Optimization Models

[0061] In the multi-objective robust optimization model of step S4, the reliability objective is defined as minimizing the weighted sum of line overload risk and power supply reliability loss. The power supply reliability loss is comprehensively evaluated using the two quantification methods mentioned above: for areas dominated by residential loads, the focus is on the number of households lost during power outages; for areas dominated by industrial and commercial loads, the focus is on the power outage loss and its economic conversion cost. During the optimization process, the power supply reliability loss for each planning scheme under each operating scenario is calculated one by one according to the above methods, and the expected value of the power supply reliability loss under all scenarios is used as the quantified value of the reliability objective to participate in the solution of the Pareto optimal set. By using power outage loss and the number of households lost during power outages as explicit quantitative indicators of power supply reliability loss, the reliability objective in the multi-objective optimization model has a calculable and comparable numerical basis, making the optimization results more scientific and operable.

[0062] Example 3

[0063] This embodiment uses a coastal city's power distribution network as an example to verify the triggering conditions and effects of the dynamic adjustment mechanism in step S5 of the present invention, focusing on verifying the impact of different preset deviation threshold values ​​on the dynamic adjustment effect of the planning scheme. This coastal city is affected by seasonal typhoons and high summer temperatures, resulting in significant fluctuations in load and distributed photovoltaic output. Therefore, the power distribution network planning scheme needs to possess strong dynamic adaptability. The city's power distribution network has an average annual maximum load of approximately 58MW, and the total installed capacity of distributed photovoltaic power in the region is approximately 12MW.

[0064] I. Setting Scheme for Preset Deviation Threshold

[0065] In the digital twin model of this city's power distribution network, a preset deviation threshold δ is used to determine whether the deviation between actual operating data and predicted data triggers a re-optimization of the planning scheme. The formula for calculating the deviation rate is:

[0066] Deviation rate = |Actual value - Predicted value| / Predicted value × 100%

[0067] To verify the impact of different threshold values, this embodiment sets up three comparison schemes:

[0068] Option A: δ=10%, meaning that re-optimization is triggered when the deviation rate exceeds 10%;

[0069] Option B: δ=15%, meaning that re-optimization is triggered when the deviation rate exceeds 15%;

[0070] Option C: δ=20%, which means that re-optimization is triggered when the deviation rate exceeds 20%.

[0071] II. Dynamically Adjusting Trigger Instances

[0072] In the actual operation of the city's power distribution network, the maximum load in the area reached 68.5MW in July 2026 due to the continuous high temperature. However, the maximum load predicted by the digital twin model based on historical data was 58.2MW, with a deviation rate of |68.5−58.2| / 58.2×100%=17.7%.

[0073] Based on the above three threshold schemes:

[0074] Option A (δ=10%): 17.7%>10%, triggering re-optimization. The digital twin model automatically initiates recalculation steps S2 to S4, outputting the adjusted planning scheme, adding one 10kV tie line and two distribution transformers for capacity expansion. The response time is approximately 4 hours from deviation detection to output of the new scheme.

[0075] Option B (δ=15%): 17.7%>15%, triggering re-optimization. The output adjustment scheme is basically the same as Option A (adding 1 tie line and increasing the capacity of 2 transformers), with a response time of approximately 4 hours.

[0076] Option C (δ=20%): 17.7%<20%, no re-optimization was triggered, and the planning scheme remains unchanged.

[0077] III. Comparative Analysis of Different Threshold Schemes

[0078] In actual operation and verification, the performance of the three schemes is as follows (the following statistics refer to the number of dynamic adjustments under normal operating conditions; data deviations under extreme weather conditions such as typhoons fall under the scope of emergency management and are at a different decision-making level from the conventional dynamic adjustment mechanism of this invention. They are implemented according to the emergency management plan and are not included in the statistical scope of conventional dynamic adjustments):

[0079] Option A (δ=10%) has a higher trigger frequency: under normal operating conditions in 2026, dynamic adjustments were triggered 6 times (3 times due to load deviation, 2 times due to photovoltaic output deviation, and 1 time due to topology changes caused by equipment failure), and an emergency management plan was implemented once during a typhoon (not included in regular statistics). The average response time for the 6 adjustments under normal operating conditions was 4.2 hours. This option is the most sensitive to changes in the power grid, but the frequent triggering of re-optimization also increases computational resources and manpower investment.

[0080] Option B (δ=15%) has a moderate triggering frequency: under normal operating conditions in 2026, dynamic adjustments were triggered 3 times (1 time for load deviation, 1 time for photovoltaic output deviation, and 1 time for equipment failure), and the emergency management plan was executed once during a typhoon (not included in routine statistics). The average response time under normal operating conditions is 3.8 hours. This option achieves a good balance between response sensitivity and resource consumption.

[0081] Option C (δ=20%) has a low trigger frequency: under normal operating conditions in 2026, dynamic adjustments were not triggered, and the emergency management plan was only implemented once during a typhoon (not included in regular statistics). If extreme deviations during typhoons are included in the statistics, it will be triggered once. Although it consumes the least computational resources, it sacrifices the ability to respond to regular fluctuations.

[0082] IV. Determining the Optimal Threshold

[0083] After comprehensive comparative analysis, Scheme B (δ=15%) performed best in this embodiment: it was within a reasonable range in several indicators, including the number of dynamic adjustments (3 times) under normal annual operating conditions, response time (3.8 hours / time), and the improvement effect of the adjusted planning scheme (a 22.3% decrease in line overload rate, a 6.5% decrease in network loss rate, and a 7.8% increase in photovoltaic absorption rate). Specifically, the 22.3% decrease in line overload rate refers to the reduction in the proportion of lines with a load rate exceeding 80% from approximately 22.5% before adjustment to approximately 17.5% after adjustment; the reduction in network loss rate from approximately 4.6% before adjustment to approximately 4.3% after adjustment; and the increase in photovoltaic absorption rate from approximately 88.5% before adjustment to approximately 95.4% after adjustment. Therefore, this embodiment recommends setting the preset deviation threshold to 15% as the optimal value that balances response sensitivity and computational resource consumption.

[0084] It should be noted that different distribution network areas can flexibly set preset deviation thresholds within the range of 10% to 20% based on their own load characteristics, renewable energy penetration rate, and equipment health level. For areas with large load fluctuations and high renewable energy penetration rates, a smaller threshold (e.g., 10%-12%) can be set to improve response sensitivity; for areas with relatively stable loads and mature grid structures, a larger threshold (e.g., 18%-20%) can be set to reduce unnecessary re-optimization. The specific numerical range of the aforementioned preset deviation thresholds and the basis for their selection have been fully explained in this embodiment through verification data from three sets of comparative schemes, providing clear implementation guidance for those skilled in the art.

[0085] The above description is merely an embodiment of the present invention and does not limit the patent scope of the present invention. Any equivalent structural or procedural transformations made based on the content of the present invention specification and drawings, or direct or indirect applications in other related technical fields, are similarly included within the patent protection scope of the present invention.

Claims

1. A distribution network planning and adjustment method based on digital twins, characterized in that, Includes the following steps: S1: Obtain the physical topology, equipment parameters, historical operating data and geographic information data of the distribution network, construct a digital twin model of the distribution network, the digital twin model includes a topology model and an electrical model, and perform synchronous power flow simulation on the power grid state variables, and perform error correction on the simulation results based on the measurement residuals; S2: Construct a load forecasting model and a distributed generation output forecasting model, predict node load and distributed generation output based on grid state variables, and feed the forecast results back to the digital twin model; generate a set of multiple operating scenarios based on historical load data, historical distributed generation output data and the forecast results; S3: Perform digital twin simulations on each set of operating scenarios to obtain the network state distribution under different scenarios and quantify the system response characteristics under uncertainty; S4: Combining the network state distribution and the system response characteristics, construct a multi-objective robust optimization model, with economy, reliability, line loss and new energy consumption as multi-objective optimization objectives, solve the Pareto optimal solution set, and optimize the distribution network planning and equipment investment scheme; S5: The actual power distribution network investment data and operating status are transmitted back to the digital twin model in real time to adjust the electrical model and the prediction model of the digital twin model, so as to realize the dynamic adjustment of the planning scheme.

2. The distribution network planning and adjustment method based on digital twins according to claim 1, characterized in that: The construction of the digital twin model in step S1 also includes: establishing a data assimilation interface between the digital twin model and the physical power distribution network, performing consistency verification on the topology model based on real-time measurement data, and correcting the boundary conditions and initial state of the electrical model according to the verification results.

3. The distribution network planning and adjustment method based on digital twins according to claim 1, characterized in that: The construction of the digital twin model in step S1 also includes: establishing a multi-year planning layer for the power distribution network based on GIS data, obtaining operational status data by combining the digital twin model, determining the areas that need to be adjusted through risk assessment, and updating the layer.

4. The distribution network planning and adjustment method based on digital twins according to claim 1, characterized in that: The load forecasting model and the distributed power generation output forecasting model described in step S2 are implemented using long short-term memory networks or gated cyclic units.

5. The distribution network planning and adjustment method based on digital twins according to claim 1, characterized in that: The generation of multiple operating scenario sets in step S2 adopts the Monte Carlo simulation method. The operating scenario set includes at least peak load scenario, low load scenario, high penetration of new energy scenario, low penetration of new energy scenario, fault state scenario and planned maintenance state scenario. The fault state scenario includes line N-1 opening fault and transformer out of operation fault.

6. The distribution network planning and adjustment method based on digital twins according to claim 1, characterized in that: The digital twin simulation described in step S3 includes performing dynamic power flow simulation for each planning scheme under different operating scenarios, and calculating the line load rate, node voltage deviation and network loss index under each scenario to evaluate the adaptability and robustness of the planning scheme under uncertainty conditions.

7. The distribution network planning and adjustment method based on digital twins according to claim 1, characterized in that: The objective function of the multi-objective robust optimization model in step S4 includes economic objectives, reliability objectives, line loss objectives, and new energy consumption objectives.

8. The distribution network planning and adjustment method based on digital twins according to claim 7, characterized in that: The economic objective is to minimize the total cost of distribution network planning and equipment investment; the reliability objective is to minimize line overload risk and power supply reliability loss, which is quantified by power outage power loss or the number of users lost when power is out; the line loss objective is to minimize distribution network losses; and the renewable energy absorption objective is to maximize the absorption capacity of distributed power sources.

9. The distribution network planning and adjustment method based on digital twins according to claim 1, characterized in that: The multi-objective robust optimization model described in step S4 adopts a sub-barbaric optimization method with the goal of minimizing the worst-case expected cost, and is solved using a non-dominated sorting genetic algorithm with an elitist strategy or a multi-objective particle swarm optimization algorithm.

10. A distribution network planning and adjustment method based on digital twins according to claim 1, characterized in that: The dynamic adjustment in step S5 also includes: a preset deviation threshold, which automatically triggers the re-optimization and adjustment of the planning scheme when the deviation between the actual running data and the predicted data exceeds the preset threshold.