Full-length steel pull rod in suspension structure
By adopting an integrated molded steel tie rod and threaded tooth connection design in the suspension structure, the traditional connecting sleeve is eliminated, solving the problem that the steel tie rod is affected by the indoor appearance, and achieving a simpler, more beautiful and reliable Multi-story floor suspension effect.
Patent Information
- Application Number
- CN202420446472.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-08
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-03-08
AI Technical Summary
In traditional suspension structures, when the steel pull rod is under a large stress, the overall length of the nut plus sleeve is too long, which affects the indoor appearance, and the multi-layer connecting sleeve increases the complexity and risk of stress.
An integrated molded steel pull rod is adopted, threaded teeth are installed at the bottom of each floor, floor bearing nuts are installed on the lower surface of the floor beam, stiffening sleeves are installed between adjacent floor beams, and connecting sleeves are cancelled to realize the entire steel Trolleys are hung on multiple floors.
The connection design is simplified, the aesthetics and reliability of the structure is improved, the complexity of stress is reduced, and the effect of hanging multi-story floors does not affect the indoor appearance.
Smart Images

Figure CN222120529U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the design fields of industrial buildings, civil buildings, bridges and the like, and in particular to a full-length steel pull rod in a suspension structure. Background Art
[0002] As a novel structural form, the suspended structure has its own advantages in terms of space layout, appearance, and stress characteristics, and has been used in more and more buildings. The structure can use trusses or cantilevered beams on the roof or intermediate transfer layer, and suspend the floor through steel tie rods, so that the column-free effect can be achieved.
[0003] In most cases, steel tie rods need to connect multiple floors. The length of a single steel tie rod is generally within 6 meters. If the length is too long, it needs to be connected through a sleeve. At the same time, the connection between the floor beam 5 and the steel tie rod also needs to be connected through a nut with a thread. In the traditional way, a floor load-bearing nut 1 is set at the bottom of the beam to transfer the floor load to the upper steel tie rod 2 through the thread, and then a connecting sleeve 3 is set downward to connect the upper steel tie rod 2 and the lower steel tie rod 4 (see the specific structure). Figure 1 ). Although this method can achieve the requirement of hanging multi-story floors, when the steel tie rod is subjected to a large force, the total length of the nut and sleeve exceeds 1m, which occupies a large part of the floor height and seriously affects the indoor appearance.
[0004] In view of the above situation, the patent applicant proposed a structural design of a full-length steel tie rod for a suspension structure, and correspondingly proposed a new supporting installation method, which can realize the suspension of multi-story floors without affecting the indoor visual effect.
[0005] The information disclosed in this background technology section is only intended to deepen the understanding of the overall background technology of the present invention, and should not be regarded as acknowledging or suggesting in any form that the information constitutes the prior art already known to those skilled in the art. Utility Model Content
[0006] The utility model aims to provide a full-length steel pull rod in a suspension structure to solve the technical problems existing in the prior art.
[0007] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0008] The utility model provides a full-length steel tie rod in a suspension structure, wherein the full-length steel tie rod is integrally formed, and the diameter of the lower steel tie rod is smaller than the diameter of the upper steel tie rod minus the depth required for the threaded teeth at the bottom of the upper steel tie rod; threaded teeth are arranged at the bottom of each layer of steel tie rod; and floor bearing nuts are arranged at corresponding positions on the lower surface of the floor beam in conjunction with the threaded teeth.
[0009] In the utility model, preferably, the surfaces of the steel tie rods between the floor beams of two adjacent layers are provided with stiffening sleeves.
[0010] By adopting the above technical solution, the utility model has the following beneficial effects:
[0011] The full-length steel tie rod of the present application eliminates the connecting sleeves between floors, and realizes the suspension of multiple floors by a whole steel tie rod. Considering the complexity of the force on the connecting sleeves, one more connecting sleeve means one more risk. Therefore, compared with the conventional method, the structural design of this patent is simpler, more beautiful and more reliable. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] In order to more clearly illustrate the specific implementation methods of the utility model or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0013] Figure 1 It is a schematic diagram of a segmented steel tie rod suspension structure in the prior art;
[0014] Figure 2 A schematic diagram of a full-length steel tie rod suspension structure provided in an embodiment of the utility model;
[0015] Figure 3 A schematic diagram of the processing and manufacturing of a full-length steel tie rod provided in an embodiment of the utility model;
[0016] Figure 4 A schematic diagram of step 1 of installing a full-length steel tie rod provided in an embodiment of the utility model;
[0017] Figure 5 A schematic diagram of step 2 of installing a full-length steel tie rod provided in an embodiment of the utility model;
[0018] Figure 6 A schematic diagram of step three of installing a full-length steel tie rod provided in an embodiment of the utility model;
[0019] Figure 7 A schematic diagram of step 4 of installing a full-length steel tie rod provided in an embodiment of the utility model;
[0020] Figure 8 A schematic diagram of step five of installing a full-length steel tie rod provided in an embodiment of the utility model. DETAILED DESCRIPTION
[0021] The technical solution of the utility model will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0022] The specific implementation of the present invention is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described here is only used to illustrate and explain the present invention, and is not used to limit the present invention.
[0023] Combination Figure 2 As shown, this embodiment provides a full-length steel tie rod in a suspension structure, the full-length steel tie rod is formed in one piece, and the diameter of the lower steel tie rod 4 is smaller than the diameter of the upper steel tie rod 2 minus the depth required for the threaded teeth at the bottom of the upper steel tie rod; threaded teeth are provided at the bottom of each layer of steel tie rod; and a floor bearing nut 1 is provided at a corresponding position on the lower surface of the floor beam in conjunction with the threaded teeth.
[0024] Preferably, the surfaces of the steel tie rods between the floor beams 5 of two adjacent layers are provided with stiffening sleeves 6 .
[0025] This application combines the law that the force on the steel tie rod decreases layer by layer from top to bottom, improves the process to lengthen the length of a single steel tie rod, reduces the number of joints connected by the intermediate sleeve, and proposes a corresponding installation method to ensure that the modified full-length steel tie rod has practical application value. This structural design and installation method can eliminate the connecting sleeves between floors and realize the suspension of multiple floors with a whole steel tie rod. Considering the complexity of the force on the connecting sleeve, one more connecting sleeve means one more risk. Therefore, compared with the conventional method, the structural design of this patent is more concise, beautiful and reliable.
[0026] The diameter of the steel tie rod for hanging structure is just required to bear the actual force, which has the characteristic of decreasing layer by layer. Therefore, the whole steel tie rod is machined to form a variable-section steel tie rod (see Figure 2 ), the cross-section of the steel tie rod decreases from top to bottom, and threads connected to nuts are set at the diameter-changing positions to fix the floor beams.
[0027] Combination Figure 3 As shown, the processing process of the full-length steel tie rod of the present application is as follows: first, a thread for bolt connection is machined on a steel rod of an initial diameter; then, a steel rod of a smaller diameter for the next floor is machined on the steel rod of the initial diameter; Figure 3 The reduced outer diameter of the steel rod after machining and the initial outer diameter of the steel rod are shown in FIG.
[0028] The installation method of the full-length steel tie rod needs to follow a reasonable sequence, including (see Figure 4-Figure 8 ):
[0029] Step 1: Set up temporary supports and install floor beams and suspension trusses from bottom to top; Figure 4 The figure shows a suspended truss 7, a suspended first floor beam 8, a suspended second floor beam 9 and a temporary support 10.
[0030] Step 2: Insert the full-length steel tie rod from top to bottom, insert it into the hanging floor beam, and then insert the floor bearing nut 1 from the bottom to the top. An anchor bolt 11 is set at the top of the full-length steel tie rod.
[0031] Step 3: Continue to insert the second-floor hanging beam downwards, and insert the floor bearing nut 1 from the bottom upwards.
[0032] Step 4: Tighten the anchor bolts 11, the upper floor load-bearing nuts 1 and the lower floor load-bearing nuts 1 to the designed positions in sequence from top to bottom.
[0033] Step 5: Remove the temporary support 10 and the installation is completed.
[0034] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, ordinary technicians in this field should understand that they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solution deviate from the scope of the technical solution of the embodiments of the utility model.
Claims
1. A full-length steel tie rod in a suspension structure, characterized in that: The full-length steel tie rod is integrally formed, and the diameter of the lower steel tie rod is smaller than the diameter of the upper steel tie rod minus the depth required for the threaded teeth at the bottom of the upper steel tie rod; threaded teeth are provided at the bottom of each layer of steel tie rod; and floor load-bearing nuts are provided at corresponding positions on the lower surface of the floor beam in conjunction with the threaded teeth.
2. The full-length steel tie rod in the suspension structure according to claim 1, characterized in that: The surfaces of the steel tie rods between the floor beams of two adjacent floors are provided with stiffening sleeves.