Sponge facility overflow well wall building construction equipment
By designing sponge facilities overflow well wall building construction equipment, and using motors to drive the sprockets and chains to drive the movement of the placement box, the inconvenience and destructive problems of raw material transportation in the existing technology are solved, and safe and efficient raw material transportation and construction efficiency are achieved. .
Patent Information
- Application Number
- CN202420016083.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-04
- Publication Date
- 2024-12-24
- Estimated Expiration
- 2034-01-04
AI Technical Summary
Existing construction equipment is not convenient for transporting construction raw materials into underground overflow wells. Traditional manual handling is dangerous and may damage the integrity of raw materials.
A sponge facilities overflow well wall building construction equipment is designed, including support frame, conveyor box, sprocket, chain and adjustment components. The motor drives the sprocket and chain to drive the placement box to achieve safe and efficient transportation of building raw materials. And adjust the conveyor box depth through the adjustment components to ensure material integrity.
It realizes safer and more efficient transportation of raw materials than manual transportation, reduces manpower use, avoids damage to raw materials, and improves construction efficiency.
Smart Images

Figure CN222225085U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of overflow well construction equipment, in particular to a sponge facility overflow well wall masonry construction equipment. Background Art
[0002] With the acceleration of urbanization and the intensification of climate change, the increase in rainwater runoff in cities has become an important factor affecting the urban water environment. In order to deal with this problem, various places have begun to explore the important factors affecting the urban water environment. In order to deal with this problem, various places have begun to build sponge cities. Overflow wells are installed in various sponge facilities. When building overflow wells, construction equipment is needed to transport raw materials.
[0003] The overflow well of sponge facilities is usually built underground. Existing construction equipment is not convenient for transporting the construction materials needed for masonry to the overflow well. Traditional manual transportation is dangerous and may also damage the integrity of the raw materials. Utility Model Content
[0004] The purpose of the utility model is to solve the problem in the prior art that it is inconvenient to transport the building materials needed for masonry to the overflow well, the traditional manual transportation has certain risks and may also damage the integrity of the raw materials, and a sponge facility overflow well wall masonry construction equipment is proposed.
[0005] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0006] A sponge facility overflow well wall masonry construction equipment, comprising a support frame, a conveying box is provided on one side of the support frame, a first motor is fixedly connected to one side of the conveying box, two groups of sprockets are rotatably connected inside the conveying box, a chain is transmission-connected between the two sprockets in each group, and one end of the output shaft of the first motor is fixedly connected to the two sprockets located above;
[0007] A plurality of placement boxes are fixedly connected between the two chains, a discharge port is provided on one side of the conveying box, and a discharge port is provided at the bottom of the conveying box;
[0008] An adjusting component is arranged on the upper surface of the supporting frame, and is used for adjusting the depth of the conveying box.
[0009] In a possible design, the adjustment assembly includes a second motor and a fixed frame, the second motor is fixedly connected to the bottom of the support frame, the fixed frame is fixedly connected to the upper surface of the support frame, the interior of the fixed frame is rotatably connected to a screw, one side of the conveying box is rotatably connected to a rotating plate, the other side of the rotating plate is fixedly connected to a lifting frame, and the screw is threadedly connected to the lifting frame.
[0010] In a possible design, a winch is fixedly connected to the upper surface of the support frame, a steel wire rope is fixedly connected to the rotating end of the winch, a lifting ring is fixedly connected to one side of the conveying box with a threaded connection, and one end of the steel wire rope is fixedly connected to the lifting ring.
[0011] In a possible design, a bottom plate is fixedly connected to one side of the support frame.
[0012] In a possible design, reinforcement frames are fixedly connected to both sides of the support frame.
[0013] In a possible design, a forward-reverse switch is fixedly connected to the upper surface of the support frame, and the forward-reverse switch is electrically connected to the first motor.
[0014] In the present application, when in use, the support frame is moved to the position where the overflow well needs to be built. When the construction raw materials needed for building the overflow well are laid, the unloading port of the conveying box is set at a safe position, and the construction raw materials are placed in a suitable placement box through the discharge port. The forward and reverse switch is turned to make the first motor drive two of the sprockets to rotate, and the two chains are driven to rotate through the two sets of sprockets to drive the placement box to move, so as to facilitate the transportation of the construction raw materials to the overflow well. Compared with manual transportation, it is safer and more efficient, can reduce the use of manpower, and will not damage the integrity of the raw materials.
[0015] When the depth of the conveying box needs to be adjusted, the second motor drives the screw to rotate, the screw drives the lifting frame to move, the lifting frame drives the rotating plate to move, and the rotating plate drives the conveying box to move up and down, so as to adjust the depth of the conveying box in the overflow well;
[0016] When the masonry construction equipment is not in use, the winch drives the steel wire rope to retract, and the steel wire rope drives the conveying box to rotate through the lifting ring, so that the conveying box is located on the bottom plate, which is convenient for placing the conveying box horizontally and moving it.
[0017] In the utility model, the sponge facility overflow well wall masonry construction equipment, through the setting of the adjustment component, the screw drives the lifting frame to move, the lifting frame drives the rotating plate to move, and the rotating plate drives the conveying box to move up and down, so as to facilitate the adjustment of the depth of the conveying box in the overflow well;
[0018] In the utility model, the sponge facility overflow well wall masonry construction equipment, through the setting of the chain, drives two chains to rotate through two sets of sprockets, drives the placement box to move, and is convenient for conveying construction raw materials into the overflow well. Compared with manual transportation, it is safer and more efficient, can reduce the use of manpower, and will not damage the integrity of the raw materials. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1This is a schematic diagram of the main structure of a sponge facility overflow well wall masonry construction equipment proposed by the utility model;
[0020] Figure 2 This is a schematic cross-sectional structure diagram of a conveying box of a sponge facility overflow well wall masonry construction equipment proposed by the utility model;
[0021] Figure 3 This is a schematic diagram of the structure of an adjustment component of a sponge facility overflow well wall masonry construction equipment proposed by the utility model;
[0022] Figure 4 This is a schematic structural diagram of a horizontally placed conveying box of a sponge facility overflow well wall masonry construction equipment proposed by the utility model.
[0023] In the figure: 1. support frame; 2. conveying box; 3. first motor; 4. unloading port; 5. discharge port; 6. sprocket; 7. chain; 8. placement box; 9. bottom plate; 10. fixed frame; 11. screw; 12. lifting frame; 13. rotating plate; 14. second motor; 15. winch; 16. reinforcement frame; 17. wire rope; 18. lifting ring. DETAILED DESCRIPTION
[0024] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.
[0025] Example 1
[0026] Reference Figure 1-Figure 4 A wall-laying construction equipment comprises: a support frame 1, a conveying box 2 is arranged on one side of the support frame 1, a first motor 3 is fixedly connected to one side of the conveying box 2, two groups of sprocket wheels 6 are rotatably connected inside the conveying box 2, a chain 7 is transmission-connected between the two sprocket wheels 6 in each group, and one end of the output shaft of the first motor 3 is fixedly connected to the two sprocket wheels 6 located above;
[0027] A plurality of placement boxes 8 are fixedly connected between the two chains 7, a discharge port 5 is provided on one side of the conveying box 2, and a discharge port 4 is provided at the bottom of the conveying box 2;
[0028] An adjustment component, which is arranged on the upper surface of the support frame 1 and is used for adjusting the depth of the conveying box 2;
[0029] The adjustment assembly includes a second motor 14 and a fixing frame 10, the second motor 14 is fixedly connected to the bottom of the support frame 1, the fixing frame 10 is fixedly connected to the upper surface of the support frame 1, a screw 11 is rotatably connected inside the fixing frame 10, a rotating plate 13 is rotatably connected to one side of the conveying box 2, a lifting frame 12 is fixedly connected to the other side of the rotating plate 13, and the screw 11 is threadedly connected to the lifting frame 12;
[0030] A forward / reverse switch is fixedly connected to the upper surface of the support frame 1, and the forward / reverse switch is electrically connected to the first motor 3;
[0031] In the above technical solution, the support frame 1 is moved to the position where the overflow well needs to be built. When the construction materials needed for building the overflow well are needed, the unloading port 4 of the conveying box 2 is set in a safe position, and the construction materials are placed in a suitable placement box 8 through the discharge port 5. The forward and reverse switch is turned to make the first motor 3 drive two of the sprockets 6 to rotate, and the two chains 7 are driven to rotate through the two sets of sprockets 6 to drive the placement box 8 to move, so as to facilitate the transportation of the construction materials to the overflow well. Compared with manual transportation, it is safer and more efficient, can reduce the use of manpower, and will not damage the integrity of the raw materials.
[0032] When the depth of the conveying box 2 needs to be adjusted, the second motor 14 drives the screw 11 to rotate, the screw 11 drives the lifting frame 12 to move, the lifting frame 12 drives the rotating plate 13 to move, and the rotating plate 13 drives the conveying box 2 to move up and down, so as to adjust the depth of the conveying box 2 in the overflow well;
[0033] Preferably, the chain 7 moves in a counterclockwise direction toward the discharge port 5 .
[0034] The present application can be used in the field of sponge facility overflow wells, and can also be used in other fields applicable to the present application.
[0035] Example 2
[0036] refer to Figure 1 , improved on the basis of Example 1:
[0037] A construction device for building a wall of a sponge facility overflow well;
[0038] A winch 15 is fixedly connected to the upper surface of the support frame 1, a steel wire rope 17 is fixedly connected to the rotating end of the winch 15, a lifting ring 18 is fixedly connected to one side of the conveying box 2 with a threaded connection, and one end of the steel wire rope 17 is fixedly connected to the lifting ring 18;
[0039] A bottom plate 9 is fixedly connected to one side of the support frame 1;
[0040] In the above technical solution, when the masonry construction equipment is not in use, the winch 15 drives the wire rope 17 to retract, and the wire rope 17 drives the conveying box 2 to rotate through the lifting ring 18, so that the conveying box 2 is located on the bottom plate 9, which is convenient for placing the conveying box 2 horizontally and moving it.
[0041] refer to Figure 3 , reinforcement frames 16 are fixedly connected to both sides of the support frame 1;
[0042] In the above technical solution, the reinforcement frame 16 is convenient for reinforcing the support frame 1 .
[0043] However, as is well known to those skilled in the art, the working principles and wiring methods of the first motor 3, the second motor 14 and the winch 15 are commonplace, and are conventional means or common knowledge, and will not be elaborated here. Those skilled in the art may make any optional selections according to their needs or convenience.
[0044] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A sponge facility overflow well wall construction equipment, characterized in that: include: A support frame (1), a conveying box (2) is provided on one side of the support frame (1), a first motor (3) is fixedly connected to one side of the conveying box (2), two groups of sprockets (6) are rotatably connected inside the conveying box (2), a chain (7) is transmission-connected between the two sprockets (6) in each group, and one end of the output shaft of the first motor (3) is fixedly connected to the two sprockets (6) located above; A plurality of placement boxes (8) are fixedly connected between the two chains (7), a discharge port (5) is provided on one side of the conveying box (2), and a discharge port (4) is provided at the bottom of the conveying box (2); An adjustment component is arranged on the upper surface of the support frame (1), and is used for adjusting the depth of the conveying box (2).
2. A sponge facility overflow well wall construction equipment according to claim 1, characterized in that: The adjustment assembly comprises a second motor (14) and a fixed frame (10), wherein the second motor (14) is fixedly connected to the bottom of the support frame (1), and the fixed frame (10) is fixedly connected to the upper surface of the support frame (1), and a screw rod (11) is rotatably connected inside the fixed frame (10), a rotating plate (13) is rotatably connected to one side of the conveying box (2), and a lifting frame (12) is fixedly connected to the other side of the rotating plate (13), and the screw rod (11) is threadedly connected to the lifting frame (12).
3. The sponge facility overflow well wall construction equipment according to claim 1, characterized in that: A winch (15) is fixedly connected to the upper surface of the support frame (1), a rotating end of the winch (15) is fixedly connected to a steel wire rope (17), one side of the conveying box (2) is fixedly connected to a lifting ring (18) threadedly connected, and one end of the steel wire rope (17) is fixedly connected to the lifting ring (18).
4. A sponge facility overflow well wall construction equipment according to claim 3, characterized in that: A bottom plate (9) is fixedly connected to one side of the support frame (1).
5. A sponge facility overflow well wall construction equipment according to claim 4, characterized in that: Reinforcement frames (16) are respectively fixedly connected to both sides of the support frame (1).
6. A sponge facility overflow well wall construction equipment according to claim 5, characterized in that: A forward / reverse switch is fixedly connected to the upper surface of the support frame (1), and the forward / reverse switch is electrically connected to the first motor (3).