Integrated electric measurement and detection laboratory

By setting up different performance test detection areas and teleportation channels in the electrical energy metering equipment detection laboratory to form a detection assembly line, the problem of low detection efficiency in existing technology and unable to simulate the actual application environment in existing technologies, realize the efficient and automation of electrical energy measurement equipment, automation and automation Test.

CN222420364UActive Publication Date: 2025-01-28ELECTRICAL INSTR ENG TECH RES CENT CO LTD HEILONGJIANG PROVINCE +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202322798380.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-10-18
Publication Date
2025-01-28
Estimated Expiration
2033-10-18

AI Technical Summary

Technical Problem

The existing electrical energy metering equipment detection technology has problems such as isolated detection, low detection efficiency, and inability to simulate the actual application environment, which cannot meet the timeliness and efficiency requirements of the inspection work.

Method used

The integrated electrical measurement detection laboratory is designed to set up a different performance test detection area, and set up a transmission channel between the detection area to form a detection assembly line to achieve automation of the automatic circulation and detection process of the inspection equipment.

Benefits of technology

It improved the detection efficiency and spatial utilization rate, reduced labor costs, realized the automation of measurement and testing, and can complete the full performance test test of the electrical measurement equipment faster and more accurately.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222420364U_ABST
    Figure CN222420364U_ABST
Patent Text Reader

Abstract

The utility model relates to an integrated electric measurement and detection laboratory, and belongs to the technical field of electric energy metering equipment detection. According to the utility model, a detection area is re-planned into different performance test detection areas according to detection experiment types and detection processes, similar test equipment is placed in the same detection area, and a transmission channel is arranged between adjacent detection equipment in each performance detection area for communication and is used for transmitting to-be-detected equipment between the detection equipment; therefore, a detection assembly line is formed, automatic circulation of the to-be-detected equipment in the detection area is facilitated, automation of metrological verification is realized, space and time efficiency is greatly improved, and the labor cost ratio is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to an integrated electrical measurement and detection laboratory, belonging to the technical field of electric energy metering equipment detection. Background Art

[0002] Electric energy metering and testing is an important technical foundation for economic activities, national defense construction, scientific research and social development. Through the transfer of measurement benchmarks and standard values, the testing laboratory completes the accurate measurement and verification of various metering products. The detection scope includes voltage, current, power, frequency, etc. to meet the needs of modern electricity meter verification technology, and also covers other metering needs such as gateway electricity meters and energy metering electricity meters. However, in the full performance test and inspection of electricity metering equipment, there are still problems such as inconsistent business processes, low detection efficiency, and blind spots in management and control. As an important part of quality supervision, the full performance test and inspection of electricity metering equipment has large differences in its work flow, detection plan, and test methods, which cannot meet the timeliness requirements of detection work, and there is still a lack of effective and objective evaluation methods for operating efficiency and application level.

[0003] At present, the development of electric energy metering equipment detection technology cannot fully match the actual application needs, which is mainly manifested in: 1) isolated detection schemes are only for single metering products; 2) detection items can only be detected sequentially, and parallel or multi-item combination detection of multiple detection items is not reflected in the detection process; 3) in the laboratory testing environment, it is impossible to simulate the performance detection of various environmental stresses superimposed in actual applications. Utility Model Content

[0004] The utility model aims to provide an integrated electrical measurement and detection laboratory to solve the problem of low detection efficiency caused by only isolated detection in the current electric energy measurement and detection process.

[0005] In order to solve the above-mentioned technical problems, the utility model provides an integrated electrical measurement and testing laboratory, which includes different performance test detection areas, each performance detection area includes an inlet for the equipment to be tested, an outlet for the equipment to be tested, and a detection device arranged in the area and adapted to the performance detection area, and a transmission channel is arranged between adjacent detection devices in each performance detection area to transmit the equipment to be tested between the detection devices to form a detection assembly line.

[0006] The utility model re-plans the detection area into different performance test areas according to the detection experiment type and the detection process, and places similar test equipment in the same detection area. A transmission channel is set between adjacent detection equipment in each performance detection area to transmit the equipment to be tested between the detection equipment to form a detection assembly line, which is convenient for the automatic flow of equipment to be tested in the detection area, realizes the automation of metrological verification, greatly improves the space and time efficiency, and reduces the proportion of labor costs.

[0007] Furthermore, the conveying channel is a roller slide, and a roller slide is arranged between the inlet of the equipment to be inspected and the detection equipment at the inlet of the equipment to be inspected, and a roller slide is arranged between the outlet of the equipment to be inspected and the detection equipment at the outlet of the equipment to be inspected.

[0008] The utility model adopts a roller slide to realize automatic transmission of the equipment to be inspected. At the same time, in order to facilitate the equipment to be inspected to enter or flow out of the inspection area, a roller slide is arranged between the inlet of the equipment to be inspected and the inspection equipment at the inlet of the equipment to be inspected, and a roller slide is arranged between the outlet of the equipment to be inspected and the inspection equipment at the outlet of the equipment to be inspected.

[0009] Furthermore, the interval between the devices in each performance detection area is greater than a set distance to avoid mutual interference between the detection devices.

[0010] Since the detection equipment in each detection area will generate electrical environmental interference such as strong magnetic field, instantaneous pulse large current, instantaneous pulse high voltage, etc. during the test, the utility model arranges the equipment at a certain interval.

[0011] Furthermore, the performance detection area includes a type test detection area, and the detection equipment arranged in the detection area includes a pulse voltage test device, a surge current test device, an overcurrent test device and a load current transient tester.

[0012] Furthermore, the performance detection area includes an electrical performance detection area, and the detection equipment installed in the detection area includes a single-phase smart electric energy meter calibration device, a three-phase smart electric energy meter calibration device, an electric energy meter function tester, a communication protocol consistency tester and a three-phase smart electric energy meter calibration device.

[0013] Furthermore, the performance testing area includes an environmental test testing area, and the testing equipment installed in the testing area includes a glow-wire test device, a sunlight radiation test chamber, a dust test chamber, a mold test chamber, a high and low temperature alternating humidity test chamber and an electric energy meter terminal temperature tester.

[0014] Furthermore, the performance testing area includes a mechanical performance testing area, and the testing equipment arranged in the testing area includes a vibration test bench.

[0015] Furthermore, the performance detection area includes an electromagnetic compatibility detection area, and the detection equipment arranged in the detection area includes an AC magnetic field influence test device, an electromagnetic radiation test device and an electric energy meter signal tester.

[0016] The utility model realizes detection of different performances in different detection areas and realizes detection of the same performance in the same detection area by setting five different detection areas.

[0017] Furthermore, the laboratory also includes an integrated testing laboratory management area, and a partition is set between the management area and the testing area to achieve the separation of the testing area and the management area. The management area is equipped with a server, a printer, a barcode scanner and testing tooling.

[0018] In order to facilitate management and avoid interference with the detection area, the utility model is also provided with an integrated detection laboratory management area separated from the detection area. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the structure of the type test detection area of ​​the utility model;

[0020] Figure 2 It is a schematic diagram of the structure of the electrical performance detection area of ​​the utility model;

[0021] Figure 3 It is a schematic diagram of the structure of the environmental test detection area of ​​the utility model;

[0022] Figure 4 It is a schematic diagram of the structure of the mechanical performance detection area of ​​the utility model;

[0023] Figure 5 It is a schematic diagram of the structure of the electromagnetic compatibility detection area of ​​the utility model;

[0024] Figure 6 It is a schematic diagram of the structure of the management area of ​​the integrated testing laboratory of the utility model. DETAILED DESCRIPTION

[0025] The specific implementation of the utility model will be further described below in conjunction with the accompanying drawings.

[0026] The integrated electrical measurement and testing laboratory includes an integrated testing laboratory management area and different performance test areas. Each performance test area includes an inlet for the equipment to be tested, an outlet for the equipment to be tested, and test equipment that is arranged in the area and adapted to the performance test area. A transmission channel is arranged between adjacent test equipment in each performance test area to transmit the equipment to be tested between the test equipment to form a test line. The test process in each test area is set and controlled through the integrated testing laboratory management area.

[0027] Specifically, the test areas set in this embodiment include five types, including type test test area 1, electrical performance test area 2, environmental test test area 3, mechanical performance test area 4 and electromagnetic compatibility test area 5, and corresponding test equipment is set in each test area. Figure 1 As shown, the testing equipment provided in the type test detection area 1 includes a pulse voltage test device 101, a surge current test device 102, a first overcurrent test device 103, a second overcurrent test device 104 and a load current transient tester 105; Figure 2 As shown, the detection equipment set in the electrical performance detection area 2 includes a single-phase smart energy meter calibration device 201, a three-phase smart energy meter calibration device 202, an energy meter function tester 203, a communication protocol consistency tester 204 and a three-phase smart energy meter calibration device 205; Figure 3 As shown, the testing equipment provided in the environmental test detection area 3 includes a glow wire test device 301, a sunlight radiation test chamber 302, a dust test chamber 303, a mold test chamber 304, a high and low temperature alternating damp heat test chamber 305 and an electric energy meter terminal temperature tester 306; Figure 4 As shown, the testing equipment provided in the mechanical performance testing area 4 includes a vibration test bench 401; Figure 5 As shown, the detection equipment set in the electromagnetic compatibility detection area 5 includes an AC magnetic field impact test device 501, an electromagnetic radiation test device 502 and an electric energy meter signal tester 503. The model parameters of each device are shown in Table 1.

[0028] Table 1

[0029]

[0030]

[0031]

[0032] The detection equipment in each detection area is set up in a similar manner. The detection equipment in each performance detection area is arranged in two rows. An artificial channel for detection personnel to pass through is set between the two rows. A transmission channel is set between any two adjacent detection equipment in each row to transmit the equipment to be tested between the detection equipment. The ends of the two rows are also connected by a transmission channel to form a detection assembly line, which is convenient for the automatic flow of equipment to be tested in the detection area, realizes the automation of metrology and calibration, greatly improves the space and time efficiency, and reduces the proportion of labor costs.

[0033] The conveying channel is a roller slide. To facilitate the equipment to be inspected to enter or flow out of the inspection area, a roller slide is set between the inlet of the equipment to be inspected and the inspection equipment at the inlet of the equipment to be inspected, and a roller slide is set between the outlet of the equipment to be inspected and the inspection equipment at the outlet of the equipment to be inspected.

[0034] As another implementation method, it can also be understood that the detection area is divided into a U-shaped structure by a transmission channel, the middle of the U-shaped structure is an artificial channel, and the detection equipment is arranged along the extension direction of the transmission channel. Since the detection equipment in the detection area will generate strong magnetic fields, instantaneous pulse large currents, instantaneous pulse high voltages and other electrical environmental interference during the test, the distance between the detection equipment in each detection area is required to be greater than 3 meters to avoid any impact.

[0035] Transmission channels can be set up between detection areas according to actual conditions. If the detection areas are arranged on the same floor, transmission channels can be set up between the detection areas. If they are not on the same floor, the flow will be determined according to actual conditions.

[0036] Each test area is an independent test unit, and its test sequence is not limited to the test sequence of the test area number, and the test areas can be freely combined. The various types of test equipment in the test area are independent test equipment, and their test sequence is not limited to the test sequence of the internal number of the test area, and the test equipment can be freely combined. The division of the test area is determined by the functional attributes of the test equipment. The test items in the type test test area are high voltage and high current detection, and the insulation protection requirements are high; the test items in the electrical performance test area are full performance tests, communication protocols and other normative function tests; the test items in the environmental test test area include smoke, burning, high and low temperature, humidity and other simulated external environment tests, and smoke exhaust pipes, drainage pipes and other facilities can be set up as needed; the mechanical performance test area is a vibration test, and it should be arranged on the first floor as much as possible and the ground needs to be hardened; the electromagnetic compatibility test area test items are strong magnetic and signal detection, and it should be as far away from other test areas as possible.

[0037] When setting up the testing area, try to install testing equipment with similar testing items in the same testing area. The location of the testing equipment in the testing area can be reasonably arranged according to the actual situation of the testing laboratory house, and the chassis base of the testing equipment is mostly equipped with casters for easy movement. There are many types, categories and models of electrical measuring equipment. The testing process will change according to different electrical measuring equipment, and can be adjusted according to the new testing process.

[0038] In order to facilitate the management of the entire testing process, this laboratory also has an integrated testing laboratory management area 6, such as Figure 6 As shown, a wall is set between the management area and the testing area to separate the testing area and the management area to avoid mutual interference. The management area is provided with a server 601, a desktop terminal 602, a printer 603, a barcode scanner 604 and a testing tool 605. The metering product to be tested is provided with a barcode. The laboratory testing personnel place the metering product to be tested on the testing tool, scan the barcode with a barcode scanner, enter the number, model and other parameters of the metering product to be tested, and then set the testing process and testing items.

[0039] The metered products to be inspected enter the inspection area through the inlet of the inspection equipment, and after being inspected in sequence, they flow out from the outlet of the inspection equipment, forming an inspection line in the inspection area, saving space and speeding up the inspection efficiency. All inspection processes, inspection data, etc. are stored in the server 601 of the integrated inspection laboratory management area 6.

Claims

1. An integrated electrical measurement and testing laboratory, characterized in that: The laboratory includes different performance test inspection areas. Each performance test area includes an inlet for equipment to be tested, an outlet for equipment to be tested, and testing equipment arranged in the area and adapted to the performance test area. A transmission channel is arranged between adjacent testing equipment in each performance test area to transmit the equipment to be tested between the testing equipment to form a testing assembly line. The performance test area includes a type test inspection area, an electrical performance test area, an environmental test inspection area, a mechanical performance test area, and an electromagnetic compatibility test area.

2. The integrated electrical measurement and testing laboratory according to claim 1 is characterized in that: The conveying channel is a roller slide, and a roller slide is arranged between the inlet of the equipment to be inspected and the detection equipment at the inlet of the equipment to be inspected, and a roller slide is arranged between the outlet of the equipment to be inspected and the detection equipment at the outlet of the equipment to be inspected.

3. The integrated electrical measurement and testing laboratory according to claim 1 is characterized in that: The distance between devices in each performance detection area is greater than the set distance to avoid mutual interference between detection devices.

4. The integrated electrical measurement and testing laboratory according to any one of claims 1 to 3, characterized in that: The testing equipment installed in the type test inspection area includes pulse voltage test equipment, impact current test equipment, overcurrent test equipment and load current transient tester.

5. The integrated electrical measurement and testing laboratory according to any one of claims 1 to 3, characterized in that: The testing equipment installed in the electrical performance testing area includes a single-phase smart energy meter calibration device, a three-phase smart energy meter calibration device, an energy meter function tester, a communication protocol consistency tester and a three-phase smart energy meter calibration device.

6. The integrated electrical measurement and testing laboratory according to any one of claims 1-3, characterized in that: The testing equipment installed in the environmental test area includes glow-wire test device, sunlight radiation test chamber, dust test chamber, mold test chamber, high and low temperature alternating humidity test chamber and electric energy meter terminal temperature tester.

7. The integrated electrical measurement and testing laboratory according to any one of claims 1 to 3, characterized in that: The testing equipment installed in the mechanical performance testing area includes a vibration test bench.

8. The integrated electrical measurement and testing laboratory according to any one of claims 1 to 3, characterized in that: The testing equipment installed in the electromagnetic compatibility testing area includes an AC magnetic field impact test device, an electromagnetic radiation test device and an electric energy meter signal tester.

9. The integrated electrical measurement and testing laboratory according to any one of claims 1 to 3, characterized in that: The laboratory also includes an integrated testing laboratory management area. A partition is set between the management area and the testing area to achieve the separation of the testing area and the management area. The management area is equipped with a server, a printer, a barcode scanner and testing tooling.