H-grade gas turbine equipment hoisting device for double-machine hoisting
By designing an H-class gas turbine equipment hoisting device for dual-unit lifting, and adopting a hydraulic system drive and modular design, the installation problem of H-class gas turbine equipment hoisting in plant layout space was solved, achieving safe, accurate and low-cost hoisting results.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- CHINA POWER CONSTR HUBEI ELECTRIC POWER CONSTR CO LTD
- Filing Date
- 2025-06-24
- Publication Date
- 2026-05-12
AI Technical Summary
Traditional hoisting methods cannot meet the installation requirements of H-class gas turbine equipment, especially when the plant layout space is limited, and cannot guarantee the installation accuracy and safety of the equipment.
Design a lifting device for H-class gas turbine equipment using dual-machine lifting, including a dual-machine lifting beam, a hydraulic lifting suspension device, and a lifting ramp. The device uses a hydraulic system as the drive, and utilizes existing overhead cranes for lifting through modular design and standardized lifting equipment, ensuring that the wire rope is perpendicular to the equipment and reducing safety risks.
It enabled the safe and precise hoisting of H-class gas turbine equipment, shortened the construction cycle, reduced costs, improved the versatility and safety of hoisting equipment, and reduced the need for operators.
Smart Images

Figure CN224226462U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of lifting and hoisting technology, and in particular to a hoisting device for dual-machine lifting of H-class gas turbine equipment. Background Technology
[0002] H-class gas turbines, currently the largest single-unit gas turbine type, are increasingly widely used in construction projects in China. The high-pressure and intermediate-pressure cylinders and the lower section of the gas turbine are key structural components of H-class gas turbines, characterized by their significant weight and high installation precision requirements. They are typically hoisted using dual cranes within the main plant. For example, if an H-class gas turbine is arranged at a high position, with the gas turbine, steam turbine, and generator on the same axis, the traditional hoisting method involves parallel operation and control of two overhead cranes, lowering both hooks into the equipment transport channel, connecting the hooks to a specialized lifting tool, and then connecting the lifting tool to the equipment. However, due to the increasingly integrated layout of H-class gas turbine plant spaces and the continuous increase in the size and specifications of overhead cranes, the width of the plant's equipment transport channel is no longer sufficient for both crane hooks to be lowered to the ground simultaneously. This renders the original lifting tools unusable, compromising the installation operation of the H-class gas turbine. Summary of the Invention
[0003] To address the technical problem that existing hoisting equipment cannot meet the installation requirements of H-class gas turbine equipment, this utility model provides a hoisting device for H-class gas turbine equipment using dual-machine lifting. This device can be used for hoisting different parts of an H-class gas turbine, ensuring the safety of lifting heavy objects and construction, and reducing safety risks during hoisting operations.
[0004] To achieve the above-mentioned technical objectives, this utility model provides a hoisting device for H-class gas turbine equipment using a dual-unit lifting system. The hoisting device includes a dual-unit lifting beam, a hydraulic lifting suspension device, and lifting ramps. The dual-unit lifting beam includes a box girder and a first and second lifting lug symmetrically arranged on the top of the box girder. Two through holes for installing the hydraulic lifting suspension device are symmetrically provided in the area between the two lifting lugs of the box girder. Two sets of hydraulic lifting suspension devices and lifting ramps are provided, each set installed at one of the two through holes in the dual-unit lifting beam. Each set of hydraulic lifting suspension devices includes a suspension lifting frame, a hydraulic lifting device, and steel strands. The suspension lifting frame passes through the through holes and is fixed to the box girder. The hydraulic lifting device is fixedly installed inside the suspension lifting frame and connected to one set of lifting ramps via the steel strands. Each set of lifting ramps is equipped with a lifting device for connecting to the first hoisting wire rope.
[0005] The preferred technical solution of this utility model is as follows: The hoisting device further includes two sets of hoisting mechanisms connected to the first lifting lug and the second lifting lug respectively. Each set of hoisting mechanisms includes a crane, a second hoisting wire rope fixed on the crane, a hook set at the lower end of the second hoisting wire rope, and a special hoisting rope for connecting the hook and the corresponding lifting lug.
[0006] The preferred technical solution of this utility model is as follows: the double-machine lifting beam is composed of two sets of box beams, which are connected as one unit along their length; the first lifting lug and the second lifting lug are respectively located on the top of the two sets of box beams near their respective sides, and the two sides of the box beams are connected by H-beams.
[0007] The preferred technical solution of this utility model is as follows: The suspended lifting frame includes an upper suspension device, a connecting frame, connecting struts, and a lower load-bearing device. The upper suspension device is fixed to the upper part of the double-machine lifting beam. The upper suspension device is a box-shaped load-bearing structure on both sides, with a pin connecting lug at the bottom and a square hole in the middle that matches the hydraulic lifting device. The connecting frame has a connecting pin at the top and round holes around the bottom, and is fixed to the bottom of the upper suspension device. There are at least four connecting struts, which are distributed at the four corners of the connecting frame. The upper end of each connecting strut is bolted to the upper suspension device, and the lower end is bolted to the load-bearing device. The lower load-bearing device has fixing bolt holes for the hydraulic lifting device on its upper surface and a safety anchor placement hole for the hydraulic lifting device in the middle. The hydraulic lifting device is fixedly installed on the lower load-bearing device.
[0008] The preferred technical solution of this utility model is as follows: both the first and second lifting lugs are provided with pins, pin sleeves and pin stops on both sides. Both the first and second lifting lugs are made of welded steel plates, and multiple triangular steel plate supports are provided on both sides.
[0009] The preferred technical solution of this utility model is as follows: the lifting device includes a component anchor, the lifting device is a triangular lifting device, the upper part of the component anchor is square with a round hole in the middle, and the lower part has ear plates extending on both sides and provided with pin holes, the upper part of the triangular lifting device is provided with a pin connection hole, and the lower part is provided with a pin, the component anchor and the triangular lifting device are rotatably connected by the pin; the steel strand is connected to the component anchor.
[0010] The preferred technical solution of this utility model is as follows: the lifting device is provided with multiple pin holes, and the lower part of the lifting rod is provided with a first pin and a second pin. The first pin and the second pin are respectively provided at both ends of the lifting rod and inserted into the pin holes. The first pin and the second pin are provided with a first lifting wire rope.
[0011] The preferred technical solution of this utility model is as follows: the distance between the first lifting lug and the second lifting lug is equal to the distance between the hooks of the two sets of lifting mechanisms, and the first lifting lug and the second lifting lug each include two symmetrical sets of pin-shaft lifting lugs, which are respectively connected to the special lifting ropes of the two sets of lifting mechanisms.
[0012] The preferred technical solution of this utility model is that the lower load-bearing lifting device has multiple sets of ribs on both sides with the same height as the lower load-bearing lifting device.
[0013] This utility model can be used for hoisting different equipment in H-class gas turbines. The hoisting equipment is standardized, reducing the cost of repetitive on-site fabrication. The hydraulic lifting device uses a hydraulic system as its drive mechanism, ensuring smooth operation and high safety. In case of emergencies (such as sudden power outages or weather changes), the hydraulic jacks and hydraulic pump station can lock the hydraulic system, ensuring the safety of lifting heavy objects and construction. It fully utilizes existing overhead cranes on the construction site, eliminating the need for delayed installation of the hoisting area structure, shortening the project construction cycle, and effectively reducing equipment installation costs. Furthermore, by connecting the crane to the H-class gas turbine using the hoisting device, the wire ropes on both cranes remain perpendicular to the H-class gas turbine during hoisting, greatly ensuring the safe load of the cranes and wire ropes and reducing safety risks during hoisting operations.
[0014] The beneficial effects of this utility model are as follows:
[0015] (1) The hoisting device of this utility model connects the first trolley, the second trolley and the H-class gas turbine equipment by setting up a double-machine lifting beam, so that during the hoisting process, the vertical angle between the steel wire rope on the first trolley and the second trolley and the H-class gas turbine equipment is always 180°, which greatly ensures the safe load of the trolley and the steel wire rope, and reduces the safety risks during hoisting operations.
[0016] (2) The lifting device of this utility model uses a hydraulic system as the drive, which is stable and safe. When an emergency occurs in the working system (such as a sudden power outage or weather change), the hydraulic jack and hydraulic pump station can lock the hydraulic system to ensure the safety of lifting heavy objects and construction.
[0017] (3) The hydraulic lifting device, double-machine lifting beam, lifting ramp, and hydraulic lifting suspension device in this utility model are all modularly designed, making installation and disassembly simple and shortening the time cycle; the lower part of the lifting ramp is designed with multiple adjustable pin shafts, which can be adjusted according to the size of the lifting lugs and center of gravity of the H-class gas turbine equipment, so as to keep the H-class gas turbine equipment horizontal during hoisting and facilitate the hoisting and positioning of the equipment.
[0018] (4) The hydraulic lifting suspension device of this utility model can be flexibly arranged above the double-machine lifting beam according to the size of the lifting lug of the H-class gas turbine equipment. It can be applied to situations where the lifting capacity of the two cranes is inconsistent, the center of gravity of the equipment is symmetrical or asymmetrical, etc., effectively improving the versatility of the lifting equipment; it can be used for the lifting of different equipment of H-class gas turbine, the lifting equipment is standardized, and the cost of repeated production on the project site is reduced.
[0019] (5) This utility model makes full use of the existing overhead cranes and hoisting machinery at the construction site, eliminating the need for delayed installation of the hoisting area structure at the construction site, shortening the project construction cycle, and effectively reducing the construction cost of equipment installation.
[0020] (6) When transferring H-class gas turbine equipment, this utility model can connect two trolleys in parallel to control one trolley, requiring only one person to directly operate the large trolleys on the two trolleys, reducing the input of operators and improving the moving accuracy of hoisting operations. Attached Figure Description
[0021] Figure 1 This is a schematic diagram of the structure of this utility model;
[0022] Figure 2 This is a schematic diagram of the structure of the double-machine lifting beam in this utility model;
[0023] Figure 3 This is a schematic diagram of the hydraulic lifting suspension device in this utility model;
[0024] Figure 4 This is a front structural diagram of the hanging device in this utility model;
[0025] Figure 5 This is a side view of the hanging bracket in this utility model;
[0026] Figure 6 This is a reference diagram showing the usage state of this utility model.
[0027] Reference numerals: 1-First lifting wire rope; 2-Lifting mechanism; 21-Crane; 22-Second wire rope; 23-Hook; 24-Special lifting rope; 3-Double-machine lifting beam; 31-Box beam; 32-H-beam; 33-First lifting lug; 34-Second lifting lug; 35-Triangular steel plate; 331-Pin; 332-Pin bushing; 333-Pin stop; 4-Hydraulic lifting suspension device; 41-Upper suspension device; 42-Connecting frame; 43-Connecting strut; 44-Hydraulic lifting device; 45-Lower load-bearing lifting device; 451-Safety anchor; 452-Rib plate; 46-Steel strand; 5-Lifting climber; 51-Component anchor; 52-Lifting tool; 521-First pin; 522-Second pin; 523-Pin hole; 6-H-class gas turbine equipment. Detailed Implementation
[0028] To make the above-mentioned objectives, features, and advantages of this application more apparent and understandable, the specific embodiments of this application are described in detail below with reference to the accompanying drawings. Many specific details are set forth in the following description to provide a thorough understanding of this application. However, this application can be implemented in many other ways different from those described herein, and those skilled in the art can make similar modifications without departing from the spirit of this application. Therefore, this application is not limited to the specific embodiments disclosed below.
[0029] The embodiment provides a hoisting device for H-class gas turbine equipment used in dual-unit lifting, such as... Figures 1 to 6As shown, the hoisting device includes a double-machine lifting beam 3, a hydraulic lifting suspension device 4, and lifting ramps 5. The double-machine lifting beam 3 includes a box girder 31 and a first lifting lug 33 and a second lifting lug 34 symmetrically arranged on the top of the box girder 31. Two through holes 36 for installing the hydraulic lifting suspension device 4 are symmetrically provided in the area between the two lifting lugs of the box girder 31. The hydraulic lifting suspension device 4 and the lifting ramps 5 are provided in two sets. The two sets of hydraulic lifting suspension devices 4 are respectively installed at the two through holes 36 of the double-machine lifting beam 3. Each set of hydraulic lifting suspension devices 4 includes a suspension lifting frame, a hydraulic lifting device 44, and a steel strand 46. The suspension lifting frame passes through the through hole 36 and is fixed to the box girder 31. The hydraulic lifting device 44 is fixedly installed in the suspension lifting frame and connected to a set of lifting ramps 5 through the steel strand 46. Each set of lifting ramps 5 is provided with a lifting device 52 for connecting to the first hoisting wire rope 1.
[0030] The hoisting device in the embodiment, in specific use, such as Figure 1 and Figure 6 As shown, it also includes two sets of lifting mechanisms 2 connected to the first lifting lug 33 and the second lifting lug 34 respectively. Each set of lifting mechanisms 2 includes a crane 21, a second lifting wire rope 22 fixed on the crane 21, a hook 23 set at the lower end of the second lifting wire rope 22, and a special lifting rope 24 for connecting the hook 23 and the corresponding lifting lug.
[0031] like Figure 2 As shown, the dual-machine lifting beam 3 in this embodiment consists of two sets of box beams 31, which are connected as a single unit along their length. The first lifting lug 33 and the second lifting lug 34 are respectively located near the top of the two sets of box beams 31 on both sides. The center of the first lifting lug 33 and the center of the second lifting lug 34 are 750mm from the end of the box beam 31. The two sides of the box beams 31 are connected by H-beams 32. To ensure the overall stability and dimensional accuracy of the dual-machine lifting beam 3, the box beams 31 and the H-beams 32 are bolted together. Each set of box beams 3 has a through hole 36. The first lifting lug 33 and the second lifting lug 34 are each equipped with a pin 331, a pin sleeve 332, and a pin stop 333 on both sides. Both the first lifting lug 33 and the second lifting lug 34 are welded from steel plates, and multiple triangular steel plates 35 are provided for support on both sides. The distance between the first lifting lug 33 and the second lifting lug 34 is equal to the distance between the hooks 23 of the two sets of lifting mechanisms 2. The first lifting lug 33 and the second lifting lug 34 each contain two symmetrical sets of pin-shaft lifting lugs, which are respectively connected to the special lifting ropes 24 of the two sets of lifting mechanisms 2.
[0032] Examples, such as Figure 3As shown, the suspended lifting frame includes an upper suspension device 41, a connecting frame 42, connecting struts 43, and a lower load-bearing lifting device 45. The upper suspension device 41 is fixed to the upper part of the double-machine lifting beam. The upper suspension device 41 is a box-shaped load-bearing structure on both sides, with a pin connecting lug at the bottom and a square hole in the middle that matches the hydraulic lifting device 44. The connecting frame 42 has a connecting pin at the top and round holes around the bottom, and is fixed to the bottom of the upper suspension device 41. There are at least four connecting struts 43, which are distributed at the four corners of the connecting frame 42. The upper end of each connecting strut 43 is bolted to the upper suspension device 41, and the lower end is bolted to the load-bearing lifting device 45. The upper surface of the lower load-bearing lifting device 45 has fixing bolt holes for the hydraulic lifting device 44, and the middle part has a hole for placing the safety anchor 451 of the hydraulic lifting device 44. The hydraulic lifting device 44 is fixedly installed on the lower load-bearing lifting device 45. The lower load-bearing hanger 45 has multiple sets of ribs 452 on both sides, with the same height as the lower load-bearing hanger 45. The connecting frame 42 is 55mm away from the inner side of the box girder 31 on both sides.
[0033] Examples, such as Figure 4 and Figure 5 As shown, the lifting device 5 includes a component anchor 51, and the lifting tool 52 is a triangular lifting tool. The upper part of the component anchor 51 is square with a round hole in the middle, and the lower part has ear plates extending on both sides, each with a pin hole. The upper part of the triangular lifting tool has a pin connection hole, and the lower part has a pin. The component anchor 51 and the triangular lifting tool are rotatably connected by the pin. The steel strand 46 is connected to the component anchor 51. The lifting tool 52 has multiple pin holes 523 to facilitate the use of different lifting ropes. The lower part of the lifting device 5 is provided with a first pin 521 and a second pin 522. The first pin 521 and the second pin 522 are respectively located at both ends of the lifting device 5 and inserted into the pin holes 523. The first lifting steel wire rope 1 is provided on the first pin 521 and the second pin 522.
[0034] During the hoisting process, the steel wire ropes 23 on both cranes remain perpendicular to the H-class gas turbine unit 1, greatly ensuring the safe load of the cranes and steel wire ropes and reducing safety risks during hoisting operations. When hoisting and transferring the H-class gas turbine unit, the two cranes can be connected in parallel for operation, requiring only one person to directly operate the trolleys on both cranes, reducing operator workload and improving the accuracy of hoisting operations.
[0035] The lifting device will be further described below with reference to its usage method. When using this utility model, the specific steps include:
[0036] Step 1: Connect the hydraulic lifting suspension device 4 to the double-machine lifting beam 3; pass the hydraulic lifting suspension device 4 through the middle hole of the double-machine lifting beam 3 from top to bottom until the hydraulic lifting suspension device 4 is lowered to the upper plane of the double-machine lifting beam 3; hoist the hydraulic lifting device 44 above the positioning middle hole of the double-machine lifting beam 3, and slowly lower it to the upper plane of the lower load-bearing lifting device 45, and connect the hydraulic lifting suspension device 4 to the double-machine lifting beam 3.
[0037] Step 2: Connect the hydraulic lifting suspension device 4 to the lifting ramp 5. The hydraulic lifting suspension device 4 is equipped with a steel strand 46, and the lower part of the lifting ramp 5 is equipped with a component anchor 51 and a special steel wire rope 6. The steel strand 46 is connected to the component anchor 51.
[0038] Step 3: Connect the H-class gas turbine equipment 6 to the hoisting platform 5; the lower part of the hoisting platform 5 is provided with a first pin 521 and a second pin 522, the first pin 521 and the second pin 522 are respectively located at both ends of the hoisting platform 5, and a first hoisting wire rope 1 is provided on the first pin 521 and the second pin 522, and the first hoisting wire rope 1 is connected to the hoisting platform 5.
[0039] Step 4: Connect the double-machine lifting beam 3 to the two sets of lifting mechanisms. Each of the two sets of cranes 21 is equipped with a second lifting wire rope 22. The lower end of each second lifting wire rope 22 is equipped with a hook 23 for lifting. The lower part of the hook 23 is equipped with a special lifting rope 24 for connecting the lifting lug. The upper part of the box beam 31 is equipped with a lifting lug for connecting with the hooks on the two sets of cranes. The lifting lug includes a first lifting lug 33 and a second lifting lug 34. The first lifting lug 33 and the second lifting lug 34 are respectively set at both ends of the box beam 31. The distance between the first lifting lug 33 and the second lifting lug 34 is equal to the distance between the hooks 23 of the two cranes. The first lifting lug 33 and the second lifting lug 34 each include two symmetrical sets of pin-shaft lifting lugs. The first lifting lug 33 and the second lifting lug 34 are connected to the special lifting rope 24.
[0040] Step 5: The hydraulic lifting device 44 lifts the H-class gas turbine unit 6. The hydraulic lifting device 44, through the steel strands 46, synchronously moves the lifting platform 5 upwards, lifting the H-class gas turbine unit 6 off the ground, until the hydraulic lifting device 44 reaches its maximum upward position. After the hydraulic lifting device 44 lifts the steel strands 46 and tauts them, the stress on each steel strand 46 needs to be checked, and any unstressed steel strands 46 need to be pre-tightened to ensure uniform stress. When the H-class gas turbine unit 6 is lifted 500mm off the ground, the connection points between the steel strands 46 and the hydraulic lifting device 44 and lifting platform 5 need to be inspected.
[0041] Step Six: Two sets of cranes lift the H-class gas turbine unit 6; the two sets of cranes synchronously drive the lifting platform 5 upward, driving the H-class gas turbine unit 6 above the positioning plane.
[0042] Step 7: Lowering and installing the H-class gas turbine equipment 6; Two sets of cranes synchronously drive the lifting platform 5 to move downwards until the H-class gas turbine equipment 6 falls onto the foundation platform. After the H-class gas turbine equipment 6 has completely fallen onto the foundation platform, disconnect the first hoisting wire rope 1 from the H-class gas turbine equipment 6.
[0043] The above description is merely one embodiment of this utility model, and while it is quite specific and detailed, it should not be construed as limiting the scope of this utility model. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of this utility model, and these all fall within the protection scope of this utility model. Therefore, the protection scope of this utility model should be determined by the appended claims.
Claims
1. A hoisting device for H-class gas turbine equipment used in dual-unit lifting, characterized in that: The hoisting device includes a double-machine lifting beam (3), a hydraulic lifting suspension device (4), and a lifting ramp (5). The double-machine lifting beam (3) includes a box beam (31) and a first lifting lug (33) and a second lifting lug (34) symmetrically arranged on the top of the box beam (31). Two through holes (36) for installing the hydraulic lifting suspension device (4) are symmetrically provided in the area between the two lifting lugs of the box beam (31). The hydraulic lifting suspension device (4) and the lifting ramp (5) are provided in two sets respectively. The devices (4) are respectively installed at the two through holes (36) of the double-machine lifting beam (3). Each set of hydraulic lifting suspension devices (4) includes a suspension lifting frame, a hydraulic lifting device (44) and a steel strand (46). The suspension lifting frame passes through the through hole (36) and is fixed on the box beam (31). The hydraulic lifting device (44) is fixedly installed in the suspension lifting frame and connected to a set of lifting rods (5) through the steel strand (46). Each set of lifting rods (5) is provided with a lifting device (52) for connecting with the first lifting wire rope (1).
2. The hoisting device for H-class gas turbine equipment for dual-unit lifting according to claim 1, characterized in that: The hoisting device also includes two sets of hoisting mechanisms (2) connected to the first lifting lug (33) and the second lifting lug (34) respectively. Each set of hoisting mechanisms (2) includes a crane (21), a second hoisting wire rope (22) fixed on the crane (21), a hook (23) set at the lower end of the second hoisting wire rope (22), and a special hoisting rope (24) for connecting the hook (23) and the corresponding lifting lug.
3. A hoisting device for H-class gas turbine equipment with dual-unit lifting as described in claim 1 or 2, characterized in that: The dual-machine lifting beam (3) is composed of two sets of box beams (31), which are connected as one unit along their length. The first lifting lug (33) and the second lifting lug (34) are respectively located on the top of the two sets of box beams (31) near their respective sides. The two sides of the box beams (31) are connected by H-beams (32).
4. A hoisting device for H-class gas turbine equipment with dual-unit lifting as described in claim 1 or 2, characterized in that: The suspended lifting frame includes an upper suspension device (41), a connecting frame (42), a connecting strut (43), and a lower load-bearing lifting device (45). The upper suspension device (41) is fixed to the upper part of the double-machine lifting beam. The upper suspension device (41) is a box-shaped load-bearing structure on both sides, with a pin connecting lug at the bottom and a square hole in the middle that matches the hydraulic lifting device (44). The connecting frame (42) has a connecting pin at the top and round holes around the bottom, and is fixed to the bottom of the upper suspension device (41). At least four connecting struts (43) are provided, which are distributed at the four corners of the connecting frame (42). The upper end of each connecting strut (43) is connected to the upper suspension device (41) by bolts, and the lower end is connected to the load-bearing lifting device (45) by bolts. The upper surface of the lower load-bearing lifting device (45) is provided with fixing bolt holes for the hydraulic lifting device (44), and the middle part is provided with a safety anchor (451) placement hole for the hydraulic lifting device (44). The hydraulic lifting device (44) is fixedly installed on the lower load-bearing lifting device (45).
5. A hoisting device for H-class gas turbine equipment with dual-unit lifting as described in claim 1 or 2, characterized in that: The first lifting lug (33) and the second lifting lug (34) are provided with a pin (331), a pin bushing (332) and a pin stop (333) on both sides. The first lifting lug (33) and the second lifting lug (34) are both made of welded steel plates and are supported by multiple triangular steel plates (35) on both sides.
6. A hoisting device for H-class gas turbine equipment with dual-unit lifting as described in claim 1 or 2, characterized in that: The lifting device (5) includes a component anchor (51), and the lifting device (52) is a triangular lifting device. The upper part of the component anchor (51) is square with a round hole in the middle, and the lower part has ear plates extending on both sides with pin holes. The upper part of the triangular lifting device has a pin connection hole, and the lower part has a pin. The component anchor (51) and the triangular lifting device are rotatably connected by the pin. The steel strand (46) is connected to the component anchor (51).
7. A hoisting device for H-class gas turbine equipment with dual-unit lifting as described in claim 1 or 2, characterized in that: The lifting device (52) is provided with multiple pin holes (523). The lower part of the lifting rod (5) is provided with a first pin (521) and a second pin (522). The first pin (521) and the second pin (522) are respectively provided at both ends of the lifting rod (5) and inserted into the pin holes (523). The first pin (521) and the second pin (522) are provided with a first lifting wire rope (1).
8. A hoisting device for H-class gas turbine equipment with dual-unit lifting as described in claim 2, characterized in that: The distance between the first lifting lug (33) and the second lifting lug (34) is equal to the distance between the hooks (23) of the two sets of lifting mechanisms (2). The first lifting lug (33) and the second lifting lug (34) each contain two sets of symmetrical pin-shaft lifting lugs, which are respectively connected to the special lifting ropes (24) of the two sets of lifting mechanisms (2).
9. A hoisting device for H-class gas turbine equipment for dual-unit lifting according to claim 4, characterized in that: The lower load-bearing lifting device (45) has multiple sets of ribs (452) on both sides with the same height as the lower load-bearing lifting device (45).