Equipment process layout and gantry robot for railway wheel and axle workshop
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- JIANGSU SUSHENG AUTOMATION EQUIP
- Filing Date
- 2025-02-16
- Publication Date
- 2026-06-30
AI Technical Summary
例如,虽然某个工序本来只需一台设备就能满足生产需要,但仍旧要在每条作业线上各配置一台同样的设备
Smart Images

Figure CN224428764U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of railway vehicle maintenance and production technology, specifically a process layout of equipment and a gantry robot for railway wheel and axle workshops. Background Technology
[0002] Currently, in the wheel and axle workshops of various railway depots and rolling stock plants across the country, the process layout of wheelset production lines is basically composed of 2-3 relatively independent work lines, i.e., arranged in series. Some work areas of wheelsets (such as wheel turning, unloading, and pressing) are relatively scattered, commonly known as a "street stall" layout. Moreover, the steel rails on the workshop floor serve as both the carrier for transporting wheelsets and the route for wheelset operations. This results in a series of problems in wheel and axle workshops, including large operating area, high investment in equipment and track construction, high labor intensity for workers, and low production efficiency. The specific situation is as follows:
[0003] 1) Redundant equipment configuration, because the equipment configuration is the same on every production line. For example, although a certain process only requires one machine to meet production needs, one of the same machines is still configured on each production line.
[0004] 2) The ground track is extensive and the wheelset transport route is long. The transport of wheelsets between various production stations mainly relies on manual labor. Therefore, the transport efficiency of wheelsets and the utilization rate of tooling equipment are very low, and the labor intensity of workers is very high.
[0005] 3) Because some production areas and equipment are scattered, and there are many production lines and long operation routes, the maintenance and production of wheelsets requires a very large area.
[0006] 4) Since there are usually only two overhead cranes in the factory, these two cranes are often contested by various work areas, which often causes work to wait.
[0007] 5) Since the tooling equipment on each independent wheelset production line is arranged in series, if any one piece of equipment fails, it will affect the production of the entire production line.
[0008] 6) Because wheelsets need to roll along the work line on the ground rails, they cannot be stored separately or crosswise on the ground rails, let alone densely, resulting in very few wheelsets stored in the production area of the wheel and axle workshop.
[0009] 7) The ground rails are divided into several isolated "segments" by the wheelset production equipment. Although wheelsets can be stored on these "segments", each "segment" can only store the wheelsets required by the preceding equipment station and cannot store the wheelsets required by other equipment stations. Utility Model Content
[0010] In view of the problems existing in the prior art, the purpose of this utility model is to provide an equipment process layout and gantry robot for railway wheel and axle workshop, so as to solve the problems mentioned in the background art.
[0011] To achieve the above objectives, this utility model provides the following technical solution: In a railway vehicle depot or vehicle factory, the wheel and axle workshop building 1 includes wheelsets 1A, columns 1B, overhead tracks 1X, wheelset inspection area 1C, wheelset conveying system 1D, and pre-inspection work area 2. The pre-inspection work area 2 is the work area preceding the wheelset inspection area 1C in the wheelset maintenance and production process. Assuming the length of building 1 is longitudinal, the overhead tracks 1X installed on columns 1B are arranged longitudinally. The pre-inspection work area 2 includes an equipment area 3, a wheelset storage area 4, and a truss... The gantry robot 5 is a component of the wheelset conveying system 1D. The wheelset storage area 4 is located between two rows of horizontal columns 1B and includes several storage positions 4A. The equipment area 3 is located on both sides or one side of the wheelset storage area 4. The side of the equipment area 3 away from the wheelset storage area 4 includes a personnel passage 2C. The equipment area 3 includes several longitudinally arranged devices 3A for the maintenance of wheelsets 1A. The wheelset 1A is conveyed between the devices 3A and the storage positions 4A by the gantry robot 5 running on the overhead track 1X.
[0012] As a further embodiment of this utility model: the gantry robot 5 includes a large trolley 5A, a small trolley 5B, a lifting device 5C, and a gripper 5D. The large trolley 5A includes a transverse track 5AY. The gripper 5D that grasps the wheel pair 1A is mounted on the lifting device 5C, and the lifting device 5C is mounted on the small trolley 5B. The small trolley 5B moves laterally on the transverse track 5AY, and the large trolley 5A moves longitudinally on the aerial track 1X.
[0013] As a further embodiment of this utility model: the device 3A includes a two-station device 6, which includes a buffer position 6A, a two-station working position 6B, and a two-station conveying device 6C. The buffer position 6A is located between the two-station working position 6B and the wheelset storage area 4.
[0014] As a further embodiment of this utility model: the equipment 3A includes a three-station equipment 7, which includes a placement station 7A, a three-station working station 7B, a picking station 7C, a personnel working station, and a three-station conveying device 7D.
[0015] As a further embodiment of this utility model: the large trolley 5A includes two small trolleys 5B or the small trolleys 5B include two sets of grippers 5D, and the gantry robot 5 can simultaneously grasp two wheelsets 1A; the three-station conveying device 7D includes a three-station inclined rail 7D1, a rear stopper 7D2 and a front stopper 7D3, the three-station inclined rail 7D1 is located at the beginning of the placement position 7A and higher than the tail end of the picking position 7C, the rear stopper 7D2 is located at the placement position 7A, and the front stopper 7D3 is located at the three-station working position 7B.
[0016] As a further embodiment of this utility model: the equipment process layout and gantry robot for railway wheel and axle workshop is characterized in that the two-station workstation 6B includes a lifting and adjusting device 67, which lifts the wheelset 1A and adjusts its height so that the wheelset 1A is clamped on the two-station equipment 6.
[0017] It should be noted that the three-station workstation 7B can also be equipped with a lifting and adjusting device 67. The lifting and adjusting device 67 can lift the wheelset 1A and adjust its height so that the wheelset 1A can be clamped on the three-station equipment 7.
[0018] As a further embodiment of this utility model: the wheelset conveying system 1D includes a plate chain conveyor 8, and the running direction of the plate chain conveyor 8 is the length direction of the wheelset 1A.
[0019] As a further embodiment of this utility model: the factory building 1 includes a parallel factory building 12 that is adjacent to the wheelset inspection area 1C and the pre-inspection work area 2, although they are not in the same span. The plate chain conveyor 8 in the parallel factory building 12 includes a transversely arranged transverse conveyor 9. The wheelset inspection area 1C in the parallel factory building 12 includes a parallel inspection entrance 1C2.
[0020] The transport of wheelset 1A from the pre-inspection work area 2 to the parallel inspection entrance 1C2 is achieved by the transverse conveyor 9, which includes a plate chain entrance 9B and a wheel puller 9C. The transport of wheelset 1A from the pre-inspection work area 2 to the plate chain entrance 9B is also achieved by the gantry robot 5. The transport of wheelset 1A from the plate chain conveyor 8 to the parallel inspection entrance 1C2 is achieved by the wheel puller 9C.
[0021] As a further embodiment of this utility model: the plate chain conveyor 8 includes a high-level plate chain conveyor 8A located at the inlet 2A and a low-level plate chain conveyor 8B located at the outlet 2B. The high-level plate chain conveyor 8A and the low-level plate chain conveyor 8B are respectively located at the placement position 7A and the picking position 7C of the three-station equipment 7.
[0022] As a further embodiment of this utility model: the wheelset 1A includes a truck wheelset, the wheelset storage area 4 includes a pedestrian platform 4B, the pedestrian platform 4B includes several large treads 4B1, small treads 4B2 and axle grooves 4B3, the large treads 4B1 are located between the axles of adjacent wheelsets 1A, and the small treads 4B2 are located between the axle ends of two adjacent wheelsets 1A; the axle grooves 4B3 located in the storage position 4A are used to place the wheelset 1A.
[0023] Compared with the prior art, the main features and advantages of this utility model are as follows:
[0024] 1) The ground tracks for wheelset travel are eliminated, and the production equipment is arranged in parallel, which is a flexible production mode.
[0025] 2) Wheelset transportation between different devices, between wheelset storage locations, and between devices and wheelset storage locations is mainly achieved by using gantry robots.
[0026] 3) The layout between the wheels and axles can have pedestrian walkways and equipment areas on both sides, with the wheelset storage area in the middle. An integrated, embedded platform can be installed in the wheelset storage area, with the length direction of the stored wheelsets parallel to the length direction between the wheels and axles, and they can be staggered or crossed; this platform serves the dual function of wheelset storage and emergency personnel passage.
[0027] 4) When the gantry robot malfunctions, the operator can stand on the platform in the storage area and use the workshop crane for emergency handling.
[0028] 5) Since the wheelsets are transported in the air, they can be stored densely in the ground storage area, which can greatly increase the storage capacity of the wheelsets, not only meeting production needs but also facilitating the management and dispatch of the wheelsets.
[0029] 6) Since the wheelset production equipment is arranged in parallel, the wheelset storage area has actually become a unified large-capacity wheel storage warehouse shared by all wheelset workstations. In extreme cases, it can even become a wheel storage warehouse exclusively for a certain tooling equipment. For example, when all the wheelset bearing break-in testing equipment fails, the entire storage area can store only one type of wheelset to be broken in and tested, so as not to affect the operation of the previous process.
[0030] In summary, the main advantages of this utility model are: the production equipment and operation lines in the railway wheel and axle workshop are reasonably arranged, occupy a small area, have a high degree of automation, and have high production efficiency. In particular, the transportation efficiency of wheelsets and the utilization rate of production equipment are significantly improved, and a basic platform is built for the future intelligent wheel and axle workshop. Attached Figure Description
[0031] Figure 1This is a structural diagram of wheelset 1A, column 1B, overhead track 1X, personnel passage 2C, and pre-inspection work area 2 within factory building 1. It is also a structural diagram of equipment area 3, wheelset storage area 4, and gantry robot 5, which constitute pre-inspection work area 2. Furthermore, it is a structural diagram of storage space 4A, which constitutes wheelset storage area 4; a structural diagram of equipment 3A, which constitutes equipment area 3; a structural diagram of entrance 2A and exit 2B, which constitute pre-inspection work area 2; a structural diagram of pedestrian platform 4B, which constitutes wheelset storage area 4; and a structural diagram of the large tread 4B1, small tread 4B2, and... The structural schematic diagram of shaft groove 4B3 is also a structural schematic diagram of the two-station equipment 6 that makes up equipment 3A, a structural schematic diagram of the storage position 6A, the two-station working position 6B and the two-station conveying device 6C that make up the two-station equipment 6, a structural schematic diagram of the three-station equipment 7 that makes up equipment 3A, a structural schematic diagram of the placement position 7A, the three-station working position 7B, the picking position 7C and the three-station conveying device 7D that make up the three-station equipment 7, a structural schematic diagram of the high-level plate chain conveyor 8A and the low-level plate chain conveyor 8B that make up the plate chain conveyor 8, and a structural schematic diagram of the lifting and adjusting device 67;
[0032] Figure 2 yes Figure 1 The AA sectional view is also a structural schematic diagram of the gantry robot 5 consisting of the large trolley 5A, the small trolley 5B, the lifting device 5C, and the gripper 5D. It is also a structural schematic diagram of the transverse track 5AY that makes up the large trolley 5A. It is also a structural schematic diagram of the placement position 7A, the three-station working position 7B, the picking position 7C, and the three-station conveying device 7D that make up the three-station equipment 7. It is also a structural schematic diagram of the three-station inclined rail 7D1, the rear stop 7D2, and the front stop 7D3 that make up the three-station conveying device 7D.
[0033] Figure 3 yes Figure 1 The BB cross-sectional view is also a structural schematic diagram of the low-level plate chain conveyor 8B that makes up the plate chain conveyor 8.
[0034] Figure 4 yes Figure 1 The CC sectional view is also a structural schematic diagram of the two-station equipment 6 and the three-station equipment 7 that make up the equipment 3A, as well as a structural schematic diagram of the two-station inclined rail 6C1 and the two-station stopper 6C2 that make up the two-station conveying device 6C.
[0035] Figure 5 yes Figure 4 The DD sectional view is also a structural schematic diagram of the multi-stage lifting device 5C, and a structural schematic diagram of the gripper 5D grasping wheel pair 1.
[0036] Figure 6 yes Figure 5The enlarged view of the part is also a structural schematic diagram of the telescopic head 5D1A that makes up the telescopic device 5D1;
[0037] Figure 7 It is a structural schematic diagram of the long factory building 11 that makes up the factory building 1, a structural schematic diagram of the wheelset inspection area 1C and the pre-inspection work area 2 inside the long factory building 11, and a structural schematic diagram of the inspection entrance 1C1 that makes up the wheelset inspection area 1C.
[0038] Figure 8 It is a structural schematic diagram of the parallel workshop 12 that makes up the workshop 1, a structural schematic diagram of the parallel inspection entrance 1C2 that makes up the wheelset inspection area 1C, a structural schematic diagram of the plate chain conveyor 8 that makes up the wheelset conveying system 1D, a structural schematic diagram of the transverse conveyor 9 that makes up the plate chain conveyor 8, and a structural schematic diagram of the plate chain entrance 9B and the pulley 9C that make up the transverse conveyor 9.
[0039] Figure 9 yes Figure 5 The P-direction view;
[0040] Figure 10 This is another equipment and process layout plan of the railway wheel and axle workshop;
[0041] Figure 11 yes Figure 10 EE sectional view.
[0042] Factory building 1, wheelset 1A, column 1B, wheelset inspection area 1C, inspection entrance 1C1, parallel inspection entrance 1C2, wheelset conveyor system 1D, overhead track 1X, long factory building 11, parallel factory building 12.
[0043] Pre-inspection work area 2, entrance 2A, exit 2B, personnel passage 2C.
[0044] Equipment Area 3, Equipment 3A
[0045] Wheelset storage area 4, storage position 4A, pedestrian platform 4B, large tread 4B1, small tread 4B2, axle groove 4B3.
[0046] Gantry robot 5, main trolley 5A, transverse track 5AY, trolley 5B, lifting device 5C, gripper 5D, telescopic device 5D1, telescopic head 5D1A.
[0047] Two-station equipment 6, storage position 6A, two-station working position 6B, two-station conveyor device 6C, two-station inclined rail 6C1, two-station stopper 6C2, lifting and adjusting device 67.
[0048] Three-station equipment 7, placement station 7A, three-station working station 7B, picking station 7C, three-station conveyor device 7D, three-station inclined rail 7D1, rear stop 7D2, front stop 7D3.
[0049] Plate chain conveyor 8, high-level plate chain conveyor 8A, low-level plate chain conveyor 8B.
[0050] Horizontal conveyor 9, plate chain inlet 9B, pulley 9C. Detailed Implementation
[0051] The technical solutions of the present utility model will be described below with reference to the accompanying drawings of the embodiments of the present utility model. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present utility model without creative effort are within the protection scope of the present utility model.
[0052] Please see Figures 1-11 In this embodiment of the present invention, in a railway vehicle depot or vehicle factory, the wheel and axle workshop 1 includes wheelsets 1A, columns 1B, overhead tracks 1X, wheelset inspection area 1C, wheelset conveying system 1D, and pre-inspection work area 2. The pre-inspection work area 2 is the work area preceding the wheelset inspection area 1C in the wheelset maintenance and production process. Assuming the length of workshop 1 is longitudinal, the overhead tracks 1X installed on columns 1B are arranged longitudinally. The pre-inspection work area 2 includes an equipment area 3, a wheelset storage area 4, and a gantry robot 5. The gantry robot 5 is a component of the wheelset conveying system 1D. The wheelset storage area 4 is located between two rows of horizontal columns 1B and includes several storage positions 4A. The equipment area 3 is located on both sides or one side of the wheelset storage area 4. The side of the equipment area 3 away from the wheelset storage area 4 includes a personnel passage 2C. The equipment area 3 includes several longitudinally arranged devices 3A for the maintenance of wheelsets 1A. The wheelset 1A is conveyed between the devices 3A and the storage positions 4A by the gantry robot 5 running on the overhead track 1X.
[0053] It should be noted that the wheelsets 1A in the wheelset storage area 4 can be arranged in a staggered manner; the transport of wheelsets 1A between each device 3A and between each temporary storage position 4A can also be achieved by the gantry robot 5.
[0054] It should also be noted that the pre-inspection work area 2 includes entrance 2A and exit 2B; the transportation of wheelset 1A between entrance 2A and equipment 3A, entrance 2A and temporary storage position 4A, equipment 3A and exit 2B, and temporary storage position 4A and exit 2B can all be achieved by gantry robot 5.
[0055] It should also be noted that: there may be no equipment 3A between wheelset storage area 4 and column 1B, but there is personnel passage 2C; after the pre-inspection work is completed in pre-inspection work area 2, subsequent work can be carried out on wheelset 1A.
[0056] The gantry robot 5 includes a large trolley 5A, a small trolley 5B, a lifting device 5C, and a gripper 5D. The large trolley 5A includes a transverse track 5AY. The gripper 5D that grasps the wheel pair 1A is mounted on the lifting device 5C, and the lifting device 5C is mounted on the small trolley 5B. The small trolley 5B moves laterally on the transverse track 5AY, and the large trolley 5A moves longitudinally on the aerial track 1X.
[0057] It should be noted that: the lifting device 5C can be a multi-stage lifting device; the gripper 5D can be a horizontal telescopic device 5D1, the telescopic device 5D1 includes a telescopic head 5D1A, the telescopic head 5D1A can extend into the top of the inner concave ring of the wheel rim;
[0058] It should also be noted that the orientation of wheelset 1A in equipment area 3 and wheelset storage area 4 may not be the same. When they are perpendicular to each other, the gantry robot 5 can meet the operation requirements by adding a slewing device on the trolley 5B.
[0059] The device 3A includes a two-station device 6, which includes a buffer position 6A, a two-station working position 6B, and a two-station conveying device 6C. The buffer position 6A is located between the two-station working position 6B and the wheelset storage area 4.
[0060] It should be noted that the gantry robot 5 can operate in mode A on the two-station equipment 6. Mode A includes the following main steps:
[0061] 1) The gantry robot 5 places the wheelset 1A to be processed into the empty buffer position 6A;
[0062] 2) The gantry robot 5 then removes the completed wheelset 1A from the second workstation 6B;
[0063] 3) The two-station conveyor 6C conveys the wheelset 1A of the buffer position 6A to the working position.
[0064] It should also be noted that the gantry robot 5 can also operate in mode B on the two-station equipment 6. Mode B includes the following main steps:
[0065] 1) The two-station equipment 6 places the completed wheelset 1A into the two-station work station 6B;
[0066] 2) The two-station conveyor 6C conveys the wheelset 1A of the two-station working position 6B to the buffer position 6A;
[0067] 3) The gantry robot 5 places the wheelset 1A to be processed at the second workstation 6B;
[0068] 4) The gantry robot 5 removes wheel pair 1A from buffer position 6A;
[0069] It should also be noted that: 1) the two-station equipment 6 may include a wheelset spinning machine; 2) the two-station conveying device 6C may include a two-station inclined rail 6C1 and a two-station stopper 6C2. The two-station stopper 6C2 is installed between the buffer position 6A and the two-station working position 6B. When the two-station stopper 6C2 retracts, the wheelset 1A at the higher position can roll to the lower position.
[0070] The equipment 3A includes a three-station equipment 7, which includes a placement station 7A, a three-station working station 7B, a picking station 7C, a personnel working station, and a three-station conveying device 7D.
[0071] It should be noted that: the three-station equipment 7 may include an ultrasonic flaw detector; the part picking station 7C and the personnel work station may be the same location;
[0072] It should also be noted that the operation mode of the gantry robot 5 on the three-station equipment 7 includes the following main steps:
[0073] 1) The gantry robot 5 places the wheelset 1A to be processed into the empty placement position 7A;
[0074] 2) The gantry robot 5 takes away the wheelset 1A that has been processed on the picking position 7C;
[0075] 3) The three-station conveyor 7D conveys the wheelset 1A on the three-station work station 7B to the pick-up station 7C, and then conveys the wheelset 1A on the placement station 7A to the three-station work station 7B.
[0076] 4) Operators enter their work positions.
[0077] The large trolley 5A includes two small trolleys 5B, or the small trolleys 5B include two sets of grippers 5D. The gantry robot 5 can simultaneously grasp two wheelsets 1A. The three-station conveying device 7D includes a three-station inclined rail 7D1, a rear stopper 7D2, and a front stopper 7D3. The three-station inclined rail 7D1 is located at the beginning of the placement position 7A, which is higher than the end of the picking position 7C. The rear stopper 7D2 is located at the placement position 7A, and the front stopper 7D3 is located at the three-station working position 7B.
[0078] It should be noted that both the rear stop 7D2 and the front stop 7D3 are retractable stops; when the rear stop 7D2 retracts, the wheel pair 1A of the placement position 7A can roll to the three-position working position 7B; when the front stop 7D3 retracts, the wheel pair 1A of the three-position working position 7B can roll to the picking position 7C.
[0079] It should also be noted that the position of one wheelset 1A on the pick-up position 7C, which is close to the three-station work position 7B, can be a personnel work position.
[0080] The equipment process layout and gantry robot for railway wheel and axle workshop are characterized in that the two-station workstation 6B includes a lifting and adjusting device 67, which lifts the wheelset 1A and adjusts its height so that the wheelset 1A is clamped on the two-station equipment 6.
[0081] The wheelset conveying system 1D includes a plate chain conveyor 8, and the running direction of the plate chain conveyor 8 is the length direction of the wheelset 1A.
[0082] It should be noted that: the factory building 1 may include the wheelset inspection area 1C and the pre-inspection work area 2 in the same span of the long factory building 11. The wheelset inspection area 1C in the long factory building 11 includes the inspection entrance 1C1. The transport of wheelset 1A from the pre-inspection work area 2 to the inspection entrance 1C1 is achieved by the gantry robot 5.
[0083] The aforementioned factory building 1 includes a parallel factory building 12, which is adjacent to the wheelset inspection area 1C and the pre-inspection work area 2, although they are not in the same span. The plate chain conveyor 8 in the parallel factory building 12 includes a transversely arranged transverse conveyor 9. The wheelset inspection area 1C in the parallel factory building 12 includes a parallel inspection entrance 1C2.
[0084] The transport of wheelset 1A from the pre-inspection work area 2 to the parallel inspection entrance 1C2 is achieved by the transverse conveyor 9, which includes a plate chain entrance 9B and a wheel puller 9C. The transport of wheelset 1A from the pre-inspection work area 2 to the plate chain entrance 9B is also achieved by the gantry robot 5. The transport of wheelset 1A from the plate chain conveyor 8 to the parallel inspection entrance 1C2 is achieved by the wheel puller 9C.
[0085] The plate chain conveyor 8 includes a high-level plate chain conveyor 8A located at the inlet 2A and a low-level plate chain conveyor 8B located at the outlet 2B. The high-level plate chain conveyor 8A and the low-level plate chain conveyor 8B are respectively located at the placement position 7A and the picking position 7C of the three-station equipment 7.
[0086] The wheelset 1A includes a truck wheelset, and the wheelset storage area 4 includes a pedestrian platform 4B. The pedestrian platform 4B includes several large treads 4B1, small treads 4B2, and axle grooves 4B3. The large treads 4B1 are located between the axles of adjacent wheelsets 1A, and the small treads 4B2 are located between the axle ends of two adjacent wheelsets 1A. The axle grooves 4B3 located in the storage position 4A are used to place the wheelsets 1A.
[0087] It should be noted that the height of the large tread 4B1 and small tread 4B2 can be higher than the axle body of wheelset 1A.
[0088] It should also be noted that: steps may be provided around the pedestrian platform 4B and between two adjacent devices 3A, so that workers can enter and exit the pedestrian platform 4B for emergency handling in case of abnormal conditions such as malfunction of the gantry robot 5.
[0089] In the description of this utility model, it should be noted that the terms "center," "upper," "lower," "left," "right," "vertical," "horizontal," "front," and "rear," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this utility model. In this utility model, it should also be noted that the terms "installation" and "connection" should be interpreted broadly. For example, they can refer to fixed connection, detachable connection, integral molding connection, mechanical connection, or indirect connection through an intermediate medium. The specific meaning of the terms in this utility model can be understood according to the specific circumstances.
[0090] Furthermore, it should be understood that although this specification describes embodiments, not every embodiment contains only one independent technical solution. This narrative style is merely for clarity. Those skilled in the art should consider the specification as a whole, and the technical solutions in each embodiment can also be appropriately combined to form other embodiments that can be understood by those skilled in the art.
Claims
1. A process layout for equipment and a gantry robot used in a railway wheel and axle workshop, characterized by: The wheel and axle workshop (1) in a railway vehicle depot or rolling stock plant includes wheelsets (1A), columns (1B), overhead tracks (1X), wheelset inspection area (1C), wheelset conveying system (1D), and pre-inspection work area (2). The pre-inspection work area (2) is the work area preceding the wheelset inspection area (1C) in the wheelset maintenance and production process. Assuming the length of the workshop (1) is longitudinal, the overhead tracks (1X) installed on the columns (1B) are arranged longitudinally. The pre-inspection work area (2) includes an equipment area (3), a wheelset storage area (4), and a gantry robot (5). The gantry robot (5) is... The wheelset conveying system (1D) consists of a wheelset storage area (4) located between two rows of horizontal columns (1B) and includes several storage positions (4A); an equipment area (3) located on one or both sides of the wheelset storage area (4) and includes a personnel passage (2C) on the side of the equipment area (3) away from the wheelset storage area (4); and several longitudinally arranged equipment (3A) for wheelset (1A) maintenance. The wheelset (1A) is conveyed between the equipment (3A) and the storage positions (4A) by a gantry robot (5) running on an overhead track (1X).
2. The equipment process layout and gantry robot for a railway wheel and axle workshop according to claim 1, characterized in that: The gantry robot (5) includes a large trolley (5A), a small trolley (5B), a lifting device (5C), and a gripper (5D). The large trolley (5A) includes a transverse track (5AY). The gripper (5D) that grasps the wheelset (1A) is mounted on the lifting device (5C), and the lifting device (5C) is mounted on the small trolley (5B). The small trolley (5B) moves laterally on the transverse track (5AY), and the large trolley (5A) moves longitudinally on the aerial track (1X).
3. The equipment process layout and gantry robot for a railway wheel and axle workshop according to claim 2, characterized in that: The device (3A) includes a two-station device (6), which includes a buffer position (6A), a two-station working position (6B) and a two-station conveying device (6C). The buffer position (6A) is located between the two-station working position (6B) and the wheelset storage area (4).
4. The equipment process layout and gantry robot for a railway wheel and axle workshop according to claim 2, characterized in that: The equipment (3A) includes a three-station equipment (7), which includes a placement station (7A), a three-station working station (7B), a picking station (7C), a personnel working station, and a three-station conveying device (7D).
5. The equipment process layout and gantry robot for a railway wheel and axle workshop according to claim 2, characterized in that: The large vehicle (5A) includes two small vehicles (5B) or the small vehicles (5B) include two sets of grippers (5D). The gantry robot (5) can simultaneously grab two wheelsets (1A). The three-station conveying device (7D) includes a three-station inclined rail (7D1), a rear stop (7D2) and a front stop (7D3). The three-station inclined rail (7D1) is located at the beginning of the placement position (7A) and higher than the end of the picking position (7C). The rear stop (7D2) is located at the placement position (7A) and the front stop (7D3) is located at the three-station working position (7B).
6. The equipment process layout and gantry robot for a railway wheel and axle workshop according to claim 3, characterized in that: The two-station workstation (6B) includes a lifting and adjusting device (67), which lifts the wheelset (1A) and adjusts its height so that the wheelset (1A) is clamped on the two-station equipment (6).
7. The equipment process layout and gantry robot for a railway wheel and axle workshop according to claim 6, characterized in that: The wheelset conveying system (1D) includes a plate chain conveyor (8), and the running direction of the plate chain conveyor (8) is the length direction of the wheelset (1A).
8. The equipment process layout and gantry robot for a railway wheel and axle workshop according to claim 7, characterized in that: The factory building (1) includes a parallel factory building (12) where the wheelset inspection area (1C) and the pre-inspection work area (2) are not in the same span but are adjacent. The plate chain conveyor (8) in the parallel factory building (12) includes a transversely arranged transverse conveyor (9). The wheelset inspection area (1C) in the parallel factory building (12) includes a parallel inspection entrance (1C2). The conveying of the wheelset (1A) from the pre-inspection work area (2) to the parallel inspection entrance (1C2) is achieved by the transverse conveyor (9). The transverse conveyor (9) includes a plate chain entrance (9B) and a wheel puller (9C). The conveying of the wheelset (1A) from the pre-inspection work area (2) to the plate chain entrance (9B) is also achieved by the gantry robot (5). The conveying of the wheelset (1A) from the plate chain conveyor (8) to the parallel inspection entrance (1C2) is achieved by the wheel puller (9C).
9. The equipment process layout and gantry robot for a railway wheel and axle workshop according to claim 7, characterized in that: The plate chain conveyor (8) includes a high-level plate chain conveyor (8A) located at the inlet (2A) and a low-level plate chain conveyor (8B) located at the outlet (2B). The high-level plate chain conveyor (8A) and the low-level plate chain conveyor (8B) are respectively located at the placement position (7A) and the picking position (7C) of the three-station equipment (7).
10. The equipment process layout and gantry robot for a railway wheel and axle workshop according to claim 1, characterized in that: The wheelset (1A) includes a truck wheelset. The wheelset storage area (4) includes a pedestrian platform (4B). The pedestrian platform (4B) includes several large treads (4B1), small treads (4B2) and axle grooves (4B3). The large treads (4B1) are located between the axles of adjacent wheelsets (1A), and the small treads (4B2) are located between the axle ends of two adjacent wheelsets (1A). The axle grooves (4B3) located in the storage position (4A) are used to place the wheelsets (1A).