一种建筑砖生产用成品砖运输机构
By adding a hydraulic cylinder and electromagnet clamping mechanism to the robotic arm, the problem of clamping difficulties caused by inconsistent brick sizes was solved, achieving stable clamping of bricks and accident alerts, thus improving transportation safety.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- YONGJING SHILUO BUILDING MATERIALS CO LTD
- Filing Date
- 2025-09-19
- Publication Date
- 2026-07-17
Smart Images

Figure CN224512550U_ABST
Abstract
Claims
1. A finished brick transporting mechanism for building brick production, comprising a clamping mechanism (1), characterized by: The clamping mechanism (1) includes a clamping arm (101), with two limiting plates (102) fixedly connected to the inner wall of the clamping arm (101), two sliding rods (103) fixedly connected between the two limiting plates (102), and two inner clamping boxes (104) slidably connected between the two sliding rods (103). A return spring (105) sleeved on the sliding rod (103) is fixedly connected between the upper ends of the two inner clamping boxes (104). A sliding column (108) is fixedly connected inside the clamping arm (101). 108) Two outer clamping plates (106) are slidably connected on the upper side. A lead screw (107) is rotatably connected inside the clamping arm (101). Two sliding sleeves (109) are threaded on the lead screw (107) and fixedly connected to the outer clamping plates (106). A motor (110) is fixedly connected to the side wall of the clamping arm (101), and the output end of the motor (110) is fixedly connected to the lead screw (107). A pressure boosting mechanism (2) is provided on the upper side wall of the clamping arm (101), and a reminder mechanism (3) is provided on the pressure boosting mechanism (2).
2. The finished brick conveying mechanism for the production of building bricks according to claim 1, characterized in that: The pressurization mechanism (2) includes a hydraulic cylinder (201) fixedly connected to the upper side wall of the clamping arm (101), a magnetic plug (202) is slidably connected inside the hydraulic cylinder (201), and a tension spring (203) is fixedly connected between the magnetic plug (202) and the clamping arm (101).
3. The finished brick conveying mechanism for the production of building bricks according to claim 2, characterized in that: An electromagnet (204) is fixedly connected to the upper end of the hydraulic cylinder (201), and the electromagnet (204) is magnetically connected to the magnetic plug (202).
4. The finished brick conveying mechanism for the production of building bricks according to claim 3, characterized in that: Hydraulic pipes (205) are connected between the hydraulic cylinder (201) and the two inner clamping boxes (104).
5. A finished brick transporting mechanism for the production of building bricks according to claim 4, characterized in that: The reminder mechanism (3) includes an air pipe (301) connected to the lower end of the hydraulic cylinder (201), an air flow sensor (302) is provided on the air pipe (301), and an audible and visual alarm (303) is fixedly connected to the clamping arm (101), and the audible and visual alarm (303) is electrically connected to the air flow sensor (302).
6. A finished brick transporting mechanism for a building brick production according to claim 5, characterized in that: A rubber bladder (1042) is fixedly connected to the side wall of the inner clamping box (104), and a plurality of thin rods (1041) for supporting the rubber bladder (1042) are fixedly connected to the side wall of the inner clamping box (104).
7. A finished brick transporting mechanism for a building brick production according to claim 6, characterized in that: The upper end of the clamping arm (101) is fixedly connected to a protective cover (4), and the upper end of the protective cover (4) is fixedly connected to a robotic arm (5).