一种塔机地脚固定工装

The design of the sinking mechanism, columns, and adjustment mechanism solved the problem of displacement and tilting of the tower crane's foundation during the pouring process, ensuring the stability of the foundation and the safety of the tower crane, and achieving stable installation of the tower crane.

CN224513075UActive Publication Date: 2026-07-17SHANDONG MINGWEI ELEVATORING EQUIP

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
SHANDONG MINGWEI ELEVATORING EQUIP
Filing Date
2025-04-10
Publication Date
2026-07-17

AI Technical Summary

Technical Problem

The foundation of a tower crane is prone to shifting and tilting during the pouring process, which can lead to non-compliance with verticality requirements, affecting the installation and structural stability of the tower crane, and may even cause the tower crane to collapse.

Method used

The system employs a sinking mechanism, columns, adjustment mechanism, and support mechanism. The position of the anchor is adjusted by the cooperation of adjustment plates, moving blocks, screws, and rotating wheels. Before concrete pouring, a first and second base plate are pre-embedded to fix the anchor, and reinforcement blocks and installation blocks are used to enhance stability.

Benefits of technology

It effectively prevents the foundation from shifting or tilting during the pouring process, ensures the verticality of the foundation, improves the convenience of tower crane installation and structural stability, and avoids the risk of tower crane collapse due to unstable foundation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224513075U_ABST
    Figure CN224513075U_ABST
Patent Text Reader

Abstract

本实用新型公开了一种塔机地脚固定工装,属于塔机地脚技术领域。一种塔机地脚固定工装,包括沉没机构、立柱以及调节机构,所述沉没机构和调节机构的数量为四个,所述立柱位于四个沉没机构之间,四个所述调节机构位于立柱的四角,所述地脚和立柱之间设有支撑机构。本实用新型通过沉没机构、立柱以及调节机构,一法盘和二法盘在浇筑过程中提前放置混泥土内部,而地脚与一法盘固接,能够保证地脚的稳定性,立柱与调节机构配合使用不仅通过调节板和螺杆的配合使用调节四个沉没机构之间的间距,能够适配不同型号的塔吊,提高了地脚的适用性。
Need to check novelty before this filing date? Find Prior Art

Claims

1. A tower crane footing fixing tool, comprising a sinking mechanism (1), a column (2) and an adjusting mechanism (3), characterized in that: The number of the sinking mechanism (1) and the adjustment mechanism (3) is four. The column (2) is located between the four sinking mechanisms (1). The four adjustment mechanisms (3) are located at the four corners of the column (2). A support mechanism (4) is provided between the foot (11) and the column (2).

2. The tower crane anchor point fixing tool of claim 1, wherein: The adjustment mechanism (3) includes an adjustment plate (31), a moving block (32), a screw (33) and a rotating wheel (34). One end of the adjustment plate (31) is rotatably connected to the bottom of the column (2) through a rotating shaft. The other end of the adjustment plate (31) is rotatably connected to the side of the moving block (32) through a rotating shaft. The screw (33) is located inside the column (2). The moving block (32) is sleeved on the surface of the screw (33) and engaged. The top of the screw (33) extends through to the outside of the column (2) and is fixedly connected to the rotating wheel (34). The bottom of the screw (33) is rotatably connected to the inside of the column (2) through a rotating shaft.

3. The tower crane anchor point securing tool of claim 1, wherein: The sinking mechanism (1) includes a base (11), a first plate (12) and a second plate (13). The bottom of the base (11) is fixed to the top of the first plate (12). The first plate (12) is fixed to the second plate (13) by bolts. The second plate (13) is located inside the concrete.

4. The tower crane anchor point securing tool of claim 3, wherein: The support mechanism (4) includes a straight plate (41) and two straight plates (42). One end of the straight plate (41) is fixed to the side of the foot (11), and one end of the two straight plates (42) is fixed to the side of the column (2). The other end of the straight plate (41) extends into the interior of the other end of the two straight plates (42).

5. The tower crane anchor point securing tool of claim 2, wherein: The column (2) has a sliding groove inside, and the moving block (32) moves up and down inside the sliding groove.

6. The tower crane anchor point securing tool of claim 3, wherein: The bottom of the two-plate (13) is fixedly connected to a reinforcing block (5), which is conical in shape and has a matching conical spiral groove on its surface.

7. The tower crane anchor point securing tool of claim 1, wherein: The four corners of the column (2) are fixed with mounting blocks (6), and the mounting blocks (6) are fixed to the concrete by bolts.