一种电梯钢结构走廊楼承板

The elevator steel structure design, including the combination of support beams, connecting beams, support plates, outer protective plates, glass frames, and handrails, solves the problems of simple floor deck structure and insufficient protection, improves load-bearing capacity and safety, and enhances aesthetics.

CN224514520UActive Publication Date: 2026-07-17郑州中塔钢结构有限公司

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
郑州中塔钢结构有限公司
Filing Date
2025-08-04
Publication Date
2026-07-17

AI Technical Summary

Technical Problem

Existing floor decking structures are simple, have limited load-bearing capacity, are prone to deformation or breakage, and lack protection, affecting safety and user experience.

Method used

The elevator adopts a steel structure design, including a combination of support beams, connecting beams, support plates, outer protective plates, glass frames and handrails, which enhances the load-bearing capacity and provides all-round protection.

Benefits of technology

It improves the load-bearing capacity and safety of the floor decking, enhances its aesthetics, reduces psychological stress, and provides protection in severe weather.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224514520U_ABST
    Figure CN224514520U_ABST
Patent Text Reader

Abstract

本实用新型涉及电梯结构技术领域,具体为一种电梯钢结构走廊楼承板;包括电梯井,电梯井与楼房间设置有多个楼承板;楼承板包括一对相互平行的支撑梁,支撑梁两端均设置有梁连接块,梁连接块分别与相对应的电梯井和楼房相连接;支撑梁之间设置有一对连接梁,连接梁的两端分别与相对应的支撑梁固接;支撑梁上均固接有多个连接卡板,支撑梁之间设置有多个支撑板,连接卡板上均设置有与支撑板相配合的卡槽;支撑梁外侧设置有外防护板,支撑板、支撑梁和连接卡板均与外防护板相配合;外防护板上方均设置有玻璃架和扶手,外防护板上方的玻璃架相互对应;有效解决了现有技术中电梯井与楼房间支撑板结构简单和支撑板上缺乏防护的问题。
Need to check novelty before this filing date? Find Prior Art

Claims

1. An elevator steel structure corridor floor deck, characterized by: The system includes an elevator shaft (1), which is parallel to the building. Multiple floor decks are installed between the elevator shaft (1) and the building. Each floor deck includes a pair of parallel support beams (5). Each support beam (5) has a beam connecting block (8) at both ends. The beam connecting block (8) is connected to the corresponding elevator shaft (1) and the building, respectively. A pair of connecting beams (7) are installed between the support beams (5). The connecting beams (7) are cross-connected and their ends are fixed to the corresponding support beams (5), respectively. Multiple connecting plates (6) are fixedly connected to the support beams (5), and multiple support plates (3) are provided between the support beams (5). The connecting plates (6) are provided with slots that cooperate with the support plates (3). An outer protective plate (4) is provided on the outside of the support beams (5). The support plates (3), support beams (5) and connecting plates (6) are all in cooperation with the outer protective plate (4). A glass frame (2) and a handrail are provided on the top of the outer protective plate (4). The glass frames (2) on the top of the outer protective plate (4) correspond to each other.

2. The elevator steel structural corridor floor deck according to claim 1, wherein: The upper end of the glass frame (2) is connected to the lower end of the outer protective plate (4) in the floor deck above it.

3. The elevator steel structural corridor floor deck of claim 1, wherein: The support beam (5) and the beam connecting block (8) are fixed together by screws and nuts.

4. The elevator steel structural corridor floor deck of claim 1, wherein: The support plates (3) are arranged in an array on the support beam (5).

5. The elevator structural steel corridor floor deck of claim 1, wherein: The two ends of the support plate (3) are fixedly connected to the corresponding support beams (5).

6. The elevator structural steel corridor floor deck of claim 1, wherein: The adjacent support plates (3) are in contact with each other.

7. The elevator structural steel corridor floor deck according to claim 1, characterized in that: The outer protective plate (4) surrounds the support beam (5) and the connecting plate (6).

8. The elevator steel structural corridor floor deck of claim 1, wherein: The handrail is located on the inside of the glass frame (2).