一种建筑脚手架及钢构一体式支撑结构

By combining frame-type horizontal bars, square tube supports, and wooden plywood in the construction scaffolding design, the problems of scaffolding stiffness attenuation and load variation in existing technologies have been solved. This has resulted in a stable three-dimensional force-bearing system and dynamic control, improving construction safety and efficiency, and meeting the needs of cultural relic protection.

CN224514684UActive Publication Date: 2026-07-17YUNNAN CONSTR ENG GENERAL CONTRACTING

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
YUNNAN CONSTR ENG GENERAL CONTRACTING
Filing Date
2025-07-30
Publication Date
2026-07-17

Smart Images

  • Figure CN224514684U_ABST
    Figure CN224514684U_ABST
Patent Text Reader

Abstract

本实用新型涉及建筑施工技术领域,具体为一种建筑脚手架及钢构一体式支撑结构,包括主体架,主体架包括若干立杆和水平杆,主体架的顶部安装有主桁架,主桁架的中部下方安装有方管支撑,方管支撑的底部与主体架的顶部之间安装有木层板,上下两层水平杆之间通过斜杆支撑固定,水平杆采用横向龙骨和纵向龙骨组成框架结构。该建筑脚手架及钢构一体式支撑结构中,在结构稳定性与承载能力上,框架式水平杆、方管支撑与木层板组合及水平剪力撑的协同作用,形成稳固的立体受力体系,大幅降低变形量,提升整体稳定系数,能有效应对大跨度主桁架施工中的荷载挑战。
Need to check novelty before this filing date? Find Prior Art

Claims

1. A building scaffold and steel structure integrated support structure comprising a main body frame, characterized in that: The main frame includes several uprights (2) and horizontal bars (1). A main truss (6) is installed on the top of the main frame. A square tube support (10) is installed below the middle of the main truss (6). A wooden shelf (7) is installed between the bottom of the square tube support (10) and the top of the main frame. The upper and lower horizontal bars (1) are supported and fixed by diagonal bars (3). The horizontal bars (1) are framed by transverse keels (11) and longitudinal keels (12).

2. The construction scaffold and steel integrated support structure according to claim 1, wherein: Several horizontal shear braces (4) and horizontal protective nets (5) are installed horizontally from top to bottom on the main frame.

3. The construction scaffold and steel integrated support structure according to claim 1, wherein: The bottom of the pole (2) is fitted with a wooden pad (21).

4. The construction scaffold and steel integrated support structure according to claim 1, wherein: The top side of the main frame is equipped with a high edge guardrail (8).

5. The construction scaffold and steel integrated support structure according to claim 1, wherein: A steel cage ladder (9) is vertically installed on the side of the main frame.

6. The construction scaffold and steel integrated support structure according to claim 1, wherein: A support adjustment component is installed between the bottom of the longitudinal keel (12) and the top of the upright (2).

7. The construction scaffold and steel construction integrated support structure according to claim 6, characterized in that: The support adjustment component includes a sleeve (22), the top of the upright (2) is provided with an insertion port, the bottom of the sleeve (22) is inserted into the top of the upright (2), the sleeve (22) is inserted with a threaded lifting rod (23), the top of the upright (2) is rotatably connected with a turntable (221), the turntable (221) is threadedly connected to the threaded lifting rod (23), the top of the threaded lifting rod (23) is equipped with a support seat (231), the support seat (231) is a U-shaped structure and is engaged with the longitudinal keel (12).