A large top pipe joint prefabricated steel fast positioning binding pedestal for a tunneling engineering

By designing a rapid positioning and binding platform that includes a steel pad box base, support poles, and hole support poles, the problems of low binding efficiency and large spacing deviation of precast steel bars for large jacking pipe sections in underground excavation projects were solved, achieving rapid positioning and precise control, and improving safety and binding quality.

CN224525886UActive Publication Date: 2026-07-21TWENTY METALLURGICAL GRP (SHENZHEN) CONSTR DEV CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
TWENTY METALLURGICAL GRP (SHENZHEN) CONSTR DEV CO LTD
Filing Date
2025-04-11
Publication Date
2026-07-21

AI Technical Summary

Technical Problem

Existing methods for binding precast steel bars in large-scale tunnel jacking sections are inefficient, have large deviations in steel bar spacing, and require multiple people to work together, posing safety hazards.

Method used

Design a rapid positioning and binding platform including a steel pad box base, support poles and hole support poles. The support poles provide vertical support, and the hole support poles provide insertion holes for the insertion connecting rods, so as to realize rapid positioning and precise spacing control of the reinforcing bars.

Benefits of technology

It improves the efficiency of rebar tying and the accuracy of spacing control, reduces the number of workers, enhances safety and tying quality, and meets the requirements of the specifications for joint location preparation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224525886U_ABST
    Figure CN224525886U_ABST
Patent Text Reader

Abstract

The utility model provides a kind of large top pipe pipe joint prefabricated reinforcement fast positioning binding pedestal of subsurface engineering, which comprises a steel pad box base, a plurality of support vertical poles arranged along the circumference of the steel pad box base, and each of the support vertical poles is provided with a plurality of spaced-apart hole support rods along its length direction, and each of the hole support rods is provided with a plug-in hole; a plug-in connecting rod is inserted into the plug-in hole to provide a reinforcement binding support surface. The pedestal provided by the utility model can greatly improve the efficiency of reinforcement binding and the accuracy of reinforcement spacing control. Using the fast positioning binding pedestal, prefabricated positioning reinforcement can be quickly positioned and modularized, the spacing of reinforcement can be accurately determined, the joint position for distributing reinforcement overlap or mechanical connection can be prepared according to the specification, the reinforcement binding and installation speed is accelerated, the number of workers is reduced, and the quality of reinforcement binding is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of underground excavation engineering technology, and more specifically, to a rapid positioning and binding platform for precast steel bars of large jacking pipe sections in underground excavation engineering. Background Technology

[0002] The pipe jacking section has a high reinforcement ratio and large main bars. Using traditional rebar tying techniques, multiple people are needed to tie and fix the main reinforcement skeleton, making construction difficult and making it hard to control the spacing of the rebars, resulting in excessive deviations. In addition, the lack of a support platform makes it easy for the rebar to become unstable during installation, potentially tipping over and injuring the rebar tying workers. Summary of the Invention

[0003] In view of this, this utility model proposes a rapid positioning and binding platform for precast steel bars of large jacking pipe sections in underground excavation projects, aiming to solve the problems of low efficiency and large deviation of steel bar spacing in the traditional steel bar binding method for precast large jacking pipe sections in underground excavation projects.

[0004] This utility model proposes a rapid positioning and binding platform for precast steel bars of large-scale pipe jacking sections in underground excavation projects. The platform includes: a steel pad base; several support columns arranged at intervals along the circumference of the steel pad base, and each support column has several spaced hole support rods along its length, each hole support rod having an insertion hole; and an insertion connecting rod inserted into the insertion hole to provide a support surface for binding the steel bars.

[0005] Furthermore, in the aforementioned rapid positioning and binding platform for precast steel reinforcement of large jacking pipe sections in the underground excavation project, the cross-section of the supporting upright is an I-shaped structure or a C-shaped structure, and the hole support rod is arranged perpendicular to the flange plate of the supporting upright.

[0006] Furthermore, in the aforementioned rapid positioning and binding platform for precast steel bars of large jacking pipe sections in the underground excavation project, the hole support rod is connected to the two flange plates of the support column.

[0007] Furthermore, in the aforementioned rapid positioning and binding platform for precast steel reinforcement of large jacking pipe sections in the underground excavation project, the supporting uprights and the steel pad box base are connected by welding.

[0008] Furthermore, in the aforementioned rapid positioning and binding platform for precast steel bars of large jacking pipe sections in the underground excavation project, the hole support rod and the support column are connected by welding.

[0009] Furthermore, in the aforementioned rapid positioning and binding platform for precast steel reinforcement of large jacking pipe sections in the underground excavation project, the insertion connecting rod is inserted into the insertion hole in a detachable manner.

[0010] Furthermore, in the aforementioned rapid positioning and binding platform for precast steel bars of large jacking pipe sections in the underground excavation project, the inserted connecting rod is a pin or a steel bar structure.

[0011] Furthermore, in the aforementioned rapid positioning and binding platform for precast steel reinforcement of large jacking pipe sections in the underground excavation project, the hole support rod is a tubular structure with a hollow interior serving as an insertion hole for inserting the insertion connecting rod.

[0012] Furthermore, in the aforementioned rapid positioning and binding platform for precast steel reinforcement of large jacking pipe sections in the underground excavation project, the supporting uprights are made of steel.

[0013] Furthermore, in the aforementioned rapid positioning and binding platform for precast reinforcing bars of large jacking pipe sections in the underground excavation project, the hole support rod is made of steel.

[0014] This utility model provides a rapid positioning and binding platform for precast rebar in large-scale tunnel jacking sections. It features a steel base for bottom support and vertical support via support columns. Hole-mounted support rods on these columns allow for the insertion of connecting rods, providing a support surface for rebar binding. This platform significantly improves the efficiency of rebar binding and the accuracy of rebar spacing control, solving the problems of low efficiency and large spacing deviations in traditional rebar binding methods for large-scale tunnel jacking sections. Using this rapid positioning and binding platform allows for quick modular positioning of precast rebar, precise determination of rebar spacing, and preparation of lap or mechanical connection joints according to specifications. This accelerates rebar binding and installation, reduces the number of workers required, improves rebar binding quality, and significantly enhances the safety of rebar binding operations. With few accessories and a simple structure, this rebar binding platform has high practical value. Attached Figure Description

[0015] Various other advantages and benefits will become apparent to those skilled in the art upon reading the following detailed description of preferred embodiments. The accompanying drawings are for illustrative purposes only and are not intended to limit the scope of the invention. Furthermore, the same reference numerals denote the same parts throughout the drawings. In the drawings: Figure 1 A schematic diagram of the structure of the precast steel reinforcement quick positioning and binding platform for large-scale jacking pipe sections in underground excavation projects provided in this embodiment of the present utility model. Detailed Implementation

[0016] Exemplary embodiments of the present disclosure will now be described in more detail with reference to the accompanying drawings. While exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be implemented in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided to enable a more thorough understanding of the present disclosure and to fully convey the scope of the disclosure to those skilled in the art. It should be noted that, unless otherwise specified, embodiments and features of the present invention can be combined with each other. The present invention will now be described in detail with reference to the accompanying drawings and embodiments.

[0017] See Figure 1 This is a schematic diagram of the structure of the rapid positioning and binding platform for precast reinforcing bars of large jacking pipe sections in underground excavation projects, provided by an embodiment of this utility model. As shown in the figure, the rapid positioning and binding platform for precast reinforcing bars of large jacking pipe sections in underground excavation projects includes: a steel base box 1, several supporting uprights 2, hole support rods 3, and insertion connecting rods 4; wherein, Several supporting uprights 2 are arranged at circumferential intervals along the steel pad base 1, and each supporting upright 2 has an additional support along its length direction (e.g., ...). Figure 1 In the vertical direction shown, there are several spaced hole support rods 3, and each hole support rod 3 is provided with a fixing hole; the fixing connecting rod 4 is inserted into the fixing hole to provide a support surface for tying the reinforcing bars.

[0018] Specifically, the steel base 1 can be a square structure with multiple supporting uprights 2 along its outer edge. This embodiment uses eight uprights as an example, meaning each side edge has two spaced-apart supporting uprights 2 to provide a support platform. Each supporting upright 2 is vertically arranged, and its bottom end can be welded and fixed to the top wall of the steel base 1. Alternatively, it can be fixed using other connection methods, which are not limited in this embodiment. Each supporting upright 2 has multiple spaced and evenly arranged hole-position supporting rods 3 along its length (vertical direction). Each hole-position supporting rod 3 is horizontally installed on the supporting upright 2, and the spacing between each hole-position supporting rod 3 is the same and can be determined based on the rebar fixing spacing. The hole-position supporting rods 3 can be welded and fixed to the supporting upright 2. Furthermore, each hole-position supporting rod 3 has an insertion hole, into which a connecting rod 4 is inserted to provide a support surface for rebar binding. In this embodiment, the insertion connecting rod 4 is inserted into the insertion hole in a detachable manner, and the insertion position and insertion spacing of the insertion connecting rod 4 can be flexibly adjusted.

[0019] In this embodiment, the cross-section of the support rod 2 is an I-shaped or C-shaped structure, and the hole-position support rod 3 is arranged perpendicular to the flange plate of the support rod 2. The support rod 2 can be made of steel, i.e., an I-beam steel rod. The hole-position support rod 3 is connected to the two flange plates of the support rod 2 and can be fixed by welding, facilitating connection and fixation.

[0020] In this embodiment, the hole support rod 3 is a tubular structure with a hollow interior serving as an insertion hole for inserting the insertion connecting rod. Specifically, the hole support rod 3 can be made of steel, i.e., a steel pipe structure, providing the insertion position for the insertion connecting rod 4.

[0021] In this embodiment, the insertion connecting rod 4 can be a pin or a steel bar structure, or other structures, and no limitation is made in this embodiment.

[0022] In this embodiment, the steel pad base 1 serves as a platform. During manufacturing, the steel pad base 1 is welded and fixed to the support column 2. Then, the hole support rod 3 is welded and fixed to the support column 2 according to the designed rebar spacing. The insertion connecting rod 4 is a movable part that can be flexibly inserted into the insertion hole position as needed, providing a support surface for rebar binding. After the steel pad base 1 is arranged, the rebar binding can begin. The rebar can be placed directly on the platform with manual assistance, and binding and connection can be performed on the insertion connecting rod 4.

[0023] In summary, the rapid positioning and binding platform for precast rebar in large-scale tunnel jacking sections provided in this embodiment uses a steel base 1 for bottom support and support rods 2 for vertical support. The connecting rods 4 can be inserted into the support rods 3 via holes on the support rods 2, providing a support surface for rebar binding. This platform significantly improves the efficiency of rebar binding and the accuracy of rebar spacing control, solving the problems of low efficiency and large rebar spacing deviation in traditional rebar binding methods for large-scale tunnel jacking sections. Using this rapid positioning and binding platform allows for quick modular positioning of precast rebar, precise determination of rebar spacing, and preparation of rebar lap or mechanical connection joint positions according to specifications. This accelerates rebar binding and installation, reduces the number of workers, improves rebar binding quality, and significantly enhances the safety of rebar binding operations. This rebar binding platform has few accessories, a simple structure, and high practical value.

[0024] It should be noted that in the description of this utility model, the terms "upper", "lower", "left", "right", "inner", "outer", etc., indicating the direction or positional relationship are based on the direction or positional relationship shown in the drawings. This is only for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, it should not be construed as a limitation of this utility model.

[0025] Furthermore, it should be noted that, in the description of this utility model, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "joining" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model according to the specific circumstances.

[0026] Obviously, those skilled in the art can make various modifications and variations to this utility model without departing from its spirit and scope. Therefore, if these modifications and variations fall within the scope of the claims of this utility model and their equivalents, this utility model also intends to include these modifications and variations.

Claims

1. A rapid positioning and binding platform for precast reinforcing bars of large pipe jacking sections in underground excavation projects, characterized in that, include: Steel base plate; Several support poles are arranged at intervals along the circumference of the steel pad box base, and each support pole is provided with several spaced hole support rods along its length, and each hole support rod is provided with a fixing hole. The insertion connecting rod is inserted into the insertion hole to provide a support surface for tying the reinforcing bars.

2. The rapid positioning and binding platform for precast steel bars of large-scale pipe jacking sections in underground excavation projects according to claim 1, characterized in that, The cross-section of the support column is an I-shaped structure or a C-shaped structure, and the hole support rod is arranged perpendicular to the flange plate of the support column.

3. The rapid positioning and binding platform for precast steel bars of large-scale pipe jacking sections in underground excavation projects according to claim 2, characterized in that, The hole support rod is connected to the two flange plates of the support column.

4. The rapid positioning and binding platform for precast reinforcing bars of large-scale pipe jacking sections in underground excavation projects according to any one of claims 1 to 3, characterized in that, The supporting upright is connected to the steel pad box base by welding.

5. The rapid positioning and binding platform for precast reinforcing bars of large-scale pipe jacking sections in underground excavation projects according to any one of claims 1 to 3, characterized in that, The hole support rod and the support column are connected by welding.

6. The rapid positioning and binding platform for precast reinforcing bars of large-scale pipe jacking sections in underground excavation projects according to any one of claims 1 to 3, characterized in that, The insertion connecting rod is inserted into the insertion hole in a detachable manner.

7. The rapid positioning and binding platform for precast steel bars of large-scale pipe jacking sections in underground excavation projects according to claim 3, characterized in that, The insertion connecting rod is a pin or a steel bar structure.

8. The rapid positioning and binding platform for precast reinforcing bars of large-scale pipe jacking sections in underground excavation projects according to any one of claims 1 to 3, characterized in that, The hole support rod is a tubular structure with a hollow interior serving as a insertion hole for inserting the insertion connecting rod.

9. The rapid positioning and binding platform for precast reinforcing bars of large-scale pipe jacking sections in underground excavation projects according to any one of claims 1 to 3, characterized in that, The supporting pole is made of steel.

10. The rapid positioning and binding platform for precast reinforcing bars of large-scale pipe jacking sections in underground excavation projects according to any one of claims 1 to 3, characterized in that, The hole support rod is made of steel.