A water discharge device for an external sampling pipe of a coke oven gas pipeline

By designing a water discharge device for the external sampling pipe of coke oven gas pipeline, the automatic discharge of condensate is achieved by using a water seal cylinder and a water discharge pipe. This solves the problem of condensate affecting the operating environment and posing safety hazards during coke oven gas sampling, and realizes a safe and efficient sampling process.

CN224581216UActive Publication Date: 2026-07-31HANDAN IRON & STEEL GROUP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
HANDAN IRON & STEEL GROUP CO LTD
Filing Date
2025-06-09
Publication Date
2026-07-31

AI Technical Summary

Technical Problem

When sampling coke oven gas, if the amount of condensate is large, it is necessary to vent for a long time, which may cause gas to be ejected, affecting the operating environment and posing a safety hazard.

Method used

Design a water discharge device for an external sampling pipe of a coke oven gas pipeline, comprising a steam evacuation pipe, a water seal cylinder, a water seal pipe, a steam inlet pipe, a base, an insulation cylinder, a water supply pipe, a water discharge pipe, a liquid drain pipe, a sampling pipe, a sampling pipe drain valve, and a gas pipeline. The automatic discharge of condensate is achieved through the water discharge pipe and the water seal pipe inside the water seal cylinder.

Benefits of technology

It enables real-time drainage of condensate, eliminates safety and environmental hazards, shortens sampling time, and features a simple structure that is easy to install and maintain.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224581216U_ABST
    Figure CN224581216U_ABST
Patent Text Reader

Abstract

This utility model relates to a water discharge device for an external sampling pipe of a coke oven gas pipeline, belonging to the technical field of gas water seal equipment in the metallurgical industry. The technical solution is as follows: the insulation cylinder (7) is fixed on the base (6), the water seal cylinder (2) is fixed in a ring around the insulation cylinder (7), the steam exhaust pipe (1) and the steam inlet pipe (4) are respectively connected to the insulation cylinder (7), the water seal pipe (3), the water supply pipe (8) and the drain pipe (12) are respectively connected to the water seal cylinder (2), one end of the water discharge pipe (11) is connected to the water seal cylinder (2), and the other end of the water discharge pipe (11) is connected to the sampling pipe drain valve (14) through the water discharge valve (10). The sampling pipe drain valve (14) is connected to the sampling pipe (13), and the sampling pipe (13) is connected to the gas pipeline (16). The beneficial effect of this utility model is that it can realize the automatic real-time discharge of condensate in the gas sampling pipe, avoid manual drainage operation, and eliminate safety hazards.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to a water discharge device for an external sampling pipe of a coke oven gas pipeline, belonging to the technical field of gas water seal equipment in the metallurgical industry. Background Technology

[0002] During the coke oven gas purification process, it is necessary to sample and test the gas periodically. The common method is to extend a sampling pipe from above the gas pipeline to a lower location or operating platform for convenient sampling. A sampling valve is installed at the bottom of the sampling pipe. When sampling is required, the sampling valve is first opened to release the condensate in the sampling pipe, and then the sampling hose is connected for sampling. When the amount of condensate in the sampling pipe is large, the venting time is long, and gas may spray out with the condensate, affecting the operating environment and posing a safety hazard. Utility Model Content

[0003] The purpose of this invention is to provide a water discharge device for an external sampling pipe of a coke oven gas pipeline, which can automatically and in real time discharge condensate from the gas sampling pipe, avoiding manual drainage operations, eliminating safety hazards, and solving the problems existing in the background technology.

[0004] The technical solution of this utility model is:

[0005] A water discharge device for an external sampling pipe of a coke oven gas pipeline includes a steam evacuation pipe, a water seal cylinder, a water seal pipe, a steam inlet pipe, a base, a heat insulation cylinder, a water supply pipe, a water discharge valve, a water discharge pipe, a drain pipe, a sampling pipe, a sampling pipe drain valve, and a gas pipeline. The heat insulation cylinder is fixed on the base, and the water seal cylinder is fixed in a ring around the heat insulation cylinder. The steam evacuation pipe and the steam inlet pipe are respectively connected to the heat insulation cylinder. The water seal pipe, the water supply pipe, and the drain pipe are respectively connected to the water seal cylinder. One end of the water discharge pipe is connected to the water seal cylinder, and the other end of the water discharge pipe is connected to the sampling pipe drain valve through the water discharge valve. The sampling pipe drain valve is connected to the sampling pipe, and the sampling pipe is connected to the gas pipeline.

[0006] The steam inlet pipe is connected to the top of the insulation cylinder, and the steam outlet pipe is connected to the bottom of the insulation cylinder.

[0007] A water supply valve is installed on the water supply pipe.

[0008] Both the drain pipe and the water seal pipe are inserted into the water seal cylinder and are a certain distance from the bottom of the water seal cylinder.

[0009] The water seal cylinder is provided with a vent at the bottom.

[0010] Both the water seal cylinder and the insulation cylinder have an insulation layer on their outer walls.

[0011] A sampling valve is installed on the sampling tube.

[0012] The beneficial effects of this invention are as follows: During operation, the condensate in the gas sampling tube is directly discharged through the drain pipe and water seal pipe inside the water seal cylinder, achieving a water seal effect. The real-time discharge of condensate from the sampling tube reduces the need to drain condensate before sampling, eliminates the safety and environmental hazards of gas leaking out with the condensate, and shortens the sampling time. The structure is simple, easy to manufacture, and convenient to install and maintain. Attached Figure Description

[0013] Figure 1 This is a schematic diagram of the pipe connection of this utility model;

[0014] Figure 2 This is the front view of the present utility model;

[0015] Figure 3 This is a top view of the present invention;

[0016] Figure 4 for Figure 2 Schematic diagram of water seal cylinder and pipe arrangement;

[0017] In the diagram: 1. Steam exhaust pipe; 2. Water seal cylinder; 3. Water seal pipe; 4. Steam inlet pipe; 5. Vent port; 6. Base; 7. Insulation cylinder; 8. Water supply pipe; 9. Water supply valve; 10. Water drain valve; 11. Water drain pipe; 12. Drain pipe; 13. Sampling pipe; 14. Sampling pipe drain valve; 15. Sampling valve; 16. Gas pipeline; 17. Insulation layer. Detailed Implementation

[0018] The present invention will be further described below with reference to the accompanying drawings and examples.

[0019] See attached document Figure 1-4 A water discharge device for an external sampling pipe of a coke oven gas pipeline includes a steam evacuation pipe 1, a water seal cylinder 2, a water seal pipe 3, a steam inlet pipe 4, a base 6, a heat insulation cylinder 7, a water supply pipe 8, a water discharge valve 10, a water discharge pipe 11, a drain pipe 12, a sampling pipe 13, a sampling pipe drain valve 14, and a gas pipeline 16. The heat insulation cylinder 7 is fixed on the base 6, and the water seal cylinder 2 is annularly fixed around the heat insulation cylinder 7. The steam evacuation pipe 1 and the steam inlet pipe 4 are respectively connected to the heat insulation cylinder 7. The water seal pipe 3, the water supply pipe 8, and the drain pipe 12 are respectively connected to the water seal cylinder 2. One end of the water discharge pipe 11 is connected to the water seal cylinder 2, and the other end of the water discharge pipe 11 is connected to the sampling pipe drain valve 14 through the water discharge valve 10. The sampling pipe drain valve 14 is connected to the sampling pipe 13, and the sampling pipe 13 is connected to the gas pipeline 16.

[0020] In this embodiment, Figure 1 As shown, after installation, the drain pipe 11 is connected to the sampling pipe drain valve 14 via the drain valve 10, the sampling drain valve 14 is connected to the sampling pipe 13, the sampling pipe 13 is connected to the gas pipeline 16, and a sampling valve 15 is installed on the sampling pipe 13, above the sampling pipe drain valve 14, to facilitate gas sampling.

[0021] Figure 1 The display shows that the steam inlet pipe 4 enters from the top of the device, the steam outlet pipe 1 is at the bottom, the steam outlet is discharged from the bottom, the condensate water is replenished through the water replenishment valve 8 and the water replenishment pipe 9, and the condensate water is discharged through the drain pipe 12.

[0022] Figure 1 As shown, after installation, the outer wall of this new type is provided with a heat insulation layer 17.

[0023] Figure 2 The display shows that the insulation cylinder 7 is welded to the base 6, and the water seal cylinder 2 is welded in a ring around the insulation cylinder 7. The top end face of the insulation cylinder 7 and the water seal cylinder 2 are flush, and the insulation cylinder 7 is slightly longer than the water seal cylinder 2.

[0024] Figure 2 The diagram shows that the steam exhaust pipe 1 and the steam inlet pipe 4 are welded to the insulation cylinder 7, and the water seal pipe 3, the water supply pipe 8, the water discharge pipe 11, and the liquid drain pipe 12 are welded to the water seal cylinder 2.

[0025] Figure 3 The display shows that the drain pipe 11 and the water seal pipe 3 are both inserted into the water seal cylinder 2, and are a certain distance from the bottom of the water seal cylinder 2. The drain pipe 12 is welded to the upper part of the water seal cylinder 2 and extends into the cylinder body.

[0026] The usage process of this utility model is as follows:

[0027] First, seal the vent 5 to ensure it is tight and leak-free. Then, fill the water seal cylinder 2 with water through the water supply pipe 8 and water supply valve 9 until the drain pipe 12 is full. Finally, close the water supply valve 9.

[0028] The condensate generated by the drain pipe 12 and the steam return pipe 1 is led to the condensate recovery device in the production area. The drain valve 10 is connected to the sampling drain valve 14. The new device is connected to the gas pipeline 16 through the sampling pipe 13.

[0029] During sampling, simply open sampling valve 15 to introduce gas into the sampling device, thus achieving sampling without releasing condensate.

[0030] When inspecting or shutting down, simply close the sampling drain valve 14. If necessary, disconnect the pipe between the sampling drain valve 14 and the drain valve 10. Remove the sealing cap of the vent 5 at the bottom of the water seal cylinder 2, and introduce cleaning water through the water supply pipe 8 to perform cleaning and maintenance work on this new device. Alternatively, disconnect the exhaust pipe 1 and the drain pipe 12 from the outside to perform off-line maintenance or replacement of this device.

Claims

1. A water draining device for a coke oven gas pipeline external sampling pipe, characterized in that: The system includes a steam evacuation pipe (1), a water seal cylinder (2), a water seal pipe (3), a steam inlet pipe (4), a base (6), an insulation cylinder (7), a water supply pipe (8), a water drain valve (10), a water drain pipe (11), a drain pipe (12), a sampling pipe (13), a sampling pipe drain valve (14), and a gas pipeline (16). The insulation cylinder (7) is fixed on the base (6), and the water seal cylinder (2) is fixed in a ring around the insulation cylinder (7). The steam evacuation pipe (1) and The steam inlet pipe (4) is connected to the insulation cylinder (7), the water seal pipe (3), the water supply pipe (8) and the drain pipe (12) are connected to the water seal cylinder (2), one end of the drain pipe (11) is connected to the water seal cylinder (2), and the other end of the drain pipe (11) is connected to the sampling pipe drain valve (14) through the drain valve (10). The sampling pipe drain valve (14) is connected to the sampling pipe (13), and the sampling pipe (13) is connected to the gas pipeline (16).

2. A water draining device for a coke oven gas pipe external sampling tube according to claim 1, characterized in that: The steam inlet pipe (4) is connected to the top of the insulation cylinder (7), and the steam outlet pipe (1) is connected to the bottom of the insulation cylinder (7).

3. A water draining device for a coke oven gas pipe external sampling tube according to claim 1, characterized in that: A water supply valve (9) is installed on the water supply pipe (8).

4. A water draining device for a coke oven gas pipe external sampling tube according to claim 1, characterized in that: The drain pipe (11) and the water seal pipe (3) are both inserted into the water seal cylinder (2) and are a certain distance from the bottom of the water seal cylinder (2).

5. A water draining device for a coke oven gas pipe external sampling tube according to claim 1, characterized in that: The water seal cylinder (2) is provided with a vent (5) at the bottom.

6. A water draining device for a coke oven gas pipe external sampling tube according to claim 1, characterized in that: Both the water seal cylinder (2) and the heat insulation cylinder (7) have a heat insulation layer (17) on their outer walls.

7. A water draining device for a coke oven gas pipe external sampling tube according to claim 1, characterized in that: A sampling valve (15) is installed on the sampling tube (13).