A tunnel reinforcing steel corrugated plate transportation and installation trolley

CN224664626UActive Publication Date: 2026-08-21CHENGDU RUIHE MACHINERY MFG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202521563872.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-07-25
Publication Date
2026-08-21
Estimated Expiration
2035-07-25

AI Technical Summary

Technical Problem

[0005]鉴于传统安装方式难以满足隧道交叉口区域钢波纹板加固施工的实际需求

Benefits of technology

[0061]运输台车和安装台车下方均设计为可通过降速行驶的社会车辆,在隧道钢波纹板加固施工过程中无需中断交通,有效保障了隧道内正常的交通流量,减少了因施工对交通造成的影响,降低了对周边交通环境和经济活动的干扰。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224664626U_ABST
    Figure CN224664626U_ABST
Patent Text Reader

Abstract

The utility model belongs to the field of trolley, especially a kind of steel corrugated plate transport and installation trolley for tunnel reinforcement, the existing trolley is increased ventilation inclined shaft in tunnel middle position, the mouth is increased in the side of original old tunnel, original concrete bearing structure needs to be destroyed, old concrete structure needs to be reinforced.Using steel corrugated plate, stick in tunnel inside problem, present and propose the following scheme, including transport trolley main body and installation trolley main body;The transport trolley main body includes transport trolley portal upright column, transport trolley lower longitudinal beam, transport trolley rubber-tired travelling device, transport trolley longitudinal movement trolley, transport trolley vertical oil cylinder and transport trolley translation device, in the utility model, transport trolley is designed with walkway protection device and anti-falling device, to provide safety guarantee for construction personnel and equipment, reduce the security risk in the process of transportation, installation trolley portal four corners are equipped with lifting and translation device, the upper portion of portal is designed with small car track, the position of steel corrugated plate can be accurately adjusted.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of trolley technology, and in particular to a trolley for transporting and installing corrugated steel plates for tunnel reinforcement. Background Technology

[0002] Older highways didn't have ventilation shafts. Now, for tunnels, adding ventilation shafts in the middle and openings on the sides of the existing tunnels requires damaging the original concrete load-bearing structure, necessitating reinforcement. Here, corrugated steel sheets are used, attached to the inside of the tunnel, and then grout is injected.

[0003] Through comparison and optimization of various construction schemes, the steel corrugated plate reinforcement technology for tunnel intersection areas was developed.

[0004] Whether using traditional manual scaffolding or modified arch frame installation vehicles, construction must be carried out while traffic is interrupted.

[0005] Given that traditional installation methods cannot meet the actual needs of steel corrugated plate reinforcement construction in tunnel intersection areas.

[0006] However, using a shield trolley as a protective and construction platform, with manual installation of corrugated steel sheets, resulted in a narrowest point where the shield trolley and the tunnel secondary lining were only about 30 centimeters apart, making it impossible for personnel to operate. Through repeated demonstrations and discussions, the corrugated steel sheet construction equipment was efficiently integrated with the shield trolley.

[0007] This allows for the installation of corrugated steel sheets using a shield trolley under continuous traffic conditions. Utility Model Content

[0008] The purpose of this invention is to address the shortcomings of existing technologies where adding ventilation shafts in the middle of tunnels and openings on the sides of existing tunnels requires damaging the original concrete load-bearing structure and necessitates reinforcement. This invention utilizes corrugated steel sheets, which are attached to the inner side of the tunnel and then grouted. Through comparison and optimization of various construction schemes, the corrugated steel sheet reinforcement process at tunnel intersections, whether using traditional manual scaffolding or modified arch frame installation vehicles, suffers from the drawback of requiring construction to be carried out during traffic disruptions. Therefore, this invention proposes a corrugated steel sheet transportation and installation trolley for tunnel reinforcement.

[0009] To achieve the above objectives, the present invention adopts the following technical solution:

[0010] A steel corrugated plate transport and installation trolley for tunnel reinforcement includes a transport trolley body and an installation trolley body;

[0011] The main body of the transport trolley includes a transport trolley gantry column, a transport trolley lower longitudinal beam, a transport trolley rubber-tired traveling device, a transport trolley longitudinal trolley, a transport trolley vertical hydraulic cylinder, and a transport trolley translation device.

[0012] The main body of the installation trolley includes an installation trolley gantry column, an installation trolley lower longitudinal beam, an installation trolley traveling device, an installation trolley vertical hydraulic cylinder, an installation trolley translation device, and an installation trolley longitudinal trolley.

[0013] The transport trolley rubber-wheel walking device and the installation trolley walking device both use solid rubber wheels and are equipped with motor reducers for driving the trolley to move; the transport trolley vertical cylinder and the installation trolley vertical cylinder are used to realize the overall lifting and lowering of the trolley; the transport trolley translation device and the installation trolley translation device are used to realize the translation of the trolley.

[0014] The trolley is designed to allow social vehicles to travel at reduced speeds, so that traffic can be maintained without interruption during the tunnel steel corrugated plate reinforcement construction, effectively ensuring normal traffic flow.

[0015] In one possible design, the main body of the transport trolley also includes an upper crossbeam, a crossbeam-covered platform, and a longitudinal connecting beam for the longitudinal trolley.

[0016] The upper crossbeam is fixedly installed on the top of the transport trolley gantry column, the crossbeam full-coverage platform is fixedly installed between the two upper crossbeams, the longitudinal connecting beam of the longitudinal trolley is arranged between the upper crossbeams, and the longitudinal trolley of the transport trolley is fixedly installed on the top of the upper crossbeam.

[0017] In one possible design, the main body of the installation trolley also includes a gantry beam, an upper translation trolley, and an upper lifting cylinder;

[0018] The gantry beam is fixedly installed on the top of the gantry column of the installation trolley. The upper translation trolley is slidably connected to the top of the gantry beam. The upper lifting cylinder is fixedly installed on the top of the upper translation trolley. An arc-shaped beam is fixedly installed on the top of the piston rod of the upper lifting cylinder. A ladder is fixedly installed on the side of the gantry column of the installation trolley. A second lateral working platform is fixedly installed on one side of the gantry column of the installation trolley. A corrugated plate pushing cylinder is fixedly installed on the side of the second lateral working platform through a connecting assembly. One end of the two corrugated plate pushing cylinders is fixedly connected to both ends of the arc-shaped beam. Multiple longitudinally connected crossbeams are fixedly installed on the top of the main body of the transport trolley. An upper translation device is fixedly installed on the top of the gantry beam.

[0019] In one possible design, a connecting component is also included, which includes a side wheel and a limiting groove;

[0020] The side guard wheel is slidably connected to the side of the side arch corrugated steel plate, and the side of the side arch corrugated steel plate is fixedly equipped with a traveling wheel, which is embedded in the limiting groove for guidance.

[0021] In one possible design, the main body of the transport trolley also includes a generator set and an eight-unit solenoid valve hydraulic station;

[0022] The generator set is fixedly installed inside the main body of the transport trolley and is used to power the traveling device; the eight-cell solenoid valve hydraulic station is fixedly installed inside the main body of the transport trolley and is used to control the hydraulic system.

[0023] In one possible design, the vertical cylinder of the installation trolley has a design stroke of 400mm, a working stroke of 150mm, and a reserved lifting stroke of 250mm.

[0024] The maximum stroke of the installation trolley translation device is 100mm, and the stroke can be adjusted by 50mm to the left and right of the center of the tunnel. A gantry longitudinal joint is fixedly installed on the top of the installation trolley body. Multiple gantry longitudinal trusses are fixedly installed inside the installation trolley body. A fourteen-unit solenoid valve hydraulic station is fixedly installed inside the installation trolley body.

[0025] In one possible design, both the transport trolley body and the installation trolley body include guardrails and walkway protection devices. Multiple single-layer tilting platforms are fixedly installed on the outer wall of the installation trolley body. Top-level platform ladders are provided on both sides of the transport trolley gantry column. First lateral working platforms are installed on both sides of the transport trolley gantry column. Lateral platform ladders are fixedly installed on the sides of the first lateral working platforms. Multiple longitudinal truss bodies are provided inside the transport trolley body.

[0026] The guardrails are fixedly installed on both sides of the top of the corrugated steel plate of the arch, and the walkway protection device is fixedly installed on the side working platform to prevent construction workers from falling.

[0027] In one possible design, an installation trolley clearance clearance is provided between the installation trolley body and the tunnel, and a transport trolley clearance clearance is provided between the transport trolley body and the tunnel interior.

[0028] One possible design also includes a multi-functional hoist, a small down-the-hole drill, and the ZDY650 fully hydraulic tunnel drilling rig for coal mines;

[0029] The multi-functional hoist is fixedly installed on the top side of the transport trolley body and the installation trolley body for vertical hoisting of the corrugated steel plate; the small down-the-hole drill and the ZDY650 coal mine full hydraulic tunnel drill are fixedly installed on the installation trolley body for completing the anchor bolt locking and grouting operations.

[0030] In this application, I. Before the trolley travel reducer is put into operation, 220-320 medium-load gear oil must be added (for cycloidal pinwheel reducers, add machine oil).

[0031] II. Before the hydraulic system is put into operation, 46# anti-wear hydraulic oil must be added. When the trolley hydraulic system is put into operation for the first time, the air in the hydraulic system pipeline and cylinder needs to be purged so that the hydraulic oil fills the hydraulic system pipeline and cylinder. Hydraulic oil needs to be added in multiple times to ensure that the hydraulic oil level in the pump station is not lower than its specified level.

[0032] III. When positioning the trolley, the center of the top formwork must be aligned with the center line of the tunnel before the side formwork is supported in place. The center distance of the track must meet the design requirements, and the error must not exceed 10mm; the error between the center of the track and the center of the tunnel must not exceed 20mm.

[0033] IV. After the template is assembled, it should be leveled and aligned, and the gap should not be greater than 1.5mm. The operating window should open flexibly, and the gap between it and the template should not be greater than 1.5mm. There should be no misalignment, and the bolt connections should not be loose.

[0034] V. There must be no leakage at any pipe joint in the hydraulic system, and the test pressure should be set according to the hydraulic system requirements.

[0035] VI. After the machine is fully installed, it should be tested on site to ensure that each walking system runs smoothly and each jack operates safely and flexibly without any sluggishness (the hydraulic system pressure has been adjusted before leaving the factory and should not be adjusted arbitrarily on site).

[0036] 1. Install the lightweight down-the-hole drilling rig and grouting machinery mounted on the trolley to complete the anchor bolt locking and grouting operations, ensuring that the construction of the corrugated steel plate at the tunnel intersection can be carried out while maintaining normal traffic flow.

[0037] 2. To facilitate the adjustment of the trolley to adapt to changes in cross slope and superelevation and to ensure the stability of the trolley, the vertical lifting mechanism of the trolley is located at the lower part of the trolley gantry, and the trolley is lifted as a whole.

[0038] 3. The vertical hydraulic cylinder is designed with a stroke of 400mm, a working stroke of 150mm, and a reserved lifting stroke of 250mm.

[0039] 4. The maximum stroke of the trolley translation cylinder is 100mm, and the stroke can be adjusted by 50mm to the left and right of the center of the tunnel.

[0040] 5. The track gauge of the trolley is 7200mm, and the clearance height of the trolley is 5000mm.

[0041] 6. The trolley travel speed is 9m / min, the trolley travel motor power is 4kW*2, and the rated pressure of the trolley hydraulic system is 16MPa.

[0042] 7. The walking mechanism has solid rubber wheels, two active walking mechanisms driven by motors and reducers, and powered by an onboard generator. The steering mechanism has a built-in translation function. The column surface has reflective stickers and warning lights, and the top has height limit signs and warning lights. The clearance for the shield trolley to pass through is 4.5m*5m; the trolley is equipped with lifting cylinders and translation cylinders.

[0043] Construction process of corrugated steel plate integral reinforcement

[0044] Through comparison and optimization of various construction schemes, it was found that the corrugated steel sheet reinforcement process in tunnel intersection areas, whether using traditional manual scaffolding or modified arch frame installation vehicles, requires construction to be carried out under traffic interruption conditions. Given that traditional installation methods cannot meet the actual needs of corrugated steel sheet reinforcement construction in tunnel intersection areas, and that using shield trolleys as a protective and construction platform for manual installation of corrugated steel sheets presents challenges, the narrowest point between the shield trolley and the tunnel secondary lining is only about 30 centimeters, making manual operation impossible. Through repeated demonstrations and discussions, and by efficiently integrating corrugated steel sheet construction equipment with shield trolleys, it was achieved that corrugated steel sheet installation can be carried out using shield trolleys under continuous traffic conditions.

[0045] The overall reinforcement of the corrugated steel sheet is carried out through three main stages: 1. Assembly of the corrugated steel sheet outside the tunnel; 2. Overall transportation of the corrugated steel sheet inside the tunnel; 3. Installation of the corrugated steel sheet. Utilizing a lightweight down-the-hole drill rig and grouting machinery mounted on an installation trolley, the anchor bolts and grouting operations are completed, ensuring that the construction of the corrugated steel sheet at the tunnel intersection can proceed while maintaining normal traffic flow.

[0046] 1. Transport trolley

[0047] 1. Design a solid rubber tire and install a motor reducer drive device.

[0048] 2. Lifting and translation devices are installed at the four corners of the gantry.

[0049] 3. A small trolley is designed above the gantry. The trolley can travel along the connecting tracks to the installation trolley to transport the corrugated steel sheet to the installation trolley.

[0050] 4. The transport trolley is equipped with a generator set and travels between the tunnel entrance and the middle of the tunnel. Its function is to transport the corrugated steel sheets from outside the tunnel into the installation position inside the tunnel.

[0051] 5. The transport trolley allows slow-moving vehicles to pass underneath without disrupting traffic. The transport trolley is equipped with walkway protection and anti-fall devices to ensure safe passage for vehicles.

[0052] II. Installation trolley

[0053] 1. Design a solid rubber tire and install a motor reducer drive device.

[0054] 2. Lifting and translation devices are installed at the four corners of the gantry.

[0055] 3. A trolley track is designed above the gantry, which can transport the corrugated steel sheet from the transport trolley to the installation trolley via the track.

[0056] 4. The installation trolley is equipped with a corrugated steel plate extension device and a translation device for adjusting the position of the corrugated steel plate.

[0057] 5. The trolley allows slow-moving vehicles to pass underneath without disrupting traffic. The trolley is equipped with walkway safety devices and anti-fall devices to ensure safe passage for vehicles.

[0058] 6. The side walkways on both sides of the installation trolley are designed with hydraulic cylinder pushing devices to push the corrugated steel plate to the designed installation position.

[0059] The walking device includes: 4 solid tires and 2 sets of motor reducers K97-142-4kW-4.

[0060] Beneficial effects:

[0061] Both the transport trolley and the installation trolley are designed to be accessible to other vehicles traveling at reduced speeds. This ensures that traffic can be maintained during the tunnel steel corrugated plate reinforcement construction without interrupting traffic, effectively guaranteeing normal traffic flow within the tunnel, reducing the impact of construction on traffic, and minimizing interference with the surrounding traffic environment and economic activities.

[0062] The transport trolley is designed with walkway protection devices and fall protection devices, providing safety for construction personnel and equipment and reducing safety risks during transportation. At the same time, the transport trolley is equipped with a generator set, which can independently supply power to ensure stable operation inside the tunnel, accurately transporting the corrugated steel sheets from outside the tunnel to the installation location inside.

[0063] The installation trolley gantry is equipped with lifting and translating devices at its four corners, and a trolley track is designed above the gantry for precise adjustment of the corrugated steel sheet position. The side walkways on both sides of the installation trolley are designed with hydraulic cylinder pushing devices, which can accurately push the corrugated steel sheet to the designed installation position, ensuring the accuracy and quality of installation.

[0064] This utility model efficiently integrates corrugated steel sheet construction equipment with a shield trolley, using the shield trolley as a protective and construction platform for corrugated steel sheet installation. This overcomes the limitations of traditional installation methods in tunnel intersection areas, improves construction efficiency, and ensures the safety of construction personnel.

[0065] The vertical lifting mechanism of the trolley is located at the lower part of the trolley gantry, which allows the trolley to be raised and lowered as a whole. This facilitates the adjustment of the trolley to adapt to changes in cross slope and superelevation, ensuring the stability of the trolley under different geological conditions and tunnel slopes, and expanding the scope of application of the equipment.

[0066] The trolley's translation cylinder has a maximum stroke of 100mm and an adjustable stroke of 50mm to the left and right of the tunnel center, which can flexibly adjust the trolley position according to actual construction needs, improving the flexibility and adaptability of construction.

[0067] The installation trolley is equipped with a lightweight down-the-hole drill and grouting machinery, which can complete the anchor bolt locking and grouting operations. It realizes the integration of corrugated steel plate installation and related auxiliary operations, reduces the number of construction equipment and construction procedures, improves construction efficiency, and reduces construction costs.

[0068] Both the transport trolley and the installation trolley are equipped with complete hydraulic systems. There must be no leakage at any pipe joints in the hydraulic systems. The commissioning pressure is as required, and the rated pressure of the hydraulic systems is clearly defined, ensuring stable operation and reliable operation of the equipment. Furthermore, there are clear requirements for adding hydraulic oil before operation, ensuring the normal functioning of the hydraulic systems. Attached Figure Description

[0069] Figure 1 This is a schematic diagram of the main structure of a steel corrugated plate transportation and installation trolley for tunnel reinforcement proposed in this utility model;

[0070] Figure 2 This is a schematic diagram of the main structure of the transport trolley in the tunnel reinforcement steel corrugated plate transport and installation trolley proposed in this utility model;

[0071] Figure 3 This is a schematic diagram of the main structure of the transport trolley in the tunnel reinforcement steel corrugated plate transport and installation trolley proposed in this utility model;

[0072] Figure 4 This is a side view of the installation trolley in the transportation and installation trolley for steel corrugated plates used in tunnel reinforcement proposed in this utility model.

[0073] Figure 5 This is a schematic diagram of the main structure of the installation trolley in the transportation and installation trolley for steel corrugated plates used in tunnel reinforcement proposed in this utility model.

[0074] Figure 6 This is an enlarged view of part A of the steel corrugated plate transportation and installation trolley for tunnel reinforcement proposed in this utility model.

[0075] In the diagram: 1. Guardrail; 2. Upper crossbeam; 3. Top platform ladder; 4. Transport trolley gantry column; 5. First lateral working platform; 6. Lateral platform ladder; 7. Lower longitudinal beam of the transport trolley; 8. Transport trolley rubber-tired walking device; 9. Crossbeam-covered platform; 10. Transport trolley longitudinal trolley; 11. Top arch corrugated steel plate; 12. Transport trolley clearance clearance; 13. Side arch corrugated steel plate; 14. Longitudinal connecting beam of the longitudinal trolley; 15. Longitudinal crossbeam; 16. Longitudinal truss main body; 17. Generator set; 18. Eight-unit solenoid valve hydraulic station; 19. Transport trolley vertical cylinder; 20. Transport trolley translation device; 21. Arc beam; 22. Upper translation device; 23. Upper lifting cylinder; 24. Upper translation trolley; 25. 1. Install the longitudinal trolley; 26. Gantry crossbeam; 27. Install the gantry column; 28. Ladder; 29. ​​Second lateral working platform; 30. Side corrugated plate push cylinder; 31. Install trolley clearance clearance; 32. Install trolley lower longitudinal beam; 33. Install trolley traveling device; 34. Gantry longitudinal linkage; 35. Gantry longitudinal truss; 36. Fourteen-unit solenoid valve hydraulic station; 37. Install trolley vertical cylinder; 38. Install trolley translation device; 39. First-floor tilting platform; 40. Small down-the-hole drill; 41. Multi-functional hoist; 42. ZDY650 coal mine fully hydraulic tunnel drilling rig; 43. Side retaining wheel; 44. Limiting groove; 45. Traveling wheel; 46. Transport trolley body; 47. Install trolley body. Detailed Implementation

[0076] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present utility model. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments.

[0077] In one embodiment: Refer to Figure 1-6 The specific implementation method of the trolley is as follows:

[0078] The trolley consists of a transport trolley body 46 and an installation trolley body 47, which are fixedly connected as one unit. The lower longitudinal beams 7 of the transport trolley are symmetrically fixed to both sides of the bottom of the transport trolley gantry column 4 of the transport trolley body 46. A rubber-wheeled traveling device 8 is installed at the bottom of the lower longitudinal beam 7. The traveling device uses solid rubber wheels and is equipped with two sets of motor reducers (K97-142-4kW-4) and a motor drive system. Power is supplied by a generator set 17 installed inside the transport trolley body 46. The top of the transport trolley gantry column 4 is connected to a full-coverage platform 9 via an upper crossbeam 2. A longitudinal connecting beam 14 for the longitudinal trolley is installed between the two upper crossbeams 2, and a longitudinal trolley 10 for the transport trolley is installed on top of the upper crossbeams 2. A top-level platform ladder 3 and a first lateral working platform 5 are configured on both sides of the column 4. A lateral platform ladder 6 is installed on the side of the first lateral working platform 5, and a side-arched corrugated steel plate 13 is fixed via a connecting assembly. The connecting assembly consists of side guide wheels 43 and limiting grooves 44. The side guide wheels 43 are slidably connected to the side of the side arch corrugated steel plate 13. Traveling wheels 45 are installed on the side of the side arch corrugated steel plate 13, and the traveling wheels 45 are embedded in the limiting grooves 44 for guidance. The top of the two side arch corrugated steel plates 13 is fixed with a top arch corrugated steel plate 11, and guardrails 1 are set on both sides of the top arch corrugated steel plate 11. A clearance clearance 12 is maintained between the main body 46 of the transport trolley and the tunnel wall. A vertical hydraulic cylinder 19 of the transport trolley is set at the bottom, and its piston rod is connected to the transport trolley translation device 20 to realize the overall lifting and translation function of the trolley. The internal hydraulic system is controlled by an eight-unit solenoid valve hydraulic station 18. The longitudinal truss main body 16 enhances the structural strength, and the top crossbeam longitudinal bracing 15 improves the overall rigidity.

[0079] The gantry column 27 of the installation trolley body 47 is fixed with a gantry beam 26 at its top. An upper translation device 22 is installed on the top of the gantry beam 26 to move the upper translation trolley 24. An upper lifting cylinder 23 is installed on the top of the upper translation trolley 24, and its piston rod is connected to an arc-shaped beam 21. A ladder 28 and a second lateral working platform 29 are configured on the side of the gantry column 27. A corrugated plate push cylinder 30 is fixed to the side of the second lateral working platform 29 via a connecting assembly of the same structure. The ends of the two cylinders are connected to both ends of the arc-shaped beam 21. A lower longitudinal beam 32 of the trolley is fixed to the bottom of the gantry column 27, and a trolley traveling device 33 is installed at its bottom. The traveling device uses the same solid rubber wheel drive system as the transport trolley. A clearance clearance 31 is maintained between the installation trolley body 47 and the tunnel wall. A gantry longitudinal linkage 34 reinforcement structure is installed at the top, and a gantry longitudinal truss 35 and a fourteen-unit solenoid valve hydraulic station 36 are configured internally. A vertical hydraulic cylinder 37 for the installation trolley is installed at the bottom, and its piston rod is connected to the trolley translation device 38 to realize the lifting and translation functions of the installation trolley.

[0080] A multi-functional hoist 41 is fixedly installed on one side of the top of both the transport trolley body 46 and the installation trolley body 47 for the vertical hoisting of the corrugated steel plates. The trolley's traveling system uses a cycloidal pinwheel reducer, which requires 220-320 medium-load gear oil before operation. During the first operation of the hydraulic system, 46# anti-wear hydraulic oil needs to be added in multiple stages to ensure the pump station level meets requirements and to purge air from the pipelines. When positioning the trolley, first align the center of the top formwork with the tunnel centerline, then support the side formwork in place. The track center distance error should be controlled within ±10mm, and the track center error with the tunnel center should not exceed 20mm. After the templates are assembled, the gap should not exceed 1.5mm, the operating window should open flexibly with a gap of no more than 1.5mm from the template, and the bolt connections should be secure and not loose. The hydraulic system should be tested under pressure according to design requirements, and there should be no leakage at any pipeline joint. After the entire machine is installed, a trial run should be conducted on-site to ensure the traveling system is stable, the jacks operate flexibly without lag, and the hydraulic system pressure maintains the factory setting value.

[0081] The complete process of the steel corrugated plate reinforcement construction using this trolley includes: the pre-assembly stage outside the tunnel where the steel corrugated plates are assembled into an integral structure; the transportation stage inside the tunnel where the steel corrugated plates are transported from outside the tunnel to the installation position via the longitudinal trolley 10 of the transport trolley, while maintaining the clearance 12 of the transport trolley to meet the requirements for the passage of social vehicles during the transportation process; the installation stage where the steel corrugated plates are transferred to the installation position using the longitudinal trolley 25 of the installation trolley, the vertical position of the steel corrugated plates is adjusted by the upper lifting cylinder 23 and the arc beam 21, the side corrugated plate pushing cylinder 30 pushes the steel corrugated plates into horizontal position, the ZDY650 coal mine full hydraulic tunnel drilling rig 42 and the small down-the-hole drilling rig 40 complete the anchor bolt construction, and the fourteen-unit solenoid valve hydraulic station 36 controls the coordinated operation of each cylinder. The vertical hydraulic cylinder 19 of the transport trolley and the vertical hydraulic cylinder 37 of the installation trolley are designed with a stroke of 400mm, a working stroke of 150mm, and a reserved 250mm lifting stroke; the translation cylinder has a maximum stroke of 100mm, allowing for 50mm adjustment to the left and right of the tunnel center. The trolley track gauge is set at 7200mm, the clearance height is 5000mm, the traveling speed is 9m / min, the traveling motor power is 4kW×2, and the hydraulic system rated pressure is 16MPa, meeting the construction requirements under conditions of uninterrupted traffic. The trolley surface is equipped with reflective stickers, warning lights, and height limit signs. The top height limit sign and warning lights ensure that the clearance for the shield trolley to pass meets the 4.5m×5m standard. The lifting cylinder and translation cylinder work together to achieve precise adjustment of the trolley's posture.

[0082] This application can be used in the field of trolleys, or in other fields applicable to this application.

[0083] In another embodiment: Reference Figure 1-6A steel corrugated plate transport and installation trolley for tunnel reinforcement is used in the field of trolleys. The top of the gantry beam 26 is equipped with a longitudinal trolley 25, and a layer of tilting platform 39 and ZDY650 coal mine full hydraulic tunnel drilling rig 42 are installed on the side. Multiple small down-the-hole drilling rigs 40 are configured on the outer wall.

[0084] However, as is well known to those skilled in the art, the working principles and wiring methods of the coal mine full hydraulic tunnel drilling rig 42, small down-the-hole drilling rig 40, generator set 17, eight-unit solenoid valve hydraulic station 18, and fourteen-unit solenoid valve hydraulic station 36 are all conventional means or common knowledge, and will not be elaborated here. Those skilled in the art can make any selections according to their needs or convenience.

[0085] The above description is only a preferred embodiment of the present utility model, but the protection scope of the present utility model is not limited thereto. Any equivalent substitutions or changes made by those skilled in the art within the technical scope disclosed in the present utility model, based on the technical solution and the inventive concept of the present utility model, should be included within the protection scope of the present utility model.

Claims

1. A trolley for transporting and installing corrugated steel sheets for tunnel reinforcement, characterized in that, include: The main body of the transport trolley (46) and the main body of the installation trolley (47); The main body (46) of the transport trolley includes a transport trolley gantry column (4), a transport trolley lower longitudinal beam (7), a transport trolley rubber-wheel travel device (8), a transport trolley longitudinal trolley (10), a transport trolley vertical cylinder (19), and a transport trolley translation device (20). The main body (47) of the installation trolley includes the installation trolley gantry column (27), the installation trolley lower longitudinal beam (32), the installation trolley traveling device (33), the installation trolley vertical cylinder (37), the installation trolley translation device (38), and the installation trolley longitudinal trolley (25); The transport trolley rubber wheel walking device (8) and the installation trolley walking device (33) both use solid rubber wheels and are equipped with motor reducers for driving the trolley to move; the transport trolley vertical cylinder (19) and the installation trolley vertical cylinder (37) are used to realize the overall lifting of the trolley; the transport trolley translation device (20) and the installation trolley translation device (38) are used to realize the translation of the trolley. The trolley is designed to allow social vehicles to travel at reduced speeds, so that traffic can be maintained without interruption during the tunnel steel corrugated plate reinforcement construction, effectively ensuring normal traffic flow.

2. The steel corrugated plate transportation and installation trolley for tunnel reinforcement according to claim 1, characterized in that, The main body of the transport trolley (46) also includes an upper crossbeam (2), a crossbeam full-coverage platform (9), and a longitudinal connecting beam (14) for the longitudinal trolley; The upper crossbeam (2) is fixedly installed on the top of the transport trolley gantry column (4), the crossbeam full-coverage platform (9) is fixedly installed between the two upper crossbeams (2), the longitudinal connecting beam (14) of the longitudinal trolley is arranged between the upper crossbeams (2), and the longitudinal trolley (10) of the transport trolley is fixedly installed on the top of the upper crossbeam (2).

3. The steel corrugated plate transportation and installation trolley for tunnel reinforcement according to claim 1, characterized in that, The main body of the installation trolley (47) also includes a gantry beam (26), an upper translation trolley (24), and an upper lifting cylinder (23); The gantry beam (26) is fixedly installed on the top of the gantry column (27) of the installation trolley. The upper translating trolley (24) is slidably connected to the top of the gantry beam (26). The upper lifting cylinder (23) is fixedly installed on the top of the upper translating trolley (24). An arc-shaped beam (21) is fixedly installed on the top of the piston rod of the upper lifting cylinder (23). A ladder (28) is fixedly installed on the side of the gantry column (27) of the installation trolley. A second lateral working platform (29) is fixedly installed on one side of the column (27). A corrugated plate push cylinder (30) is fixedly installed on the side of the second lateral working platform (29) through a connecting component. One end of the two corrugated plate push cylinders (30) is fixedly connected to both ends of the arc beam (21). Multiple crossbeams are fixedly installed at the top of the transport trolley body (46). An upper translation device (22) is fixedly installed on the top of the gantry crossbeam (26).

4. The steel corrugated sheet transportation and installation trolley for tunnel reinforcement according to any one of claims 1 to 3, characterized in that, It also includes a connecting component, which includes a side wheel (43) and a limiting groove (44); The side guard wheel (43) is slidably connected to the side of the side arch corrugated steel plate (13), and the side of the side arch corrugated steel plate (13) is fixedly installed with a walking wheel (45), which is embedded in the limiting groove (44) for guidance.

5. The steel corrugated plate transportation and installation trolley for tunnel reinforcement according to claim 1, characterized in that, The main body of the transport trolley (46) also includes a generator set (17) and an eight-unit solenoid valve hydraulic station (18); The generator set (17) is fixedly installed inside the main body (46) of the transport trolley and is used to power the walking device; the eight-cell solenoid valve hydraulic station (18) is fixedly installed inside the main body (46) of the transport trolley and is used to control the hydraulic system.

6. The steel corrugated plate transportation and installation trolley for tunnel reinforcement according to claim 1, characterized in that, The vertical cylinder (37) of the installation trolley has a designed stroke of 400mm, a working stroke of 150mm, and a reserved lifting stroke of 250mm. The maximum stroke of the installation trolley translation device (38) is 100mm, and the stroke can be adjusted by 50mm to the left and right of the center of the tunnel. A gantry longitudinal joint (34) is fixedly installed on the top of the installation trolley body (47). Multiple gantry longitudinal trusses (35) are fixedly installed inside the installation trolley body (47). A fourteen-unit solenoid valve hydraulic station (36) is fixedly installed inside the installation trolley body (47).

7. The steel corrugated plate transportation and installation trolley for tunnel reinforcement according to claim 1, characterized in that, The transport trolley body (46) and the installation trolley body (47) both include guardrails (1) and walkway protection devices. Multiple single-layer tilting platforms (39) are fixedly installed on the outer wall of the installation trolley body (47). Top-level platform ladders (3) are provided on both sides of the transport trolley gantry column (4). First lateral working platforms (5) are installed on both sides of the transport trolley gantry column (4). Lateral platform ladders (6) are fixedly installed on the side of the first lateral working platform (5). Multiple longitudinal truss bodies (16) are provided inside the transport trolley body (46). The guardrail (1) is fixedly installed on both sides of the top of the corrugated steel plate (11) of the arch, and the walkway protection device is fixedly installed on the side working platform to prevent construction workers from falling.

8. The steel corrugated plate transportation and installation trolley for tunnel reinforcement according to claim 1, characterized in that, An installation trolley clearance clearance (31) is provided between the installation trolley body (47) and the tunnel, and a transport trolley clearance clearance clearance (12) is provided between the transport trolley body (46) and the tunnel interior.

9. The steel corrugated plate transportation and installation trolley for tunnel reinforcement according to claim 1, characterized in that, It also includes a multi-functional hoist (41), a small down-the-hole drill (40), and a ZDY650 coal mine full hydraulic tunnel drilling rig (42); The multi-functional hoist (41) is fixedly installed on the top side of the transport trolley body (46) and the installation trolley body (47) for vertical hoisting of the corrugated steel plate; the small down-the-hole drill (40) and the ZDY650 coal mine full hydraulic tunnel drill (42) are fixedly installed on the installation trolley body (47) for completing the anchor bolt locking and grouting operations.