Temporary support system of large-span spherical roof with intersecting arc-shaped curved rib beams
Patent Information
- Application Number
- CN202520427827.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-12
- Publication Date
- 2026-09-04
- Estimated Expiration
- 2035-03-12
AI Technical Summary
这样的结构特点使得传统支撑体系难以满足施工需求,不仅材料用量巨大,搭设难度也大,且对架体的整体高宽比和加固措施提出了更高要求,影响了施工的整体安全性和稳定性
[0021] This utility model adopts the above design and has the following significant features:
Smart Images

Figure CN224717371U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of building isolation and protection, specifically a temporary support system for a large-span spherical roof with intersecting arc-shaped curved ribs. Background Technology
[0002] In the field of modern building construction, the large-span spherical roof with intersecting curved ribs and beams has extremely high requirements for the temporary support system during construction due to its unique shape and complex structural characteristics.
[0003] like Figure 1 , Figure 2 A building structure employing a reinforced concrete frame-shear wall system has a roof structure consisting of intersecting curved beams and slabs. Loads are transferred through a parallelogram-shaped ring beam at 16.50 meters and 36 structural columns below. This complex roof structure, including intersecting curved ribs and slabs, cannot be directly transferred to the completed ring beams and columns due to the design of the construction sequence, as the loads from reinforcement, formwork, and concrete work cannot be directly transferred. Therefore, a temporary support system is needed to bear this load and ensure the smooth progress of construction. This temporary support system must not only possess sufficient load-bearing capacity and stability but also be able to adapt to the complex characteristics of the roof, such as its high span and intersecting curved surfaces.
[0004] Currently, various support systems existing in the fields of building construction and bridges, such as modular scaffolding and formwork trusses, have shown limitations when applied to this project. While modular scaffolding is lightweight and easy to assemble, its span and height are limited, and it is difficult to adapt to complex structures such as circular ring beams on roofs. Although formwork trusses have strong load-bearing capacity, their construction is complex and costly, and they also cannot fully meet the specific requirements of this project.
[0005] In particular, the roof of this project is a high-altitude, large-span, intersecting, curved, ribbed spherical structure with varying beam cross-sectional dimensions and curvature. The highest point of the concrete roof is 49.27 meters above the ground foundation, with a span of 130 meters. These structural characteristics make traditional support systems inadequate for construction needs, resulting in enormous material consumption, significant erection difficulties, and higher requirements for the overall height-to-width ratio and reinforcement measures of the scaffolding, thus affecting the overall safety and stability of the construction.
[0006] Therefore, given the characteristics and needs of this project, there is an urgent need for a new type of efficient and stable temporary support system to solve the support problem of a large-span spherical roof with intersecting curved ribs during construction. Utility Model Content
[0007] The purpose of this invention is to overcome the aforementioned shortcomings and propose a highly efficient combined support system for a large-span spherical roof with intersecting curved ribbed beams. This temporary support system features strong load-bearing capacity, good stability, strong adaptability, convenient construction, and economic rationality, while also ensuring the smooth progress of construction and the safety and stability of the roof structure.
[0008] To achieve the above objectives, this utility model is implemented as follows:
[0009] A temporary support system for a large-span spherical roof with intersecting curved ribbed beams, including...
[0010] Functional frame structure: includes multiple high-strength steel pipe columns, sturdily connected steel pipe horizontal bars and steel pipe diagonal bars. The steel pipe columns are firmly fixed to the ground or substructure through specially designed connecting ends, forming a basic frame supporting the roof. The functional frame structure is used to provide load-bearing capacity and its position and size can be flexibly adjusted according to construction needs to adapt to the support requirements of the curvature and curved surfaces of different areas of the roof.
[0011] Enhanced top truss: Installed on top of the functional frame structure, it is composed of H-beams that have been structurally designed and selected. It is used to enhance the overall load-bearing capacity and stability of the functional frame structure and effectively prevent and resist various lateral and vertical loads that occur during construction.
[0012] Modular disc-lock support system: Installed on the functional frame structure and top truss, it consists of standardized disc-lock uprights, horizontal bars and diagonal bars tightly connected by reliable fasteners to form a matrix-distributed full-span frame structure, used to bear the self-weight of the upper beams and slabs and various construction loads, ensuring safety and stability during construction.
[0013] The temporary support system forms a stable support foundation through a five-ring circumferentially arranged functional frame structure. The support columns of each ring are arranged according to a predetermined spacing and layout to ensure the uniformity and stability of the support.
[0014] The top truss is divided into two layouts: circumferential trusses and radial trusses. The circumferential trusses are arranged along the periphery of the functional frame structure and connected to the functional frame structure to enhance the circumferential stiffness of the entire functional frame structure in the horizontal direction. The radial trusses extend outward from the central area of the functional frame structure and form a stable connection with the circumferential trusses and the functional frame structure, effectively transferring loads and enhancing the stability of the supporting structure in the radial direction.
[0015] Furthermore, the steel pipe columns, steel pipe crossbars, and steel pipe diagonal bars of the frame structure are securely connected through a specific connection method to form a triangular support configuration with enhanced stability; and the top truss is made of selected H-beams to further improve the rigidity of the overall structure; at the same time, the disc buckle support system uses standardized components and achieves quick and reliable assembly and disassembly through a unique fastening method.
[0016] Furthermore, in the temporary support system of the aforementioned large-span spherical roof with intersecting curved ribs, the steel pipe columns, steel pipe crossbars, and steel pipe diagonal bars of the frame structure are securely connected by welding or bolting to form a stable triangular support structure.
[0017] Furthermore, in the temporary support system of the aforementioned large-span spherical roof with intersecting curved ribs, the H-beams of the top truss are connected by welding or high-strength bolts to ensure the overall rigidity and stability of the truss structure.
[0018] Furthermore, the temporary support system for the aforementioned large-span spherical roof with intersecting curved ribs, including the disc-lock support system, consists of standardized components such as the disc-lock uprights, horizontal bars, and diagonal bars. These components are connected quickly and reliably via fasteners, facilitating on-site assembly and disassembly.
[0019] Furthermore, the temporary support system for the aforementioned large-span spherical roof with intersecting curved ribs also includes additional connectors to enhance overall stability. These additional connectors are located between the frame structure, the top truss, and the disc-lock support system, and are fixedly connected to each component by welding or bolting.
[0020] Furthermore, the temporary support system for the aforementioned large-span spherical roof with intersecting curved ribs has an adjustment device at the bottom of the steel pipe columns of the formwork structure, which is used to adjust the height and level of the formwork structure to adapt to the needs of different construction sites.
[0021] This utility model adopts the above design and has the following significant features:
[0022] 1. Functional frame structure:
[0023] The steel pipe columns are securely and adjustablely fixed to the ground or substructure via specially designed connecting ends, forming a solid foundation framework supporting the roof. This design allows the formwork structure to be flexibly adjusted in position and size according to construction needs, adapting to the curvature and surface variations of different areas of the roof;
[0024] The steel pipe columns, steel pipe crossbars, and steel pipe diagonal bars are firmly connected by welding or high-strength bolts, forming a triangular support structure with extremely high stability, which further enhances the overall structure's resistance to lateral forces and overturning.
[0025] 2. Regarding the top truss:
[0026] Constructed from H-beams using rigorous structural design and selection, this structure ensures high strength and rigidity in practical applications. This not only enhances the overall load-bearing capacity and stability of the functional formwork structure but also effectively prevents and resists various lateral and vertical loads that may occur during construction, such as wind loads and construction equipment loads.
[0027] 3. Modular disc buckle support system:
[0028] The support system consists of standardized disc-lock uprights, horizontal bars, and diagonal bars, which are installed on the functional frame structure and the top truss to form a matrix-distributed full-span frame structure.
[0029] These components achieve quick and tight connections through reliable fasteners, greatly improving construction efficiency and ease of on-site assembly.
[0030] The modular disc-locking support system can bear the self-weight of the upper beams and slabs as well as various construction loads, ensuring safety and stability during construction, while providing a safe working platform for construction personnel.
[0031] 4. Regarding standardized components and additional connectors:
[0032] This combined support system uses a large number of standardized components, such as H-beams and disc-lock uprights. The standardized production of these components not only reduces costs but also improves construction speed and on-site management efficiency.
[0033] To further enhance overall stability, this combined support system also incorporates additional connectors between the frame structure, the top truss, and the modular support system. These connectors are fixed to the various components via welding or bolting, forming a more robust overall structure. Attached Figure Description
[0034] Figure 1 This is a top view of a large-span spherical roof with intersecting curved ribbed beams.
[0035] Figure 2 This is a schematic diagram of the temporary support system construction shown in this invention. Figure 1 .
[0036] Figure 3 This is a schematic diagram of the functional frame structure in the temporary support system shown in this invention.
[0037] Figure 4 This is a schematic diagram of the reinforced top truss in the temporary support system shown in this invention.
[0038] Figure 5This is a schematic diagram of the assembly of the temporary support system shown in this invention.
[0039] Figure 6 This is a schematic diagram of the temporary support system construction shown in this invention. Figure 2 .
[0040] Figure 7 This is a schematic diagram of the modular disc buckle support system in the temporary support system shown in this invention.
[0041] Figure 8 This is a schematic diagram of the temporary support system construction shown in this invention. Figure 3 .
[0042] Figure 9 This is a schematic diagram of the temporary support system construction shown in this invention. Figure 4 . Detailed Implementation
[0043] To further illustrate the technical means and effects of the present invention in achieving its intended purpose, the following detailed description of the specific implementation methods, structures, features, and effects of the present invention, in conjunction with the accompanying drawings and preferred embodiments, is provided below.
[0044] Example 1
[0045] This embodiment addresses a reinforced concrete frame-shear wall system building structure, whose upper roof structure is a cross-shaped curved beam-slab 1 (e.g., Figure 1 The load is transferred through a parallelogram-shaped ring beam 2 at 16.50 meters and 36 structural columns 3 at the bottom. The roof structure is complex, including intersecting curved rib beams and slabs. The highest point of the concrete roof is 49.27 meters above the ground foundation, with a span of 130 meters, which places extremely high demands on the temporary support system during construction.
[0046] To meet the requirements of the temporary support system during the above construction process, this embodiment proposes a temporary support system for a large-span spherical roof with intersecting curved ribbed beams (such as...). Figure 2 ).
[0047] I. The following is the method for constructing the temporary support system:
[0048] 1. Construction of functional frame structure 4 (e.g.) Figure 3 ).
[0049] 1.1 Material Selection and Preparation:
[0050] High-strength steel pipes are selected as the uprights 41, horizontal bars 42, and diagonal bars 43 of the frame structure 4, and the material conforms to relevant standards (such as Q335B). At the same time, specially made connecting ends are prepared to firmly fix the uprights 41 to the ground or the underlying frame structure 4.
[0051] 1.2 Basic Processing:
[0052] The construction area is laid out to determine the installation position of the column 41 in the frame structure 4. The column 41 is connected to the concrete base plate with chemical bolts (such as M24 chemical bolts), and the bottom gap is filled with high-strength grout (such as BY60 type) to ensure the firmness and stability of the connection.
[0053] 1.3 Assembly of frame structure 4:
[0054] Based on the design drawings and actual site conditions, the columns 41, horizontal bars 42, and diagonal bars 43 are assembled according to the predetermined spacing and layout. They are then securely connected by welding or high-strength bolts to form a triangular support structure with enhanced stability.
[0055] 1.4 Height and Level Adjustment:
[0056] The height and level of the frame structure 4 are adjusted using the adjustment device (such as an adjustable base or an adjustable top support) at the bottom of the column 41 to ensure that the construction requirements are met.
[0057] 2. Installation of reinforced top truss 5 (e.g.) Figure 4 , Figure 5 )
[0058] 2.1 Material Selection and Processing:
[0059] H-beam 51, selected through structural design and type selection, was chosen as the component of the top truss 5. The material conforms to relevant standards (such as HN or HW series H-beams of Q355B material). The H-beam 51 was processed by cutting, drilling, and other procedures according to the design drawings.
[0060] 2.2 Truss Assembly:
[0061] The pre-fabricated H-beams 51 are assembled according to the design drawings to form circumferential and radial trusses. The overall rigidity and stability of the truss structure are ensured by welding or high-strength bolt connections.
[0062] 2.3 Truss Installation:
[0063] The assembled reinforced top truss 5 is installed on top of the functional frame structure 4 to form a stable overall structure.
[0064] 3. Construction of the modular disc buckle support system 6 (e.g.) Figure 6 , Figure 7 )
[0065] 3.1 Material Preparation:
[0066] Prepare standardized components such as disc buckle uprights 61, horizontal bars 62, diagonal bars 63, and buckle connectors, with materials conforming to relevant standards (such as Q345A, Q235B, etc.).
[0067] 3.2 Support System Assembly:
[0068] Based on the design drawings and actual site conditions, a modular disc-lock support system 6 is constructed on top of the functional frame structure 4 and the top truss 5. The disc-lock uprights 61, horizontal bars 62, and diagonal bars 63 are tightly connected together through fasteners to form a matrix-distributed full-span frame structure.
[0069] 3.3 Load Testing and Adjustment:
[0070] During the construction process, load tests are conducted on the support system to ensure it meets construction requirements. If necessary, the support system is adjusted and optimized.
[0071] 4. Installation of additional connectors
[0072] 4.1 Material Preparation:
[0073] Prepare additional connectors, such as connector plates and pins, made of materials that meet relevant standards.
[0074] 4.2 Installation of connectors:
[0075] Additional connectors are placed between the frame structure 4, the top truss 5, and the disc buckle support system 6, and are fixedly connected to each component by welding or bolting, further enhancing the stability of the overall structure.
[0076] II. The following is a method for constructing a temporary support system for a large-span spherical roof with intersecting curved ribbed beams:
[0077] 5.1. Sectional and segmented erection of cross-shaped curved surface beam support structure:
[0078] The construction area is divided into four construction zones, and the frame structure 4 is erected in a zoned and block-based manner. For the entire large-span spherical roof with intersecting arc-shaped curved ribs, a five-ring support system from the inside out is to be implemented. The ring support system is mainly composed of the frame structure 4, the top truss 5, and the buckle support system 6.
[0079] 5.2 Construction route layout and hoisting:
[0080] Two construction routes were set up, each equipped with corresponding hoisting equipment (such as 80t and 50t truck cranes), and the installation of the frame structure 4 was carried out in a symmetrical construction manner.
[0081] 5.3 Installation of frame structure 4:
[0082] Loosen out and position the first section of the frame structure 4 at the center position below the spherical roof;
[0083] After accurate positioning, install the first section of the first ring frame structure 4 and effectively connect and reinforce it with the frame structure 4 at the center position;
[0084] Install the first ring belt frame structure 4 and the frame mechanism 4 at the center position onto the top, and install the conversion truss;
[0085] Install the second ring belt frame structure 4 to the top, install the transfer truss, and connect and fix the second ring belt frame structure 4 to the first ring belt frame structure 4 with the connecting rod 7. Install the main beam between the first section frame structure 4 at the center position and the first ring belt frame structure 4.
[0086] 5.4 Repeat the above steps to install the frame structure 4 of the third ring belt, the fourth ring belt, and the fifth ring belt and the conversion truss in sequence, and connect and fix each ring frame through the connecting rod 7. At the same time, install the corresponding main beam 8 and secondary beam 9.
[0087] Install the side support truss 10 and the remaining main and secondary beams (such as...) Figure 8 , Figure 9 );
[0088] Install the support frame, transfer truss, main beam, and secondary beam in the passageway area, and finally exit from the passageway;
[0089] 6. Assembly of the disc buckle support system:
[0090] After the frame and upper truss are installed, the process is divided into three levels. The I-beams are laid out on the truss step by step, the columns are positioned, and the disc fasteners are installed symmetrically to complete the assembly of the disc fastener support system.
[0091] 7. Monitoring and maintenance during construction.
[0092] 7.1 Load Monitoring:
[0093] During construction, the load on the support system is monitored in real time to ensure that it does not exceed the design bearing capacity.
[0094] 7.2 Safety Inspection:
[0095] Regularly conduct safety inspections of the support system, including the tightness of connectors and the deformation of components, to ensure safety and stability during construction.
[0096] 7.3 Maintenance and Care:
[0097] Perform necessary maintenance and upkeep on the support system, such as tightening loose connections and replacing damaged components, to extend the service life of the support system.
[0098] Following the aforementioned construction steps, the efficient combined support system for the large-span spherical roof with intersecting curved ribs, as proposed in this invention, was successfully constructed. This support system not only possesses strong load-bearing capacity and stability but also adapts to complex and changing construction environments. During construction, the support system demonstrated excellent adaptability and reliability, ensuring the smooth progress of construction and the safety and stability of the roof structure.
[0099] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention in any way. Although the present invention has been disclosed above with reference to preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art can make some modifications or alterations to the above-disclosed technical content to create equivalent embodiments without departing from the scope of the present invention. Any simple modifications, equivalent changes and alterations made to the above embodiments based on the technical essence of the present invention without departing from the scope of the present invention shall still fall within the scope of the present invention.
Claims
1. A temporary support system for a large-span spherical roof with intersecting arc-shaped curved ribs, characterized in that: include Functional frame structure: includes multiple high-strength steel pipe columns, sturdily connected steel pipe horizontal bars and steel pipe diagonal bars. The steel pipe columns are firmly fixed to the ground or substructure through specially designed connecting ends, forming a basic frame supporting the roof. The functional frame structure is used to provide load-bearing capacity and its position and size can be flexibly adjusted according to construction needs to adapt to the support requirements of the curvature and curved surfaces of different areas of the roof. Enhanced top truss: Installed on top of the functional frame structure, it is composed of H-beams that have been structurally designed and selected. It is used to enhance the overall load-bearing capacity and stability of the functional frame structure and effectively prevent and resist various lateral and vertical loads that occur during construction. Modular disc-lock support system: Installed on the functional frame structure and top truss, it consists of standardized disc-lock uprights, horizontal bars and diagonal bars tightly connected by reliable fasteners to form a matrix-distributed full-span frame structure, used to bear the self-weight of the upper beams and slabs and various construction loads, ensuring safety and stability during construction. The temporary support system forms a stable support foundation through a five-ring circumferentially arranged functional frame structure. The support columns of each ring are arranged according to a predetermined spacing and layout to ensure the uniformity and stability of the support. The top truss is divided into two layouts: circumferential trusses and radial trusses. The circumferential trusses are arranged along the periphery of the functional frame structure and connected to the functional frame structure to enhance the circumferential stiffness of the entire functional frame structure in the horizontal direction. The radial trusses extend outward from the central area of the functional frame structure and form a stable connection with the circumferential trusses and the functional frame structure, effectively transferring loads and enhancing the stability of the supporting structure in the radial direction.
2. The temporary support system for a large-span spherical roof with intersecting arc-shaped curved ribs according to claim 1, characterized in that: The steel pipe columns, steel pipe crossbars, and steel pipe diagonal braces of the frame structure are securely connected by a specific connection method to form a triangular support configuration with enhanced stability; and the top truss is made of selected H-beams to further improve the rigidity of the overall structure; at the same time, the disc buckle support system uses standardized components and achieves quick and reliable assembly and disassembly through a unique fastening method.
3. The temporary support system for a large-span spherical roof with intersecting arc-shaped curved ribs according to claim 2, characterized in that: The steel pipe columns, steel pipe crossbars, and steel pipe diagonal bars of the frame structure are securely connected by welding or bolting to form a stable triangular support structure.
4. The temporary support system for a large-span spherical roof with intersecting arc-shaped curved ribs according to claim 2 or 3, characterized in that: The H-beams of the top truss are connected by welding or high-strength bolts to ensure the overall rigidity and stability of the truss structure.
5. The temporary support system for a large-span spherical roof with intersecting arc-shaped curved ribs according to claim 2 or 3, characterized in that: The disc buckle support system consists of standardized components, including uprights, horizontal bars, and diagonal bars. These components are connected quickly and reliably via fasteners, facilitating on-site assembly and disassembly.
6. The temporary support system for a large-span spherical roof with intersecting arc-shaped curved ribs according to claim 1 or 2, characterized in that: The temporary support system also includes additional connectors to enhance overall stability. These additional connectors are disposed between the frame structure, the top truss, and the disc buckle support system, and are fixedly connected to each component by welding or bolting.
7. The temporary support system for a large-span spherical roof with intersecting arc-shaped curved ribs according to claim 1 or 2, characterized in that: The bottom of the steel pipe column of the frame structure is equipped with an adjustment device to adjust the height and level of the frame structure to adapt to the needs of different construction sites.