Dust-reducing vertical construction waste transport device

CN224729282UActive Publication Date: 2026-09-08THE THIRD CONSTR OF CHINA CONSTR EIGHTH ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522107463.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-09-29
Publication Date
2026-09-08
Estimated Expiration
2035-09-29

AI Technical Summary

Technical Problem

[0003]实用新型目的:本实用新型目的在于针对现有技术的不足,提供一种可降尘的建筑垃圾垂直运输装置,有效解决了传统建筑垃圾清运存在的效率低、易产生大量灰尘等问题

Benefits of technology

与传统技术相比,本实用新型将垃圾垂直运输技术与施工现场的临时水降尘系统相结合,不仅提高了垃圾运输效率,而且不易产生大量灰尘,维护了现场施工环境,体现了绿色施工理念。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224729282U_ABST
    Figure CN224729282U_ABST
Patent Text Reader

Abstract

The utility model discloses a vertical transport device of construction waste can reduce dust, including the garbage pipeline of setting in the elevator shaft in the building and the dust reduction system of setting on each floor and accessing the garbage pipeline, all set up a garbage throw -in mouth in each floor in the corresponding position on the garbage pipeline, infrared switch is arranged below the garbage throw -in mouth, and the infrared switch is connected with dust reduction system signal, the garbage pipeline bottom is connected the garbage storage box, is provided with the garbage cleaning mouth on the garbage storage box, and the garbage storage box top also is provided with one end is equipped with the temporary water pipeline of shower head. The utility model combines garbage vertical transport technology and the temporary water dust reduction system of construction site, not only has improved garbage transport efficiency, moreover, does not easily produce a large amount of dust, has maintained the scene construction environment, has embodied the green construction concept.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of building construction technology, and in particular relates to a vertical transportation device for construction waste that can reduce dust. Background Technology

[0002] During the secondary structure construction phase, the construction industry generates a large amount of solid waste, such as concrete slag, mortar, and wall panel fragments, as processes like partition wall construction, plastering, and structural openings are carried out. Efficiently and environmentally friendly transporting this waste from each floor to the ground floor is a significant challenge. Currently, the common method is to pile the waste, load it into handcarts, and transport it to the ground floor using passenger and freight elevators. However, this method not only generates a large amount of dust during transport but also has low efficiency. To address these technical problems, this invention designs a dust-reducing vertical transport device for construction waste. Utility Model Content

[0003] Purpose of the utility model: The purpose of this utility model is to address the shortcomings of the existing technology by providing a vertical transportation device for construction waste that can reduce dust, effectively solving the problems of low efficiency and large amount of dust generated in traditional construction waste transportation.

[0004] Technical solution: A vertical transportation device for construction waste with dust suppression capability includes a waste pipe running from the top floor to the first floor of a building and a dust suppression system installed on each floor and connected to the waste pipe. The dust suppression system includes a water supply pipe, the front end of which is connected to the side of the waste pipe and equipped with a sprinkler head, and the rear end of which is connected to a temporary water point on the construction site. A valve is also installed on the water supply pipe. A waste disposal port is installed at a corresponding position on each floor of the waste pipe, and an infrared switch is installed below the waste disposal port. The infrared switch is connected to the sprinkler head signal. A waste collection box is connected to the bottom of the waste pipe, and the waste collection box is equipped with a waste collection port for centralized cleaning of waste.

[0005] Furthermore, the top of the garbage collection bin is also equipped with a water pipe with a spray head at one end. This water pipe serves as a branch pipe, with its other end connected to the water pipe of the dust suppression system on the first floor.

[0006] Furthermore, the garbage pipe is installed in the elevator shaft inside the building, and the garbage pipe is assembled from multiple pipe sections, with adjacent pipe sections connected by bolts. The diameter of the garbage pipe is 800mm.

[0007] Furthermore, each floor's garbage disposal opening is equipped with a foldable cover.

[0008] Beneficial effects: Compared with traditional technologies, this utility model combines vertical waste transportation technology with a temporary water dust suppression system at the construction site, which not only improves waste transportation efficiency but also reduces the generation of large amounts of dust, maintains the on-site construction environment, and embodies the concept of green construction. Attached Figure Description

[0009] Figure 1 This utility model presents a schematic diagram of the structure of a vertical transportation device for construction waste that can reduce dust.

[0010] In the diagram: 1-Garbage pipe, 2-Garbage disposal port, 3-Infrared switch, 4-Dust suppression system, 41-Sprayer head, 42-Valve, 43-Water supply pipe, 5-Garbage collection bin, 6-Garbage collection port. Detailed Implementation

[0011] The technical solution of this utility model will be described in detail below with reference to the accompanying drawings, but the protection scope of this utility model is not limited to the described embodiments.

[0012] like Figure 1 As shown, the dust-reducing vertical transport device for construction waste of this utility model includes a waste pipe 1 that runs from the top floor to the first floor and a dust reduction system 4 installed on each floor and connected to the waste pipe 1.

[0013] like Figure 1 As shown, the dust suppression system 4 includes a spray head 41, a valve 42, and a water supply pipe 43. The front end of the water supply pipe 43 is connected to the side of the garbage pipe 1 and a spray head 41 is installed thereon. The rear end of the water supply pipe 43 is connected to a temporary water point at the construction site to provide water for dust suppression spraying. A valve 42 is also installed on the water supply pipe 43 to facilitate the shut-off of the water supply when the garbage pipe 1 is under maintenance.

[0014] like Figure 1 As shown, a garbage disposal port 2 is installed at a corresponding position on each floor of the garbage duct 1. An infrared switch 3 is also installed below the garbage disposal port 2. The infrared switch 3 is connected to the spray head 41 in the dust suppression system 4. The infrared switch 3 senses whether a worker is dumping garbage into the garbage disposal port 2, thereby triggering the spray head 41 in the dust suppression system 4 to start spraying and achieve dust suppression.

[0015] like Figure 1 As shown, a garbage collection box 5 is connected to the bottom of the garbage pipe 1. A garbage cleaning port 6 is provided on the garbage collection box 5 to facilitate the centralized cleaning of the garbage in the garbage collection box 5. A water pipe 43 with a spray head 41 at one end is also provided on the top of the garbage collection box 5. The water pipe 43 here is a branch pipe, and its other end is connected to the water pipe 43 of the dust suppression system 4 on the first floor.

[0016] Garbage pipe 1 can be installed in the elevator shaft inside the building. To facilitate installation and disassembly, garbage pipe 1 is assembled from several pipe sections. The upper and lower pipe sections are connected by bolts, and the pipe diameter is about 800mm.

[0017] like Figure 1 As shown, in order to prevent dust from flying out of the garbage pipe 1 when workers are disposing of garbage, a foldable cover is installed on the garbage disposal port 2 on each floor. When disposing of garbage, the cover is opened and closed when the garbage is disposed of.

[0018] The principle of this utility model is to combine vertical garbage transportation technology with a temporary water dust suppression system at the construction site. When workers put garbage into the garbage disposal port 2 on each floor, the garbage slides down the garbage pipe 1 into the garbage collection bin 5. At the same time, the infrared switch 3 controls the dust suppression system 4 to spray water to suppress dust in the garbage pipe 1. After the garbage is disposed of, the dust suppression system 4 continues to suppress dust for 20 seconds before shutting off. Using this principle, this utility model not only improves the efficiency of garbage transportation but also protects the environment, embodying the construction concept of green construction.

[0019] As described above, although the present invention has been shown and described with reference to specific preferred embodiments, it should not be construed as limiting the present invention itself. Various changes in form and detail may be made to the present invention without departing from the spirit and scope of the appended claims.

Claims

1. A vertical transport device for construction waste with dust reduction capability, characterized in that, The system includes a garbage pipe (1) running from the top floor to the first floor and a dust suppression system (4) installed on each floor and connected to the garbage pipe (1); the dust suppression system (4) includes a water pipe (43), the front end of which is connected to the side of the garbage pipe (1) and a sprinkler head (41) is installed, the rear end of which is connected to a temporary water point at the construction site, and a valve (42) is also installed on the water pipe (43); a garbage disposal port (2) is installed on the garbage pipe (1) at a corresponding position on each floor, and an infrared switch (3) is installed below the garbage disposal port (2), and the infrared switch (3) is connected to the sprinkler head (41) by signal; a garbage collection box (5) is connected to the bottom of the garbage pipe (1), and a garbage collection port (6) is installed on the garbage collection box (5) for centralized garbage collection.

2. The dust-reducing vertical transport device for construction waste according to claim 1, characterized in that, The top of the garbage collection bin (5) is also equipped with a water pipe (43) with a spray head (41) at one end. The water pipe (43) here is a branch pipe, and its other end is connected to the water pipe (43) of the dust suppression system (4) on the first floor.

3. The dust-reducing vertical transport device for construction waste according to claim 1, characterized in that, The garbage pipe (1) is installed in the elevator shaft inside the building, and the garbage pipe (1) is assembled from multiple pipe sections. Adjacent pipe sections are connected by bolts. The diameter of the garbage pipe (1) is 800mm.

4. The dust-reducing vertical transport device for construction waste according to claim 1, characterized in that, Each floor's garbage disposal opening (2) is equipped with a foldable cover.