A prefabricated pump station
Patent Information
- Application Number
- CN202522222830.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-10-21
- Publication Date
- 2026-09-15
- Estimated Expiration
- 2035-10-21
AI Technical Summary
但该方案导致无法对出水口与污水泵之间的管道进行预装,只能在施工现场再进行安装,如果入水口最终角度与设计角度不同,管道还需要重新设计拼装,影响施工进度
本实用新型能实现快速的排污,提高工作效率。本实用新型通过粉碎组件可以防止排污的堵塞,进一步提升排污的效率。
Smart Images

Figure CN224755178U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of sewage pumping stations, and in particular to a prefabricated pumping station. Background Technology
[0002] With social development, the demand for sewage discharge in rural and urban areas is increasing, leading to the emergence of various drainage equipment. Integrated pumping stations, with their advantages of small footprint, factory prefabrication, and short construction period, are widely used in sewage systems. Their main function is to be installed in the sewage pipeline system to raise the elevation of sewage, allowing it to flow by gravity to the intercepting sewer network and ultimately be transported to the sewage treatment plant.
[0003] Chinese patent document CN104265615B discloses an integrated prefabricated pump station, including a casing with an inlet on the lower side and an outlet on the upper side. A sewage pump is located at the bottom of the casing, and the sewage pump is connected to the outlet via a pipe. Using this solution, the integrated prefabricated pump station only needs to be transported to the site for installation. However, the angle between the inlet and outlet in this solution is fixed. If there is a deviation in the connection angle with the existing inlet and outlet pipes, additional adapter pipes need to be fabricated, increasing the connection difficulty and reducing the tolerance for error.
[0004] Furthermore, Chinese patent application CN107083791A discloses a prefabricated pump station simplified structure, including a shell, which is a segmented structure connected by steel strips. While this approach allows the inlet and outlet to be located on different segments of the shell, enabling adjustment of the angle between them, it also prevents pre-installation of the piping between the outlet and the sewage pump. This necessitates on-site installation, and if the final inlet angle differs from the design angle, the piping needs to be redesigned and reassembled, impacting construction progress.
[0005] Meanwhile, the aforementioned pumping stations are not very efficient, and some large impurities may affect the efficiency of sewage discharge.
[0006] In view of the above-mentioned shortcomings, the designer actively researched and innovated in order to create a new type of prefabricated pumping station with greater industrial value. Utility Model Content
[0007] To solve the above-mentioned technical problems, the purpose of this utility model is to provide a prefabricated pumping station.
[0008] To achieve the above objectives, the present invention adopts the following technical solution: A prefabricated pumping station includes a fixed base, on which a pumping station cylinder is connected. One side of the pumping station cylinder is connected to an inlet pipe communicating with it, and the other side of the pumping station cylinder, opposite the inlet pipe, is connected to an outlet pipe communicating with it. A pulverizing and processing box is connected inside the pumping station cylinder. The inlet of the pulverizing and processing box is connected to the inlet pipe via a transition pipe, and the outlet of the pulverizing and processing box is connected to the pumping station cylinder. A pulverizing component for pulverizing impurities is connected to the pulverizing and processing box. A closed support is connected inside the pumping station cylinder, and a sliding door is provided on the closed support. A trough, a sealing plate for sealing the water outlet pipe is connected to the closed support that slides along the trough, and a lifting cylinder for sliding the sealing plate is connected to the closed support. A water pump is connected to the pump station cylinder located between the crushing and processing box and the closed support. The outlet of the water pump is connected to one end of a connecting pipe, and the other end of the connecting pipe is connected to one end of a ball check valve. The other end of the ball check valve is connected to one end of a sewage outlet pipe, and the other end of the sewage outlet pipe is connected to the top of the pump station cylinder and is also connected to a flexible joint. A maintenance platform is connected to the pump station cylinder.
[0009] Preferably, in the prefabricated pumping station, the pumping station cylinder is composed of a cylinder base, a cylindrical cylinder wall, and a cylinder top cover, which are connected by welding.
[0010] Preferably, in the prefabricated pumping station, the pumping station cylinder is made of stainless steel.
[0011] Preferably, in the prefabricated pumping station, two water pumps are provided.
[0012] Preferably, in the prefabricated pumping station, the maintenance platform includes maintenance mounting rings, maintenance platform supports, and maintenance benches. The maintenance mounting rings are installed on the inner wall of the pumping station cylinder, the maintenance platform supports are installed between the maintenance mounting rings, and the maintenance benches are installed between the maintenance platform supports. The maintenance benches are located between the pulverizing and processing box and the ball check valve.
[0013] Preferably, in the prefabricated pumping station, a ladder support for accessing the maintenance platform is connected inside the pumping station cylinder.
[0014] Preferably, in the prefabricated pump station, the crushing assembly includes a crushing motor, a crushing rod, and crushing blades. The crushing motor is mounted on the top of the crushing processing box, and the drive shaft of the crushing motor passes through the crushing processing box and is connected to the crushing rod. Crushing blades that rotate synchronously with the crushing rod are connected to the crushing rod.
[0015] Preferably, in the prefabricated pumping station, an inspection port is provided on the pumping station cylinder, and an inspection grating is connected inside the inspection port.
[0016] By means of the above solution, this utility model has at least the following advantages: This invention enables rapid wastewater discharge, improving work efficiency. The pulverizing component prevents blockages in the wastewater discharge process, further enhancing efficiency.
[0017] The above description is only an overview of the technical solution of this utility model. In order to better understand the technical means of this utility model and to implement it in accordance with the contents of the specification, the preferred embodiments of this utility model are described in detail below with reference to the accompanying drawings. Attached Figure Description
[0018] To more clearly illustrate the technical solutions of the embodiments of this utility model, the drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show some embodiments of this utility model and should not be regarded as a limitation on the scope. For those skilled in the art, other related drawings can be obtained based on these drawings without creative effort.
[0019] Figure 1 This is a schematic diagram of the structure of this utility model; Figure 2 yes Figure 1 A schematic diagram of the internal structure. Detailed Implementation
[0020] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, and not all embodiments. The components of the embodiments of this application described and shown in the accompanying drawings can generally be arranged and designed in various different configurations.
[0021] Therefore, the following detailed description of the embodiments of this application provided in the accompanying drawings is not intended to limit the scope of the claimed application, but merely to illustrate selected embodiments of the application. All other embodiments obtained by those skilled in the art based on the embodiments of this application without inventive effort are within the scope of protection of this application.
[0022] Example like Figure 1 , Figure 2As shown, a prefabricated pumping station includes a fixed base 1, on which a pumping station cylinder 2 is connected. One side of the pumping station cylinder 2 is connected to an inlet pipe 3, and the other side of the pumping station cylinder 2, opposite to the inlet pipe 3, is connected to an outlet pipe 4. A pulverizing and processing box 5 is connected inside the pumping station cylinder 2. The inlet of the pulverizing and processing box 5 is connected to the inlet pipe 3 via a transition pipe, and the outlet of the pulverizing and processing box 5 is connected to the pumping station cylinder 2. A pulverizing component for pulverizing impurities is connected to the pulverizing and processing box 5. A closed support 6 is connected inside the pumping station cylinder 2, and a sliding door is provided on the closed support 6. A trough, a sealing plate 7 for sealing the water outlet pipe is connected to the closed support 6 that slides along the trough, and a lifting cylinder 8 for sliding the sealing plate 7 is connected to the closed support 6. A water pump 9 is connected inside the pump station cylinder 2 located between the crushing and processing box and the closed support. The outlet of the water pump 9 is connected to one end of a connecting pipe, and the other end of the connecting pipe is connected to one end of a ball check valve 10. The other end of the ball check valve 10 is connected to one end of a sewage outlet pipe 11. The other end of the sewage outlet pipe 11 is connected to the top of the pump station cylinder 2 and is also connected to a flexible joint 12. A maintenance platform 13 is connected inside the pump station cylinder 2.
[0023] In this embodiment, the pump station cylinder 2 is composed of a cylinder base, a cylindrical cylinder wall, and a cylinder top cover, which are connected by welding. The pump station cylinder 2 is made of stainless steel.
[0024] In this embodiment, two water pumps 9 are provided, and the two water pumps can work simultaneously to improve the efficiency of sewage discharge.
[0025] In this embodiment, the maintenance platform 13 includes a maintenance mounting ring 131, a maintenance platform support 132, and a maintenance platform 133. The maintenance mounting ring 131 is installed on the inner wall of the pump station cylinder 2, the maintenance platform support 132 is installed between the maintenance mounting rings 131, and the maintenance platform 133 is installed between the maintenance platform supports 132. The maintenance platform 133 is located between the crushing and processing box and the ball check valve.
[0026] The maintenance installation ring 131 is welded to the pump station cylinder, while the maintenance platform bracket 132 and the maintenance platform 133 are connected to the corresponding components by fixing bolts.
[0027] The pump station cylinder 2 is equipped with a ladder support 14 for accessing the maintenance platform. An inspection port is provided on the pump station cylinder 2, and a maintenance grating 16 is connected inside the inspection port. This facilitates personnel access to the pump station cylinder 2 for maintenance.
[0028] In this embodiment, the pulverizing assembly includes a pulverizing motor 15, a pulverizing rod, and pulverizing blades. The pulverizing motor 15 is mounted on the top of the pulverizing chamber, and the drive shaft of the pulverizing motor 15 passes through the pulverizing chamber and is connected to the pulverizing rod. Pulverizing blades that rotate synchronously with the pulverizing motor are connected to the pulverizing rod.
[0029] The working principle of this utility model is as follows: In actual operation, sewage enters through the inlet pipe, and impurities are crushed by the crushing components on the crushing treatment box before entering the pump station cylinder, and then the sewage is discharged by the water pump.
[0030] During the above-mentioned sewage discharge process, the sealing plate is in a closed state to prevent sewage from being discharged from the outlet pipe. If the flow rate is large, the sealing plate can be opened to discharge water that exceeds the height of the outlet pipe. At the same time, the water pump is also in operation.
[0031] It should be noted that similar labels and letters in the following figures indicate similar items. Therefore, once an item is defined in one figure, it does not need to be further defined and explained in subsequent figures.
[0032] In the description of this application, it should be noted that the terms "vertical," "horizontal," "inner," and "outer," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, or the orientation or positional relationship commonly used when the product is in use. They are used only for the convenience of describing this application and for simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this application. Furthermore, the terms "first," "second," etc., are used only to distinguish descriptions and should not be construed as indicating or implying relative importance.
[0033] Furthermore, terms such as "horizontal" and "vertical" do not imply that components must be absolutely horizontal or vertical, but rather that they can be slightly tilted. For example, "horizontal" simply means that its direction is more horizontal than "vertical," and does not mean that the structure must be completely horizontal, but can be slightly tilted.
[0034] In the description of this application, it should also be noted that, unless otherwise expressly specified and limited, the terms "set up," "install," "connect," and "link" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.
[0035] The above description is only a preferred embodiment of the present utility model and is not intended to limit the present utility model. It should be noted that for those skilled in the art, several improvements and modifications can be made without departing from the technical principles of the present utility model, and these improvements and modifications should also be considered within the protection scope of the present utility model.
Claims
1. A prefabricated pumping station, characterized in that: The system includes a fixed base (1), on which a pump station cylinder (2) is connected. One side of the pump station cylinder (2) is connected to an inlet pipe (3) communicating with it, and the other side of the pump station cylinder (2) opposite to the inlet pipe (3) is connected to an outlet pipe (4) communicating with it. A crushing and processing box (5) is connected inside the pump station cylinder (2). The inlet of the crushing and processing box (5) is connected to the inlet pipe (3) through a transition pipe, and the outlet of the crushing and processing box (5) is connected to the pump station cylinder (2). A crushing component for crushing impurities is connected to the crushing and processing box (5). A closed support (6) is connected inside the pump station cylinder (2). A sliding groove is opened on the closed support (6) along the sliding groove. A sealing plate (7) for sealing the water outlet pipe is connected to the sliding closed support (6). A lifting cylinder (8) for sliding the sealing plate (7) is connected to the closed support (6). A water pump (9) is connected inside the pump station cylinder (2) located between the crushing and processing box and the closed support. The outlet of the water pump (9) is connected to one end of the connecting pipe. The other end of the connecting pipe is connected through one end of the ball check valve (10). The other end of the ball check valve (10) is connected to one end of the sewage outlet pipe (11). The other end of the sewage outlet pipe (11) is connected to the top of the pump station cylinder (2) and is also connected to the flexible joint (12). A maintenance platform (13) is connected inside the pump station cylinder (2).
2. A prefabricated pumping station according to claim 1, characterized in that: The pump station cylinder (2) consists of a cylinder base, a cylindrical cylinder wall and a cylinder top cover, which are connected by welding.
3. A prefabricated pumping station according to claim 1 or 2, characterized in that: The pump station cylinder (2) is made of stainless steel.
4. A prefabricated pumping station according to claim 1, characterized in that: Two water pumps (9) are provided.
5. A prefabricated pumping station according to claim 1, characterized in that: The maintenance platform (13) includes a maintenance installation ring (131), a maintenance platform support (132), and a maintenance platform (133). The maintenance installation ring (131) is installed on the inner wall of the pump station cylinder (2). The maintenance platform support (132) is installed between the maintenance installation rings (131). The maintenance platform (133) is installed between the maintenance platform supports (132) and is located between the crushing and processing box and the ball check valve.
6. A prefabricated pumping station according to claim 1, characterized in that: The pump station cylinder (2) is connected to a ladder support (14) for accessing the maintenance platform.
7. A prefabricated pumping station according to claim 1, characterized in that: The crushing assembly includes a crushing motor (15), a crushing rod, and crushing blades. The crushing motor (15) is installed on the top of the crushing processing box. The drive shaft of the crushing motor (15) passes through the crushing processing box and is connected to the crushing rod. The crushing rod is connected to crushing blades that rotate synchronously with it.
8. A prefabricated pumping station according to claim 1, characterized in that: The pump station cylinder (2) is provided with an inspection port, and an inspection grating plate (16) is connected inside the inspection port.
Citation Information
Patent Citations
Integrated prefabricated pumping station
CN104265615B
Prefabricated tubular pumping house structure
CN107083791A