Technical Problem

[0002]在水利水电土建施工领域,混凝土浇筑是极为关键的环节,而浇筑模板的性能直接影响着混凝土浇筑的质量与效率,目前,市面上常见的混凝土浇筑模板多为固定高度设计,这种固定高度的模板在实际应用中存在诸多不便,由于不同工程项目以及同一工程项目的不同施工部位,对混凝土浇筑的高度有着多样化的需求,当遇到需要较高混凝土浇筑高度的情况时,固定高度的模板无法满足施工要求,施工人员不得不采用多层模板叠加的方式进行搭建,这一过程不仅操作繁琐、耗费大量人力与时间,增加了施工成本,而且多层模板叠加时,各层模板之间的连接稳定性难以得到有效保障,容易出现松动、移位等问题,进而影响混凝土浇筑的质量,导致浇筑后的结构表面不平整、强度不均匀等缺陷,给工程质量带来潜在隐患

Benefits of technology

[0013]1、该一种水利水电土建施工用混凝土浇筑模板,通过下部模板和加高模板可设置多个,且加高模板能设置在下部模板上部,施工人员可根据不同工程对混凝土浇筑高度的实际需求,灵活组合下部模板和加高模板的数量,无需像传统模板那样因高度固定而进行繁琐的改造或重新定制,极大地提高了模板的通用性和适用性,有效节省了施工成本和时间。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224833603U_ABST
    Figure CN224833603U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of formwork for civil construction, and disclose a kind of concrete pouring formwork for water conservancy and hydropower civil construction, including lower formwork and heightening formwork, the lower formwork and heightening formwork can be multiple, and heightening formwork is set in the upper portion of lower formwork. Multiple can be set as needed by lower formwork and heightening formwork, and construction personnel can flexibly combine quantity, meet the requirement of different engineering to concrete pouring height, without the need to reform or customize due to the height of traditional formwork is fixed, improve versatility and applicability, save cost and time, the sealing plate of lower portion and heightening formwork and sealing groove accurate cooperation, form tight structure, prevent cement mortar leakage, avoid material waste and outside concrete hardening, ensure that formwork is used repeatedly, reduce cleaning difficulty, keep environment neat, in addition, support frame and connecting angle steel enhance the stability and compression resistance of formwork, prevent deformation, ensure engineering quality.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of formwork technology for civil engineering construction, specifically a concrete pouring formwork for water conservancy and hydropower civil engineering construction. Background Technology

[0002] In the field of water conservancy and hydropower civil engineering construction, concrete pouring is a crucial step, and the performance of the pouring formwork directly affects the quality and efficiency of concrete pouring. Currently, most concrete pouring formwork on the market is designed with a fixed height. This type of fixed-height formwork has many inconveniences in practical applications. Due to the diverse requirements for concrete pouring heights in different engineering projects and different construction parts of the same project, fixed-height formwork cannot meet the construction requirements when a higher concrete pouring height is needed. Construction workers have to use multi-layer formwork stacking, which is not only cumbersome and consumes a lot of manpower and time, increasing construction costs, but also makes it difficult to effectively guarantee the connection stability between the multiple layers of formwork. Problems such as loosening and displacement are prone to occur, which in turn affect the quality of concrete pouring, resulting in defects such as uneven surface and uneven strength of the poured structure, posing potential risks to the quality of the project.

[0003] Besides the height limitations, existing concrete pouring formwork also has significant shortcomings in sealing performance and reinforcement structure. In terms of sealing, many formwork joints are poorly designed and lack effective sealing measures, which makes it easy for cement slurry to leak out from the joints during concrete pouring. This not only wastes cement materials and increases project costs, but also forms hardened concrete on the outside of the formwork, affecting its reuse. At the same time, the leaked cement slurry will also pollute the construction site environment, making subsequent cleanup work difficult.

[0004] In terms of structural reinforcement, some formwork uses relatively simple reinforcement methods, resulting in limited strength and difficulty in withstanding the large lateral pressure generated during concrete pouring. During pouring, the formwork is prone to deformation and bulging due to excessive lateral pressure, severely affecting the shape and dimensional accuracy of concrete components, reducing project quality, and potentially causing formwork damage, leading to safety accidents and threatening the lives of construction workers. Therefore, we propose a concrete pouring formwork for water conservancy and hydropower civil engineering construction to address these problems. Utility Model Content

[0005] To address the shortcomings of existing technologies, this utility model provides a concrete pouring formwork for water conservancy and hydropower civil engineering construction, thereby solving the problems mentioned in the background art.

[0006] This utility model provides the following technical solution: a concrete pouring formwork for water conservancy and hydropower civil construction, including a lower formwork and an extension formwork. There may be multiple lower formworks and extension formworks, and the extension formwork is set on the upper part of the lower formwork. A first sealing plate is welded to one side wall and the top of the lower formwork. A second sealing plate is welded to one side wall and the top of the extension formwork. A first reinforcing plate is welded to one side of the lower formwork. A support frame is hinged to the first reinforcing plate. An installation fixing plate is hinged to the side of the support frame away from the first reinforcing plate. A second reinforcing plate is welded to one side of the extension formwork. Connecting angle steel is provided on the top of the two uppermost extension formworks that are in a parallel state.

[0007] As a preferred technical solution of this utility model, a sealing groove matching the first sealing plate is provided on the other side wall of the lower template, and multiple connecting through holes are provided on both sides of the lower template.

[0008] As a preferred technical solution of this utility model, a sealing groove matching the second sealing plate is provided on the other side wall of the heightened template, and a sealing groove matching the first sealing plate is provided at the bottom of the heightened template. The first sealing plate and the second sealing plate have the same structure and size.

[0009] As a preferred embodiment of this utility model, the top of the lower template and the upper and lower parts of the heightening template are provided with mounting holes, and the lower template and the heightening template are connected by bolts and nuts.

[0010] As a preferred technical solution of this utility model, the connecting angle steel is provided with multiple mounting holes, and the connecting angle steel and the heightening template are connected by bolts and nuts. The heightening templates in parallel state are connected by multiple connecting angle steels through bolts and nuts.

[0011] As a preferred embodiment of this utility model, the mounting plate is provided with multiple mounting through holes, and the bottom of the lower template is inclined.

[0012] Compared with the prior art, the present invention has the following beneficial effects:

[0013] 1. This concrete pouring formwork for water conservancy and hydropower civil engineering construction can be configured with multiple lower formwork and extension formwork, with the extension formwork positioned on top of the lower formwork. Construction workers can flexibly combine the number of lower and extension formwork according to the actual needs of different projects for concrete pouring height. Unlike traditional formwork, which requires cumbersome modifications or customization due to fixed height, this greatly improves the versatility and applicability of the formwork, effectively saving construction costs and time.

[0014] 2. This concrete pouring formwork for water conservancy and hydropower civil engineering construction, through a first sealing plate welded to one side wall and top of the lower formwork, and a second sealing plate welded to one side wall and top of the raised formwork, precisely matches with the corresponding sealing grooves to form a tight sealing structure. During the concrete pouring process, it can effectively prevent cement slurry from leaking out from the formwork joints, avoid the waste of cement materials, reduce the problem of concrete hardening on the outside of the formwork due to leakage, ensure the repeated use of the formwork, reduce the difficulty of cleaning the construction site, and maintain the cleanliness of the construction environment.

[0015] 3. This concrete pouring formwork for water conservancy and hydropower civil engineering construction features a support frame hinged to a first reinforcing plate welded to one side of the lower formwork. Multiple through holes are provided on an installation fixing plate hinged to the other side of the support frame. This allows the installation fixing plate to be securely fixed to the construction site in various ways, providing reliable support for the lower formwork. A second reinforcing plate welded to one side of the raised formwork, along with connecting angle steels at the top of the two parallel raised formwork sections, are connected by bolts and nuts. This enhances the connection strength and overall stability between the raised formwork sections, enabling it to withstand the significant lateral pressure generated during concrete pouring. It effectively prevents formwork deformation and bulging, ensuring the shape and dimensional accuracy of the concrete components and improving project quality. Attached Figure Description

[0016] Figure 1 This is a three-dimensional structural diagram of the present invention;

[0017] Figure 2 This is a schematic diagram of the back structure of the heightened template of this utility model;

[0018] Figure 3 This is a schematic diagram of the back structure of the lower template of this utility model.

[0019] In the diagram: 1. Lower template; 101. First reinforcing plate; 102. First sealing plate; 2. Heightening template; 201. Second reinforcing plate; 202. Second sealing plate; 3. Connecting angle steel; 4. Support frame; 401. Mounting and fixing plate. Detailed Implementation

[0020] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0021] Example 1: Please refer to Figure 1 , Figure 2 and Figure 3A concrete pouring formwork for water conservancy and hydropower civil engineering construction includes a lower formwork 1 and a raised formwork 2. First, the number of lower formwork 1 and raised formwork 2 is determined according to the required concrete pouring height. The lower formwork 1 is placed in a predetermined position. Since the bottom of the lower formwork 1 is inclined, it further enhances the stability of the poured concrete. A support frame 4 is hinged to a first reinforcing plate 101 welded to one side of the lower formwork 1. Then, an installation fixing plate 401 is hinged to the side of the support frame 4 away from the first reinforcing plate 101. Through multiple installation through holes on the installation fixing plate 401, anchor bolts or similar materials can be used to firmly fix the installation fixing plate 401 to the ground of the construction site, thus providing stable support for the lower formwork 1. Next, the raised formwork 2 is placed on top of the lower formwork 1, so that the first sealing plate 101 welded to the top of the lower formwork 1... 2. Insert the first sealing plate 102 into the sealing groove at the bottom of the raised template 2, which matches the first sealing plate 102. Simultaneously, insert the second sealing plate 202 welded to one side wall of the raised template 2 into the sealing groove at the other side wall of the adjacent raised template 2, which matches the second sealing plate 202, to achieve a sealed splicing between the templates. Then, using the mounting holes at the top of the lower template 1 and the upper and lower parts of the raised template 2, use bolts and nuts to tightly connect the lower template 1 and the raised template 2. For the two uppermost raised templates 2 that are parallel, place connecting angle steel 3 on their tops. Use bolts and nuts to connect and fix the connecting angle steel 3 to the raised template 2 using multiple mounting holes on the connecting angle steel 3. If necessary, multiple connecting angle steels 3 can also be connected between the parallel raised templates 2 using bolts and nuts to enhance the stability of the overall structure. After the template assembly is completed, concrete pouring can begin.

[0022] Example 2: Please refer to Figure 1 , Figure 2 and Figure 3In another concrete pouring scenario of water conservancy and hydropower civil engineering construction, the same concrete pouring formwork is used. First, select an appropriate number of lower formwork 1 and extension formwork 2 according to the project requirements. Place the lower formwork 1 on the leveled and compacted construction site. Install the support frame 4 on the first reinforcing plate 101, and install the fixing plate 401 on the support frame 4. Use chemical anchors to fix the fixing plate 401 to the ground through the installation through holes to ensure the stability of the lower formwork 1. Alternatively, expansion bolts can be used to fix it to the pre-poured concrete foundation to make the lower formwork 1 stable. Then, the extension formwork is stacked one by one. 2. During the stacking process, ensure that the first sealing plate 102 of the lower template 1 is accurately inserted into the sealing groove at the bottom of the raised template 2, and that the second sealing plate 202 of the raised template 2 is inserted into the sealing groove on the side wall of the adjacent raised template 2 to prevent grout leakage during concrete pouring. Utilize the mounting holes on the lower template 1 and the raised template 2 to connect them with bolts and nuts. For the uppermost parallel raised template 2, install connecting angle steel 3. Through the mounting holes on the connecting angle steel 3, use bolts and nuts to tightly connect the connecting angle steel 3 to the raised template 2. As needed, arrange multiple connecting angle steels 3 between the raised templates 2 to enhance the template's resistance to lateral pressure. After the template installation is complete, concrete pouring is carried out. During the pouring process, the good sealing and reinforcement effect of the template effectively ensures the quality of the concrete pouring.

[0023] Implementation results: Multiple lower formwork 1 and raised formwork 2 can be set, and raised formwork 2 can be set on top of lower formwork 1. Construction workers can flexibly combine the number of lower formwork 1 and raised formwork 2 according to the actual needs of concrete pouring height for different projects. Unlike traditional formwork, which requires cumbersome modification or customization due to fixed height, this greatly improves the versatility and applicability of the formwork and effectively saves construction costs and time.

[0024] The first sealing plate 102 welded to one side wall and top of the lower template 1, and the second sealing plate 202 welded to one side wall and top of the raised template 2, precisely match the corresponding sealing grooves to form a tight sealing structure. During the concrete pouring process, this effectively prevents cement slurry from leaking out from the template joints, avoids waste of cement materials, reduces the problem of concrete hardening on the outside of the template due to leakage, ensures the template can be reused multiple times, reduces the difficulty of cleaning the construction site, and maintains a clean construction environment.

[0025] A support frame 4 is hinged to the first reinforcing plate 101 welded to one side of the lower template 1. The mounting plate 401, which is hinged to the other side of the support frame 4, has multiple mounting through holes. The mounting plate 401 can be firmly fixed to the construction site in various ways, providing reliable support for the lower template 1. The second reinforcing plate 201 welded to one side of the raised template 2 and the connecting angle steel 3 set at the top of the two uppermost raised templates 2 in a parallel state are connected by bolts and nuts, which enhances the connection strength and overall stability between the raised templates 2. It can withstand the large lateral pressure generated during concrete pouring, effectively prevent template deformation and bulging, ensure the shape and dimensional accuracy of the concrete components, and improve the quality of the project.

[0026] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the present invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A concrete pouring formwork for water conservancy and hydropower civil construction, comprising a lower formwork (1) and a raised formwork (2), characterized in that: There may be multiple lower templates (1) and heightening templates (2), and the heightening templates (2) are set on the upper part of the lower templates (1). A first sealing plate (102) is welded to one side wall and the top of the lower templates (1). A second sealing plate (202) is welded to one side wall and the top of the heightening templates (2). A first reinforcing plate (101) is welded to one side of the lower templates (1). A support frame (4) is hinged on the first reinforcing plate (101). An installation fixing plate (401) is hinged to the side of the support frame (4) away from the first reinforcing plate (101). A second reinforcing plate (201) is welded to one side of the heightening templates (2). Connecting angle steel (3) is set on the top of the two uppermost heightening templates (2) that are in a parallel state.

2. A concrete pouring formwork for water conservancy and hydropower civil construction according to claim 1, characterized in that: The other side wall of the lower template (1) is provided with a sealing groove that matches the first sealing plate (102), and both sides of the lower template (1) are provided with multiple connecting through holes.

3. A concrete pouring formwork for water conservancy and hydropower civil construction according to claim 1, characterized in that: The other side wall of the heightened template (2) is provided with a sealing groove that matches the second sealing plate (202), and the bottom of the heightened template (2) is provided with a sealing groove that matches the first sealing plate (102). The first sealing plate (102) and the second sealing plate (202) have the same structure and size.

4. A concrete pouring formwork for water conservancy and hydropower civil construction according to claim 1, characterized in that: The lower template (1) has mounting holes at its top and the upper and lower parts of the heightening template (2), and the lower template (1) and the heightening template (2) are connected by bolts and nuts.

5. A concrete pouring formwork for water conservancy and hydropower civil construction according to claim 1, characterized in that: The connecting angle steel (3) has multiple mounting holes, and the connecting angle steel (3) and the heightening template (2) are connected by bolts and nuts. The heightening templates (2) in parallel state are connected by multiple connecting angle steels (3) through bolts and nuts.

6. A concrete pouring formwork for water conservancy and hydropower civil construction according to claim 1, characterized in that: The mounting plate (401) has multiple mounting through holes, and the bottom of the lower template (1) is inclined.