A grouting machine with controllable grouting amount
Patent Information
- Application Number
- CN202522475420.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-21
- Publication Date
- 2026-10-09
- Estimated Expiration
- 2035-11-21
AI Technical Summary
[0003]当前市面上的注浆机在实际应用中仍存在明显不足:一方面,浆液中常夹杂砂石、结块等大颗粒杂质,易导致输浆管路堵塞,不仅中断注浆作业,还需耗费大量时间拆解管路清理,严重影响施工进度;另一方面,现有设备多缺乏便捷的滤网清理结构,即便部分设备设有过滤组件,清理时也需停机拆卸多个部件,操作繁琐且维护成本高;同时,传统注浆机的注浆量控制多依赖人工手动调节,精度较低,难以适配不同工程对注浆量的差异化需求,因此,针对以上现状,迫切需要开发一种通过电磁阀搭配流量控制阀可灵活控制注浆量;输浆管中的滤网可过滤大颗粒杂质,且通过储水箱、冲洗管及排渣口、排废孔的配合,能便捷清理滤网上的堵塞杂质,整体兼具注浆精准可控、使用便捷、维护方便的特点,提升了注浆作业的效率与质量的注浆量可控的注浆机,以克服当前实际应用中的不足,满足当前的需求
[0011]本实用新型的有益效果是:该注浆量可控的注浆机,使用时,将砂浆加入到储浆箱内,通过搅拌机构对砂浆进行搅拌,加注时,人将喷嘴对着需要浇筑的位置,然后,打开第一电磁阀和第四电磁阀,关闭第二电磁阀和第三电磁阀,启动高压输送泵从输浆管抽取储浆箱内的砂浆,通过滤网过滤掉砂浆内的大颗粒杂质,然后,砂浆经过出浆管、软管、喷嘴排出,通过流量控制阀可以对砂浆的流量进行控制;使用一段时间后对滤网进行清理,将堵头拧下,关闭第一电磁阀和第四电磁阀,打开第二电磁阀和第三电磁阀,启动高压输送泵从进水管抽取储水箱内自来水,自来水从冲洗管排出,由上至下对滤网进行冲洗,滤网上堵塞的杂质被水流冲下从排渣口排出并穿过排废孔落到地上。综上所述,本实用新型通过电磁阀搭配流量控制阀可灵活控制注浆量;输浆管中的滤网可过滤大颗粒杂质,且通过储水箱、冲洗管及排渣口、排废孔的配合,能便捷清理滤网上的堵塞杂质,整体兼具注浆精准可控、使用便捷、维护方便的特点,提升了注浆作业的效率与质量。
Smart Images

Figure CN224833733U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of grouting machine technology, and in particular to a grouting machine with controllable grouting volume. Background Technology
[0002] Grouting machines are key equipment used in construction, geological engineering and other fields to transport fluid materials such as mortar and cement slurry. They are widely used in foundation reinforcement, crack repair, tunnel lining and other operations. Their core function is to stably and quantitatively deliver grout to the target area, which directly affects the quality and efficiency of engineering construction.
[0003] Current grouting machines on the market still have significant shortcomings in practical applications: Firstly, the grout often contains large particles such as sand, gravel, and lumps, which can easily clog the grout delivery pipeline, interrupting the grouting operation and requiring a significant amount of time to disassemble and clean the pipeline, severely impacting the construction progress. Secondly, existing equipment often lacks convenient filter cleaning structures; even if some equipment has filter components, cleaning requires stopping the machine and disassembling multiple parts, making the operation cumbersome and maintenance costly. Furthermore, the grouting volume control of traditional grouting machines largely relies on manual adjustment, resulting in low precision and difficulty in... To adapt to the varying grouting volume requirements of different projects, there is an urgent need to develop a grouting machine that allows for flexible control of grouting volume through a combination of a solenoid valve and a flow control valve. This machine features a filter in the grout delivery pipe that can filter large particles of impurities, and the use of a water storage tank, flushing pipe, slag discharge port, and waste discharge hole allows for easy cleaning of clogged impurities on the filter. The machine combines precise and controllable grouting, ease of use, and convenient maintenance, thereby improving the efficiency and quality of grouting operations. This would overcome the shortcomings of current practical applications and meet current needs. Utility Model Content
[0004] The purpose of this invention is to provide a grouting machine with controllable grouting volume to solve the problems mentioned in the background art.
[0005] To achieve the above objectives, the present invention adopts the following technical solution:
[0006] A grouting machine with controllable grouting volume includes a trolley, a grout storage tank, a water storage tank, a mixing mechanism, a high-pressure delivery pump, a No. 1 tee connector, a No. 2 tee connector, a grout delivery pipe, a water inlet pipe, a flushing pipe, a grout outlet pipe, a hose, and a nozzle. The grout storage tank, water storage tank, and high-pressure delivery pump are all fixed to the trolley. The mixing mechanism is installed on the grout storage tank and inserted inside it. The inlet end of the high-pressure delivery pump is connected to a No. 1 tee connector, and the outlet end is connected to a No. 2 tee connector. The grout delivery pipe and water inlet pipe are respectively connected to the No. 1 tee connector. The lower end of the grout delivery pipe is connected to the grout storage tank. The water inlet pipe... The lower end of the slurry pipe is connected to the water storage tank. A filter screen is fixed inside the slurry pipe. A slag discharge port is provided directly below the filter screen at the bottom end of the slurry pipe. A plug for blocking the slag discharge port is detachably installed at the bottom end of the slurry pipe. A first solenoid valve is installed on the slurry pipe. A second solenoid valve is installed on the water inlet pipe. The flushing pipe and the slurry outlet pipe are respectively connected to a No. 2 three-way connector. The lower end of the flushing pipe is connected to the slurry pipe and faces the filter screen. A third solenoid valve is installed on the flushing pipe. A fourth solenoid valve and a flow control valve are installed on the slurry outlet pipe. The nozzle is connected to the slurry outlet pipe through a hose.
[0007] Preferably, a waste discharge hole is provided on the trolley directly below the slurry delivery pipe.
[0008] Preferably, the stirring mechanism includes a drive motor and a stirring shaft, wherein the drive motor is fixed on the slurry storage tank, and the output shaft of the drive motor is connected to the stirring shaft via a coupling.
[0009] Preferably, the plug is detachably fixed to the grout delivery pipe via a sealing pipe thread.
[0010] Preferably, a PLC controller is fixedly installed on the trolley, and the drive motor, high-pressure delivery pump, first solenoid valve, second solenoid valve, third solenoid valve, fourth solenoid valve and flow control valve are electrically connected to the PLC controller.
[0011] The beneficial effects of this utility model are as follows: When using this grouting machine with controllable grouting volume, mortar is added to the grout storage tank, and the mortar is stirred by the stirring mechanism. During grouting, the person points the nozzle at the position to be poured, then opens the first and fourth solenoid valves, closes the second and third solenoid valves, and starts the high-pressure delivery pump to draw mortar from the grout storage tank through the grout delivery pipe. Large particles of impurities in the mortar are filtered out through the filter screen. Then, the mortar is discharged through the grout outlet pipe, hose, and nozzle. The flow rate of the mortar can be controlled by the flow control valve. After a period of use, the filter screen is cleaned by unscrewing the plug, closing the first and fourth solenoid valves, opening the second and third solenoid valves, and starting the high-pressure delivery pump to draw tap water from the water inlet pipe. The tap water is discharged from the flushing pipe and flushes the filter screen from top to bottom. The impurities clogging the filter screen are washed down by the water flow and discharged from the slag outlet and fall to the ground through the waste discharge hole. In summary, this utility model allows for flexible control of the grouting volume through a combination of a solenoid valve and a flow control valve; the filter screen in the grout delivery pipe can filter out large particles of impurities, and the combination of a water storage tank, flushing pipe, slag discharge port, and waste discharge hole can easily clean the clogging impurities on the filter screen. Overall, it features precise and controllable grouting, convenient use, and easy maintenance, thus improving the efficiency and quality of grouting operations. Attached Figure Description
[0012] Figure 1 This is a schematic diagram of the three-dimensional structure of the present invention. Figure 1 .
[0013] Figure 2 This is a schematic diagram of the three-dimensional structure of the present invention. Figure 2 .
[0014] Figure 3 This is an internal cross-sectional view of the slurry storage tank of this utility model.
[0015] Figure 4 This is a partial structural schematic diagram of the present invention.
[0016] Figure 5 This is an internal view of the slurry delivery pipe in this utility model.
[0017] Figure 6 This utility model Figure 5 A diagram showing the open state.
[0018] Legend:
[0019] 1. Trolley; 101. Waste discharge port; 2. PLC controller; 3. Slurry storage tank; 4. Water storage tank; 5. Mixing mechanism; 501. Drive motor; 502. Mixing shaft; 6. High-pressure delivery pump; 7. No. 1 tee connector; 8. No. 2 tee connector; 9. Slurry delivery pipe; 901. First solenoid valve; 902. Filter screen; 903. Plug; 904. Slag discharge port; 10. Water inlet pipe; 1001. Second solenoid valve; 11. Flushing pipe; 1101. Third solenoid valve; 12. Slurry outlet pipe; 1201. Fourth solenoid valve; 1202. Flow control valve; 13. Hose; 14. Nozzle. Detailed Implementation
[0020] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of the present utility model.
[0021] Specific implementation examples are given below.
[0022] See Figures 1-6In this embodiment of the utility model, a grouting machine with controllable grouting volume includes a trolley 1, a grout storage tank 3, a water storage tank 4, a mixing mechanism 5, a high-pressure delivery pump 6, a No. 1 tee connector 7, a No. 2 tee connector 8, a grout delivery pipe 9, a water inlet pipe 10, a flushing pipe 11, a grout outlet pipe 12, a flexible hose 13, and a nozzle 14. The grout storage tank 3, the water storage tank 4, and the high-pressure delivery pump 6 are all fixed on the trolley 1. The grout storage tank 3 is used to store mortar, and the water storage tank 4 is used to store tap water. The mixing mechanism 5 is installed on the grout storage tank 3 and inserted into it. The mixing mechanism 5 is used to mix the mortar to prevent it from settling. The inlet end of the high-pressure delivery pump 6 is connected to the No. 1 tee connector 7, and the outlet end is connected to the No. 2 tee connector 8. The grout delivery pipe 9 and the water inlet pipe 10 are respectively connected to the No. 1 tee connector 7. The lower end of the grout delivery pipe 9 is connected to the grout storage tank 3, and the lower end of the water inlet pipe 10 is connected to the water storage tank 4. A filter screen 902 is fixed inside the mortar and is used to filter large particles of impurities. A slag discharge port 904 is provided at the bottom of the grout delivery pipe 9 directly below the filter screen 902. A plug 903 is detachably installed at the bottom of the grout delivery pipe 9 to block the slag discharge port 904. The plug 903 is detachably fixed to the grout delivery pipe 9 through a sealing pipe thread. A first solenoid valve 901 is installed on the grout delivery pipe 9, and a second solenoid valve 1001 is installed on the water inlet pipe 10. The flushing pipe 11 and the grout outlet pipe 12 are respectively connected to the No. 2 three-way connector 8. The lower end of the flushing pipe 11 is connected to the grout delivery pipe 9 and faces the filter screen 902. A third solenoid valve 1101 is installed on the flushing pipe 11, and a fourth solenoid valve 1201 and a flow control valve 1202 are installed on the grout outlet pipe 12. The flow control valve 1202 controls the output flow rate of the grout. The nozzle 14 is connected to the grout outlet pipe 12 through a hose 13.
[0023] A waste discharge hole 101 is provided directly below the slurry pipe 9 on the trolley 1. Impurities discharged from the slag discharge port 904 pass through the waste discharge hole 101 and fall to the ground.
[0024] The mixing mechanism 5 includes a drive motor 501 and a mixing shaft 502. The drive motor 501 is fixed on the slurry storage tank 3. The output shaft of the drive motor 501 is connected to the mixing shaft 502 through a coupling. In use, the drive motor 501 drives the mixing shaft 502 to rotate, and the mixing shaft 502 mixes the mortar.
[0025] A PLC controller 2 is fixedly installed on the trolley 1. The PLC controller 2 is equipped with a display screen and operation buttons. The drive motor 501, high-pressure delivery pump 6, first solenoid valve 901, second solenoid valve 1001, third solenoid valve 1101, fourth solenoid valve 1201 and flow control valve 1202 are electrically connected to the PLC controller 2 and are controlled by the PLC controller 2.
[0026] Working principle: This grouting machine with controllable grouting volume operates by adding mortar to the storage tank 3 and agitating it using the mixing mechanism 5. During grouting, the operator points the nozzle 14 towards the desired location, then opens the first solenoid valve 901 and the fourth solenoid valve 1201, closes the second solenoid valve 1001 and the third solenoid valve 1101, and starts the high-pressure delivery pump 6 to draw mortar from the storage tank 3 through the delivery pipe 9. Large particles of impurities in the mortar are filtered out by the filter screen 902. The mortar is then discharged through the outlet pipe 12, hose 13, and nozzle 14. The flow control valve 1202 can control the flow rate of mortar. After a period of use, the filter screen 902 is cleaned by unscrewing the plug 903, closing the first solenoid valve 901 and the fourth solenoid valve 1201, opening the second solenoid valve 1001 and the third solenoid valve 1101, and starting the high-pressure delivery pump 6 to draw tap water from the water inlet pipe 10 into the water storage tank 4. The tap water is discharged from the flushing pipe 11 and flushes the filter screen 902 from top to bottom. The impurities that clog the filter screen 902 are washed down by the water flow and discharged from the slag discharge port 904 and fall to the ground through the waste discharge hole 101.
[0027] Furthermore, it should be noted that, in the description of this utility model, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "joining" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this utility model according to the specific circumstances.
[0028] The above description is only a preferred embodiment of the present utility model, but the protection scope of the present utility model is not limited thereto. Any equivalent substitutions or changes made by those skilled in the art within the technical scope disclosed in the present utility model, based on the technical solution and the inventive concept of the present utility model, should be included within the protection scope of the present utility model.
Claims
1. A grouting machine with controllable grouting volume, characterized in that, The system includes a trolley (1), a slurry storage tank (3), a water storage tank (4), a stirring mechanism (5), a high-pressure delivery pump (6), a No. 1 tee connector (7), a No. 2 tee connector (8), a slurry delivery pipe (9), a water inlet pipe (10), a flushing pipe (11), a slurry outlet pipe (12), a hose (13), and a nozzle (14). The slurry storage tank (3), the water storage tank (4), and the high-pressure delivery pump (6) are all fixed on the trolley (1). The stirring mechanism (5) is installed on the slurry storage tank (3) and inserted into it. The inlet end of the high-pressure delivery pump (6) is connected to the No. 1 tee connector (7), and the outlet end is connected to the No. 2 tee connector (8). The slurry delivery pipe (9) and the water inlet pipe (10) are respectively connected to the No. 1 tee connector (7). The lower end of the slurry delivery pipe (9) is connected to the slurry storage tank (3), and the lower end of the water inlet pipe (10) is connected to the water storage tank (4). (9) A filter screen (902) is fixed inside. A slag discharge port (904) is provided at the bottom of the slurry pipe (9) directly below the filter screen (902). A plug (903) for blocking the slag discharge port (904) is detachably installed at the bottom of the slurry pipe (9). A first solenoid valve (901) is installed on the slurry pipe (9). A second solenoid valve (1001) is installed on the water inlet pipe (10). The flushing pipe (11) and the slurry outlet pipe (12) are respectively connected to the No. 2 three-way connector (8). The lower end of the flushing pipe (11) is connected to the slurry pipe (9) and faces the filter screen (902). A third solenoid valve (1101) is installed on the flushing pipe (11). A fourth solenoid valve (1201) and a flow control valve (1202) are installed on the slurry outlet pipe (12). The nozzle (14) is connected to the slurry outlet pipe (12) through a hose (13).
2. The grouting machine with controllable grouting volume according to claim 1, characterized in that, A waste discharge hole (101) is provided on the trolley (1) directly below the slurry pipe (9).
3. The grouting machine with controllable grouting volume according to claim 1, characterized in that, The stirring mechanism (5) includes a drive motor (501) and a stirring shaft (502). The drive motor (501) is fixed on the slurry tank (3), and the output shaft of the drive motor (501) is connected to the stirring shaft (502) through a coupling.
4. The grouting machine with controllable grouting volume according to claim 1, characterized in that, The plug (903) is detachably fixed to the grout delivery pipe (9) via a sealing pipe thread.
5. The grouting machine with controllable grouting volume according to claim 3, characterized in that, A PLC controller (2) is fixedly installed on the trolley (1). The drive motor (501), high-pressure delivery pump (6), first solenoid valve (901), second solenoid valve (1001), third solenoid valve (1101), fourth solenoid valve (1201) and flow control valve (1202) are electrically connected to the PLC controller (2).