Technical Problem

[0005]上述检索专利人工将槽钢移动至施打工作面并定位准确,人工成本较高,安全风险大,并且采用桩机在槽钢顶部施加压力,将槽钢压入土体,施工速度减慢,施工效率低下,故而存在一定局限性

Benefits of technology

[0013]其一:本实用新型采用自动化锁定装置,能够自动抱死连接杆两侧预留凹槽,与槽钢形成连接整体,打桩时机械呈规律性小幅度上下震动使地下土体逐渐松动直至可直接将槽钢打入土体,同时亦可提高拔桩效率。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224849384U_ABST
    Figure CN224849384U_ABST
Patent Text Reader

Abstract

The utility model relates to a construction device belongs to civil engineering and municipal public works field, concretely is a new -type channel steel construction device, including automatic locking device and pile driver head, still include, connecting rod, the connecting rod fixed mounting is in automatic locking device, the utility model reached the effect that improved channel steel construction efficiency, greatly reduced the safe risk, solved the existing manual channel steel and moved to the accurate location of the channel steel and the construction face, the manual cost is higher, the safe risk is big, and the problem that the construction speed slows down, the construction efficiency is low is solved to the pile machine and is pressed into the soil body to the channel steel top and exerts the pressure, constructs the efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the technical field of civil engineering and municipal public works, and in particular to a novel channel steel construction device. Background Technology

[0002] Channel steel construction equipment is mainly used in foundation pit engineering and underground concealed engineering for construction operations that use channel steel as the foundation pit support method. Specifically, it is applicable to the driving and extraction of channel steel piles.

[0003] A search revealed Chinese patent CN215483005U, which discloses a novel channel steel support structure. This structure comprises two symmetrically arranged channel steel frames connected by horizontal support rods. Each channel steel frame includes a first horizontal support rod, a second horizontal support rod, a first vertical support rod, and a second vertical support rod. Both the first and second vertical support rods have adjustable latches at their bottoms. The top of the first vertical support rod is fixedly connected to one end of the first horizontal support rod, and the other end of the first horizontal support rod is connected to the top of the second vertical support rod. The second horizontal support rod is located above the latches, parallel to the first horizontal support rod, with one end fixedly connected to the first vertical support rod and the other end fixedly connected to the second vertical support rod. The adjustable latches on the vertical support frame allow for adjustment of the support structure according to the working depth, meeting the high-precision elevation and positioning requirements of construction projects, minimizing disturbance to the rock strata, and maximizing construction safety in confined working environments.

[0004] Based on the above search and existing technology, the findings were as follows:

[0005] The aforementioned patents involve manually moving the channel steel to the working face and accurately positioning it, which is labor-intensive, poses significant safety risks, and uses a pile driver to apply pressure to the top of the channel steel to press it into the soil, which slows down the construction speed and reduces construction efficiency. Therefore, these patents have certain limitations. Utility Model Content

[0006] To address the aforementioned technical problems, this utility model proposes a novel channel steel construction device that improves channel steel construction efficiency and significantly reduces safety risks.

[0007] The technical solution to achieve the purpose of this utility model is: a new type of channel steel construction device, including an automatic locking device and a pile driver head, and also including;

[0008] A connecting rod, which is fixedly mounted on an automated locking device.

[0009] Preferably, the connecting rod has a groove in the middle, and both sides of the automatic locking device and the pile driver head are provided with a set of automatic pulleys.

[0010] Preferably, a channel steel is fixedly installed inside the groove, and a steel wire rope is sleeved between each group of automated pulleys.

[0011] Preferably, the pile driver head is provided with a drive pulley, and the connection between the automatic locking device and the connecting rod is provided with a rubber ring.

[0012] Compared with existing technologies, the significant advantages of this invention are:

[0013] Firstly, this utility model adopts an automated locking device that can automatically lock the pre-reserved grooves on both sides of the connecting rod to form a connection whole with the channel steel. During pile driving, the machine vibrates up and down in a regular manner to gradually loosen the underground soil until the channel steel can be directly driven into the soil, which can also improve the efficiency of pile extraction.

[0014] Secondly, due to the existence of the self-locking device, the channel steel hardly shakes during the installation and removal process, which improves the stability and safety factor. After removal, the automatic pulley is activated to slowly lower the channel steel to the designated position for standardized stacking. The construction process is stable and efficient, and it is convenient for site removal or reuse.

[0015] This method solves the problems of high labor costs and significant safety risks associated with manually moving and accurately positioning the channel steel to the working face, as well as the slow construction speed and low construction efficiency caused by using a pile driver to apply pressure to the top of the channel steel and press it into the soil. Attached Figure Description

[0016] The present invention will be further explained below with reference to the accompanying drawings and embodiments:

[0017] Figure 1 This is a front view structural diagram provided by this utility model;

[0018] Figure 2 This is a side view structural diagram provided by this utility model.

[0019] Explanation of reference numerals in the attached figures:

[0020] 1. Automated locking device; 2. Connecting rod; 201. Groove; 3. Pile driver head; 4. Automated pulley; 5. Rubber ring; 6. Drive pulley; 7. Channel steel; 8. Steel wire rope. Detailed Implementation

[0021] The present invention will now be described in detail, and the technical solutions in the embodiments of the present invention will be clearly and completely described. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the protection scope of the present invention.

[0022] This utility model provides a novel channel steel construction device through improvements. The technical solution of this utility model is as follows:

[0023] like Figures 1-2 As shown, a new type of channel steel construction device includes an automated locking device 1 and a pile driver head 3. During pile driving, the machine vibrates regularly with small amplitudes up and down to gradually loosen the underground soil until the channel steel 7 can be directly driven into the soil. At the same time, it can also improve the efficiency of pile extraction. It also includes:

[0024] Connecting rod 2 is fixedly installed on automatic locking device 1. With the presence of the self-locking device, the channel steel 7 hardly shakes during the installation and removal process, which improves the safety factor.

[0025] Furthermore, a groove 201 is provided in the middle of the connecting rod 2, and a set of automatic pulleys 4 are provided on both sides of the automatic locking device 1 and the pile driver head 3. After being pulled out, the automatic pulleys 4 are activated, and the channel steel 7 can be slowly lowered to the designated position for standardized stacking, which is convenient for removal or reuse.

[0026] As a further embodiment of this utility model, a channel steel 7 is fixedly installed inside the groove 201, and a steel wire rope 8 is sleeved between each set of automated pulleys 4. Fixing the channel steel 7 in the groove 201 can reduce the dependence on manual labor, and no manual straightening is required during insertion, which greatly reduces the safety risks of construction.

[0027] Furthermore, a drive pulley 6 is provided on the pile driver head 3, and a rubber ring 5 is provided at the connection between the automatic locking device 1 and the connecting rod 2 to increase the friction at the connection and improve the safety level.

[0028] The specific working method is as follows: The automated locking device 1 with rubber ring 5 is connected to the automated pulley 4 fixed on the pile driver head 3 via a steel wire rope 8. The automated pulley 4 is driven by the drive pulley 6. The automated locking device 1 is connected to the channel steel 7 via a connecting rod 2 with groove 201 for driving and removing the channel steel 7. After installing the device according to the above steps, during use, workers only need to insert and remove the connecting rod 2 with groove 201 to install and remove the channel steel 7. After the channel steel 7 is installed, it is driven by the automated pulley 4. The automatic locking device 1 is tightly fixed to the pile driver head 3 by the drive pulley 6 and the wire rope 8. The vibration of the pile driver head 3 drives the channel steel 7 into the soil. Then the connecting rod 2 is removed, and the driving of the channel steel 7 is completed. When the channel steel 7 needs to be removed, the device is connected by the connecting rod 2. The vibration device of the pile driver head 3 is used to remove the channel steel 7. Then the drive pulley 6 drives the automatic pulley 4 to release the wire rope 8 and lay the channel steel 7 flat on the ground. Then the worker removes the connecting rod 2. Thus, one cycle of construction is completed.

[0029] The technical means disclosed in this utility model are not limited to those described above, but also include technical solutions composed of equivalent substitutions of the above technical features. Matters not covered in this utility model are common knowledge to those skilled in the art.

Claims

1. A novel channel steel construction device, comprising an automated locking device (1) and a pile driver head (3), characterized in that: Also includes; Connecting rod (2), the connecting rod (2) is fixedly installed on the automatic locking device (1), the connecting rod (2) has a groove (201) in the middle, and a set of automatic pulleys (4) are provided on both sides of the automatic locking device (1) and the pile driver head (3).

2. The novel channel steel construction device according to claim 1, characterized in that: A channel steel (7) is fixedly installed inside the groove (201), and a steel wire rope (8) is sleeved between each set of automated pulleys (4).

3. A novel channel steel construction device according to any one of claims 1-2, characterized in that: The pile driver head (3) is equipped with a drive pulley (6), and the connection part between the automatic locking device (1) and the connecting rod (2) is equipped with a rubber ring (5).