Shaft concrete pouring and separating device

CN224849865UActive Publication Date: 2026-10-13CHINA HUAYE GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522356728.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-06
Publication Date
2026-10-13
Estimated Expiration
2035-11-06

AI Technical Summary

Technical Problem

[0004]鉴于上述问题,本实用新型的目的是提供一种竖井混凝土浇筑分灰装置,以解决现有技术中,由于分灰器没有支撑结构,使用时需要通过钢丝绳悬吊在吊盘的立柱上,因此存在分灰器摇晃、遗撒、风险因素高等问题

Benefits of technology

[0019]从上面的技术方案可知,本实用新型提供的竖井混凝土浇筑分灰装置,通过在分灰主体结构上增设可调支撑机构,在使用时,只需根据现场的空间情况,调整第一支撑臂和第二支撑臂分别与固定在分灰槽底部的底座之间的铰接角度,便可对分灰槽形成可靠支撑,具有稳定性和灵活性;避免在井筒施工中混凝土输送时分灰器呈现的不稳定和易散落的情况,且通过第一支撑臂和第二支撑臂的结构设计,第一支撑臂和第二支撑臂的下端可固定在吊盘上,避免悬吊分灰槽带来的安全隐患,本实用新型能够有效解决现有分灰器没有支撑结构,使用时需要通过钢丝绳悬吊在吊盘的立柱上,所导致的分灰器摇晃、遗撒、风险因素高等问题。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224849865U_ABST
    Figure CN224849865U_ABST
Patent Text Reader

Abstract

The utility model provides a vertical shaft concrete pouring divides ash device belongs to vertical shaft construction technical field, including divides ash main part structure and adjustable support mechanism, divides ash main part structure includes divides ash groove and slide ash pipe, is provided with the slide ash hole in the bottom of divides ash groove, and the upper end of slide ash pipe is connected with slide ash hole, adjustable support mechanism includes the base of fixedly being established in divides ash groove bottom respectively, first support arm and second support arm are hinged with the both opposite side ends of base respectively. Utilize the utility model, can solve the prior art, because the ash divider does not have the supporting structure, needs through the steel wire rope to hang in the column of the hanging tray when using, therefore exists the problem such as ash divider shaking, scattering, risk factor and so on.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of shaft construction technology, and more specifically, to a concrete pouring and ash distribution device for shafts. Background Technology

[0002] The mining industry is gradually shifting from surface to underground operations and from shallow to deep construction, with vertical shaft construction exceeding 1,000 meters becoming the mainstream. For ultra-deep vertical shafts, in order to meet the requirements of rapid and safe concrete pouring, each form of concrete needs to be lowered from the shaft opening through a mortar hopper to the lower flared end of a three-layer hoisting platform. Then, the concrete is transported through the bottom of the mortar hopper to the mortar distributor, and finally, the concrete is delivered to the pouring position via a steel wire hose at the bottom of the mortar distributor.

[0003] The ash separator currently in use lacks a supporting structure. During use, the ash separator needs to be suspended from the column of the hanging platform by steel wire rope. When discharging ash, the ash separator often shakes and spills, which brings certain risks and instabilities to the concrete pouring construction. Utility Model Content

[0004] In view of the above problems, the purpose of this utility model is to provide a vertical shaft concrete pouring ash distribution device to solve the problems of swaying, spillage and high risk factors in the existing technology, since the ash distributor has no supporting structure and needs to be suspended from the column of the hanging plate by steel wire rope during use.

[0005] The vertical shaft concrete pouring and ash-distributing device provided by this utility model includes an ash-distributing main structure and an adjustable support mechanism; wherein...

[0006] The ash-distributing main structure includes an ash-distributing trough and an ash-discharging pipe; an ash-discharging hole is provided at the bottom of the ash-distributing trough, and the upper end of the ash-discharging pipe is connected to the ash-discharging hole.

[0007] The adjustable support mechanism includes a base fixed to the bottom of the ash distribution trough, a first support arm and a second support arm hinged to the two opposite ends of the base.

[0008] Furthermore, a preferred structure is that the ash distribution trough is a trapezoidal structure with an opening cross-section larger than the bottom cross-section, and is formed by welding steel plates.

[0009] Furthermore, a preferred configuration is that a short connecting pipe is fixedly installed at the ash chute; the upper end of the ash chute is connected to the lower end of the short connecting pipe via a detachable connector.

[0010] Furthermore, in a preferred configuration, the upper end of the short connecting pipe is welded to the ash chute.

[0011] Furthermore, a preferred configuration is that the detachable connector is a flange.

[0012] Furthermore, in a preferred configuration, the number of ash chute holes is at least two, and each ash chute hole is connected to an ash chute pipe.

[0013] In addition, a preferred structure is that the base is welded and fixed to the bottom of the ash distribution trough, and a ash chute through hole is provided on the base corresponding to the ash chute hole.

[0014] Furthermore, a preferred configuration is that the first support arm is hinged to the end of the base via a first shaft mechanism; and / or, the second support arm is hinged to the end of the base via a second shaft mechanism.

[0015] Furthermore, a preferred structure is that the first shaft mechanism includes a first bearing seat disposed on both sides of the upper end of the first support arm, a first bearing disposed inside the first bearing seat, a first hinge lug disposed at the end of the base, and a first hinge shaft passing through the first hinge lug.

[0016] The two ends of the first hinge shaft are respectively located inside the first bearing on both sides of the upper end of the first support arm.

[0017] Furthermore, a preferred structure is that the second shaft mechanism includes a second bearing seat disposed on both sides of the upper end of the second support arm, a second bearing disposed inside the second bearing seat, a second hinge lug disposed at the end of the base, and a second hinge shaft passing through the second hinge lug.

[0018] The two ends of the second hinge shaft are respectively located inside the first bearing on both sides of the upper end of the second support arm.

[0019] As can be seen from the above technical solution, the vertical shaft concrete pouring ash-distributing device provided by this utility model, by adding an adjustable support mechanism to the main structure of the ash-distributing device, can reliably support the ash-distributing trough by simply adjusting the hinge angle between the first and second support arms and the base fixed at the bottom of the ash-distributing trough according to the space conditions on site. It has stability and flexibility; it avoids the instability and easy scattering of the ash-distributing device when the concrete is transported during shaft construction. Moreover, through the structural design of the first and second support arms, the lower ends of the first and second support arms can be fixed on the hanging platform, avoiding the safety hazards caused by suspending the ash-distributing trough. This utility model can effectively solve the problems of existing ash-distributing devices that do not have a support structure and need to be suspended on the column of the hanging platform by steel wire rope during use, resulting in swaying, spillage, and high risk factors. Attached Figure Description

[0020] Other objects and results of this invention will become clearer and easier to understand with reference to the following description taken in conjunction with the accompanying drawings, and with a more comprehensive understanding of the invention.

[0021] Figure 1 This is a schematic diagram of the elevation structure of the vertical shaft concrete pouring and ash distribution device according to an embodiment of the present utility model;

[0022] Figure 2 This is a top view of the concrete pouring and ash distribution device for vertical shafts according to an embodiment of the present invention.

[0023] Figure 3 This is a schematic diagram of the structure of the vertical shaft concrete pouring and ash distribution device in use according to an embodiment of the present utility model;

[0024] Figure 4 This is a three-dimensional structural diagram of the concrete pouring and ash distribution device for vertical shafts according to an embodiment of the present utility model.

[0025] In the attached drawings, 11-ash distribution trough, 111-ash chute, 112-short connecting pipe, 12-ash chute, 13-flange, 21-base, 22-first support arm, 221-first pedestrian structure, 23-second support arm, 231-second pedestrian structure, 24-first shaft mechanism, 25-second shaft mechanism, 3-hanging plate, 31-column, 4-lifting lug.

[0026] In all the accompanying drawings, the same reference numerals indicate similar or corresponding features or functions. Detailed Implementation

[0027] In response to the aforementioned issues, in the existing technology, since the ash separator lacks a supporting structure and needs to be suspended from the column of the hanging platform by steel wire rope during use, there are problems such as swaying, spillage, and high risk factors. Therefore, a vertical shaft concrete pouring ash separator device is proposed.

[0028] The specific embodiments of this utility model will be described in detail below with reference to the accompanying drawings.

[0029] To illustrate the concrete pouring and ash distribution device for vertical shafts provided by this utility model Figure 1 The elevation structure of the vertical shaft concrete pouring and ash distribution device according to an embodiment of the present invention is shown; Figure 2 The top view of the vertical shaft concrete pouring and ash distribution device according to an embodiment of the present invention is shown; Figure 3 The structure of the vertical shaft concrete pouring and ash distribution device according to an embodiment of the present invention is shown in use; Figure 4 The three-dimensional structure of the concrete pouring and ash distribution device for vertical shafts according to an embodiment of the present invention is shown.

[0030] like Figures 1 to 4 As shown in the figure, the vertical shaft concrete pouring and mortar distribution device provided by this utility model includes a mortar distribution main structure and an adjustable support mechanism; wherein,

[0031] The main structure of the ash distribution system includes an ash distribution trough 11 and an ash chute 12; an ash chute hole 111 is provided at the bottom of the ash distribution trough 11, and the upper end of the ash chute 12 is connected to the ash chute hole 111.

[0032] The adjustable support mechanism includes a base 21 fixed to the bottom of the ash distribution trough 11, a first support arm 22 and a second support arm 23 respectively hinged to the two opposite ends of the base 21.

[0033] By adding an adjustable support mechanism to the main structure of the ash separator, during use, it is only necessary to adjust the hinge angle between the first support arm 22 and the second support arm 23 and the base 21 fixed at the bottom of the ash separator 11 according to the space conditions on site. This provides reliable support for the ash separator 11, ensuring stability and flexibility. It avoids the instability and easy scattering of the ash separator during concrete transportation in well construction. Furthermore, through the structural design of the first support arm 22 and the second support arm 23, the lower ends of the first support arm 22 and the second support arm 23 can be fixed on the hanging plate 3, avoiding the safety hazards caused by suspending the ash separator 11. This utility model can effectively solve the problems of existing ash separators lacking a support structure and needing to be suspended from the column 31 of the hanging plate by steel wire rope during use, which leads to swaying, spillage, and high risk factors.

[0034] As a preferred embodiment of this utility model, the ash distribution trough 11 is a trapezoidal structure with an opening cross-section larger than the bottom cross-section, and is formed by welding steel plates.

[0035] Specifically, the ash distribution trough 11 is a trapezoidal structure with an opening cross-section larger than the bottom cross-section, which facilitates the addition of concrete into its interior. Of course, the shape of the ash distribution trough 11 is not limited to this, and it can be designed into other shapes according to actual needs. This utility model does not make any special limitation on this. The ash distribution trough 11 is preferably made of δ4mm steel plate by machining and welding.

[0036] As a preferred embodiment of this utility model, a short pipe 112 is fixedly provided at the ash discharge hole 111; the upper end of the ash discharge pipe 12 is connected to the lower end of the short pipe 112 by a detachable connector.

[0037] Specifically, by setting a short connecting pipe 112, it is convenient to detachably connect the ash chute 12 and the ash chute hole 111, making the overall structure easier to disassemble and place. Of course, it can also be designed so that the ash chute 12 is directly fixedly connected to the ash chute hole 111. This utility model does not make any special limitation on this.

[0038] As a preferred embodiment of this utility model, the upper end of the short pipe 112 is welded to the ash chute 111.

[0039] Specifically, the upper end of the short pipe 112 is preferably welded to the ash discharge hole 111. Alternatively, when designing the ash distribution trough 11, the short pipe 112 and the ash distribution trough 11 can be directly machined into one piece. This utility model does not impose any particular limitation on this.

[0040] As a preferred embodiment of this utility model, the detachable connector is flange 13.

[0041] It should be noted that the detachable connector is preferably, but not limited to, the flange 13, and may also be replaced by a clamp or other structure. This utility model does not make any special limitation on this.

[0042] As a preferred embodiment of this utility model, the number of ash discharge holes 111 is at least two, and each ash discharge hole 111 is connected to an ash discharge pipe 12.

[0043] It should be noted that the number of ash chute holes 111 can be set according to actual needs, and can be one, two, three, etc. Setting it to at least two can improve the pouring efficiency. This utility model does not make any special limitation on this.

[0044] As a preferred embodiment of this utility model, the base 21 is welded and fixed to the bottom of the ash distribution trough 11, and a through hole for the ash discharge pipe 12 is provided on the base 21 corresponding to the ash discharge hole 111.

[0045] Specifically, the base 21 is preferably made of double channel steel, with a clearance hole for the ash chute 12 at its bottom to avoid affecting the use of the overall ash distribution structure.

[0046] As a preferred embodiment of the present invention, the first support arm 22 is hinged to the end of the base 21 via the first shaft mechanism 24; and / or, the second support wall 23 is hinged to the end of the base 21 via the second shaft mechanism 25.

[0047] It should be noted that the first support arm 22 and the second support wall 23 are preferably, but not limited to, hinged to the end of the base 21 through a shaft mechanism. Other hinge mechanisms may also be used instead, and this utility model does not make any special limitation on this.

[0048] As a preferred embodiment of the present invention, the first shaft mechanism 24 includes a first bearing seat disposed on both sides of the upper end of the first support arm 22, a first bearing disposed inside the first bearing seat, a first hinge lug disposed at the end of the base 21, and a first hinge shaft passing through the first hinge lug.

[0049] The two ends of the first hinge shaft are respectively located inside the first bearing on both sides of the upper end of the first support arm 22.

[0050] As a preferred embodiment of the present invention, the second shaft mechanism 25 includes a second bearing seat disposed on both sides of the upper end of the second support arm 23, a second bearing disposed inside the second bearing seat, a second hinge lug disposed at the end of the base 21, and a second hinge shaft passing through the second hinge lug.

[0051] The two ends of the second hinge shaft are respectively located inside the first bearing on both sides of the upper end of the second support arm 23.

[0052] As a preferred embodiment of the present invention, a first pedestrian structure 221 is provided on the outer surface of the first support arm 22; and a second pedestrian structure 231 is provided on the outer surface of the second support arm 23.

[0053] Specifically, the first pedestrian structure 221 and the second pedestrian structure 231 can be stepped structures to facilitate construction workers to carry out construction on them.

[0054] As a preferred embodiment of this utility model, in order to facilitate the hoisting and installation of the entire device, a lifting lug 4 is provided on the top of the ash distribution trough 11.

[0055] As can be seen from the above specific embodiments, the vertical shaft concrete pouring ash distribution device provided by this utility model, by adding an adjustable support mechanism to the main structure of the ash distribution device, can reliably support the ash distribution trough by simply adjusting the hinge angle between the first and second support arms and the base fixed at the bottom of the ash distribution trough according to the space conditions on site. It has stability and flexibility; it avoids the instability and easy scattering of the ash distributor during concrete transportation in shaft construction. Moreover, through the structural design of the first and second support arms, the lower ends of the first and second support arms can be fixed on the hanging platform, avoiding the safety hazards caused by suspending the ash distribution trough. This utility model can effectively solve the problems of existing ash distributors that do not have a support structure and need to be suspended from the column of the hanging platform by steel wire rope during use, resulting in swaying, spillage, and high risk factors.

[0056] The concrete pouring and ash separating device for vertical shafts according to the present invention has been described above by way of example with reference to the accompanying drawings. However, those skilled in the art should understand that various modifications can be made to the concrete pouring and ash separating device for vertical shafts according to the present invention without departing from the scope of the present invention. Therefore, the scope of protection of the present invention should be determined by the contents of the appended claims.

Claims

1. A vertical shaft concrete pouring and mortar distribution device, characterized in that, This includes the main ash-distributing structure and an adjustable support mechanism; among which, The ash-distributing main structure includes an ash-distributing trough and an ash-discharging pipe; an ash-discharging hole is provided at the bottom of the ash-distributing trough, and the upper end of the ash-discharging pipe is connected to the ash-discharging hole. The adjustable support mechanism includes a base fixed to the bottom of the ash distribution trough, a first support arm and a second support arm hinged to the two opposite ends of the base.

2. The vertical shaft concrete pouring and mortar distribution device according to claim 1, characterized in that, The ash distribution trough is a trapezoidal structure with an opening cross-section larger than the bottom cross-section, and is formed by welding steel plates.

3. The vertical shaft concrete pouring and mortar distribution device according to claim 1, characterized in that, A short connecting pipe is fixedly installed at the ash chute; The upper end of the ash chute is connected to the lower end of the short pipe via a detachable connector.

4. The vertical shaft concrete pouring and mortar distribution device according to claim 3, characterized in that, The upper end of the short pipe is welded to the ash chute.

5. The vertical shaft concrete pouring and mortar distribution device according to claim 3, characterized in that, The detachable connector is a flange.

6. The vertical shaft concrete pouring and mortar distribution device according to claim 1, characterized in that, The number of ash chute holes is at least two, and each ash chute hole is connected to an ash chute pipe.

7. The vertical shaft concrete pouring and mortar distribution device according to claim 1, characterized in that, The base is welded and fixed to the bottom of the ash distribution trough, and a ash chute through hole is provided on the base corresponding to the ash chute hole.

8. The vertical shaft concrete pouring and mortar distribution device according to claim 1, characterized in that, The first support arm is hinged to the end of the base via a first shaft mechanism; and / or, The second support arm is hinged to the end of the base via a second shaft mechanism.

9. The vertical shaft concrete pouring and mortar distribution device according to claim 8, characterized in that, The first shaft mechanism includes a first bearing seat disposed on both sides of the upper end of the first support arm, a first bearing disposed inside the first bearing seat, a first hinge lug disposed at the end of the base, and a first hinge shaft passing through the first hinge lug. The two ends of the first hinge shaft are respectively located inside the first bearing on both sides of the upper end of the first support arm.

10. The vertical shaft concrete pouring and mortar distribution device according to claim 8, characterized in that, The second shaft mechanism includes a second bearing seat disposed on both sides of the upper end of the second support arm, a second bearing disposed inside the second bearing seat, a second hinge lug disposed at the end of the base, and a second hinge shaft passing through the second hinge lug; The two ends of the second hinge shaft are respectively located inside the first bearing on both sides of the upper end of the second support arm.