A boiler steel structure installation base

CN224850556UActive Publication Date: 2026-10-13QINGDAO SANLIAN METAL STRUCTURE
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522505916.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-26
Publication Date
2026-10-13
Estimated Expiration
2035-11-26

Smart Images

  • Figure CN224850556U_ABST
    Figure CN224850556U_ABST
Patent Text Reader

Abstract

The application relates to the technical field of boiler steel structure, and provides a boiler steel structure mounting base, which comprises a foundation base, a plurality of vertical steel bars are fixedly arranged at the upper end of a conical supporting layer, the vertical steel bars are fixedly connected through horizontal connecting frames, an L-shaped connecting column is fixedly arranged on a top plate, the lower end of the L-shaped connecting column is inserted into the gap between the vertical steel bars, a threaded part is arranged at the upper end of the L-shaped connecting column, a leveling nut and a fixing nut are threadedly arranged on the threaded part, an intermediate connecting frame is fixedly arranged on a lower connecting plate, an arc-shaped elastic plate is arranged between an intermediate mounting frame and the intermediate connecting frame, and an upper connecting plate is arranged at the upper end of the intermediate mounting frame. The boiler steel structure mounting base has the beneficial effects that: the components are fixed through welding, bolt connection and solidification with concrete, the wind load resistance and the shock resistance of the structure are improved, the overall structure is modularized, the base and the boiler steel structure are prolonged in service life, and the boiler steel structure mounting base is suitable for various industrial boiler installation scenes.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of boiler steel structure technology, and specifically relates to a boiler steel structure mounting base. Background Technology

[0002] Industrial boilers, as core equipment for energy conversion, are widely used in various industrial fields such as chemical, power, and metallurgy. Their operational stability is directly related to production efficiency and operational safety. As the supporting carrier of the boiler body, the boiler steel structure must withstand the boiler's own weight, the weight of the medium, operating vibration, and complex loads such as external wind loads and earthquakes for a long time. Therefore, the structural reliability and load-bearing capacity of the mounting base are key technical points.

[0003] Existing boiler steel structure installation bases mostly adopt a single concrete pouring or simple steel structure splicing design, which has many technical limitations. First, traditional bases are mostly integrated cast-in-place structures, lacking layered bearing and load distribution design. The coordinated stress optimization between the conical support layer and the steel reinforcement skeleton is insufficient, resulting in concentrated soil pressure per unit area. Long-term use can easily lead to foundation pit settlement and affect the stability of the support. Second, the lack of precise leveling mechanisms during installation, relying on secondary leveling operations on site, not only results in long construction cycles and high labor costs, but also makes it difficult to guarantee the accuracy of the installation benchmark, thus affecting the stable operation of the boiler.

[0004] Meanwhile, existing bases have weak vibration damping performance, mostly consisting of rigid connection structures, which cannot effectively absorb the vibration and impact loads generated during boiler operation. This not only leads to structural fatigue damage and shortens the service life of the base and boiler steel structure, but also transmits vibrations to surrounding facilities, causing noise pollution or potential resonance hazards in adjacent structures. In addition, traditional bases have a single connection method, lacking multiple fixing designs including welding, bolting, and concrete curing, resulting in insufficient wind load and seismic resistance, making them unsuitable for use in complex industrial environments. Utility Model Content

[0005] In view of this, the present invention provides a boiler steel structure mounting base, in which each component is connected by welding and bolts and solidified with concrete to form multiple fixation, which improves the structure's resistance to wind loads and seismic performance. Moreover, the overall modular design facilitates later inspection and maintenance, extends the service life of the base and the boiler steel structure, and is suitable for various industrial boiler installation scenarios.

[0006] The technical solution is as follows: A boiler steel structure mounting base includes a foundation base. A conical support layer is fixedly installed on the upper end of the foundation base. Multiple vertical steel bars are fixedly installed on the upper end of the conical support layer, and the multiple vertical steel bars are connected and fixed by a horizontal connecting frame. A top plate is fixedly installed on the upper end of the vertical steel bars, and multiple L-shaped connecting columns are fixedly installed on the top plate. The lower end of the L-shaped connecting column is inserted into the gap between the multiple vertical steel bars. A threaded part is provided on the upper end of the L-shaped connecting column. A leveling nut and a fixing nut are threaded on the threaded part, and a lower connecting plate is detachably installed between the two. An intermediate connecting frame is fixedly installed on the lower connecting plate. A groove is opened on the intermediate connecting frame, and an intermediate mounting frame is fixedly installed in the groove. An arc-shaped elastic plate is provided between the intermediate mounting frame and the intermediate connecting frame. An upper connecting plate is provided on the upper end of the intermediate mounting frame, and multiple circumferentially evenly distributed connecting bolts are fixedly installed on the upper connecting plate.

[0007] Preferably, multiple vertical reinforcing bars are installed in a 'U' shape at the upper end of the conical support layer.

[0008] Preferably, the top plate has a through hole, the L-shaped connecting post passes through the through hole and is welded to the top plate, the lower connecting plate has a connecting hole, the threaded part passes through the connecting hole, and the leveling nut and the fixing nut are located on the upper and lower end faces of the lower connecting plate, respectively.

[0009] Preferably, a support frame is fixedly provided at the middle position of the upper end of the lower connecting plate, and the middle connecting frame is fixedly installed at the upper end of the support frame, and multiple reinforcing plates are provided between the lower connecting plate and the middle connecting frame.

[0010] Preferably, the tapered support layer and the lower end of the threaded part on the L-shaped connecting column are connected by concrete pouring to form a lower pouring layer, which is buried in the foundation pit below the ground.

[0011] Preferably, the lower end of the middle position of the intermediate connecting frame is connected to the lower pouring layer by pouring concrete to form an upper pouring layer, and the upper pouring layer is located above the ground.

[0012] Preferably, the groove and the intermediate mounting bracket are square, and a gap is reserved between the intermediate mounting bracket and the intermediate connecting bracket. The arc-shaped elastic plate is installed in the gap. The arc-shaped elastic plate is composed of three sets of superimposed arc-shaped plates, one end of which is connected and fixed to the intermediate mounting bracket, and the other end of which is connected and fixed to the intermediate connecting bracket.

[0013] Preferably, a shock absorber is provided between the intermediate mounting bracket and the upper connecting plate for shock absorption and buffering.

[0014] Preferably, multiple telescopic mechanisms are provided between the intermediate connecting frame and the upper connecting plate to support the upper connecting plate and to work in conjunction with the shock absorber.

[0015] Preferably, the telescopic mechanism includes a telescopic tube fixedly installed on the intermediate connecting frame, a telescopic rod slidably installed on the telescopic tube, and the upper end of the telescopic rod is fixed to the upper connecting plate.

[0016] After adopting the above technical solution, the beneficial effects of this utility model are: This base boasts significant practical value. Firstly, its layered load-bearing structure, combined with a U-shaped steel reinforcement frame and a two-stage concrete pouring design, greatly enhances the overall load-bearing capacity. The expanded diameter of the conical support layer effectively reduces soil pressure per unit area, preventing foundation pit settlement and ensuring long-term support stability. Secondly, the threaded adjustment structure of the L-shaped connecting columns allows for precise leveling during installation, solving the problem of low installation accuracy in traditional bases, shortening the construction cycle, and reducing labor costs. Thirdly, three sets of superimposed arc-shaped elastic plates form a highly efficient buffer system, effectively absorbing boiler operating vibrations and impact loads, reducing structural fatigue damage, and mitigating the impact of vibration transmission on surrounding facilities. Furthermore, the components are secured through welding, bolting, and concrete curing, enhancing the structure's wind and seismic resistance. The modular design of the overall structure facilitates later inspection and maintenance, extending the service life of the base and boiler steel structure, making it suitable for various industrial boiler installation scenarios. Attached Figure Description

[0017] To more clearly illustrate the technical solutions in the embodiments of this utility model or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this utility model. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0018] Figure 1 This is an installation effect diagram of the present invention; Figure 2 This is a perspective view of the present utility model; Figure 3 This is an exploded view of the present invention; Figure 4 This is a perspective view of the basic base of this utility model; Figure 5 This is a perspective view of the L-shaped connecting column of this utility model; Figure 6 This is a perspective view of the installation of the upper connecting plate of this utility model; Figure 7 This is a top view of the upper connecting plate of this utility model; In the diagram, 1. Foundation base; 2. Conical support layer; 3. Vertical reinforcement; 4. Horizontal connecting frame; 5. Top plate; 6. Through hole; 7. L-shaped connecting column; 8. Threaded part; 9. Leveling nut; 10. Fixing nut; 11. Washer plate; 12. Lower connecting plate; 13. Connecting hole; 14. Reinforcing plate; 15. Intermediate connecting frame; 16. Groove; 17. Intermediate mounting frame; 18. Arc-shaped elastic plate; 19. Vibration damper; 20. Upper connecting plate; 21. Connecting bolt; 22. Telescopic mechanism; 23. Lower pouring layer; 24. Upper pouring layer; Detailed Implementation

[0019] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model. Example

[0020] like Figures 1 to 7 As shown, a boiler steel structure mounting base includes a foundation base 1. A conical support layer 2 is fixedly installed on the upper end of the foundation base 1. Multiple vertical reinforcing bars 3 are fixedly installed on the upper end of the conical support layer 2, and the multiple vertical reinforcing bars 3 are connected and fixed by a horizontal connecting frame 4. A top plate 5 is fixedly installed on the upper end of the vertical reinforcing bars 3, and multiple L-shaped connecting columns 7 are fixedly installed on the top plate 5. The lower end of the L-shaped connecting column 7 is inserted into the gap between the multiple vertical reinforcing bars 3. A threaded part 8 is provided on the upper end of the L-shaped connecting column 7. The upper thread is fitted with a leveling nut 9 and a fixing nut 10, and a lower connecting plate 12 is detachably installed between the two. An intermediate connecting frame 15 is fixedly installed on the lower connecting plate 12. A groove 16 is opened on the intermediate connecting frame 15, and an intermediate mounting frame 17 is fixedly installed in the groove 16. An arc-shaped elastic plate 18 is provided between the intermediate mounting frame 17 and the intermediate connecting frame 15. An upper connecting plate 20 is provided at the upper end of the intermediate mounting frame 17, and multiple circumferentially evenly distributed connecting bolts 21 are fixedly installed on the upper connecting plate 20.

[0021] Multiple vertical reinforcing bars 3 are installed in a 'U' shape at the upper end of the conical support layer 2. A through hole 6 is provided on the top plate 5. The L-shaped connecting column 7 passes through the through hole 6 and is welded to the top plate 5. A connecting hole 13 is provided on the lower connecting plate 12. The threaded part 8 passes through the connecting hole 13. The leveling nut 9 and the fixing nut 10 are located at the upper and lower ends of the lower connecting plate 12, respectively. Two washers 11 are movably installed on the threaded part 8, distributed at the upper end of the leveling nut 9 and the lower end of the fixing nut 10. A support frame is fixedly installed at the middle position of the upper end of the lower connecting plate 12, and a middle connecting frame 15 is fixedly installed on the upper end of the support frame. Multiple reinforcing bars are provided between the lower connecting plate 12 and the middle connecting frame 15. The lower pouring layer 23 is formed by pouring concrete between the tapered support layer 2 and the lower end of the threaded part 8 on the L-shaped connecting column 7, and is buried in the foundation pit below the ground. The lower end of the middle position of the intermediate connecting frame 15 is poured with concrete between it and the lower pouring layer 23, forming an upper pouring layer 24, which is located above the ground. The groove 16 and the intermediate mounting frame 17 are square, and a gap is reserved between the intermediate mounting frame 17 and the intermediate connecting frame 15. The arc-shaped elastic plate 18 is installed in the gap. The arc-shaped elastic plate 18 is composed of three sets of superimposed arc-shaped plates, one end of which is connected and fixed to the intermediate mounting frame 17, and the other end of which is connected and fixed to the intermediate connecting frame 15.

[0022] In practical operation: The boiler steel structure installation base achieves stable support through a combination of layered load-bearing and elastic buffering design. First, the bottom load-bearing structure is formed by the foundation base 1 and the conical support layer 2. The conical support layer 2 uses an expanded diameter design to distribute the load above and evenly transfer the pressure to the foundation base 1 and the foundation pit soil. Multiple vertical steel bars 3 arranged in a "U" shape are reinforced by a horizontal connecting frame 4 to form a three-dimensional skeleton, which, together with the top plate 5, forms the intermediate load-bearing layer. The L-shaped connecting column 7 passes through the through hole 6 of the top plate 5 and is welded and fixed. Its lower end is inserted into the gap of the vertical steel bar 3 to enhance the connection strength. The conical support layer 2, the vertical steel bar 3, and the lower end of the L-shaped connecting column 7 are solidified into a whole by pouring concrete in the lower pouring layer 23, which improves the structural stability within the foundation pit. During installation, the lower connecting plate is adjusted using the leveling nut 9 of the threaded part 8 of the L-shaped connecting column 7. The boiler steel structure is leveled to ensure accurate installation reference. The lower connecting plate 12 is then locked with fixing nuts 10 to complete the positioning. The boiler steel structure is fixed by the connecting bolts 21 of the upper connecting plate 20. The load is transferred to the intermediate mounting frame 17 through the upper connecting plate 20. The three sets of superimposed arc-shaped elastic plates 18 between the intermediate mounting frame 17 and the intermediate connecting frame 15 can absorb the vibration and impact generated by the boiler operation. The arc-shaped structure deformation buffers the stress and avoids structural damage caused by rigid transmission. The support frame and reinforcing plate 14 between the intermediate connecting frame 15 and the lower connecting plate 12 strengthen the vertical bearing capacity. The upper pouring layer 24 concrete further fixes the connection between the intermediate connecting frame 15 and the lower pouring layer 23, forming a secondary stable structure above the ground. The whole structure realizes the comprehensive functions of load distribution, precise leveling, vibration buffering and stable support. Example

[0023] Based on Embodiment 1, a shock absorber 19 is provided between the intermediate mounting frame 17 and the upper connecting plate 20 for shock absorption and buffering. Multiple telescopic mechanisms 22 are provided between the intermediate connecting frame 15 and the upper connecting plate 20 to support the upper connecting plate 20 and work in conjunction with the shock absorber 19. Each telescopic mechanism 22 includes a telescopic tube fixedly installed on the intermediate connecting frame 15, a telescopic rod slidably installed on the telescopic tube, and the upper end of the telescopic rod is fixed on the upper connecting plate 20.

[0024] In practical operation: the added damping shock absorber 19 and telescopic mechanism 22 further optimize the shock absorption and support effect. After the load is transmitted to the intermediate mounting frame 17, part of the vibration and impact is directly absorbed by the damping shock absorber 19, and its damping characteristic can rapidly attenuate the vibration energy to avoid resonance. The telescopic mechanism 22 on the intermediate connecting frame 15 works in coordination with the damping shock absorber 19, and the telescopic rod inside the telescopic tube can slide flexibly along with the tiny displacement of the upper connecting plate 20, which not only provides stable vertical support for the upper connecting plate 20, but also does not hinder the buffering action of the damping shock absorber 19. When the boiler operates and generates vibration, the telescopic rod telescopically adapts along the telescopic tube, and cooperates with the arc-shaped elastic plate 18 and the damping shock absorber 19 to form a multiple buffering system, which greatly improves the impact resistance of the structure, and meanwhile ensures that the upper connecting plate 20 always maintains a stable posture, providing a more reliable mounting support foundation for the boiler steel structure.

[0025] The working principle of the utility model is as follows: the boiler steel structure mounting base realizes stable support through the design combining layered load bearing and elastic buffering. Firstly, the base base 1 and the conical support layer 2 form a bottom load-bearing structure. The conical support layer 2 disperses the upper load by using the diameter-expanding design, and uniformly transmits the pressure to the base base 1 and the foundation pit soil. A plurality of vertical rebars 3 arranged in a "loop" shape are reinforced by the transverse connecting frame 4 to form a three-dimensional framework, which cooperates with the top plate 5 to form an intermediate force-bearing layer. The L-shaped connecting column 7 passes through the through hole 6 of the top plate 5 and is fixed by welding, and its lower end is inserted into the gap between the vertical rebars 3 to enhance the connection strength. The lower ends of the conical support layer 2, the vertical rebars 3 and the L-shaped connecting column 7 are solidified into a whole through concrete pouring of the lower pouring layer 23, so as to improve the stability of the structure in the foundation pit. During installation, the leveling nut 9 on the threaded portion 8 of the L-shaped connecting column 7 is used to adjust the levelness of the lower connecting plate 12 to ensure that the mounting reference of the boiler steel structure is accurate, and then the lower connecting plate 12 is locked by the fixing nut 10 to complete positioning. The boiler steel structure is fixed by the connecting bolt 21 on the upper connecting plate 20, the load is transmitted to the intermediate mounting frame 17 through the upper connecting plate 20, and three sets of stacked arc-shaped elastic plates 18 between the intermediate mounting frame 17 and the intermediate connecting frame 15 can absorb the vibration and impact generated by the operation of the boiler, and buffer the stress through the deformation of the arc-shaped structure to avoid structural damage caused by rigid transmission. The support frame and the reinforcing plate 14 between the intermediate connecting frame 15 and the lower connecting plate 12 strengthen the vertical load bearing, and the concrete of the upper pouring layer 24 further fixes the connection between the intermediate connecting frame 15 and the lower pouring layer 23 to form a secondary stable structure above the ground. The whole structure realizes the comprehensive functions of load dispersion, precise leveling, vibration buffering and stable support.

[0026] The foregoing has shown and described the basic principles, main features, and advantages of this utility model. Those skilled in the art should understand that this utility model is not limited to the above embodiments. The embodiments and descriptions in the specification are merely illustrative of the principles of this utility model. Various changes and modifications may be made to this utility model without departing from its spirit and scope. All such changes and modifications fall within the scope of protection of this utility model as defined by the appended claims and their equivalents.

Claims

1. A boiler steel structure mounting base, comprising a foundation base (1), wherein a conical support layer (2) is fixedly disposed on the upper end of the foundation base (1), characterized in that: A plurality of vertical steel bars (3) are fixedly arranged at the upper end of the conical support layer (2), and the plurality of vertical steel bars (3) are connected and fixed through a transverse connecting frame (4). A top plate (5) is fixedly arranged at the upper end of the vertical steel bars (3), a plurality of L-shaped connecting columns (7) are fixedly arranged on the top plate (5), and the lower ends of the L-shaped connecting columns (7) are inserted into the gaps between the plurality of vertical steel bars (3). A threaded portion (8) is arranged at the upper end of the L-shaped connecting column (7), a leveling nut (9) and a fixing nut (10) are threadedly mounted on the threaded portion (8), and a lower connecting plate (12) is detachably mounted between the two. An intermediate connecting frame (15) is fixedly arranged on the lower connecting plate (12), a groove (16) is formed in the intermediate connecting frame (15), and an intermediate mounting frame (17) is fixedly arranged in the groove (16). An arc-shaped elastic plate (18) is arranged between the intermediate mounting frame (17) and the intermediate connecting frame (15), an upper connecting plate (20) is arranged at the upper end of the intermediate mounting frame (17), and a plurality of connecting bolts (21) uniformly distributed in the circumferential direction are fixedly arranged on the upper connecting plate (20).

2. The boiler steel structure mounting base according to claim 1, characterized in that, The plurality of vertical steel bars (3) are installed on the upper end of the conical support layer (2) in a shape of a Chinese character 'hui'.

3. A boiler steel structure mounting base according to claim 2, characterized in that, A through hole (6) is formed in the top plate (5), the L-shaped connecting column (7) passes through the through hole (6) and is welded on the top plate (5), a connecting hole (13) is formed in the lower connecting plate (12), the threaded portion (8) passes through the connecting hole (13), and the leveling nut (9) and the fixing nut (10) are respectively located on the upper and lower end faces of the lower connecting plate (12).

4. A boiler steel structure mounting base according to claim 3, characterized in that, A support frame is fixedly arranged at the middle position of the upper end of the lower connecting plate (12), the intermediate connecting frame (15) is fixedly installed at the upper end of the support frame, and a plurality of reinforcing plates (14) are arranged between the lower connecting plate (12) and the intermediate connecting frame (15).

5. A boiler steel structure mounting base according to claim 4, characterized in that, The space between the conical support layer (2) and the lower end of the threaded portion (8) on the L-shaped connecting column (7) is poured with concrete to form a lower pouring layer (23), which is buried in the foundation pit below the ground surface.

6. A boiler steel structure mounting base according to claim 5, characterized in that, The space between the lower end of the middle position of the intermediate connecting frame (15) and the lower pouring layer (23) is poured with concrete to form an upper pouring layer (24), and the upper pouring layer (24) is located above the ground surface.

7. A boiler steel structure mounting base according to any one of claims 1-6, characterized in that, The groove (16) and the intermediate mounting frame (17) are respectively square, and a gap is reserved between the intermediate mounting frame (17) and the intermediate connecting frame (15). The arc-shaped elastic plate (18) is installed in the gap, the arc-shaped elastic plate (18) is composed of three groups of superposed arc-shaped plates, one end of the arc-shaped elastic plate is connected and fixed with the intermediate mounting frame (17), and the end of the other end is connected and fixed with the intermediate connecting frame (15).

8. A boiler steel structure mounting base according to claim 7, characterized in that, A damping damper (19) is arranged between the intermediate mounting frame (17) and the upper connecting plate (20), which is used for shock absorption and buffering.

9. A boiler steel structure mounting base according to claim 8, characterized in that, A plurality of telescopic mechanisms (22) are arranged between the intermediate connecting frame (15) and the upper connecting plate (20), which are used for supporting the upper connecting plate (20) and are used in cooperation with the damping damper (19).

10. A boiler steel structure mounting base according to claim 9, characterized in that, The telescopic mechanism (22) includes a telescopic tube fixedly installed on the intermediate connecting frame (15), a telescopic rod slidably installed on the telescopic tube, and the upper end of the telescopic rod is fixed on the upper connecting plate (20).