Concrete curing device
Patent Information
- Application Number
- CN202521912019.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-09-05
- Publication Date
- 2026-10-20
- Estimated Expiration
- 2035-09-05
AI Technical Summary
[0002]混凝土试块在制作完成后,往往需要将其储存在专用给的混凝土养护装置内,通过控制其温度和湿度来实现对混凝土的养护工作,针对混凝土的湿度控制,多采用喷雾式结构,对混凝土表面喷洒水雾来控制湿度,但是现有的一些养护装置通常在对喷洒后的水直接排出
[0013]1、本实用新型使用时,在水雾喷洒后,水流向下流动时会穿过透水槽,最后落入收纳盒中进行收集,从而完成对使用后的水源进行收集的工作,防止浪费水资源。
Smart Images

Figure CN224867570U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of building materials technology, specifically to a concrete curing device. Background Technology
[0002] After concrete test blocks are made, they are often stored in a special concrete curing device. The curing of concrete is achieved by controlling its temperature and humidity. For humidity control, a spray structure is often used to spray water mist onto the concrete surface to control humidity. However, some existing curing devices usually discharge the sprayed water directly.
[0003] In some existing concrete curing methods, the water used to control humidity is directly discharged after use and cannot be collected, resulting in a significant waste of water resources. Utility Model Content
[0004] In view of this, the present invention provides a concrete curing device that can collect water after use in a centralized manner to prevent water waste.
[0005] To solve the above-mentioned technical problems, this utility model provides a concrete curing device, including a box and a storage cavity opened inside the box. A door panel is installed on the box corresponding to the storage cavity by a hinge. Multiple storage mechanisms are evenly arranged on the inner wall of the storage cavity. Each storage mechanism is distributed from top to bottom along the inner wall of the storage cavity, and the distance between any two adjacent storage mechanisms is the same. Each storage mechanism includes a placement plate for placing concrete. A water-permeable groove is opened on the surface of the placement plate, and a storage box is installed at the bottom of each placement plate. By placing the prepared concrete test block on the surface of the placement plate, after water mist is sprayed, the water flows downward and passes through the water-permeable groove, and finally falls into the storage box for collection, thereby completing the work of collecting the used water and preventing waste of water resources.
[0006] The storage mechanism also includes a fixing frame, which is fixed to the inner wall of the storage cavity. The mounting plate is slidably mounted on the inner wall of the fixing frame, and the storage box is located inside the fixing component and below the mounting plate. The mounting plate can be pulled out or slid into the fixing frame by sliding the mounting plate, which facilitates the handling of concrete test blocks.
[0007] The mounting plate is equipped with sliding strips on both sides, and the inner side walls of the fixing frame are provided with sliding grooves that fit the sliding strips. The sliding strips are slidably set in the sliding grooves. When the worker pulls the mounting plate, the sliding strips on both sides of the mounting plate slide in the sliding grooves. Through the limiting of the sliding strips and sliding grooves, the mounting plate can only slide along the length of the sliding groove, thus making it convenient to pick up and put down the mounting plate.
[0008] Each mounting plate is equipped with a connecting pipe at the top, and multiple nozzles are evenly distributed at the bottom of the connecting pipe. The end of the connecting pipe is connected to a water supply component, which is used to supply water into the connecting pipe. The water source is delivered into the connecting pipe through the water supply component, and the water source is sprayed downwards through the nozzles in a ring-shaped water mist, so that the water mist can cover the concrete test block on the surface of the mounting plate, thereby performing humidity curing.
[0009] The water supply assembly includes a water storage tank located at the bottom of the storage chamber, a water pump installed at the bottom of the tank, with the water pump inlet connected to the inside of the water storage chamber, and a water supply pipe connected to the water pump outlet. The end of the connecting pipe is connected to the inside of the water supply pipe. An inlet pipe is installed on the surface of the tank and is connected to the water storage tank. Water is added to the water storage tank through the inlet pipe, and then the water pump is started. The water pump draws water from the water storage tank and delivers it to the water supply pipe. The water source is then delivered to the connecting pipe through the water supply pipe, and finally the water is sprayed out through the nozzle, thus completing the spraying work.
[0010] A filter screen is installed inside the inlet pipe to filter the used water. After the staff removes the collection box from the fixed frame, they can collect the wastewater from each collection box and then pour the collected wastewater into the inlet pipe. Other water pumps can be connected to the inlet pipe, and when the wastewater is transported to the inlet pipe, the filter screen inside the inlet pipe can filter out impurities in the wastewater. Depending on the usage, a quartz sand filter layer, an activated carbon filter layer, or a filter cloth can be used. If the wastewater contains oil, it can be purified by external purification equipment, so that the filtered water can be reused in the storage tank, thereby improving the water resource utilization rate.
[0011] The bottom of the water storage tank is equipped with a guide slope, which is used to concentrate the water to the water pump inlet for discharge, so that the sewage can be pumped out in a concentrated manner, improving its practicality.
[0012] In summary, compared with the prior art, this application includes at least one of the following beneficial technical effects:
[0013] 1. When this utility model is used, after the water mist is sprayed, the water flows downward and passes through the permeable trough, and finally falls into the collection box for collection, thereby completing the work of collecting the water after use and preventing waste of water resources.
[0014] 2. When using this utility model, the worker pulls the mounting plate, causing the sliders on both sides of the mounting plate to slide in the groove. Through the limiting of the sliders and the groove, the mounting plate can only slide along the length of the groove, thus making it convenient to pick up and put down the mounting plate.
[0015] 3. When this utility model is used, the guide slope is used to concentrate water to the water pump inlet for discharge, so that sewage can be pumped out in a concentrated manner, thus improving its practicality.
[0016] 4. When this utility model is used, the filter screen in the water inlet pipe can filter impurities in the sewage. Specifically, depending on the usage, a quartz sand filter layer, an activated carbon filter layer, or a filter cloth can be used. If the sewage contains oil, it can be purified by external purification equipment, so that the filtered water can enter the water storage tank for reuse, thereby improving the water resource utilization rate. Attached Figure Description
[0017] Figure 1 This is a schematic diagram of the main structure of this utility model; Figure 2 This is a partial sectional view of the internal structure of the water storage chamber of this utility model; Figure 3 For the present utility model Figure 1 Enlarged cross-sectional view of the structural placement plate at point A.
[0018] Explanation of reference numerals in the attached figures: 100. Box body; 101. Storage cavity; 200. Mounting plate; 201. Water permeable trough; 202. Sliding strip; 300. Storage box; 400. Fixing frame; 401. Sliding groove; 500. Water storage tank; 501. Filter pipe; 502. Water pump; 503. Water supply pipe; 600. Connecting pipe; 601. Nozzle. Detailed Implementation
[0019] To make the objectives, technical solutions, and advantages of the embodiments of this utility model clearer, the following will be described in conjunction with the accompanying drawings of the embodiments of this utility model. Figure 1-3 The technical solutions of the embodiments of this utility model are clearly and completely described herein. Obviously, the described embodiments are only some, not all, of the embodiments of this utility model. All other embodiments obtained by those skilled in the art based on the described embodiments of this utility model are within the protection scope of this utility model.
[0020] Concrete curing equipment, such as Figure 1 , Figure 2 and Figure 3As shown: It includes a box body 100 and a storage cavity 101 opened inside the box body 100. A door panel is installed on the box body 100 corresponding to the position of the storage cavity 101 by a hinge. Multiple storage mechanisms are evenly arranged on the inner wall of the storage cavity 101. Each storage mechanism is distributed from top to bottom along the inner wall of the storage cavity 101. The spacing between any two adjacent storage mechanisms is the same. The storage mechanism includes a placement plate 200 for placing concrete. A water permeable groove 201 is opened on the surface of the placement plate 200, and a storage box 300 is installed at the bottom of each placement plate 200. By placing the prepared concrete test block on the surface of the placement plate 200, after water mist is sprayed, the water flows downward and passes through the water permeable groove 201, and finally falls into the storage box 300 for collection, thereby completing the work of collecting the used water and preventing waste of water resources.
[0021] The storage mechanism also includes a fixing frame 400, which is fixed to the inner wall of the storage cavity 101. The mounting plate 200 is slidably mounted on the inner wall of the fixing frame 400. The storage box 300 is located inside the fixing component and below the mounting plate 200. By sliding the mounting plate 200, the mounting plate 200 can be pulled out or slid into the fixing frame 400, which facilitates the handling of concrete test blocks.
[0022] The mounting plate 200 is provided with slide bars 202 on both sides. The inner side walls of the fixing frame 400 are provided with slide grooves 401 adapted to the slide bars 202. The slide bars 202 are slidably disposed in the slide grooves 401. When the operator pulls the mounting plate 200, the slide bars 202 on both sides of the mounting plate 200 slide in the slide grooves 401. Through the limiting of the slide bars 202 and the slide grooves 401, the mounting plate 200 can only slide along the length direction of the slide grooves 401, so that the mounting plate 200 can be easily picked up and put down.
[0023] Each mounting plate 200 is equipped with a connecting pipe above it. Multiple nozzles are evenly distributed at the bottom of the connecting pipe. A water supply component is connected to the end of the connecting pipe. The water supply component is used to supply water into the connecting pipe. The water source is delivered into the connecting pipe through the water supply component. The water source is sprayed downwards through the nozzles in a ring-shaped water mist, so that the water mist can cover the concrete test block on the surface of the mounting plate 200, thereby performing humidity curing.
[0024] The water supply assembly includes a water storage tank 500 located at the bottom of the storage chamber 101. A water pump 502 is installed at the bottom of the tank 100, and the inlet of the water pump 502 is connected to the inside of the water storage chamber. The outlet of the water pump 502 is connected to a water supply pipe 503, and the end of the connecting pipe is connected to the inside of the water supply pipe 503. A water inlet pipe is installed on the surface of the tank 100 and is connected to the water storage tank 500. Water is added to the water storage tank 500 through the water inlet pipe. Then, the water pump 502 is started, and the water pump 502 draws water from the water storage tank 500 and delivers it to the water supply pipe 503. The water source is delivered to the connecting pipe through the water supply pipe 503, and finally, the water is sprayed out through the nozzle, thereby completing the spraying work.
[0025] A filter screen is installed inside the inlet pipe to filter the used water. After the staff removes the collection box 300 from the fixing frame 400, they can collect the wastewater from each collection box 300 and then pour the collected wastewater into the inlet pipe. An external water pump 502 can be connected to the inlet pipe. When the wastewater is transported to the inlet pipe, the filter screen inside the inlet pipe can filter the impurities in the wastewater. Depending on the usage, a quartz sand filter layer, an activated carbon filter layer, or a filter cloth can be used. If the wastewater contains oil, it can be purified by external purification equipment. The filtered water can then enter the storage tank 500 for reuse, improving water resource utilization.
[0026] The bottom of the water storage tank 500 is provided with a guide slope, which is used to concentrate the water to the water inlet of the water pump 502 for discharge, so that the sewage can be pumped out in a concentrated manner and the practicality can be improved.
[0027] First, it should be clarified that this utility model is mainly used for the recycling of wastewater after spraying. It should be noted that the purification equipment and water pump 502 are common equipment in the prior art. Therefore, the model is not limited here, nor is the structure described in detail. Only the usage method and installation position of the storage mechanism are described in detail.
[0028] The above description is the preferred embodiment of this utility model. It should be noted that for those skilled in the art, several improvements and modifications can be made without departing from the principle of this utility model, and these improvements and modifications should also be considered within the protection scope of this utility model.
Claims
1. A concrete curing device, comprising a housing (100) and a storage cavity (101) formed within the housing (100), characterized in that: The inner wall of the storage cavity (101) is uniformly provided with a plurality of storage mechanisms. The storage mechanism includes a placement plate (200) for placing concrete. The surface of the placement plate (200) is provided with a water permeable groove (201), and a storage box (300) is installed at the bottom of each placement plate (200). The sprayed water will pass through the water permeable groove (201) and fall into the storage box (300) for collection.
2. The concrete curing device as described in claim 1, characterized in that: The storage mechanism also includes a fixing frame (400), which is fixed on the inner wall of the storage cavity (101). The mounting plate (200) is slidably disposed on the inner wall of the fixing frame (400). The storage box (300) is disposed inside the fixing member and is located below the mounting plate (200).
3. The concrete curing device as described in claim 2, characterized in that: The mounting plate (200) is provided with slide bars (202) on both sides, and the two inner side walls of the fixing frame (400) are provided with slide grooves (401) adapted to the slide bars (202), and the slide bars (202) are slidably disposed in the slide grooves (401).
4. The concrete curing device as described in claim 3, characterized in that: Each of the mounting plates (200) is provided with a connecting pipe above it, and a plurality of nozzles are evenly distributed at the bottom of the connecting pipe. A water supply assembly is connected to the end of the connecting pipe, and the water supply assembly is used to supply water into the connecting pipe.
5. The concrete curing device as described in claim 4, characterized in that: The water supply assembly includes a water storage tank (500) located at the bottom of the storage chamber (101). A water pump (502) is provided at the bottom of the housing (100), and the inlet of the water pump (502) is connected to the inside of the water storage chamber. The outlet of the water pump (502) is connected to a water supply pipe (503), and the end of the connecting pipe is connected to the inside of the water supply pipe (503). A water inlet pipe is provided on the surface of the housing (100), and the water inlet pipe is connected to the water storage tank (500).
6. The concrete curing device as described in claim 5, characterized in that: A filter screen is installed inside the water inlet pipe, which is used to filter the water after use.
7. The concrete curing device as described in claim 5, characterized in that: The bottom of the water storage tank (500) is provided with a guide slope, which is used to concentrate water to the water inlet of the water pump (502) for discharge.