An axis adjusting device for horizontal static load test in pile foundation detection

CN224870641UActive Publication Date: 2026-10-20ANHUI ELECTRIC POWER DESIGN INST CEEC
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202620070884.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2026-01-20
Publication Date
2026-10-20
Estimated Expiration
2036-01-20

AI Technical Summary

Technical Problem

[0004]上述这种基于人为目测进行轴线调整的做法,至少存在以下重要缺陷:人为目测时,必须要站远一点,方能对两桩位置有整体把握,而在确定好方向后,再来近距离调整垫块,往往与预想的有差距,导致既费时费力,又无法保障质量

Benefits of technology

[0015]借助上述技术方案,本实用新型的一种桩基检测中水平静载试验的轴线调整装置,通过设置组合一体的环桩组件和可伸缩承载组件,先利用环桩组件实现与试验桩和锚桩的连接且可锁定桩心位置,再利用可伸缩承载组件搭载水平力加载组件且将其布置在了桩心连线上,从而保证了力加载的方向始终准确,简化了现有的找准步骤,节省了人力和时间成本,提高了工作效率,保证了较高的试验质量和试验结果的准确性。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224870641U_ABST
    Figure CN224870641U_ABST
Patent Text Reader

Abstract

An axis adjusting device for horizontal static load test in pile foundation detection, comprising: a ring pile assembly, the ring pile assembly comprising a first ring pile piece detachably connected to the outer periphery of a test pile and a second ring pile piece detachably connected to the outer periphery of an anchor pile; and a telescopic bearing assembly, both ends of the telescopic bearing assembly being fixedly connected to the outside of the first ring pile piece and the second ring pile piece respectively and simultaneously located in the radial direction of both, the telescopic bearing assembly being configured for placing a horizontal force loading assembly. The device can solve the problem of difficult adjustment of horizontal test cushion block in the existing manual visual method, improve the adjustment efficiency, reduce the labor and time cost, and ensure the quality of the horizontal test.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to an axis adjustment device for horizontal static load testing in pile foundation inspection, and belongs to the field of pile foundation inspection technology. Background Technology

[0002] As is known, the horizontal static load test of a test pile usually involves applying a horizontal force between the test pile and the anchor pile, and the process of applying the horizontal force requires that the horizontal force passes exactly through the core of the test pile and the anchor pile.

[0003] Currently, the existing method for adjusting the axis of the test pile in the horizontal static load test usually involves first determining a direction by visual inspection, and then adjusting the position of the pad by continuously applying and removing pressure, so as to make the horizontal force pass through the core of the test pile and the anchor pile.

[0004] The above-mentioned method of adjusting the axis based on human visual inspection has at least the following important drawbacks: When making a visual inspection, one must stand at a distance to have an overall grasp of the positions of the two piles. After determining the direction, adjusting the pads at close range often results in discrepancies with expectations, leading to both time and effort being wasted and the quality not being guaranteed. Summary of the Invention

[0005] To overcome the above-mentioned shortcomings of the prior art, this utility model provides an axis adjustment device for horizontal static load test in pile foundation testing. This device can help operators quickly find the direction of the horizontal loading force during installation, which can improve efficiency and save costs. It also has the advantages of simple and convenient operation, high test quality and accurate test results.

[0006] The technical solution adopted by this utility model to solve its technical problem is:

[0007] An axis adjustment device for horizontal static load testing in pile foundation inspection includes:

[0008] A ring pile assembly, comprising a first ring pile member detachably connected to the outer periphery of the test pile and a second ring pile member detachably connected to the outer periphery of the anchor pile; and

[0009] The retractable load-bearing assembly has its two ends fixedly connected to the outside of the first ring pile and the second ring pile respectively and located in the radial direction of both. The retractable load-bearing assembly is configured to place the horizontal force loading assembly.

[0010] As a further optional design of this technical solution, the first ring pile and the second ring pile have the same structure, both of which are adjustable metal cable ties.

[0011] As a further optional design of this technical solution, the adjustable metal cable tie includes a strip of iron, one end of which is provided with a buckle, and the other end is provided with multiple adjustable slots that can be connected with the buckle.

[0012] As a further optional design of this technical solution, the telescopic load-bearing component is a telescopic channel steel, with both ends of the telescopic channel steel welded and fixed to the strip iron plates of the first ring pile and the second ring pile respectively.

[0013] As a further optional design of this technical solution, the retractable load-bearing component includes multiple retractable channel steels that are interlocked with each other, with the ends of the two retractable channel steels located at the beginning and end welded to the first ring pile and the second ring pile respectively.

[0014] As a further optional design of this technical solution, the horizontal force loading assembly includes a jack connected between the test pile and the anchor pile. The jack is connected to the test pile and the anchor pile respectively through a first shim block assembly and a second shim block assembly. The jack, the first shim block assembly and the second shim block assembly are placed together on the telescopic channel steel.

[0015] By utilizing the above technical solution, the present invention provides an axis adjustment device for horizontal static load testing in pile foundation inspection. By setting up an integrated ring pile assembly and a telescopic bearing assembly, the ring pile assembly is first used to connect with the test pile and anchor pile and lock the pile core position. Then, the telescopic bearing assembly is used to carry the horizontal force loading assembly and arrange it on the line connecting the pile cores, thereby ensuring that the direction of force loading is always accurate, simplifying the existing alignment steps, saving manpower and time costs, improving work efficiency, and ensuring high test quality and accuracy of test results.

[0016] Other features and advantages of the present invention will become clear from the following detailed description of exemplary embodiments of the present invention with reference to the accompanying drawings. Attached Figure Description

[0017] The present invention will be further described below with reference to the accompanying drawings and embodiments.

[0018] Figure 1 This is a schematic diagram of the structure of an axis adjustment device according to an embodiment of the present invention.

[0019] Figure 2 This is a schematic diagram of the application structure of an axis adjustment device according to an embodiment of the present invention.

[0020] Explanation of the markings in the diagram:

[0021] 10 - Axis adjustment device;

[0022] 11-Ring pile assembly; 111-First ring pile component; 112-Second ring pile component; 1111-Adjustable metal cable tie; 1111-1-Strip iron sheet; 1111-1-Snap buckle; 1111-1-2-Adjusting latch;

[0023] 12 - Telescopic load-bearing component; 121 - Telescopic channel steel;

[0024] 20 - Horizontal force loading component;

[0025] 21-Jack; 211-First shim block assembly; 212-Second shim block assembly.

[0026] 30 - Test pile;

[0027] 40-Anchor pile. Detailed Implementation

[0028] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. The following description of at least one exemplary embodiment is merely illustrative and is in no way intended to limit the present utility model or its application or use. All other embodiments obtained by those skilled in the art based on the embodiments of the present utility model without creative effort are within the scope of protection of the present utility model.

[0029] Unless otherwise specifically stated, the relative arrangement, numerical expressions, and values ​​of the components and steps described in these embodiments do not limit the scope of this invention. It should also be understood that, for ease of description, the dimensions of the various parts shown in the drawings are not drawn to actual scale. Techniques, methods, and devices known to those skilled in the art may not be discussed in detail, but where appropriate, such techniques, methods, and devices should be considered part of the specification. In all examples shown and discussed herein, any specific values ​​should be interpreted as merely exemplary and not as limitations. Therefore, other examples of exemplary embodiments may have different values. It should be noted that similar reference numerals and letters in the following drawings denote similar items; therefore, once an item is defined in one drawing, it need not be further discussed in subsequent drawings.

[0030] In the description of this utility model, it should be understood that the use of terms such as "first" and "second" to define components is merely for the purpose of distinguishing the corresponding components. Unless otherwise stated, these terms have no special meaning and therefore should not be construed as limiting the scope of protection of this utility model. In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "joining" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a direct connection or an indirect connection through an intermediate medium. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.

[0031] For ease of description, spatial relative terms such as "above," "on top of," "on the upper surface of," "above," etc., are used herein to describe the spatial positional relationship of a device or feature as shown in the figures to other devices or features. It should be understood that spatial relative terms are intended to encompass different orientations in use or operation beyond the orientation of the device as described in the figures. For example, if the device in the figures were inverted, a device described as "above" or "on top of" other devices or structures would subsequently be positioned as "below" or "under" other devices or structures. Thus, the exemplary term "above" can include both "above" and "below." The device may also be positioned in other different ways (rotated 90 degrees or in other orientations), and the spatial relative descriptions used herein will be interpreted accordingly.

[0032] Figure 1 and Figure 2 A schematic diagram of a preferred embodiment of the present invention is shown. The diagram illustrates an axis adjustment device 10 for a horizontal static load test in pile foundation inspection, comprising a ring pile assembly 11 and a telescopic load-bearing assembly 12. Wherein:

[0033] The ring pile assembly 11 includes a first ring pile member 111 detachably connected to the outer periphery of the test pile 30 and a second ring pile member 112 detachably connected to the outer periphery of the anchor pile 40; the two ends of the telescopic bearing assembly 12 are respectively fixedly connected to the outside of the first ring pile member 111 and the second ring pile member 112 and are located in the radial direction of both, and the telescopic bearing assembly 12 is configured to place the horizontal force loading assembly 20.

[0034] In specific implementation, the axis adjustment device 10 of this embodiment achieves a fixed connection with the test pile 30 and the anchor pile 40 through the first ring pile member 111 and the second ring pile member 112, and locks the pile center positions of the two. Then, the horizontal force loading component 20 is mounted by the retractable bearing component 12 connected in the radial direction of the two, so that the horizontal force during the horizontal force loading process can pass through the pile center of the test pile 30 and the anchor pile 40. This not only simplifies the operation process, saves time and effort, and is safe and reliable, but also improves work efficiency, ensures test quality, and ensures the accuracy of test results.

[0035] For example, refer to Figure 1 and Figure 2 In this embodiment, the first ring pile 111 and the second ring pile 112 have the same structure, both being adjustable metal cable ties 1111.

[0036] The adjustable metal cable tie 1111 ring pile assembly 11 can wrap around the test pile 30 or anchor pile 40 so that the center line of the telescopic bearing assembly 12 passes through the pile core, thus meeting the axis adjustment requirements of the horizontal static load test.

[0037] For further details, please refer to Figure 1 The adjustable metal cable tie 1111 in this embodiment may include a strip iron sheet 1111-1. One end of the strip iron sheet 1111-1 is provided with a buckle 1111-1-1, and the other end is provided with a plurality of adjustable slots 1111-1-2 that can be connected to the buckle 1111-1-1.

[0038] In practice, the buckle 1111-1-1 is connected to buckles 1111-1-1 in different positions, which makes the length of the strip iron sheet 1111-1 adjustable, that is, it can obtain rings with different inner diameters, which can meet the testing needs of piles with different diameters.

[0039] In use, the adjustable metal cable tie 1111 is untied and wrapped around the test pile 30 and anchor pile 40. The protruding buckles 1111-1-1 on the strip iron plate 1111-1 and the pre-drilled adjustable slots 1111-1-2 on the strip iron plate 1111-1 are used to tighten and secure the cable tie to the test pile 30 and anchor pile 40. At this time, the telescopic channel steel 121 is aligned with the center of the two piles, ensuring that the loading direction is always perpendicular to the pile center.

[0040] For example, refer to Figure 1 and Figure 2 The telescopic load-bearing component 12 is a telescopic channel steel 121, and the two ends of the telescopic channel steel 121 are respectively welded and fixed to the strip iron sheet 1111-1 of the first ring pile 111 and the second ring pile 112.

[0041] The design of the telescopic channel steel 121 specifically realizes the adjustable size of the telescopic load-bearing component 12, which can flexibly meet the testing requirements of piles with different pile spacings.

[0042] Further preferred options are those that refer to... Figure 1 and Figure 2 The retractable load-bearing component 12 in this embodiment may include a plurality of retractable channel steels 121 that are interlocked with each other, and the ends of the two retractable channel steels 121 located at the beginning and end are respectively welded to the first ring pile 111 and the second ring pile 112.

[0043] The multiple overlapping telescopic channel steels 121 are suitable for situations with large pile spacing, and the test pile 30 and anchor pile 40 can be connected over a long distance by overlapping.

[0044] Reference Figure 2 In this embodiment, the horizontal force loading component 20 may include a jack 21 connected between the test pile 30 and the anchor pile 40. The jack 21 is connected to the test pile 30 and the anchor pile 40 respectively through a first shim block assembly 211 and a second shim block assembly 212. The jack 21, the first shim block assembly 211 and the second shim block assembly 212 are placed together on the telescopic channel steel 121.

[0045] In practice, the first shim block assembly 211 and the second shim block assembly 212 have the same structure, both consisting of several shims and several blocks stacked together. During use, the jack 21 utilizes the telescopic channel steel 121 to ensure the accuracy of the loading force direction.

[0046] This embodiment provides an axis adjustment device 10 for horizontal static load testing in pile foundation inspection. Its complete working process is as follows:

[0047] During the horizontal static load test, the pile spacing is first measured and determined. Then, the length of the telescopic load-bearing assembly 12 is adjusted to match the distance between the piles. After determining the dimensions, the first ring pile member 111 and the second ring pile member 112 of the ring pile assembly 11 are connected to the test pile 30 and the anchor pile 40, respectively. After completing the above steps, the horizontal force loading assembly 20 is placed on the telescopic load-bearing assembly 12, and the test can then begin.

[0048] As can be seen, this process is simple, convenient, safe and reliable, eliminating the need to constantly adjust the loading direction of the pad block and jack 21, thus improving work efficiency.

[0049] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of this utility model and not to limit it; although the utility model has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications can still be made to the specific implementation of this utility model or equivalent substitutions can be made to some technical features without departing from the spirit of the technical solution of this utility model, and all such modifications and substitutions should be covered within the scope of the technical solution claimed by this utility model.

Claims

1. An axis adjustment device for horizontal static load testing in pile foundation inspection, characterized in that, include: A ring pile assembly, comprising a first ring pile member detachably connected to the outer periphery of a test pile and a second ring pile member detachably connected to the outer periphery of an anchor pile; and A retractable load-bearing assembly, the two ends of which are fixedly connected to the outside of the first ring pile and the second ring pile respectively and located in the radial direction of both, the retractable load-bearing assembly being configured to place a horizontal force loading assembly.

2. The axis adjustment device for horizontal static load test in pile foundation testing according to claim 1, characterized in that, The first ring pile and the second ring pile have the same structure, both being adjustable metal cable ties.

3. The axis adjustment device for horizontal static load test in pile foundation testing according to claim 2, characterized in that, The adjustable metal cable tie includes a strip of iron, one end of which is provided with a buckle, and the other end is provided with multiple adjustable slots that can be connected to the buckle.

4. The axis adjustment device for horizontal static load test in pile foundation testing according to claim 3, characterized in that, The retractable load-bearing component is a retractable channel steel, and the two ends of the retractable channel steel are respectively welded and fixed to the strip iron plates of the first ring pile and the second ring pile.

5. The axis adjustment device for horizontal static load test in pile foundation testing according to claim 4, characterized in that, The retractable load-bearing component includes a plurality of retractable channel steels that are interlocked with each other, and the ends of the two retractable channel steels located at the beginning and end are respectively welded to the first ring pile and the second ring pile.

6. The axis adjustment device for horizontal static load test in pile foundation testing according to claim 4 or 5, characterized in that, The horizontal force loading assembly includes a jack connected between the test pile and the anchor pile. The jack is connected to the test pile and the anchor pile respectively through a first shim block assembly and a second shim block assembly. The jack, the first shim block assembly and the second shim block assembly are placed together on the telescopic channel steel.